+ All Categories
Home > Documents > EUROPEAN ORGANIZATION FOR NUCLEAR...

EUROPEAN ORGANIZATION FOR NUCLEAR...

Date post: 27-Jun-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
6
CERN-ACC-2013-0084 31/07/2013 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS AND TECHNOLOGY SECTOR The First Long Shutdown (LS1) for the LHC F. Bordry, S. Baird, K. Foraz, A.-L. Perrot, R. Saban, J.Ph. Tock CERN, Geneva, Switzerland The LHC has been delivering data to the physics experiments since the first collisions in 2009. The first long shutdown (LS1), which started on 14 February 2013, was triggered by the need to consolidate the magnet interconnections to allow the LHC to operate at the design energy of 14 TeV in the centre-of-mass. It has now become a major shutdown, which, in addition, includes other repairs, consolidation, upgrades and cabling across the whole accelerator complex and the associated experimental facilities. A detailed CERN-wide resource-loaded schedule was prepared aiming at resuming LHC physics in early 2015, while the rest of the CERN complex will gradually start up again in the second half of 2014. The paper describes the preparation phase with the prioritisation of the activities, the building of the teams and the planning of the shutdown. Then, it gives an overview of the injector activities and the main projects in the LHC. The decision to restart at 6.5 TeV after the LS1 is recalled. Presented at IPAC'2013, 4th International Particle Accelerator Conference 12-17 May 2013 - Shanghai, China Geneva, Switzerland CERN-ATS-2013-0084 July 2013
Transcript
Page 1: EUROPEAN ORGANIZATION FOR NUCLEAR …cds.cern.ch/record/1575133/files/CERN-ACC-2013-0084.pdfCERN-ACC-2013-0084 31/07/2013 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS

CER

N-A

CC

-201

3-00

8431

/07/

2013

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCHCERN - ACCELERATORS AND TECHNOLOGY SECTOR

The First Long Shutdown (LS1) for the LHC

F. Bordry, S. Baird, K. Foraz, A.-L. Perrot, R. Saban, J.Ph. TockCERN, Geneva, Switzerland

The LHC has been delivering data to the physics experiments since the first collisions in 2009. The first long

shutdown (LS1), which started on 14 February 2013, was triggered by the need to consolidate the magnet

interconnections to allow the LHC to operate at the design energy of 14 TeV in the centre-of-mass. It has now become

a major shutdown, which, in addition, includes other repairs, consolidation, upgrades and cabling across the whole

accelerator complex and the associated experimental facilities. A detailed CERN-wide resource-loaded schedule was

prepared aiming at resuming LHC physics in early 2015, while the rest of the CERN complex will gradually start up

again in the second half of 2014.

The paper describes the preparation phase with the prioritisation of the activities, the building of the teams and the

planning of the shutdown. Then, it gives an overview of the injector activities and the main projects in the LHC. The

decision to restart at 6.5 TeV after the LS1 is recalled.

Presented at IPAC'2013, 4th International Particle Accelerator Conference12-17 May 2013 - Shanghai, China

Geneva, Switzerland

CERN-ATS-2013-0084

July 2013

Page 2: EUROPEAN ORGANIZATION FOR NUCLEAR …cds.cern.ch/record/1575133/files/CERN-ACC-2013-0084.pdfCERN-ACC-2013-0084 31/07/2013 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS

THE FIRST LONG SHUTDOWN (LS1) FOR THE LHC

F. Bordry, S. Baird, K. Foraz, A.L. Perrot, R. Saban, J.P Tock, CERN, Geneva, Switzerland

Abstract The LHC has been delivering data to the physics

experiments since the first collisions in 2009. The first long shutdown (LS1), which started on 14 February 2013, was triggered by the need to consolidate the magnet interconnections to allow the LHC to operate at the design energy of 14 TeV in the centre-of-mass. It has now become a major shutdown, which, in addition, includes other repairs, consolidation, upgrades and cabling across the whole accelerator complex and the associated experimental facilities. A detailed CERN-wide resource-loaded schedule was prepared aiming at resuming LHC physics in early 2015, while the rest of the CERN complex will gradually start up again in the second half of 2014.

The paper describes the preparation phase with the prioritisation of the activities, the building of the teams and the planning of the shutdown. Then, it gives an overview of the injector activities and the main projects in the LHC. The decision to restart at 6.5 TeV after the LS1 is recalled.

