+ All Categories
Home > Documents > Explanatory Memorandum (Rev D)

Explanatory Memorandum (Rev D)

Date post: 13-Jan-2022
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
250
Application Reference: EN070001 Deadline 4 March 2015 Explanatory Memorandum (Rev D) The Yorkshire and Humber (CCS Cross Country Pipeline) Development Consent Order 3.2 D O C U M E N T
Transcript
Page 1: Explanatory Memorandum (Rev D)

Application Reference: EN070001

Deadline 4

March 2015

Explanatory Memorandum (Rev D)

The Yorkshire and Humber (CCS Cross Country

Pipeline) Development Consent Order

3.2 D

O C

U M

E N

T

Page 2: Explanatory Memorandum (Rev D)

Contents

Clause Name Page

1 Introduction to the Onshore and Offshore Schemes ........................................ 1

2 This Explanatory memorandum..................................................................... 3

3 Purpose of the order ................................................................................... 5

4 Ancillary matters ......................................................................................... 9

5 The draft Order......................................................................................... 13

6 Part II of the Order - Works Provisions ........................................................ 21

7 Part III of the Order - Acquisition and Possession of Land .............................. 38

8 Part IV of the Order - Miscellaneous and General .......................................... 54

9 Schedules ................................................................................................ 61

Appendix Name Page

Tracked change version of the Order against the DCO Model Provisions .......... 87

Page 3: Explanatory Memorandum (Rev D)

1

1 INTRODUCTION TO THE ONSHORE AND OFFSHORE SCHEMES

1.1 National Grid Carbon Limited (the “undertaker”) proposes

constructing and operating a carbon dioxide transportation and storage system to support the provision of carbon capture and storage (“CCS”) technology in the Yorkshire and Humber Region.

The project in its entirety, known as The Yorkshire and Humber CCS Transportation and Storage project (the “Project”), would comprise the construction of a Cross Country Pipeline and sub-sea pipeline for

transporting carbon dioxide captured from power projects in the region to a permanent geological storage site beneath the North Sea.

1.2 The Project includes both onshore and offshore elements which are subject to separate consenting regimes (the “Onshore Scheme” and the “Offshore Scheme”).

1.3 The onshore elements of the Project are collectively termed the Yorkshire and Humber Carbon Capture and Storage Cross Country Pipeline (shortened to the “Onshore Scheme”) and are proposed to

comprise the construction of a cross country pipeline and associated infrastructure including pipeline internal gauge (“PIG”) traps, a multi-junction, three block valves, a pumping station (collectively termed

“Above Ground Installations” or “AGIs”) and any necessary interconnecting local pipelines and associated works.

1.4 The Onshore Scheme requires a new buried high pressure cross

country pipeline of approximately 67km in length with an external diameter of up to 610mm for the transportation of carbon dioxide in liquid form to a location on the Holderness coast.

1.5 As the length of the proposed cross country pipeline comprised in the Onshore Scheme will exceed 16.093km it constitutes a nationally significant infrastructure project (“NSIP”) pursuant to the Planning

Act 2008. This requires an application to be made to the Secretary of State for a development consent order (“DCO”).

1.6 The cross country pipeline will have an external diameter of up to 610mm and will be sized to accommodate up to 17 million tonnes (mt) of carbon dioxide emissions per year. The multi-junction would

enable the connection of multiple pipelines from regional carbon dioxide emitters to the Onshore Scheme. At present one installation for the capture of carbon dioxide streams, the White Rose CCS

project adjacent to Drax Power Station at Selby, being promoted by Capture Power Limited, would require a pipeline connection into the cross country pipeline. An interconnecting pipeline between the White

Rose CCS project and the multi-junction will form part of the application for the Onshore Scheme.

Page 4: Explanatory Memorandum (Rev D)

2

1.7 PIG traps would be sited at the start and end of each pipeline to launch PIGs (these are required as part of the planned pipeline

inspection and maintenance programme). Following a site appraisal, a PIG trap site has been identified in the vicinity of the White Rose CCS project adjacent to the Drax Power Station, near Selby.

1.8 The multi junction will facilitate the connection of multiple pipelines from other regional carbon dioxide emitters to the Onshore Scheme in the future. A site options appraisal has identified a site on land to

the south of the A645, Camblesforth as the preferred site option for the multi junction.

1.9 Block valves will be required at regular intervals along the length of the cross country pipeline to enable the isolation of sections of pipeline for maintenance and safety. Site appraisals have been

undertaken for all the block valves and preferred sites have been identified as land to the south of Skiff Lane, Tollingham; land to the south of Lund Wold Road, South Dalton; and land to the south of the

unnamed track to Copper Hall, Skerne.

1.10 A pumping station is required to re-pressurise the carbon dioxide before it is transported offshore. This is proposed to be constructed

near to the coast. A site appraisal has been undertaken and identified land to the south of Sands Road, Barmston as the preferred site.

1.11 The offshore elements of the Project are collectively termed the

Yorkshire and Humber CCS Sub-Sea Pipeline and Geological Storage Site (shortened to the “Offshore Scheme”) and are proposed to comprise the construction of a 90km subsea pipeline to a geological

storage site. This is subject to a separate consenting regime requiring authorisation by the Secretary of State for Energy and Climate Change in accordance with the Petroleum Act 1998 and the Energy

Act 2008 respectively.

1.12 The sub-sea pipeline will have an external diameter of up to

approximately 610mm and would be sized to accommodate up to 17mt of carbon dioxide emissions per year. The geological storage site presently proposed would comprise the permanent storage of

captured carbon dioxide in a saline aquifer located approximately 1000m below the seabed. The undertaker has been granted an agreement to lease area 5/42 in the southern North Sea for the

purpose of geological storage of carbon dioxide. The capacity of the storage site is subject to on-going investigations but it is expected to accommodate at least 200mt of captured carbon dioxide. It is

anticipated that once this site has reached capacity further storage sites would be identified and utilised.

Page 5: Explanatory Memorandum (Rev D)

3

1.13 The Onshore and Offshore Schemes would be joined at the Mean Low Water Mark using appropriate landfall techniques; this is also the

juncture of the onshore and offshore consenting regimes.

1.14 A more detailed explanation of the authorised development, as set out in Schedule 1 (authorised development) of the Order and on the

works plans (Document Reference 2.3) can be found in the Construction Report (Document Reference 7.6).

2 THIS EXPLANATORY MEMORANDUM

2.1 A draft DCO accompanies the application for the Onshore Scheme and is entitled The Yorkshire and Humber (Carbon Capture and

Storage Cross Country Pipeline) Order 201[●] (the "Order").

2.2 As required by Regulation 5(2)(c) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009,

this explanatory memorandum also accompanies the application for the Onshore Scheme. It explains the purpose and effect of provisions in the draft Order.

2.3 The Planning Inspectorate’s Advice Note Thirteen as republished in April 2012 (“Advice Note 13”) clarifies its approach to the Infrastructure Planning (Model Provisions) (England and Wales)

Order 2009 (the “DCO Model Provisions”) as follows:

“‘Model provisions’

Model provisions were set out in the Infrastructure Planning (Model Provisions) (England and Wales) Order 2009 (SI 2009/2265). They included provisions which could be common to all NSIPs, others which relate to particular infrastructure development types, in particular railways and harbours, and model provisions in respect of requirements. The Localism Act 2011 removed the requirement for the decision-maker to have regard to the prescribed model provisions in deciding an application for development consent.

Model provisions were intended as a guide for developers in drafting orders, rather than a rigid structure, but aided consistency, and assisted developers to draft a comprehensive set of lawful provisions.

In the absence of relevant guidance published by DCLG, it would be helpful for the Planning Inspectorate to receive a track-change draft of the DCO showing any departures from the model provisions. The Planning Inspectorate would wish to receive such a track-change draft of the DCO both at the pre-

Page 6: Explanatory Memorandum (Rev D)

4

application stage and with the formal submission of the application for development consent.

Other provisions

Provisions used in ‘predecessor’ regimes such as for Transport and Works Act Orders or Harbour Empowerment Orders may be helpful in the drafting of a DCO. Developers should though satisfy themselves that the inclusion of particular wording is appropriate and relevant in all the circumstances of a given development. The relevant precedent and the rationale for including the particular wording of a provision will need to be set out and justified in the explanatory memorandum.”

2.4 This explanatory memorandum complies with the requirements of Advice Note 13.

2.5 The Order follows the DCO Model Provisions but, where appropriate for the circumstances of the Onshore Scheme, there are certain departures from these. Such departures, where material, are

explained in this explanatory memorandum.

2.6 Certain of these departures from the DCO Model Provisions reflect wording from the Transport and Works (Model Clauses for Railways

and Tramways) Order 2006 (the "TWA Model Provisions") and Orders made under the Transport and Works Act 1992 (“TWA Orders”). Where appropriate, this explanatory memorandum sets

out the rationale for including such wording in the context of the 2008 Act and the Onshore Scheme.

2.7 Where relevant, regard has also been had to the precedents set in

the development consent orders made by the Secretary of State under the 2008 Act; and references to such orders are made in this explanatory memorandum as appropriate.

2.8 Again, where relevant, regard has been had to the Planning Inspectorate’s Advice Note Fifteen “Drafting Development Consent

Orders”.

2.9 A comparison version of the draft Order against the DCO Model Provisions is also provided at appendix 1 to this explanatory

memorandum, showing any departures from the DCO Model Provisions.

Page 7: Explanatory Memorandum (Rev D)

5

3 PURPOSE OF THE ORDER

Nationally significant infrastructure development

3.1 Under sections 14(1)(g) and 21 of the Planning Act 2008 (the “2008 Act”) the construction of a cross-country1 pipeline in England2 other than by a gas transporter,3 which would otherwise require

authorisation under section 1(1) of the Pipe-lines Act 1962 (the “Pipe-lines Act”)4 (on account of the pipeline exceeding 16.093km in length),5 constitutes an NSIP. As stated at paragraph 1.4 above,

the cross-country pipeline comprised in the Onshore Scheme is approximately 67 km in length and will thus exceed 16.093 km in

length.

3.2 Section 31 of the 2008 Act provides that a development consent order is required to the extent that a development is or forms part of

an NSIP.

3.3 Accordingly, the undertaker is making an application to the Secretary of State under section 37 of the 2008 Act in order to obtain

development consent for the Onshore Scheme. The Order is part of the application.

Associated development

3.4 Pursuant to section 115(1) of the 2008 Act and in accordance with the principles set out in the document entitled “Planning Act 2008: Guidance on associated development applications for major

infrastructure projects” published in April 2013 by the Department for Communities and Local Government (the “CLG Guidance”), the Order also seeks consent for associated development set out in

Schedule 1 (authorised development) of the Order. Examples of items of associated development with their own Work Nos. in the Schedule include:

3.4.1 access roads;

3.4.2 temporary working areas;

3.4.3 temporary pipeline stores; and

3.4.4 office, welfare and security facilities.

1 S.21(1)(a) of the 2008 Act

2 S.21(2)(a) of the 2008 Act

3 S.14(1)(g) of the 2008 Act

4 S.21(1)(b) of the 2008 Act

5 S.1(1) and s.66(1) of the Pipe-lines Act

Page 8: Explanatory Memorandum (Rev D)

6

3.5 A list of further associated development is included at the end of Schedule 1 (authorised development) for works associated with

multiple Work Nos. These include in summary:

3.5.1 site preparation works and construction compounds for certain of the AGIs;

3.5.2 the installation of wires, cables, conductors, pipes and ducts;

3.5.3 pipeline construction works;

3.5.4 works to remove or alter the position of apparatus including mains,

sewers drains and cables, which will be required where these items need to be temporarily or permanently removed to allow the

construction and operation of the authorised development. Examples include the possible temporary diversion of a utility pipe or cable to provide working space to allow construction of permanent works;

3.5.5 locating aerial markers, cathodic protection test posts and field boundary markers;

3.5.6 landscaping, ecological mitigation works and other works to mitigate

any adverse effects of the construction, maintenance or operation of the authorised development;

3.5.7 works for the benefit or protection of land affected by the authorised

development, which might (where the undertaker considers it necessary) include works to reinstate land to its former condition including land drainage systems or providing fencing to replace that

temporarily removed or to provide a delineation between land ownership or usage;

3.5.8 works required for the strengthening, improvement, maintenance or

reconstruction of any streets, which may be required where existing tracks or streets are to carry increased heavy traffic or increased numbers of vehicles. Crossings of existing public and private

highways are required and reinstatement of excavated trenches will be necessary;

3.5.9 works to alter or remove road furniture;

3.5.10 ramps, means of access, footpaths and bridleways, which are required to access the facilities as a whole and to safely access

individual areas and buildings associated with the development;

3.5.11 the carrying out of street works pursuant to article 10 (street works), works to alter the layout of streets pursuant to article 11 (power to alter layout, etc., of streets) and the alteration or removal of road furniture;

Page 9: Explanatory Memorandum (Rev D)

7

3.5.12 works for the decommissioning, restoration and aftercare of the authorised development;

3.5.13 installation of drainage, drainage attenuation and land drainage including outfalls; and

3.5.14 other works, including working sites, storage areas and works of

demolition necessary for the construction or operation of the authorised development.

3.6 The undertaker considers there to be two types of works in this

“further associated development” section above:

3.6.1 The first is of the residual type described at paragraph 3.5.14: “other

works [etc.] as may be necessary for […] the construction or operation of the authorised development”. In the context of a large and complex nationally significant infrastructure project such as this,

it is acknowledged and understood that there may well be some minor works required for the purposes of carrying out and or operating the authorised development which were not specifically

foreseen and thus individually itemised in the Schedule of Works at the time the Order is granted. The Secretary of State has historically made them subject to the test that these kinds of unspecified

(because unknown and unforeseeable) works for the purposes of the authorised development are only authorised to the extent that they do not give rise to any materially new or different effects from those

assessed in the environmental statement (see for example paragraph (p) on page 62 of the recent Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014. This limitation wording is included in

the Order for the works at paragraph 3.5.14. Further to the first written questions, on review, the undertaker considered that the categories of works identified in paragraphs 3.5.4, 3.5.6 and 3.5.7

could, arguably, also be viewed as being of a similar type; though even here, the need for these types of works was clearly understood

at the time of the environmental impact assessment process carried out for the authorised development and, therefore, taken into account as part of that process. Strictly speaking, therefore, those

categories of works are not really unknown and unforeseeable in the same way as the works at 3.5.14. Thus the need for the additional caveat does not therefore arise in the same way but, to go some way

towards accommodating the point expressed in the written questions, the undertaker agrees to the limitation wording being added to paragraphs 3.5.4, 3.5.6 and 3.5.7 that the works must not give rise

to any materially different effects from those assessed in the environmental statement.

3.6.2 The second type of “further associated development” comprises

works which were clearly contemplated at the time of the environmental impact assessment process for the authorised

Page 10: Explanatory Memorandum (Rev D)

8

development as foreseeable activities, and in some detail. One example is those forms of “further associated development” included

in this final part of Schedule 1 (authorised development) simply as a drafting approach so as not to relist each form of associated development with every single related pipeline section Work No.: e.g.

the pipeline construction works in 3.5.3 or markers in 3.5.5. The significant environmental effects likely to be caused by this second type of work were therefore within the contemplation of the

environmental impact assessment process which has taken place to date in just the same way as the other items of development set out

in Schedule 1 (authorised development). The Infrastructure Planning (EIA) Regulations 2009 (the “EIA Regulations”) require applications for DCOs to be accompanied by an environmental statement which

contains a description of the development, a description of the aspects of the environment likely to be affected by the development and a description of the likely significant effects of the development

on the environment. However, the description of the development must be proportionate – clearly it would not be practicable to describe every piece of material, no matter how small, or every

movement or minor operation which will be undertaken in order to complete the development. Case law simply requires the description of the proposed development to be sufficient to enable the main

effects which that development is likely to have on the environment to be identified and assessed (R. v Rochdale MBC Ex p. Milne (No. 1) [1999] 3 P.L.R. 74; [2000] Env L.R. 1). Moreover, the second type of

“further associated development” described in this response would not permit the construction of a project “which could be very different in scale or impact from that applied for, assessed or

permitted” (R (Midcounties Co-operative Ltd) v Wyre Forest DC [2009] EWHC 964 (Admin)). In other words, whether this second

type of “further associated development” would require a retrospective, second environmental assessment mechanism after the DCO is made needs to be understood in the context of the

appropriate level of detail that was required under the EIA Regulations the first time, and whether it could give rise to very different effects to what was contemplated and assessed that first

time, sufficient to justify a second assessment. None of the other types of further associated development described in the paragraphs in the list at the end of Schedule 1 (authorised development) could

justify a second environmental assessment exercise to determine whether or not they fall within the scope of the authorised development. This is because they clearly form part of what has been

assessed and could not give rise to a very different scheme to the one which has been assessed. ” The undertaker therefore does not consider it either “necessary” or “reasonable in all respects” for the

purposes of paragraph 4.1.7 of EN-1 for a second environmental assessment exercise to be carried out for any “further associated

Page 11: Explanatory Memorandum (Rev D)

9

development” above, other than as currently set out in the draft Order.

3.7 Separately, the undertaker considers that all of the works described in Schedule 1 (authorised development) are either development for which development consent is required or associated development

for which development consent may be granted (in accordance with sections 31 and 115 of the 2008 Act and CLG Guidance) and, accordingly, may lawfully form part of an application for an Order

granting development consent under the 2008 Act.

4 ANCILLARY MATTERS

4.1 The Order also contains several matters ancillary to the development for which consent is sought.

4.2 Powers of compulsory acquisition

The main ancillary matter is that the Order seeks (1) powers of compulsory acquisition for land (and rights in or over land) that are required for, facilitate or are incidental to the Onshore Scheme under

sections 122 and 159 of the 2008 Act and (2) the power to override easements and other rights within the Order limits under sections 120(3) and (4) and paragraphs 2 and 3 of Schedule 5 of the 2008

Act. Justification for these powers is set out more particularly in the statement of reasons (Document Reference 4.1), which accompanies the application.

4.3 Approach of book of reference and land plans

The book of reference

4.3.1 The application for the Onshore Scheme is accompanied by a “book

of reference” as defined in Regulation 7 of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 (the “Regulations”). It should be read in conjunction with:

4.3.2 the Order (Document Reference 3.1); and

4.3.3 the twenty five “land plans” (Document Reference 2.1) with

drawing nos. HUMBCC-2014-1-JH-SH1 to HUMBCC-2014-1-JH-SH25,

which also accompany the application.

4.3.4 The book of reference is split into five parts, listing (in summary):

(a) in Part 1, the plots of land over which powers of compulsory acquisition or temporary possession are sought for the purposes of the authorised development. These plots together

Page 12: Explanatory Memorandum (Rev D)

10

form the “Order land”, more particularly defined in article 2 of the Order;

(b) in Part 2, any persons who “would or might” be entitled to make a claim under section 10 of the Compulsory Purchase Act 1965 (the “1965 Act”) or Part 1 of the Land

Compensation Act 1973 (the “1973 Act”) as a result of the Order being implemented or as a result of the use of the land once the Order has been implemented. The 1965 Act relates

to claims that may be made by those persons who have no land taken but who have the benefit of a right over the Order

land and whose right is interfered with or breached by the construction or use of the authorised development in such a way as to depreciate the value of its own land. The 1973 Act

relates to claims by persons whose property is sufficiently close to be depreciated in value by execution of works for the authorised development;

(c) in Part 3, any persons who have rights over the Order land, which may be extinguished, suspended or interfered with due to the carrying out of the authorised development;

(d) in Part 4, any of the Order land in which the Crown has an interest; and

(e) in Part 5, any Order land which falls into a "special category",

i.e. forming part of a common, open space, National Trust land or fuel or field garden allotment.

4.3.5 The first page of each Part provides the statutory language

describing what it lists.

Types of land on the land plans

4.3.6 The land plans show three different types of land within the Order

land:

(a) The land tinted dark grey is land which (if the Order is made)

may be subject to the exercise of compulsory acquisition powers (as further explained in paragraph 4.3.8 below). In addition to those compulsory acquisition powers, this land may

also be subject to the exercise of temporary possession powers for carrying out the authorised development generally and maintaining it (as further explained in paragraph 4.3.9

below), which includes in particular carrying out drainage works (as further explained in paragraph 4.3.10 below).

(b) The land tinted light grey is land which (if the Order is made)

may be subject to the exercise of temporary possession

Page 13: Explanatory Memorandum (Rev D)

11

powers for carrying out the authorised development generally and maintaining it (as further explained in paragraph 4.3.9

below), which, again, includes in particular carrying out drainage works (as further explained in paragraph 4.3.10 below). The differentiating feature of this type of land is that

none of the land tinted light grey is land that may be subject to the exercise of compulsory acquisition powers under the Order.

(c) The land shown cross-hatched may (if the Order is made) be subject to the exercise of temporary possession powers for

drainage works (as further explained in paragraph 4.3.10 below). The differentiating feature of this type of land is that none of the cross-hatched land may be subject to the exercise

of compulsory acquisition powers under the Order and the purposes for which temporary possession powers may be exercised is narrower than that at paragraph 4.3.6(b) above.

4.3.7 In other words, the purpose of the differentiation above is to ensure that the rights sought are proportionate to the requirements of constructing, operating and maintaining the authorised development

on different parts of the Order land.

Compulsory acquisition powers and temporary possession

4.3.8 The compulsory acquisition powers to which the land tinted dark grey

relate are conferred by articles 23-27 (inclusive) of the Order. These are either:

(a) referred to in this book of reference as “Permanent Type 1”

i.e. the acquisition of all interests and estates in the land; and/or

(b) referred to in this book of reference as “Permanent Type 2”

i.e. the creation of the following permanent new rights in relation to the land in a 24.4 metres wide strip of land (within

which a pipeline comprised in the authorised development (as defined in article 2 of The Yorkshire and Humber (Carbon Capture and Storage Cross Country Pipeline) Order 201[●])

may be located):

(i) rights to construct lay inspect test maintain repair protect reconstruct replace dismantle remove or render

unusable the authorised development in upon and over the land;

(ii) rights to use the authorised development for the

purposes for which it was designed;

Page 14: Explanatory Memorandum (Rev D)

12

(iii) rights to enter, pass and repass with or without vehicles over the said 24.4 metres wide strip of land for

all purposes associated with these rights;

(iv) rights to prevent the planting or removal of any trees, bushes or other fauna within the said 24.4 metres wide

strip of land which could damage or obstruct the authorised development or obstruct the undertaker from exercising its rights and powers in relation to the

authorised development (and which for the avoidance of doubt shall not prevent the planting of conventional

cereal crops);

(v) rights to prevent the construction of or remove any new building, structure or erection which is within the

said 24.4 metres wide strip of land;

(vi) rights of continuous vertical and lateral support for the pipeline and ancillary apparatus (if any) within the said

24.4 metres wide strip of land;

(vii) rights to install, adjust, alter and remove cathodic protection test posts, aerial markers, field boundary

markers transformer rectifier kiosks and electricity cabinets;

(viii) rights to prevent anything being done or caused or

permitted to be done on the 24.4m wide strip of land that is calculated or likely to interfere with or cause damage or injury to the authorised development or its

operation and to require that all reasonable precautions are taken to prevent such interference, damage or injury;

(ix) rights to prevent without the prior written consent of the undertaker (such consent not to be unreasonably

withheld or delayed) a material alteration being made or caused or permitted to be made to, or the deposit of anything being made on, any part of the 24.4m wide

strip of land so as to interfere with or obstruct the access to the said strip of land or to the authorised development or so as to lessen or in any way interfere

with the support afforded to the authorised development by the surrounding soil including minerals or so as materially to reduce the depth of soil above

the authorised development.

4.3.9 Referred to in this book of reference as “Temporary - general”, the temporary possession powers to which the land tinted dark grey and

Page 15: Explanatory Memorandum (Rev D)

13

light grey relate are more particularly described in articles 28 and 29 and Schedule 9 of the Order and, in summary, authorise the

temporary possession of the relevant land for the construction and (for the duration of a five year maintenance period where the undertaker so chooses) the maintenance of the authorised

development on the terms set out in the those provisions.

4.3.10 Referred to in this book of reference as “Temporary - drainage”, the temporary possession powers for “drainage works” (defined in

article 2 of the Order) to which the land tinted dark grey and light grey and the land shown cross-hatched relate are more particularly

described in articles 28 and 29 and Schedule 9 of the Order and, in summary, authorise the temporary possession of the relevant land for the construction of the drainage works and (for the duration of a

five year maintenance period where the undertaker so chooses) the maintenance of the authorised development on the terms set out in the those provisions.

4.4 Statutory instrument

The Order seeks to apply and modify certain statutory provisions as set out below in this explanatory memorandum, in particular in

relation to compulsory acquisition, under section 120(5) of the 2008 Act. Accordingly, pursuant to section 117(4) of the 2008 Act, the Order is set out in the form of a statutory instrument.

4.5 Other ancillary matters

Other ancillary matters include, for example, the maintenance and operation of the Onshore Scheme, the improvement, alteration and

temporary stopping up of lengths of existing highways necessary for the Onshore Scheme, the creation of new private means of access, the interaction between leases of the Onshore Scheme and landlord

and tenant law and provision for disputes and appeals under the Order. These are more particularly described at paragraph 5 below.

5 THE DRAFT ORDER

The purpose and effect of the Order are summarised as follows:

5.1 Preamble to the Order

As with every statutory instrument, the Order is introduced by a preamble, which amongst other things, recites the powers under which the instrument would be made.

5.2 Part I of the Order - Preliminary

Part I of the Order contains preliminary provisions.

Page 16: Explanatory Memorandum (Rev D)

14

Article 1 (citation and commencement) provides for the

commencement and citation of the Order.

Article 2 (interpretation) follows article 1 of the DCO Model

Provisions and provides for the interpretation of words and phrases used in the Order. The definitions in article 1 of the DCO Model Provisions have been

amended and supplemented to reflect the particular circumstances of the authorised development.

Amongst other things:

• “approved plans” means the plans listed in Part 4 of Schedule 2 (plans) to the Order, with which the authorised development must be

carried out in accordance (unless otherwise set out in the Requirements, for example where approval of detailed design is to follow

the making of the Order). The matter of approved plans is dealt with at Requirement 3 in Schedule 3 (requirements);

• The term “drainage works” is defined for the purposes of article 6(2), which clarifies that

these can be constructed within the Order limits;

• “Maintain” is defined as including “inspect,

examine, monitor, test, repair, set up, configure, dismantle and/or reconstruct the authorised development and/or replace part

or a section of the authorised development with a part or section which materially serves the same purpose”. Save for “dismantle”

“examine”, “monitor”, “set up” and “configure” all of these elements are derived from Article 1 of Schedule 2 to the DCO Model Provisions.

It is appropriate that maintenance should include the ability of the undertaker to inspect, examine, test and monitor the

authorised development to ascertain the extent of maintenance required. “Set up” and

“configure” relate to equipment and apparatus comprised in the authorised development. “Repair” and “dismantle”, by way of their plain

meaning, relate to development already constructed at the time of maintenance,

Page 17: Explanatory Memorandum (Rev D)

15

rather than potential for the construction of new development. “Reconstruct” is necessary,

particularly in the event that the authorised development, or part of it, were damaged such that reconstruction were required, and it

would not be appropriate in such circumstances for a nationally significant

infrastructure project to require a new development consent or planning permission, particularly when a plain English interpretation

of “reconstruct” must relate to a reconstruction of what had existed previously rather than unenvisaged development and, in

any event, article 5(a) (maintenance of authorised development) makes it clear that the power to maintain is subject to the proviso

that following reconstruction, the authorised development may not, save in immaterial respects, vary from the description of it given

in Schedule 1 (authorised development). “Replace”, again from the DCO Model Provisions, is qualified twofold: first by

clarification that replacement must be of part or a section of the authorised development

with a part or section which materially serves the same purpose (rather than by unenvisaged development, for example);

secondly by way of the proviso at article 5(a) that “maintenance” cannot vary from the description of the authorised development

given in Schedule 1 (authorised development). The above amendments are permitted by section 120(5)(c) of the 2008 Act, as they give

full effect to the power to maintain the authorised development under article 5 (maintenance of authorised development). The above definition of “maintain”, as qualified in article 5 (maintenance of authorised development) also complies with

the relevant case law tests, as it would not permit the construction of a project “which could be very different in scale or impact from

that applied for, assessed or permitted” (R (Midcounties Co-operative Ltd) v Wyre Forest DC [2009] EWHC 964 (Admin)). This is because the Infrastructure Planning (Environmental Impact Assessment)

Regulations (the “EIA Regulations”) require

Page 18: Explanatory Memorandum (Rev D)

16

the assessment of a project’s likely “significant” effects. The undertaker has

already considered and assessed the likely significant effects of the authorised development, as defined in Schedule 1 of the

Order, in accordance with the EIA Regulations (see the Environmental Statement (document

reference 6.0) and no materially new or different likely significant effects may arise as a result of maintenance of the authorised

development, because either those maintenance works will not lead to any variation in the authorised development (the

likely significant effects of which have been assessed) or, if they did, the variation in the authorised development would not be

immaterial, and the effects would fall foul of the restriction in Article 5(b). If the Secretary of State is minded that it is appropriate in the

public interest for the authorised development to be constructed and brought into operation (which would be consistent with what is said

in the National Policy Statement about carbon capture and storage being “a priority for UK

energy policy” – see paragraph 3.6.5) it is essential that the Order allows the authorised development to be kept in operation to fulfil

its important function without undue restrictions, as set out in this definition.

• the definition of “Order land” is brought in line

with section 159 of the 2008 Act, which clarifies that for the purposes of Part 7 of the 2008 Act, “land” includes any interest in or

right over land: it is appropriate that the same applies in this definition as the book of reference (Document Reference 4.3) provides

for the acquisition of both land and interests in and rights over land. Further, it is clarified that the land within the Order limits may also

be “used”, i.e. in accordance with temporary possession powers pursuant to articles 28 (temporary use of land for carrying out the authorised development) and 29 (temporary use of land for maintaining the authorised development);

• the definition of “relevant planning authority”

Page 19: Explanatory Memorandum (Rev D)

17

has been amended to clarify that the relevant planning authority will be the district planning

authority for any area of land to which any particular provision relates; and for clarity on the face of the draft Order, this article

specifies who these bodies currently are;

• the definition of statutory undertaker removes

references to sections 128 and 129 of the 2008 Act as these were repealed by the Growth and Infrastructure Act 2013;

• the definition of “street authority” has the same meaning as in section 49 of Part 3 of the New Roads and Street Works Act 1991

(i.e. for publicly maintainable highway: the “highway authority”; for other highway: the “street managers”), as per the DCO Model

Provisions, but for consistency it is made clear that the definition of “highway authority” in section 49 should relate back to the Order

definition, meaning either East Riding of Yorkshire Council or North Yorkshire County Council, for the purposes of the Order;

• at the request of North Yorkshire County Council, for the purposes of Article 17 (traffic regulation) a definition for “traffic authority” has been included, by reference to the Road Traffic Regulation Act 1984;

• the definition of “watercourse” from article 2 of Schedule 1 of the DCO Model provisions relates only to article 19 (discharge of water), for which it was intended in the Model provisions, and has therefore been inserted at article 19(8)(b) for ease;

• A definition of “flood risk assessment” is provided for the purposes of Article 49 (certification of plans etc.) and Requirement 9

of Schedule 3 (requirements). Similarly “Barmston Pumping Station parameter plan”, “Camblesforth Multi-junction parameter plan”,

“code of construction practice”, “drainage strategy” and “project design statement” are defined for the purposes of Article 49

(certification of plans etc.). However, these

Page 20: Explanatory Memorandum (Rev D)

18

definitions are provided by reference to meanings given in the Requirements: it is

considered easier for the reader of the Requirements to find terms used only in particular Requirements in Schedule 3

(requirements) substantively defined in that Schedule rather than having to refer to the

start of the DCO in Article 2 only because the documents appear in the certification list at Article 49 (certification of plans etc.).

Paragraph (2) provides that apart from the definition of the “undertaker”, the definitions in paragraph (1) do not apply to Schedule 10 (deemed marine licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009). This is because Schedule 10 has its own set of definitions and, whilst the deemed

marine licence is in law merely another schedule of the draft Order to be made by the Secretary of State, rather than the Marine Management Organisation

(“MMO”), in practice the licence is likely to be considered by contractors and agents as a self-contained document. Significant cross-references to

the draft Order would then be unduly complex. Moreover, if the licence is varied by the MMO under

section 72 (variation, suspension, revocation and transfer) of the Marine and Coastal Access Act 2009, the draft Order will become increasingly remote,

making cross-reference to it more burdensome.

Paragraph (3) specifies that the definition of “undertaker” in paragraph 1 does not apply to

Schedule 11 (protective provisions). This is because in Schedule 11, so as to avoid any confusion, National Grid Carbon is referred to as “the promoter” on the

basis that in protective provisions the term “undertaker” is commonly used to relate to the relevant statutory undertaker in whose favour the

protective provisions are made.

Further, it is clarified:

• at paragraph (4) that, as with recent DCOs,

including at article 1(2) of the Hinkley Point C (Nuclear Generating Station) Order 2013, references to rights over land include rights in

relation to and under that land as well as above it;

Page 21: Explanatory Memorandum (Rev D)

19

• at paragraph (5) that all distances, directions and lengths referred to in the Order, such as

in the works plan, land plan and other drawings, are approximate and distances between points on a work are to be taken to

be measured along that work. In particular in respect of scheduled linear works referred to

in this Order all distances are measured along the indicative pipeline route as shown on the works plans for that work. This is to ensure

consistency between interpretation of the Order and the documents to which it refers;

• at paragraph (6) that all areas described in

metres in the book of reference are approximate;

• at paragraph (7) that a reference in the Order

to a work designated by a number, or by a combination of letters and numbers (for example “Work No. 2”) is a reference to one

of the works listed in Schedule 1 (authorised development);

• at paragraph (8) that a reference in the Order

to a document or plan required to be submitted for certification under article 49

(certification of plans etc.) is a reference to the version of that document or plan that has been so certified;

• at paragraph (9) that a reference in the Order to legislation includes that legislation as amended.

Article 3 (application, modification and disapplication of legislative provisions) has similar effect to article 6 of Schedule 1 of the DCO Model provisions.

Paragraph (1) would provide for the application, modification and exclusion of public general legislation set out in Part 1 of Schedule 12 (miscellaneous controls). This is only used as a drafting mechanism for the purposes of SSSI consent, and for applying

certain regulations under the Pipeline Safety Regulations 1996 which would otherwise not apply to the authorised development, as more particularly

explained in respect of Schedule 12 below.

Page 22: Explanatory Memorandum (Rev D)

20

Paragraphs (2) to (4) would exclude byelaws and statutory provisions of local application having effect,

but only so far as these would be inconsistent with powers exercised under the Order. Although the undertaker has made diligent efforts to search for

relevant local legislation and byelaws, and sets out amendments to particular known byelaws of internal

drainage boards at Part 2 of Schedule 12 (explained more particularly in the row of this table which relates to that Schedule below), such searches can never be

entirely definitive. Accordingly, paragraph (2) extends exclusion to any statutory provision of local application to avoid any unknown local legislation acting as an

impediment to the Onshore Scheme. For the avoidance of doubt, paragraph (3) further clarifies that certain key activities necessary for the construction,

operation and maintenance of the authorised development, which could otherwise be compromised by common provisions in local enactments or statutory

provisions of local application, are allowed under the Order.

East Riding of Yorkshire Council (“ERYC”) has brought

to National Grid’s attention that, in its capacity as Lead Local Flood Authority, it will in due course bring

forward byelaws which are likely to conflict with activities required for the carrying out of the authorised development but which may not provide

scope for consent under the terms of those byelaws. Paragraph (5) therefore provides that any byelaws made by ERYC in its capacity as lead local flood

authority are excluded if the provision:

(a) would prevent or restrict the taking of any action under the Order; and

(b) does not include provision that would permit the taking of that action with the consent of ERYC, an internal drainage board or the Environment Agency.

This approach differs to that taken in respect of internal drainage boards described in respect of paragraphs 1 to 8 of Part 2 of Schedule 12. This is

because those bodies currently have byelaws in place which may be amended for the purposes of the Order to enable scope for consent, whereas the terms of any

ERYC byelaws are not known at this time.

Page 23: Explanatory Memorandum (Rev D)

21

ERYC is aware of this provision. It will therefore be able to add savings provisions in its byelaws in respect

of the Order to reflect that the relevant ERYC byelaws enable scope for consent rather than being outright prohibitions. Inserting savings for particular bodies or

particular circumstances is common. This would mean that paragraph (5) may never have practical effect

once ERYC includes those savings, as it would only apply to byelaws which do not allow scope for consent. Nevertheless, in the context of the certainty required

by a nationally significant infrastructure project, it is important that this paragraph be included in the Order.

Separately, as a safeguard, under paragraph (6) if the

undertaker is notified by anyone that anything to be done under the Order would contravene a statutory provision of local application, the undertaker has to

respond within 14 days setting out whether it agrees that there would be a contravention and the grounds on which it believes the article is excluded and the

extent of that exclusion.

The provisions of this article may be made pursuant to section 120(5)(a) of the 2008 Act. That section

provides that an Order granting development consent may apply, modify or exclude a statutory provision

which relates to any matter for which provision may be made in the Order.

6 PART II OF THE ORDER - WORKS PROVISIONS

6.1 Principal powers

Articles 4 to 7 of the Order contain provisions for the principal powers needed for the authorised development.

Article 4 (development consent etc. granted by the Order) is

based on Article 2 of Schedule 1 of the DCO Model Provisions and grants development consent for the authorised development to be carried out within the

Order limits and maintained.

The authorised development means the development under sections 14(1)(g) and 21 of the 2008 Act and

associated development under section 115 of the 2008 Act. Schedule 1 (authorised development) describes

Page 24: Explanatory Memorandum (Rev D)

22

the authorised development.

Development consent for the authorised development

is subject to the requirements set out in Schedule 3 (requirements).

Sub-paragraph (b) of the article provides for consent

to operate and use the authorised development for the purpose for which it is designed. Section 157(2) of the

2008 Act expressly allows the authorisation for use of a “building” for the purpose for which it is designed. However, the authorised development includes key

elements, such as the pipeline, which are not buildings and therefore the clarification provided in sub-paragraph (b) is necessary. Such a paragraph may be

included in the Order because such provision is sensible and section 120(3) of the 2008 Act allows a draft Order to make provision relating to the

development for which consent is granted.

Article 5 (maintenance of authorised development) follows the wording of article 3 of Schedule 1 of the DCO Model

Provisions, providing for the maintenance of the authorised development, save that it clarifies for the

avoidance of doubt that following maintenance activities being completed the resulting works may not vary from the description of those works in Schedule 1

(authorised development).

Article 6 (limits of deviation) The works plans set out that the limits of deviation for where the pipeline is to be

located are narrower than the construction corridor, i.e. the Order limits, required for construction of the pipeline. Accordingly, in terms of lateral limits of

deviation, article 6 of Schedule 2 of the DCO Model Provisions has been tailored to clarify for the

avoidance of doubt that whilst the ultimate location of works themselves fall within the limits of deviation, the construction activities for those works may be carried

out anywhere within the Order limits. This does not apply to the drainage works: it is clarified in the article that these may be located anywhere within the Order

limits.

In terms of vertical limits of deviation:

• it should be noted that the Order does not use

such limits in respect of development at above ground installations as a proxy for the concept

Page 25: Explanatory Memorandum (Rev D)

23

of a building envelope, where instead the conventional approach for defining built

development is adopted by way of Requirements 3 (approved details), 5 (Barmston Pumping Station) and 6

(Camblesforth Multi-junction design) and the approved plans listed in Part 4 of Schedule 2

(approved plans).

• paragraph (3) clarifies that aerial markers, cathodic protection test posts and field

boundary markers may be up to 3 metres high;

• paragraph (4) specifies that the authorised

development may deviate vertically from ground surface levels to any extent downwards as may be found to be necessary

or convenient. This wording is directly from article 6(b)(ii) of Schedule 2 of the DCO Model Provisions and article 5(b)(ii) of the TWA

Model Provisions. It is common in linear projects: see article 8(b)(ii) of the Network Rail (North Doncaster Chord) Order 2012 and

article 7(b)(ii) of the Network Rail (Ipswich Chord) Order 2012, for example. Although a

minimum depth of cover, in terms of how much ground must be kept above a pipeline, is relevant because of receptors above it, such

as roads and rivers, for example (and such depths of cover are secured by way of the description in relevant Work Nos. in Schedule

1 (authorised development)), the amount of ground which is to lie beneath a pipeline does not need to be constrained. Indeed, an

element of flexibility as to how deep a pipeline is to be installed is necessary so that installation can be carried out in line with the

ground conditions ascertained during construction, and this is recognised in both the DCO and TWA Model Provisions. In any

event, there is no material prejudice to land ownership the deeper a pipeline is installed.

Article 7 (defence to proceedings in respect of statutory nuisance) follows article 7 of Schedule 1 of the DCO Model Provisions and provides that no one can bring

statutory nuisance proceedings under the

Page 26: Explanatory Memorandum (Rev D)

24

Environmental Protection Act 1990 in respect of noise, if:

• the noise relates to premises used by the undertaker for the purposes of or in connection with the construction or

maintenance of the authorised development and notice has been given under section 60 or

consent obtained under section 61 or 65 of the Control of Pollution Act 1974 or it is unavoidable; or

• the noise relates to premises used by the undertaker for the authorised development and the authorised development is being used

in accordance with a scheme for noise management approved by the relevant planning authority as described in paragraph

15 of Schedule 3 (requirements) of the draft Order.

6.2 Benefit of Order

Articles 8 and 9 of the Order contain provisions relating to the benefit and transfer of the benefit of the Order.

Article 8 (benefit of Order) follows article 4 of Schedule 1 of the DCO Model Provisions and would, subject to article

9 (transfer of benefit of Order) of the Order, grant only National Grid Carbon Limited the benefit of the Order rather than allowing the benefit to run with ownership

of the land as envisaged by the 2008 Act.

Paragraph (2) excepts where works are carried out for the benefit or protection of persons or land affected by

the authorised development, so that it is clear that in these cases the benefit of the “planning permission”

equivalent of the Order, i.e. development consent, for those mitigation works is not personal to the undertaker but also for the users of the relevant land.

