Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009
Transcript
Page 1: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

Evaluation of Preliminary DFIRMsPhase I Findings

Evaluation of Preliminary DFIRMsPhase I Findings

Terrebonne Parish June 22, 2009

Page 2: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

Creation of a BFECreation of a BFE

Page 3: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

The ModelsThe ModelsStill Water Elevation =

1. ADCIRC – Advanced Circulation Model for Coastal Ocean Hydrodynamics. Developed by the USACE to determine the SWEL or storm surge levels for coastal LA.

2. STWAVE – a numerical model used to generate and transform w aves to the shore.

3. JPM-OS – provides a means to model the effects and probabilities of storms that historically have not occurred.

Wave Height =

4. WHAFIS – FEMA’s wave model, based on transects. Topographic characterics along each transect serve as inputs in the model (ground elevation, SWEL, vegetation, and physical features).

Preliminary DFIRMs

Page 4: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

02M

0620

07D

Summary of Phase I FindingsSummary of Phase I Findings

• Review of FEMA information indicates numerous scientific and technical deficiencies exist in the DFIRMs

• Primary deficiency appears to be the treatment of barriers in FEMA’s models

• The accurate horizontal location and vertical elevation of barriers should be identified and revised in the models (ex. Thompson Road Extension)

Page 5: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

Task 4.3: Review Set-up of Surge Models Used in the FIS

Task 4.3: Review Set-up of Surge Models Used in the FIS

***GRAPHICs dokka***

Page 6: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

Task 4.3: Review Set-up of Surge Models Used in the FIS

Task 4.3: Review Set-up of Surge Models Used in the FIS

***GRAPHIC***

Approximately 3 miles north of Dulac, east of Grand Caillou Road: Mis-location of barriers. Barriers defined by FEMA, green; Interagency Performance Team levees, yellow; Red dots, all barriers. Note major gap in barrier near center of picture.

Page 7: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

Possible OptionsPossible Options

Page 8: Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.

02M

0620

07D

Discussion of Phase II Discussion of Phase II

• Establish/Confirm Parish Objectives– Insurance Rates, Flood Protection, etc.

• Tailor Scope of Work to Target Objectives – Ensure models accurately depict barriers– Identify barriers that exist today– Identify barriers designed, funded, and at least 50%

complete– Establish horizontal accuracy– Remodel and re-map

• Prepare Appeal/Protest Document