+ All Categories
Home > Documents > Exam Marking Schedule (1)

Exam Marking Schedule (1)

Date post: 17-Aug-2015
Category:
Upload: gunugantiadithya
View: 249 times
Download: 7 times
Share this document with a friend
Description:
exam
Popular Tags:
13
Faculty of Technology and Built Environment Department of Construction BACHELOR OF CONSTRUCTION PROGRAMME 2014 EXAMINATION SUBJECT: CONSTRUCTION MANAGEMENT 1 SHEET: 1 of 16 plus Question 1 A3 Programme and Question 3 (a) Graph paper DATE: DURATION: 2 Hours Assessment breakdown: This examination 30 Other 70 This examination has Four questions The total mark for this examination is 70 10 minutes reading time will be allowed before commencement of this examination. This is an open book examination. Answer ALL questions. Answer Question 2 (a-c) on the chart provided and Question 3 (a) on the blank graph paper provided. Non programmable electronic calculators are permitted. The following texts are permitted: Any Start each question on a new page and write on one side of the paper only. Upon completion of this examination, ensure that on the front page of your answer book you have ticked the questions that you have completed, and also recorded your student ID number, subject and subject code. Before handing in your script, ensure that your student ID number is on the top of any loose pages, and that all pages are attached and in the correct order. MARKING SCHEDULE COURSE REPORT
Transcript

Faculty of Technology and Built Environment Department of Construction BACHELOR OF CONSTRUCTION PROGRAMME 2014EXAMI NATI ON SUBJECT: CONSTRUCTION MANAGEMENT 1 SHEET: 1 of 16 plus Question 1 A3 Programme and Question 3 (a) Graph paper DATE: DURATION:2 Hours Assessment breakdown:This examination 30Other 70 This examination has Four questions The total mark for this examination is 70 10minutesreadingtimewillbeallowedbeforecommencementofthis examination. This is an open book examination. Answer ALL questions.Answer Question 2 (a-c) on the chart provided and Question 3 (a) on the blank graph paper provided. Non programmable electronic calculators are permitted. The following texts are permitted: Any Start each question on a new page and write on one side of the paper only. Upon completion of this examination, ensure that on the front page of your answer bookyouhavetickedthequestionsthatyouhavecompleted,andalsorecorded your student ID number, subject and subject code. Before handing in your script, ensure that your student ID number is on the top of any loose pages, and that all pages are attached and in the correct order. MARKI NGSCHEDULE COURSEREPORT Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 2 of 13 Course Report (delete as appropriate) General Overall students have Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 3 of 13 QUESTION 1(Total 15 marks) Scenario Youhavebeenaskedbyyourconstructionmanagertowritea projectreportexplainingtheintendedactionyouintendto implement to resolve some programme difficulties. The client requires the project complete at the original time and as thisclientisextremelyimportanttoyourcompany,yourCMhas agreed to fully investigate the possibilities. Take into consideration the following: i.AlltasksshownontheattachedA3programmeareon programme up to 30th June. ii.After30thJune,asignificantareaofunsuitableground conditions was encountered. iii.Thiswillresultinthefollowingincreasesintaskdurations (e.g.costswillbereimbursedbuttheoverallcontracttime must stay as the original). Task 2.25 days Task 2.33 days Task 2.42 days Task 2.61 day Task 4.25 days Task 5.24 days Task 5.13 days Note the following constraints i.Due to complicated details, 2.4 can only overlap 2.3 by one day. ii.AccessisnotavailableonSaturday5th,12thJulyand 2nd August. (a)Quantify what impact each extension above has on the critical path and suggest a suitable action.Acceptable actions include: i.overlap tasks, ii.introduce another team,iii.use contingency,iv.use float, v.work available Saturdays and any other efficiencies deemed appropriate.Refer to tasks by their WBS code and the duration in working days.(15 marks) PART A Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 4 of 13 Answers: (a) Sample overlap solution, there will be solutions involving, using Contingency, using Saturdays and any other efficencies. Status date 30/6/14 TaskStatusProblemSolution Task 2.2 5 days This is on critical path and if left un resolved would result in 5 days overall delay. As this task will now finish on the 4 July, to minimise damage to critical path overlap2.3 to start before completion of 2.2. Start 2.3 on Weds 2 July, this will minimise delay to two days Task 2.3 3 days This is on critical path and if left un resolved would result in 3 days overall delay With 2.3 now starting on 2 July but being extended by 3 days the new completion date for 2.3 is Weds 9 July. Task 2.4 2 days This is on critical path and if left un resolved would result in 2days overall delay Task 2.4 is able to start on 8 July and will finish on 16 Wed JulyTask 2.6 1 day This is on critical path and if left un resolved would result in 1days overall delay Task 2.6 is now 4 days long, by overlapping with 2.4 and starting on 15July it will be complete on 18 July. By adding up all delays to date we have 11 days which should take us to 14 July. We have finished 2.6 on 18, we have recovered 7 days but still need to recover another 4 days between now and completion .Solution overlap tasks 3.1,3.2,3.3,3.4 by one day each will recover the 4 days to bring complete back to its original date. Task 4.2 5 days This is non-critical so we can absorb this extra time of 5 days from the available float Task 5.2 4 days This is non-critical so we can absorb this extra time of 4 days from the available float Task 5.13 days This is non critical so we can absorb this extra time of 3 days from the available float Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 5 of 13 Examiners Comment (delete as appropriate) QUESTION 2 (Total 15 marks) Answersections(a-c)ofthisquestionontheprovided answer sheet. From programme data in Figure 2: (a)Complete the network diagram to show node relationships.(5 marks) (b)Completethepassforwardoperationfromstarttofinishto confirm duration.(4 marks) (c)Completethepassbackwardsoperationfromfinishtostartto confirm any float.(4 marks) (d)If two or more links are converging into one node and there are two ormoreearlystartdates,whichfiguredoyouuseforthepass forward calculation.(1 mark) (e)Summarise the total duration of this project in days.(1 mark) Figure 2:Programme data Task NameDuration Predecessors 1Award contract0 days