Article 9 (transfer of benefit of Order) follows article 5 of Schedule 1 of the DCO Model Provisions and would provide for the permanent or temporary transfer of the

benefit of the Order, subject to the consent of the Secretary of State and the transferee being subject to the same restrictions, liabilities and obligations placed

Page 27: Explanatory Memorandum (Rev D)

25

upon National Grid Carbon under the Order.

6.3 Streets

Articles 10 to 18 of the Order contain provisions relating to streets.

Article 10 (street works) follows article 8 of Schedule 1 of the DCO Model Provisions and would confer, for the purposes of the authorised development, authority on

the undertaker to break open (including for the purposes of carrying out surveys); tunnel under; place or change the position of apparatus or execute any

works incidental to these works in or under certain streets, which are specified in Schedule 4 (streets subject to street works) and within the Order limits, for

the purposes of the authorised development.

The authority given by this article is a statutory right

for the purposes of sections 48(3) (streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the New Roads and

Street Works Act 1991 (the “1991 Act”), which means that the Order replaces the need for a street works licence under the 1991 Act.

Paragraph (3) confirms that the provisions of sections 54 to 106 of the 1991 Act apply to any street works (as defined in that Act) carried out under this power

apart from the following exceptions:

• an undertaker does not ordinarily need the consent of the street authority for placing

apparatus in a protected street if it has a street works licence (see section 61(2) of the 1991 Act). The equivalent of that licence is

comprised in paragraph (1). Accordingly, sub-paragraph (3)(a) confirms that this means

that the undertaker does not need further consent from the highway authority for placing apparatus in the course of the

authorised development. This is necessary because the highway authority has identified the A1034 and A1079 as “protected streets”,

the pipeline will be crossing these and the highway authority has in pre-application discussions not indicated any objection to

that.

Page 28: Explanatory Memorandum (Rev D)

26

• sections 62(2) and 62(4) of the 1991 Act allow the Secretary of State following the

designation of a protected street to require removal or repositioning of apparatus already placed in the street, or if works are still in

progress, to give directions in respect of those. It is therefore sensible for sub-

paragraphs (3)(b) and (c) to disapply these in relation to apparatus placed in the course of the authorised development, in case streets in

which the pipeline is placed are in future designated as protected streets, as the pipeline is a nationally significant

infrastructure project requiring certainty that it will not have to be moved.

In this article, “apparatus” has the same meaning as in Part 3 of the 1991 Act. However, for the purposes of the draft Order this has been expanded to include

aerial markers, cathodic protection test posts and field boundary markers as it will be necessary to place these along the pipeline route. Pipelines, transformer

rectification kiosks and electricity cabinets are also clarified as being included within the definition of

“apparatus”.

Article 11

(power to alter layout, etc., of streets) is based on article 6 of Schedule 2 of the TWA Model Provisions

and would allow for the layout of the existing streets specified in Schedule 5 (streets subject to alteration of layout) to be altered to ensure that these are

appropriately configured to merge with the new roads comprised in Work Nos. 4C, 3G, 6C, 8B, 9C, 11C, 12 and 14B which connect the AGIs to the existing

highway network in Schedule 1 (authorised development) of the Order.

Paragraph (2) confers a broader power to alter the

layout of any street within the Order limits for the purposes of constructing and maintaining the

authorised development. However, this broader power is limited by the consent of the street authority, not to be unreasonably withheld or delayed.

This provision falls under item 15 of part 1 of Schedule 5 of the 2008 Act, namely the carrying out of civil

Page 29: Explanatory Memorandum (Rev D)

27

engineering or other works, and is permitted to be included in the draft Order under Section 120(3) of the

2008 Act.

This provision is also necessary and expedient under Section 120(5)(c) of the 2008 Act to give full effect to

article 4 (development consent etc. granted by the Order) which authorises the new roads comprised in

Work Nos. 3G, 4C, 6C, 8B, 9C, 11C, 12 and 14B in Schedule 1 (authorised development) of the Order. Article 11 also has precedent in recent linear schemes

authorised under the Transport and Works Act 1992 (e.g. at article 7 of the Network Rail Hitchin (Cambridge Junction Order) 2011) and the 2008 Act

(e.g. article 10 of the Network Rail (North Doncaster chord) Order 2012) and article 8 of The Lancashire County Council (Torrisholme to the M6 Link (A683

Completion of Heysham to M6 Link Road)) Order 2013.

Paragraph (4) is not from the DCO Model provisions but sets out a list of the types of works to streets

which may be carried out to the streets listed in Schedules 4 (streets subject to street works) and 5 (streets subject to alteration of layout). These include

the right to:

• demolish, remove, replace and relocate any

bus shelter and associated bus stop infrastructure;

• execute any works to provide or improve sight

lines required by the highway authority;

• remove and replace kerbs and flume ditches for the purposes of creating permanent and

temporary accesses;

• execute and maintain any works to provide hard and soft landscaping;

• carry out re-lining and placement of new temporary markings; and

• carry out works required that are incidental to

those kinds of works.

These items are often added by promoters of development consent orders into the list of works to

be carried out pursuant to the power equivalent to a

Page 30: Explanatory Memorandum (Rev D)

28

street works licence under the 1991 Act, i.e. article 10 (street works) but such a licence relates to the placing of apparatus rather than works to streets of this kind not necessarily related to the placing of apparatus; and for that reason these items are moved to this provision

in respect of alterations of highway layout as the more appropriate provision to which they relate. This

element of the provision may be included in the Order because it provides for the carrying out of civil engineering or other works related to the authorised

development, as permitted by sections 120(3) and (4) together with item 15 of Part 1 of Schedule 5 of the 2008 Act. The provision is also necessary and

expedient to give full effect to the power to carry out the authorised development under article 4 of the draft Order (development consent etc. granted by the Order), as permitted under Section 120(5) of the 2008 Act.

Article 12 (construction and maintenance of new, altered or diverted streets) is based on article 10 of Schedule 2 of the DCO Model Provisions and creates a mechanism

whereby any new street constructed under the Order will, if notice has been served on the highway authority, after a 12 month maintenance period, and

provided that it is completed to the reasonable satisfaction of the highway authority be adopted for maintenance at the public expense. The equivalent

DCO Model Provision, article 10, has only been modified so that:

• adoption is by notice rather than automatic on

the above criteria being met. This is because not all streets to be constructed under the Order, such as the access roads to the AGIs,

are to be adopted and the intention is for them to remain private, save for elements of junctions joining existing highway to be

determined following construction. Similar provision is made in paragraph (2) in the case

of alterations and diversions, where it is expected that the highway authority would require all such alterations or diversions to be

adopted, so the DCO Model Provisions are followed in this regard without reference to a notice system;

• at the request of North Yorkshire County

Page 31: Explanatory Memorandum (Rev D)

29

Council, paragraph (2) clarifies that the maintenance period, prior to adoption of

works as public highway maintainable at the public expense, continues until the undertaker has reinstated and make good damage or

defects in the works.

Paragraph (3) of this article provides that any street

constructed pursuant to the Order (which was not previously part of the public highway) will be deemed as dedicated as public highway on prior notice being

given to the highway authority (and if different the street authority). This is intended to make provision for the dedication of new streets, or parts of streets,

constructed under the Order. This mechanism for dedication is complementary to the mechanism from the DCO Model Provisions at paragraphs (1) and (2),

which instead relate to the terms on which:

• new streets (such as access roads to the AGIs) are to be adopted as maintainable at the public expense by the local highway authority; or

• altered parts of streets (such as those which

are altered or diverted in connecting AGI access roads to existing public highway) are to

be adopted as maintainable at the public expense by the local highway authority.

It is not proposed that any new streets constructed

pursuant to the Order that will be private will also be left in the ownership of a third party land owner and the book of reference (Document Reference 4.3)

secures the relevant land.

Paragraph (4) of this article excludes from its scope the structure of any bridge carrying a street as the

responsibility for maintaining the structure of any bridge will remain with the owner of the relevant bridge.

Following article 10 of Schedule 2 of the DCO Model Provisions, further incidental provision is made for the undertaker to have a defence against claims for loss or

damage resulting from failure to maintain any street under this article if he can prove that he took all care reasonably necessary in the circumstances to ensure

that the relevant part of the street was not dangerous

Page 32: Explanatory Memorandum (Rev D)

30

to traffic. The article sets out factors which a court can take into account in considering this defence. No

offence is created.

Article 13 (permanent stopping up of streets) follows article 9 of

Schedule 1 of the DCO Model Provisions and would provide for the permanent stopping up of any street so long as the prior approval of the local highway

authority has been given.

In relation to such streets, the local highway authority may require a substitute. There are other safeguards

for where no substitute is to be provided for a street stopped up, including ensuring that the undertaker either owns the land either side of the street being

stopped up, there being no right of access hindered or there being another reasonably convenient access. There is provision for compensation.

Where a section of street is stopped up, all rights of way over the street are extinguished and the undertaker may use it for the purpose of the

authorised development.

No such permanent stopping up is currently envisaged

but the undertaker considers it appropriate to include this provision for the following reasons:

• the authorised development covers a wide

geographical area, being an approximately 67km long cross-country pipeline between Camblesforth Multi-junction and the coast

(plus approximately a further 5.6km between the Camblesforth Multi-junction and Drax);

• there may be cases where in future it is

asserted that the highway boundary is not as shown on the local highway authorities’ plans of the extent of public highway (as such plans

are never considered definitive) or highway is created within the Order limits after the Order is made but before it is constructed. The risk

is all the greater because of the length and linear nature of the authorised development;

• such newly asserted or simply new public highway could impede the construction, maintenance or operation of the authorised

development if not permanently stopped up;

Page 33: Explanatory Memorandum (Rev D)

31

• this residual power therefore provides certainty for the construction of a linear

scheme the scale and length of the authorised development, proportionate to its urgency in policy: as set out above, paragraph 3.6.5 of

EN-1 describes carbon capture and storage as “a priority for UK energy policy”, even

amongst the urgency of other nationally significant energy projects;

• the 2008 Act provides that particular provision

may be made in an order granting development consent for “The stopping or diversion of highways” (Sub-sections 120(3)

and (4) and paragraph 17 of Part 1 of Schedule 5). Providing a mechanism for permanently stopping up highway is a matter

which relates to or is ancillary to this development for the purposes of sub-sections 120(3);

• a key objective of the Government under the 2008 Act is to provide as far as possible a “one stop shop” in terms of consents required

for nationally significant infrastructure projects, so it is entirely appropriate for this

residual power to be contained in the Order. The objective is not to compel promoters to seek powers such as this, which are available

elsewhere, outside of the Order. This is not only for the purpose of facilitating the more expeditious authorisation and implementation

of nationally significant infrastructure projects in the national interest. It is also (1) to ensure that the safeguards contained in the Order will

apply to powers required for the project in question and (2) all parties can see and understand the extent of powers and

restrictions on them in one place: in the Order.

Article 14 (temporary stopping up of streets and public rights of way) follows article 11 of the DCO Model Provisions but has been expanded to deal also with public rights

of way because the DCO Model provisions contain no provision for the temporary stopping up of such rights of way but only for permanent extinguishment. This

Page 34: Explanatory Memorandum (Rev D)

32

would provide for either the temporary stopping up, alteration or diversion:

• of those streets and rights of way listed in Schedule 6 (streets and rights of way etc. to be temporarily stopped up) to the Order,

following consultation with the relevant local highway authority; and

• of any streets and rights of way (whether or not within the Order limits) subject to the consent of the relevant local highway

authority, which may attach reasonable conditions to that consent but cannot unreasonably withhold or delay it. The

reasons for inclusion of residual provision for potentially temporarily stopping up currently unspecified streets and rights of way are the

same as in respect of Article 13 (permanent stopping up of streets), described in the row above.

The Order may make provision for the stopping up of highways under sections 120(3) and 120(4) and item 17 of Part 2 of Schedule 5 of the 2008 Act. The rights

of way to which this article refers are as much highways for the purposes of item 17, being another

form of public highway, as the streets to which article 11 of the DCO Model Provisions refers and on which this article is based.

Sub-paragraph (1)(a) of the article clarifies that both a class of traffic as well as traffic generally can be diverted under this power and is included to reduce

inconvenience to the public where possible.

This provision is necessary and expedient under section 120(5)(c) of the 2008 Act to give full effect to

article 4 (development consent etc. granted by the Order) because the streets or rights of way listed at Schedule 6 (streets and public rights of way to be temporarily stopped up) need to be stopped up, primarily to allow the laying of the cross-country pipeline across these.

Article 15 (apparatus and rights of statutory undertakers in permanently stopped up streets) is derived from article

32 of Schedule 1 of the DCO Model Provisions and would provide that the undertaker may, where a street

Page 35: Explanatory Memorandum (Rev D)

33

is permanently stopped up, require the statutory undertaker to relocate affected apparatus or provide

other apparatus in substitution for the existing apparatus. The statutory undertaker is to be reimbursed in such circumstances. Otherwise, a

statutory undertaker retains the same powers and rights in respect of its apparatus under permanently

stopped up streets which it would have had if the Order had not been made.

Article 16 (access to works) follows article 12 of Schedule 1 of

the DCO Model Provisions and confers upon the undertaker powers for the purposes of the authorised development to provide or improve access as specified

in Schedule 7 (access to works).

Similar powers are conferred in relation to any other locations within the Order limits reasonably required in

relation to the authorised development, provided that the relevant planning authority provides approval following consultation with the highway authority,

which is not to be unreasonably withheld or delayed.

Article 17 (traffic regulation) is not from the DCO Model

Provisions, but is based on article 41 of Schedule 2 of the TWA Model Provisions for tramways, i.e. for linear projects, and article 39 of the Network Rail (North

Doncaster Chord) Order 2012.

It would allow the undertaker to put in place temporary and traffic regulation measures subject to

the consent of the traffic authority should this be necessary for the purpose of the construction, maintenance and operation of the authorised

development, for example should the traffic authority require traffic lights and/or a left turn sign only as a

result of junction modifications comprised in the authorised development. It can be included in the Order under sections 120(3) and 120(4) and item 20

of Part 2 of Schedule 5 of the 2008 Act.

Article 18 (agreements with street authorities) follows article 13 of Schedule 1 of the DCO Model Provisions and would

allow the undertaker to enter into agreements with street authorities which could devolve the undertaker’s powers under the Order to the authority in respect of

the construction of new streets; the improvement of existing streets; the stopping up, alteration or

Page 36: Explanatory Memorandum (Rev D)

34

diversion of streets; and street works listed in the Order. Note that this power is a separate matter to

agreements under section 278 of the Highways Act 1980. Agreements under that section do not relate to powers under the Order but instead to a local highway

authority devolving its powers under that section to a developer, rather than the developer devolving its powers under the Order to a local highway authority, which is the purpose of this article.

Sub-paragraph 1(b) departs from the DCO Model

Provisions and clarifies that an agreement may relate to strengthening, improving, repairing or reconstructing streets under the powers conferred by

the Order. As permitted by section 120(5)(d) of the 2008 Act, this additional provision supplements the power in sub-paragraph 1(a) for an agreement to be

entered into for the construction of a street as well as article 5 of the Order (maintenance of authorised development), which would allow for such streets to

be repaired. It also has precedent in article 17 of the Nottingham Express Transit System Order 2009 and article 13 of the Network Rail (Hitchin (Cambridge

Junction)) Order 2011.

At the request of North Yorkshire County Council, the

article has also been revised to provide further legal context under the aegis of the Order, in addition to Article 12 (Construction and maintenance of new, altered or diverted streets) for the highways agreement which the undertaker is negotiating with it in respect of the adoption of certain works comprised

in the authorised development as public highway maintainable at the public expense.

6.4 Supplemental powers

Articles 19 to 22 of the Order contain provisions relating to supplemental powers.

Article 19 (discharge of water) follows article 14 of Schedule 1 of the DCO Model Provisions and would enable the

undertaker to discharge water into any watercourse, public sewer or drain in connection with the carrying out and maintenance of the authorised development

with the approval of the authority to which the watercourse, public sewer or drain belongs and subject to certain other conditions.

Page 37: Explanatory Memorandum (Rev D)

35

For the purpose of this article, public sewers or drains mean those which belong to the Environment Agency,

an internal drainage board, joint planning board, local authority or a sewerage undertaker.

Paragraph (6) clarifies the wording from the equivalent

paragraph of the DCO Model Provisions’ article 14 that nothing in this article requiring avoidance of releasing

impurities into public watercourses or drains requires the undertaker to maintain either these or private drains comprised in the authorised development:

whilst any private drains on land of which temporary possession is taken for the purposes of construction of the authorised development must be reinstated to the

satisfaction of the landowner pursuant to article 28(4), once the undertaker has vacated that land, the responsibility for maintenance of any private drains on

private land resides with the landowner, as it did prior to construction of the authorised development.

The definition of “watercourse” at article 2 of Schedule

1 of the DCO Model provisions is inserted at sub-paragraph 8(b) of this article for ease, rather than at article 2 of this Order, as this meaning of watercourse

is used only in this article.

Reference to section 85 of the Water Resources Act

1991, which appears in the DCO Model Provisions, has been deleted. This is because this section has been repealed by, inter alia, paragraph 8(a) of Schedule 26

of the Environmental Permitting (England and Wales) Regulations 2010 (the “Environmental Permitting Regulations”). Instead, paragraph (7) of the article is

updated to refer to the successor regime under the Environmental Permitting Regulations. This approach was accepted by the Secretary of State in article 13(7)

of the Network Rail (Ipswich Chord) Order 2012 and at article 14(7) of the Rookery South (Resource Recovery Facility) Order 2011.

Article 20 (protective work to buildings) follows article 15 of Schedule 1 of the DCO Model Provisions and confers

on the undertaker the right at its own expense to carry out protective works to buildings within the Order limits before or during construction of the authorised

development, in the vicinity of the building and for up to five years after that part of the authorised

Page 38: Explanatory Memorandum (Rev D)

36

development opens for use. Except in the case of emergency, there are requirements for prior notice to

be given to owners and occupiers.

Provision is also made for owners and occupiers to serve counter-notices questioning the necessity of

such protective works, with recourse to arbitration and provision for compensation.

Article 21 (authority to survey and investigate the land) follows article 16 of Schedule 1 of the DCO Model Provisions and confers on the undertaker power to survey and

investigate land, to make trial holes and remove soil samples, carry out ecological and archaeological investigations, place on/leave on/remove apparatus for

use in connection a survey, investigation or trial holes.

The power in the DCO Model Provisions is extended to include the ability to take, and process, samples of

water, air, soil or rock, flora, bodily excretions, non-human dead bodies, or any non-living thing present as a result of human action found on, in or over the land.

This wording is not contained in the DCO Model Provisions. It reflects the wording of section 53(3A) of

the 2008 Act which clarifies that the right to enter land for the purposes of surveying includes the power to take and process certain types of samples. This may

be included in a DCO under section 120(4) and item 12 of Part 1 of Schedule 5 of the 2008 Act, which makes particular provision for the inclusion of powers for

carrying out surveys or taking of soil samples.

The power to enter land and leave apparatus is subject to a requirement on the undertaker to give at least 14

days’ notice to owners and occupiers of the land.

The undertaker may be asked to provide evidence of its authority to enter the land.

Trial holes cannot be made on public highway without the consent of the highway authority or on a private street without the consent of the street authority, not

to be unreasonably withheld or delayed. There is also provision for compensation payments.

Article 22 (removal of human remains) is based on DCO Model Provision article 17. It requires the undertaker, before it carries out any development or works which will or

may disturb any human remains in any land within the

Page 39: Explanatory Memorandum (Rev D)

37

Order limits, to remove those remains. Before removing any human remains, the undertaker is

required to publish notice of its intention to do so. Notice is also required to be displayed near the site and, as soon as reasonably practicable, after its

publication a copy should be sent to the relevant planning authority.

Any relative or personal representative of any deceased person whose remains are proposed to be removed from any land within the Order limits may

undertake the removal of the remains themselves and arrange for those remains to be re-interred or cremated, the undertaker being responsible for the

reasonable costs in doing so.

In the event that such relative or personal representative does not remove the remains, the

undertaker is required to comply with any reasonable request the relative or personal representative may make in relation to the removal and re-interment or

cremation of the remains.

Paragraph (12) clarifies that the removal of remains under this article must be carried out in accordance

with any directions which may be given by the Secretary of State.

Paragraphs (14) and (16) clarify that section 25 of the Burial Act 1857 (bodies not to be removed from burial grounds save under faculty, without licence of

Secretary of State) and The Town and Country Planning (Churches, Places of Religious Worship and Burial Ground) Regulations 1950 (the “1950

Regulations”) are disapplied in relation to the authorised development. This is because this legislation contains procedures for removing human

remains which conflict with or duplicate the procedures set out in the DCO Model provisions.

Paragraph (15) applies to this Order sections 238 and

239 of the 1990 Act, which ordinarily allow the use of consecrated land or burial grounds in accordance with a planning permission notwithstanding ecclesiastical

law, so that land acquired for the authorised development or temporarily used or in relation to which rights are acquired, has the same benefit of

those 1990 Act sections as it would have done if the

Page 40: Explanatory Memorandum (Rev D)

38

Order had been a planning permission.

7 PART III OF THE ORDER - ACQUISITION AND POSSESSION OF LAND

7.1 Powers of acquisition

Articles 23 to 27 of the Order contain provisions for the compulsory acquisition of land and for the payment of compensation.

Article 23 (compulsory acquisition of land) follows article 18 of Schedule 1 of the DCO Model Provisions. It authorises the compulsory acquisition of land shown on the land

plan and described in the book of reference, so far as it is required for the authorised development, to facilitate it or is incidental to it.

The article further makes provision for the discharge or suspension of rights, trusts and incidents to which the

land was previously subject so far as their continuance would be inconsistent with the exercise of the powers under this Order. “Suspension” is not included in the

relevant DCO Model Provision but is included here to allow the undertaker to minimise private rights discharged where it is of the view that permanent discharge is not necessary. This is a more proportionate approach than article 18 of Schedule 1 of the DCO Model Provisions which would otherwise

“cleanse” the title of even those rights which the undertaker considers consistent with the authorised development.

Paragraph (3) of the article specifies that a person who suffers the loss of a private right of way under this article is entitled to compensation, a paragraph which

is repeated in article 37 of the Order, which creates a specific mechanism for the undertaker confirming that

there is no need for the extinguishment of certain private rights of way. These provisions both replicate articles 18(3) and 22(4) of Schedule 1 of the DCO

Model Provisions. Specific reference to “private rights of way” only in this article, duplicated in article 37, rather than to other private rights, mirrors articles

18(3) and 22(4) of Schedule 1 of the DCO Model Provisions. The DCO Model Provisions in turn mirror section 236 of the 1990 Act (extinguishment of rights

over land compulsorily acquired), which states as follows:

Page 41: Explanatory Memorandum (Rev D)

39

(1) Subject to the provisions of this section, upon the completion of a compulsory acquisition of land under

section 226, 228 or 230—

(a) all private rights of way […] on, under or over the land shall be extinguished […]

(4) Any person who suffers loss by the extinguishment of a right […] under this section [i.e. a right of way

over land] shall be entitled to compensation from the acquiring authority.”

In other words, the equivalent articles 18 and 37 from

the DCO Model Provisions imitate the elements of section 236 which extinguish private rights of way and clarify that compensation in certain circumstances may

be available for the extinguishment of that particular species of private right. Following legal analysis, it is not clear why the DCO Model Provisions duplicate

these elements in both their articles 18 and 37 but the undertaker has no objection to following the tendentious approach of the DCO Model Provisions in

this regard, which supplement rather than replace the compensation code in this instance. However, as per section 236, it is not necessary or appropriate to

extend reference to compensation for other private rights: any person from whom an estate or interest in

land is acquired compulsorily, i.e. who has a compensatable interest, has a right to a claim in compensation under longstanding heads of claim.

Nevertheless, it is an established principle of the compensation code that this right is not expressly stated in any statute: a large and complex body of

case law relates to it and seeking to set out such a general right in shorthand here would be unprecedented, unhelpful and unnecessary.

For clarity on the face of the Order, paragraphs 4, 5 and 6 reflect subsections 135(1) and (2) of the 2008 Act: no interest in Crown land may be acquired

pursuant to the Order unless the appropriate Crown authority consents to the acquisition; moreover, the Order only applies to Crown land so far as the

appropriate Crown authority consents.

Article 24 (compulsory acquisition of rights) follows article 21 of

Schedule 1 of the DCO Model Provisions and would confer on the undertaker the power to acquire existing

Page 42: Explanatory Memorandum (Rev D)

40

rights or create new rights in the Order land as described in the book of reference.

Upon acquisition or vesting, land over which new rights are acquired is discharged from existing rights insofar as the existing rights are inconsistent with the

new rights.

A person who suffers the loss of a private right of way

under this article is entitled to compensation.

Paragraph (4) and Schedule 13 (modification of compensation and compulsory purchase enactments for creation of new rights) are not from the DCO Model Provisions but mirror the wording of article 27(3) and Schedule 11 of the Hinkley Point C (Nuclear Generating

Station) Order 2013. These impose modifications to the compulsory purchase and compensation provisions under general legislation. They do not affect the

entitlement to compensation, but generally ensure that the compensation procedure applies to the additional categories of acquisition covered by the Order – the

creation of new rights and the imposition of restrictive covenants in particular. This is a consequence of the extension of land acquisition powers to these

categories (done to allow lesser land interests to be acquired), and is commonplace in Transport and

Works Act orders and other compulsory purchase orders made by local authorities. For the purpose of section 126(2) of the Act, the relevant compensation

provisions are modified only to the extent necessary to ensure that they apply properly to the acquisition of rights, and not to affect the amount of compensation

to which landowners would be entitled.

Paragraph (6) provides clarity on the face of the Order to reflect sub-sections 135(1) and (2) of the 2008 Act:

no existing right in Crown land may be acquired or a new right created without the consent of the appropriate Crown authority.

Article 25 (acquisition of subsoil only) is based on article 24 of Schedule 1 of the DCO Model Provisions and would

authorise the undertaker to compulsorily acquire so much of, or such rights in, the subsoil of land referred to in article 23(1) instead of acquiring the whole.

Further, the article confirms that in taking such a subsoil interest, the undertaker would not be required

Page 43: Explanatory Memorandum (Rev D)

41

to acquire an interest in any remaining part of that land.

Article 26 (power to override easements and other rights) does not derive from the DCO Model Provisions but closely

mirrors section 237 of the Town and Country Planning Act 1990 (the “1990 Act”) in keeping with similar approaches at article 25 of the Hinkley Point C

(Nuclear Generating Station) Order 2013 and article 18 of the Rookery South (Resource Recovery Facility) Order 2011.

This article addresses the fact that it is not clear whether the reference to discharging “rights, trusts and incidents” in articles 23(2) (compulsory acquisition of land) and 24(2) (compulsory acquisition of rights) of the draft Order, taken from the DCO Model Provisions, includes the discharge of items listed in section 237,

namely easements, liberties, privileges, rights or advantages annexed to land and adversely affecting any other land, including any natural right to support

or restrictions as to the user of land resulting from a contract. In particular, this resolves the doubt over

the applicability of these provisions to restrictions on user.

This lack of clarity would not be a concern for a local

planning authority promoting compulsory purchase powers to facilitate a development because under section 237 it is entitled to carry out works on land

which it has acquired or appropriated for planning purposes, notwithstanding any interference with the items listed in that section. However, the undertaker in

this draft Order is not a local planning authority, so it is necessary to apply section 237 in an amended form appropriate to the proposed development.

Sections 120(3) and (4) and item 2 of part 1 of Schedule 5 of the 2008 Act confirm that the draft Order may make provision, such as that in this article,

relating to the compulsory suspension, extinguishment or interference with interests in or rights over land.

Moreover, this article is supplementary (under section 120(5)(d) of the 2008 Act) to articles 23 (compulsory acquisition of land) and 24 (compulsory acquisition of rights) of the draft Order and is necessary and expedient to give full effect to the development consent in article 4 (development consent etc. granted

Page 44: Explanatory Memorandum (Rev D)

42

by the Order) of the draft Order (as permitted by section 230(5)(c) of the 2008 Act).

Sub-paragraphs 26(1)(a) and (b) mirror section 237(1).

The definition of “authorised activity” in this article is

based on the list of activities in sections 237(1) and 237 (1A) of the 1990 Act but modified to be bespoke

to the authorised development and the draft Order and its powers: sub-paragraphs 2(a) and 2(b) specify such activities as being the erection, construction, carrying

out, maintenance, or operation of any part of the authorised development or the exercise of any power authorised by the Order. Sub-paragraph 2(c) clarifies

that “use of any land” includes the “temporary use of land”. This gives full effect to the powers under articles 28 (temporary use of land for carrying out the authorised development) and 29 (temporary use of land for maintaining the authorised development) of the Order, which ought to be capable of use without

constraint by the interests etc, rights or restrictions described in paragraph (3) of this article.

Article 26(3) reflects section 237(2) of the 1990 Act

but also applies to restrictions as to the user of land arising by virtue of contract.

No drafting is included to reflect section 237(3), because it may be necessary to alter the apparatus of statutory undertakers in accordance with the Order

and the relationship between the undertaker and statutory undertakers is provided for in the protective provisions included at Schedule 11 (protective provisions) of the Order.

Article 26(4) makes provision for compensation and is based on section 237(4) of the 1990 Act and

comments of the (now abolished) IPC in relation to the Rookery South (Resource Recovery Facility) Order 2011 in relation to removal of reference to the Land

Clauses Consolidation Act 1845.

Section 237(6) of the 1990 Act is not reflected in the article because the undertaker is not a local planning

authority and, as the promoter of the authorised development itself, it will not have an indemnity agreement from a promoter relating to compensation

liability.

Page 45: Explanatory Memorandum (Rev D)

43

Article 26(5) mirrors the wording of section 237(7) of the 1990 Act.

Article 27 (application of the Compulsory Purchase (Vesting Declarations) Act 1981) follows article 23 of the DCO

Model Provisions and would provide for the application, with modifications, of the Compulsory Purchase (Vesting Declarations) Act 1981 (in this paragraph the

“1981 Act”), which makes provision for vesting procedures for land subject to compulsory purchase.

Some wording has been added to this article to ensure

that the 1981 Act is applied properly to the undertaker and the draft Order. This is because article 23(1) of the DCO Model Provisions was drafted on the

assumption that the undertaker is a public authority under section 1(2) of the 1981 Act. However, as the undertaker is not a public authority, the additional

wording has been included to clarify that it is to constitute a public authority for the purposes of the 1981 Act, so that its vesting procedures would apply to

the Order.

It is noted that the draft Order does not contain an

express provision incorporating Part I of the Compulsory Purchase Act 1965. This is because section 125 of the 2008 Act already applies that Part to a

development consent order authorising the compulsory acquisition of land.

7.2 Temporary possession of land

Articles 28 to 29 of the Order contain provisions for the temporary possession of land for the purposes of or in connection with the authorised development.

Article 28 (temporary use of land for carrying out the authorised development) follows article 28 of Schedule 1 of the DCO Model Provisions and confers upon the undertaker a right to enter on and take possession of:

• land specified in Schedule 9 (land of which temporary possession may be taken) to carry out those elements of the authorised

development listed in that Schedule. This is the land tinted light grey or shown cross-

Page 46: Explanatory Memorandum (Rev D)

44

hatched on the land plans (Document Reference 4.3);

• any other Order land where no notice of entry has been served and no general vesting declaration made, i.e. where compulsory

acquisition powers have not yet been exercised. This is the land tinted dark grey on

the land plans (Document Reference 4.3).

This approach means that the undertaker may use temporary use powers to construct the authorised

development in the particular Order land described in paragraph 28(1)(a)(ii) and, following construction, once the exact location of the pipeline is known, the

undertaker may compulsorily acquire the 24.4 metre wide easement strip required for the ongoing use, access and maintenance of the pipeline.

This approach does not preclude the undertaker from instead both (i) exercising its compulsory acquisition powers pursuant to article 24 (compulsory acquisition of rights) to acquire the 24.4 metre wide easement strip for carrying out the authorised development (i.e. laying the pipeline) and at the same time (ii) pursuant

to temporary use powers also taking possession of land necessary for construction in the wider Order

limits described in paragraph 28(1)(a)(ii) outside of that easement strip. In this way, the minimum width of land possible will be burdened by the permanent rights

comprised in the easement strip. This is because, once the pipeline has been located in that 24.4 metre wide easement strip, the remaining land of which

possession was taken only temporarily for construction will be returned to its owners in accordance with this article without being subject to permanent rights.

The AGIs are likely to be subject to compulsory acquisition alone but circumstances may arise in which it is sensible to make provision for temporary

possession powers as well, so as not to burden any land with permanent rights where this can be avoided.

Both of the above alternatives allow flexibility for the

undertaker; at the same time, for landowners they allow the compulsory acquisition of land or rights to match the final location of the authorised

development, which in certain Work Nos., such as the

Page 47: Explanatory Memorandum (Rev D)

45

pipeline, will not extend to the full width of the limits of deviation, whilst allowing land necessary for

carrying out the authorised development to be returned to its owners after only temporary use.

Separately, land listed in paragraph 28(1)(a)(i), by way

of a Schedule in the Order, i.e. the land tinted light grey or shown cross-hatched on the land plans

(Document Reference 4.3), relates to areas where there are to be no permanent works remaining following construction and temporary use is necessary

for the duration of construction only, with no subsequent permanent rights or land to be taken compulsorily (although protective works and surveys, it

is clarified, can still be carried out on that land pursuant to articles 20 (protective work to buildings) and 21 (authority to survey and investigate the land).

Use of the two paragraphs 28(1)(a)(i) and (ii) is a slightly different drafting approach to the Model DCO Provisions but has the same effect: it simply means

that it is not necessary to schedule out in Schedule 9 (land of which temporary possession may be taken) all plots set out in the book of reference but only those

where no permanent rights or land are subsequently to be taken. This approach also allows the undertaker to

provide clarity to the owners of paragraph 28(1)(a)(i) plots that the proposals affect their land only in terms of temporary use and not the compulsory acquisition of rights over land or of land itself. Separately, the owners of paragraph 28(1)(a)(ii) plots know that the easement strip could be located on their land but other

than that 24.4m strip, possession rights for construction will be only temporary, pursuant to this article. This approach has previously been adopted at

article 23 of the Network Rail (Ipswich Chord) Order 2012, article 40 of the Able Marine Energy Park Development Consent Order 2014 and article 23 of the

Network Rail (Redditch Branch Enhancement) Order 2013.

Sub-paragraphs (1)(b), (c) and (d) further confer upon

the undertaker the right to remove any building and vegetation, construct temporary works and buildings and carry out any mitigation works specified in

Schedule 9 (land of which temporary possession may be taken).

Page 48: Explanatory Memorandum (Rev D)

46

Prior notice to owners and occupiers is required and the article makes further provision for restoring land

after temporary use and compensation.

The article clarifies at paragraph (3) that the undertaker may not (unless the landowners agree)

remain in possession:

• in relation to the land specified in Schedule 9

(land of which temporary possession may be taken), i.e. where no permanent land or rights are to be taken, for longer than one year after

the authorised development has been completed; or

• in relation to other Order land, i.e. where

permanent land or rights might be taken, for longer than one year after the authorised development has been completed, unless the

undertaker exercises compulsory acquisition powers over it by serving a notice of entry or making a general vesting declaration.

Paragraph (3) amends the DCO Model Provision equivalent so that the year runs from when the undertaker has certified that the entire Onshore

Scheme is first capable of being brought into operational use for the purpose for which it was

designed rather than from when the works on that land in isolation are complete. This is a critical amendment for a linear scheme such as a cross-

country pipeline where construction on any given element is not complete, potentially requiring testing, back-checks and further works (as necessary)

depending on construction matters arising further down the line, until the entire linear scheme can be considered to be complete. The undertaker is best

placed to certify such completion and, in practice, the compensation provision at paragraph 5 means that there can be confidence that undue delay in issuing

appropriate certificates would be minimised.

Paragraph 11 also clarifies that nothing in this article prevents the taking of possession more than once in

relation to land specified in Schedule 9 (land of which temporary possession may be taken).

Sub-paragraph 4(b) and (c) extend the DCO Model

Page 49: Explanatory Memorandum (Rev D)

47

Provisions to clarify that in restoring land, the undertaker does not have to restore areas where

permanent mitigation works listed in Schedule 9 (land of which temporary possession may be taken) remain and also cannot be required to remove ground

strengthening works.

Sub-paragraphs (8)(a) and (b) expand the DCO Model

Provisions to clarify that even though land listed in paragraph (1)(a)(i) cannot be acquired, nor can interests in it be acquired or created compulsorily, the

undertaker can still carry out protective works and surveys under other provisions of the Order.

The additions to this article may be included under

section 120(3) of the 2008 Act as they make important provision for the development for which consent is sought, namely in respect of rights required for its

construction.

Article 29 (temporary use of land for maintaining the authorised development) follows article 29 of Schedule 1 of the

DCO Model Provisions and provides that the undertaker may take temporary possession of land

within the Order limits reasonably required for the purpose of maintaining the authorised development and constructing such temporary works and buildings

on the land as may be reasonably necessary.

Sub-paragraph 1(b) of the article extends article 29 of the DCO Model Provisions to include a right to enter on

any land within the Order limits for the purpose of gaining access where this is reasonably required to maintain the authorised development. This

supplemental provision clarifies that the undertaker can secure appropriate access within the Order limits to those parts of the authorised development which

need to be maintained, giving full effect to the maintenance powers granted under sub-paragraph (1)(a).

This article is subject to safeguards:

• The above powers may only be exercised

during the “maintenance period”. As per article 29(12) of Schedule 1 of the DCO Model Provisions this is 5 years but this runs from

the date on which the entire authorised development is first brought into operational

Page 50: Explanatory Memorandum (Rev D)

48

use for the purpose for which it was designed rather than the completion of only a part of it.

This amendment to the DCO Model Provision equivalent is critical for a linear scheme such as a cross-country pipeline where the

maintenance period cannot be allowed to run in a “rolling” set of consecutive dates when

the scheme must be treated as an interacting whole, with issues (if any) in one location potentially requiring attention further down

the line on sections completed earlier;

• Provision is made for notice, restoration and compensation;

• The undertaker must give 28 days’ notice before entering on and taking temporary possession of land for the purposes of

maintenance, except where there is an identified potential risk to the safety of the authorised development, the public or the

surrounding environment (in which case such notice, if any, as is reasonably practicable should be given).

7.3 Compensation

Articles 30 to 32 of the Order contain provisions clarifying existing

principles of compensation in relation to the compulsory acquisition and temporary possession of land in connection with the authorised development.

Article 30 (disregard of certain interests and improvements) is not contained in the DCO Model Provisions but follows

article 26 of Schedule 1 of the TWA Model Provisions.

It would provide for disregarding certain interests in

and enhancements to the value of land for the purposes of assessing compensation with respect to its compulsory acquisition, where the creation of the

interest or the making of the enhancement was designed with a view to obtaining compensation or increased compensation.

It complies with section 126 (Compensation for compulsory acquisition) of the 2008 Act as it does not have the effect of modifying or excluding the

Page 51: Explanatory Memorandum (Rev D)

49

application of an existing provision relating to compulsory purchase compensation.

The wording of this article mirrors section 4 (Assessment of compensation) of the Acquisition of Land Act 1981 (in this paragraph the “1981 Act”). It

is necessary to specifically apply the effect of section 4 of the 1981 Act in the draft Order. This is because the

1981 Act only applies to a compulsory purchase to which any other statutory instrument has applied its provisions section 1 (application of Act)) and neither

the 2008 Act nor the DCO Model Provisions apply section 1 of the 1981 Act to the draft Order.

Sections 120(3) and 120(5)(a) and item 36 of part 1 of

Schedule 5 allow the application in an Order of statutory provisions which relate to the payment of compensation.

Article 31 (set-off for enhancement in value of retained land) is not contained in the DCO Model Provisions but follows article 27 of Schedule 1 of the TWA Model Provisions.

It would provide that in assessing the compensation payable to any person in respect of the acquisition of

any land, the Lands Chamber of the Upper Tribunal shall set off against the value of the acquired land any increase in value of any contiguous or adjacent land

belonging to that person arising out of construction of the authorised development.

These provisions comply with section 126(2) of the

2008 Act. This is because it does not have the effect of modifying the application of an existing provision relating to compulsory purchase compensation. The

principle in this article is established in section 7 of the Land Compensation Act 1961 (effect of certain actual or prospective development of adjacent land in same ownership), which needs to be applied. Sections 120(3) and 5(a) and item 36 of part 1 of Schedule 5 allow the application in an Order of statutory

provisions which relate to the payment of compensation.

Article 32 (no double recovery) is not contained in the DCO Model Provisions but predominantly follows article 44 of the TWA Model Provisions.

It provides that compensation is not payable both

Page 52: Explanatory Memorandum (Rev D)

50

under this Order and other compensation regimes for the same loss or damage.

In addition, this article provides that there is to be no double recovery under two or more different provisions of this Order, precedence for which can be found in

numerous TWA Orders.

The principle of equivalence, namely that a claimant in

a compulsory purchase matter shall be compensated for no more and no less than his loss, is long established and no part of the compensation code

conflicts with this principle.

Accordingly, this article complies with section 126(2) of the 1990 Act and is a supplementary provision under

section 120(5)(d) of the 2008 Act as well as a provision relating to the payment of compensation under sections 120(3) and (4) and item 36 of Part 1 of

Schedule 5 of the 2008 Act.

7.4 Supplementary

Articles 33 to 40 of the Order contain supplementary provisions

relating to the compulsory acquisition provisions in Part III of the Order.

Article 33

(acquisition of part of certain properties) follows article 26 of Schedule 1 of the DCO Model Provisions, replaces

section 8(1) of the Compulsory Purchase Act 1965 and would enable the undertaker to acquire a part rather than the whole of properties subject to compulsory acquisition.

Further, it contains a procedure enabling the relevant owner to require the whole to be taken, in certain circumstances, with disputes to be determined by the

Lands Chamber of the Upper Tribunal.