INTRODUCTION Following the incident in one of the main dipole

circuits of the LHC on September 19th 2008, a detailed analysis was carried out [1]. Thanks to the availability of spare magnets, Sector 3-4 could be repaired in 6 months. In addition, a global consolidation of the magnet protection system and important re-engineering of several systems took place so that such an incident would be avoided in the future.

An upgraded quench protection system was designed and installed to protect all bus-bar joints of the arc main dipole and main quadrupole circuits [2]. In parallel an improved pressure relief system for the insulation vacuum was installed on the magnet cryostats. But in order to restart quickly the LHC (November 2009) and to provide data to the experiments, it was decided to warm-up only four LHC sectors, therefore the 200 mm diameter valves for the improvement of the pressure relief system were only installed on these four sectors.

The interconnections between the LHC main magnets are made of soldered joints (splices) of two superconducting cables stabilized by a copper bus bar. The measurements performed in 2009 in the four warm sectors demonstrated that there are defective copper bus bar joints in the machine (10-15% of the high current interconnections). Based on these measurements, it was decided to restart the LHC operation at 3.5 TeV and to consolidate the LHC during the LS1 in 2012. With the respectable integrated luminosity in 2011, the CERN management decide to run the LHC through 2012 to give

to the experiments the data needed to fully explore this energy range before moving up to higher energy. To enhance the discovery potential, after two years of operation and an operational experience with stored beams exceeding 100 MJ, the beam energy was increased to 4 TeV in 2012.

Thanks to the fantastic LHC performance [3], this staged strategy proved successful and culminated, with the announcement of the discovery of a Higgs-like boson on 4th July 2012.

LS1 STRATEGY AND RESSOURCES As described above, the LS1 was triggered by the need

to consolidate the magnet interconnections to allow the LHC to operate at the design energy of 14 TeV in the centre-of-mass. It became rapidly a major shutdown, which, in addition, includes other repairs, consolidations, upgrades and cabling across the whole accelerator complex and the associated experimental facilities. LS1 will see a massive programme of maintenance for the LHC and its injectors in the wake of more than three years of operation without the long winter shutdowns that were the norm in the past.

The LS1 preparation started just after the decision to resume the LHC operation at 3.5 TeV, i.e. more than three years ago. The strategy was to define the duration of key activities needed for safe and reliable operation of the CERN accelerator complex (LHC and its injectors) to run the LHC at 7 TeV at the nominal luminosity. After several iterations with the technical coordination of the LHC experiments, the LHC machine and its injectors, the minimum time needed from “beam off” to “beam on” in the LHC was determined to be 20 months. Rapidly it became clear that it would be necessary to prioritize all the activities requested by equipment groups and the projects; this to ensure that the 20 month time frame would be sufficient to perform all the consolidation and upgrades needed to achieve the goals of LS1 (as well as carry out the full maintenance of the different systems),. Often these interventions are planned and organized in terms of the resources in the groups, therefore it was vital to gather all the information on the support needed from other groups, to check the coactivity conflicts and to define the required manpower. Regular and dedicated meetings were held with the different stakeholders to obtain a clear and complete picture of the activities related to the accelerator complex and the LHC experiments. All the information was compiled in a database and a special software tool (PLAN) was developed as a decision support tool.

The five following levels were set to prioritize all the activities:

MOZB202 Proceedings of IPAC2013, Shanghai, China

ISBN 978-3-95450-122-9

44Cop

yrig

htc ○

2013

byJA

CoW

—cc

Cre

ativ

eC

omm

onsA

ttri

butio

n3.

0(C

C-B

Y-3.

0)

01 Circular and Linear Colliders

A01 Hadron Colliders

Page 3: EUROPEAN ORGANIZATION FOR NUCLEAR …cds.cern.ch/record/1575133/files/CERN-ACC-2013-0084.pdfCERN-ACC-2013-0084 31/07/2013 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS

Priority

P0

P1

P2

P3

P4

All activit

the LS1 schewere only rCERN-wide injection in tnot retained (12-13 weekLS2 (current

The availasuccess and were made tLS1 activitieinternational industrial serof these exteabove 850 pe

A massivelast two yesafety analysChange Req

Table1:

