CER
N-A
CC
-201
3-00
8431
/07/
2013
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCHCERN - ACCELERATORS AND TECHNOLOGY SECTOR
The First Long Shutdown (LS1) for the LHC
F. Bordry, S. Baird, K. Foraz, A.-L. Perrot, R. Saban, J.Ph. TockCERN, Geneva, Switzerland
The LHC has been delivering data to the physics experiments since the first collisions in 2009. The first long
shutdown (LS1), which started on 14 February 2013, was triggered by the need to consolidate the magnet
interconnections to allow the LHC to operate at the design energy of 14 TeV in the centre-of-mass. It has now become
a major shutdown, which, in addition, includes other repairs, consolidation, upgrades and cabling across the whole
accelerator complex and the associated experimental facilities. A detailed CERN-wide resource-loaded schedule was
prepared aiming at resuming LHC physics in early 2015, while the rest of the CERN complex will gradually start up
again in the second half of 2014.
The paper describes the preparation phase with the prioritisation of the activities, the building of the teams and the
planning of the shutdown. Then, it gives an overview of the injector activities and the main projects in the LHC. The
decision to restart at 6.5 TeV after the LS1 is recalled.
Presented at IPAC'2013, 4th International Particle Accelerator Conference12-17 May 2013 - Shanghai, China
Geneva, Switzerland
CERN-ATS-2013-0084
July 2013
THE FIRST LONG SHUTDOWN (LS1) FOR THE LHC
F. Bordry, S. Baird, K. Foraz, A.L. Perrot, R. Saban, J.P Tock, CERN, Geneva, Switzerland
Abstract The LHC has been delivering data to the physics
experiments since the first collisions in 2009. The first long shutdown (LS1), which started on 14 February 2013, was triggered by the need to consolidate the magnet interconnections to allow the LHC to operate at the design energy of 14 TeV in the centre-of-mass. It has now become a major shutdown, which, in addition, includes other repairs, consolidation, upgrades and cabling across the whole accelerator complex and the associated experimental facilities. A detailed CERN-wide resource-loaded schedule was prepared aiming at resuming LHC physics in early 2015, while the rest of the CERN complex will gradually start up again in the second half of 2014.
The paper describes the preparation phase with the prioritisation of the activities, the building of the teams and the planning of the shutdown. Then, it gives an overview of the injector activities and the main projects in the LHC. The decision to restart at 6.5 TeV after the LS1 is recalled.
INTRODUCTION Following the incident in one of the main dipole
circuits of the LHC on September 19th 2008, a detailed analysis was carried out [1]. Thanks to the availability of spare magnets, Sector 3-4 could be repaired in 6 months. In addition, a global consolidation of the magnet protection system and important re-engineering of several systems took place so that such an incident would be avoided in the future.
An upgraded quench protection system was designed and installed to protect all bus-bar joints of the arc main dipole and main quadrupole circuits [2]. In parallel an improved pressure relief system for the insulation vacuum was installed on the magnet cryostats. But in order to restart quickly the LHC (November 2009) and to provide data to the experiments, it was decided to warm-up only four LHC sectors, therefore the 200 mm diameter valves for the improvement of the pressure relief system were only installed on these four sectors.
The interconnections between the LHC main magnets are made of soldered joints (splices) of two superconducting cables stabilized by a copper bus bar. The measurements performed in 2009 in the four warm sectors demonstrated that there are defective copper bus bar joints in the machine (10-15% of the high current interconnections). Based on these measurements, it was decided to restart the LHC operation at 3.5 TeV and to consolidate the LHC during the LS1 in 2012. With the respectable integrated luminosity in 2011, the CERN management decide to run the LHC through 2012 to give
to the experiments the data needed to fully explore this energy range before moving up to higher energy. To enhance the discovery potential, after two years of operation and an operational experience with stored beams exceeding 100 MJ, the beam energy was increased to 4 TeV in 2012.