Article

34

(statutory undertakers) is based on article 31 of Schedule 1

to the DCO Model Provisions. It authorises the undertaker to (1) compulsorily acquire land belonging to statutory undertakers shown on the land plans, (2) remove or

reposition any statutory undertakers’ apparatus, where it is anywhere within the Order limits and (3) acquire compulsorily new rights over land belonging to statutory

undertakers.

Page 53: Explanatory Memorandum (Rev D)

51

Sections 120(3) and (4) together with item 14 of part 1 of Schedule 5 of the 2008 Act allow particular provision

relating to the removal, disposal or re-siting of apparatus.

Article

35

(recovery of costs of new connections) follows article 33 of

Schedule 1 of the DCO Model Provisions and would provide for an owner or occupier of premises to recover from the undertaker the costs of reconnecting to public

utilities/communications services if these are removed pursuant to article 34 of the Order (statutory undertakers).

Article

36

(time limit for exercise of authority to acquire land compulsorily) follows article 20 of Schedule 1 of the DCO Model Provisions and would impose a time limit of eight years from the Order coming into force for the exercise of

the proposed powers of acquisition and temporary possession. Sections 154(3) and (4) of the 2008 Act and

regulation 3 of the Infrastructure Planning (Miscellaneous Prescribed Provisions) Regulations 2010 allow the Order to prescribe a period longer than five years for exercise of

such powers. Eight years is considered to be necessary in respect of the Order for the reasons set out in the statement of reasons (Document Reference 4.1) which

accompanies the application for the Onshore Scheme.

Article 37

(private rights of way) follows article 22 of Schedule 1 of the DCO Model Provisions and enables extinguishment of

private rights of way over land subject to compulsory acquisition under the Order.

Private rights of way over land of which the undertaker

takes temporary possession are suspended and unenforceable for as long as the undertaker remains in

lawful possession of the land. There is no need to amend this article from the DCO Model Provisions to refer to other types of private right as these are addressed in articles

23(2) and 24(2).

This provision can be disapplied by a notice from the undertaker or by agreement with the owner of the right of

way.

It also makes provision for persons suffering loss as a result of the suspension or extinguishment of such private rights

of way to be entitled to compensation.

It is important to note that there are key differences in purpose between Articles 37 and Articles 23(2) and 24(2):

Page 54: Explanatory Memorandum (Rev D)

52

• Article 37(3) specifies that private rights of way over land of which National Grid takes temporary possession under Articles 28 and 29 are suspended and unenforceable for as long as National Grid remains in lawful possession of the land; Articles

23(2) and 24(2), however, do not deal with temporary possession, only the permanent

acquisition of land.

• Separately, Article 37 is intended to provide a useful mechanism for reducing the interference

with private rights of way of landowners (likely to be the most prevalent private rights along a long, rural, linear route) where compulsory acquisition

has had to be used:

• Article 23(2), for example, extinguishes rights where they are “inconsistent with the exercise of powers under [the Order]”. This would be a question to be assessed objectively on the facts in each case.

• Article 37, however, allows the undertaker (by way of notice) to clarify to a person with the benefit of particular right of way

that, so far as its engineers are concerned, i.e. a subjective judgment in favour of that

person, the right is not inconsistent with its powers under the Order and the person may continue to use it. In other words, this

assist persons with the benefit of private rights of way.

The value of the article, for the reasons given above, has

been recognised by the Secretary of State by its inclusion in the following made Orders:

• Article 28 (Private rights of way) of the Hinkley

Point C (Nuclear Generating Station) Order 2013;

• Article 46 (Private rights of way) of the Thames

Water Utilities Limited (Thames Tideway Tunnel)

Order 2014.

Article 38

(rights under or over streets) follows article 27 of Schedule 1 of the DCO Model Provisions and provides that the

undertaker may use the subsoil under and airspace over a street required for the authorised development without

Page 55: Explanatory Memorandum (Rev D)

53

being required to acquire any part of the street or any easement or right in the street.

Provision is made for compensation.

Article

39

(incorporation of the mineral code) is derived from article

19 of the DCO Model Provisions. Part 2 of Schedule 2 of the Acquisition of Land Act 1981 (in this paragraph the “1981 Act”) would be incorporated into the Order to provide that

the undertaker would not be entitled to any mines of coal, ironstone, slate and other minerals under the land acquired under the draft Order unless they have been expressly

purchased, apart from minerals necessarily extracted or used in the construction of the authorised development. Part 3 of Schedule 2 of the 1981 Act regulates the

relationship between the owner of the mines which lie below the land taken for the authorised development and the undertaker.

Article 40

(open space) Under section 132 of the 2008 Act, an order granting development consent is subject to special

parliamentary procedure to the extent that it authorises the compulsory acquisition of a right over land, forming part of, amongst other things, open space, unless:

• the Secretary of State is satisfied that certain statutory criteria under that section apply; and

• his satisfaction and the relevant subsection are

recorded in the Order.

Land referencing commissioned in connection with the Onshore Application has identified that there are potentially

three plots listed in the book of reference (Document Reference 4.3) accompanying the application for the Onshore Scheme which constitute open space and in

respect of which the Order authorises the compulsory acquisition of rights. These are Plots 232, 233 and 268.

The letter from Berwin Leighton Paisner LLP on behalf of the undertaker dated June 2014 to the Secretary of State, care of the National Planning Casework Unit, contains an

application setting out the subsection of section 132 which the undertaker submits apply to these Plots, with supporting information for this view.

If the Secretary of State concurs with the undertaker’s submissions in that letter, he is invited pursuant to section 132 to record his satisfaction and the relevant subsection in

Page 56: Explanatory Memorandum (Rev D)

54

the form proposed in Schedule 8 (record of the satisfaction of the Secretary of State pursuant to section 132 of the 2008 Act) of the Order.

8 PART IV OF THE ORDER - MISCELLANEOUS AND GENERAL

Articles 41 to 54 of the Order contain a number of miscellaneous and general provisions.

Article 41 (application of landlord and tenant law) follows article 35 of Schedule 1 to the DCO Model Provisions and would override the application of landlord and tenant

law in so far as it may prejudice the operation of any agreement for leasing the whole or part of the authorised development or the right to operate the

same and any agreement for the construction, maintenance, use or operation of the authorised

development or any part of it entered into by the undertaker.

Article 42 (deemed consent under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009) does not make reference to deemed consent under section 34 of the Coast Protection Act 1949 as per article 37 of

Schedule 1 of the DCO Model Provisions. This is because that provision has been repealed by the Marine and Coastal Access Act 2009 (the “2009 Act”).

Section 149A of the 2008 Act allows provision in a development consent order for a deemed marine licence under the 2009 Act.

Accordingly, this article would constitute deemed consent under section 65 of the 2009 Act, the

successor provision to section 34 of the Coast Protection Act 1949.

Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009) sets out the terms on which the deemed licence would be granted by the Secretary of State.

The Marine Management Organisation has reviewed the form of licence and discussions between it and the undertaker in respect of the application are ongoing.

The terms of the licence are explained more particularly below in this explanatory memorandum where Schedule 10 is explained.

Page 57: Explanatory Memorandum (Rev D)

55

For information, an overlay of the deemed marine licence coordinates over the relevant works plans with

drawing number 10-2574-GND-01-05-0056 Rev A accompanies the Onshore Scheme application (Document Reference 2.7).

Article 43 (operational land for the purposes of the 1990 Act) follows article 36 of Schedule 1 of the DCO Model

Provisions and provides that, for the purposes of section 264(3)(a) of the 1990 Act, the development consent granted by the Order is to be treated as

specific planning permission.

Article 44 (felling or lopping of trees or shrubs) follows article 39 of Schedule 1 of the DCO Model Provisions (save in

relation to hedgerows). It would enable the undertaker to fell or lop trees and shrubs for the purposes of

preventing obstruction or interference with the authorised development and danger to people constructing, maintaining, operating or using the

authorised development. In the case of unnecessary damage, provision is included for the payment of compensation for loss or damage.

Reference to “passengers” at sub-paragraph (1)(b) of the equivalent DCO Model Provision has been removed as this is not relevant to the authorised development.

This article departs from the DCO Model Provisions in that paragraphs (3) to (6) remove the need to obtain a hedgerow licence under the Hedgerow Regulations

1997. The removal of hedgerows shown on the hedgerow plans (listed in Part 5 of Schedule 2 (plans) and given Document Reference 2.5) is instead to be

consented in this article or, should the removal of any hedgerows other than those shown on the hedgerow

plans be required (if any), consent from the local planning authority will be needed. This is similar to the approach taken at article 15 of the Brechfa Forest

West Wind Farm Order 2013. Section 120(5)(a) of the 2008 Act enables a DCO to exclude a statutory provision which relates to any matter for which

provision may be made in the Order. Sections 120(3) and (4) together with item 15 of Part 1 of Schedule 5 of the 2008 Act allow a DCO to make a provision for

carrying out civil engineering or other works. The authorised development, a civil engineering work, will

Page 58: Explanatory Memorandum (Rev D)

56

necessitate the removal of hedgerows, particularly for the laying of the pipeline. Accordingly, the Hedgerow

Regulations 1997 are excluded under the Order.

Article 45 (trees subject to tree preservation orders) departs

from article 40 of Schedule 1 of the DCO Model Provisions in that the undertaker has assessed the Order limits and determined that no trees subject to an

existing tree preservation order will be adversely affected by the carrying out of the authorised development. However, the undertaker considers that

it would be prudent and sensible to include a provision allowing it to fell or lop any tree, or cut back its roots, which has been made the subject of a tree

preservation order since the date of its application for development consent. This power will only be exercisable where the undertaker reasonably believes

it to be necessary to prevent obstruction or interference with the construction, maintenance or operation of the authorised development or to prevent

a danger to people constructing, maintaining, operating or using the authorised development.

The permission granted by the article would constitute a deemed consent under a tree preservation order.

Article 46 (resumption of land use following certain works) is

derived from article 10 of the Hinkley Point C (Nuclear Generating Station) Order 2013. It is intended for the protection of landowners so that after their land has

been used under temporary possession powers for office accommodation and pipe stores, for example, irrespective of the duration of that use, it will be clear

that they do not need planning permission to resume a use which predated the making of this Order. This is

done by appropriately applying section 57(2) of the Town and Country Planning Act 1990 - this clarifies that where planning permission is granted for a limited

period, once it expires, permission is not needed for the original use.

Article 47 (application of the Community Infrastructure Levy) provides that the Order is to be treated for the purposes of the Community Infrastructure Levy Regulations 2010 as a planning permission granted for

a temporary period. The community infrastructure levy (CIL) is not chargeable on temporary planning permissions, so this would have the effect of excluding

Page 59: Explanatory Memorandum (Rev D)

57

the authorised development from the CIL charging provisions. Similar provision was made in article 11 of

the Hinkley Point C (Nuclear Generating Station) Order 2013.

Article 48 (protective provisions) gives effect to Schedule 11 (protective provisions) which would contain specific safeguards for statutory undertakers within the Order

limits.

Article 49 (certification of plans etc) follows article 41 of Schedule 1 of the DCO Model Provisions and would

require the undertaker to submit copies of key documents referred to in the Order to the Secretary of State for certification as true copies following the

making of the Order.

Article 50 (service of notices) would make provision as to the

manner in which notices or other documents required or authorised to be served under the Order are to be served.

The article mirrors section 229 of the 2008 Act (which applies only to notices under that Act rather than under an Order made under it) and its inclusion is

permitted as an incidental provision under section 120(5)(d) of the 2008 Act.

Article 51 (arbitration) follows article 42 of Schedule 1 of the DCO Model Provisions and would make provision for differences or disputes arising under any provision of

the Order to be settled by arbitration.

Additional wording is included to exclude differences or disputes referred to the Lands Chamber of the Upper

Tribunal (because that is the appropriate forum for disputes relating to the compensation relating to the compulsory acquisition of land and rights etc.) and

allows parties to agree to methods of dispute resolution other than arbitration.

There is significant precedence for such additional

wording in TWA Orders and has been accepted in recent development consent orders, including at article 42 of The Lancashire County Council (Torrisholme to

the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013. Sections 120(3) and (4) together with item 37 of part 1 of Schedule 5 of the 2008 Act

also permit the inclusion of provisions relating to the

Page 60: Explanatory Memorandum (Rev D)

58

submission of disputes to arbitration.

Further, the DCO Model Provision equivalent has been

amended so that if the parties fail to agree on an arbitrator, one will be appointed by the Secretary of State rather than the Institute of Civil Engineers. This

approach was proposed by PINS and was followed at article 34 of the National Grid (King’s Lynn B Power

Station Connection) Order 2013.

Article 52 (requirements) introduces Schedule 3 (requirements) which contains requirements corresponding to

conditions which, under section 120(2) of the 2008 Act, could have been imposed on the grant of planning permission for the authorised development had it not

fallen within the 2008 Act planning regime.

Such requirements may be imposed in the Order under section 120(1) of the 2008 Act.

Paragraph (2) has been added to the article as part of the mechanism within the Order of dividing the authorised development between those parts subject

to the Requirements in Schedule 3 (requirements), with the local planning authorities as the appropriate

approving bodies, and those parts subject to the deemed marine licence conditions in Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009) with the MMO as the appropriate approving body.

Paragraph (2) therefore clarifies that the Requirements

at Schedule 3 (requirements) will not apply to parts of the authorised development which fall within the UK marine area (apart from the listed exceptions, which

should apply across all the Work Nos. irrespective of whether they fall within the UK marine area or otherwise). This is because, for the most part, it is

appropriate for areas submerged at mean high water springs that the authorised development should be governed only by the licence conditions attached to

the marine licence at Part 2 of Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009), so as to avoid inconsistency with the Requirements.

Article 53 (procedure in relation to certain approvals etc.) gives

effect to Schedule 14 (procedure in relation to certain approvals etc.) which is not derived from the DCO

Page 61: Explanatory Memorandum (Rev D)

59

Model Provisions but follows the wording of article 46 and Schedule 14 of the Hinkley Point C (Nuclear

Generating Station) Order 2013.

The Schedule sets out procedures for determinations made by the relevant discharging authority pursuant

to:

• the Requirements set out in Schedule 3

(requirements);

• the deemed marine licence conditions in Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009);

• consent from the relevant planning authority

in respect of the removal of hedges not set out on the hedgerow plan (if required) pursuant to article 44;

• provisions in the Order requiring the consent of the highway authority in respect of street works (including pursuant to consents under

the incorporated provisions of the 1991 Act), the alteration of layout of streets, the construction and maintenance of streets, the

temporary and permanent stopping up of streets, traffic regulation or where consent is

required for surveying land comprised of highway;

• the issuing of notices and consents under the

Control of Pollution Act 1974 (“COPA”); and

• the following byelaws:

• the Selby Area Internal Drainage Board

Byelaws 1999;

• the Beverley and North Holderness Internal Drainage Board Byelaws 2012;

• the Ouse and Humber Internal Drainage Board Land Drainage Byelaws; and

• those made by East Riding of Yorkshire Council in its capacity as lead local flood authority.

Page 62: Explanatory Memorandum (Rev D)

60

Paragraph (1) of the Schedule sets out timescales for determinations. These mirror those in article 29(2)(b)

(time periods for decision) of the Town and Country Planning (Development Management Procedure) (England) Order 2010, namely 8 weeks, other than in

respect of COPA applications, which mirror the 28 days in section 62 of COPA. Reasonable timescales for

requests for information are also addressed.

Paragraph (2) of the Schedule sets out the fee to be paid in relation to the discharge of Requirements, as

no provision is made in existing legislation – the fee follows the equivalent charge for conditions attached to planning permissions in the Town and Country

Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012. Scope is provided for the fee to increase in line with

amendments to those Regulations over time pursuant to sections 303 (fees for planning applications etc.) and 333(2A) (regulations and orders) of the 1990 Act.

Fees for other consents to which this Schedule relates are provided for directly in existing legislation, unlike Requirements pursuant to a development consent

order.

Paragraph (3) of the Schedule sets out an appeal

procedure to the Secretary of State which may be exercised in circumstances which mirror the wording of sub-sections 78(1) and (2) of the 1990 Act (right to appeal against planning decisions and failure to take such decisions), extended to:

• where the undertaker does not agree that

requests for information are reasonable:

• deemed marine licence conditions (which are, as described in this explanatory

memorandum, simply terms of the Order in the same way as Requirements, are the only difference being that the Secretary of State

has designated a specialist discharging authority different to the relevant planning authority, namely the MMO, because of its

particular marine expertise);

• if a notice further to section 60 of COPA is issued; and

Page 63: Explanatory Memorandum (Rev D)

61

• the three sets of internal drainage byelaws referred to above. Although the byelaws

contain a dispute resolution procedure before the Secretary of State, it is only open to local authorities and relates only to some of the

byelaws in each set.

The process for appeals in sub-paragraph 3(2) of the

Schedule is broadly similar to the Town and Country Planning (Appeals) (Written Representations Procedure) (England) Regulations 2009, save that

timescales are shorter proportionate to the need for expedition for nationally significant infrastructure projects and to the fact that appeals would not relate

to entire applications for planning permission but to narrower consents.

The DCO Model Provisions provide for items required

under requirements to be submitted to the former IPC for approval. However, CLG Guidance for local authorities states that a draft Order can allow scheme

promoters to appeal local authority decisions on a subsequent approval as with previous regimes. Indeed, it is now common practice for such an article

to be included in Orders made under the 2008 Act: in addition to the Hinkley Point C (Nuclear Generating

Station) Order 2013, this approach was accepted in the Rookery South (Resource Recovery Facility) Order 2011, Network Rail (Ipswich Chord) Order 2012 and

the Network Rail (North Doncaster Chord) Order 2012; and Schedule 16 may be included in the draft Order as a supplementary provision under section 120(5)(d) of

the 2008 Act.

Article 54 (Saving for Trinity House) Trinity House requested this provision, which confirms that nothing in the Order

prejudices the rights, duties or privileges of Trinity House, which provides aids to navigation.

9 SCHEDULES

Schedules 1 to 14 of the Order contain information referred to in the articles of the Order.

Schedule 1 (authorised development) lists out the particular Work Nos. comprised in the authorised development for

Page 64: Explanatory Memorandum (Rev D)

62

which development consent is sought and which are to be read alongside the works plans. See paragraphs

3.1 to 3.5.14 above for further explanation.

Schedule 2 (plans) lists the works plans (Part 1), land plans (Part

2), access plans (Part 3), hedgerow plans (Part 5) and other plans submitted for approval (including plans where only certain parts are for approval) (Part 4). It

also lists parameters (Part 6) for the purposes of any future applications made for certain further approvals pursuant to Requirement 3 of Schedule 3

(requirements) as well as a list of planting drawings (Part 7) for the purposes of excluding these from such applications.

Other indicative and illustrative plans will be provided as part of the application.

This approach to scheduling plans in a Schedule rather

than in the Requirements themselves has precedence in Part 2 of Schedule 1 of the Hinkley Point C (Nuclear Generating Station) Order 2013.

Schedule 3 (requirements) contains requirements corresponding to conditions which, under section 120(2) of the 2008

Act, could have been imposed on the grant of planning permission for the authorised development had it not fallen within the 2008 Act regime. Such requirements

may be imposed in the Order under section 120(1) of the 2008 Act.

The Requirements in Schedule 3 are based on the

Requirements set out in Schedule 4 of the DCO Model Provisions, but these have been modified as appropriate for the Onshore Scheme and following

dialogue with the relevant planning, highways and marine authorities.

Appropriate Requirements in this Schedule have been amended to make a further body (such as the Environment Agency ("EA"), Natural England (“NE”) or

the local highway authority) a consultee in the approval process set out in the relevant Requirement.

A number of DCO Model Provisions Requirements have

not been included in Schedule 3 because the proposed development will not produce the kinds of effects which those Requirements seek to control. For

example, it was not necessary to include Requirement

Page 65: Explanatory Memorandum (Rev D)

63

31 (Control of insects) from the DCO Model Provisions because the authorised development is not in a

location, or of a nature, where there is a real risk of infestation or emanation of insects. Similarly, Requirement 29 (Control of smoke emissions) from the

DCO Model Provisions is not necessary because construction of the authorised development will not

result in smoke emissions. Other Model Provisions have been amended to make them applicable to the nature of the authorised development (i.e. a cross-

country linear construction project). Several have been combined.

An explanation of the Requirements in their current

form can be found below. Reference to a Requirement in the DCO Model Provisions means the corresponding paragraph at Schedule 4 of those provisions.

Requirement 1 (Interpretation) sets out the meaning of words and phrases used in this Schedule which are in addition to the terms defined within the main body

of the Order. Some definitions additional to those found in Requirement 1 of the DCO Model Provisions are necessary to define elements particular to the

Project such as “AGIs”, “Area B” and “Construction Compounds”. It is also sensible to include a definition

of “commence”/”commencement” of the authorised development for clarity on the triggers of discharge, which is common in development consent orders made

by the Secretary of State, including, to give one example, paragraph 1(1) of Schedule 2 of the Hinkley Point C (Nuclear Generating Station) Order 2012. The

Order, however, does not use a single definition of “commence” but instead three separate definitions (namely “commence (type 1)”, “commence (type 2)”

and “commence (type 3)”). These are to reflect that certain works with significant environmental effects should not take place prior to Requirements being

discharged which are themselves intended to address those particular effects. In summary:

• the first one is where there is no link between

the Requirement and the commencement in terms of the potential for likely significant

effects, i.e. all pre-commencement works can take place without there being any risk of an associated significant environmental effect

occurring;

Page 66: Explanatory Memorandum (Rev D)

64

• the second is where no pre-commencement

work can take place, e.g. in respect of European protected species, the Barmston Pumping Station design and trees and

hedgerows;

• the third type of commencement is one that is

a “middle ground”. There are some specified activities that the undertaker would be able to carry out before a particular Requirement is

discharged, as there is no relationship between the activity and the Requirement, but not other specified activities as those could

lead to significant environmental effects occurring.

The undertaker considers that this tiered approach

avoids exactly the possibility that potentially significant works could be carried out before the relevant

mitigation measures contained in the relevant Requirements are in place. The undertaker does not consider it “necessary” or “reasonable in all respects”,

for the purposes of paragraph 4.1.7 of EN-1, for works to be prevented before discharge of particular Requirements when those works would not give rise to

any significant environmental effects prior to the discharge of those particular Requirements.

It is important to bear in mind that the statutory

definition in section 155 of the 2008 Act defines when development is considered to have begun, i.e. the “earliest date on which any material operation

comprised in, or carried out for the purposes of, the development begins to be carried out” for the purposes of stipulating when development consent will expire if it has not been so “begun”, i.e. implemented, rather than for any purpose associated with the proper

securing of environmental mitigation. Whilst the tiered approach described above in this Order uses this definition as one of the types of commencement, and

as a starting point for the other two, there is no requirement for it to apply across all of the Requirements provided that appropriate environmental

mitigation is secured in each Requirement, as is the case here.

By way of example, paragraph 1(5) of Schedule 3

Page 67: Explanatory Memorandum (Rev D)

65

(requirements) of the Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 clarifies that

where there are different sites, commencement before particular Requirements specific to a site mean only commencement on that site, i.e. in the context of a

long, linear project, works unrelated to a particular Requirement are not to be delayed by discharge of

that Requirement.

Separately, the undertaker has agreed to include Requirement 1(2) at the request of North Yorkshire

County Council, creating a statutory requirement on Selby District Council to consult it on certain Requirements.

Requirement 2 (Time limits) sets out a time limit within which the authorised development must be begun within five years of the Order being made, the

period provided in regulation 3 of the Infrastructure Planning (Miscellaneous Prescribed Provisions) Regulations 2010, and follows Requirement 2 of the

DCO Model Provisions. Justification for this period is further set out in section 5 of the Statement of Reasons (Document Reference 4.1).

Requirement 3 (Approved details) requires the authorised development to be carried out in

accordance with the approved details.

The approved details would either be the approved plans listed in Part 4 (approved plans) of Schedule 2

(plans), or revised versions of those plans.

If the undertaker wished to implement in accordance with revised plans, three criteria would then need to

be met:

• Firstly, the relevant local planning authority would need to approve any revision;

• Secondly, any revised details would need to remain within certain parameters set by the DCO to reflect what has been assumed for the

purposes of assessment. These are specified in Part 6 (parameters) of Schedule 2 (approved plans). Part 6 sets out tables for

the Drax Pig Trap, Camblesforth Multi-Junction (but not Area B – see below), Tollingham Block Valve, Dalton Block Valve

Page 68: Explanatory Memorandum (Rev D)

66

and Skerne Block Valve. Each table:

• groups together the relevant

parameters from the planning arrangement, elevation and operational site drawings for the AGI in question;

• provides in paragraph (a) a single height restriction for development

within the weld mesh security fence; and

• sets out in paragraph (b), and in two

columns below it, the maximum heights which particular elements within the AGIs cannot exceed.

(Note that not all “approved plans” listed in Part 4 (approved plans) of Schedule 2 (plans) are referenced in

Part 6 (parameters). These include, for example, the site location and highways access drawings for the AGIs.

This is because those drawings do not set parameters, for the purposes of the environmental statement, within which

AGI development must take place). The planting drawings are also not

referenced in Part 6 (parameters) as they are not to be part of the mechanism for approvals to changes to

approved plans in Requirement 3(1). This is clarified in Requirement 3(2);

• Thirdly, the relevant local planning authority

would need to be satisfied that the revisions would not give rise to any materially new or materially different significant environmental

effects.

Note that Requirement 3(1) clarifies that the above is separate to Requirements 5 (Barmston Pumping Station) and 6 (Camblesforth Multi-junction). Those Requirements contain bespoke provisions for reserved matters approvals for the Barmston Pumping Station

and Area B of the Camblesforth Multi-junction in accordance with their own parameter plans, where detailed design is to follow at the appropriate later

stage (for the reasons set out in this Explanatory

Page 69: Explanatory Memorandum (Rev D)

67

Memorandum in relation to those Requirements), rather than, as in Requirement 3(1), where there are

detailed design drawings but some minor details may be subject to later approval where it is necessary to capture any advances in technology.

The need for this small but essential element of flexibility arises for the following reasons:

• The proposed development may not be commenced for some years;

• The front end engineering and design process

has not been concluded, contractors have not been taken on and materials have not been ordered;

• There is potential for some minor details to change as a result of the relatively new CCS technology and continued innovations in it,

including in the layout within AGIs;

• This is recognised in EN-1, which explains that “there is a high level of confidence that the

technology involved in CCS will be effective” (paragraph 4.7.8) and that the demonstration projects such as the authorised development

are a “priority for UK energy policy” (paragraph 3.6.5) but that CCS is “an

emerging technology” (paragraph 4.7.1) and “at a relatively early stage of development” (paragraph 4.7.6);

• Some examples of minor changes currently envisaged as possible include, as a result of the availability of certain specified materials at

the time of construction and the technical design of equipment such as valve seals, flange seals, axillary pipework, vents, pressure

points, valve actuators and electronic equipment, which might need to be subject to minor modification prior to construction. The

point of the proposed mechanism in this Requirement, however, is to capture potential for currently unknown innovations, which will

be essential to the operation of the authorised development but cannot be definitively listed at this stage;

Page 70: Explanatory Memorandum (Rev D)

68

• The changes are not considered likely, realistically, to generate any controversy, or

make any difference to the potential for likely significant environmental effects;

• The principle is not new. Although more minor

and different technically for the authorised development, this is a planning point broadly

analogous to an element of The Hinkley Point C (Nuclear Generating Station) Order 2013 (“Hinkley Point C DCO”): there, the DCO

was being promoted during a period in which a global reappraisal of appropriate safety mechanisms in new nuclear power stations

had not yet been concluded. EDF therefore submitted detailed drawings for approval, and also parameters. This was to allow EDF to

submit revised details in due course if needed, but any such revised details had to be within those parameters (see Requirement PW3 in

the Hinkley Point C DCO (page 76)).

Separately, the undertaker notes as follows:

• The mechanism in Requirement 3 relates only

to changes to the “approved plans”, which show the above ground installations (“AGIs”)

at the Drax Pig Trap, Camblesforth Multi-Junction (but not Area B), Tollingham Block Valve, Dalton Block Valve and Skerne Block

Valve. They do not show the below ground cross-country pipeline, i.e. the NSIP for the purposes of sections 14(1)(g) and 21 of the

Planning Act 2008;

• The cross-country pipeline is governed separately to Requirement 3, as is standard,

by limits of deviation pursuant to Article 5 (Limits of deviation) shown on the works plans;

• The proposed mechanism in Requirement 3 accords with the advice in paragraph 19.4 of PINS’s “Advice note fifteen: Drafting

Development Consent Orders”, which stipulates that “the tailpiece (or other wording) should not allow the LPA to approve

details which stray outside the parameters set

Page 71: Explanatory Memorandum (Rev D)

69

for the development as part of the examination process and subsequent approval

of the Secretary of State.”;

• There is no objection from the local planning authorities in relation to both the proposed

AGI design or the principles for the proposed Requirement 3. The AGIs are a relatively small

part of the circa 67km cross-country pipeline.

Requirement 4 (Stages of authorised development) sets out defined stages of the authorised development.

This is because it is proposed that Requirements may be discharged separately for different elements of the authorised development for the purposes of carrying

out the authorised development expeditiously. This approach is envisaged in Requirement 3 of the DCO Model Provisions and is common on linear schemes

such as the authorised development.

Requirement 5 (Barmston Pumping Station) requires certain details for the Barmston Pumping Station

(including layout, scale, external appearance, surface treatments, method of drainage and planting) to be approved by the relevant planning authority (in

consultation with the EA) before its construction can commence, which must be carried out in accordance

with the approved details.

The design and scale of the Barmston Pumping Station will be within the parameters set in the relevant

parameter plan (Document Reference 2.14) and guiding principles established in Chapter 8 of the Design and Access Statement. The parameter plan sets

out the maximum envelope within which the buildings and infrastructure will be constructed. However, the detailed design of the Barmston Pumping Station

needs to take place on a flexible basis, for later approval, because precise equipment and its exact location within the site will be known closer to the

point of implementation. As such, by seeking outline consent at this time, the undertaker can ensure that the detailed design of the Barmston Pumping Station

reflects the appropriate equipment available at the time of construction.

Separately, there are controls on the type and use of

external lighting.

Page 72: Explanatory Memorandum (Rev D)

70

Requirement 6 (Camblesforth Multi-junction design) requires certain details for the Area B of the

Camblesforth Multi-Junction (including layout, scale, external appearance, surface treatments and method of drainage) to be approved by the relevant planning

authority (in consultation with the EA) before its construction can commence, which must be carried out

in accordance with the approved details. Above ground structures installed within “Area B” of the Multi-junction are limited to 4 metres in height. The reason

for this Requirement is that the proposed Camblesforth Multi-junction has been designed to accommodate up to four incoming pipeline connections (4 PIG traps)

and one outgoing connection (1 PIG trap) into the cross country pipeline. However, general arrangement drawings, elevations and profiles comprised in the

application for the Order show:

• design for two PIG traps to accommodate an

inlet PIG Trap for the pipeline connection from the White Rose CCS Project and an outlet PIG Trap to the cross country pipeline comprised

in the authorised development; and

• “Area B”. Area B cannot yet be designed in

detail as the capacity and rate at which the area is built out will depend on when third party connectors come forward and the

direction from which they enter the facility. Capacity has been provided for three PIG Traps within this Area B and this Requirement

secures detailed design approval by the relevant authority when such details become available.

Separately, there are controls on the type and use of external lighting.

Requirement 7 (European Protected Species) follows Requirement 34 of the DCO Model Provisions and requires that prior to commencement of each stage of

the authorised development, surveys need to be carried out to ascertain whether there are any European protected species present on land affected

by the authorised development. Where such species are present, that stage of the authorised development cannot be carried out until, following consultation with

Page 73: Explanatory Memorandum (Rev D)

71

Natural England, a scheme of protection and mitigation has been approved by the relevant planning authority;

and the scheme must be complied with.

Requirement 8 (Scheme of ecological mitigation and reinstatement) requires each stage of the authorised

development to be carried out in accordance with a scheme of ecological mitigation (and, for pipeline

stages, reinstatement) approved by the relevant planning authority. There is provision for pre-submission consultation with the relevant planning

authority as well as with the MMO as a consultee in its area. This has the same effect as Requirement 17 of the DCO Model Provisions, save that it relates

specifically to pipeline stages. In addition, similar to Requirement 8 of the DCO Model Provisions, it provides for the replacement of any shrub, hedge or

tree planted as part of the scheme that dies or becomes seriously damaged or diseased within five years of completion of the authorised development.

Requirement 9 (Water) requires construction works for the authorised development to be carried out in accordance with an approved construction water

management plan and a pollution prevention and control plan. Further:

• crossing methods for the authorised development in relation to watercourses must be undertaken in a manner which will not

cause an increase in flood risk;

• drainage measures to control surface water runoff in the flood risk assessment must be

complied with during construction;

• particular provision is made to reduce flood risk in the handling of spoil, including no

permanent raising of the floodplain by the undertaker.

Requirement 10 (Removal of trees and hedgerows) is required because the laying of the pipeline is likely to require the removal of certain trees or hedges along the pipeline route, which is provided for in the Order.

This Requirement means that the relevant planning authority must approve details of those trees and hedgerows to be removed during a particular stage of

the authorised development before work on that stage

Page 74: Explanatory Memorandum (Rev D)

72

can commence. The approach to tree planting following the installation of the pipeline is dealt with as

part of the landscaping works under Requirement 8 above, as is the reinstatement of hedgerows.

Requirement 11 (AGI hard landscaping, lighting and drainage) prohibits a stage of the development commencing until details of hard surfacing materials,

lighting and drainage methods for any AGIs in that stage have been submitted to and approved by the relevant planning authority. This Requirement does not

apply to the Pumping Station or Area B of the Multi Junction because, as explained above, detailed design for these is to follow and would address hard surfacing

and drainage so far as appropriate.

Requirement 12 (Archaeology) follows the approach in Requirement 16 of the DCO Model Provisions and

requires that each stage of the authorised development must be carried out in accordance with a written archaeological scheme approved by the

relevant planning authority. The archaeological scheme will identify areas where a programme of archaeological investigation is required, and measures

to protect, record or preserve any archaeological remains that are found. This is because construction

of an underground pipeline may reveal undiscovered archaeological artefacts. The undertaker has remained in regular dialogue with English heritage on the

progression of the Onshore Scheme.

Requirement 13 (Construction Hours) means that construction of the authorised development can only

take place during set hours, other than in relation to certain listed operations, in cases of emergency or if otherwise approved by the relevant planning authority.

More limited working hours have been introduced for works at the Barmston Pumping Station during winter months. This is because this is a location where

construction activities will be carried out between October and February for the purposes of the two year build. The list of operations which may take place

outside of the set time frames is included because either, due to the engineering nature of the activity, they require 24-hour working or, in the case of

temporary possession of railway infrastructure, construction hours will be determined by third parties

(like Network Rail).

Page 75: Explanatory Memorandum (Rev D)

73

Requirement 14 (Code of Construction Practice) follows Requirement 18 of the DCO Model Provisions

and requires that construction works are carried out in accordance with the code of construction practice submitted with the application, unless otherwise

agreed by the relevant local planning authority. The code of construction practice contains a series of

measures and standards of work to be applied by the undertaker and its contractors during construction of the authorised development.

Requirement 15 (Noise) requires the authorised development to be constructed in accordance with specified construction noise levels at stated times.

Further, Barmston Pumping Station must be operated in accordance with a noise report:

• approved by the relevant planning authority;

• demonstrating that noise for permanent fixed plant / machinery at the nearest residential receptor, Rise Cottage, will not exceed certain

levels; and

• considering low frequency noise.

Requirement 16 (Land drainage) requires that subject to any alternative approved in respect of AGIs pursuant to Requirement 11 above, the authorised

development must be constructed in accordance with the Drainage Strategy submitted with the application. The authorised development is a long linear scheme

excavating a trench for much of the pipeline. As such, some existing drains may be severed. The purpose of this Requirement is to secure compliance with that

Drainage Strategy. This approach to land drainage, and the resultant likely effects on the Order limits as a result of drainage design, were detailed as part of the

Stage 2 statutory consultation.

Requirement 17 (Contaminated land and groundwater) has the same effect as Requirement 15

of the DCO Model Provisions and requires that if previously unidentified contamination is found whilst carrying out the authorised development, it must be

immediately reported to the relevant planning authority. It also requires that an investigation and risk assessment is completed in accordance with an

Page 76: Explanatory Memorandum (Rev D)

74

approved scheme. Any necessary remediation must be carried out in accordance with an approved

scheme, and following completion of the remediation, a verification report must be produced, and approved by the relevant planning authority. The purpose of this

Requirement is to ensure that potentially significant effects of previously unidentified contamination (if any)

along the pipeline route are dealt with in a responsible and satisfactory manner.

Requirement 18 (Traffic Management Plan) requires

that the authorised development be carried out in accordance with a Traffic Management Plan to be submitted to and approved by the relevant planning

authority in consultation with the highway authority. This would need to addresses the management of construction traffic, which includes deliveries of pipe,

construction plant and materials as well as construction workers travelling to and from the temporary construction compounds and the

construction working areas.

Requirement 19 (Restoration of land used temporarily for construction) follows Requirement 35

of the DCO Model Provisions and requires that any land used temporarily for construction must be

reinstated to a condition fit for its former use within 12 months of completion of the relevant stage of the authorised development (though the undertaker may

return for construction works in accordance with the powers under Article 28). Though the DCO Model Provision Requirement requires reinstatement of land

to its “former condition”, Requirement 18 provides for reinstatement to “a condition fit for its former use”. This is to account for immaterial changes resulting

from the installation of the pipeline which do not affect the landowner or occupier continuing with the former use of the land used for construction.

Requirement 20 (Requirement for written approval) follows Requirement 36 of the DCO Model Provisions and requires that any approvals by the relevant

planning authority must be provided in writing.

Requirement 21 (Amendments to approved details) clarifies that where the relevant planning authority

approves details with which the undertaker must comply, and later agrees compliance with amended

Page 77: Explanatory Memorandum (Rev D)

75

details, the originally approved details are to be considered in light of the amendments which have

been subsequently approved but only so far as those amendments do not give rise to any materially new or materially different significant environmental effects

from those assessed in the environmental statement. This follows Requirement 37 of the DCO Model

Provisions with additional wording to limit the scope of the approvals.

Requirement 22 (Decommissioning) provides a

framework for the relevant planning authority approving the approach to the authorised development at the end of its operational life. Accordingly, this

Requirement sets out that at least six months before the operations of the authorised development come to a permanent end, a scheme of decommissioning,

restoration and aftercare must be submitted for approval by the relevant planning authority. Following the end of operations, that scheme must then be

implemented as approved.

Requirement 23 (Driffield Construction Compound) provides control over the extent of the buildings to be

demolished, or not as the case may be, in accordance with the assumptions made in the course of the

environmental impact assessment.

Requirement 24 (Venting for AGI maintenance) provides control over the planned maintenance venting

of AGIs. It controls the frequency, duration and noise emission level of that activity.

Requirement 25 (AGI venting for pipeline inspections) provides control over the planned internal inspection of pipelines using PIGs and venting of PIG traps at AGIs for the purposes of the internal

inspection of pipelines. It controls the frequency, duration and noise emission levels of that activity.

Requirement 26 (AGI venting notifications) governs

how the public would be forewarned about venting operations described in Requirements 24 (Venting for AGI maintenance) and 26 (AGI venting for pipeline inspections).

Schedule 4 (streets subject to street works) sets out those streets

referred to in article 10 (street works) subject to street works.

Page 78: Explanatory Memorandum (Rev D)

76

Schedule 5 (streets subject to alteration of layout) sets out those streets referred to in article 11 (power to alter layout, etc., of streets) subject to alteration of layout.

Schedule 6 (streets and rights of way to be temporarily stopped up) sets out those streets and rights of way referred to in article 14 (temporary stopping up of streets and rights of way) to be temporarily stopped up.

Schedule 7 (access to works) sets out the new accesses referred to in article 16 (access to works) to be constructed as part of the authorised development.

Schedule 8 (record of the satisfaction of the Secretary of State pursuant to section 132 of the 2008 Act) records

further to article 40 that the Secretary of State (if he is so minded) is satisfied that a subsection of section 132 of the 2008 Act applies to Plots 232, 233 and 268 of

the book of reference (Document Reference 4.3).

Schedule 9 (land of which temporary possession may be taken) sets out the land referred to in article 28 (temporary use of land for carrying out the authorised development) of which temporary possession may be taken.

Schedule 10

(deemed marine licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009) sets out the marine licence referred to in article 42, which would be deemed to be granted for works comprised in the authorised development below mean

high water spring tide and the conditions to which the licence would be subject.

Background to deemed marine licences

In terms of background, the MMO was established pursuant to the Marine and Coastal Access Act 2009 (“2009 Act”). The 2009 Act requires a Marine Licence

to be obtained to carry out specified “licensable marine activities” in the area submerged at mean high water spring tide (“MHWS”) and the waters of rivers so far

as the tide flows at MHWS. The MMO would ordinarily, i.e. outside of the Planning Act 2008 (“2008 Act”), be

the decision-maker responsible for determining whether to grant a Marine Licence under the 2009 Act.

However, this is not the case for nationally significant

Page 79: Explanatory Memorandum (Rev D)

77

infrastructure projects falling under the 2008 Act, such as the Onshore Scheme. Should the Secretary of State

accept the Onshore Scheme for Examination, and that it is therefore subject to the 2008 Act, he will be the decision-maker responsible for determining whether to

grant development consent in the form of the DCO for the Onshore Scheme, which will include the area

within the Order limits of the DCO submerged at MHWS down to mean low water spring tide (“MLWS”). This would include the areas within the

Order limits seaward of MHWS at Barmston Sands and the tidal reach of the River Ouse, which are shown for information only on the Deemed Marine Licence Co-

ordinates drawing with reference 0-2574-GND-01-05-0056 (Document Reference 2.7). Section 149A of the 2008 Act allows a DCO made by the Secretary of State

to deem that a Marine Licence has been granted pursuant to the 2009 Act. The draft DCO sought by the undertaker deems such a licence to have been issued

in article 42 and sets out in this Schedule the terms of that deemed Marine Licence.