Activity

Safety

LHC operaperformanc

Reliable op

CERN app

Non-CERN

ties classified edule. The acretained if th

resource-loadthe LHC machare postpone

ks) after 2015tly planned in ability of humin defining th

to redirect CEes, to initiate o

institutes arvice contracternal resourceersons during e and solid prears: detailed sis, ALARA

quest (ECR),

LS1 Priorities

ation at 7 TeVce

peration up to

proved project

N approved pr

as P0 to P2 ctivities with phey were comded planning hine by Januad for the win or for the ne2018).

man resources he length of LERN internal or strengthen cand to estabs. Figure 1 shes during thethe summer 2eparation has

and documplans, integralogistics, etc

Figure 2

s

V with nomin

LS2

ts

rojects

were integratpriority P3 anmpatible with

allowing a bary 2015. Activnter technical ext long shutd

is decisive foLS1. Major eresources tow

collaborationsblish or reinhows the evol LS1 with a

2013. taken place i

mented procedation, Engine. With all the

2: The main L

nal

ted in nd P4 h the beam vities stops down

or the efforts wards s with nforce lution peak

in the dures, eering e co-

activthe conf

Figudurin

Seof ninclucater

DedefinFiguthatblock

InLHCprese

LS1 schedule f

vities and the accelerators

firmed as THE

ure 1: Overall ng LS1.

everal logisticnew personneluded registratiring, accommoetailed scheduned, discussedure 2 shows, a

is driven byks).

n the followinC injectors andented.

for the LHC m

large number(up to 1600

E priority of th

additional nu

cs issues, indul, had to be ion, training, odation, etc. ules for the Ld and approveas an exampley the splice

ng sections, thd the two mai

machine.

rs of persons ipersons), th

he LS1.

umber of pers

uced by the mspecially addtransport, par

LHC and its ied by all the , the scheduleconsolidation

the main activain projects in

intervening ine safety was

sons at CERN

massive arrivaldressed: theserking, access,

njectors werestakeholders.

e for the LHCn work (blue

vities for then the LHC are

n s

N

l e ,

e .

C e

e e

Proceedings of IPAC2013, Shanghai, China MOZB202

01 Circular and Linear Colliders

A01 Hadron Colliders

ISBN 978-3-95450-122-9

45 Cop

yrig

htc ○

2013

byJA

CoW

—cc

Cre

ativ

eC

omm

onsA

ttri

butio

n3.

0(C

C-B

Y-3.

0)

Page 4: EUROPEAN ORGANIZATION FOR NUCLEAR …cds.cern.ch/record/1575133/files/CERN-ACC-2013-0084.pdfCERN-ACC-2013-0084 31/07/2013 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS

MAIN AAfter mor

long winter sLHC injectora full mainten

Several acthe LHC injduring LS1 bLS2 largely dteams. As it is impoprincipal onePS and PS B Installat

systems Replace Upgrade Improve

the PS Renovat Alignme Preparat

the PSBbeams, e

The main act Vacuum

test Upgrade

kicker s Major u

4 MW) Major c

allow th Replace

power c Realignm Replace

(sextant Installat

sectors (As an ex

managementvacuum leakLS1, should by its spare spare should

The LHC areas will rehalf of 2014and the SPS b

SUPERCCIRCUIT

As mentiSeptember 2detailed analy

ACTIVITIre than three shutdowns thars and the assnance of all th

ctivities in theectors (LIU p

but some LIU due to the ove

ossible to menes are listed booster (PSB) tion and com

ement of the coe of the RF syement of th

tion of the PSent work tory works fo

B (e.g. new beetc.). tivities in the

m coating of 1

e and reductystems

upgrade of RF

apacity upgrahe above RF uement of 18 converters ment works

ement of irrt 1) and in Nortion of new (BA1, BA5 anxample of t of the shutdok in injection be mentionedis compulsorybe planned. injectors ansume gradual

4: the PSB byby mid-Octob

CONDUCTTS CONSOioned in the2008 incident,ysis of all the

IES FOR INyears of ope

at were the noociated experhe equipment e framework project [4]) hactivities wer

erload of the c

ntion all the below. The maare:

mmissioning o

ooling and veystems he radiation

vacuum cont

or 2 GeV upgream bump to h

SPS are: 6 dipoles for

tion of the i

systems (pow

ade for coolingupgrade tests a

kV transform

adiated cablerth experimenoptical fibre

nd BA6) the dynamic

own activities,PSB kicker,

d. The replacemy and the con

nd the respeclly their operay mid-June, thber 2014.