2Site establishment5 days 1 3Bulk cut site to RL4 days 2 4Excavate Foundations2 day 3 5Box Reo Pour fdts8 days 4 6Lay header blocks and grout2 days 5 7Under slab services2days 6 8Backfill5 days 7 9Prep Slab2 days 7,8 10Pour slab1 day 9 11Erect timber frames5 days 10 12Erect roof trusses3 days 11 13Complete roof structure2 days 12 14Install roofing5 days 13 15 Exterior windows anddoors5 days 14 16Complete exterior cladding8 days 15 171st fix services5 days 14 18Interior Finishes12 14,16,17 19Fit off and hardware5 18 20Inspections and Remedials5 19 21Handover complete0 20 Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 6 of 13 Answers: Construction Management two Q12014 IDNetwork Template Answer2 Site Est 7 U/S servs 12 Trusses 17 1st FixSrs0 5 5 21 2 23 36 3 39 46 5 510 0 5 21 0 23 36 0 39 54 8 593 Bulk cut 8 Backfill 13 Roof Strt. 18 Int. finish5 4 9 23 5 28 39 2 41 59 12 715 0 9 23 0 28 39 0 41 59 0 711 Award 4 Exc.Fdts 9 Prep slab 14 Roofing 21 Handover0 0 0 9 2 11 28 2 30 41 5 46 81 0 810 0 0 9 0 11 28 0 30 41 0 46 81 0 815 Blockwork 10 Pour slab 15 Windows 19 Fit off11 8 19 30 1 31 46 5 51 71 5 76WBS Name 11 0 19 30 0 31 46 0 51 71 0 76ES Duration EFLS Float LFNode template 6 U/S Servs 11 Erect walls 16 Cladding 20 Inspect19 2 21 31 5 36 51 8 59 76 5 8119 0 21 31 0 36 51 0 59 76 0 81Box Reo Headr Blk Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 7 of 13Examiners Comment (delete as appropriate) Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 8 of 13 PART B QUESTION 3Quality Systems and Commissioning(Total 20 marks) Analyse the two case studies below using the framework of Quality Systems. (a)Describe one event, activity or decision that falls under each of the headings of: i) TQM ii) Quality Assuranceiii) Quality Controliv) Third Party Inspection. You can select from either of the case studies or just one. (1 mark) (1 mark) (1 mark) (1 mark) (b)Justify whyeach of the events, activities or decisions fit under the chosen Quality Systems headings.(8 marks) (c)Suggestwhatcontributioneachevent,activityordecisionhas madetotheendresult.Illustratethiswithanexampleofthe impact on a building service for each heading. You can also explain where the lack of an event under a particular heading had a negative impact on the final result.(8 marks) Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 9 of 13 Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 10 of 13 Answers: 1 mark for each identification 2 marks for each justification1 mark for contribution with a half a mark for a relevant service example e.g. Possible answers i) a)ThelackofuseofacommissioningmanagementorganisationinProjectB shows a lack of TQM.b)TQM indicates a desire for continual improvement requires a commitment to commissioningatthe outset.A commissioning management organisation would have a focus on achieving quality from the outset of the project and illustrates a commitment at the highest level of the organisation. Failure to employ one shows a lack of interest in improving. c)Theabsenceprobablymeantalackofaclearcommissioningplanforthe airconditioningsystemwhichmayhavenotmaintainedcomfortableconditions early in its occupancy ii) a)TheafterhandovermodificationsinProjectAindicatealackofQuality Control. b) Quality Control activities include Self Checking by the installers rather than byathirdparty.Theneedformodificationslaterintheprojectshowthatthis Shelf checking had not been done. c)Ifthesehadbeencheckedbytheinstallersitcouldhaveavoided the need for themodificationsafterhandover.Thiscouldeasilyhavemeantthatfanswere not operating to the right level before air balancing was started. iii) a) Quality Assurance processes were in place in project A.b)ThisisdemonstratedbythefactthattheCommissioningEngineeridentified modificationsduringtheinstallation.Thesecheckswouldhavebeenpartofa Quality Assurance process.c)Itdidnothelpbecausethemodificationswereignored.Thiscouldhave identifiedmodificationstolinksbetweentheairconditioningsystemandfire protection system. Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 11 of 13iv) a) Third party inspection was clearly present in Project B b)Thecheckingbythecommissioningengineersidentifiedsnagsthatneeded fixing.Commissioningengineerscheckingotherpeoplesworkisthirdparty inspection.c))Thiswouldhavecontributedtothedelayofhandoverasworkneededtobe corrected. Faults with the building controls were identified. Examiners CommentGenerallyquitewellanswered.Thereweresomeexcellentresponsesconnecting principles to actual events in the case studies. Somestudentsfailedtomakeanyconnectiontothecasestudiesatallsimplyre- statingcontentfromnotes.Asthiswasanopenbookexam,thisapproachwasnot showing the depth of understanding required and generally failed to earn half marks. There were few answers that really demonstrated complete understanding by failing togiveanexampleofanactualserviceinsectionc).Annumberwerebroad referencestoHVACbutamoredetailedaspectconsideringforexample,cooling equipment or fan capacitywas needed QUESTION 4Building Warrants of Fitness, O&M manuals andExisting Buildings (Total 20 marks) (a)OutlinethedifferencebetweenBuildingWarrantsofFitnessand O& M manuals by describing: i)Their key functionii)Who creates them iii)Who uses them.(6 marks) (b)Consider that Building A in the assignment is to have another floor addedtoit10yearsaftercompletion.Referringtofivedifferent buildingservices,describeadifferentchallengethattheyprovide inextendingthisbuildingandspecificsectionsofdocumentsthat might need to be consulted to help overcome the challenge. (14 marks) Answers: a)i)O&Mdocumentthebuildingitsservicesanditscommissioningstate at handover. BWoF document the acceptable ongoing maintenance of the building in its life. (2 marks) ii) O&Ms are created by the services subcontractor and main contractor. BWoF are initially completed by the same but then updated by an IQP(2 marks) iii)Thebuildingmaintenance operative will use O&Ms to maintain the buildingorconsultantsto involved in upgrading or subdividing. BWOf areusedbytheownertodemonstratecompliancewiththeCodetothe public. (2 marks) b)2 marks for each realistic challenge applied toa relevant service in the building Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 12 of 13e.g.keepingtheexistingbuildingoperatingwhilstaddingon. SpecificallyrelocatingtheoutdoorcondensingunitsontheroofofA. Manufacturersinformationtoguidewhethertheadditionalheightcan be handles by existing equipment. (2 marks) Or Routingnewelectricalcablestothenewfloor.SpecificallyAsBuilt Drawingsshowinglocationsofexistingdistributionboardsandmain switchboards equipment. Examiners Comment (delete as appropriate) Semester 1, 2014 Marking ScheduleCONS 7308 Construction Management 2Page 13 of 13 Construction Management two Q2 (a-c)2014 IDNetwork Template2 Site Est 7 U/S servs 12 Trusses 17 1st FixSrs5 2 3 503 Bulk cut 8 Backfill 13 Roof Strt. 18 Int. finish4 5 2 121 Award 4 Exc.Fdts 9 Prep slab 14 Roofing 21 Handover0 2 2 5 05 Box Reo 10 Pour slab 15 Windows 19 Fit off8 1 5 5WBS NameES Duration EFLS Float LFNode template 6 Header Blk 11 Erect walls 16 Cladding 20 Inspect2 5 8 5


Recommended