+ All Categories
Home > Documents > Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at...

Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at...

Date post: 19-Mar-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
13
Transcript
Page 1: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged
Page 2: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged
Page 3: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged

Example 1 INSPECTOR’S DAILY REPORT EXAMPLES

Page 4: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged
Page 5: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged

Example 2

Page 6: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged
Page 7: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged

Example 3

Page 8: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged
Page 9: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged

Example 4

Page 10: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged
Page 11: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged

Example 5

Page 12: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged
Page 13: Example 1 - NCDOT...tickets). During the pour, depth and cwer checks were made witha wire probe at 10th point locations. C.cwer was over 25" at all locations. Depth readings ranged

Recommended