TING MALIDATIONe introductio, a dedicated magnet circu

NJECTOReration withouorm in the pasrimental areassystems. of the upgrad

have been plare postponed tcabling superv

activities, onlain activities i

of the new a

ntilation syste

n shielding

trol system

rade during Lhandle Linac4

e-cloud mitig

impedance o

wer increased

g and ventilatiand later operamers for the

es in one sntal area (TCCe systems in

c and contin, the discoveryat the start o

ment of this knstruction of a

ctive experimation in the sehe PS by mid

AGNETS AN (SMACCon, following

task force mauits [1].

RS ut the st, the need

de of anned to the vision

ly the in the

access

em

over

LS2 in 4 type

gation

f the

up to

ion to ation main

sector C2)

three

nuous y of a of the kicker a new

mental econd d-July

AND C) g the ade a

Thof althe n

Fo(Octspecdesigqualend 2

Thconsa newdesigenvirstresrequ

Figuquad

Figusupp

Thconsinsulsplicthe s

he Splices Tasll supercondunecessary consollowing threetober 2010, Noification of thgn, the detaiity assurance 2012. he central csists in addingw electrical ingn had to beronment and t

ss, radiation uirements:

The shunts arenewing thcontinuity ofall conditionsThe electricproviding sucircuits and mechanical deformationsLorentz force

ure 3: Designdrupole magne

ure 4: The neport box enclo

he quality consolidated splilation boxes ces. In additiosplices have to

sk Force was cting splices isolidation actie reviews by aovember 2011he consolidatiled consolida

(QA) were f

consolidation g a shunt acrosnsulation systee compatible to meet electrresistance a

applied to thehem) have tf the copper sts. al insulationfficient dielec

to ground, restraint th

s of the bus es.

n of the consets bus splice.

ew electrical ising two para

ntrols will be aices. The newill be instal

on, it is expeco be completel

set up to reviin the LHC aions [5]. an internation1 and Novembted splices, thation procedufinalised and

of the inss the splice iem (see Figs.

e with the exrical resistancand hydraulic

e present splto ensure t

stabiliser of th

n system, in ctric strength

also has that limits s

bars and sp

solidated dipo

insulation anallel bus line sp

applied both toew shunts alled on all 13cted that abouly opened and

iew the statusand to prepare

nal committeeber 2012), thehe subsequentures and theapproved by

nterconnectioninterfaces and3 and 4). Thexisting splicee, mechanicalc impedance

lices (withoutthe electricalhe bus bars in

addition toh between theo provide astresses andplices due to

ole (top) and

d mechanicalplices.

o existing andand the new3 kA bus barut 10-15 % ofd remade.

s e

e e t e y

n d e e l e

t l n

o e a d o

d

l

d w r f

MOZB202 Proceedings of IPAC2013, Shanghai, China

ISBN 978-3-95450-122-9

46Cop

yrig

htc ○

2013

byJA

CoW

—cc

Cre

ativ

eC

omm

onsA

ttri

butio

n3.

0(C

C-B

Y-3.

0)

01 Circular and Linear Colliders

A01 Hadron Colliders

Page 5: EUROPEAN ORGANIZATION FOR NUCLEAR …cds.cern.ch/record/1575133/files/CERN-ACC-2013-0084.pdfCERN-ACC-2013-0084 31/07/2013 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS

That meanredone and mpossible prosuperconduct

The teambetween eacwill repair ana time, withentire 27-kmproduction raconstant chal

LS1 is alsoin the magnoperation atsuperconduct3 quadrupole

The SMACthe cryogenicrelief valves2009. Figuremain activitie

These activeffort of abou

RADIATA Radiati

created in 2radiation inunderground

The level ofrom the col

Fig

ns that 1000–more than 27oblems with ting cable and

ms will need h of the 1695nd consolidateh a work sitem circumferenate of 53 interllenge and is co the opportun

net circuits, wt 7 TeV perting magnets

es. CC project alc feed boxes

s on the secte 5 illustrateses of the SMAvities will requt 260 person

TION TO Eion to Electr

2007 to evalun the controld areas of the Lof the flux of llimation syste

gure 5: The m

–1500 splices,000 shunts a

poor contad the copper st

to open the5 main magne around 500 ie that will grnce of the Lrconnections pclosely monitonity to resolve

which could br beam. As will be replac

so includes thand the instal

tors that weres, in a very ACC project [6quire 15 months.

