Date post: | 21-Feb-2018 |
Category: |
Documents |
Upload: | maslena-arbi |
View: | 231 times |
Download: | 0 times |
of 28
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
1/28
ABB GroupApril 1, 2011 | Slide 1
Safety of Ex nA, Ex e and Class IDivision 2 motors
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
2/28
ABB GroupApril 1, 2011 | Slide 2
Standard with verification requirements
Only the latest editions of the IECand EN standards specify theproblem!
Many countries implement the IEC-standards into their nationalstandards.
Various countries define the edition
of the standards by internal rules
=> Many countries do not fol lowcontemporary the latestrequirements and therefore they arenot addressing the sparkingphenomena today.
Which international standards are addressing the sparkingphenomena?
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
3/28
ABB GroupApril 1, 2011 | Slide 3
Which international standards are addressing thesparking phenomena?
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
4/28
ABB GroupApril 1, 2011 | Slide 4
History of accident in theU.K.
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
5/28
ABB GroupApril 1, 2011 | Slide 5
Actions taken by Authorities
Initiated several studies
Based on studies, they gave series ofrecommendation to users mainly in the UK
The development of international standardswere initiated
Actions taken by End Users
Required gas environment testing in practiceand experience from the tests
Comparison between different practices tofulfill the standard requirements
Inspection and overhaul of electric motors onfield
Actions taken by standardizationcommittees
ENV 50269
Risk assessment requirements implementedto IEC/EN standards
History of accidents involving electric motors in the UK
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
6/28
ABB GroupApril 1, 2011 | Slide 6
Where and when sparkingcan occur
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
7/28
ABB GroupApril 1, 2011 | Slide 7
When and Where it can occur?
All the time when the motor isrunning
Partial discharges (PD) at thesurface of the winding
Partial discharges at the surfaces ofconnection cables
Main reasons for stator sparking
High voltage and improper stressgrading
Inadequate clearance distances
Direct contact between groundenclosure and high voltage cable
Heating wires mounted on coiloverhangs
Aging of the windings Voltage transients
Dirty surfaces of windings
Stator sparking in respect of safety
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
8/28
ABB GroupApril 1, 2011 | Slide 8
When and Where can it occur?
During the first cycles when motorsare started
Between rotor bars and rotor core
Close to end of rotor core packs orclose to the first radial cooling ducts
Main reasons for rotor sparking
Leakage current from rotor bar to rotorcore is switching due to possiblemovements of the rotor bars in the
slots
Rotor sparking in respect of safety
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
9/28
ABB GroupApril 1, 2011 | Slide 9
Circulating currents
Where and When can it occur?
Between separate parts of enclosures
When motor magnetized and running Over-voltages
Main reasons for circulating current
Parts get charges due to magnetic fluxcreated by the stator
Parts are not equip-potential bondedand they floating on own potential
Improper grounding Equip-potential cables are
disconnected
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
10/28
ABB GroupApril 1, 2011 | Slide 11
Note, waiver from some dutytypes where the motor isstarted once per week orless.
Non-sparking motors (IEC 60079-15:2005 and EN 60079-15:2005)
When risk assessment is applicable?
Increased safety motors (IEC 60079-7:2006 and EN 60079-7:2007)
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
11/28
ABB GroupApril 1, 2011 | Slide 12
Stator risk assessmentIncreased safety motors
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
12/28
ABB GroupApril 1, 2011 | Slide 13
Risk assessments for the Ex nA stator
constructions shall be if the sum of
risk factors is greater than 6:
Stator design shall be pass the required
non-sparking tests, or
Motor shall be equipped with a provision
pre-start ventilation (Note! operatorneeds to make decision to use it or not
based their possibility accept the risk)
Note, the table will be moved to IEC 60079-14 in the future, and the stator
gas testing will be compulsory for all random-wound high-voltage stators
and all high-voltage form-wound stators in gas groups IIC and IIB, as well as
in gas group IIA if the nominal voltage is greater than 6.6kV
Stator risk assessmentNon-sparking motors
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
13/28
ABB GroupApril 1, 2011 | Slide 14
Non-sparking motors (IEC 60079-15:2005and EN 60079-15:2005)
Increased safety motors (IEC 60079-7:2006 and EN 60079-7:2007)
Special measures shall be applied if the sum
of risk factors is greater than 5
Special measures shall be applied if the sum
of risk factors is greater than 6
Rotor risk assessment
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
14/28
ABB GroupApril 1, 2011 | Slide 15
Tests to verify that thedesigns are non-sparking
per IEC 60079 standards
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
15/28
ABB GroupApril 1, 2011 | Slide 16
Stator testSinusoidal voltage test
Sinusoidal voltage test continuousoperation
Insulation systems and connectioncables shall be tested in an explosivegas mixture comprised of (21 5) %hydrogen-in-air or (7,8 1) % ethylene-in-air, v/v
U = A sinusoidal voltage of 1,5 timesthe rated r.m.s. line voltage for 3 min
The maximum rate of voltage rise shallbe 0,5 kV/s
In this test will be tested insulationbetween
Phase and earth
Phase and other phases
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
16/28
ABB GroupApril 1, 2011 | Slide 17
Stator testVoltage impulses test
Voltage impulses test transient conditions
Insulation systems and connection cables
shall be tested in an explosive gas mixture
comprised of (21 5) % hydrogen-in-air or