In other words, the Secretary of State, rather than the

MMO, is the decision-maker for the Marine Licence, deemed to be granted by the DCO and contained

within it. There is therefore no “crossover” of jurisdictions and no separate Marine Licence is required from the MMO. However, the MMO plays the

following important roles under the 2008 Act regime:

(A) The MMO is a consultee on the deemed Marine Licence, whose representations,

amongst other things, may inform what conditions are to be attached to the deemed marine licence by the Secretary of State;

(B) The Secretary of State may specify in the deemed Marine Licence that the MMO is the responsible discharging body for conditions

attached to that deemed Marine Licence. This is the case in the deemed Marine Licence contained in the DCO;

(C) The MMO is responsible for enforcing breaches of the conditions attached to the deemed Marine Licence, with a choice of

enforcement procedures under the 2008 and 2009 Acts.

Page 80: Explanatory Memorandum (Rev D)

78

Terms of the deemed marine licence

The terms of the marine licence can be summarised as

follows:

PART 1: INTERPRETATION AND DETAILS OF LICENSED MARINE ACTIVITIES

Paragraph 1 (interpretation) sets out the interpretation of certain words and phrases used in the

licence and contact details for the MMO and other relevant organisations including, inter alia, the Environment Agency, Natural England and English

Heritage.

Paragraph 2 (details of licensed marine activities) authorises the construction of those elements of the

authorised development which fall within the English inshore region, i.e. the area submerged at MHWS for which marine licences are ordinarily required, and

constitute licensable activities for the purposes of the 2009 Act. This includes the following: the deposit of specified substances at sea; the construction,

inspection and maintenance of works in, under or over the intertidal area and the River Ouse; and sampling or investigative works required in connection with these.

The paragraph also specifies the parameters of the licensed area within which the licensed activities are

permitted.

PART 2: LICENCE CONDITIONS

Paragraph 1 (application of licence conditions) provides that the licence conditions will not apply to areas of the authorised development which fall outside the English inshore region, i.e. the landward side of

MHWS and for which the relevant local planning authority would be the appropriate discharging and enforcing body pursuant to the Requirements in

Schedule 3. This has been agreed with the MMO.

Paragraph 2 (licensed location) specifies the area within which the licensed activities may be carried out.

Paragraph 3 (notifications and inspections) sets out the persons who must be given a copy of the Schedule, and where it will be available for inspection,

as well as certain notification and publication

Page 81: Explanatory Memorandum (Rev D)

79

requirements.

The paragraph provides that only persons and vessels

notified to the MMO are permitted to carry out the licensed activities, and each of these persons must be provided with a copy of the Schedule. The undertaker

must also appoint suitably qualified liaison officers (Fisheries Liaison Officer(s) and Environmental Liaison

Officer(s)) and their identities and responsibilities must be notified to the MMO. Prior to commencement of licensed activities, the undertaker must give notice to

the MMO and mariners (mariners’ notices must be updated at least once a week) and a notice must be published in the Kingfisher Fortnightly Bulletin. This is

to ensure that other vessels in the vicinity can safely plan and conduct their passage. In addition, the undertaker must comply with notice requirements

regarding completion.

The undertaker must also provide access to the MMO to carry out any inspection of the works.

Provision is made for notices to the MMO in the event that the whole benefit of the deemed marine licence is transferred under the Order.

Paragraph 4 (chemicals, drilling and debris) restricts the use of chemicals, drilling fluids, coatings and

treatments. It provides that all chemicals used in the construction of the licensed works must be selected from an approved list and the undertaker must ensure

that any coatings and treatments are suitable for use in the marine environment and are used in accordance with specified Environment Agency and Health and

Safety Executive guidelines. This is to ensure that hazardous chemicals that may be toxic, persistent or bioaccumulative are not released into the marine

environment and are used appropriately.

In addition, the undertaker is required to ensure that the storage, handling, transport and use of fuels,

lubricants, chemicals etc. is carried out in a way so as to prevent releases into the marine environment. This is to prevent marine pollution incidents by adopting

best practice techniques.

The undertaker is also required to report any accidental spillages of coatings or treatments to the

MMO within 6 hours. This is to ensure that any spills

Page 82: Explanatory Memorandum (Rev D)

80

are appropriately recorded and managed to minimise the impact to sensitive receptors and the general

marine environment.

For any drilling works other than those using water-based mud, the MMO’s approval is required in relation

to the proposed disposal of any arisings from the drilling works.

Further, any waste, debris, equipment and temporary works must be removed within 4 weeks of completion. This is to prevent the accumulation of unlicensed

material/debris and the potential environmental damage, safety and navigational issues associated with such material/debris.

Paragraph 5 (pre-construction plans and documentation) requires the undertaker to submit for the approval of the MMO, four months before

commencement of licensed activities the following documents: a construction and monitoring programme; a construction method statement; a

project environmental management plan; and a written scheme of archaeological investigation. Each of these documents must contain certain specified

information. No licensed activity can commence until the relevant programme/plan has been approved by

the MMO and all licensed activities must be carried out in accordance with the approved programmes/plans. Separately, the undertaker must:

• obtain consent from the MMO in relation to materials to be stored in temporary construction compounds and management

arrangements for these;

• provide a detailed piling method statement before works in the landfill area are

commenced;

• provide a method statement for monitoring and managing sediment arising from the

cofferdam used in constructing the pipeline in the intertidal area; and

• provide details for approval of the pipeline to

be placed temporarily in the River Ouse for the purposes of hydrostatic testing.

Page 83: Explanatory Memorandum (Rev D)

81

Paragraph 6 (reporting of engaged agents, contractors and vessels) requires the undertaker to

provide details to the MMO of agents, contractors and vessels that will be carrying out the licensed activities.

Paragraph 7 (equipment and operation of vessels engaged in licensed activities) requires the undertaker to ensure all vessels being used to carry out the

licensed activities meet specified technical requirements and are constructed and equipped to enable compliance with the licence conditions.

Paragraph 8 (pre-construction baseline) requires the undertaker to submit a pre-construction baseline report to the MMO for approval prior to

commencement of licensed activities. The form and content of the pre-construction baseline report must be agreed with the MMO in advance and must include

certain specified information.

Paragraph 9 (construction monitoring) requires the undertaker to submit environmental monitoring reports

to the MMO during construction (in accordance with paragraph 5). The monitoring reports must include certain specified information.

Paragraph 10 (post construction) requires the undertaker to submit environmental monitoring reports

to the MMO following construction of the licensed works (in accordance with paragraph 5).

Paragraph 11 (aids to navigation) requires the

undertaker to comply with certain safeguards in relation to aids to navigation for shipping, as set out by Trinity House, which is responsible for such aids.

Paragraph 12 (amendments to approved details) makes provision for any amendments lawfully approved by the MMO to be included in the approved

details for the purposes of carrying out the licensed activities in accordance with the details provided.

Schedule

11

(protective provisions) sets out protective provisions

for specified statutory undertakers who have been identified as having apparatus within the Order limits.

The provisions have been based on those contained in several recent TWA Orders and Orders under the 2008 Act.

Page 84: Explanatory Memorandum (Rev D)

82

Schedule 12

(miscellaneous controls) part 1 of this Schedule applies, modifies and excludes specified general

statutory provisions which relate to matters for which provision may be made in the Order:

Paragraph 2 provides the consents necessary under

the Wildlife and Countryside Act 1981 for the proposed non-intrusive installation of the pipeline beneath Kelk

Beck, part of the River Hull Headwaters SSSI, and a bridge to allow access for construction traffic over it. The consents are subject to the provisions of the

Order, particularly the requirements in Schedule 3 (requirements). This application of and modification to the Wildlife and Countryside Act 1981 may be made

pursuant to section 120(5)(a) of the 2008 Act and the Planning Inspectorate have confirmed that this is an appropriate approach.

The context of paragraph 3 is as follows:

• The Pipeline Safety Regulations 1996 (the “1996 Regulations”) (which are Regulations

made under the Health and Safety at Work etc Act 1974) apply to the authorised development in general terms.

• However, the authorised development is not a “major accident hazard pipeline”, as defined

under the 1996 Regulations, and therefore certain additional duties imposed on major accident hazard pipelines do not apply to the

authorised development.

• The specific Regulations under the 1996 Regulations that have been applied by this

Order relate to the requirement to notify the relevant authorities prior to construction and prior to use, the need to have a major

accident prevention document and to have in place certain emergency procedures. In other words, the undertaker, therefore, has adopted

a precautionary approach and has elected to operate the proposed pipelines as if Carbon Dioxide were classed as a “dangerous fluid”

under Part III of the Pipeline Safety Regulations 1996, even though this is not presently the case.

Page 85: Explanatory Memorandum (Rev D)

83

• The provisions that have not been applied relate primarily to the incorporation of

emergency shut-down valves into the design and the need to have an emergency plan approved by the relevant authority. These

provisions are unnecessary given that the undertaker is voluntarily assuming certain

duties that otherwise would not apply. The emergency shut-down valves are only relevant to offshore pipelines. In addition, the criminal

provisions of the Health and Safety at Work etc. Act 1974 need to be disapplied because these duties are by virtue of incorporation into

the draft Order “terms of a development consent order”, breach of which is already a criminal offence pursuant to the section 161

(breach of terms of order granting development consent).

Part 2 of this Schedule applies, modifies and excludes

specified local legislation which relates to matters for which provision may be made in the Order. The approach in relation to the byelaws of three internal

drainage boards (“IDBs”), namely the Selby Area Internal Drainage Board Byelaws, Ouse and Humber

Drainage Board Byelaws and Beverley and North Holderness Internal Drainage Board Byelaws, is as follows:

• byelaws which do not conflict with the carrying out of the authorised development are not excluded or amended in the Order and

remain unaltered;

• byelaws which prohibit an activity required for the carrying out of the authorised

development but which refer to scope for obtaining the consent of the relevant IDB are not excluded or amended in the Order and, it

has been agreed with these bodies, such consents will be sought following the making of the Order; and

• byelaws which conflict with activities required for the carrying out of the authorised development but which do not provide scope

for consent under the terms of those byelaws

Page 86: Explanatory Memorandum (Rev D)

84

are made subject to the mechanism described below:

• Article 3(2)(a) (Application, modification and disapplication of legislative provisions) clarifies that the

particular IDB byelaws listed in Part 2 of Schedule 12 do apply to the

authorised development but only as amended in Part 2, i.e. they are no longer outright prohibitions on activities

required for the authorised development but requirements for consent;

• Under Article 3(2)(c), other IDB byelaws do not apply to the authorised development so far as they are

inconsistent with what is specified in the Order. Nevertheless, requiring a separate consent is entirely consistent

with the Order (as nothing in the Order removes the need for such consents), so this does not affect the application

of IDB byelaws more widely. This is intended on a precautionary basis

given the certainty required by a nationally significant infrastructure project (as described in respect of

article 3 above) and also relates to provisions of local application more widely;

• Then, for the purposes of the authorised development only, paragraphs 1 – 7 in Part 2 of Schedule

12 replace the particular IDB byelaws mentioned in it with equivalents which are no longer outright prohibitions on

activities required for the authorised development but, instead, requirements for consent.

• Separately, paragraph 8 provides an IDB with the residual option of consenting to actions under any of its

byelaws if it considers this appropriate – this is prudent in the context of the

Page 87: Explanatory Memorandum (Rev D)

85

complexity of matters which might arise in the construction of a nationally

significant infrastructure project and the certainty which such projects require;

• As described in respect of Schedule 14 above, Schedule 14 (Procedure in relation to certain approvals etc.) is a mechanism derived from previous DCOs made by the Secretary of State

which sets out periods within which a promoter can appeal decisions made by local authorities etc. to the Secretary of

State and the procedure for such appeals. Such a mechanism is important in the context of the

certainty required for a nationally significant infrastructure project. If IDB byelaws are to remain in effect but

subject to consents, it is appropriate for those consents to be subject to the same mechanism as other consents

under the DCO. Schedule 14 has therefore been amended to incorporate

IDB byelaws and directions so far as they apply to the authorised development.

Schedule 13

(modification of compensation and compulsory purchase enactments for creation of new rights) as explained above in relation to article 24(4)

(compulsory acquisition of rights), mirrors the wording of Schedule 11 of the Hinkley Point C (Nuclear Generating Station) Order 2013 and imposes

modifications to the compulsory purchase and compensation provisions under general legislation which do not affect the entitlement to compensation,

but generally ensure that the compensation procedure applies to the additional categories of acquisition

covered by the Order – namely, the creation of new rights and the imposition of restrictive covenants in particular.

Schedule 14

(procedure in relation to certain approvals etc.) sets out a procedure in respect of certain approvals to be determined pursuant to the Order, which is more

particularly explained in this explanatory memorandum

Page 88: Explanatory Memorandum (Rev D)

86

at article 53 above.

Berwin Leighton Paisner LLP

March 2015

32330277.18

Page 89: Explanatory Memorandum (Rev D)

87

Appendix Tracked change version of the Order against the DCO Model Provisions

Page 90: Explanatory Memorandum (Rev D)

Page 28 of 99PART 1

PRELIMINARY

1. Citation and Commencement

12. Interpretation

2 Incorporation of the Railway Clauses Acts3 . Application and, modification and disapplication of legislative provisions

PART 2

WORKS PROVISIONS

Principal Ppowers

4 . Development consent etc. granted by the Order

5 . Maintenance of authorised projectdevelopment

6 . Limits of Ddeviation

7 Benefit of Order. Defence to proceedings in respect of statutory nuisance

Benefit of Order

8. Benefit of Order

8 Consent to transfer9. Transfer of benefit of Order

Streets

9 10. Street works

10 1. Power to alter layout, etc., of streets

12. Construction and maintenance of new or, altered or diverted streets

11 Stopping up of streets12 Application of the 1991 Act

13 Public rights of way. Permanent stopping up of streets

14 . Temporary stopping up of streets and public rights of way

15 . Apparatus and rights of statutory undertakers in permanently stopped up streets

16. Access to works

16 7. Traffic regulation

18. Agreements with street authorities

17 Construction of bridges and tunnels

2 2

S T A T U T O R Y I N S T R U M E N T

201[●] No. [●]

INFRASTRUCTURE PLANNING

The [Draft] Yorkshire and Humber (Carbon Capture and Storage

Cross Country Pipeline) Order 201[●]

Made - - - - [●] 201[●]

Coming into force - - [●] 201[●]

CONTENTS

Preliminary

Page 91: Explanatory Memorandum (Rev D)

Page 29 of 99

34 Rights under or over streets35 28. Temporary use of land for carrying out the authorised projectdevelopment

36 29. Temporary use of land for maintaining the authorised projectdevelopment

Compensation

37 Special category land0. Disregard of certain interests and improvements

31. Set-off for enhancement in value of retained land

38 Statutory undertakers2. No double recovery

Supplementary

33. Acquisition of part of certain properties

34. Statutory undertakers

39 Apparatus and rights of statutory undertakers in stopped up streets5. Recovery of

costs of new connections

36. Time limit for exercise of authority to acquire land compulsorily

37. Private rights of way

38. Rights under or over streets

39. Incorporation of the mineral code

40 Recovery of costs of new connections

Operations. Open space

PART 4

MISCELLANEOUS AND GENERAL

41 Operation and use of railways. Application of landlord and tenant law

42 F a r es 43 . Deemed consent under section 34 of the Coast Protection Act 194Part 4

(marine licensing) of the Marine and Coastal Access Act 2009

3 3

18 Level Crossings19 Railway and navigation undertakings

Supplemental Ppowers

20 19. Discharge of water

210. Protective work to buildings

22 1. Authority to survey and investigate the land

23 2. Removal of human remains

PART 3

ACQUISITION AND POSSESSION OF LAND

Powers of Aacquisition

23. Compulsory acquisition of land

24 . Compulsory acquisition of landrights

25 Compulsory acquisition of land--incorporation of the mineral code.Acquisition of subsoil only

26 Time limit for exercise of authority to acquire land compulsorily.Power to override easements and other rights

27 Compulsory acquisition of rights

28 Private rights of way29 . Application of the Compulsory Purchase (Vesting

Declarations) Act 1981

30 Acquisition of subsoil only31Acquisition of land limited to subsoil lying more than 9 metres beneath surfaceTemporary

possession of land

32 Acquisition of part of certain properties33 Application of the Land Compensation Act 1973

Page 92: Explanatory Memorandum (Rev D)

Page 30 of 9953. Procedure in relation to certain approvals etc.

54. Saving for Trinity House

4 4

44 Deemed licence under Part 2 of the Food and Environment Protection Act 19853.Operational land for purposes of the 1990 Act

445 . Felling or lopping of trees or shrubs

46 5. Trees subject to tree preservation orders

Miscellaneous and General

46. Resumption of land use following certain works

47 . Application of landlord and tenant lawthe Community Infrastructure Levy

48 Operational land for purposes of the 1990 Act49 Defence to proceedings in respect of statutory nuisance50 Protections of Interests. Protective provisions

5149. Certification of plans etc.

52 Arbitration0. Service of notices

Schedule A--Authorised Project

Part 1--Authorised Development Part 2--Ancillary Works

Schedule B--Streets Subject to Street Works Schedule C--Streets to be Stopped Up

Part 1--Streets for which a Substitute is to be Provided Part 2--Streets for which No Substitute is to be Provided

Schedule D--Streets to be Temporarily Stopped UpSchedule E--Access to WorksSchedule F--Land of which Only Subsoil More than 9 Metres Beneath Surface may beAcquiredSchedule G--Land of which Temporary Possession may be TakenSchedule H--Deemed Consent Under Coast Protection Act 1949

51. Arbitration

Schedule I--Deemed Licence Under the Food and Environment Protection Act 198552.Requirements

Schedule J--Trees Subject to Tree Preservation OrdersSchedule K--Level CrossingsSchedule L--Protective Provisions

Preliminary

Page 93: Explanatory Memorandum (Rev D)

SCHEDULES

SCHEDULE 1 — AUTHORISED DEVELOPMENT

SCHEDULE 2 — PLANS

PART 1 — WORKS PLANS

PART 2 — LAND PLANS

PART 3 — ACCESS, RIGHTS OF WAY AND TEMPORARY STOPPING UP

PLANS

PART 4 — APPROVED PLANS

PART 5 — HEDGEROW PLANS

PART 6 — PARAMETERS

PART 7 — PLANTING DRAWINGS

SCHEDULE 3 — REQUIREMENTS

SCHEDULE 4 — STREETS SUBJECT TO STREET WORKS

SCHEDULE 5 — STREETS SUBJECT TO ALTERATION OF LAYOUT

PART 1 — STREETS SUBJECT TO TEMPORARY ALTERATION OF

LAYOUT

PART 2 — STREETS SUBJECT TO PERMANENT ALTERATION OF

LAYOUT

SCHEDULE 6 — STREETS AND PUBLIC RIGHTS OF WAY TO BE

TEMPORARILY STOPPED UP

PART 1 — STREETS

PART 2 — RIGHTS OF WAY

SCHEDULE 7 — ACCESS TO WORKS

PART 1 — TEMPORARY ACCESS

PART 2 — PERMANENT ACCESS

SCHEDULE 8 — RECORD OF THE SATISFACTION OF THE SECRETARY OF

STATE PURSUANT TO SECTION 132 OF THE 2008 ACT

SCHEDULE 9 — LAND OF WHICH TEMPORARY POSSESSION MAY BE

TAKEN

SCHEDULE 10 — DEEMED MARINE LICENCE UNDER PART 4 (MARINE

LICENSING) OF THE MARINE AND COASTAL ACCESS ACT

2009

PART 1 — INTERPRETATION AND DETAILS OF LICENSED MARINE

ACTIVITIES

PART 2 — LICENCE CONDITIONS

SCHEDULE 11 — PROTECTIVE PROVISIONS

PART 1 — FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND

SEWERAGE UNDERTAKERS

PART 2 — FOR THE PROTECTION OF OPERATORS OF ELECTRONIC

COMMUNICATIONS CODE NETWORKS

SCHEDULE 12 — MISCELLANEOUS CONTROLS

PART 1 — PUBLIC GENERAL LEGISLATION

PART 2 — LOCAL LEGISLATION

SCHEDULE 13 — MODIFICATION OF COMPENSATION AND COMPULSORY

PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

SCHEDULE 14 — PROCEDURE IN RELATION TO CERTAIN APPROVALS ETC.

EXPLANATORY NOTE

An application was made to the Secretary of State in accordance with section 37 of the Planning Act

2008(a) for an order under sections 37, 114, 115, 120 and 122 of that Act.

5 5

(a) 2008 c.29; section 37 is amended by the Localism Act 2011 (c. 20) s.137 and Sch. 13, para.5(2), (3).

Page 94: Explanatory Memorandum (Rev D)

The Examining authority(b) appointed by the Secretary of State examined the application in accordance

with Chapter 4 of Part 6 of that Act(c) and made a recommendation under section 74 of that Act(d) that

the application should be granted.

The Secretary of State, having the function of deciding the application(e), in exercise of the powers

conferred by sections 103, 114, 115, 120 and 122 of that Act, makes the following Order—

PART 1

PRELIMINARY

Citation and Commencement

This Order may be cited as the Yorkshire and Humber (Carbon Capture and Storage Cross Country 1.

Pipeline) Order 201[●] and comes into force on [●] 201[●].

Interpretation 1

(1) —a) In this Order--, unless the context requires otherwise—2.

"“the 1961 Act"” means the Land Compensation Act 1961(f);

"“the 1965 Act"” means the Compulsory Purchase Act 1965(g);

"“the 1980 Act"” means the Highways Act 1980(h);

“the 1984 Act” means the Road Traffic Regulation Act 1984(i);

"“the 1990 Act"” means the Town and Country Planning Act 1990(j);

"“the 1991 Act"” means the New Roads and Street Works Act 1991(k);

"the 2008 Act" means the Planning Act 2008;

"ancillary works" means the ancillary works described in Part 2 of Schedule A (authorised project) [and any other works authorised by the Order] and which are not development within the meaning of section 32 of the 2008 Act;

“the 2008 Act” means the Planning Act 2008;

“access, rights of way and temporary stopping up plans” means the plans certified as the access,

rights of way and temporary stopping up plans by the Secretary of State for the purposes of this

Order and listed in Part 3 (access, rights of way and temporary stopping up plans) of Schedule 2

(plans);

“approved plans” means the plans listed in Part 4 (approved plans) of Schedule 2 (plans);

"“authorised development"” means the development and associated development described in Part 1

of Schedule A1 (authorised projectdevelopment) [and any other development authorised by this

Order], which is development within the meaning of section 32 of the 2008 Act;

6 6

(b) See section 86 of the Planning Act 2008 as amended by the Localism Act 2011, Sch. 13 para.37.

(c) The provisions of that Part are amended by the Localism Act 2011.

(d) Section 74 is amended by the Localism Act 2011, Sch.13 para.29(3) and Sch. 25 para.1.

(e) See section 103 of the Planning Act 2008 as amended by the Localism Act 2011 Schs. 13, 25.

(f) 1961 c.33.

(g) 1965 c.56.

(h) 1980 c.66.

(i) 1984 c. 27.

(j) 1990 c.8.

(k) 1991 c.22.

Page 95: Explanatory Memorandum (Rev D)

"the authorised project" means the authorised development and the ancillary works authorised by

this Order;the “Barmston Pumping Station parameter plan” has the meaning given in Requirement

5(2)(b) (Barmston Pumping Station) of Schedule 3 (requirements);

"“the book of reference"” means the book of reference certified by the decision-makerSecretary of

State as the book of reference for the purposes of this Order;

"“building"” includes any structure or erection or any part of a building, structure or erection;

the “Camblesforth Multi-junction parameter plan” has the meaning given in Requirement 6(2)

(Camblesforth Multi-junction design) of Schedule 3 (requirements);

"“carriageway"” has the same meaning as in the 1980 Act;

“code of construction practice” has the meaning given in Requirement 1 (interpretation) of Schedule

3 (requirements);

"“compulsory acquisition notice"” means a notice served in accordance with section 134 of the 2008

Act; "the decision-maker" has the same meaning as in section 103 of the 2008 Act;

"highway" and "highway authority" have the same meaning as in the 1980 Act(l);

“drainage works” means that part of the authorised development comprised in paragraph (m)

(further associated development) in Schedule 1 (authorised development) and such other further

associated development in connection with that paragraph as is listed at paragraphs (e), (g), (h), (i),

(j), (k), (l) and (n) (further associated development) of that Schedule;

“drainage strategy” has the meaning given in Requirement 16 (land drainage) of Schedule 3

(requirements);

“environmental statement” means the document(s) certified as the environmental statement by the

Secretary of State for the purposes of this Order together with any supplemental or additional

environmental statement submitted for the purposes of complying with and/or discharging the

Requirements in Schedule 3 (requirements) or conditions in Schedule 10 (deemed marine licence

under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009);

“flood risk assessment” has the meaning given in Requirement 9(6) (water) of Schedule 3

(requirements);

“hedgerow plans” has the meaning given in article 44(7)(b) (felling or lopping of trees or shrubs);

“highway” has the same meaning as in the 1980 Act;

“highway authority” means North Yorkshire County Council or East Riding of Yorkshire Council as

the case may be including their successor; and where the relevant matter is located in the

administrative areas of both then it means both;

"“the land plans"” means the plans certified as the land plans by the decision-makerSecretary of

State for the purposes of this Order and listed in Part 2 (land plans) of Schedule 2 (plans);

"limits of deviation" means the limits of deviation referred to in article 6;

"“maintain" and any of its derivatives include to” includes inspect, examine, monitor, test, repair,

adjust, alter, remove,set up, configure, dismantle and/or reconstruct the authorised development

and/or replace the authorised project and any derivative of "maintain" shallpart or a section of the

authorised development with a part or section which materially serves the same purpose; and

“maintained”, “maintaining” and “maintenance” must be construed accordingly;

“National Grid Carbon” means National Grid Carbon Limited (company number 03932833) whose

registered office is at 1 - 3 Strand, London, WC2N 5EH;

"“Order land"” means the land shown on the land plans which is within the limits of land, and

interests in or rights over land, to be acquired and/or used and described in the book of reference;

"“the Order limits"” means the limits shown on the works plans within which the authorised

projectdevelopment may be carried out;

7 7

(l) Section 134 is amended by the Localism Act 2011 (c.20), s.142 and Sch. 25.

Page 96: Explanatory Memorandum (Rev D)

(m) 1981 c.67; the definition of “owner” is amended by the Planning and Compensation Act 1991 (c. 34), Sch.15(I) para.9.

(n) Section 48 is amended by the Local Transport Act 2008 (c. 26), Pt 7 s.124(2).

(o) 2009 c.23.

Page 31 of 99

facility, in which case it means the county planning authority;

(ii) a National Park Authority;

(iii) the Broads Authority; and

(iv) the Greater London Authority if the land to which the provisions of this Order or requirements apply is situated in Greater London;

"rights plan" means the plan certified as the rights plan by the decision-maker for the purposes of this Order;

"the sections" means the sections shown on the plan certified as the section drawings plan by the decision-maker for the purposes of this Order;

"“statutory undertaker"” means any person falling within section 127(8), 128(5) or 129(2) of the

2008 Act (statutory undertakers’ land);

"“street"” means a street within the meaning of section 48 of the 1991 Act(n), together with land on

the verge of a street or between two carriageways, and includes part of a street;

"“street authority"”, in relation to a street, has the same meaning as in Part 3 (street works in

England and Wales) of the 1991 Act, for which purpose “highway authority” has the meaning given

in this article; "tree preservation order"

“traffic authority” has the meaning given in section 19821A of the 199084 Act; "

“the tribunal"” means the Lands Chamber of the Upper Tribunal;

“UK marine area” has the same meaning as in section 42 of the Marine and Coastal Access Act

2009(o);

"“undertaker"” means the person who has the benefit of this Order in accordance with section 156 of

the 2008 Act;articles 8 and 9; and

"watercourse" includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain; and

8 8

"“owner"”, in relation to land, has the same meaning as in section 7 of the Acquisition of Land Act

1981(m) (interpretation); "

“PIG” means a pipeline inspection gauge or pipeline internal gauge;

“project design statement” has the meaning given in paragraph 1 (interpretation) of Part 1

(interpretation and details of licensed marine activities) of Schedule 10 (deemed marine licence

under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009);

“relevant planning authority" means--” means Selby District Council or East Riding of Yorkshire

Council as the case may be including their successor and where the relevant matter is located in the

administrative areas of both then it means both;

(i) the district planning authority for the area in which the land to which the provisions of this Order apply is situated unless the provisions relate to the construction or alteration of a hazardous waste

Page 97: Explanatory Memorandum (Rev D)

Page 32 of 99

section 77 (presumption that minerals excepted from acquisition of land);

sections 78 to 83, 85 to 85E and Schedules 1 to 3 (minerals under railways), as respectively substituted and inserted by section 15 of the Mines (Working Facilities and Support) Act 1923; and

section 105 (carriage of dangerous goods on railway), except for the words from "and if any person" to "for every such offence".

(2) The following provisions of the Railways Clauses Act 1863 shall be incorporated in this

Order-- sections 5 and 7 (level crossings); and

section 12 (signals, watchmen etc).

(3) In those provisions, as incorporated in this Order--

"the company" means the undertaker;

9 9

"“the works plans"” means the plans certified as the works plans by the decision-makerSecretary of

State for the purposes of this Order and listed in Part 1 (works plans) of Schedule 2 (plans).

Save for the definition of the “undertaker”, the definitions in paragraph (1) do not apply to (1)

Schedule 10 (deemed marine licence under Part 4 (marine licensing) of the Marine and Coastal

Access Act 2009).

The definition of the “undertaker” in paragraph (1) does not apply to Schedule 11 (protective (2)

provisions).

(2) References in this Order to rights over land include references to rights to do, or to place and(3)

maintain, anything in, on or under land or in the air-space above its surface.

(3) All distances, directions and lengths referred to in this Order or in any document referred to in (4)

this Order are approximate and distances between points on a work comprised in the authorised project

shall bedevelopment are taken to be measured along that work (and in particular in respect of scheduled

linear works referred to in this Order all distances are measured along the indicative pipeline route as

shown on the works plans for that work).Incorporation of the Railway

Clauses Acts 2

(1) The following provisions of the Railways Clauses Consolidation Act 1845 shall be incorporated in this Order--

section 46 (crossing of roads--level crossings), subject to paragraph (4) and article 18 (level

crossings);

section 58 (company to repair roads used by them), except for the words from "and if any question" to the end;section 61 (company to make sufficient approaches and fences to highways crossing on the

level); section 68 (accommodation works by company);

section 71 (additional accommodation works by owners), except for the words "or directed by such justices to be made by the company" and "or, in case of difference, as shall be authorised by two justices";

sections 72 and 73 (supplementary provisions relating to accommodation works);

Page 98: Explanatory Memorandum (Rev D)

"goods" includes any thing conveyed on the railway authorised to be constructed by this

Order; "lease" includes an agreement for a lease;

"prescribed", in relation to any such provision, means prescribed by this Order for the purposes of that provision;

"the railway" means any railway authorised to be constructed by this Order and any other authorised development; and

"the special Act" means this Order.

(4) In section 46 of the Railways Clauses Consolidation Act 1845, as incorporated in this Order, for the proviso there shall be substituted "Provided always that, with the consent of the highway authority and subject to such conditions as the authority may reasonably impose, the railway may be carried across a highway on the level.".

Application and modification

All areas described in square metres in the book of reference are approximate.(5)

A reference in this Order to a work designated by a number, or by a combination of letters and (6)

numbers (for example, “Work No. 2”), is a reference to the work so designated in Schedule 1

(authorised development).

A reference in this Order to a document or plan required to be submitted for certification under (7)

article 49 (certification of plans etc.) is a reference to the version of that document or plan that has been

certified under article 49.

References in this Order to any statute, order, regulation or similar instrument are to be construed (8)

as references to the statute, order, regulation or instrument as amended by any subsequent statute, order,

regulation or instrument or as contained in any subsequent re-enactment.

Application, modification and disapplication of legislative provisions

3

(1) Subject to the modifications set out in paragraph (2) [the following provisions of] the [insert short title of the relevant Act] shall be incorporated in this Order--

—a) Part 1 (public general legislation) of Schedule 12 (miscellaneous controls) to this Order, 3.

which makes provision applying, modifying and excluding statutory provisions which relate to matters

for which provision may be made by this Order, has effect.

The byelaws specified in Part 2 (local legislation) of Schedule 12 (miscellaneous controls) and (1)

any other statutory provision of local application—

have effect subject to the provisions of that Part;(a)

subject to those provisions, have effect subject to the other provisions of this Order, and(b)

subject to those other provisions, are excluded and do not apply to the extent that they would be (c)

inconsistent with a provision of, or the exercise of a power conferred by, this Order.

In particular (and subject to the provisions of Part 2 (local legislation) of Schedule 12 (2)

(miscellaneous controls) in relation to byelaws), a power conferred by this Order may be exercised

despite, and without having regard to, a provision made by or by virtue of a specified enactment, or any

other statutory provision of local application, that—

requires or permits a specified road, path, passage, bridge, parapet, fence or other place or (a)

structure to be kept open or maintained generally or in a specified manner;

requires or permits the provision and maintenance of lights or other apparatus or structures (b)

generally or in a specified manner;

prohibits or restricts (or imposes conditions or penalties on or in relation to) the obstruction or (c)

removal of, or the causing of damage to, a specified place or structure (or class of places or

structures);

10 10

Page 99: Explanatory Memorandum (Rev D)

prohibits or restricts (or imposes conditions on or in relation to) the erection of structures, or the (d)

undertaking of other works, in a specified place or structure (or class of places or structures);

permits or requires a specified place or structure to be closed;(e)

makes provision about the conduct of persons using a specified walkway or other place or (f)

structure (or class of places or structures) whether by prohibiting or restricting movement (of

persons, vehicles or animals) or otherwise;

specifies a minimum or maximum depth for, or otherwise restricts or imposes conditions in (g)

relation to, the laying of pipes or the carrying out of any other works;

prohibits the laying of pipes or the carrying out of any other works generally or without the (h)

consent of a specified person;

makes provision about the construction or maintenance of, or any other matter relating to, pipes, (i)

drains or other means of connecting with sewers;

prohibits or restricts interference with the banks or bed of, or traffic on, the River Ouse, the (j)

River Foulness, Market Weighton Canal, the River Hull, Driffield Canal, Nafferton Highland

Stream, White Dike or Kelk Beck; or

in any other way would or might apply in relation to anything done, or omitted to be done, in the (k)

exercise of a power conferred by this Order.

For the purposes of paragraph (2) a provision is inconsistent with the exercise of a power conferred (3)

by this Order if and in so far as (in particular)—

it would make it an offence to take action, or not to take action, in pursuance of a power (a)

conferred by this Order;

action taken in pursuance of a power conferred by this Order would cause the provision to (b)

apply so as to enable a person to require the taking of remedial or other action or so as to enable

remedial or other action to be taken;

action taken in pursuance of a power or duty under the provision would or might interfere with (c)

the exercise of any work authorised by this Order.

A power conferred by this Order may be exercised despite, and without having regard to, any (4)

provision of byelaws made by the East Riding of Yorkshire Council in its capacity as lead local flood

authority; but this paragraph does not apply to a provision which permits the taking of any action with

the consent of East Riding of Yorkshire Council, of an internal drainage board or of the Environment

Agency.

Where any person notifies the undertaker in writing that anything done or proposed to be done by (5)

the undertaker or by virtue of this Order would amount to a contravention of a statutory provision of

local application, the undertaker must as soon as reasonably practicable, and at any rate within 14 days

of receipt of the notice, respond in writing setting out—

section X [specify relevant section(s)]; andwhether the undertaker agrees that the action (a)

taken or proposed does or would contravene the provision of local application;

section X [specify relevant section(s)].if the undertaker does agree, the grounds (if any) on (b)

which the undertaker believes that the provision is excluded by this article; and

(4) The provisions of the [insert relevant Act] Act [date] as incorporated in this Order shall be modified as follows [insert relevant modifications].

(5) In construing the [insert relevant Act] Act [date] as incorporated the following expressions shall have the following meanings [insert relevant expressions and definitions.

the extent of that exclusion.(c)

11 11

Page 100: Explanatory Memorandum (Rev D)

Page 33 of 99

development consent for the authorised development; and to be carried out within the Order (a)

limits and to be maintained; and

consent to operate and use the authorised development for the purposes for which it is designed.(b)

(b) consent for the ancillary works, to be carried out within the Order limits. Maintenance of

authorised projectdevelopment

5

The undertaker may at any time maintain the authorised development—5.

provided that, following such maintenance, the authorised development may not, save in (a)

immaterial respects, vary from the description of it given in Schedule 1 (authorised

development);

The undertaker may at any time maintain the authorised project, except to the extent that this(b)

Order, or an agreement made under this Order, provides otherwise.

Limits of Ddeviation

6

In carrying out linear works—a) Save in relation to the drainage works (in which case paragraph 6.

(2) applies), the undertaker may--—

in respect of the location of any work comprised in the authorised development deviate laterally(a)

from the lines or situations of the authorised development shown on the works plans to the

extent of the limits of deviation for that work shown on that those plans; and

deviate vertically from the levelscarry out construction activities for the purposes of the(b)

authorised development shown onanywhere within the sections--Order limits.

The undertaker may construct the drainage works anywhere within the Order limits.(1)

(i) Aerial markers, cathodic protection test posts, field boundary markers, transformer rectifier (2)

kiosks and electricity cabinets comprised in the authorised development may deviate vertically from

ground surface levels to any extent not exceeding [insert number]3 metres upwards; or.

(ii) to any extent downwards as may be found to be necessary or convenient.The authorised (3)

development may deviate vertically from ground surface levels to any extent downwards as may be

found to be necessary or convenient.

12 12

PART 2

WORKS PROVISIONS

Principal Ppowers

Development consent etc. granted by the Order

4

Subject to the provisions of this Order and to the requirements in the Schedule 3 (requirements)4.

attached to this Order the undertaker is granted--—

Page 101: Explanatory Memorandum (Rev D)

Defence to proceedings in respect of statutory nuisance

—a) Where proceedings are brought under section 82(1) of the Environmental Protection Act 7.

1990(p) (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance

falling within section 79(1)(g) of that Act (noise emitted from premises so as to be prejudicial to health

or a nuisance) no order may be made, and no fine may be imposed, under section 82(2) of that Act if—

the defendant shows that the nuisance—(a)

relates to premises used by the undertaker for the purposes of or in connection with the (i)

construction or maintenance of the authorised development and that the nuisance is

attributable to the carrying out of the authorised development in accordance with a notice

served under section 60 (control of noise on construction site), or a consent given under

section 61 (prior consent for work on construction site) or 65 (noise exceeding registered

level) of the Control of Pollution Act 1974(q); or

is a consequence of the construction or maintenance of the authorised development and (ii)

cannot reasonably be avoided; or

the defendant shows that the nuisance— (b)

relates to premises used by the undertaker for the purposes of or in connection with the (i)

use of the authorised development and that the nuisance is attributable to the use of the

authorised development which is being used in accordance with Requirement 15 (noise) of

Schedule 3 (requirements); or

is a consequence of the use of the authorised development and cannot reasonably be (ii)

avoided.

Section 61(9) (consent for work on construction site to include statement that it does not of itself (1)

constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the

Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to

consent for registered noise level to be exceeded), do not apply where the consent relates to the use of

premises by the undertaker for the purposes of or in connection with the construction or maintenance of

the authorised development.

Benefit of Order

7

Benefit of Order

—a) Subject to article 8 9 (consent to transfer of benefit of Order) and paragraph (2) of this article,8.

the provisions of articles [ ] and [ ] [specify relevant articles] shallthis Order have effect solely for the

benefit of [specify person, body or class of person]National Grid Carbon.

[NOTE: This article is required where provisions of the Order are specific to a named undertaker or class of undertaker (see section 156(2) of the 2008 Act).]

Consent to transfer

Paragraph (1) does not apply to the benefit of the consent granted by this Order for works carried (1)

out by the undertaker for the benefit or protection of land or persons (including statutory undertakers)

affected by the authorised development.

Transfer of benefit of Order

8

13 13

(p) 1990 c.43; section 82 is amended by section 5 of the Noise and Statutory Nuisance Act 1993 (c.40), Schedule 17 to the Environment Act 1995 (c.25) and section 103 of the Clean Neighbourhoods and Environment Act 2005 (c.16).

(q) 1974 c.40; sections 61 and 65 are amended by section 133 of the Building Act 1984 (c.55), Schedule 24 to the Environment Act 1995 (c.25) and section 162 of, and Schedule 15 to, the Environmental Protection Act 1990 (c.43); there are other amendments

not relevant to this Order.

Page 102: Explanatory Memorandum (Rev D)

(r) Section 48 is amended by the Local Transport Act 2008 (c. 26) s.124(2); section 51 is amended by Schedule 1 to the Traffic Management Act 2004 (c.18).

Page 34 of 99

Street works

9

(1)—a) The undertaker may, for the purposes of the authorised projectdevelopment, enter on so10.

much of any of the streets specified in Schedule B4 (streets subject to street works) as is within the

Order limits and may--—

break up or open the street, or any sewer, drain or tunnel under it (including for the purposes of (a)

carrying out surveys to ascertain the location of apparatus);

tunnel or bore under the street;(b)

place apparatus in the street;(c)

maintain apparatus in the street or change its position; and(d)

execute any works required for or incidental to any works referred to in sub-paragraphs (a), (b), (e)

(c) and to (d) above.

(2) The authority given by paragraph (1) is a statutory right for the purposes of sections 48(3)(1)

(streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the

1991 Act(r).

(3) The provisions of sections 54 (advance notice of certain works) to 106 (index of defined (2)

expressions) of the 1991 Act apply to any street works carried out under paragraph (1). save that—

(4) In this article "apparatus" has the same meaning as in Part 3 of the 1991 Act.

[NOTE: This article should not be used for the purposes of authorising street works that affect a trunk road (as defined in the 1980 Act); no trunk roads should be specified in Schedule B (streets subject to street works). For any street works affecting a trunk road the undertaker should make an application for a licence under section 50 of the 1991 Act.]

section 61(1) of the 1991 Act (under which the consent of the street authority is required for the (a)

placing of apparatus in a protected street) does not apply to the placing of apparatus in the

course of the authorised development;

section 62(2) of the 1991 Act (power following the designation of a protected street to require (b)

removal or repositioning of apparatus already placed in the street) does not, unless otherwise

agreed with the undertaker, apply in relation to apparatus placed in the course of the authorised

development;

section 62(4) of the 1991 Act (power when a designation as a protected street commences or (c)

ceases to give directions with respect to works in progress) does not, unless otherwise agreed

with the undertaker, apply in relation to the authorised development.