ELECTROronics (R2E) uate the risk l equipment LHC. hadrons in theem (Point 7 o

ain SMACC c

s will need tadded to overacts betweentabilizer. e interconnecnet cryostats. interconnectioradually cove

LHC. The plaper week willored. e non-conformbe a limitatioa result 18

ced: 15 dipole

he consolidatillation of prese not equippeconcise form6]. hs and a comb

ONICS (R2ETask Force

of failures duinstalled in

e multi MeV rof LHC) and

consolidations

to be rcome n the

ctions They

ons at er the anned l be a

mities on for

main es and

ion of ssure-ed in

m, the

bined

E) was ue to

n the

range from

the cinduelectlocatLHC(fromthe relocshielachiefor fnom

A aftercriticactioetc.) The threerespo

DuPoinpowshielwill are min pProtethan R2Eand a

s during the L

collisions in Auce Single Etronics presentions. During

C operation wm 12 dumps p2011-2012 wcation of senlding. During eved to increafailures of con

minal beam conphased strate

r massive equcal componenons (relocation

was establishR2E project

e years, in cloonsible for LHuring LS1, 15

nts 1, 5, 7 aner racks willlding in the sbe reinforced

most vulnerabower convertection System1000 circuit

work is expea combined ef

Long Shutdown

Atlas, CMS anEvent Errors nt in the equip

2011 and 20as measured (per fb-1 to 3 d

winter stop wnsitive equipm

LS1 a reductase the MTBFntrols electronnditions. egy was propuipment testints, and a prn or redesign

hed to solve thteam has bee

ose collaboratHC equipment5 equipment gd 8, where ml have to beservice cavernd. In the LHC ble to single-eters, cryogeni

m). To make thcards will be cted to take slffort of about

wn 1.

nd LHCb (Poin(SEEs) on

pment located012, the pertur(Fig. 6). The dumps per fb

was obtained ment and sotion by a factF of the LHCnics caused b

posed by theing campaignragmatic list n of equipmehe identified pen working ftion with all t and servicesgroups will b

more than 100e moved. In ns (RR) at Potunnel, the el

event effects aics and the Qhe QPS more

e replaced durlightly more t150 persons.

nts 1,5 and 8)the standard

d around theserbation to theimprovement-1) brought inby a partial

ome strategictor 6 must be

C to one weeky radiation at

R2E projectns to identifyof mitigation

ent, shielding,problems for more thanof the groups.

be working at0 control andaddition, the

oints 1 and 5lectronics thatare those usedQPS (Quenche robust, morering LS1. Thethan 70 weeks

) d e e t n l c e k t

t y n ,

n s

t d e 5 t d h e e s

Proceedings of IPAC2013, Shanghai, China MOZB202

01 Circular and Linear Colliders

A01 Hadron Colliders

ISBN 978-3-95450-122-9

47 Cop

yrig

htc ○

2013

byJA

CoW

—cc

Cre

ativ

eC

omm

onsA

ttri

butio

n3.

0(C

C-B

Y-3.

0)

Page 6: EUROPEAN ORGANIZATION FOR NUCLEAR …cds.cern.ch/record/1575133/files/CERN-ACC-2013-0084.pdfCERN-ACC-2013-0084 31/07/2013 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS

Figure 6: LHagainst beam

LAll the LH

T, i.e. well during indivithe first estnominal wasdipoles. In 2trained to 5 was pushed quenches wenone for themagnets werrepairs, not ithem were te3.5 TeV anddata was amodelling sid

An analysnegligible trquenches for(10-15 quenc

Figure 7: SumLHC dipoles

Obviouslyassociated towill be confiin June 2014

HC beam dumm luminosity.

LHC ENERHC main dipo

above 8.3 Tidual tests at timate of ~3 given, i.e. ab

2008 all the LTeV, two seup to 6.6 TeVere needed toe quadrupolesre removed frinvolving the ested in SM1d 4 TeV duriaccumulated de was deploysis of all the raining is ner 6.25 TeV aches per secto

mmary of estis to reach 6-7 T

y due to the o these estimairmed during

4.

mps due to si

RGY AFTERoles were trainT or 7 TeV e

CERN [7]. B30 quenches

bout one quencLHC main dictors to 6 TeV. In the 5-6 o retrain the s. After the rom Sector 3-active part of8. As the LHing 2012, no but addition

yed. available es

eeded to reaand 0-100 quer) (Fig. 7).