Thanks to the fantastic LHC performance [3], this staged strategy proved successful and culminated, with the announcement of the discovery of a Higgs-like boson on 4th July 2012.
LS1 STRATEGY AND RESSOURCES As described above, the LS1 was triggered by the need
to consolidate the magnet interconnections to allow the LHC to operate at the design energy of 14 TeV in the centre-of-mass. It became rapidly a major shutdown, which, in addition, includes other repairs, consolidations, upgrades and cabling across the whole accelerator complex and the associated experimental facilities. LS1 will see a massive programme of maintenance for the LHC and its injectors in the wake of more than three years of operation without the long winter shutdowns that were the norm in the past.
The LS1 preparation started just after the decision to resume the LHC operation at 3.5 TeV, i.e. more than three years ago. The strategy was to define the duration of key activities needed for safe and reliable operation of the CERN accelerator complex (LHC and its injectors) to run the LHC at 7 TeV at the nominal luminosity. After several iterations with the technical coordination of the LHC experiments, the LHC machine and its injectors, the minimum time needed from “beam off” to “beam on” in the LHC was determined to be 20 months. Rapidly it became clear that it would be necessary to prioritize all the activities requested by equipment groups and the projects; this to ensure that the 20 month time frame would be sufficient to perform all the consolidation and upgrades needed to achieve the goals of LS1 (as well as carry out the full maintenance of the different systems),. Often these interventions are planned and organized in terms of the resources in the groups, therefore it was vital to gather all the information on the support needed from other groups, to check the coactivity conflicts and to define the required manpower. Regular and dedicated meetings were held with the different stakeholders to obtain a clear and complete picture of the activities related to the accelerator complex and the LHC experiments. All the information was compiled in a database and a special software tool (PLAN) was developed as a decision support tool.
The five following levels were set to prioritize all the activities:
MOZB202 Proceedings of IPAC2013, Shanghai, China
ISBN 978-3-95450-122-9
44Cop
yrig
htc ○
2013
byJA
CoW
—cc
Cre
ativ
eC
omm
onsA
ttri
butio
n3.
0(C
C-B
Y-3.
0)
01 Circular and Linear Colliders
A01 Hadron Colliders
Priority
P0
P1
P2
P3
P4
All activit
the LS1 schewere only rCERN-wide injection in tnot retained (12-13 weekLS2 (current
The availasuccess and were made tLS1 activitieinternational industrial serof these exteabove 850 pe
A massivelast two yesafety analysChange Req
Table1:
Activity
Safety
LHC operaperformanc
Reliable op
CERN app
Non-CERN
ties classified edule. The acretained if th
resource-loadthe LHC machare postpone
ks) after 2015tly planned in ability of humin defining th
to redirect CEes, to initiate o
institutes arvice contracternal resourceersons during e and solid prears: detailed sis, ALARA
quest (ECR),
LS1 Priorities
ation at 7 TeVce
peration up to
proved project
N approved pr
as P0 to P2 ctivities with phey were comded planning hine by Januad for the win or for the ne2018).
man resources he length of LERN internal or strengthen cand to estabs. Figure 1 shes during thethe summer 2eparation has
and documplans, integralogistics, etc
Figure 2
s
V with nomin
LS2
ts
rojects
were integratpriority P3 anmpatible with
allowing a bary 2015. Activnter technical ext long shutd
is decisive foLS1. Major eresources tow
collaborationsblish or reinhows the evol LS1 with a
2013. taken place i
mented procedation, Engine. With all the
2: The main L
nal
ted in nd P4 h the beam vities stops down
or the efforts wards s with nforce lution peak
in the dures, eering e co-
activthe conf
Figudurin
Seof ninclucater
DedefinFiguthatblock
InLHCprese
LS1 schedule f
vities and the accelerators
firmed as THE
ure 1: Overall ng LS1.
everal logisticnew personneluded registratiring, accommoetailed scheduned, discussedure 2 shows, a
is driven byks).