In this article “apparatus” and “street works” have the same meanings as in Part 3 (street works in (3)

England and Wales) of the 1991 Act save that “apparatus” further includes pipelines (and parts of

14 14

(1)—a) The undertaker may, with the consent of the [specify person or body] --Secretary of 9.

State—

transfer to another person (“the transferee”) any or all of the benefit of the provisions of this (a)

Order and such related rights as may be agreed between the undertaker and the transferee; or

grant to another person ("“the lessee"”) for a period agreed between the undertaker and the(b)

lessee any or all of the benefit of the provisions of this Order and such related statutory rights

as may be so agreed.

(2) Where an agreement has been made in accordance with paragraph (1) references in this Order(1)

to the undertaker, except in paragraph (3), shall include references to the transferee or the lessee.

(3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or(2)

grant under paragraph (1) shall beis subject to the same restrictions, liabilities and obligations as would

apply under this Order if those benefits or rights were exercised by the undertakerNational Grid Carbon.

Streets

Page 103: Explanatory Memorandum (Rev D)

them), aerial markers, cathodic protection test posts, field boundary markers, transformer rectifier kiosks

and electricity cabinets.

Power to alter layout, etc., of streets

—a) The undertaker may alter the layout of a street specified in column (2) of Schedule 5 (streets 11.

subject to alteration of layout) in the manner specified in relation to that street in column (3).

Without prejudice to the specific powers conferred by article 4 (development consent etc. granted (1)

by the Order) or paragraph (4) but subject to paragraph (3), the undertaker may, for the purposes of

constructing and maintaining the authorised development, alter the layout of any street within the Order

limits and the layout of any street having a junction with such a street; and, without limiting the scope of

this paragraph, the undertaker may—

increase the width of the carriageway of the street by reducing the width of any kerb, footpath, (a)

footway, cycle track, verge or central reservation within the street;

alter the level or increase the width of any such kerb, footpath, footway, cycle track, verge or (b)

central reservation;

reduce the width of the carriageway of the street;(c)

make crossovers and passing places;(d)

carry out works for the provision or alteration of parking places, loading bays and cycle tracks; (e)

and

execute any works required for or incidental to any works referred to in sub-paragraphs (a) to (f)

(e) above.

The powers conferred by paragraph (2) must not be exercised without the consent of the street (2)

authority but such consent must not be unreasonably withheld or delayed.

The undertaker may, for the purposes of the authorised development, enter on so much of any of (3)

the streets specified in Schedule 4 (streets subject to street works) and Schedule 5 (streets subject to

alteration of layout) as is within the Order limits and may—

demolish, remove, replace and relocate any bus shelter and associated bus stop infrastructure;(a)

execute any works to provide or improve sight lines required by the highway authority;(b)

remove and replace kerbs and flume ditches for the purposes of creating permanent and (c)

temporary accesses;

execute and maintain any works to provide hard and soft landscaping;(d)

carry out re-lining and placement of new temporary markings; and(e)

execute any works required for or incidental to any works referred to in sub-paragraphs (a) to (f)

(e) above.

Construction and maintenance of new or, altered or diverted streets

10

(1) —a) Any street (other than [insert relevant private streets]) to be constructed under this12.

Order shallin respect of which the undertaker has given the highway authority notice that this paragraph

applies must be completed to the reasonable satisfaction of the highway authority and, unless otherwise

agreed with the highway authority, shallmust be maintained by and at the expense of the undertaker for a

period of [12 months] from its completion and at the expiry of that period by and at the expense of the

highway authority.

Where a street is altered or diverted under this Order, the altered or diverted part of the street(1)

shallmust, when completed to the reasonable satisfaction of the street authority, unless otherwise agreed

with the street authority, be maintained by and at the expense of the undertaker for athe specified period

of [12 months] from its completion and at the expiry of that period by and at the expense of the street

authority.; and in this paragraph the “specified period” means the later of—

a period of 12 months from that completion; or(a)

if upon the end of that 12 month period the street authority (acting reasonably) provides the (b)

undertaker with written notice that it requires the undertaker to reinstate and make good any

damage or defect in an altered or diverted part of a street, which includes details of the damage

15 15

Page 104: Explanatory Memorandum (Rev D)

Page 35 of 99

whether the undertaker knew, or could reasonably have been expected to know, that the(d)

condition of the part of the street to which the action relates was likely to cause danger to users

of the street;

where the undertaker could not reasonably have been expected to repair that part of the street(e)

before the cause of action arose, what warning notices of its condition had been displayed,

but for the purposes of such a defence it is not relevant to prove that the undertaker had arranged for a

competent person to carry out or supervise the maintenance of the part of the street to which the action

relates unless it is also proved that the undertaker had given the competent person proper instructions

with regard to the maintenance of the street and that the competent person had carried out those

instructions.

(6) Nothing in this article shall--— (6)

prejudices the operation of section 87 of the 1991 Act (prospectively maintainable highways);(a)

and the undertaker shallis not by reason of any duty under thatis article to maintain a street to

be taken to be a street authority in relating to that street for the purposes of Part 3 (street works

in England and Wales) of that Act; or

haves effect in relation to the street works with regard to which the provisions of Part 3 (street (b)

works in England and Wales) of the 1991 Act apply.

StoppingPermanent stopping up of streets 11

(1)—a) Subject to the provisions of this article, the undertaker may, in connection with the carrying13.

out of the authorised project, stop up each of the streets specified in columns (1) and (2) of Parts 1

and 2 of Schedule C (streets to be stopped up) to the extent specified, by reference to the letters

and numbers shown on the works plan, in column (3) of those Parts of that Scheduledevelopment

stop up any street with the consent of the highway authority, which must not be unreasonably withheld or

delayed but the highway authority may attach reasonable conditions to any such consent.

(2) No street specified in columns (1) and (2) of Part 1 of Schedule C (being a street to be stopped(1)

up pursuant to paragraph (1) for which the highway authority acting reasonably requires a substitute is

to be provided) shall may be wholly or partly stopped up under this article unless--—

the new street to be substituted for it, which is specified in column (4) of that Part of that (a)

Schedule, has been completed to the reasonable satisfaction of the street authority and is open

for use; or

a temporary alternative route for the passage of such traffic as could have used the street to be(b)

stopped up is first provided and subsequently maintained by the undertaker, to the reasonable

satisfaction of the street authority, between the commencement and termination points for the

stopping up of the street until the completion and opening of the new street in accordance with

sub-paragraph (a).

16 16

and defect, the date on which all the damage or defects specified in that notice have been

reinstated and made good to the reasonable satisfaction of the street authority.

Where any street not previously part of the public highway is constructed pursuant to this Order it (2)

will on the undertaker giving notice to the highway authority (and street authority if different) that this

paragraph applies be deemed to be dedicated for public use as highway on the completion of that street.

(3) Paragraphs (1) and (2to (3) do not apply in relation to the structure of any bridge or tunnel (3)

carrying a street over or under any railway of the undertaker.

(4) In any action against the undertaker in respect of loss or damage resulting from any failure by it(4)

to maintain a street under this article, it shallwill be a defence (without prejudice to any other defence or

the application of the law relating to contributory negligence) to prove that the undertaker had taken such

care as in all the circumstances was reasonably required to secure that the part of the street to which the

action relates was not dangerous to traffic.

(5) For the purposes of a defence under paragraph (45), the court shallmust in particular have(5)

regard to the following matters--—

the character of the street and the traffic which was reasonably to be expected to use it;(a)

the standard of maintenance appropriate for a street of that character and used by such traffic;(b)

the state of repair in which a reasonable person would have expected to find the street;(c)

Page 105: Explanatory Memorandum (Rev D)

Page 36 of 99

Any person who suffers loss by the suspension or extinguishment of any private right of way under(5)

this article shall beis entitled to compensation to be determined, in case of dispute, under Part 1 of the

1961 Act (determination of questions of disputed compensation).

This article is subject to article 39 15 (apparatus etcand rights of statutory undertakers in (6)

permanently stopped up streets). Application of the 1991 Act

12

Works carried out under this Order in relation to a highway which consists of or includes a carriageway shall be treated for the purposes of Part 3 of the 1991 Act (street works) as major transport works if--

(a)they are of a description mentioned in any of paragraphs (a), (c) to (e), (g) and (h) of section 86(3) of that Act (which defines what highway authority works are major highway works); or

(b)they are works which, had they been carried out by the highway authority, might have been carried out in exercise of the powers conferred by section 64 of the 1980 Act (dual carriageways and roundabouts).

Public rights of way

13

(1) With effect from the [date of publication of this Order] [the date of certification by the local highway authority that the agreed alternative right of way has been created to the standard defined in the implementation plan], [the section of] the public right of way (being a [insert one of: footpath/bridleway/byway open to all traffic/restricted byway]) shown marked in [red] between the points [A] and [B] on the rights plan is extinguished.

(2) With effect from [that same date] [insert later date] an alternative section of [insert description of right of way of that same type] as marked in [green] between the points [C] and [D] on the rights plan is created.

(3) In this article--

"implementation plan" means the written plan agreed between the undertaker and the local highway authority for creation of the agreed alternative right of way to the defined standard; and

"local highway authority" has the same meaning as in section 329(1) of the 1980 Act. Temporary

stopping up of streets and public rights of way

14

17 17

(3) No street specified in columns (1) and (2) of Part 2 of Schedule C (being a street to be stopped(2)

up pursuant to this article for which no substitute is to be provided) shall may be wholly or partly

stopped up under this article unless the condition specified in paragraph (4) is satisfied in relation to all

the land which abuts on either side of the street to be stopped up.

(4) The condition referred to in paragraph (3) is that--—(3)

the undertaker is in possession of the land; or(a)

there is no right of access to the land from the street concerned; or(b)

there is reasonably convenient access to the land otherwise than from the street concerned; or(c)

the owners and occupiers of the land have agreed to the stopping up.(d)

(5) Where a street has been stopped up under this article--—(4)

all rights of way over or along the street so stopped up shall beare extinguished; and(a)

the undertaker may appropriate and use for the purposes of the authorised projectdevelopment(b)

so much of the site of the street as is bounded on both sides by land owned by the undertaker or

as is otherwise provided in this Order.

Page 106: Explanatory Memorandum (Rev D)

Page 37 of 99

any street or public right of way specified as mentioned in paragraph (3) without first(a)

consulting the streethighway authority; and

any other street or public right of way without the consent of the streethighway authority which, (b)

which must not be unreasonably withheld or delayed but the highway authority may attach

reasonable conditions to any such consent.

(5) Any person who suffers loss by the suspension of any private right of way under this article(4)

shall beis entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(determination of questions of disputed compensation).

Apparatus and rights of statutory undertakers in permanently stopped up streets

—a) Where a street is stopped up under article 13 (permanent stopping up of streets), any 15.

statutory utility whose apparatus is under, in, on, along or across the street has the same powers and

rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not been

made.

Where a street is stopped up under article 13 (permanent stopping up of streets), any statutory (1)

utility whose apparatus is under, in, on, over, along or across the street may, and if reasonably requested

to do so by the undertaker must—

remove the apparatus and place it or other apparatus provided in substitution for it in such other (a)

position as the utility may reasonably determine and have power to place it; or

provide other apparatus in substitution for the existing apparatus and place it in such position as (b)

described in sub-paragraph (a).

Subject to the following provisions of this article, the undertaker must pay to any statutory utility (2)

an amount equal to the cost reasonably incurred by the utility in or in connection with—

the execution of the relocation works required in consequence of the stopping up of the street; (a)

and

the doing of any other work or thing rendered necessary by the execution of the relocation (b)

works.

If in the course of the execution of relocation works under paragraph (2)—(3)

apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution (a)

for existing apparatus; or

apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed (b)

at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at

that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not

determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation

works exceeding that which would have been involved if the apparatus placed had been of the existing

type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from

18 18

(1)—a) The undertaker, during and for the purposes of carrying out the authorised14.

projectdevelopment, may temporarily stop up, alter or divert any street or any public right of way and

may for any reasonable time--—

divert the traffic or a class of traffic from the street or public right of way; and(a)

subject to paragraph (2), prevent all persons from passing along the street or public right of (b)

way.

(2) The undertaker shallmust provide reasonable access for pedestrians going to or from premises(1)

abutting a street or public right of way affected by the temporary stopping up, alteration or diversion of a

street or public right of way under this article if there would otherwise be no such access.

(3) Without prejudice to the generality of paragraph (1), the undertaker may temporarily stop up,(2)

alter or divert the streets or public rights of way specified in columns (1) and (2) of Parts 1 and 2 of

Schedule D6 (streets and public rights of way to be temporarily stopped up) to the extent specified, by

reference to the letters and numbers shown on the works planaccess, rights of way and temporary

stopping up plans, in column (3) of Parts 1 and 2 of that Schedule.

(4) The undertaker shallmay not temporarily stop up, alter or divert--—(3)

Page 107: Explanatory Memorandum (Rev D)

this paragraph, would be payable to the statutory utility by virtue of paragraph (3) must be reduced by

the amount of that excess.

For the purposes of paragraph (4)—(4)

an extension of apparatus to a length greater than the length of existing apparatus is not to be (a)

treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

where the provision of a joint in a cable is agreed, or is determined to be necessary, the (b)

consequential provision of a jointing chamber or of a manhole is to be treated as if it also had

been agreed or had been so determined.

An amount which, apart from this paragraph, would be payable to a statutory utility in respect of (5)

works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) must, if the

works include the placing of apparatus provided in substitution for apparatus placed more than 7 years

and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for

renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

Paragraphs (3) to (6) do not apply where the authorised development constitutes major highway (6)

works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act (street

works in England and Wales), but instead—

the allowable costs of the relocation works must be determined in accordance with section 85 of (a)

that Act (sharing of cost of necessary measures) and any regulations for the time being having

effect under that section; and

the allowable costs must be borne by the undertaker and the statutory utility in such proportions (b)

as may be prescribed by any such regulations.

In this article—(7)

“apparatus” has the same meaning as in Part 3 of the 1991 Act (street works in England and

Wales);

“relocation works” means work executed, or apparatus provided, under paragraph (2); and

“statutory utility” means a statutory undertaker for the purposes of the 1980 Act or a public

communications provider as defined in section 151(1) of the Communications Act 2003(s)

(Interpretation of Chapter 1).

Access to works

15

The undertaker may, for the purposes of the construction and/or the maintenance of the authorised16.

project--development—

form and lay out means of access, or improve existing means of access, in the locationas(a)

specified in columns (1) and (2) of Parts 1 and 2 of Schedule E7 (access to works); and

with the approval of the relevant planning authority, which is not to be unreasonably withheld (b)

or delayed, after consultation with the highway authority, form and lay out such other means of

access or improve existing means of access, at such locations within the Order limits as the

undertaker reasonably requires for the purposes of the authorised projectdevelopment.

Traffic regulation

—a) Subject to the provisions of this article and the consent of the traffic authority in whose area 17.

the road concerned is situated, which consent must not be unreasonably withheld or delayed, the

undertaker may, in so far as may be expedient or necessary for the purposes of or in connection with

construction, operation, or maintenance of the authorised development—

revoke, amend or suspend in whole or in part any order made, or having effect as if made, under (a)

the 1984 Act;

permit, prohibit or restrict the stopping, parking, waiting, loading or unloading of vehicles on (b)

any road;

authorise the use as a parking place of any road;(c)

make provision as to the direction or priority of vehicular traffic on any road; and(d)

19 19

(s) 2003 c.21.

Page 108: Explanatory Memorandum (Rev D)

permit or prohibit vehicular access to any road;(e)

either at all times or at times, on days or during such periods as may be specified by the undertaker.

The undertaker may not exercise the powers in paragraph (1) unless it has—(1)

given not less than 4 weeks’ notice in writing of its intention so to do to the chief officer of (a)

police and to the traffic authority in whose area the road is situated; and

advertised its intention in such manner as the traffic authority may specify in writing within 7 (b)

days of its receipt of notice of the undertaker’s intention under sub-paragraph (a).

Any prohibition, restriction or other provision made by the undertaker under paragraph (1)—(2)

has effect as if duly made by, as the case may be—(a)

the traffic authority in whose area the road is situated as a traffic regulation order under (i)

the 1984 Act; or

the local authority in whose area the road is situated as an order under section 32 of the (ii)

1984 Act (power of local authorities to provide parking places); and

is deemed to be a traffic order for the purposes of Schedule 7 to the Traffic Management Act (b)

2004(t) (road traffic contraventions subject to civil enforcement).

Any prohibition, restriction or other provision made under this article may be suspended, varied or (3)

revoked by the undertaker from time to time by subsequent exercise of the powers conferred by

paragraph (1) at any time.

Before complying with the provisions of paragraph (2) the undertaker must consult the chief officer (4)

of police and the traffic authority in whose area the road is situated.

Expressions used in this article and in the 1984 Act have the same meaning in this article as in that (5)

Act.

Agreements with street authorities

16

(1)—a) A street authority and the undertaker may enter into agreements with respect to--—18.

the construction of any new street, including any structure carrying the street over or under a (a)

railwayany part of the authorised by this Orderdevelopment;

the maintenance of the structurestrengthening, improvement, repair or reconstruction of any(b)

bridge or tunnel carrying a street over or under a railway;the powers conferred by this Order;

any stopping up, alteration or diversion of a street authorised by this Order; or(c)

the carrying outundertaking in the street of any of the works referred to in article 9 10(1) (street(d)

works).; and/or

the adoption by a street authority which is a highway authority of works—(e)

undertaken on a street which is existing publicly maintainable highway; and/or(i)

which the undertaker and highway authority agree are to be adopted as publicly (ii)

maintainable highway.

(2) SuchIf such an agreement provides that the street authority must undertake works on behalf of (1)

the undertaker the agreement may, without prejudice to the generality of paragraph (1)--—

make provision for the street authority to carry out any function under this Order which relates(a)

to the street in question;

include an agreement between the undertaker and street authority specifying a reasonable time(b)

for the completion of the works; and

contain such terms as to payment and otherwise as the parties consider appropriate. (c)

Construction of bridges and tunnels

17

20 20

(b) 2004 c.18.

Page 109: Explanatory Memorandum (Rev D)

Page 38 of 99

(2)The undertaker may in constructing any new level crossing alter the level of any highway specified in Schedule K.

(3)The highway authority and the undertaker may enter into agreements with respect to the construction and maintenance of any new level crossing; and such an agreement may contain such terms as to payment or otherwise as the parties consider appropriate.

(4)In this article--

"new level crossing" means the place at which the railway is authorised by this article to cross a highway on the level; and"the railway" means the railway authorised to be constructed by

this Order. Railway and navigation undertakings

19

(1) Subject to the following provisions of this article, the undertaker may not under article 9 (street works) break up or open a street where the street, not being a highway maintainable at public expense (within the meaning of the 1980 Act)--

(a)is under the control or management of, or is maintainable by, railway or tramway undertakers or a navigation authority; or

(b)forms part of a level crossing belonging to any such undertakers or to such an authority or to any other person,

except with the consent of the undertakers or authority or, as the case may be, of the person to whom the level crossing belongs.

(2) Paragraph (1) shall not apply to the carrying out under this Order of emergency works, within the meaning of Part 3 of the 1991 Act.

(3) A consent given for the purpose of paragraph (1) may be made subject to such reasonable conditions as may be specified by the person giving it but shall not be unreasonably withheld.

(4) In this paragraph "navigation authority" means any person who has a duty or power under any enactment to work, maintain, conserve, improve or control any canal or other inland navigation, navigable river, estuary or harbour.

Supplemental Ppowers

Discharge of water

20

21 21

Any bridge or tunnel to be constructed under this Order for carrying a highway over or under a railway shall be constructed in accordance with the plans and specifications approved by the relevant planning authority after consultation with the highway authority.

Level Crossings

18

(1) The undertaker may construct the railway so as to carry it on the level across the highways specified in Schedule K.

Page 110: Explanatory Memorandum (Rev D)

(u) 1991 c.56; section 106 is amended by sections 36(2) and 99 of the Water Act 2003 (c.37); there are other amendments to that section that are not relevant to this Order.

(v) S.I. 2010/675.

(w) 1991 c.57.

Page 39 of 99

(4) The undertaker shallmust not make any opening into any public sewer or drain except--—(3)

in accordance with plans approved by the person to whom the sewer or drain belongs, but such(a)

approval shallmust not be unreasonably withheld or delayed; and

where that person has been given the opportunity to supervise the making of the opening.(b)

(5) The undertaker shallmust not, in carrying out or maintaining works pursuant to this article,(4)

damage or interfere with the bed or banks of any watercourse forming part of a main river.

(6) The undertaker shallmust take such steps as are reasonably practicable to secure that any water(5)

discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be

practicable from gravel, soil or other solid substance, oil or matter in suspension.; but nothing in this

Order requires the undertaker to maintain a watercourse or public sewer or drain or the drainage works.

(7) This article does not authorise the discharge or entry into controlledinland fresh waters or (6)

coastal waters of any matter whose entry or discharge into controlledthose waters is prohibited by

section 85(1), (2) or (3) of the Water Resources Act 1991 (offences of polluting waterregulation 38 of

the Environmental Permitting (England and Wales) Regulations 2010(v).

(8) In this article--— (7)

"“public sewer or drain"” means a sewer or drain which belongs to the Homes and (a)

Communities Agency, the Environment Agency, a harbour authority within the meaning of

section 57 of the Harbours Act 1964, an internal drainage board, a joint planning board, a local

authority, a National Park Authority, or a sewerage undertaker or an urban development

corporation;

“watercourse” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, (b)

sewers and passages through which water flows except a public sewer or drain; and

(b) other expressions, excluding watercourse, used both in this article and in the Water(c)

Resources Act 1991(w) have the same meaning as in that Act.

Protective work to buildings 21

(1)—a) Subject to the following provisions of this article, the undertaker may at its own expense20.

carry out such protective works to any building lying within the Order limits as the undertaker considers

necessary or expedient.

(2) Protective works may be carried out--—(1)

at any time before or during the carrying out in the vicinity of the building of any part of the(a)

authorised projectdevelopment; or

after the completion of that part of the authorised projectdevelopment in the vicinity of the(b)

building at any time up to the end of the period of 5 years beginning with the day on which that

part of the authorised project is first opened for usedevelopment is first brought into operational

use for the purpose for which it was designed.

22 22

(1) —a) The undertaker may use any watercourse or any public sewer or drain for the drainage of19.

water in connection with the carrying out or maintenance of the authorised projectdevelopment and for

that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make

openings into, and connections with, the watercourse, public sewer or drain.

Any dispute arising from the making of connections to or the use of a public sewer or drain by the(1)

undertaker pursuant to paragraph (1) shallis to be determined as if it were a dispute under section 106 of

the Water Industry Act 1991(u) (right to communicate with public sewers).

The undertaker shallmust not discharge any water into any watercourse, public sewer or drain(2)

except with the consent of the person to whom it belongs; and such consent may be given subject to such

terms and conditions as that person may reasonably impose, but shallmust not be unreasonably withheld

or delayed.

Page 111: Explanatory Memorandum (Rev D)

Page 40 of 99

a right under sub-paragraph (4)(a) to enter a building and land within its curtilage; or(c)

a right under sub-paragraph (4)(b) to enter land,(d)

the undertaker shallmust, except in the case of emergency, serve on the owners and occupiers of the

building or land not less than 14 days'’ notice of its intention to exercise that right and, in a case falling

within subparagraph sub-paragraph (a) or (c), specifying the protective works proposed to be carried

out.

(6) Where a notice is served under sub-paragraph (5)(a), (5)(c) or (5)(d), the owner or occupier of(5)

the building or land concerned may, by serving a counter-notice within the period of 10 days beginning

with the day on which the notice was served, require the question whether it is necessary or expedient to

carry out the protective works or to enter the building or land to be referred to arbitration under article

521 (arbitration).

(7) The undertaker shallmust compensate the owners and occupiers of any building or land in(6)

relation to which rights under this article have been exercised for any loss or damage arising to them by

reason of the exercise of those rights.

(8) Where--—(7)

protective works are carried out under this article to a building; and(a)

within the period of 5 years (beginning with the day on which the part of the authorised(b)

projectdevelopment carried out in the vicinity of the building is first opened for usebrought

into operational use for the purpose for which it was designed) it appears that the protective

works are inadequate to protect the building against damage caused by the carrying out or use

of that part of the authorised projectdevelopment,

the undertaker shallmust compensate the owners and occupiers of the building for any loss or damage

sustained by them.

(9) Nothing in this article shall relieverelieves the undertaker from any liability to pay(8)

compensation under section 10(2) of the 1965 Act (compensation for injurious affection).

(10) Any compensation payable under paragraph (7) or (8) shallmust be determined, in case of(9)

dispute, under Part 1 of the 1961 Act ((determination of questions of disputed compensation).

(11) In this article "“protective works"” in relation to a building means--—(10)

underpinning, strengthening and any other works the purpose of which is to prevent damage(a)

which may be caused to the building by the carrying out, maintenance or use of the authorised

projectdevelopment; and

any works the purpose of which is to remedy any damage which has been caused to the building(b)

by the carrying out, maintenance or use of the authorised projectdevelopment.

Authority to survey and investigate the land 22

(1)—a) The undertaker may for the purposes of this Order enter on any land shown within the21.

Order limits or which may be affected by the authorised projectdevelopment and--—

survey and/or investigate the land;(a)

23 23

(3) For the purpose of determining how the functions under this article are to be exercised the(2)

undertaker may enter and survey any building falling within paragraph (1) and any land within its

curtilage.

(4) For the purpose of carrying out protective works under this article to a building the undertaker(3)

may (subject to paragraphs (5) and (6))--—

enter the building and any land within its curtilage; and(a)

where the works cannot be carried out reasonably conveniently without entering land which is(b)

adjacent to the building but outside its curtilage, enter the adjacent land (but not any building

erected on it).

(5) Before exercising--—(4)

a right under paragraph (1) to carry out protective works to a building;(a)

a right under paragraph (3) to enter a building and land within its curtilage;(b)

Page 112: Explanatory Memorandum (Rev D)

Page 41 of 99

The power conferred by sub-paragraph (1)(c) includes without prejudice to the generality of that (1)

sub-paragraph the power to take, and process, samples of or from any of the following found on, in or

over the land—

water;(a)

air;(b)

soil or rock;(c)

its flora;(d)

bodily excretions, or dead bodies, of non-human creatures; or(e)

any non-living thing present as a result of human action.(f)

(2) No land may be entered or equipment placed or left on or removed from the land under(2)

paragraph (1) unless at least 14 days’ notice has been served on every owner and occupier of the land.

(3) Any person entering land under this article on behalf of the undertaker--—(3)

shallmust, if so required entering the land, produce written evidence of their authority to do so;(a)

and

may take with them such vehicles and equipment as are necessary to carry out the survey or,(b)

investigation, monitoring, or to make the trial holes.

(4) No trial holes shallmay be made under this article--—(4)

in land located within the highway boundary without the consent of the highway authority; or(a)

in a private street without the consent of the street authority, but such consent shall not be (b)

unreasonably withheld.

but such consent must not be unreasonably withheld or delayed.

(5) The undertaker shallmust compensate the owners and occupiers of the land for any loss or(5)

damage arising by reason of the exercise of the authority conferred by this article, such compensation to

be determined, in case of dispute, under Part 1 of the 1961 Act (determination of questions of disputed

compensation).

Removal of human remains 23

(1) —a) In this article "“the specified land"” means [insert description of the land]any land 22.

within the Order limits.

(2) Before the undertaker carries out any development or works which will or may disturb any(1)

human remains in the specified land it shallmust remove those human remains from the specified land, or

cause them to be removed, in accordance with the following provisions of this article.

(3) Before any such remains are removed from the specified land the undertaker shallmust give(2)

notice of the intended removal, describing the specified land and stating the general effect of the

following provisions of this article, by--—

publishing a notice once in each of two successive weeks in a newspaper circulating in the area(a)

of the authorised projectdevelopment; and

displaying a notice in a conspicuous place on or near to the specified land.(b)

(4) As soon as reasonably practicable after the first publication of a notice under paragraph (3) the(3)

undertaker shallmust send a copy of the notice to [insertthe relevant localplanning authority].

(5) At any time within 56 days after the first publication of a notice under paragraph (3) any(4)

person who is a personal representative or relative of any deceased person whose remains are interred in

24 24

without prejudice to the generality of sub-paragraph (a), make trial holes in such positions on(b)

the land as the undertaker thinks fit to investigate the nature of the surface layer and/or subsoil

and/or to remove soil samples;

without prejudice to the generality of sub-paragraph (a), carry out ecological and/or(c)

archaeological investigations on suchthe land; and/or

place on, leave on and remove from the land apparatus for use in connection with the survey(d)

and/or investigation of land and, the making of trial holes.

Page 113: Explanatory Memorandum (Rev D)

(x) 1857 c.81; section 25 is amended by the Criminal Justice Act 1982 (c.48) s.46.

Page 42 of 99 representative or relative as that person claims to be, or that the remains in question can

be identified, the question shallmust be determined on the application of either party in a summary

manner by the county court, and the court may make an order specifying who shallmust remove the

remains and as to the payment of the costs of the application.

(8) The undertaker shallmust pay the reasonable expenses of removing and re-interring or(7)

cremating the remains of any deceased person under this article.

(9) If--—(8)

within the period of 56 days referred to in paragraph (5) no notice under that paragraph has(a)

been given to the undertaker in respect of any remains in the specified land; or

such notice is given and no application is made under paragraph (7) within 56 days after the(b)

giving of the notice but the person who gave the notice fails to remove the remains within a

further period of 56 days; or

within 56 days after any order is made by the county court under paragraph (7) any person,(c)

other than the undertaker, specified in the order fails to remove the remains; or

it is determined that the remains to which any such notice relates cannot be identified,(d)

subject to paragraph (10) the undertaker shallmust remove the remains and cause them to be

reinterredre-interred in such burial ground or cemetery in which burials may legally take place as the

undertaker thinks suitable for the purpose; and, so far as possible, remains from individual graves

shallmust be reinterredre-interred in individual containers which shallmust be identifiable by a record

prepared with reference to the original position of burial of the remains that they contain.

(10) If the undertaker is satisfied that any person giving notice under paragraph (5) is the(9)

personal representative or relative as that person claims to be and that the remains in question can be

identified, but that person does not remove the remains, the undertaker shallmust comply with any

reasonable request that person may make in relation to the removal and re-interment or cremation of the

remains.

(11) On the re-interment or cremation of any remains under this article--—(10)

a certificate of re-interment or cremation shallmust be sent by the undertaker to the Registrar(a)

General by the undertaker giving the date of re-interment or cremation and identifying the place

from which the remains were removed and the place in which they were reinterredre-interred or

cremated; and

a copy of the certificate of re-interment or cremation and the record mentioned in paragraph (9)(b)

shallmust be sent by the undertaker to [insertthe relevant localplanning authority] mentioned in

paragraph (4).

(12) The removal of the remains of any deceased person under this article shallmust be carried(11)

out in accordance with any directions which may be given by the Secretary of State.

(13) Any jurisdiction or function conferred on the county court by this article may be exercised by(12)

the district judge of the court.

(14) Section 25 of the Burial Act 1857(x) (bodies not to be removed from burial grounds, save(13)

under faculty, without licence of Secretary of State) shalldoes not apply to a removal carried out in

accordance with this article.

25 25

the specified land may give notice in writing to the undertaker of that person'’s intention to undertake the

removal of the remains.

(6) Where a person has given notice under paragraph (5), and the remains in question can be(5)

identified, that person may cause such remains to be--—

removed and re-interred in any burial ground or cemetery in which burials may legally take(a)

place; or

removed to, and cremated in, any crematorium,(b)

and that person shallmust, as soon as reasonably practicable after such re-interment or cremation,

provide to the undertaker a certificate for the purpose of enabling compliance with paragraph (11).

(7) If the undertaker is not satisfied that any person giving notice under paragraph (5) is(6)

the personal

Page 114: Explanatory Memorandum (Rev D)

(y) S.I. 1950/792.

Page 43 of 99

As from the date on which a compulsory acquisition notice under section 134(3) of the 2008 Act (1)

(notice of authorisation of compulsory acquisition) is served or the date on which the Order land, or

any part of it, is vested in the undertaker, whichever is the later, all rights, trusts and incidents to which

that land or that part of it which is vested (as the case may be) shall be discharged from all rights, trusts

and incidents to which it was previously subject are discharged or suspended, so far as their continuance

would be inconsistent with the exercise of the powers under this Order.

Any person who suffers loss by the extinguishment or suspension of any private right of way under(2)

this article shall beis entitled to compensation to be determined, in case of dispute, under Part 1 of the

1961 Act (determination of questions of disputed compensation).

This article is subject to article 31 (acquisition of land limited to subsoil lying more than 9 metres (3)

beneath surface) and article 35 (temporary use of land for carrying out the authorised project).No

interest in Crown land may be acquired pursuant to this Order unless the appropriate Crown authority

consents to such acquisition.

Compulsory acquisition of land--incorporation of the mineral code

25

[Part(s)] 2 [and 3] of Schedule 2 to the Acquisition of Land Act 1981(minerals) [is/are] incorporated in this Order subject to the modifications that--

(a)paragraph 8(3) is not incorporated;

26 26

Sections 238 and 239 of the 1990 Act (use and development of consecrated land and burial (14)

grounds) apply—

in relation to land, other than a right over land, acquired for the purposes of the authorised (a)

development (whether or not by agreement), so as to permit use by the undertaker in accordance

with the provisions of this Order; and

in relation to a right over land so acquired (whether or not by agreement), or the temporary use (b)

of land pursuant to articles 28 (temporary use of land for carrying out the authorised

development) and 29 (temporary use of land for maintaining the authorised development), so

as to permit the exercise of that right or the temporary use by the undertaker in accordance with

the provisions of this Order, without prejudice to the status of the land over which the right is

exercised as consecrated land,

and in section 238(1)(b) of the 1990 Act reference to a “planning permission” includes this Order, in

section 240(1) of the 1990 Act reference to “regulations made for the purposes of sections 238(3) and

(4) and 239(2)” means, so far as applicable to land or a right over land acquired under this Order,

paragraphs (2) to (13) of this article and in section 240(3) of the 1990 Act reference to a “statutory

undertaker” includes the undertaker and reference to “any other enactment” includes this Order.

The Town and Country Planning (Churches, Places of Religious Worship and Burial Ground) (15)

Regulations 1950(y) do not apply to the authorised development.

PART 3

ACQUISITION AND POSSESSION OF LAND

Powers of AcquisitionCompulsory acquisition

Compulsory acquisition of land 24

(1) —a) The undertaker may acquire compulsorily so much of the Order land as is required for the23.

authorised project [development or to facilitate it, or is incidental, to it][or is required as replacement

land].

(2)As from the date on which a compulsory acquisition notice under section 134(3) of the 2008 Act is

Page 115: Explanatory Memorandum (Rev D)

Page 44 of 99

28

27 27

(b)for "the acquiring authority" substitute "the undertaker";

(c)[insert additional modifications].

Time limit for exercise of authority to acquire land compulsorily

26

(1) After the end of the period of [5 years] beginning on the day on which the Order is made--

(a)no notice to treat shall be served under Part 1 of the 1965 Act; and

(b)no declaration shall be executed under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 as applied by article 29 (application of the Compulsory Purchase (Vesting Declarations) Act 1981).

(2) The authority conferred by article 35

This Order applies to Crown land only to the extent that the appropriate Crown authority consents (4)

to such application.

In this article, “Crown land” and “the appropriate Crown authority” have the same meanings as (5)

those given in section 227 of the 2008 Act.

This article is subject to article 25 (acquisition of subsoil only) and article 28 (temporary use of(6)

land for carrying out the authorised project) shall cease at the end of the period referred to in paragraph

(1), save that nothing in this paragraph shall prevent the undertaker remaining in possession of land after

the end of that period, if the land was entered and possession was taken before the end of that

period.development).

Compulsory acquisition of rights

27

(1) —a) The undertaker may acquire compulsorily the existing rights and create and acquire24.

compulsorily the new rights described in the book of reference and shown on the land plan [rights

plan]plans.

As from the date on which a compulsory acquisition notice is served or the date on which any new(1)

right is vested in the undertaker, whichever is the later, the land over which any new rights is acquired

shall beis discharged from all rights, trusts and incidents to which it was previously subject so far as

their continuance would be inconsistent with the exercise of that new right.

Subject to section 8 of the 1965 Act (other provisions as to divided land), as substituted by article(2)

323 (acquisition of part of certain properties), where the undertaker acquires an existing right over land

under paragraph (1), the undertaker shallis not be required to acquire a greater interest in that land.

Schedule 13 (modification of compensation and compulsory purchase enactments for creation of (3)

new rights) has effect for the purpose of modifying the enactments relating to compensation and the

provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article

of a right over land by the creation of a new right or the imposition of a restrictive covenant.

(4) Any person who suffers loss as a result of the extinguishment or suspension of any private right(4)

of way under this article shall beis entitled to compensation to be determined, in case of dispute, under

Part 1 of the 1961 Act (determination of questions of disputed compensation) .

Private rights of way

Page 116: Explanatory Memorandum (Rev D)

(1) Subject to the provisions of this article, all private rights of way over land subject to compulsory acquisition under this Order shall be extinguished--

No existing right in Crown land may be acquired or new right created and/or acquired pursuant to (5)

this Order unless the appropriate Crown authority consents to such acquisition and/or creation; and in

this paragraph “Crown land” and “the appropriate Crown authority” have the same meanings as those

given in section 227 of the 2008 Act.

Acquisition of subsoil only

—a) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land 25.

referred to in paragraph 23(1) of article 23 (compulsory acquisition of land) as may be required for any

purpose for which that land may be acquired under that provision instead of acquiring the whole of the

land.

Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the (1)

undertaker is not required to acquire an interest in any other part of the land.

Paragraph (2) does not prevent article 33 (acquisition of part of certain properties) from applying (2)

where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building

or manufactory.

Power to override easements and other rights

—a) Any authorised activity which takes place on land within the Order limits (whether the activity 26.

is undertaken by the undertaker or by any person deriving title from the undertaker or by any servants or

agents of the undertaker) is authorised by this Order if it is done in accordance with the terms of this

Order, notwithstanding that it involves—

an interference with an interest or right to which this article applies; or(a)

a breach of a restriction as to the user of land arising by virtue of a contract.(b)

In this article “authorised activity” means—(1)

as from the date of acquisition of the land by the undertaker, whether compulsorily or by (a)

agreement; orthe erection, construction or carrying out, operation or maintenance of any part of

the authorised development;

on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act (power of (b)

entry),the exercise of any power authorised by this Order; or

whichever is the earliest.

(2) Subject to the provisions of this article, all private rights of way over land owned by the undertaker which, being within the limits of land which may be acquired shown on the land plan, is required for the purposes of this Order shall be extinguished on the appropriation of the land by the undertaker for any of those purposes.

(3) Subject to the provisions of this article, all private rights of way over land of which the undertaker takes temporary possession under this Order shall be suspended and unenforceable for as long as the undertaker remains in lawful possession of the land.

(4) Any person who suffers loss by the extinguishment or suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) This article does not apply in relation to any right of way to which section 138 of the 2008 Act (extinguishment of rights, and removal of apparatus, of statutory undertakers etc) or article 38 (statutory undertakers) applies.

(6) Paragraphs (1) to (3) shall have effect subject to--

(a) any notice given by the undertaker before--

(i)the completion of the acquisition of the land;

28 28

Page 117: Explanatory Memorandum (Rev D)

(z) 1981 c.66.

Page 45 of 99 compulsory purchase order and as if the undertaker were a public authority under

section 1(2) of that Act.

(2) The Compulsory Purchase (Vesting Declarations) Act 1981, as so applied, shall havehas effect(1)

with the following modifications.

(3) In section 3 (preliminary notices), for subsection (1) there shall beis substituted--—(2)

"“(1) Before making a declaration under section 4 with respect to any land which is subject to a

compulsory purchase order, the acquiring authority shallmust include the particulars specified in

subsection (3) in a notice which is--—

(a) (a) given to every person with a relevant interest in the land with respect to which the

declaration is to be made (other than a mortgagee who is not in possession); and

(b) (b) published in a local newspaper circulating in the area in which the land is situated."”.

(4) In that section, in subsection (2), for "“(1)(b)"” there shall beis substituted "“(1)"” and(3)

after "“given"” thereshall be is inserted "“and published"”.

(5) In that section, for subsections (5) and (6) there shall beis substituted--—(4)

"“(5) For the purposes of this section, a person has a relevant interest in land if--—

29 29

(ii) the undertaker's appropriation of it;

(iii)the undertaker's entry onto it; or

(iv)the undertaker's taking temporary possession of it,

that any or all of those paragraphs shall not apply to any right of way specified in the notice;

and

(b) any agreement made at any time between the undertaker and the person in or to whom the right of way in question is vested or belongs.

(7) If any such agreement as is referred to in

the use of any land (including the temporary use of land).(c)

The interests and rights to which this article applies include any easement, liberty, privilege, right (2)

or advantage annexed to land and adversely affecting other land, including any natural right to support

and include restrictions as to the user of land arising by virtue of a contract.

Where an interest, right or restriction is overridden by paragraph (6)(b)-- (1), compensation— (3)

is made with a person in or to whom the right of way is vested or belongs; andis payable (a)

under section 7 or 10 of the 1965 Act; and

is expressed to have effect also for the benefit of those deriving title from or under that (b)

person,must be assessed in the same manner and subject to the same rules as in the case of

other compensation under those sections where—

it shall be effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement

the compensation is to be estimated in connection with a purchase under that Act; or(i)

the injury arises from the execution of works on or use of land acquired under that Act.(ii)

Nothing in this article may be construed as authorising any act or omission on the part of any (4)

person which is actionable at the suit of any person on any grounds other than such an interference or

breach as is mentioned in paragraph (1) of this article.

