March 29, 2000 March 29, 2000 SAP R/3 upgrades SAP R/3 upgrades  A Methodology overview  A Methodology overview
Transcript
Page 1: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 1/21

March 29, 2000March 29, 2000

SAP R/3

upgrades

SAP R/3

upgrades A Methodology overview A Methodology overview

Page 2: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 2/21

Overview

Why Upgrade ? What¶s Effected ?

What Can Be Reused ?

What Will Be New or Changed ?

What Does The Project Include ?

What¶s New With Upgrading to 4.x?

Lessons Learned

Page 3: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 3/21

Why Upgrade ?

Provide new capabilities Fix bugs

Eliminate customization

Stay current (Address end of life issues)

Business process extension

 ± mySAP.com

 ± APO

 ± CRM

 ± BW

To upgrade other components

 ± Database

 ± Operating system

Corporate structure changes

 ± Merger, acquisition, divestiture

Page 4: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 4/21

What¶s Effected ?

Database servers Application servers and workstation GUIs

Processes

Data

Interfaces

Customization

Reports

Training and documentation

People - users, IS, and project team

Page 5: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 5/21

What Can Be Reused ?

Processes that do not change betweenversions

 ± Related documentation and training materials

Technical design/code potentially not effected

by the upgrade

 ± Interfaces ± Customizations

 ± Reports

 ± Layout Sets

SAP terminology, knowledge, skills

 ± Project team ± Process knowledge of the end user community

Page 6: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 6/21

What Will be New or Changed?

New or changed processes, documentation, &training

Interfaces, reports, etc. impacted by changes in

the target SAP table structures, coding syntax,

and/or different screen flow

New customized functionality ± To supplement new, changed, or existing

processes

Customization that can be removed

 ± User exits

 ± Custom ABAPs

Page 7: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 7/21

What Does The Project Include?

SYSTEM DESIGN 

TEST & TRAINING

GO-LIVE & SUPPORT 

PROJECT PREPARATION 

SYSTEM CONSTRUCTION 

Page 8: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 8/21

What Does The Project Include?

Project Preparation ± Build the business case and justification

 ± Define the scope

 ± Prepare the project work plan

 ± Review user requirements

What outstanding system change requests can be met by

the upgrade? What new functionality do we want from the upgrade?

 ± Review organizational change impact

 ± Develop other project management deliverables

Issue resolution plan

Risk analysis

Project standards

Software configuration management plan

Page 9: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 9/21

What Does The Project Include?

System Design ± Review/Setup environments

Sandbox

Development

QA

Others

 ± Process design and regression

As-Is flows

To-Be flows

Results in new and modified flows as needed

Page 10: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 10/21

What Does The Project Include?

System Design (continued) ± Data design and regression

R/2 - R/3 ABAPs

Source to target table changes

 ± Customization design and regression

Resulting in customization specifications for functionality

gaps between the current and new version

 ± Interface design and regression

Resulting in interface design for new and modified

interfaces

 ± Report design and regression

Resulting in report design for new and modified reports

 ± Establish business scenarios

For new and modified business flows that will need to betested

Page 11: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 11/21

What Does The Project Include?

System Construction ± Develop upgrade execution plan

 ± Develop training plan and training materials

For new and changed functionality

 ± Develop system test plan

Individual business process tests

Fixes and rework End-to-end test

Produce records

Page 12: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 12/21

Page 13: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 13/21

What Does The Project Include?

Test & Training ± Conduct system test - iterate with conversion

Test the actual upgrade

Individual business process tests

Test ABAP customized code and changed SAP code

End-to-end test

Re-testing for time estimates and documentation

verification

Produce records

 ± Plan detailed organizational changes

For new or modified functionality

 ± Conduct user training

For new and modified functionality

Page 14: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 14/21

What Does The Project Include?

Test & Training (Continued) ± Conduct additional testing

Performance testing/tuning

User acceptance testing

 ± Develop detailed cut-over plans

How long will it take?

What is the landscape path?

Who is responsible for what?

Page 15: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 15/21

What Does The Project Include?

Go-Live & Support ± Finalize cut-over plan

 ± Develop ³Go Live´ contingency plan

 ± Develop system support plan

 ± Install upgraded system

Use records produced during construction/test iteration

 ± Implement organizational changes ± Go Live

 ± Support system

Page 16: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 16/21

Upgrade Components

Operating System/DatabaseOperating System/Database

 Authorizations Authorizations

 Data Dictionary Objects Data Dictionary Objects

 Modifications/Enhancements Modifications/Enhancements

ConfigurationConfiguration

 Interfaces/EDI/Conversions Interfaces/EDI/Conversions

 Reports/Layout Sets Reports/Layout Sets

 Business Processes Business Processes

 Basis Basis

 Development  Development 

 Preparation  Preparation Post   Post--Processing  Processing UpgradeUpgrade

(R3up/R3Setup)(R3up/R3Setup)

Page 17: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 17/21

Upgrading to 4.x

R/3 Upgrade Assistant - Upgrade systemsremotely via a web browser 

PREPARE tool pre-loads data and helps

reduce upgrade time

Modification conflicts can be identified via

PREPARE - prior to actually upgrading

Page 18: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 18/21

Lessons Learned

The current functionality will still exist in theupgraded system

Make sure to look at:

 ± Configuration that may have changed during the

upgrade

 ± New configuration that needs to be adjusted to

fit the current process flows

Follow a structured methodology

Similar in many ways to a straight

implementation

Page 19: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 19/21

Page 20: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 20/21

Lessons Learned

Even if it doesn¶t appear to be affected, test tomake sure

Schedule MANY dry run test upgrades

Upgrade project is very linear - plan

accordingly and do not expect overlap

Pay attention to the version of everythinginvolved

 ± SAP

 ± Database

 ± Operating system

 ± Interfacing systems

Page 21: Example of Project Life Cycle for R-3 Migrations

8/8/2019 Example of Project Life Cycle for R-3 Migrations

http://slidepdf.com/reader/full/example-of-project-life-cycle-for-r-3-migrations 21/21

Lessons Learned

Complexity of the upgrade is directly related tohow well the systems have been maintained

Select team members carefully

 ± Similar to the original implementation, they

should have a strong understanding of the

business process in their area

 ± If not, some of the processes may be overlooked


Recommended