n the followinC injectors andented.
for the LHC m
large number(up to 1600
E priority of th
additional nu
cs issues, indul, had to be ion, training, odation, etc. ules for the Ld and approveas an exampley the splice
ng sections, thd the two mai
machine.
rs of persons ipersons), th
he LS1.
umber of pers
uced by the mspecially addtransport, par
LHC and its ied by all the , the scheduleconsolidation
the main activain projects in
intervening ine safety was
sons at CERN
massive arrivaldressed: theserking, access,
njectors werestakeholders.
e for the LHCn work (blue
vities for then the LHC are
n s
N
l e ,
e .
C e
e e
Proceedings of IPAC2013, Shanghai, China MOZB202
01 Circular and Linear Colliders
A01 Hadron Colliders
ISBN 978-3-95450-122-9
45 Cop
yrig
htc ○
2013
byJA
CoW
—cc
Cre
ativ
eC
omm
onsA
ttri
butio
n3.
0(C
C-B
Y-3.
0)
MAIN AAfter mor
long winter sLHC injectora full mainten
Several acthe LHC injduring LS1 bLS2 largely dteams. As it is impoprincipal onePS and PS B Installat
systems Replace Upgrade Improve
the PS Renovat Alignme Preparat
the PSBbeams, e
The main act Vacuum
test Upgrade
kicker s Major u
4 MW) Major c
allow th Replace
power c Realignm Replace
(sextant Installat
sectors (As an ex
managementvacuum leakLS1, should by its spare spare should
The LHC areas will rehalf of 2014and the SPS b
SUPERCCIRCUIT
As mentiSeptember 2detailed analy
ACTIVITIre than three shutdowns thars and the assnance of all th
ctivities in theectors (LIU p
but some LIU due to the ove
ossible to menes are listed booster (PSB) tion and com
ement of the coe of the RF syement of th
tion of the PSent work tory works fo
B (e.g. new beetc.). tivities in the
m coating of 1
e and reductystems
upgrade of RF
apacity upgrahe above RF uement of 18 converters ment works
ement of irrt 1) and in Nortion of new (BA1, BA5 anxample of t of the shutdok in injection be mentionedis compulsorybe planned. injectors ansume gradual
4: the PSB byby mid-Octob
CONDUCTTS CONSOioned in the2008 incident,ysis of all the
IES FOR INyears of ope
at were the noociated experhe equipment e framework project [4]) hactivities wer
erload of the c
ntion all the below. The maare:
mmissioning o
ooling and veystems he radiation
vacuum cont
or 2 GeV upgream bump to h
SPS are: 6 dipoles for
tion of the i
systems (pow
ade for coolingupgrade tests a
kV transform
adiated cablerth experimenoptical fibre
nd BA6) the dynamic
own activities,PSB kicker,
d. The replacemy and the con
nd the respeclly their operay mid-June, thber 2014.
TING MALIDATIONe introductio, a dedicated magnet circu
NJECTOReration withouorm in the pasrimental areassystems. of the upgrad
have been plare postponed tcabling superv
activities, onlain activities i
of the new a
ntilation syste
n shielding
trol system
rade during Lhandle Linac4
e-cloud mitig
impedance o
wer increased
g and ventilatiand later operamers for the
es in one sntal area (TCCe systems in
c and contin, the discoveryat the start o
ment of this knstruction of a
ctive experimation in the sehe PS by mid
AGNETS AN (SMACCon, following
task force mauits [1].