Application of the Compulsory Purchase (Vesting Declarations) Act 1981

29

(1)—a) The Compulsory Purchase (Vesting Declarations) Act 1981 shall apply(z) applies as if27.

this Order were a

Page 118: Explanatory Memorandum (Rev D)

Page 46 of 99

30 30

(a) (a) that person is for the time being entitled to dispose of the fee simple of the land,

whether in possession or in reversion; or

(b) (b) that person holds, or is entitled to the rents and profits of, the land under a lease or

agreement, the unexpired term of which exceeds one month."”.

(6) In section 5 (earliest date for execution of declaration)--—(5)

in subsection (1), after "“publication"” there shall beis inserted "“in a local newspaper(a)

circulating in the area in which the land is situated"”; and

subsection (2) shall beis omitted.(b)

(7) In section 7 (constructive notice to treat), in subsection (1)(a), the words "“(as(6)

modified by section 4 of the Acquisition of Land Act 1981)" shall be” are omitted.

(8) References to the 1965 Act in the Compulsory Purchase (Vesting Declarations) Act 1981shall (7)

are to be construed as references to that Act as applied by section 125 of the 2008 Act to the compulsory

acquisition of land under this Order.Acquisition of

subsoil only 30

(1)The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in article 24(1) (compulsory acquisition of land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.

Temporary possession of land

Temporary use of land for carrying out the authorised development

—a) The undertaker may, in connection with the carrying out of the authorised development—28.

enter on and take temporary possession of— (a)

the land specified in columns (1) and (2) of Schedule 9 (land of which temporary (i)

possession may be taken) for the purpose specified in relation to that land in column (3) of

that Schedule relating to the part of the authorised development specified in column (4) of

that Schedule;

any Order land in respect of which no notice of entry has been served under section 11 of (ii)

the 1965 Act (powers of entry) (other than in connection with the requisition of rights

only) and no declaration has been made under section 4 of the Compulsory Purchase

(Vesting Declarations) Act 1981 (execution of declaration) for the purposes of

constructing and carrying out the authorised development;

remove any buildings and vegetation from the land referred to in paragraphs (1) (a)(i) and (b)

(a)(ii);

construct temporary works (including the provision of means of access) and buildings on the (c)

land referred to in paragraphs (1) (a)(i) and (a)(ii); and

construct and carry out any mitigation works on the land referred to in paragraphs (a)(i) and (d)

(a)(ii).

Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the (1)

undertaker shall not be required to acquire an interest in any other part of the land.Not less than 14 days

before entering on and taking temporary possession of land under this article the undertaker must serve

notice of the intended entry on the owners and occupiers of the land.

Paragraph (2) shall not prevent article 32 (acquisition of part of certain properties) from applying (2)

where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building

or manufactory.The undertaker may not, without the agreement of the owners of the land, remain in

possession of any land under this article—

Acquisition of land limited to subsoil lying more than 9 metres beneath surface

Page 119: Explanatory Memorandum (Rev D)

31

(1)This article applies to the land specified in Schedule F (land of which only subsoil more than 9 metres beneath surface may be acquired).

in the case of land specified in paragraph (1)(a)(i) after the end of the period of one year (a)

beginning with the date of completion the authorised development; or

in the case of land referred to in paragraph (1)(a)(ii), after the end of the period of one year (b)

beginning with the date of completion of the authorised development unless the undertaker has,

before the end of that period, served a notice of entry under section 11 of the 1965 Act or made

a declaration under section 4 of the Compulsory Purchase (Vesting Declaration) Act 1981,

and in this paragraph the date on which the authorised development is completed means the date (c)

on which the undertaker has certified that it is first capable of being brought into operational

use for the purpose for which it was designed.

Before giving up possession of land of which temporary possession has been taken under this (3)

article, unless otherwise agreed by the owners of the land, the undertaker must remove all temporary

works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is

not required to—

replace a building removed under this article;(a)

restore the land on which any permanent works have been constructed under sub-paragraph (b)

(1)(d); or

remove any ground-strengthening works which have been placed in that land to facilitate (c)

construction of the authorised development.

The undertaker must pay compensation to the owners and occupiers of land of which temporary (4)

possession is taken under this article for any loss or damage arising from the exercise in relation to the

land of the provisions of any power conferred by this article.

Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount (5)

of the compensation, must be determined under Part 1 of the 1961 Act (determination of questions of

disputed compensation).

Nothing in this article affects any liability to pay compensation under section 10(2) of the 1965 (6)

Act (further provisions as to compensation for injurious affection) or under any other enactment in

respect of loss or damage arising from the carrying out of the authorised development, other than loss or

damage for which compensation is payable under paragraph (5).

The undertaker may not compulsorily acquire under this Order the land referred to in paragraph (7)

(1)(a)(i), or acquire existing rights or create and acquire new rights over any part of that land under

article 24 (compulsory acquisition of rights), or acquire any part of the subsoil (or rights in the subsoil)

of that land under article 25 (acquisition of subsoil only), except that the undertaker is not be precluded

from—

carrying out protective works on that land under article 20 (protective work to buildings); or(a)

carrying out a survey on that land under article 21 (authority to survey and investigate the (b)

land).

Where the undertaker takes possession of land under this article, the undertaker is not required to (8)

acquire the land or any interest in it.

Section 13 of the 1965 Act(aa) (refusal to give possession to acquiring authority) applies to the (9)

temporary use of land pursuant to this article to the same extent as it applies to the compulsory

acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory

acquisition provisions).

Subject to paragraph (3), nothing in this article prevents the taking of temporary possession (10)

pursuant to it more than once in relation to any land specified in paragraph (1).

31 31

(aa) Section 13 is amended by section 139 of the Tribunals, Courts and Enforcement Act 2007 (c.15).

Page 120: Explanatory Memorandum (Rev D)

Temporary use of land for maintaining the authorised development

—a) Subject to paragraph (2) the undertaker may during the maintenance period—29.

enter on and take temporary possession of any land within the Order limits if such possession is (a)

reasonably required for the purpose of maintaining the authorised development;

enter on any land within the Order limits for the purpose of gaining access as is reasonably (b)

required for the purpose of maintaining the authorised development; and

construct such temporary works (including the provision of means of access) and buildings on (c)

the land as may be reasonably necessary for that purpose.

In the case of land to which this article applies, the undertaker may only acquire compulsorily (1)

under article 24 (compulsory acquisition of land) so much of, or such rights in, the subsoil of the land as

may be required for the purposes of the authorised project.Paragraph (1) does not authorise the

undertaker to take temporary possession of—

any house or garden belonging to a house; or(a)

any building (other than a house) if it is for the time being occupied.(b)

Where the undertaker acquires any part of, or rights in, the subsoil of the land to which this article (2)

applies, the undertaker shall not be required to acquire a greater interest in the land or an interest in any

other part of it.Not less than 28 days before entering on and taking temporary possession of land under

this article the undertaker must serve notice of the intended entry on the owners and occupiers of the

land, except as provided in paragraph (11).

References in this article to the subsoil of land are references to the subsoil lying more than 9 (3)

metres beneath the level of the surface of the land; and for this purpose "level of the surface of the land"

means--The undertaker may only remain in possession of land under this article for so long as may be

reasonably necessary to carry out the maintenance of the part of the authorised development for which

possession of the land was taken.

Before giving up possession of land of which temporary possession has been taken under this (4)

article, the undertaker must remove all temporary works and restore the land to the reasonable

satisfaction of the owners of the land.

The undertaker must pay compensation to the owners and occupiers of land of which temporary (5)

possession is taken under this article for any loss or damage arising from the exercise in relation to the

land of the provisions of this article.

Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount (6)

of the compensation, must be determined under Part 1 of the 1961 Act (determination of questions of

disputed compensation).

Nothing in this article affects any liability to pay compensation under section 10(2) of the 1965 (7)

Act (further provisions as to compensation for injurious affection) or under any other enactment in

respect of loss or damage arising from the maintenance of the authorised development, other than loss or

damage for which compensation is payable under paragraph (6).

Where the undertaker takes possession of land under this article, the undertaker is not required to (8)

acquire the land or any interest in it.

Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the (9)

temporary use of land pursuant to this article to the same extent as it applies to the compulsory

acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory

acquisition provisions).

Where the undertaker has identified a potential risk to the safety of—(10)

the authorised development or any part of it; or(a)

the public; or(b)

the surrounding environment,(c)

the requirement to serve not less than 28 days’ notice under paragraph (3) does not apply and the

undertaker may enter the land pursuant to paragraph (1) subject to giving such period of notice (if any)

as is reasonably practicable in all the circumstances.

32 32

Page 121: Explanatory Memorandum (Rev D)

In this article the “maintenance period” means in relation to any part of the authorised (11)

development the period of 5 years beginning with the date on which the authorised development is first

brought into operational use for the purpose for which it was designed.

Compensation

Disregard of certain interests and improvements

—a) In assessing the compensation payable to any person on the acquisition from that person of 30.

any land or right over any land under this Order, the tribunal must not take into account—

any interest in land; or(a)

any enhancement of the value of any interest in land by reason of any building erected, works (b)

executed or improvement or alteration made on relevant land,

if the tribunal is satisfied that the creation of the interest, the erection of the building, the execution of

the works or the making of the improvement or alteration as part of the authorised development was not

reasonably necessary and was undertaken with a view to obtaining compensation or increased

compensation.

In paragraph (1) “relevant land” means the land acquired from the person concerned or any other (1)

land with which that person is, or was at the time when the building was erected, the works executed or

the improvement or alteration made as part of the authorised development, directly or indirectly

concerned.

Set-off for enhancement in value of retained land

—a) In assessing the compensation payable to any person in respect of the acquisition from that 31.

person under this Order of any land (including the subsoil) the tribunal must set off against the value of

the land so acquired any increase in value of any contiguous or adjacent land belonging to that person in

the same capacity which will accrue to that person by reason of the construction of the authorised

development.

In assessing the compensation payable to any person in respect of the acquisition from that person (1)

of any new rights over land (including the subsoil), under article 24 (compulsory acquisition of rights),

the tribunal must set off against the value of the rights so acquired—

in the case of any land on which a building is erected, the level of the surface of the ground (a)

adjoining the building;any increase in the value of the land over which the new rights are

required; and

in the case of a watercourse or other water area, the level of the surface of the ground nearest to (b)

it which is at all times above water level; orany increase in value of any contiguous or adjacent

land belonging to that person in the same capacity,

which will accrue to that person by reason of the construction of the authorised development.

The 1961 Act has effect, subject to paragraphs (1) and (2), as if this Order were a local enactment (2)

for the purposes of that Act.

No double recovery

Compensation is not payable in respect of the same matter both under this Order and under any 32.

other enactment, any contract or any rule of law, or under two or more different provisions under this

Order.

Supplementary

(c) in any other case, ground surface level. Acquisition of part of certain properties

32

(1)—a) This article shall applyapplies instead of section 8(1) of the 1965 Act (other provisions as33.

divided land) (as applied by section 125 of the 2008 Act) where--—

33 33

Page 122: Explanatory Memorandum (Rev D)

Page 47 of 99

without material detriment to the remainder of the land subject to the counter-notice; or(a)

where the land subject to the notice to treat consists of a house with a park or garden, without(b)

material detriment to the remainder of the land subject to the counter-notice and without

seriously affecting the amenity and convenience of the house,

the notice to treat shall beis deemed to be a notice to treat for that part.

(7) If on such a reference the tribunal determines that--—(6)

the land subject to the notice to treat cannot be taken without material detriment to the(a)

remainder of the land subject to the counter-notice; but

the material detriment is confined to a part of the land subject to the counter-notice,(b)

the notice to treat shall beis deemed to be a notice to treat for the land to which the material detriment is

confined in addition to the land already subject to the notice, whether or not the additional land is land

which the undertaker is authorised to acquire compulsorily under this Order.

(8) If the undertaker agrees to take the land subject to the counter-notice, or if the tribunal(7)

determines that--—

none of the land subject to the notice to treat can be taken without material detriment to the(a)

remainder of the land subject to the counter-notice or, as the case may be, without material

detriment to the remainder of the land subject to the counter-notice and without seriously

affecting the amenity and convenience of the house; and

the material detriment is not confined to a part of the land subject to the counter-notice,(b)

the notice to treat shall beis deemed to be a notice to treat for the land subject to the counter-notice

whether or not the whole of that land is land which the undertaker is authorised to acquire compulsorily

under this Order.

(9) Where, by reason of a determination by the tribunal under this article, a notice to treat is(8)

deemed to be a notice to treat for less land or more land than that specified in the notice, the undertaker

may, within the period of 6 weeks beginning with the day on which the determination is made, withdraw

the notice to treat; and, in that event, shallmust pay the owner compensation for any loss or expense

occasioned to the owner by the giving and withdrawal of the notice, to be determined in case of dispute

by the tribunal.

(10) Where the owner is required under this article to sell only part of a house, building or(9)

manufactory or of land consisting of a house with a park or garden, the undertaker shallmust pay the

34 34

a notice to treat is served on a person ("“the owner"”) under the 1965 Act (as so applied) in(a)

respect of land forming only part of a house, building or manufactory or of land consisting of a

house with a park or garden ("“the land subject to the notice to treat"”); and

a copy of this article is served on the owner with the notice to treat.(b)

(2) In such a case, the owner may, within the period of 21 days beginning with the day on which(1)

the notice was served, serve on the undertaker a counter-notice objecting to the sale of the land subject to

the notice to treat which states that the owner is willing and able to sell the whole ("“the land subject to

the counter-notice"”).

(3) If no such counter-notice is served within that period, the owner shall beis required to(2)

sell the land subject to the notice to treat.

(4) If such a counter-notice is served within that period, the question whether the owner shall beis(3)

required to sell only the land subject to the notice to treat shallmust, unless the undertaker agrees to take

the land subject to the counter-notice, be referred to the tribunal.

(5) If on such a reference the tribunal determines that the land subject to the notice to treat can be(4)

taken--—

without material detriment to the remainder of the land subject to the counter-notice; or(a)

where the land subject to the notice to treat consists of a house with a park or garden, without(b)

material detriment to the remainder of the land subject to the counter-notice and without

seriously affecting the amenity and convenience of the house,

the owner shall be required tomust sell the land subject to the notice to treat.

(6) If on such a reference the tribunal determines that only part of the land subject to the notice to(5)

treat can be taken--—

Page 123: Explanatory Memorandum (Rev D)

Page 48 of 99

within the Order limits as may be required for the purposes of the authorised project and may use the subsoil or air-space for those purposes or any other purpose ancillary to the authorised project.

(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.

(3) Paragraph (2) shall not apply in relation to--

(a)any subway or underground building; or

(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(4) Subject to paragraph (5), any person who is an owner or occupier of land appropriated under paragraph (1) without the undertaker acquiring any part of that person's interest in the land, and who suffers loss as a result, shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Compensation shall not be payable under paragraph (4) to any person who is an undertaker to whom section 85 of the 1991 Act (sharing cost of necessary measures) applies in respect of measures of which the allowable costs are to be borne in accordance with that section.Temporary use of land for carrying out the

authorised project 35

(1) The undertaker may, in connection with the carrying out of the authorised project--

(a)enter on and take temporary possession of the land specified in columns (1) and (2) of Schedule G (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule relating to the part of the authorised project specified in column (4) of that Schedule;

(b)remove any buildings and vegetation from that land; and

35 35

owner compensation for any loss sustained by the owner due to the severance of that part in addition to

the value of the interest acquired.

Application of the Land Compensation Act 1973

33

(1)Any regulations made by the Secretary of State under section 20 (sound proofing of buildings affected by public works) and 20A (power to make payments in respect of caravans and other structures affected by noise of public works) of the Land Compensation Act 1973 which apply to a railway provided or used in the exercise of statutory powers shall apply to the railway comprised in the authorised project as if that railway was provided or used in the exercise of statutory powers.

(2)Section 28 (power to pay expenses) of the Land Compensation Act 1973 shall have effect as if any works comprised in the authorised project were public works for the purposes of that section.

Rights under or over streets

34

(1) The undertaker may enter on and appropriate so much of the subsoil of, or air-space over,

any street

Page 124: Explanatory Memorandum (Rev D)

Page 49 of 99

except that the undertaker shall not be precluded from--

(a)acquiring new rights over any part of that land under article 27 (compulsory acquisition of rights); or

(b)acquiring any part of the subsoil (or rights in the subsoil) of that land under article 30 (acquisition of subsoil only) or in accordance with article 31 (acquisition of land limited to subsoil lying more than 9 metres beneath surface).

(9)Where the undertaker takes possession of land under this article, the undertaker shall not be required to acquire the land or any interest in it.

(10)Section 13 of the 1965 Act (refusal to give possession to acquiring authority) shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).Temporary use of land for maintaining

authorised project 36

(1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised project, the undertaker may--

(a)enter on and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised project; and

36 36

(c)construct temporary works (including the provision of means of access) and buildings on that

land.

(2) Not less than 14 days before entering on and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.

(3) The undertaker may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the part of the authorised project specified in relation to that land in column (4) of Schedule G.

(4) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker shall not be required to replace a building removed under this article.

(5) The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(6) Any dispute as to a person's entitlement to compensation under paragraph (5), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

(7) Nothing in this article shall affect any liability to pay compensation under section 10(2) of the

1965Act (further provisions as to compensation for injurious affection) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised project, other than loss or damage for which compensation is payable under paragraph (5).

(8) The undertaker may not compulsorily acquire under this Order the land referred to in

paragraph (1)

Page 125: Explanatory Memorandum (Rev D)

Page 50 of 99

temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).

(11) In this article "the maintenance period", in relation to any part of the authorised project, means theperiod of 5 years beginning with the date on which that part of the authorised project is first opened for use.

Special category land

37

(1)The special category land shall not vest in the undertaker until the undertaker has acquired the replacement land and [insert name of relevant body] has certified that a scheme for the provision of the replacement land as [common/open space/fuel or field garden allotment] has been implemented to its satisfaction.

(2)On the requirements of paragraph (1) being satisfied, the replacement land shall vest in [insert name of relevant body] subject to the same rights, trusts and incidents as attached to the special category land; and the special category land shall be discharged from all rights, trusts and incidents to which it was previously subject.

37 37

(b)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) Paragraph (1) shall not authorise the undertaker to take temporary possession of--

(a)any house or garden belonging to a house; or

(b)any building (other than a house) if it is for the time being occupied.

(3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.

(4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised project for which possession of the land was taken.

(5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(6) The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(7) Any dispute as to a person's entitlement to compensation under paragraph (6), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

(8) Nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965Act (further provisions as to compensation for injurious affection) or under any other enactment in respect of loss or damage arising from the maintenance of the authorised project, other than loss or damage for which compensation is payable under paragraph (6).

(9) Where the undertaker takes possession of land under this article, the undertaker shall not be required to acquire the land or any interest in it.

(10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) shall apply to

the

Page 126: Explanatory Memorandum (Rev D)

Page 51 of 99

(3) Subject to the following provisions of this article, the undertaker shall pay to any statutory utility anamount equal to the cost reasonably incurred by the utility in or in connection with--

(a)the execution of the relocation works required in consequence of the stopping up of the

street; and

(b)the doing of any other work or thing rendered necessary by the execution of the relocation

works.

(4) If in the course of the execution of relocation works under paragraph (2)--

(a)apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or

38 38

(3)In this article--

"the special category land" means the land identified as forming part of a common, open space, or fuel or field garden allotment in the book of reference and on the plan entitled "Special Category Land Plan" attached to the land plan, which may be acquired compulsorily under this Order and for which replacement land is to be provided; and

"the replacement land" means the land identified in the book of reference and on the plan entitled "Replacement Land Plan" attached to the land plan.

Statutory undertakers

38

—a) The undertaker may--—34.

acquire compulsorily the land belonging to statutory undertakers shown on the land plans within(a)

the limits of the land to be acquired and described in the book of reference;

extinguish the rights of, remove or reposition the apparatus belonging to statutory undertakers(b)

shown on the [insert name] plan and described in the book of reference; andwhere such

apparatus is anywhere within the Order limits; and

acquire compulsorily the new rights over land belonging to statutory undertakers shown on the (c)

[insert name] plan and described in the book of reference. and shown on the land plans.

Apparatus and rights of statutory undertakers in stopped up streets

39

(1)Where a street is stopped up under article 11 (stopping up of streets) any statutory utility whose apparatus is under, in, on, along or across the street shall have the same powers and rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not been made.

Where a street is stopped up under article 11 any statutory utility whose apparatus is under, in, on, (1)

over, along or across the street may, and if reasonably requested to do so by the undertaker shall--Parts 1

and 2 of Schedule 11 (protective provisions) apply to the power in sub-paragraph (1)(b).

(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the utility may reasonably determine and have power to place it; or

(b)provide other apparatus in substitution for the existing apparatus and place it in such position as described in sub-paragraph (a).

Page 127: Explanatory Memorandum (Rev D)

Page 52 of 99 under article 384 (statutory undertakers) any person who is the owner or occupier of

premises to which a supply was given from that apparatus shall beis entitled to recover from the

undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of

the removal, for the purpose of effecting a connection between the premises and any other apparatus

from which a supply is given.

(2) Paragraph (1) shalldoes not apply in the case of the removal of a public sewer but where such a(1)

sewer is removed under article 38,4 any person who is--—

the owner or occupier of premises the drains of which communicated with that sewer; or(a)

39 39

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from this paragraph, would be payable to the statutory utility by virtue of paragraph (3) shall be reduced by the amount of that excess.

(5) For the purposes of paragraph (4)--

(a)an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole shall be treated as if it also had been agreed or had been so determined.

(6) An amount which, apart from this paragraph, would be payable to a statutory utility in respect of works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

(7) Paragraphs (3) to (6) shall not apply where the authorised project constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead--

(a)the allowable costs of the relocation works shall be determined in accordance with section 85 of that Act (sharing of cost of necessary measures) and any regulations for the time being having effect under that section; and

(b)the allowable costs shall be borne by the undertaker and the statutory utility in such proportions as may be prescribed by any such regulations.

(8) In this article--

"apparatus" has the same meaning as in Part 3 of the 1991 Act;

"relocation works" means work executed, or apparatus provided, under paragraph (2); and

"statutory utility" means a statutory undertaker for the purposes of the 1980 Act or a public communications provider as defined in section 151(1) of the Communications Act 2003.

Recovery of costs of new connections 40

(1)—a) Where any apparatus of a public utility undertaker or of a public communications provider35.

is removed

Page 128: Explanatory Memorandum (Rev D)

the owner of a private sewer which communicated with that sewer,(b)

shall beis entitled to recover from the undertaker compensation in respect of expenditure reasonably

incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer

belonging to that person communicate with any other public sewer or with a private sewerage disposal

plant.

(3) This article shalldoes not have effect in relation to apparatus to which article 39 (apparatus and (2)

rights of statutory undertakers in stopped-up streets) or Part 3 of the 1991 Act (street works in England

and Wales) applies.

(4) In this paragraph--—(3)

"“public communications provider"” has the same meaning as in section 151(1) of the

Communications Act 2003(bb); and

"“public utility undertaker"” has the same meaning as in the 1980 Act.

Operations

Operation and use of railways

41

(1)The undertaker may operate and use the railway and any other elements of the authorised project as a system, or part of a system, of transport for the carriage of passengers and goods.

Time limit for exercise of authority to acquire land compulsorily

—a) After the end of the period of 8 years beginning on the day on which this Order is made—36.

no notice to treat is to be served under Part 1 of the 1965 Act; and(a)

no declaration is to be executed under section 4 of the Compulsory Purchase (Vesting (b)

Declarations) Act 1981(cc) as applied by article 27 (application of the Compulsory Purchase

(Vesting Declarations) Act 1981).

The authority conferred by article 28 (temporary use of land for carrying out the authorised (1)

development) ceases at the end of the period referred to in paragraph (1), save that nothing in this

paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land

was entered and possession was taken before the end of that period.

Private rights of way

—a) Subject to the provisions of this article, all private rights of way over land subject to 37.

compulsory acquisition under this Order are extinguished—

as from the date of acquisition of the land by the undertaker, whether compulsorily or by (a)

agreement; or

on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act(dd) (b)

(power of entry),

whichever is the earlier.

Nothing in this Order, or in any enactment incorporated with or applied by this Order, shall (1)

prejudice or affect the operation of Part 1 of the Railways Act 1993 (the provision of railway

services).Subject to the provisions of this article, all private rights of way over land owned by the

undertaker which, being within the limits of land which may be acquired shown on the land plans, is

required for the purposes of this Order are extinguished on the appropriation of the land by the

undertaker for any of those purposes.

40 40

(bb) 2003 c.21; there are amendments to section 151 that are not relevant to this Order.

(cc) 1981 c.66.

(dd) Section 11 is amended by Schedule 4 to the Acquisition of Land Act 1981 (c.67), Schedule 1 to the Housing (Consequential Provisions) Act 1985 (c.71), the Church of England (Miscellaneous Provisions) Measure 2006 No. 1 Sch.5 para.12(1) and

the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307).

Page 129: Explanatory Memorandum (Rev D)

Page 53 of 99

Felling or lopping of trees

45

(1) The undertaker may fell or lop any tree or shrub near any part of the authorised project, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub--

Subject to the provisions of this article, all private rights of way over land of which the undertaker (2)

takes temporary possession under this Order are suspended and unenforceable for as long as the

undertaker remains in lawful possession of the land.

Any person who suffers loss by the extinguishment or suspension of any private right of way under (3)

this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act

(determination of questions of disputed compensation).

This article does not apply in relation to any right of way to which section 138 of the 2008 Act (4)

(extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) or article 34

(statutory undertakers) applies.

Paragraphs (1) to (3) have effect subject to—(5)

any notice given by the undertaker before—(a)

the completion of the acquisition of the land,(i)

the undertaker’s appropriation of it,(ii)

the undertaker’s entry onto it, or(iii)

the undertaker’s taking temporary possession of it,(iv)

that any or all of those paragraphs do not apply to any right of way specified in the notice; and

any agreement made at any time between the undertaker and the person in or to whom the right (b)

of way in question is vested or belongs.

If any such agreement as is referred to in sub-paragraph (6)(b)—(6)

from obstructing or interfering with the construction, maintenance or operation of the authorised (a)

project or any apparatus used in connection with the authorised project; oris made with a person

in or to whom the right of way is vested or belongs; and

41 41

Fares

42

The undertaker may demand, take and recover or waive such charges for carrying passengers or goods on the railway comprised in the authorised project, or for any other services or facilities provided in connection with the operation of that railway, as it thinks fit.

Deemed consent under section 34 of the Coast Protection Act 1949

43

The undertaker is granted deemed consent under section 34 of the Coast Protection Act 1949 to carry out the works described in Schedule H, subject to the requirements set out in that Schedule.

Deemed licence under Part 2 of the Food and Environment Protection Act 1985

44

The undertaker is granted a deemed licence under Part 2 of the Food and Environment Protection Act 1985 to carry out the works described in Schedule I, subject to the requirements set out in that Schedule.

Page 130: Explanatory Memorandum (Rev D)

from constituting a danger to passengers or other persons using the authorised project.is (b)

expressed to have effect also for the benefit of those deriving title from or under that person,

(2) In carrying out any activity authorised by paragraph (1), the undertaker shall do no unnecessary damage to any tree or shrub and shall pay compensation to any person for any loss or damage arising from such activity.

(3) Any dispute as to a person's entitlement to compensation under paragraph (2), or as to the amount of compensation, shall be determined under Part 1 of the 1961 Act.

Trees subject to tree preservation orders

46

(1) The undertaker may fell or lop any tree described in Schedule J and identified on the [insert name] plan, or cut back its roots if it reasonably believes it to be necessary in order to do so to prevent the tree or shrub--

it is effective in respect of the persons so deriving title, whether the title was derived before or after the

making of the agreement.

Rights under or over streets

—a) The undertaker may enter on and appropriate so much of the subsoil of, or air-space over, any 38.

street within the Order limits as may be required for the purposes of the development and may use the

subsoil or air-space for those purposes or any other purpose ancillary to the authorised development.

Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in (1)

relation to a street without being required to acquire any part of the street or any easement or right in the

street.

Paragraph (2) does not apply in relation to—(2)

from obstructing or interfering with the construction, maintenance or operation of the authorised (a)

project or any apparatus used in connection with the authorised project; orany subway or

underground building; or

from constituting a danger to passengers or other persons using the authorised project.any (b)

cellar, vault, arch or other construction in, on or under a street which forms part of a building

fronting onto the street.

(2) In carrying out any activity authorised by paragraph (1)--

Subject to paragraph (5), any person who is an owner or occupier of land appropriated under (3)

paragraph (1) without the undertaker acquiring any part of that person’s interest in the land, and who

suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1 of

the 1961 Act (determination of questions of disputed compensation).

Compensation is not payable under paragraph (4) to any person who is an undertaker to whom (4)

section 85 of the 1991 Act (sharing cost of necessary measures) applies in respect of measures of which

the allowable costs are to be borne in accordance with that section.

Incorporation of the mineral code

Parts 2 and 3 of Schedule 2 to the Acquisition of Land Act 1981(ee) (minerals) are incorporated 39.

in this Order subject to the modifications that—

the undertaker shall do no unnecessary damage to any tree or shrub and shall pay compensation (a)

to any person for any loss or damage arising from such activity; andfor “the acquiring

authority” substitute “the undertaker”;

the duty contained in section 206(1) of the 1990 Act (replacement of trees) shall not (b)

apply.for “undertaking” substitute “authorised development”; and

(3) The authority given by paragraph (1) shall constitute a deemed consent under the relevant tree preservation order.

42 42

(ee) 1981 c.67.

Page 131: Explanatory Memorandum (Rev D)

(ff) 2009 c.23.

Page 54 of 99 granted by or under that agreement is to be provided for that person'’s use.

No enactment or rule of law regulating the rights and obligations of landlords and tenants shall (1)

prejudiceprejudices the operation of any agreement to which this article applies.

Accordingly, no such enactment or rule of law shall applyapplies in relation to the rights and(2)

obligations of the parties to any lease granted by or under any such agreement so as to--—

exclude or in any respect modify any of the rights and obligations of those parties under the(a)

terms of the lease, whether with respect to the termination of the tenancy or any other matter;

confer or impose on any such party any right or obligation arising out of or connected with(b)

anything done or omitted on or in relation to land which is the subject of the lease, in addition to

any such right or obligation provided for by the terms of the lease; or

restrict the enforcement (whether by action for damages or otherwise) by any party to the lease(c)

of any obligation of any other party under the lease.

Deemed consent under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009

—a) A marine licence is deemed to have been issued to the undertaker under Part 4 (marine 42.

licensing) of the Marine and Coastal Access Act 2009(ff).

The marine licence deemed to have been issued under this article is set out at Schedule 10 (deemed (1)

marine licence under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009).

Operational land for purposes of the 1990 Act

48

Development consent granted by this Order shallis to be treated as specific planning permission for43.

the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not being

operational land for the purposes of that Act).

Defence to proceedings in respect of statutory nuisance

43 43

(4) Any dispute as to a person's entitlement to compensation under paragraph (2), or as to the amount of compensation, shall be determined under Part 1 of the 1961 Act

for compulsory purchase order” substitute “this Order”. (c)

Open space

Schedule 8 (record of the satisfaction of the Secretary of State pursuant to section 132 of the 40.

2008 Act) to this Order has effect.

Miscellaneous and General

PART 4

MISCELLANEOUS AND GENERAL

Application of landlord and tenant law

47

(1) —a) This article applies to--—41.

any agreement for leasing to any person the whole or any part of the authorised(a)

projectdevelopment or the right to operate the same; and

any agreement entered into by the undertaker with any person for the construction,(b)

maintenance, use or operation of the authorised projectdevelopment, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease

Page 132: Explanatory Memorandum (Rev D)

49

(1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990 (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraph (g) of section 79(1) of that Act (noise emitted from premises so as to be prejudicial to health or a nuisance) no order shall be made, and no fine may be imposed, under section 82(2) of that Act if--

(a) the defendant shows that the nuisance--

(i)relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project and that the nuisance is attributable to the carrying out of the authorised project in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site) or 65 (noise exceeding registered level), of the Control of Pollution Act 1974; or

(ii)is a consequence of the construction or maintenance of the authorised project and that it cannot reasonably be avoided; or

(b) the defendant shows that the nuisance--

Felling or lopping of trees or shrubs

—a) The undertaker may fell or lop any tree or shrub near any part of the authorised development, 44.

or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—

from obstructing or interfering with the construction, maintenance or operation of the authorised (a)

development or any apparatus used in connection with the authorised development; or

from constituting a danger to persons constructing, maintaining, operating or using the (b)

authorised development.

The undertaker may not pursuant to paragraph (1) fell or lop a tree within the extent of the publicly (1)

maintainable highway without the approval of the highway authority (which is not to be unreasonably

withheld or delayed).

In carrying out any activity authorised by paragraph (1), the undertaker must not cause (2)

unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or

damage arising from such activity.

The undertaker may remove—(3)

hedgerows shown on the hedgerow plans; (a)

with the approval of the relevant planning authority, which is not to be unreasonably withheld (b)

or delayed, any other hedgerow within the Order limits if the undertaker reasonably believes it

to be necessary to do so for the purposes of the construction and/or carrying out of the

authorised development.

The undertaker is not required to obtain any consent to remove a hedgerow referred to in paragraph (4)

( (4)) under the Hedgerows Regulations 1997(gg).

Reference to “planning permission” in regulation 6 (permitted work) of the Hedgerows (5)

Regulations 1997 includes this Order.

In this article—(6)

“hedgerow” includes—(a)

relates to premises used by the undertaker for the purposes of or in connection with the (i)

use of the authorised project and that the nuisance is attributable to the use of the

authorised project which is being used in accordance with a scheme of monitoring and

attenuation of noise agreed with the Commission as described in requirement 25;

orhedgerows to which the Hedgerows Regulations 1997 apply; and

is a consequence of the use of the authorised project and that it cannot reasonably be (ii)

avoided.any part of a hedgerow; and

44 44

(gg) S.I. 1997/1160.

Page 133: Explanatory Memorandum (Rev D)

Page 55 of 99

Protections of Interests

50

the “hedgerow plans” mean the drawings listed in Part 5 (hedgerow plans) of Schedule 2 (b)

(plans) and certified as the hedgerow plans by the Secretary of State for the purposes of this

Order.

Any dispute as to a person’s entitlement to compensation under paragraph (3), or as to the amount (7)

of compensation, is to be determined under Part 1 of the 1961 Act (determination of questions of

disputed compensation).

Trees subject to tree preservation orders

—a) The undertaker may fell or lop any tree in respect of which a tree preservation order has been 45.

made on or after 10 June 2014, or cut back its roots if it reasonably believes it to be necessary in order

to do so to prevent the tree or shrub—

from obstructing or interfering with the construction, maintenance or operation of the authorised (a)

development or any apparatus used in connection with the authorised development; or

from constituting a danger to persons constructing, maintaining, operating or using the (b)

authorised development.

In carrying out any activity authorised by paragraph (1)—(1)

the undertaker must not do unnecessary damage to any tree or shrub and must pay compensation (a)

to any person for any loss or damage arising from such activity; and

the duty contained in section 206(1) of the 1990 Act (replacement of trees) does not apply.(b)

The authority given by paragraph (1) constitutes a deemed consent under the relevant tree (2)

preservation order.

Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount (3)

of compensation, is to be determined under Part 1 of the 1961 Act (determination of questions of

disputed compensation).

In this article “tree preservation order” means an order made or having effect as if made under (4)

section 198 of the 1990 Act (power to make tree preservation orders).

Resumption of land use following certain works

—a) This article applies to the resumption of the use of land used for the specified works for the 46.

use for which that land had normally been used before this Order was made.

Where this article applies, section 57(2) of the 1990 Act (planning permission required for (1)

development) applies as if the development consent granted by this Order were planning permission to

develop land granted for a limited period.

In this article “specified works” means Work Nos. 2A, 7, 12, 14A(a) and paragraph (b) (further (2)

associated development) of Schedule 1 (authorised development).

45 45

(2) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), shall not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project.

Page 134: Explanatory Memorandum (Rev D)

Application of the Community Infrastructure Levy

The Community Infrastructure Levy Regulations 2010(hh) apply to the authorised development as 47.

if this Order were a planning permission (for the purposes of regulation 5(1) of those Regulations) which

(for the purposes of regulation 5(2) of those Regulations) had been granted for a limited period.

Protective provisions

Schedule 11 (protective provisions) to this Order has effect.48.

Schedule L to this Order has effect. Certification of plans etc.

51

(1)—a) The undertaker shallmust, as soon as practicable after the making of this Order, submit to49.

the decision-makerSecretary of State copies of--—

the access, rights of way and temporary stopping up plans;(a)

the approved plans;(b)

the Barmston Pumping Station parameter plan; (c)

(a) the book of reference;(d)

(b) the landCamblesforth Multi-junction parameter plan;(e)

the code of construction practice; (f)

the drainage strategy; (g)

the environmental statement;(h)

the flood risk assessment; (i)

the hedgerow plans; (j)

the land plans;(k)

(c) the rights plan;project design statement; and(l)

(d) the works plans;,(m)

(e)the sections; and

(f) any other plans or documents referred to in this Order, for certification that they are true

copies of the plans or documents referred to in this Order.

(2) A plan or document so certified shall beis admissible in any proceedings as evidence of the(1)

contents of the document of which it is a copy.

Service of notices

—(1) A notice or other document required or authorised to be served, given or supplied under this 50.

Order may be served, given or supplied in any of these ways—

by delivering it to the person on whom it is to be served or to whom it is to be given or supplied;(a)

by leaving it at the usual or last known place of abode of that person or, in a case where an (b)

address for service has been given by that person, at that address;

by sending it by post, addressed to that person at that person’s usual or last known place of (c)

abode or, in a case where an address for service has been given by that person, at that address;

by sending it in a prepaid registered letter, or by the recorded delivery service, addressed to that (d)

person at that person’s usual or last known place of abode or, in a case where an address for

service has been given by that person, at that address;

in a case where an address for service using electronic communications has been given by that (e)

person, by sending it using electronic communications, in accordance with the condition set out

in paragraph (2), to that person at that address;

in the case of an incorporated company or body—(f)

46 46

(hh) S.I. 2010/948.

Page 135: Explanatory Memorandum (Rev D)

by delivering it to the secretary or clerk of the company or body at their registered or (i)

principal office;

by sending it by post, addressed to the secretary or clerk of the company or body at that (ii)

office; or

by sending it in a prepaid registered letter or, or by the recorded delivery service, (iii)

addressed to the secretary or clerk of the company or body at that office.

The condition mentioned in sub-paragraph (1) (e) is that the notice or other document must be -(1)

capable of being accessed by the person mentioned in that provision;(a)

legible in all material respects; and(b)

in a form sufficiently permanent to be used for subsequent reference.(c)

For the purposes of paragraph (2), “legible in all material respects” means that the information (2)

contained in the notice or document is available to that person to no lesser extent than it would be if

served, given or supplied by means of a notice or document in printed form.

Arbitration

52

Any difference or dispute under any provision of this Order (other than a difference or dispute 51.

which falls to be determined by the tribunal) must, unless otherwise provided for in this Order or unless

otherwise agreed between the parties, shall be referred to and settled by a single arbitrator to be agreed

between the parties or, failing agreement, to be appointed on the application of either party (after giving

notice in writing to the other) by the [insert appropriate body]Secretary of State.

Requirements

—a) Schedule 3 (requirements) of this Order has effect.52.

Save for paragraphs 2 (time limits), 3 (approved details), 4 (stages of authorised development), 7 (1)

(European protected species), 8 (scheme of ecological mitigation and reinstatement), 9 (water), 10

(removal of trees and hedgerows), 12 (archaeology), 13 (construction hours), 14 (code of

construction practice), 15 (noise), 18 (construction traffic plan), 19 (restoration of land used

temporarily for construction), 20 (requirement for written approval), 21 (amendments to approved

details), and 22 (decommissioning) of Schedule 3 (requirements) and the definitions in paragraph 1

(interpretation) of Schedule 3 (requirements) which relate to those paragraphs, Schedule 3

(requirements) does not apply to Work Nos. 5C and 15B of Schedule 1 (authorised development) so far

as these fall within the UK marine area.

Procedure in relation to certain approvals etc.

Schedule 14 (procedure in relation to certain approvals etc.) to this Order has effect.53.

Saving for Trinity House

Nothing in this Order prejudices or derogates from any of the rights, duties or privileges of Trinity 54.

House; and in this article “Trinity House” has the same meaning as that given in paragraph 1

(interpretation) of Part 1 of Schedule 10 (deemed marine licence under Part 4 (marine licensing) of

the Marine and Coastal Access Act 2009).

Signed by authority of the Secretary of State

[Name of Secretary of State]

[●] [●] 201[●] Department of [●]

47 47

Page 136: Explanatory Memorandum (Rev D)

SCHEDULES

SCHEDULE 1 Articles 2 and 4

AUTHORISED DEVELOPMENT

Schedule AA nationally significant infrastructure project as defined in sections 14 and 21 of the 2008

Act and associated development within the meaning of section 115 of the 2008 Act comprising the works

described below.Authorised Project

Part 1Authorised Development

[NOTE: This Part should describe as fully as possible the elements of the proposed project (including any associated development), which are development for the purposes of section 32 of the 2008 Act, for which development consent is sought. It should not include any elements of development which would be authorised by specific provisions in the Order.]

Part 2Ancillary Works

[NOTE: This Part should describe as fully as possible the ancillary works for which consent is sought and which are not development within the meaning of section 32 of the 2008 Act and which are not be the subject of a separate provision [article] in this Order.]