(7,8 1) % ethylene-in-air, v/v
U = 10 voltage impulses of three times peak
phase voltage with
a tolerance of 3 %
A voltage rise time between 0,2 s and 0,5
s
A time to half value which is at least 20 s
but normally not exceeding 30 s
Electrical connection same as a sinusoidal
voltage test
In this test will be tested insulation between
Phase and earth
Phase and other phases
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
17/28
ABB GroupApril 1, 2011 | Slide 18
Rotor test
Aging
The rotor cage shall be subject to an
ageing process comprising a minimumof five locked rotor tests
The maximum temperature of the cage
shall cycle between the maximum
design temperature and less than 70C
The applied voltage shall be not less
than 50 % of the rated voltage
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
18/28
ABB GroupApril 1, 2011 | Slide 19
Rotor test
Tests
The same gas mixtures as for stator testing
Motors shall be subjected to 10 direct-on-line uncoupled
starts or 10 locked rotor tests. These tests shall have a
duration of at least 1 s
No explosion shall occur
During the tests, the terminal voltage shall not fall below 90
% of the rated voltage. The concentration of hydrogen or
ethylene shall be confirmed after each test
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
19/28
ABB GroupApril 1, 2011 | Slide 20
Scenarios to users andtheir pros and cons
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
20/28
ABB GroupApril 1, 2011 | Slide 21
Three scenarios for end users
1. To perform Risk Assessment for each case together with
Manufacturer and keep fingers crossed, or
2. To have a Provision for Pre-Purging if Risk factors limitsare exceeded, or
3. To require manufacturers to carry out gas testing and
provide certification based on that
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
21/28
ABB GroupApril 1, 2011 | Slide 22
Scenario 1To perform risk assessment for each case
Easiest and most attractive procedure from Manufacturer, butin practice its brings couple of issues
In most of the cases, the risk factor limits are exceeded, and
special measures are needed.
Lack of information flow
Effective co-operation is needed between End User andManufacturer during the motor design phase (through
mech.vendor and contractor) All information is not typically available at that time
Changing specification
Risk assessment results might change many times during
tendering Varying conditions during the machines life time
Certificate will have limitation of use per risk assessmentresults
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
22/28
ABB GroupApril 1, 2011 | Slide 23
Scenario 2Provision for Pre-Purging when Risk Factor Limits Exceeded
Another easy and economical solution formanufacturers
Manufacturer provides flanges and End User / Operator
takes the responsibility to decide to use them or not
Safety engineers typically require purging if the risks areindicated
If pre-purging is selected by end user
Does NOT protect against stator partial discharges,which can occur all the time. Thats the reason why IEC60079-7:2006 requires stator testing for all motorsabove 1kV
10 to 60min delay in the start Additional investments to purge control device, piping
and air compressor
Additional cost for operator to run air compressor
Overall reliability is reduced due to additionalcomponents
S
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
23/28
ABB GroupApril 1, 2011 | Slide 24
Scenario 3Gas testing and Certification
To required that Gas testing is carried out for Rotor &
Stator is probably the best way for End Users &
Operators
No ones responsibility on end user of motor safety
To get confirmation that the design is non-sparking per
international standards
Not to have any limitations of the use of a need to review
risk assessment if factors are changing e.g. starting
frequency or maintenance strategy
Longer life-time for stator insulation due to no surfacedischarges
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
24/28
ABB GroupApril 1, 2011 | Slide 25
ABB approach
Th i d t t f d f t f
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
25/28
ABB GroupApril 1, 2011 | Slide 26
The gas test covers
LV Motors: M3_P motors produced in Vaasa(rotor test)
Induction Machines: HXR, AMA, AMI, M3produced in Helsinki or Shanghai (stator &rotor test)
Synchronous Machines: AMG and AMZproduced in Helsinki (stator test)
Results of the test
All rotor test passed (LV & HV)
Stator test passed (HV)
13.2 kV with IIC gases
15 kV with IIA and IIB gases
Other Ex nA motors which are not coveredby the type testing are equipped with aprovision for pre-start purging
Purge control units are always available asan option
The required gas tests are performed for most ofHV motors
B fit f t t d t f O t / E d U
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
26/28
ABB GroupApril 1, 2011 | Slide 27
Benefits of gas tested motor for Operators / End Users
Streamlining the risk assessment process
(not need of risk factor calculations)
Re-inforce the insulation system increase the
time life of products
The alternative to testing and certification
involves equipping the motor with provision
for pre-purging
Investment in a higher capacity air
compressor, piping, and a purge control
unit
Requires an additional operation
purging every time the motor is started
Benefits of gas tested motor for Operators / End Users
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
27/28
ABB GroupApril 1, 2011 | Slide 28
Benefits of the ABB approach thereforeinclude reduced
Initial capital expenditure
Lower operating costs
Faster starting
Higher reliability is improved as no
additional components are required
Most importantly, ABBs certified motorsoffer proven safety, as testing representsthe only way to verify that equipment is
really safeDanger is often marked with black and
yellow.Thats why our machines are blue!
Benefits of gas tested motor for Operators / End Users
7/24/2019 Ex NA and Ex e Motore Risk Assessment_RevC
28/28