RS ut the st, the need
de of anned to the vision
ly the in the
access
em
over
LS2 in 4 type
gation
f the
up to
ion to ation main
sector C2)
three
nuous y of a of the kicker a new
mental econd d-July
AND C) g the ade a
Thof althe n
Fo(Octspecdesigqualend 2
Thconsa newdesigenvirstresrequ
Figuquad
Figusupp
Thconsinsulsplicthe s
he Splices Tasll supercondunecessary consollowing threetober 2010, Noification of thgn, the detaiity assurance 2012. he central csists in addingw electrical ingn had to beronment and t
ss, radiation uirements:
The shunts arenewing thcontinuity ofall conditionsThe electricproviding sucircuits and mechanical deformationsLorentz force
ure 3: Designdrupole magne
ure 4: The neport box enclo
he quality consolidated splilation boxes ces. In additiosplices have to
sk Force was cting splices isolidation actie reviews by aovember 2011he consolidatiled consolida
(QA) were f
consolidation g a shunt acrosnsulation systee compatible to meet electrresistance a
applied to thehem) have tf the copper sts. al insulationfficient dielec
to ground, restraint th
s of the bus es.
n of the consets bus splice.
ew electrical ising two para
ntrols will be aices. The newill be instal
on, it is expeco be completel
set up to reviin the LHC aions [5]. an internation1 and Novembted splices, thation procedufinalised and
of the inss the splice iem (see Figs.
e with the exrical resistancand hydraulic
e present splto ensure t
stabiliser of th
n system, in ctric strength
also has that limits s
bars and sp
solidated dipo
insulation anallel bus line sp
applied both toew shunts alled on all 13cted that abouly opened and
iew the statusand to prepare
nal committeeber 2012), thehe subsequentures and theapproved by
nterconnectioninterfaces and3 and 4). Thexisting splicee, mechanicalc impedance
lices (withoutthe electricalhe bus bars in
addition toh between theo provide astresses andplices due to
ole (top) and
d mechanicalplices.
o existing andand the new3 kA bus barut 10-15 % ofd remade.
s e
e e t e y
n d e e l e
t l n
o e a d o
d
l
d w r f
MOZB202 Proceedings of IPAC2013, Shanghai, China
ISBN 978-3-95450-122-9
46Cop
yrig
htc ○
2013
byJA
CoW
—cc
Cre
ativ
eC
omm
onsA
ttri
butio
n3.
0(C
C-B
Y-3.
0)
01 Circular and Linear Colliders
A01 Hadron Colliders
That meanredone and mpossible prosuperconduct
The teambetween eacwill repair ana time, withentire 27-kmproduction raconstant chal
LS1 is alsoin the magnoperation atsuperconduct3 quadrupole
The SMACthe cryogenicrelief valves2009. Figuremain activitie
These activeffort of abou
RADIATA Radiati
created in 2radiation inunderground
The level ofrom the col
Fig
ns that 1000–more than 27oblems with ting cable and
ms will need h of the 1695nd consolidateh a work sitem circumferenate of 53 interllenge and is co the opportun
net circuits, wt 7 TeV perting magnets
es. CC project alc feed boxes
s on the secte 5 illustrateses of the SMAvities will requt 260 person
TION TO Eion to Electr
2007 to evalun the controld areas of the Lof the flux of llimation syste
gure 5: The m
–1500 splices,000 shunts a
poor contad the copper st
to open the5 main magne around 500 ie that will grnce of the Lrconnections pclosely monitonity to resolve
which could br beam. As will be replac
so includes thand the instal
tors that weres, in a very ACC project [6quire 15 months.