Schedule B

In the District of Selby in the County of North Yorkshire and in the East Riding of Yorkshire—

Work No. 1A – A carbon dioxide pipeline inspection facility at Drax, to be known as the Drax PIG

Trap, including the following works and structures—

construction and/or installation of above and below ground piping, piping bridles and bypasses, (a)

insulation joints, valves, actuators, vents, analysers, meters and filtration;

construction and/or installation of a PIG trap reception and insertion area including associated (b)

hard standing, pipe supports, instrument building and associated photo voltaic cells, hard

standing for temporary generator, backfilled pits and chambers, gated security fence and

cameras, pedestrian access, satellite dish, troughs, trays, ducting, drainage and drainage

attenuation, internal vehicular access routes, turning areas, pedestrian areas, post and rail

fencing and landscape screening;

electrical and instrumentation construction and/or installation including instrumentation, (c)

electrical cables, earthing protection, electricity and communications kiosks, satellite dish,

control and telecommunications cables, utilities and utility metering, intruder detection systems

and closed circuit television;

works, including pipes, to enable a tie in to the White Rose carbon capture and storage project (d)

adjacent to Drax power station, Selby; and

48 48

Page 137: Explanatory Memorandum (Rev D)

extensions of those parts of the carbon dioxide pipeline comprised in Work No. 3A, the (e)

cathodic protection facility comprised in Work No. 1B and an access road which link to

elements within this Work No. 1A.

Work No. 1B – A cathodic protection facility including a transformer rectifier kiosk with control

cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic

protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.

Work No. 2A – A temporary pipeline store and office area including temporary–

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

spoil storage areas;(h)

internal haul roads;(i)

access parking; and (j)

water management areas. (k)

Work No. 3A – A carbon dioxide pipeline from Drax PIG Trap (Work No. 1A) to Pear Tree Avenue

(Work No. 3B), approximate chainage 1592 metres, laid in trench, in sleeves or by trenchless methods;

such pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the

true clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or

sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises

to interface with the Drax PIG Trap (Work No. 1A).

Work No. 3B – A carbon dioxide pipeline from and beneath Pear Tree Avenue, approximate chainage

1592 metres, to Carr Lane (Work No. 3C), approximate chainage 2313 metres, laid in trench, in sleeves

or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less

than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 3C – A carbon dioxide pipeline from and beneath Carr Lane, approximate chainage 2313

metres, to Main Road (Work No. 3D), approximate chainage 2972 metres, laid in trench, in sleeves or

by trenchless methods (save beneath the open drain/ditch adjacent to the disused railway embankment at

approximate chainage 2478 metres where it must be laid by trenchless methods); such pipeline to be not

less than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom of

rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not less

than 2 metres below public highways where applicable).

Work No. 3D – A carbon dioxide pipeline from and beneath Main Road, approximate chainage 2972

metres, to Church Dike Lane (Work No. 3E), approximate chainage 3933 metres, laid in trench, in

sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or

1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding

land drains, culverts or sewers and not less than 2 metres below public highways where applicable).

Work No. 3E - A carbon dioxide pipeline from and beneath Church Dike Lane, approximate chainage

3933 metres, to Brickhill Lane (Work No. 3F), approximate chainage 4713 metres, laid in trench, in

sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or

1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding

land drains, culverts or sewers and not less than 2 metres below public highways where applicable).

Work No 3F – A carbon dioxide pipeline from and beneath Brickhill Lane, from approximate chainage

4713 metres to A645 (Work No. 3E), approximate chainage 5298 metres, laid in trench, in sleeves or by

trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less than

1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding

land drains, culverts or sewers and not less than 2 metres below public highways where applicable).

49 49

Page 138: Explanatory Memorandum (Rev D)

Work No. 3G – A carbon dioxide pipeline from and beneath A645, approximate chainage 5298 metres,

to Camblesforth Multi-Junction (Work No. 4A), approximate chainage 5630 metres, laid in trench, in

sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or

not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable) save where the pipeline rises to interface with the Camblesforth Multi Junction (Work No.

4A).

Work No. 4A – A carbon dioxide pipeline multiple inspection facility at Camblesforth, to be known as

the Camblesforth Multi-junction, including the following works and structures—

construction and/or installation of above and below ground piping, piping bridles and bypasses, (a)

insulation joints, valves, actuators and vents;

construction and/or installation of up to 5 PIG trap reception and insertion areas including (b)

associated hard standing, pipe supports, instrument building and associated photo voltaic cells,

hard standing for temporary generator, backfilled pits and chambers, gated security fence,

pedestrian access, satellite dish, troughs, trays, ducting, drainage and drainage attenuation,

internal vehicular access routes, turning areas, pedestrian areas, post and rail fencing and

landscape screening;

electrical and instrumentation construction and/or installation including instrumentation, (c)

electrical cables, earthing protection, electricity and communications kiosks, satellite dish,

control and telecommunications cables, utilities and utility metering, intruder detection systems

and closed circuit television; and

extensions of those parts of the carbon dioxide pipeline comprised in Work No. 3G and Work (d)

No.5A, the cathodic protection facility comprised in Work No. 4B and the road comprised in

Work No. 4C which link to elements within this Work No. 4A.

Work No. 4B – A cathodic protection facility including a transformer rectifier kiosk with control

cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic

protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.

Work No. 4C – A road from A645 / Wade House Lane junction up to and including the carbon dioxide

facility at Camblesforth Multi-junction (Work No. 4A) including any splays, gates, fencing, drainage,

drainage attenuation and interceptors, piped culverts, utilities, associated ducting and landscape works.

Work No. 4D – A temporary pipeline store and office area including temporary–

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

spoil storage areas;(h)

internal haul roads;(i)

access parking; and (j)

water management areas. (k)

CAMBLESFORTH TO TOLLINGHAM

Work No. 5A – A carbon dioxide pipeline from Camblesforth Multi-junction (Work No. 4A) to the

A645, approximate chainage 5984 metres, laid in trench, in sleeves or by trenchless methods; such

pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the true

clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or

sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises

to interface with the Camblesforth Multi-junction (Work No. 4A).

Work No. 5B – A carbon dioxide pipeline from and beneath the A645, approximate chainage 5984

metres to Church Dike Lane (Work No. 5C), approximate chainage 7458 metres, laid in trench, in

50 50

Page 139: Explanatory Memorandum (Rev D)

sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or

not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 5C – A carbon dioxide pipeline from and beneath Church Dike Lane, approximate chainage

7458 metres, to Barmby Road (Work No. 5D), approximate chainage 11,089 metres, laid in trench, in

sleeves or by trenchless methods (save beneath the true clean bottom of the River Ouse where it must be

laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not

less than 1.7 metres below the true clean bottom of rivers (other than beneath the River Ouse, where the

pipeline is to be not less than 3.5 metres below its true clean bottom), streams, open drains, canals or

dykes but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 5D – A carbon dioxide pipeline from and beneath Barmby Road, approximate chainage

11,089 metres, to the A63, Hull Road (Work No. 5E), approximate chainage 12,969 metres, laid in

trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 5E – A carbon dioxide pipeline from and beneath the A63, Hull Road, approximate chainage

129,69 metres, to Brind Lane (Work No. 5F), approximate 15,252 metres, laid in trench, in sleeves or

by trenchless methods (save beneath the Howden to Wressle railway line where it must be laid by

trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not less than

1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding

land drains, culverts or sewers, not less than 2 metres below public highways or not less than 4 metres

below the underside of the railway sleepers comprised in the Howden to Wressle railway line where

applicable).

Work No. 5F – A carbon dioxide pipeline from and beneath Brind Lane, approximate chainage 15,252

metres, to the B1228, Wood Lane (Work No. 5G), approximate chainage 16,603 metres, laid in trench,

in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface

(or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes,

but excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 5G – A carbon dioxide pipeline from and beneath the B1228, Wood Lane, approximate

chainage 16,603 metres, to the A614, Holme Road (Work No. 5H), approximate chainage 20,737

metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres

below ground surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open

drains, canals or dykes, but excluding land drains, culverts or sewers and not less than 2 metres below

public highways where applicable).

Work No. 5H – A carbon dioxide pipeline from and beneath the A614, Holme Road, approximate

chainage 20,737 metres, to Bursea Lane (Work No. 5I), approximate chainage 23,217 metres, laid in

trench, in sleeves or by trenchless methods (save beneath the bed of the River Foulness where it must be

laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not

less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways and the true

clean bottom of the River Foulness where applicable).

Work No. 5I – A carbon dioxide pipeline from and beneath Bursea Lane, approximate chainage 23,217

metres, to Drain Lane (Work No. 5J), approximate chainage 24,757 metres, laid in trench, in sleeves or

by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less

than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 5J – A carbon dioxide pipeline from and beneath Drain Lane, approximate chainage 24,757

metres, to Tollingham Block Valve (Work No. 6A), laid in trench, in sleeves or by trenchless methods;

such pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the

true clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or

51 51

Page 140: Explanatory Memorandum (Rev D)

sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises

to interface with Tollingham Block Valve (Work No 6A).

Work No. 6A – A carbon dioxide pipeline isolation facility at Tollingham, to be known as the

Tollingham Block Valve, including the following works and structures—

construction and/or installation including above and below ground piping, piping bridles and (a)

bypasses, insulation joints, valves, actuators and vents;

construction and/or installation including pipe supports, instrument building and associated (b)

photo voltaic cells, hard standing for temporary generator, backfilled pits and chambers, gated

security fence and cameras, pedestrian access, satellite dish, troughs, trays, ducting, drainage

and drainage attenuation, internal vehicular access routes, turning areas, pedestrian areas, post

and rail fencing and landscape screening;

electrical and instrumentation construction and/or installation including instrumentation, (c)

electrical cables, earthing protection, satellite dish, control and telecommunications cables,

utility metering, intruder detection systems and closed circuit television; and

extensions of those parts of the carbon dioxide pipeline comprised in Work No. 5J and Work (d)

No.8A, the cathodic protection facility comprised in Work No. 6B and the road comprised in

Work No. 6C which link to elements within this Work No. 6A.

Work No. 6B – A cathodic protection facility including a transformer rectifier kiosk with control

cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic

protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.

Work No. 6C - A road from Skiff Lane up to and including the carbon dioxide facility at Tollingham

Block Valve (Work No. 6A) including any splays, gates, fencing, drainage, drainage attenuation and

interceptors, piped culverts, electricity kiosk, utilities, associated ducting and landscape works.

Work No. 6D – A temporary pipeline store and office area including temporary—

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

spoil storage areas;(h)

internal haul roads;(i)

access parking; and (j)

water management areas. (k)

Work No. 7 – A temporary pipeline store and office area to be known as Tollingham Construction

Compound including temporary—

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

spoil storage areas;(h)

internal haul roads;(i)

access parking; (j)

vehicle maintenance area including washing facilities; and (k)

water management areas. (l)

52 52

Page 141: Explanatory Memorandum (Rev D)

TOLLINGHAM TO DALTON

Work No. 8A – A carbon dioxide pipeline from Tollingham Block Valve (Work No. 6A) to Skiff Lane,

approximate chainage 26,010 metres, laid in trench, in sleeves or by trenchless methods; such pipeline to

be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom

of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not

less than 2 metres below public highways where applicable) save where the pipeline rises to interface

with the Tollingham Block Valve (Work No. 6A).

Work No. 8B – A carbon dioxide pipeline from and beneath Skiff Lane, approximate chainage 26,010

metres, to Lock Lane (Work No. 8C), approximate chainage 27,238 metres, laid in trench, in sleeves or

by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less

than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 8C – A carbon dioxide pipeline from and beneath Lock Lane, approximate chainage 27,238

metres, to Sands Lane (Work No. 8D), approximate chainage 29,025 metres, laid in trench, in sleeves or

by trenchless methods (save beneath the bed of the disused Market Weighton Canal where it must be

laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not

less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways or the

beneath the true clean bottom of the disused Market Weighton Canal where applicable).

Work No. 8D – A carbon dioxide pipeline from and beneath Sands Lane, approximate chainage 29,025

metres, to Cliffe Road (Work No. 8E), approximate chainage 32,750 metres, laid in trench, in sleeves or

by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less

than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 8E – A carbon dioxide pipeline from and beneath Cliffe Road, approximate chainage 32,750

metres, to the A1034 Sancton Road (Work No. 8F), approximate chainage 34,547 metres, laid in trench,

in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface

(or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes,

but excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 8F – A carbon dioxide pipeline from and beneath the A1034 Sancton Road, approximate

chainage 34,547 metres, to the A1079 Arras Hill (Work No. 8G), approximate chainage 36,283 metres,

laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below

ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 8G – A carbon dioxide pipeline from and beneath the A1079 Arras Hill, approximate

chainage 36,283 metres, to Kiplingcotes Lane (Work No. 8H), approximate chainage 39,393 metres,

laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below

ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 8H – A carbon dioxide pipeline from and beneath Kiplingcotes Lane, approximate chainage

39,393 metres, to Kiplingcotes Road (Work No. 8I), approximate chainage 40,231 metres, laid in

trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 8I – A carbon dioxide pipeline from and beneath Kiplingcotes Road, approximate chainage

40,231 metres, to Kiplingcotes Race Course Road (Work No. 8J), approximate chainage 40,600 metres,

laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below

ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

53 53

Page 142: Explanatory Memorandum (Rev D)

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 8J – A carbon dioxide pipeline from and beneath Kiplingcotes Race Course Road,

approximate chainage 40,600 metres to Park Road (Work No. 8K), approximate chainage 41,370

metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres

below ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals

or dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 8K – A carbon dioxide pipeline from and beneath Park Road, approximate chainage 41,370

metres, to Holme Wold Road (Work No. 8L), approximate chainage 43,264 metres, laid in trench, in

sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or

1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding

land drains, culverts or sewers and not less than 2 metres below public highways where applicable).

Work No. 8L – A carbon dioxide pipeline from and beneath Holme Wold Road, approximate chainage

43,264 metres to Dalton Block Valve (Work No. 9A), laid in trench, in sleeves or by trenchless

methods; all to be not less than 1.2 metres below ground surface (or 1.7 metres below the true clean

bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and

not less than 2 metres below public highways where applicable) save where the pipeline rises to

interface with Dalton Block Valve (Work No. 9A).

Work No. 9A – A carbon dioxide pipeline isolation facility at Dalton to be known as the Dalton Block

Valve including the following works and structures—

construction and/or installation including above and below ground piping, piping bridles and (a)

bypasses, insulation joints, valves, actuators and vents;

construction and/or installation including pipe supports, instrument building and associated (b)

photo voltaic cells, hard standing for temporary generator, backfilled pits and chambers, gated

security fence and cameras, pedestrian access, satellite dish, troughs, trays, ducting, drainage

and drainage attenuation, internal vehicular access routes, turning areas, pedestrian areas, post

and rail fencing and landscape screening;

electrical and instrumentation construction and/or installation including instrumentation, (c)

electrical cables, earthing protection, satellite dish, control and telecommunications cables,

utility metering, intruder detection systems and closed circuit television; and

extensions of those parts of the carbon dioxide pipeline comprised in Work No. 8L and Work (d)

No.10A, the cathodic protection facility comprised in Work No. 9B and the road comprised in

Work No. 9C which link to elements within this Work No. 9A.

Work No. 9B – A cathodic protection facility including a transformer rectifier kiosk with control

cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic

protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.

Work No. 9C – A road from Lund Wold Road up to and including the carbon dioxide facility at Dalton

Block Valve (Work No. 9A) including any splays, gates, fencing, drainage, drainage attenuation and

interceptors, piped culverts, electricity kiosk, utilities, associated ducting and landscape works.

Work No. 9D – A temporary pipeline store and office area including temporary—

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

spoil storage areas;(h)

internal haul roads;(i)

access parking; and (j)

54 54

Page 143: Explanatory Memorandum (Rev D)

water management areas. (k)

DALTON TO SKERNE

Work No. 10A – A carbon dioxide pipeline from Dalton Block Valve (Work No. 9A) to Lund Wold

Road (Work No. 10B), approximate chainage 45,909 metres, laid in trench, in sleeves or by trenchless

methods; such pipeline to be not less than 1.2 metres below ground surface (or 1.7 metres below the true

clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or

sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises

to interface with the Dalton Block Valve (Work No. 9A).

Work No. 10B – A carbon dioxide pipeline from and beneath Lund Wold Road, approximate chainage

45,909 metres, to Middleton Road (Work No. 10C), approximate chainage 46,874 metres, laid in trench,

in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface

(or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding

land drains, culverts or sewers and not less than 2 metres below public highways where applicable).

Work No. 10C – A carbon dioxide pipeline from and beneath Middleton Road, approximate chainage

46,874 metres, to the B1248 Lund Road (Work No. 10D), approximate chainage 47,913 metres, laid in

trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 10D – A carbon dioxide pipeline from and beneath the B1248 Lund Road, approximate

chainage 47,913 metres, to Middleton Road (Work No. 10E), approximate chainage 48,823 metres, laid

in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways where

applicable).

Work No. 10E - A carbon dioxide pipeline from and beneath Middleton Road, approximate chainage

48,823 metres to unnamed road from Bracken Lane to Burnbutts Lane (Work No. 10F), approximate

chainage 50,921 metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less

than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom of rivers,

streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not less than 2

metres below public highways where applicable).

Work No. 10F – A carbon dioxide pipeline from and beneath unnamed road from Bracken Lane to

Burnbutts Lane, approximate chainage 50,921 metres, to Burnbutts Lane (Work No. 10G), approximate

chainage 51,349 metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less

than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom of rivers,

streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not less than 2

metres below public highways where applicable).

Work No. 10G – A carbon dioxide pipeline from and beneath Burnbutts Lane, approximate chainage

51,349 metres, to Southburn Road (Work No. 10H), approximate chainage 54,681 metres, laid in

trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 10H – A carbon dioxide pipeline from and beneath Southburn Road, approximate chainage

54,681 metres, to the A164, Beverley Road (Work No. 10I), approximate chainage 54,964 metres, laid

in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 10I – A carbon dioxide pipeline from and beneath the A164, Beverley Road, approximate

chainage 54,964 metres, to Jenkinson Lane (Work No. 10J), approximate chainage 55,172 metres, laid

in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

55 55

Page 144: Explanatory Memorandum (Rev D)

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 10J – A carbon dioxide pipeline from and beneath Jenkinson Lane, approximate chainage

55,172 metres, to Ricklepits (Work No. 10K), approximate chainage 57,185 metres, laid in trench, in

sleeves or by trenchless methods (save beneath the Driffield to Hutton Cranswick railway line where it

must be laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface

(or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes,

but excluding land drains, culverts or sewers, not less than 2 metres below public highways or not less

than 4 metres below the underside of the railway sleepers comprised in the Driffield to Hutton

Cranswick railway line where applicable).

Work No. 10K – A carbon dioxide pipeline from and beneath Ricklepits, approximate chainage

57,185metres, to Skerne Block Valve (Work No. 11A), laid in trench, in sleeves or by trenchless

methods; such pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres

below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains,

culverts or sewers and not less than 2 metres below public highways where applicable) save where the

pipeline rises to interface with Skerne Block Valve (Work No. 11A).

Work No. 11A – A carbon dioxide pipeline isolation facility at Skerne, to be known as the Skerne

Block Valve, including the following works and structures—

construction and/or installation of above and below ground piping, piping bridles and bypasses, (a)

insulation joints, valves, actuators and vents;

construction and/or installation of pipe supports, instrument building and associated photo (b)

voltaic cells, hard standing for temporary generator, backfilled pits and chambers, gated

security fence and cameras, pedestrian access, satellite dish, troughs, trays, ducting, drainage

and drainage attenuation, internal vehicular access routes, turning areas, pedestrian areas, post

and rail fencing and landscape screening;

electrical and instrumentation construction and/or installation including instrumentation, (c)

electrical cables, earthing protection, satellite dish, control and telecommunications cables,

utility metering, intruder detection systems and closed circuit television; and

extensions of those parts of the carbon dioxide pipeline comprised in Work No. 10K and Work (d)

No.13A, the cathodic protection facility comprised in Work No. 11B and the road comprised in

Work No. 11C which link to elements within this Work No. 11A.

Work No. 11B – A cathodic protection facility including a transformer rectifier kiosk with control

cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic

protection cables, utility meter and cabling; and cathodic protection test post and aerial markers.

Work No. 11C – A road from Main Street up to and including the carbon dioxide facility at Skerne

Block Valve (Work No. 11A) including any splays, gates, fencing, drainage, drainage attenuation and

interceptors, piped culverts, electricity kiosk, utilities, associated ducting and landscape works.

Work No. 11D – A temporary pipeline store and office area including temporary—

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

spoil storage areas;(h)

internal haul roads;(i)

access parking; and (j)

water management areas. (k)

Work No. 12 – A temporary pipeline store and office area, to be known as the Driffield Construction

Compound, including temporary—

56 56

Page 145: Explanatory Memorandum (Rev D)

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

spoil storage areas;(h)

internal haul roads;(i)

access parking; (j)

vehicle maintenance area including washing facilities; and (k)

water management areas. (l)

SKERNE TO PUMPING STATION

Work No. 13A - A carbon dioxide pipeline from Skerne Block Valve (Work No. 11A) to the B1249,

Frodingham Road (Work No. 13B), approximate chainage 60,990 metres, laid in trench, in sleeves or by

trenchless methods (save beneath the beds of the River Hull and the Driffield Canal where it must be

laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not

less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but

excluding land drains, culverts or sewers and not less than 2 metres below public highways or the true

clean bottom of the River Hull and the Driffield Canal where applicable) save where the pipeline rises to

interface with the Skerne Block Valve (Work No. 11A).

Work No. 13B – A carbon dioxide pipeline from and beneath the B1249, Frodingham Road,

approximate chainage 60,990 metres, to Main Street (Work No. 13C), approximate chainage 64,982

metres, laid in trench, in sleeves or by trenchless methods (save beneath the beds of the Nafferton

Highland Spring Drain, White Dike and Kelk Beck where it must be laid by trenchless methods); such

pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the true

clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or

sewers and not less than 2 metres below public highways and the true clean bottom of the Nafferton

Highland Spring Drain, White Dike and Kelk Beck where applicable).

Work No. 13C – A carbon dioxide pipeline from and beneath Main Street, approximate chainage

64,982 metres, to Gransmoor Road (Work No. 13D), approximate chainage 68,618 metres, laid in

trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground

surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or

dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways

where applicable).

Work No. 13D – A carbon dioxide pipeline from and beneath Gransmoor Road, approximate chainage

68,618 metres, to the A165, Bridlington Road (Work No. 13E), approximate chainage 71,453 metres,

laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below

ground surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains,

canals or dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public

highways where applicable).

Work No 13E – A carbon dioxide pipeline from and beneath the A165, Bridlington Road, approximate

chainage 71,453 metres, to Barmston Pumping Station (Work No. 14A), laid in trench, in sleeves or by

trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less than

1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding

land drains, culverts or sewers and not less than 2 metres below public highways where applicable) save

where the pipeline rises to interface with Barmston Pumping Station (Work No. 14A).

PUMPING STATION

Work No. 14A – A carbon dioxide pumping facility at Barmston, to be known as the Barmston

Pumping Station, including the following works and structures—

temporary working area for constructing the Barmston Pumping Station including temporary—(a)

57 57

Page 146: Explanatory Memorandum (Rev D)

office, welfare and security facilities;(i)

power supplies and temporary lighting;(ii)

enclosures;(iii)

pipe, equipment and fittings storage;(iv)

plant storage(v)

fabrication area;(vi)

waste storage areas;(vii)

spoil handling and storage areas;(viii)

internal haul roads;(ix)

access and parking; and(x)

water management areas;(xi)

water supply works, foul drainage provision, surface water management system and culverting;(b)

construction and/or installation of two PIG trap reception and insertion areas including above (c)

and below ground piping, piping bridles and bypasses, filtration, meters, analysers, pumping

facility bypass, insulation joints, actuators, vents and vent stacks, valves (including non return

valves, emergency shutdown valves and recycle valves), coolers, chillers, monoethylene glycol

(MEG) tank and water tank;

construction and/or installation of pipe supports, local and remote instrument building and (d)

associated photo voltaic cells, control and domestic building, stores areas, workshops, pump

houses, air and nitrogen building, substation, switchroom, variable speed drive containers,

metering buildings, analyser building, associated bottle store and hard standing hard standing

for temporary generator, backfilled pits and chambers, gated security fence and cameras,

pedestrian access, lighting columns, satellite dish, weather station, troughs, trays, ducting,

internal vehicular access routes, turning areas, pedestrian areas, pond, post and rail fencing and

landscape screening, planting and earthworks;

construction and/or installation of instrumentation, electrical cables, earthing protection, (e)

satellite dish, control and telecommunications cables, utility metering, intruder detection

systems and closed circuit television, electrical cables, cathodic protection facility including a

transformer rectifier kiosk, anode canisters, electrical and cathodic protection cables, utility

supplies, meters and cabling, earthing protection, backfilled pits and chambers, electricity and

communications kiosks, control and telecommunications cables, troughs, trays, ducting,

drainage and drainage attenuation; and

extensions of those parts of the carbon dioxide pipeline comprised in Work No. 13E and Work (f)

No. 15A and the road comprised in Work No 14B which link to elements within this Work No.

Work No. 14B – A cathodic protection facility including a transformer rectifier kiosk with control

cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic

protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.

Work No. 14C – Modifications to Sands Road between A165, Bridlington Road and Sands Road track;

modification of junction between Sands Road tarmac road and Sands Road track; upgrading Sands Road

track between junction with Sands Road tarmac road and access to Barmston Pumping Station; and a

road from Sands Road track up to and including the Barmston Pumping Station (Work No. 14A)

including any splays, gates, fencing, drainage, drainage attenuation and interceptors, piped culverts,

utilities, associated ducting and landscape screening.

Work No. 14D – A temporary pipeline store and office areas including temporary—

office, welfare and security facilities;(a)

power supplies and temporary lighting;(b)

enclosures;(c)

pipe, equipment and fittings storage;(d)

plant storage;(e)

fabrication area;(f)

waste storage areas;(g)

58 58

Page 147: Explanatory Memorandum (Rev D)

spoil storage areas;(h)

internal haul roads;(i)

access parking; (j)

vehicle maintenance area including washing facilities; and (k)

water management areas. (l)

LANDFALL

Work No. 15A – A carbon dioxide pipeline from Barmston Pumping Station (Work No. 14A) to a

landfall drive shaft (Work No. 15B), approximate chainage 73,094 metres, laid in trench, in sleeves or

by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface save where the

pipeline rises to interface with the Barmston Pumping Station (Work No. 14A).

Work No. 15B A carbon dioxide pipeline from a landfall drive shaft comprised in this Work No. 15B to

mean low water spring tide (which has the same meaning as that given in Schedule 10 (deemed marine

licence under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009), approximate

chainage 73,568 metres, laid by trench in sleeves or by trenchless methods (save beneath the cliffs

where it must be laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground

surface; and which may include the following works and structures—

temporary working areas including temporary—(a)

office, welfare and security facilities;(i)

power supplies and temporary lighting;(ii)

workshops and stores;(iii)

materials and pipe, equipment and fittings storage;(iv)

water tanks;(v)

control cabin;(vi)

waste storage areas;(vii)

spoil handling and storage areas, spoil separators and settlement lagoons;(viii)

de-watering systems and water management areas; (ix)

generators and switchgear;(x)

air receivers and compressors;(xi)

oil store;(xii)

drive shaft, slip trench;(xiii)

drilling rig, anchor blocks, slip trench;(xiv)

crane working areas;(xv)

reception pit / tie-in pit;(xvi)

access to the drive shaft/ drilling rig and reception area/ beach and parking;(xvii)

construction and installation of the pipeline under the cliffs by trenchless methods which may (b)

include the installation of a concrete sleeve drive shaft and tunnel; backfilling of permanent

structures not less than 1.2 metres below ground surface; and temporary works including tunnel

boring/pipeline drilling, reception pit, hydraulic rams, rollers and brackets and winch;

construction and installation of pipeline within the inter tidal zone which may include (c)

cofferdams and temporary works including crane working areas, raised causeway, channel

dredging, shallow bottomed barge, winch, reception/tie-in pit and spoil storage.

FURTHER ASSOCIATED DEVELOPMENT

In connection with the above Work Nos. further associated development within the Order limits

consisting of—

in relation to Work Nos. 1A, 4A, 6A, 9A, 11A and 14A site preparation works, site clearance (a)

(including fencing, vegetation removal and creation of new footpaths), earthworks (including

soil stripping and storage) and site levelling;

in relation to Work Nos. 1A, 4A, 6A, 9A and 11A establishment of site construction (b)

compounds, storage areas, temporary vehicle parking, construction fencing (including perimeter

59 59

Page 148: Explanatory Memorandum (Rev D)

enclosure and security fencing), construction related buildings, welfare facilities, construction

lighting, haulage roads, fabrication areas, waste storage areas, spoil storage area, access,

parking and water management areas;

installation of wires, cables, conductors, pipes and ducts;(c)

in relation to Work Nos. 3A, 3B, 3C, 3D, 3E, 3F, 3G, 5A, 5B, 5C, 5D, 5E, 5F, 5G, 5H, 5I, 5J, (d)

8A, 8B, 8C, 8D, 8E, 8F, 8G, 8H, 8I, 8J, 8K, 8L, 10A, 10B, 10C, 10D, 10E, 10F, 10G, 10H,

10I, 10J, 10K, 13A, 13B, 13C, 13D, 13E, 15A and 15B pipeline construction works

including—

surveying and setting-out;(i)

breaking-through, site clearance (including vegetation removal) and establishment of (ii)

temporary working area;

installation of demarcation fencing/stockproof fencing/heras fencing or similar;(iii)

pre-construction drainage;(iv)

topsoil stripping;(v)

levelling and benching;(vi)

archaeological surveys and watching brief;(vii)

pipe stringing, pipe bending, end preparation, front end welding, back end welding, (viii)

fabrication welding, pipeline coating, pipeline trench excavation, disruption or

fragmentation of rock (including by mechanical means), dewatering activities, trenchless

crossings, lower and lay, sand padding, backfilling, pipeline tie-ins, re-grading of soil, post

construction drainage, cross-ripping and reinstatement of top-soil, internally swab and

gauge pipeline test sections;

filling, testing and dewatering test sections;(ix)

reinstating test locations;(x)

removing demarcation fencing;(xi)

reinstating boundary walls, hedges, and fencing; (xii)

final gauge plate and calliper surveys;(xiii)

drying and commissioning pipelines; (xiv)

demobilisation from site; and(xv)

works to enable power supplies;(xvi)

works to remove or alter the position of apparatus including mains, sewers, drains and cables (e)

which do not give rise to any materially new or materially different significant effects from

those assessed in the environmental statement;

in relation to Work Nos. 1A, 3A, 3B, 3C, 3D, 3E, 3F, 3G, 4A, 5A, 5B, 5C, 5D, 5E, 5F, 5G, (f)

5H, 5I, 5J, 6A, 8A, 8B, 8C, 8D, 8E, 8F, 8G, 8H, 8I, 8J, 8K, 8L, 9A, 10A, 10B, 10C, 10D,

10E, 10F, 10G, 10H, 10I, 10J, 10K, 11A, 13A, 13B, 13C, 13D, 13E, 14A, 15A, 15B the

location of aerial markers, cathodic protection test posts and field boundary markers;

landscaping and other works to mitigate any adverse effects of the construction, maintenance or (g)

operation of the authorised development which do not give rise to any materially new or

materially different significant effects from those assessed in the environmental statement;

works for the benefit or protection of land affected by the authorised development which do not (h)

give rise to any materially new or materially different significant effects from those assessed in

the environmental statement;

works required for the strengthening, improvement, maintenance or reconstruction of any (i)

streets;

the carrying out of street works pursuant to article 10 (street works), works to alter the layout (j)

of streets pursuant to article 11 (power to alter layout, etc., of streets) and the alteration or

removal of road furniture;

ramps, means of access, provision of footpaths, bridleways, cycleways and footpath linkages;(k)

works for the decommissioning (including removal and demolition), restoration and aftercare of (l)

the authorised development which fall within the scheme approved pursuant to paragraph 22

(decommissioning) of Schedule 3 (requirements);

60 60

Page 149: Explanatory Memorandum (Rev D)

installation of drainage, drainage attenuation and land drainage including outfalls; and(m)

such other works, including working sites, storage areas and works of demolition, as may be (n)

necessary for the purposes of or in connection with the construction or operation of the

authorised development and which do not give rise to any materially different effects from those

assessed in the environmental statement.

61 61

Page 150: Explanatory Memorandum (Rev D)

62

Page 56 of 99SCHEDULE 2

Streets Subject to Street Works

(1) (2)

Area Street subject to street works

Schedule CStreets to be Stopped Up

Part 1Streets for which a Substitute is to be Provided

(1) (2) (3) (4)

Area Street to be stopped up Extent of stopping up New street to be

substituted

Part 2Streets for which No Substitute is to be Provided

(1) (2) (3)

Area Street to be stopped up Extent of stopping up

Schedule DStreets to be Temporarily Stopped Up

(1) (2) (3)

Area Street to be temporarily stopped Extent of temporary stopping up

up

Schedule EAccess to Works

Page 151: Explanatory Memorandum (Rev D)

Sheet 1 of 25 10-2574-GND-01-05-0031

Sheet Number Drawing Number

Sheet 2 of 25

Sheet 3 of 25

Sheet 4 of 25

Sheet 5 of 25

Sheet 6 of 25

Sheet 7 of 25

Sheet 8 of 25

Sheet 9 of 25

Sheet 10 of 25

Sheet 11 of 25

Sheet 12 of 25

Sheet 13 of 25

Sheet 14 of 25

Sheet 15 of 25

Sheet 16 of 25

Sheet 17 of 25

Sheet 18 of 25

Sheet 19 of 25

Sheet 20 of 25

Sheet 21 of 25

Sheet 22 of 25

Sheet 23 of 25

Sheet 24 of 25

Sheet 25 of 25

10-2574-GND-01-05-0032

10-2574-GND-01-05-0033

10-2574-GND-01-05-0034

10-2574-GND-01-05-0035

10-2574-GND-01-05-0036

10-2574-GND-01-05-0037

10-2574-GND-01-05-0038

10-2574-GND-01-05-0039

10-2574-GND-01-05-0040

10-2574-GND-01-05-0041

10-2574-GND-01-05-0042

10-2574-GND-01-05-0043

10-2574-GND-01-05-0044

10-2574-GND-01-05-0045

10-2574-GND-01-05-0046

10-2574-GND-01-05-0047 Rev B

10-2574-GND-01-05-0048 Rev B

10-2574-GND-01-05-0049

10-2574-GND-01-05-0050

10-2574-GND-01-05-0051

10-2574-GND-01-05-0052

10-2574-GND-01-05-0053

10-2574-GND-01-05-0054 Rev B

10-2574-GND-01-05-0055 Rev B

(1) (2)

Area Description of access

PLANS

PART 1 Article 2

WORKS PLANS

Drawing title

63

Works plans

Page 152: Explanatory Memorandum (Rev D)

Location Plan HUMBCC-2014-1-LP-JH-OV

Sheet Number Drawing Number

Land plans

Sheet 1 of 25

Sheet 2 of 25

Sheet 3 of 25

Sheet 4 of 25

Sheet 5 of 25

Sheet 6 of 25

Sheet 7 of 25

Sheet 8 of 25

Sheet 9 of 25

Sheet 10 of 25

Sheet 11 of 25

Sheet 12 of 25

Sheet 13 of 25

Sheet 14 of 25

Sheet 15 of 25

Sheet 16 of 25

Sheet 17 of 25

Sheet 18 of 25

Sheet 19 of 25

Sheet 20 of 25

Sheet 21 of 25

Sheet 22 of 25

Sheet 23 of 25

Sheet 24 of 25

Sheet 25 of 25

HUMBCC-2014-1-LP-JH-S1

HUMBCC-2014-1-LP-JH-S2

HUMBCC-2014-1-LP-JH-S3

HUMBCC-2014-1-LP-JH-S4

HUMBCC-2014-1-LP-JH-S5

HUMBCC-2014-1-LP-JH-S6

HUMBCC-2014-1-LP-JH-S7

HUMBCC-2014-1-LP-JH-S8

HUMBCC-2014-1-LP-JH-S9

HUMBCC-2014-1-LP-JH-S10

HUMBCC-2014-1-LP-JH-S11

HUMBCC-2014-1-LP-JH-S12

HUMBCC-2014-1-LP-JH-S13

HUMBCC-2014-1-LP-JH-S14

HUMBCC-2014-1-LP-JH-S15

HUMBCC-2014-1-LP-JH-S16

HUMBCC-2014-1-LP-JH-S17 Rev G

HUMBCC-2014-1-LP-JH-S18 Rev G

HUMBCC-2014-1-LP-JH-S19

HUMBCC-2014-1-LP-JH-S20

HUMBCC-2014-1-LP-JH-S21

HUMBCC-2014-1-LP-JH-S22

HUMBCC-2014-1-LP-JH-S23

HUMBCC-2014-1-LP-JH-S24 Rev G

HUMBCC-2014-1-LP-JH-S25 Rev G

PART 2 Article 2

LAND PLANS

Drawing title

64

Land plans – Location Plan

Page 153: Explanatory Memorandum (Rev D)

Sheet Number Drawing Number

Access, rights of way and

temporary stopping up plans

Sheet 1 of 25 10-2574-GND-01-05-0061 Rev C

PART 3 Article 2

ACCESS, RIGHTS OF WAY AND TEMPORARY STOPPING UP PLANS

Drawing title

Sheet 2 of 25

Sheet 3 of 25

Sheet 4 of 25

Sheet 5 of 25

Sheet 6 of 25

Sheet 7 of 25

Sheet 8 of 25

Sheet 9 of 25

Sheet 10 of 25

Sheet 11 of 25

Sheet 12 of 25

Sheet 13 of 25

Sheet 14 of 25

Sheet 15 of 25

Sheet 16 of 25

Sheet 17 of 25

Sheet 18 of 25

Sheet 19 of 25

Sheet 20 of 25

Sheet 21 of 25

Sheet 22 of 25

Sheet 23 of 25

Sheet 24 of 25

Sheet 25 of 25

10-2574-GND-01-05-0062

10-2574-GND-01-05-0063

10-2574-GND-01-05-0064

10-2574-GND-01-05-0065

10-2574-GND-01-05-0066

10-2574-GND-01-05-0067

10-2574-GND-01-05-0068

10-2574-GND-01-05-0069

10-2574-GND-01-05-0070

10-2574-GND-01-05-0071

10-2574-GND-01-05-0072

10-2574-GND-01-05-0073

10-2574-GND-01-05-0074

10-2574-GND-01-05-0075

10-2574-GND-01-05-0076

10-2574-GND-01-05-0077 Rev B

10-2574-GND-01-05-0078 Rev B

10-2574-GND-01-05-0079

10-2574-GND-01-05-0080

10-2574-GND-01-05-0081

10-2574-GND-01-05-0082

10-2574-GND-01-05-0083

10-2574-GND-01-05-0084 Rev B

10-2574-GND-01-05-0085 Rev B

65

Page 154: Explanatory Memorandum (Rev D)

B

Camblesforth Multi-junction Planting

Drawing

10-2574-PLN-01-0328 B

A

Drawing Number

Tollingham Block Valve Location Plan 10-2574-PLN-01-0304 A

Drax PIG Trap Elevations (Operational

Site

10-2574-PLN-01-0303

Tollingham Block Valve Planning

Arrangement

10-2574-GA-01-0319 B

B

Revision

Tollingham Block Valve Elevations (N

& E)

10-2574-GA-01-0320 B

Drax PIG Trap Planning Arrangement

Drax PIG Trap Planting Drawing

Tollingham Block Valve Elevations (S

& W)

10-2574-GA-01-0321 B

10-2574-PLN-01-0327 A

Tollingham Block Valve Elevations

(Operational Site)

10-2574-PLN-01-0323 B

10-2574-GA-01-0306 B

Tollingham Block Valve Planting

Drawing

10-2574-PLN-01-0329 B

Camblesforth Multi-junction Location

Plan

10-2574-PLN-01-0326

Dalton Block Valve Location Plan 10-2574-PLN-01-0308 A

A

PART 4 Article 2

APPROVED PLANS

Dalton Block Valve Planning

Arrangement

10-2574-GA-01-0322 B

Drawing title

Camblesforth Multi-junction Planning

Arrangement

Dalton Block Valve Elevations (N &

E)

10-2574-GA-01-0323 B

10-2574-GA-01-0316 B

Dalton Block Valve Elevations (S &

W)

10-2574-GA-01-0324 B

Drax PIG Trap Elevations (N & E) 10-2574-GA-01-0307

Dalton Block Valve Elevations

(Operational Site)

10-2574-PLN-01-0324 B

Camblesforth Multi-junction

Elevations (N & E)

10-2574-GA-01-0317

Dalton Block Valve Planting Drawing 10-2574-PLN-01-0331 B

B

B

Skerne Block Valve Location Plan 10-2574-PLN-01-0310 A

Drax PIG Trap Location Plan A

Camblesforth Multi-junction

Elevations (S & W)

Skerne Block Valve Planning

Arrangement

10-2574-GA-01-0325 B

10-2574-GA-01-0305 B

Skerne Block Valve Elevations (N &

E)

10-2574-GA-01-0326 B

10-2574-PLN-01-0302

Drax PIG Trap Elevations (S & W)

Skerne Block Valve Elevations (S & 10-2574-GA-01-0327 B

Camblesforth Multi-junction

Elevations (Operational Site)

10-2574-PLN-01-0325 B

66

10-2574-GA-01-0308

Page 155: Explanatory Memorandum (Rev D)

10-2574-PLN-01-1050 A

A

Skerne Block Valve Elevations

(Operational Site)

Widening of Sands Road Between

A165 Junction and Site Access

10-2574-PLN-01-1051 A

10-2574-PLN-01-0322

Camblesforth Multi-junction

Permanent Vehicular Access (A645)

Tollingham Construction Compound

Temporary Vehicular Access (Skiff

Lane)

10-2574-PLN-01-1052 A

10-2574-PLN-01-1045 A

Driffield Construction Compound

Temporary Vehicular Access (A614)

10-2574-PLN-01-1053 A

B

Revision

Drax PIG Trap Permanent Vehicular

Access (New Road) Swept Path

Analysis

10-2574-PLN-01-1054 A

Tollingham Block Valve Permanent

Vehicular Access (Skiff Lane)

10-2574-PLN-01-1046

Camblesforth Multi-junction

Permanent Vehicular Access (A645)

Swept Path Analysis

10-2574-PLN-01-1055 A

A

Drawing title

Tollingham Block Valve Permanent

Vehicular Access (Skiff Lane) Swept

Path Analysis

10-2574-PLN-01-1056 A

Skerne Block Valve Planting Drawing

Dalton Block Valve Permanent

Vehicular Access (Lund Wold Road)

Dalton Block Valve Permanent

Vehicular Access (Lund Wold Road)

Swept Path Analysis

10-2574-PLN-01-1057 A

10-2574-PLN-01-1047 A

Skerne Block Valve Permanent

Vehicular Access (Main Street,

Skerne) Swept Path Analysis

10-2574-PLN-01-1058 A

10-2574-PLN-01-0330 B

Barmston Pumping Station Permanent

Vehicular Access (Sands Road) Swept

Path Analysis

10-2574-PLN-01-1059 A

Skerne Block Valve Permanent

Vehicular Access (Main Street,

Skerne)

10-2574-PLN-01-1048

Tollingham Construction Compound

Temporary Vehicular Access (Skiff

Lane) Swept Path Analysis

10-2574-PLN-01-1060 A

A

Drawing Number

Driffield Construction Compound

Temporary Vehicular Access (A614)

Swept Path Analysis

10-2574-PLN-01-1061 A

W)

Barmston Pumping Station Permanent

Vehicular Access (Sands Road)

Typical Temporary Access From

Highway Flumed Ditch Crossing

10-2574-STD-01-1014 A

10-2574-PLN-01-1049 A

Typical Temporary Access From

Highway No Flumed Ditch Crossing

10-2574-STD-01-1015 A

Drax PIG Trap Temporary

Construction Vehicular Access (New

Road)

10-2574-PLN-01-1044

67

Barmston Pumping Station Permanent

Vehicular Access (Sands Road)

Page 156: Explanatory Memorandum (Rev D)

Sheet 10 of 25 10-2574-GND-01-05-0150 rev A

Sheet 3 of 25 10-2574-GND-01-05-0143 rev A

Sheet 11 of 25 10-2574-GND-01-05-0151 rev A

10-2574-GND-01-05-0140 rev A

Sheet Number

Sheet 12 of 25 10-2574-GND-01-05-0152 rev A

Sheet 4 of 25

Sheet 13 of 25 10-2574-GND-01-05-0153 rev A

10-2574-GND-01-05-0144 rev A

Drawing Number

Sheet 14 of 25 10-2574-GND-01-05-0154 rev A

Hedgerow plans Sheet 15 of 25 10-2574-GND-01-05-0155 rev A

Sheet 5 of 25 10-2574-GND-01-05-0145 rev A

Sheet 16 of 25 10-2574-GND-01-05-0156 rev A

Sheet 1 of 25 10-2574-GND-01-05-0141 rev A

Sheet 17 of 25 10-2574-GND-01-05-0157 rev B

Sheet 6 of 25

Sheet 18 of 25 10-2574-GND-01-05-0158 rev B

10-2574-GND-01-05-0146 rev A

PART 5 Article 44

HEDGEROW PLANS

Sheet 19 of 25 10-2574-GND-01-05-0161 rev A

Drawing title

Sheet 20 of 25 10-2574-GND-01-05-0159 rev A

Sheet 7 of 25 10-2574-GND-01-05-0147 rev A

Sheet 21 of 25 10-2574-GND-01-05-0160 rev A

Sheet 2 of 25

Sheet 22 of 25 10-2574-GND-01-05-0162 rev A

Sheet 8 of 25

Sheet 23 of 25 10-2574-GND-01-05-0163 rev A

10-2574-GND-01-05-0148 rev A

10-2574-GND-01-05-0142 rev A

Sheet 24 of 25 10-2574-GND-01-05-0164 rev B

Hedgerow plans – Location

Plan

Sheet 25 of 25 10-2574-GND-01-05-0165 rev B

Sheet 9 of 25 10-2574-GND-01-05-0149 rev A

Location Plan

68

Page 157: Explanatory Memorandum (Rev D)

Table 2

Camblesforth Multi-Junction

Land taken beyond post and rail fence

Parameters for—

Camblesforth Multi-Junction Planning Arrangement Plan No. 10-2574-GA-01-0316 Rev B;

Camblesforth Multi-Junction Elevations (N + E) Plan No. 10-2574-GA-01-0317 Rev B;

Camblesforth Multi-junction Elevations (S & W) Plan No. 10-2574-GA-01-0305 Rev B;and

Camblesforth Multi-junction Elevations (Operational Site) Plan No. 10-2574-PLN-01-0325 Rev B

1 metre wide

1.2 metres high

(a) The parameters in this Table do not apply in the area labelled “Area B” on the plans

referred to in it;

(b) Subject to paragraph (a)—

no element comprised in the authorised development to be located within the area (i)

delineated by the weld mesh security fence shown on the plans referred to in this Table

(whether expressly shown on the plans or not) may exceed a height of 4.6 metres; and

no element comprised in the authorised development shown on the plans referred to (ii)

in this Table and specified in Column 1 of this Table may exceed the height or width

for that element specified in Column 2.

