+ All Categories
Home > Documents > Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100%...

Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100%...

Date post: 03-Oct-2019
Category:
Upload: others
View: 9 times
Download: 0 times
Share this document with a friend
94
1 Example Application 11 Multistage Tunnel Excavation and Support
Transcript
Page 1: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

1

Example Application 11

Multistage Tunnel Excavation

and Support

Page 2: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

2

Multi-Stage Tunnel Construction

Page 3: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

3

Multistage Tunnel Conditions

Rock Mass Properties – Mohr-Coulomb Model

unit weight 27,000 N/m3

bulk modulus 0.555 GPa

shear modulus 0.417 GPa

cohesion 10,000 Pa

friction angle 33o

tensile strength 1000 Pa

In-Situ Stress State

Ko = 0.5

Page 4: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

4

Rockbolt Properties

cross-sectional area 5.0x10-4 m2

spacing 1.0 m

Young’s modulus 2.05 GPa

tensile yield strength 0.5 MN

grout shear stiffness 15 GN/m/m

grout shear strength 800,000 N/m

Page 5: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

5

Shotcrete Liner Properties

Young’s modulus 5.28 GPa

Poisson’s ratio 0.2

thickness 0.3 m

moment of inertia 2.25x10-3 m4

compressive strength 10.0 MPa

tensile strength 1.0 MPa

Page 6: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

6

Stress Relaxation due to Tunnel Advancement

Page 7: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

7

Tunnel Construction Sequence

Side Excavation (I & II) Top-heading Excavation (III) Bench Excavation (IV)

--------------------------------------------------------------------------------------------------------------------------------------------

Percent

Relaxation 50% 75% 100% 50% 75% 100% 50% 75% 100%

-------------------------------------------------------------------------------------------------------------------------------------------- Step a b c a b c a b c

Excavation Stages Construction Steps

Stage I: right-side excavation Step a: initial excavation

Stage II: left-side excavation Step b: installation of rockbolt support

Stage III: top-heading excavation Step c: installation of a shotcrete lining

Stage IV: bench excavation

Rockbolts are installed at a distance to the face corresponding to 50% relaxation of tunnel loads, and

shotcrete lining is installed at a distance to the face corresponding to 75% relaxation of tunnel loads.

Page 8: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

8

Modeling Procedure

Step 1 Generate model grid and assign material models and properties and

boundary conditions to represent the in-situ conditions.

Step 2 Determine the initial in-situ stress state of the ground prior to construction.

Step 3 Perform an unsupported tunnel excavaation calculation to develop a ground

reaction curve for the given conditions.

Step 4a Excavate the right-side excavation with rockbolts installed after 50%

relaxation of the tunnel load (construction step a).

Step 4b Install the shotcrete support after 75% relaxation of the tunnel load

(construction step b).

Step 4c Relax the tunnel load 100% for complete excavation of the right-side

(construction step c).

Step 5a-c Repeat construction steps a, b and c for excavation of the left side.

Step 6a-c Repeat construction steps a, b and c for excavation of the top heading.

Step 7a-c Repeat construction steps a, b and c for excavation of the bench.

Page 9: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

9

Page 10: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

10

Step 1-1 Draw model boundary with [Box] edge option in [Geometry Builder]

Page 11: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

11

Step 1-2 Import TUNNEL.DXF, a sketch of tunnel excavation boundaries.

Page 12: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

12

Step 1-3 Add construction lines to divide model into quad blocks.

Page 13: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

13

Step 1-4 Add a box around tunnel to facilitate creation of quad blocks and control zoning.

Page 14: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

14

Step 1-5 Add additional construction lines to divide model into quad blocks

Page 15: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

15

Step 1-6 Use [Cleanup] stage to clean up bad vertices and edges

Page 16: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

16

Step 1-7 Check that model is divided into 4-sided blocks in [Blocks] stage. Extract 10 quad blocks for building FLAC grid by pressing [Build]. Press

[OK] to exit the [Geometry builder].