ELECTROronics (R2E) uate the risk l equipment LHC. hadrons in theem (Point 7 o
ain SMACC c
s will need tadded to overacts betweentabilizer. e interconnecnet cryostats. interconnectioradually cove
LHC. The plaper week willored. e non-conformbe a limitatioa result 18
ced: 15 dipole
he consolidatillation of prese not equippeconcise form6]. hs and a comb
ONICS (R2ETask Force
of failures duinstalled in
e multi MeV rof LHC) and
consolidations
to be rcome n the
ctions They
ons at er the anned l be a
mities on for
main es and
ion of ssure-ed in
m, the
bined
E) was ue to
n the
range from
the cinduelectlocatLHC(fromthe relocshielachiefor fnom
A aftercriticactioetc.) The threerespo
DuPoinpowshielwill are min pProtethan R2Eand a
s during the L
collisions in Auce Single Etronics presentions. During
C operation wm 12 dumps p2011-2012 wcation of senlding. During eved to increafailures of con
minal beam conphased strate
r massive equcal componenons (relocation
was establishR2E project
e years, in cloonsible for LHuring LS1, 15
nts 1, 5, 7 aner racks willlding in the sbe reinforced
most vulnerabower convertection System1000 circuit
work is expea combined ef
Long Shutdown
Atlas, CMS anEvent Errors nt in the equip
2011 and 20as measured (per fb-1 to 3 d
winter stop wnsitive equipm
LS1 a reductase the MTBFntrols electronnditions. egy was propuipment testints, and a prn or redesign
hed to solve thteam has bee
ose collaboratHC equipment5 equipment gd 8, where ml have to beservice cavernd. In the LHC ble to single-eters, cryogeni
m). To make thcards will be cted to take slffort of about
wn 1.
nd LHCb (Poin(SEEs) on
pment located012, the pertur(Fig. 6). The dumps per fb
was obtained ment and sotion by a factF of the LHCnics caused b
posed by theing campaignragmatic list n of equipmehe identified pen working ftion with all t and servicesgroups will b
more than 100e moved. In ns (RR) at Potunnel, the el
event effects aics and the Qhe QPS more
e replaced durlightly more t150 persons.
nts 1,5 and 8)the standard
d around theserbation to theimprovement-1) brought inby a partial
ome strategictor 6 must be
C to one weeky radiation at
R2E projectns to identifyof mitigation
ent, shielding,problems for more thanof the groups.
be working at0 control andaddition, the
oints 1 and 5lectronics thatare those usedQPS (Quenche robust, morering LS1. Thethan 70 weeks
) d e e t n l c e k t
t y n ,
n s
t d e 5 t d h e e s
Proceedings of IPAC2013, Shanghai, China MOZB202
01 Circular and Linear Colliders
A01 Hadron Colliders
ISBN 978-3-95450-122-9
47 Cop
yrig
htc ○
2013
byJA
CoW
—cc
Cre
ativ
eC
omm
onsA
ttri
butio
n3.
0(C
C-B
Y-3.
0)
Figure 6: LHagainst beam
LAll the LH
T, i.e. well during indivithe first estnominal wasdipoles. In 2trained to 5 was pushed quenches wenone for themagnets werrepairs, not ithem were te3.5 TeV anddata was amodelling sid
An analysnegligible trquenches for(10-15 quenc
Figure 7: SumLHC dipoles
Obviouslyassociated towill be confiin June 2014
HC beam dumm luminosity.
LHC ENERHC main dipo
above 8.3 Tidual tests at timate of ~3 given, i.e. ab
2008 all the LTeV, two seup to 6.6 TeVere needed toe quadrupolesre removed frinvolving the ested in SM1d 4 TeV duriaccumulated de was deploysis of all the raining is ner 6.25 TeV aches per secto
mmary of estis to reach 6-7 T
y due to the o these estimairmed during
4.
mps due to si
RGY AFTERoles were trainT or 7 TeV e
CERN [7]. B30 quenches
bout one quencLHC main dictors to 6 TeV. In the 5-6 o retrain the s. After the rom Sector 3-active part of8. As the LHing 2012, no but addition
yed. available es
eeded to reaand 0-100 quer) (Fig. 7).
imates of needTeV equivale
very limited ates is large, the first pow
ingle-event ef
R LS1 ned to reach equivalent en
Based on thisneeded to r
ch every four ipole circuits eV, and one s
TeV range, aLHC dipoles2008 inciden-4 and after mf the magnet,
HC was operatadditional qu
nal effort on
timates showach 6 TeV, enches to 6.5
ded training innt energy.