imates of needTeV equivale

very limited ates is large, the first pow

ingle-event ef

R LS1 ned to reach equivalent en

Based on thisneeded to r

ch every four ipole circuits eV, and one s

TeV range, aLHC dipoles2008 inciden-4 and after mf the magnet,

HC was operatadditional qu

nal effort on

timates showach 6 TeV, enches to 6.5

ded training innt energy.

dataset, thebut these numering tests sta

ffects

8.5-9 nergy,

data, reach LHC were

sector a few s, and nt, 39 minor 32 of ted at uench n the

w that 0-50

TeV

n the

error mbers arting

Baand quenTeV2015additincre

Af20132013

Thobjespliccircube fiwarmmid-compand mondash

Thbut tmanyend qual

Thpartiinvo

[1]

[2]

[3]

[4]

[5]

[6]

[7]

[8]

ased on these thermal stress

nch, a decisioV after the LS15, it could btional poweriease the energ

fter a last sh3 [3], the first 3. he first activictive to ident

ces in the muits of the LHixed during Lm-up of the 8-May 2013. Tplex have nowin the injecto

nths. The proghboards updatehe LS1 is a mthanks to a soy people, croof 2014, resity second, sc

ACKhe authors wicipating to tlved from ext

P. Lebrun et alof 19 SeptembReport 1168, 3F. Formenti, eSystems for tMachine at CEOperational ExM. Lamont, “Luminosity ProR. Garoby et aLHC Injectors”F. Bertinelli esuperconductinKyoto, May 20J.Ph. Tock et conducting cicollisions”, IPAE. Todesco, “Shutdown”, Performance, C267 http://lhcdashb

estimates andses in the supon was taken

. Based on thbe decided toing tests (e.g.gy before or af

CONCLUShift from Nov

long shutdow

ities were thetify possible l

main circuits)HC for the opeLS1. These tes

sectors of thThe main projw started, afters) and are on

gress of the Led every week

marathon and wolid preparatiossing the fini

specting the Lhedule third”.

KNOWLEDould like to the LS1 projernal collabor

REFERENl., “Report of thber 2008 at the1st March, 200et al, “Upgradthe SuperconduERN: From Conxperience”, IPA“The First Yeoduction”, IPACal., “Status and ”, IPAC’13, Shaet al., “Towarng splices for 7010

al., “Consoliircuits: a majAC’12, New Or“Energy of theChamonix 20Chamonix, Fran

oard.web.cern.c

d to limit stronperconducting

to restart thehe operational to push this . end of run) fter the LS2.

SIONS vember 2012

wn started on

e powering tlimitations (o

) on the superation at 7 Tsts were very

he LHC will bjects across ther the powerinn schedule afLS1 can be fk [8]. will not be allon and to the ish line is forLS1 slogan: .

DGMENTSthank all the

ject, as well rations and co

NCES he Task Force e LHC”, CERN09 de of the Queucting Circuitsncept and Desi

AC’10, Kyoto, Mears of LHC C’13, Shanghai

d Plans for the Uanghai, May 20rds a consolid7 TeV operati

idation of theajor step towrleans, May 201e LHC after t012 Workshonce, 6 - 10 Feb

ch/lhcdashboar

ng mechanicalcoil during a

e LHC at 6.5experience inlimit duringand whether

2 to February14th February

tests with theother than theperconductingTeV that must

positive. Thebe finished byhe acceleratorng tests (LHCfter the first 3followed with

l plain sailingdedication of

reseen for the“Safety first,

S e CERN staff

as all thoseontractors.

on the incidentN LHC Project

nch Protections of the LHCign to the First

May 2010 Operation for

i, May 2013 Upgrade of the013 dation of LHCion”, IPAC’10,

e LHC super-ards 14 TeV12 the 2013-2014op on LHCb 2012, pp.265-

rd/ls1/

l a 5 n g r

y y

e e g t e y r

C 3 h

g f e ,

f e

t t

n C t

r

e

C ,

-V

4 C -

MOZB202 Proceedings of IPAC2013, Shanghai, China

ISBN 978-3-95450-122-9

48Cop

yrig

htc ○

2013

byJA

CoW

—cc

Cre

ativ

eC

omm

onsA

ttri

butio

n3.

0(C

C-B

Y-3.

0)

01 Circular and Linear Colliders

A01 Hadron Colliders


Recommended