Page 17: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

17

Step 1-8 Enter the [Edit] tool. Select [Transform region] and right-click on the model. Select [Add and merge mirrored copy left] from the menu.

Page 18: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

18

Step 1-9 The full tunnel geometry is created, as shown.

Page 19: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

19

Step 1-10 Select the [Boundary] stage and assign standard boundary conditions using [Automatic boundary cond.] mode.

Page 20: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

20

Step 1-11 Use manual zoning to create a fine mesh density in the bench excavation region

Page 21: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

21

Step 1-12 Use density multiplier to create a uniform zoning around the tunnel

Page 22: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

22

Step 1-13 Use the density multiplier to extend the uniform zoning to the model boundaries.

Page 23: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

23

Step 1-14 Use [Adjust ratios] to gradually increase zone size away from the tunnel.

Page 24: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

24

Step 1-15 Define regions for multi-stage excavation using [Define regions] mode in [Materials] stage

Page 25: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

25

Step 1-16 In the [Assign] mode, click on [Database] and load in the MSTUNNEL.GMT material database

Page 26: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

26

Step 1-17 Assign materials to regions in the [Assign] mode

Page 27: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

27

Step 1-18 Click [OK] to exit the [Edit] tool, click [Execute] to create commands and send to FLAC, and click [Save] to save the model state (ms1.sav)

Page 28: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

28

Syy = -1.589 MPa Step 2-1 Assign initial stress state Ko = 0.5

Page 29: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

29

Step 2-2 Initialize stress state using the [Insitu]/[Initial] tool

Page 30: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

30

Step 2-3 Assign gravity with the [Settings]/[Gravity] tool.

Page 31: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

31

Step 2-4 Check that model is at equilibrium state using the [Run]/[Solve] tool.

Page 32: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

32

Step 2-5 Save the state as ms2.sav.

Page 33: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

33

Step 3-1 Excavate tunnel for ground reaction curve calculation in the [Material]/[Assign] tool by using the [Region] range to set null materials.

Page 34: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

34

Step 3-2 Initialize displacements to zero in the [In Situ]/[Initial] tool by pressing the Clear? [Displmt & velocity] button.

Page 35: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

35

Step 3-3 Create a ground reaction table. FISH function closure.fis is used to calculate tunnel closure. Closure, closure, is defined here by the sum

of the vertical displacement at the tunnel crown (at i=39,j=53) plus the invert (at i=39, j=21). Horizontal closure, closure_side, is also monitored as

horizontal displacement at the left side (at i=21,j=37) plus the right side (at i=57, j=37).

Page 36: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

36

Step 3-4 The FISH variable, closure, is recorded as a history by selecting [Fish>History] in the [Utility]/[History] tool.

Page 37: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

37

Step 3-5 The ground reaction table is generated using the [In Situ/[Apply] tool. Select [Relax] and [Long] and drag the mouse along the tunnel

boundary. Then, press [Assign] to open the Apply relax dialog. The boundary tractions will be reduced in 10 increments until reaching an end

factor of 0.2 (i.e., 80% relaxation). The vertical closure versus tunnel relaxation is recorded to table 1 by checking the [Generate Ground Reaction

Table] box, and entering Table No. 1. The horizontal closure versus tunnel relaxation is recorded to table 2.

Page 38: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

38

Step 3-6 Calculate the effect of relaxation of the tractions around the tunnel using the [Run\/[Solve] tool.

Page 39: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

39

Step 3-7 Plot the table of relaxation factor vs vertical closure. (Note that relaxation factor is the ratio of current tunnel traction to the initial

tunnel traction.) Rockbolts will be installed at tunnel advance corresponding to 1.2 cm vertical closure (50% relaxation), and liner will be installed

at tunnel advance corresponding to 2.8 cm vertical closure (75% relaxation). Save the state as ms3.sav.

Page 40: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

40

Step 4-1 Create a new branch starting from ms2.sav and perform a side excavation by nulling mstunnel:right side region in [Material]/[Assign] tool.