dataset, thebut these numering tests sta
ffects
8.5-9 nergy,
data, reach LHC were
sector a few s, and nt, 39 minor 32 of ted at uench n the
w that 0-50
TeV
n the
error mbers arting
Baand quenTeV2015additincre
Af20132013
Thobjespliccircube fiwarmmid-compand mondash
Thbut tmanyend qual
Thpartiinvo
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
ased on these thermal stress
nch, a decisioV after the LS15, it could btional poweriease the energ
fter a last sh3 [3], the first 3. he first activictive to ident
ces in the muits of the LHixed during Lm-up of the 8-May 2013. Tplex have nowin the injecto
nths. The proghboards updatehe LS1 is a mthanks to a soy people, croof 2014, resity second, sc
ACKhe authors wicipating to tlved from ext
P. Lebrun et alof 19 SeptembReport 1168, 3F. Formenti, eSystems for tMachine at CEOperational ExM. Lamont, “Luminosity ProR. Garoby et aLHC Injectors”F. Bertinelli esuperconductinKyoto, May 20J.Ph. Tock et conducting cicollisions”, IPAE. Todesco, “Shutdown”, Performance, C267 http://lhcdashb
estimates andses in the supon was taken
. Based on thbe decided toing tests (e.g.gy before or af
CONCLUShift from Nov
long shutdow
ities were thetify possible l
main circuits)HC for the opeLS1. These tes
sectors of thThe main projw started, afters) and are on
gress of the Led every week
marathon and wolid preparatiossing the fini
specting the Lhedule third”.
KNOWLEDould like to the LS1 projernal collabor
REFERENl., “Report of thber 2008 at the1st March, 200et al, “Upgradthe SuperconduERN: From Conxperience”, IPA“The First Yeoduction”, IPACal., “Status and ”, IPAC’13, Shaet al., “Towarng splices for 7010
al., “Consoliircuits: a majAC’12, New Or“Energy of theChamonix 20Chamonix, Fran
oard.web.cern.c
d to limit stronperconducting
to restart thehe operational to push this . end of run) fter the LS2.
SIONS vember 2012
wn started on
e powering tlimitations (o
) on the superation at 7 Tsts were very
he LHC will bjects across ther the powerinn schedule afLS1 can be fk [8]. will not be allon and to the ish line is forLS1 slogan: .
DGMENTSthank all the
ject, as well rations and co
NCES he Task Force e LHC”, CERN09 de of the Queucting Circuitsncept and Desi
AC’10, Kyoto, Mears of LHC C’13, Shanghai
d Plans for the Uanghai, May 20rds a consolid7 TeV operati
idation of theajor step towrleans, May 201e LHC after t012 Workshonce, 6 - 10 Feb
ch/lhcdashboar
ng mechanicalcoil during a
e LHC at 6.5experience inlimit duringand whether
2 to February14th February
tests with theother than theperconductingTeV that must
positive. Thebe finished byhe acceleratorng tests (LHCfter the first 3followed with
l plain sailingdedication of
reseen for the“Safety first,
S e CERN staff
as all thoseontractors.
on the incidentN LHC Project
nch Protections of the LHCign to the First
May 2010 Operation for
i, May 2013 Upgrade of the013 dation of LHCion”, IPAC’10,
e LHC super-ards 14 TeV12 the 2013-2014op on LHCb 2012, pp.265-
rd/ls1/
l a 5 n g r
y y
e e g t e y r
C 3 h
g f e ,
f e
t t
n C t
r
e
C ,
-V
4 C -
MOZB202 Proceedings of IPAC2013, Shanghai, China
ISBN 978-3-95450-122-9
48Cop
yrig
htc ○
2013
byJA
CoW
—cc
Cre
ativ
eC
omm
onsA
ttri
butio
n3.
0(C
C-B
Y-3.
0)
01 Circular and Linear Colliders
A01 Hadron Colliders