Experiment of 11.7GHz PE at AWA DL
2/27/2014
Charge/bunch q(nC)
Bunch length z (mm)
RF power P (MW)
Peak surface field Es (MV/m)
Maximum energy loss of the bunch Eloss (MeV)
42 2.3 207 60 860 2.3 422 86 11.4
Some Background information(i):
Some Background information(iii):
Some Background information(iv):
AWA DRIVE BEAM---19MeVWhere:
Structure
When:
Task* Description Responsible Due Note
1 KL1/2 readiness Liu 4/30
2 LLRF readiness Jing 4/30 Linac phase measurement
3 Structure readiness Jing 3/10 Re-cleaning and assembling
4 Installation readiness Scott 4/15 HW for installation
5 Safety readiness Manoel 3/30 Approval for 19MeV DL
6 Vacuum readiness Eric 4/30
7 Beamline readiness Liu 4/30 PS, magnets, actuators, remote control
8 Diagnostics readiness John 4/30 Cameras, cables, scope
9 Laser readiness John 4/30 16/32 bunch train
10 High charge Eric 4/15 New cathode fabrication and installation
11 simulation John 3/15 19MeV to DUT
Proposed starting date of experiment: 5/1
Execution before the next meeting in around a week
1. 19MeV beam simulation---John/Dan
2. Structure assembling---Jing
3. Cleaning the rf load --- Sergey
4. Installation layout--- Scott (cross, pumping, ict location…)
5. Pump and leak check of diagnostic beamline--- Eric