Page 41: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

41

Step 4-2 Initialize the displacements and velocities in the [In Situ]/[Initial] tool.

Page 42: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

42

Step 4-3 Return to the [In Situ]\[Apply] tool and select [Relax] and [Long]. Drag the mouse around the tunnel side boundary. Press [Assign] to

open the Apply relax dialog. Relax the tractions in 5 increments and set the end factor to 0.5 (50% relaxation).

Page 43: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

43

Step 4-4 Record a stress history near the tunnel springline in the [Utility]/[History] tool.

Page 44: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

44

Step 4-5 Select [Run]/[Solve] to relax the tractions around the side tunnel by 50%.

Page 45: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

45

Step 4-6 Save the state as ms4.sav. The syy stress history plot, created in the [Plot]/[History] tool, indicates a gradual change in the stress

resulting from the excavation.

Page 46: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

46

Step 4-7 Import the sketch of the rockbolt pattern (rockbolts.dxf) in the [Build]/[Sketch] tool.

Page 47: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

47

Step 4-8 Using the rockbolt.dxf sketch as a background image, install nine rockbolts (with 5 segments each) around the right-side excavation using

the [Structure]/[Rockbolt] tool. (Five segments are sufficient to place at least one rockbolt node within every zone along the bolt length.) Position

rockbolts to coincide with the sketch of rockbolt pattern. (The rockbolt pattern sketch is made visible by right-clicking to open the drop-down

menu and selecting [Show sketch].)

Page 48: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

48

Step 4-9 Assign rockbolt properties in [Structure]/[SEProp] tool. (Note that a high value for element compressive yield strength is set to prevent

compressive failure during initial transient load change.)

Page 49: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

49

Fig. 4-10 Return to the [In Situ]/[Apply] tool, press [Relax] and drag the mouse along the side boundary again. Set the number of relaxation

increments to 5 and set end factor to 0.5. The tractions are relaxed an additional 50%.

Page 50: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

50

Step 4-11 Select [Run]/[Solve] to calculate the equilibrium state with rockbolt support for the side excavation. The state is saved as ms5.sav.

Page 51: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

51

Step 4-12 Install liner around side excavation in [Structure]/[Liner] tool by dragging the mouse around the excavation boundary. Liner nodes are

attached directly to the grid

Page 52: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

52

Step 4-13 Assign liner properties in [Structure]/[SEProp] tool

Page 53: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

53

Step 4-14 Return to the [In Situ]/[Apply] tool and relax tractions 100% (end factor = 0.0) in 5 increments.

Page 54: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

54

Step 4-15 Use [Run]/[Solve] and solve to equilibrium. Save the state as ms6.sav.

Page 55: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

55

Step 4-16 The moment-thrust diagram for the liner is created with the [Plot]/[Mom-P] tool.

Page 56: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

56

Step 5-1 Excavate the left side using the [Material]/[Assign] tool.

Page 57: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

57

Step 5-2 Return to the [In Situ]/[Apply] tool and select [Relax]. Press [Long] path and drag the mouse around the tunnel side boundary. Press

[Assign] to open the Apply relax dialog. Relax the tractions in 5 increments and set the end factor to 0.5 (50% relaxation).

Page 58: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

58

Step 5-3 Record a stress history near the left-side tunnel springline in the [Utility]/[History] tool.

Page 59: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

59

Step 5-4 Select [Run]/[Solve] to relax the tractions around the left-side tunnel by 50%.

Page 60: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

60

Step 5-5 Plot stress tensors and displacement vectors in the [Plot]/[Model] tool. Save the state as ms7.sav.

Page 61: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

61

Step 5-6 Using the rockbolt.dxf sketch, install nine rockbolts (with 5 segments each) around the left-side excavation in the [Structure]/[Rockbolt]

tool.

Page 62: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

62

Step 5-7 Return to the [In Situ]/[Apply] tool, press [Relax] and [Long] path and drag the mouse along the side boundary. Press [Assign] to open

the Apply relax dialog. Relax the tractions in 5 increments and set the end factor to 0.5 (75% relaxation).

Page 63: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

63

Step 5-8 Select [Run]/[Solve] to calculate the equilibrium state with the rockbolt support.

Page 64: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

64

Step 5-9 Save the state as ms8.sav.

Page 65: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

65

Step 5-10 Install liner around the left-side excavation in [Structure]/[Liner] tool by dragging the mouse around the excavation boundary. Liner

nodes are attached directly to the grid.

Page 66: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

66

Step 5-11 Return to the [In Situ]/[Apply] tool and relax tractions 100% (end factor = 0.0) in 5 increments.

Page 67: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

67

Step 5-12 Use [Run]/[Solve] and calculate the equilibrium state.

Page 68: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

68

Step 5-13 Save the state as ms9.sav.

Page 69: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

69

Step 5-14 Check the moment-thrust diagram.

Page 70: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

70

Step 6-1 Perform the top excavation by nulling the top excavation region in the [Material]/[Assign] tool .

Page 71: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

71

Step 6-2 Also, delete liner segments between the sides and top excavations in the [Structure]/[Segments] tool.

Page 72: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

72

Step 6-3 Tractions are reduced by 50% in 5 increments along the top excavation boundary in the [In Situ]/[Apply] tool.

Page 73: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

73

Step 6-4 Calculate equilibrium using the [Run]/[Solve] tool.

Page 74: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

74

Step 6-5 Save the state as ms10.sav.

Page 75: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

75

Step 6-6 Using the rockbolt.dxf sketch as a background image, install 8 rockbolts (with 5 segments each) around the top excavation in the

[Structure]/[Rockbolt] tool.

Page 76: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

76

Step 6-7 Tractions are reduced by an additional 50% in 5 increments along the top excavation boundary in the [In Situ]/[Apply] tool.

Page 77: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

77

Step 6-8 Calculate equilibrium with tractions relaxed 75% using the [Run]/[Solve] tool.

Page 78: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

78

Step 6-9 Save this state as ms11.sav.

Page 79: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

79

Step 6-10 Install liner around top excavation in [Structure]/[Liner] tool

Page 80: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

80

Step 6-11 Tractions are reduced 100% (rstop = 0.0) in 5 increments along the top excavation boundary in the [In Situ]/[Apply] tool.

Page 81: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

81

Step 6-12 Calculate equilibrium with tractions relaxed 100% using the [Run]/[Solve] tool.

Page 82: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

82

Step 6-13 Save this state as ms12.sav.

Page 83: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

83

Step 6-14 Check the moment-thrust diagram.

Page 84: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

84

Step 7-1 Excavate the bench using the [Material]/[Assign] tool.

Page 85: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

85

Step 7-2 Delete liner segments between the bench and side excavation in the [Structure]/[Segments] tool.

Page 86: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

86

Step 7-3 Relax tractions along bench excavation boundary by 75% using the [In Situ]/[Apply] tool.

Page 87: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

87

Step 7-4 Calculate equilibrium with tractions relaxed 75% using the [Run]/[Solve] tool.

Page 88: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

88

Step 7-5 Save this state as ms13.sav

Page 89: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

89

Step 7-6 Install liner along bench excavation boundary in [Structure]/[Liner] tool.

Page 90: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

90

Step 7-7 Relax tractions along bench boundary 100% in the [In Situ]/[Apply] tool.

Page 91: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

91

Step 7-8 Solve to equilibrium with tractions relaxed 100% along bench excavation.

Page 92: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

92

Step 7-9 Save this state as ms14.sav.

Page 93: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

93

Step 7-10 Check the moment-thrust diagram.

Page 94: Example Application 11 Multistage Tunnel Excavation and ... · Step 4c Relax the tunnel load 100% for complete excavation of the right-side (construction step c). Step 5a-c Repeat

94

Step 7-11 Surface settlement after completion of Step 7 using SETTLE.FIS (Gridpoint I,j values are adjusted to correspond to values along the top

of grid.) . Save the state as ms15.sav.


Recommended