Parameters for—

Drax PIG Trap Planning Arrangement Plan No. 10-2574-GA-01-0306 Rev B;

Drax PIG Trap Elevations (N & E) Plan No. 10-2574-GA-01-0307 Rev B;

Drax PIG Trap Elevations (S & W) Plan No. 10-2574-GA-01-0308 Rev B; and

Drax PIG Trap Elevations (Operational Site) Plan No. 10-2574-PLN-01-0303 Rev B

Weld mesh security fence

Column 1 Column 1

2.4 metres high

Column 1

Post and rail gate or gates 1.2 metres high

Vent stack support

Sterile zone

Post and rail boundary fence 1.2 metres high

2 metres wide

3.1 metres high

Instrument building 3.2 metres high

Column 2

Electrical kiosk

Satellite dish 4.6 metres high

1.8 metres high

(a) No element comprised in the authorised development to be located within the area

delineated by the weld mesh security fence shown on the plans referred to in this Table

(whether expressly shown on the plans or not) may exceed a height of 4.6 metres; and

(b) No element comprised in the authorised development shown on the plans referred to in this

Table and specified in Column 1 of this Table may exceed the height or width for that

element specified in Column 2.

Vent stack support (1) 3.1 metres high

Post and rail fence

Instrument building

Vent stack support (2) 3.1 metres high

3.2 metres high

1.2 metres high

Column 1 Column 2

PART 6 Requirement 3 of Schedule 3

PARAMETERS

Table 1

Drax PIG Trap

Satellite dish 4.6 metres high

69

Cathodic protection kiosk

Page 158: Explanatory Memorandum (Rev D)

1.8 metres high

1.2 metres high

Post and rail gates 1.2 metres high

Table 3

Tollingham Block Valve

Post and rail fence

Cathodic protection kiosk 1.2 metres high

Parameters for—

Tollingham Block Valve Planning Arrangement Plan No. 10-2574-GA-01-0319 Rev B;

Tollingham Block Valve Elevations (N & E) Plan No. 10-2574-GA-01-0320 Rev B;

Tollingham Block Valve Elevations (S & W) Plan No. 10-2574-GA-01-0321 Rev B;

Tollingham Block Valve Elevations (Operational Site) Plan No. 10-2574-PLN-01-0323 Rev B

Sterile zone

Instrument building 3.2 metres high

Weld mesh security fence

(a) No element comprised in the authorised development to be located within the area

delineated by the weld mesh security fence shown on the plans referred to in this Table

(whether expressly shown on the plans or not) may exceed a height of 3.4 metres; and

(b) No element comprised in the authorised development shown on the plans referred to in this

Table and specified in Column 1 of this Table may exceed the height or width for that

element specified in Column 2.

Satellite dish 3.4 metres high

2.4 metres high

2 metres wide

Weld mesh security fence 2.4 metres high

Column 1 Column 2

Weld mesh security fence topped with three

strands of barbed wire

2.88 metres high

1.2 metres high

Weld mesh security fence topped with three

strands of barbed wire

Drainage ditch 2 metres wide

Post and rail fence 1.2 metres high

Post and rail fence with stile 2 metres wide

2.88 metres high

Table 4

Dalton Block Valve

Parameters for—

Camblesforth Multi-Junction Planning Arrangement Plan No. 10-2574-GA-01-0316 Rev B;

Camblesforth Multi-Junction Elevations (N + E) Plan No. 10-2574-GA-01-0317 Rev B;

Camblesforth Multi-junction Elevations (S & W) Plan No. 10-2574-GA-01-0305 Rev B;and

Camblesforth Multi-junction Elevations (Operational Site) Plan No. 10-2574-PLN-01-0325 Rev B

Parameters for—

Dalton Block Valve Planning Arrangement Plan No. 10-2574-GA-01-0322 Rev B;

Dalton Block Valve Elevations (N & E) Plan No. 10-2574-GA-01-0323 Rev B;

Dalton Block Valve Elevations (S & W) Plan No. 10-2574-GA-01-0324 Rev B

Dalton Block Valve Elevations (Operational Site) Plan No. 10-2574-PLN-01-0324 Rev B;

Land taken beyond post and rail fence 1 metre wide

(a) No element comprised in the authorised development to be located within the area

Cathodic protection kiosk

Electrical kiosk meter

Post and rail boundary fence

70

1.2 metres high

Page 159: Explanatory Memorandum (Rev D)

1.2 metres high

Column 1 Column 2

Land taken beyond post and rail fence 1 metre wide

Weld mesh security fence 2.4 metres high

Instrument building 3.2 metres high

Weld mesh security fence topped with three

strands of barbed wire

2.88 metres high

Parameters for—

Dalton Block Valve Planning Arrangement Plan No. 10-2574-GA-01-0322 Rev B;

Dalton Block Valve Elevations (N & E) Plan No. 10-2574-GA-01-0323 Rev B;

Dalton Block Valve Elevations (S & W) Plan No. 10-2574-GA-01-0324 Rev B

Dalton Block Valve Elevations (Operational Site) Plan No. 10-2574-PLN-01-0324 Rev B;

delineated by the weld mesh security fence shown on the plans referred to in this Table

(whether expressly shown on the plans or not) may exceed a height of 3.4 metres; and

(b) No element comprised in the authorised development shown on the plans referred to in this

Table and specified in Column 1 of this Table may exceed the height or width for that

element specified in Column 2.

Post and rail fence with stile (1) 2 metres wide

Satellite dish 3.4 metres high

Post and rail fence with tile (2) 2 metres wide

Post and rail boundary fence 1.2 metres high

Satellite dish 3.4 metres high

Weld mesh security fence 2.4 metres high

Instrument building 3.2 metres high

Post and rail fence 1.2 metres high

Electrical meter kiosk 1.8 metres high

Weld mesh security fence topped with three

strands of barbed wire

2.88 metres high

Post and rail gates 1.2 metres high

Post and rail gates

Table 5

Skerne Block Valve

Post and rail fence 1.2 metres high

1.2 metres high

Parameters for—

Skerne Block Valve Planning Arrangement Plan No. 10-2574-GA-01-0325 Rev B;

Skerne Block Valve Elevations (N & E) Plan No. 10-2574-GA-01-0326 Rev B;

Skerne Block Valve Elevations (S & W) Plan No. 10-2574-GA-01-0327 Rev B;

Skerne Block Valve Elevations (Operational Site) Plan No. 10-2574-PLN-01-0322 Rev B

Cathodic protection kiosk 1.2 metres high

Column 1 Column 2

(a) No element comprised in the authorised development to be located within the area

delineated by the weld mesh security fence shown on the plans referred to in this Table

(whether expressly shown on the plans or not) may exceed a height of 3.4 metres; and

(b) No element comprised in the authorised development shown on the plans referred to in this

Table and specified in Column 1 of this Table may exceed the height or width for that

element specified in Column 2.

71

Cathodic protection kiosk

Page 160: Explanatory Memorandum (Rev D)

B

PART 7 Requirement 3 of Schedule 3

PLANTING DRAWINGS

Drawing title

Tollingham Block Valve Planting

Drawing

10-2574-PLN-01-0329 B

Drax PIG Trap Planting Drawing 10-2574-PLN-01-0327

Dalton Block Valve Planting Drawing 10-2574-PLN-01-0331 B

A

Drawing Number

Skerne Block Valve Planting Drawing 10-2574-PLN-01-0330 B

Revision

Camblesforth Multi-junction Planting

Drawing

72

10-2574-PLN-01-0328

Page 161: Explanatory Memorandum (Rev D)

(ii) S.I. 2010/490.

73

SCHEDULE 3 Article 52

REQUIREMENTS

Interpretation

—a) In this Schedule—1.

“the 2010 Regulations” means the Conservation of Habitats and Species Regulations 2010(ii);

“AGIs” means Above Ground Installations, namely those parts of the authorised development that

are the Drax PIG trap, Camblesforth Multi-junction, Tollingham, Skerne and Dalton Block Valves

and Barmston Pumping Station;

“Area B” means the area identified as “Area B” on drawing no.10-2574-GA-01-0316 rev A

(Camblesforth MJ Planning Arrangement) listed in Part 4 of Schedule 2 (plans) as the southern

area of the Camblesforth Multi-junction site to accommodate apparatus including up to 3 PIG traps;

“Barmston Pumping Station” means that part of the authorised development described in Work No.

14A of Schedule 1 (authorised development);

“Camblesforth Multi-junction” means that part of the authorised development described in Work

No. 4A of Schedule 1 (authorised development);

“code of construction practice” means the document(s) given application document reference 7.5 and

certified as the code of construction practice by the Secretary of State for the purposes of this Order;

“commence (type 1)” means beginning to carry out any material operation (as defined in section 155

of the 2008 Act) other than operations consisting of site clearance, demolition work, archaeological

investigations and removal works, investigations for the purpose of assessing ground and geological

conditions, remedial work in respect of any contamination or other adverse ground conditions,

diversion and laying of services for temporary offices, delivery and storage of equipment and

materials to construction compounds, temporary site accommodation, de-vegetation, necessary

pre-commencement environmental mitigation, erection of any temporary means of enclosure, the

temporary display of site notices or advertisement; and “commencement (type 1)” and “commenced

(type 1)” are to be construed accordingly;

“commence (type 2)” means beginning to carry out any material operation (as defined in section 155

of the 2008 Act); and “commencement (type 2)” and “commenced (type 2)” are to be construed

accordingly;

“commence (type 3)” means beginning to carry out any material operation (as defined in section 155

of the 2008 Act) other than operations consisting of archaeological investigations and removal

works, investigations for the purpose of assessing ground and geological conditions, remedial work

in respect of any contamination or other adverse ground conditions, de-vegetation, necessary

pre-commencement environmental mitigation, the temporary display of site notices or

advertisements; and “commencement (type 3)” and “commenced (type 3)” are to be construed

accordingly;

“construction compounds” means the temporary compounds needed to store equipment, materials

and site accommodation during the construction of the authorised development;

“construction work” means works to construct the authorised development, or relevant part of it,

excluding mobilisation of plant and equipment into, out of or within the Order limits;

“the Environment Agency” means the body established under the Environment Act 1995(c) or any

successor to its statutory functions;

“European protected species” has the same meaning as in regulation 40 of the 2010 Regulations;

“European site” has the same meaning as it has in regulation 8(1) of the 2010 Regulations;

“Requirement” means the appropriate numbered paragraph or paragraphs in this Schedule to which

reference is made, for example “Requirement 6” or “these Requirements”;

Page 162: Explanatory Memorandum (Rev D)

74

“reinstatement” means the restoration of land within the Order limits for future use after

construction of the authorised development;

“relevant highway authority” means North Yorkshire County Council or East Riding of Yorkshire

Council as the case may be including their successor and where the relevant matter is located in the

administrative areas of both then it means both;

“relevant planning authority” means Selby District Council or East Riding of Yorkshire Council as

the case may be including their successor and where the relevant matter is located in the

administrative areas of both then it means both; and

“stage” means part of the authorised development as described in Requirement 4.

Where in this Schedule details or plans are to be approved by or provided for consultation purposes (1)

to a relevant planning authority which is Selby District Council, then insofar as the details or plans are

relevant to highways, ecological or archaeological matters the relevant planning authority must consult

with North Yorkshire County Council as the relevant highway authority and/or the County Ecologist

and/or the County Archaeologist of North Yorkshire County Council as the case may be.

Time limits

The authorised development must be commenced (type 2) within five years of the date of this 2.

Order.

Approved details

—a) Subject to Requirements 5 (Barmston Pumping Station) and 6 (Camblesforth Multi-junction), 3.

the authorised development referred to in Schedule 1 (authorised development) must not take place

otherwise than in accordance with the approved details; and in this Requirement the “approved details”

mean—

the approved plans; or(a)

any amendments, revisions or supplements to an approved plan which—(b)

have been approved by the relevant planning authority;(i)

do not exceed the parameters specified in Part 6 (parameters) of Schedule 2 (approved (ii)

plans) for the approved plan to which the amendments, revisions or supplements relate;

and

are not likely to give rise to any materially new or materially different significant effects (iii)

from those assessed in the environmental statement.

A planting drawing under Part 7 (planting drawings) of Schedule 2 (plans) may not be amended, (1)

revised or supplemented pursuant to Requirement 3 (1) (b).

Stages of the authorised development

The stages of the authorised development for the purposes of these Requirements are (in no order of 4.

construction phasing)—

the “Drax to Camblesforth stage”, namely Work Nos. 3A to 3G;(a)

the “Camblesforth to Tollingham stage”, namely Work Nos. 5A to 5J;(b)

the “Tollingham to grid references 490485.84 E 441486.96 N (the A0179) stage”, namely (c)

Work Nos. 8A to 8F;

the “grid references 490485.84 E 441486.96 N (the A0179) to Dalton stage”, namely Work (d)

Nos. 8G to 8L;

the “Dalton to Skerne stage”, namely Work Nos. 10A to 10K;(e)

the “Skerne to Barmston stage”, namely Work Nos. 13A to 13E;(f)

the “Barmston stage”, namely Work Nos. 14A to 14D;(g)

the “Drax PIG Trap stage”, namely Work Nos. 1A to 2A;(h)

the “Camblesforth Multi-junction stage”, namely Work Nos. 4A to 4D;(i)

the “Tollingham Block Valve stage” namely Work Nos. 6A to 6 D;(j)

the “Dalton Block Valve stage” namely Work Nos. 9A to 9D;(k)

Page 163: Explanatory Memorandum (Rev D)

75

the “Skerne Block Valve stage” namely Work Nos. 11A to 11D;(l)

the “Tollingham Construction Compound stage” namely Work No. 7;(m)

the “Driffield Construction Compound stage” namely Work No. 12;(n)

the “Landfall stage” namely Work Nos. 15A to 15B,(o)

and in each case such further associated development in connection with those Work Nos. as is listed at

paragraphs (a) to (n) (further associated development) of Schedule 1 (authorised development)

inclusive insofar as it is relevant to that stage.

Barmston Pumping Station

—a) Construction of the Barmston Pumping Station (Work Nos.14A and 14B) must not commence 5.

(type 2) until details of the layout, scale, external appearance, surface treatments, method of drainage

and landscaping of the Barmston Pumping Station have been submitted to and approved by the relevant

planning authority in consultation with the Environment Agency.

The details referred to in Requirement 5 (1) must be in accordance with the Barmston Pumping (1)

Station parameter plan and the principles of chapter 8 of the design and access statement; and in this

Requirement—

the “design and access statement” means the document(s) given application document reference (a)

7.3 and certified as the design and access statement by the Secretary of State for the purposes of

this Order; and

the “Barmston Pumping Station parameter plan” means the drawing given drawing number (b)

10-2574-PLN-01-0346 Rev B and application document reference 2.14 and certified as the

Barmston Pumping Station parameter plan by the Secretary of State for the purposes of this

Order.

The method of drainage must be designed in accordance with the principles set out in the document (2)

entitled “The SuDS Manual” issued in 2007 by CIRIA (the Construction Industry Research and

Information Association).

The construction of the Barmston Pumping Station must be carried out in accordance with the (3)

approved details.

External lighting to be affixed at the Barmston Pumping Station must be bulkhead lighting and/or (4)

low level lighting only and such lighting may only operate when the Barmston Pumping Station is

manned.

Camblesforth Multi-junction design

—a) In Area B of the Camblesforth Multi-junction (Work No. 4A)—6.

no works may commence (type 1) until details of the layout, scale and external appearance, (a)

surface treatments and method of drainage of those works have been submitted to and approved

by the relevant planning authority in consultation with the Environment Agency; and

no structure comprised in the authorised development may exceed a height of 4 metres above (b)

ground surface.

The details referred to in Requirement 6 (1) must be in accordance with the Camblesforth (1)

Multi-junction parameter plan; and in this Requirement the “Camblesforth Multi-junction parameter

plan” means the drawing given drawing number 10-2574-GA-01-0316 and document reference 2.25 and

certified as the Camblesforth Multi-junction parameter plan by the Secretary of State for the purposes of

this Order.

The method of drainage must be designed in accordance with the principles set out in the document (2)

entitled “The SuDS Manual” issued in 2007 by CIRIA (the Construction Industry Research and

Information Association).

The construction of Area B of the Camblesforth Multi-junction must be carried out in accordance (3)

with the approved details.

External lighting to be affixed at the Camblesforth Multi-junction must be bulkhead lighting and/or (4)

low level lighting only and such lighting may only operate when the Camblesforth Multi-junction is

manned.

Page 164: Explanatory Memorandum (Rev D)

76

European protected species

—a) No stage of the authorised development may commence (type 2) until, for that stage, further 7.

survey work has been carried out to establish whether a European protected species is present—

on any land which may be affected by that stage of the authorised development; (a)

in any of the trees to be lopped or felled, in hedgerows removed or in buildings to be (b)

demolished during that stage of the authorised development,

and the results of the survey must be provided to Natural England. (c)

Where a European protected species is shown to be present by the further survey work referred to (1)

in Requirement 7(1), the stage of the authorised development to which that survey work relates must not

commence (type 2) until a scheme of protection and mitigation measures has been submitted to and

approved by the relevant planning authority, following consultation with Natural England; and that stage

of the authorised development must be carried out in accordance with the approved scheme.

Scheme of ecological mitigation and reinstatement

—a) No stage of the authorised development may commence (type 3) until a scheme of ecological 8.

mitigation for that stage (which in respect of a pipeline stage must also set out proposals for the

reinstatement of that pipeline stage) has been submitted—

no less than 14 days prior to an application for approval under Requirement 8(1)(b) in draft (a)

form for consultation with the relevant planning authority and, so far as the scheme relates to

the licensed location, with the MMO (and “licensed location” and “MMO” have the meanings

given in paragraph 1 of Part 1 (interpretation and details of licensed marine activities) of

Schedule 10 (deemed marine licence under Part 4 (marine licensing) of the Marine and

Coastal Access Act 2009); and

in final form for approval by the relevant planning authority and has been approved. (b)

The scheme must contain, insofar as it is relevant for that stage—(1)

the survey results and ecological mitigation measures for species and habitats that are not (a)

subject to the need for a licence pursuant to the 2010 Regulations (and which are included in

the environmental statement); and

a strategy for the reinstatement, re-planting and restoration of hedgerows and trees (so far as (b)

relevant) that are removed in the course of the carrying out of that stage of the authorised

development.

The scheme must include an implementation timetable applicable to that stage of the authorised (2)

development.

Any stage of the authorised development must be carried out in accordance with the approved (3)

scheme for that stage.

Any tree, shrub or hedge planted as part of a scheme of ecological mitigation and reinstatement (4)

which dies or becomes within a period of 5 years after completion of a stage of the authorised

development, in the opinion of the relevant planning authority, seriously damaged or diseased, must be

replaced in the first available planting season (provided that it is within the 5 year period referred to in

this Requirement 8(5)) with a specimen of the same species and size as that originally planted, unless

otherwise approved by the relevant planning authority.

In this Requirement, “pipeline stage” means the stages listed in Requirements 4(a) to (f) (5)

(inclusive) 4 (stages of the authorised development).

Water

—a) No stage of the authorised development may commence (type 1) until, for that stage, both a 9.

construction water management plan and pollution prevention and control plan have been submitted to

and approved by the relevant planning authority, in consultation with the Environment Agency.

The construction water management plan must include the following— (1)

details of measures to ensure discharge from dewatering is non-polluting and will not (a)

exacerbate flood risk;

Page 165: Explanatory Memorandum (Rev D)

77

details of areas at risk of water pollution from surface water run-off, and any special control (b)

measures required in those areas;

details of measures to minimise suspension of and pollution due to sediment;(c)

a commitment that works in the channel will be carried out in a bunded, dry working space with (d)

any water entering the space being pumped out for treatment prior to discharge back to the

watercourse;

a commitment that no discharges or abstractions will take place to or from ponds; (e)

where it is considered necessary to store material in the flood plain, the requirements for (f)

mitigation will be agreed with the Environment Agency before construction commences (type

1);

details of hydrostatic testing requirements, including water sources and discharge points, and (g)

water quality monitoring of test water discharged;

a commitment that water will be returned to the catchment it was abstracted from or if a (h)

groundwater source is used that groundwater is discharged to a surface water location identified

in consultation with the Environment Agency; and

all necessary licenses and consents will be obtained. (i)

The pollution prevention and control plan must include the following—(2)

details of a pollution incident response plan; (a)

details of storage and management of fuel and any other potentially polluting chemicals;(b)

details of pollution control measures;(c)

details regarding the control of mud at site accesses using road sweepers;(d)

details of the design and management of vehicle wash areas within the main construction (e)

compounds.

The construction works for each stage of the authorised development must be carried out in (3)

accordance with the approved construction water management plan and pollution prevention and control

plan.

The method of crossing main rivers and ordinary watercourses (including land drains) must be (4)

undertaken in a manner which will not cause an increase in flood risk to any area upstream, downstream

or surrounding the crossing.

Surface water runoff from temporary works/construction compounds must be in accordance with (5)

flood risk assessment drainage measures to control surface water runoff in the construction phase of the

authorised development; and in this Requirement the “flood risk assessment” means the document

certified by the Secretary of State for the purposes of this Order as the flood risk assessment dated June

2014 (given application document reference 5.2);

All excess spoil must be removed from the areas of Flood Zones 2 and 3 at the earliest opportunity.(6)

Any temporary stock-piling of spoil during the construction phase shall be sited outside Flood (7)

Zones 2 and 3 wherever possible.

Where Flood Zones 2 and 3 cannot be avoided, regular gaps shall be incorporated in any spoil (8)

heaps.

There must be no permanent raising of ground levels within the floodplain by the undertaker.(9)

Removal of trees and hedgerows

—a) No stage of the authorised development may commence (type 2) until, for that stage, details 10.

identifying the trees, groups of trees and hedgerows to be removed during that stage have been submitted

to and approved by the relevant planning authority.

Each stage of the authorised development must be carried out in accordance with the approved (1)

details (if any) for that stage.

AGI hard landscaping, lighting and drainage

—a) No stage of the authorised development may commence (type 1) until, for that stage, details of 11.

hard surfacing materials (if any), external lighting (if any) and drainage methods for all AGIs (with the

exception of Area B of the Camblesforth Multi-junction and the Barmston Pumping Station), have been

Page 166: Explanatory Memorandum (Rev D)

78

submitted to and approved by the relevant planning authority in consultation with the Environment

Agency.

The method of drainage must be designed in accordance with the principles set out in the document (1)

entitled “The SuDS Manual” issued in 2007 by CIRIA (the Construction Industry Research and

Information Association).

The authorised development must be carried out in accordance with the approved details.(2)

External lighting to be affixed at any AGI must be bulkhead lighting and/or low level lighting only (3)

and such lighting may only operate when that AGI is manned.

Archaeology

—a) No stage of the authorised development may commence (type 1) until a written scheme of 12.

archaeological investigation for that stage has been submitted to and approved by the relevant planning

authority.

The written scheme must identify areas where a programme of archaeological investigation is (1)

required and the measures to be taken to protect, record or preserve any significant archaeological

remains that may be found.

Any archaeological works or watching brief for a stage of the authorised development must be (2)

carried out in accordance with the approved written scheme for that stage.

Construction hours

—a) Subject to Requirements 13(3) and 13(4), except in the event of an emergency or unless 13.

otherwise agreed in writing by the relevant planning authority, construction work must only take place

between the hours of 07:00 and 19:00 from Monday to Saturday and between 07:00 and 17:00 on

Sundays and Bank Holidays except that during the winter months (October to February) construction

work at the Barmston Pumping Station—

must only take place between the hours of 08:00 and 18:00 from Monday to Saturday; and(a)

may not take place on Sundays or Bank Holidays. (b)

In the event of an emergency, notification of that emergency must be given to the relevant planning (1)

authority as soon as practicable.

The following operations may take place outside the working hours referred to in Requirement (2)

13(1)—

microtunnelling;(a)

horizontal directional drilling;(b)

filling, testing, dewatering and drying locations (c)

works within the landfall, namely Work Nos. 15A and 15B;(d)

dewatering activities;(e)

temporary possession of railway infrastructure;(f)

commissioning. (g)

Nothing in Requirement 13(1) above precludes—(3)

a reasonable start-up period and a reasonable shut-down period on Mondays to Saturdays (a)

(inclusive); and

maintenance at any time of plant and machinery engaged in the construction of the authorised (b)

development.

In this Requirement “emergency” means a situation where, if the relevant action is not taken, there (4)

will be adverse health, safety, security or environmental consequences that in the reasonable opinion of

the undertaker would outweigh the adverse effects to the public (whether individuals, classes or

generally as the case may be) of taking that action.

Code of construction practice

The authorised development must be carried out in accordance with the code of construction 14.

practice, unless otherwise approved in writing by the relevant planning authority.

Page 167: Explanatory Memorandum (Rev D)

Monday – Saturdays 19.00 – 23.00 55

Time of day SPL, dB LAeq,T

Sundays and Bank Holidays07.00 – 19.00

65 in respect of pipeline

construction works;

55 in respect of—

AGI construction works; (a)

and

construction work related (b)

to the crossing of the

River Ouse in the areas

delineated as “pipeline

envelope temporary

construction area 3” and

“pipeline envelope

temporary construction

area 4” on onshore

scheme map 1 of 10 of

figure 3.2 of the onshore

scheme description (given

application document

reference 6.3) of the

environmental statement

Construction noise threshold (at

the nearest façade)

Noise

—a) Subject to Requirement 15(2), the construction of the authorised development must take place 15.

in accordance with, and not exceed, the following construction noise levels at the stated times—

19:00 – 23:00(d) 55(e)

Monday – Fridays

Saturday

07.00 – 19.00

07.00 – 19.00

Each day 23.00 – 07.00 45

65

65

The noise level restrictions set out in Requirement 15(1) do not apply where—(1)

the undertaker notifies the relevant planning authority that to facilitate the effective and (a)

expeditious carrying out of a particular construction activity comprised within the authorised

development a particular noise level restriction will or may be exceeded for a particular

temporary duration; and

the undertaker sets out to the satisfaction of the relevant planning authority a different noise (b)

level restriction for that activity and that temporary duration,

in which case the undertaker must instead comply with that different noise level restriction for that

activity and that temporary duration.

The operation of Barmston Pumping Station (Work Nos. 14A and 14B) must not commence until a (2)

noise report for that operation is submitted to and approved by the relevant planning authority. The

noise report must assess noise from fixed plant / machinery at Barmston Pumping Station in accordance

with Requirements 15(4) and 15(5).

The noise report referred to in Requirement 15(3) must—(3)

be based on the methodology set out in British Standard 4142:1997; and (a)

Effect assessment period

79

Day of week

Page 168: Explanatory Memorandum (Rev D)

80

demonstrate that when the fixed plant / machinery located at the Barmston Pumping Station (b)

operates, the rating noise level at the property located at national grid reference 515432,

461508 (Rose Cottage), being the nearest existing receptor, for that permanent fixed plant /

machinery will not exceed 26.7 LA90,T, being the lowest background noise level recorded in July

2013 at that property.

The noise report referred to in Requirement 15(3) must, in respect of low frequency noise— (4)

include source noise levels of fixed plant/ machinery to be located in the Barmston Pumping (a)

Station specified by the manufacturers of the fixed plant / machinery or, where available, based

on other appropriate sources;

include a comparison of those dBA source noise levels with those dBC source noise levels for (b)

the plant; and

if the difference between those dBA source noise levels and those dBC source noise levels is (c)

greater than 20dB, include appropriate mitigation for low frequency noise identified in the

report as arising from the Barmston Pumping Station.

The authorised development must be carried out in accordance with any— (5)

noise limits; and (a)

specifications for— (b)

site design and material;(i)

plant and machinery;(ii)

operation and maintenance,(iii)

specified in the noise report approved pursuant to Requirement 15(3), unless otherwise

approved by the relevant planning authority.

Land drainage

Subject to Requirement 11 (AGI hard landscaping and drainage), the authorised development 16.

must take place in accordance with the drainage strategy, unless otherwise agreed in writing by the

relevant planning authority; and in this Requirement “drainage strategy” means the document certified

by the Secretary of State for the purposes of this Order as the drainage report dated June 2014 (given

application document reference 7.7) but does not mean the plans given application document reference

7.7.1.

Contaminated land and groundwater

—a) In the event that contamination is found at any time when carrying out the authorised 17.

development that has not been previously identified it must be reported in writing immediately to the

relevant planning authority.

A scheme setting out the process for carrying out, and the content of, an investigation and risk (1)

assessment in respect of an instance of contamination referred to Requirement 17(1) must be submitted

to the relevant planning authority for approval within 14 days of the date on which the instance of

contamination is reported to the relevant planning authority under Requirement 17(1).

An investigation and risk assessment must be completed in accordance with the scheme approved (2)

under Requirement 17(2) to assess the nature and extent of any contamination on the part of the Order

limits within which works are being carried out, whether or not that contamination originates on that part

of the Order limits; and that investigation and risk assessment must be undertaken by competent persons

and a written report of the findings must be produced and provided to the relevant planning authority no

later than—

28 days after the date on which the instance of contamination is reported to the relevant (a)

planning authority under Requirement 17(1); or

if later, 14 days after the date on which the relevant planning authority has approved the scheme (b)

submitted under Requirement 17(2).

Where remediation is required a detailed remediation scheme to bring a part of the Order limits (3)

within which works are being carried out to a condition suitable for the intended use must be prepared

and submitted for the written approval of the relevant planning authority provided to the relevant

planning authority no later than—

Page 169: Explanatory Memorandum (Rev D)

81

35 days after the date on which the instance of contamination is reported to the relevant (a)

planning authority under Requirement 17(1); or

if later, the period ending 21 days after the date on which the relevant planning authority has (b)

approved the scheme submitted under Requirement 17(2).

The remediation scheme approved under Requirement 17(4) must be carried out in accordance (4)

with its terms unless otherwise approved in writing by the relevant planning authority and, following

completion of measures identified in the approved remediation scheme, a verification report that

demonstrates the effectiveness of the remediation carried out must be produced and approved in writing

by the relevant planning authority.

Construction traffic plan

No stage of the authorised development may commence (type 3) until a traffic management plan 18.

for that stage has been submitted to and, following consultation with the highway authority, been

approved by the relevant planning authority; and each stage of the authorised development must be

carried out in accordance with the traffic management plan for that stage.

Restoration of land used temporarily for construction

Subject to article 28(4) (temporary use of land for carrying out the authorised development), any 19.

land within the Order limits which is used temporarily for construction as part of a stage of the

authorised development must be reinstated to a condition fit for its former use, or such other condition as

the relevant planning authority may approve, within 12 months of completion of that stage; but nothing

in this Requirement prevents the undertaker from exercising powers under article 28 (temporary use of

land for carrying out the authorised development) in respect of that land following such reinstatement,

in which case this Requirement applies again following that subsequent exercise of those powers.

Requirement for written approval

Where under any of the Requirements the approval or agreement of the relevant planning authority 20.

or another person is required, that approval or agreement must be given in writing.

Amendments to approved details

—a) With respect to any Requirement which requires the authorised development to be carried out 21.

in accordance or general accordance with details approved by the relevant planning authority, the

approved details include any amendments that may subsequently be approved in writing by the relevant

planning authority to the extent that such amendments do not give rise to any materially new or

materially different significant environmental effects from those assessed in the environmental statement.

Where a Requirement allows for changes to the restrictions imposed or to a plan or scheme (or (1)

similar) approved so long as those changes are approved or agreed in writing by the relevant planning

authority, that approval or agreement may not be given unless it has been demonstrated to the

satisfaction of the relevant planning authority that the subject-matter of the approval or agreement sought

is unlikely to give rise to any materially new or materially different significant environmental effects

from those assessed in the environmental statement.

Decommissioning

—a) At least six months prior to the permanent cessation of operation of the authorised 22.

development, a scheme of decommissioning, restoration and aftercare of the authorised development

must be submitted for approval by the relevant planning authority, in consultation with the MMO so far

as the scheme relates to the licensed location; and “licensed location” and “MMO” have the meanings

given in paragraph 1 of Part 1 (interpretation and details of licensed marine activities) of Schedule 10

(deemed marine licence under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009).

The scheme must include proposals for—(1)

future uses of the above ground installations following permanent cessation of such installations (a)

or (if none) the means of decommissioning such installations;

future uses of the pipelines comprised in the authorised development or (if none) the means of (b)

decommissioning of such pipelines;

Page 170: Explanatory Memorandum (Rev D)

82

what above-ground structures, buildings and other parts of the authorised development are to be (c)

demolished or retained and the means of any demolition;

the phasing of any decommissioning, demolition and/or removal proposed in Requirements (d)

22(2)(a) to (c);

the means of removal of decommissioning materials and demolition waste arising from the (e)

activities listed in Requirements 22(2)(a) to (c);

works for the restoration of land within the Order limits on which the authorised development is (f)

located and the phasing of such restoration works;

aftercare of the authorised development, having regard to any future uses of elements of the (g)

authorised development, including the long term retention and maintenance of cathodic

protection;

a risk management plan setting out measures to be taken in appropriate circumstances to (h)

minimise risk in respect of the authorised development following permanent cessation of

operation of the authorised development; and

a timetable for implementation of the scheme.(i)

The scheme must be implemented as approved following the permanent cessation of the operation (2)

of the authorised development.

In this Requirement—(3)

“aftercare” means monitoring, maintenance and management of land within the Order limits (a)

following its reinstatement and restoration;

“decommissioning” means the decommissioning of the authorised development on the later of (b)

(a) the date on which it is no longer required for operational use or (b) the permanent cessation

of operation of the authorised development, as the case may be;

“operational use” or “operation of the authorised development” means use of the authorised (c)

development for the purposes for which it is authorised; and

“permanent cessation” means the cessation of operation of the authorised development, or (d)

relevant part of it, where there is a demonstrable intention to cease permanently those

operations.

Driffield Construction Compound

In the Driffield Construction Compound comprised in Work No. 12 no buildings may be 23.

demolished in the area shown coloured blue, cross-hatched orange and labelled “no buildings to be

demolished as part of the Onshore Scheme” on the drawing entitled “Environmental Commitments Map

8 of 10” provided in the code of construction practice.

Venting for AGI maintenance

For planned maintenance of each of the AGIs, the internal inventory of carbon dioxide may only 24.

be vented twice a year—

at a rate whereby noise emissions at each site do not exceed a maximum of 70dB LAeq, 1hr at (a)

the nearest existing noise sensitive receptor;

where the duration of a vent activity does not exceed one hour; and (b)

between the hours of 07:00 and 19:00 Monday to Friday.(c)

AGI venting for pipeline inspections

—a) The initial frequency of planned internal inspection of pipelines using PIGs will be set at once 25.

every five years. Over time the frequency will be adjusted following examination of previous inspection

data. That is, the inspection intervals could be extended or reduced to meet the needs of maintaining a

safe operating pipeline.

Venting of the internal inventory of carbon dioxide at PIG traps at AGIs, for the purposes of (1)

internal inspection of pipelines, may only occur—

at a rate whereby noise emissions at each site do not exceed a maximum of 70dB LAeq, 1hr at (a)

the nearest existing noise sensitive receptor;

Page 171: Explanatory Memorandum (Rev D)

83

over a venting duration of no more than one hour per day for each site, which may be repeated (b)

on multiple days over a period which does not exceed 14 days at each AGI;

between the hours of 07:00 and 19:00 Monday to Friday.(c)

AGI venting notifications

—a) No less than 24 hours prior to—26.

an individual venting event referred to in Requirement 24 (Venting for AGI maintenance); or(a)

a venting period referred to in Requirement 25 (AGI venting for pipeline inspections),(b)

a letter providing notice of the activity taking place and its likely duration must be posted

through the door of (if any) any residential and commercial property within a noise contour

which the undertaker considers is likely to experience noise levels above 60 dB(A) LAeq, 1hr.

Prior to an individual venting event referred to in Requirement 24 (Venting for AGI maintenance) (1)

or in Requirement 25 (AGI venting for pipeline inspections) taking place an operative of the undertaker

must place a notice at locations (if any) where a public right of way or other public highway intersects

with a noise contour which the undertaker considers likely to experience noise levels above 70dB(A)

LAeq, 1hr noise contour; and the notice—

must set out the activity taking place and its likely duration; and(a)

may be removed on completion of the activity to which it relates. (b)

Page 172: Explanatory Memorandum (Rev D)

For the purposes of Work No. 3A, unnamed private farm track east of Lendall

Drain (for information indicated as TX 0/3 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0061

sheet 1 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

SCHEDULE 4 Article 10

STREETS SUBJECT TO STREET WORKS

North Yorkshire

County Council, Selby

District Council

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3A, unnamed private tarmac track to Drax

pump house and River Ouse (for information indicated as TX 0/4 on access,

rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0061 sheet 1 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

For the purposes of Work No. 3A, Long Drax Footpath 35.47/6/1 in the event

that it is diverted under the public path diversion order entitled “Footpath Nos.

35.47/1, 35.47/6 & 35.47/10, Long Drax and 35.6/12, Barlow, Drax Power

Station, Long Drax Diversion Order 2014”, under any other public path

diversion order pertaining to Public Footpath No. 35.47/6/1 or otherwise

(which shall include such other footpath number or numbers (if different) or

such other route or routes as may be specified in the instrument by which the

diversion is given effect) where crossed by the authorised development within

the Order limits (and for information (where the proposed diversion routes are

known but remain to be determined) indicated on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0061

sheet 1 of 25).

Works plans drawing number 10-2574-GND-01-05-0031 (sheet 1 of 25)

(1)

Area

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3B, Pear Tree Avenue, Long Drax (for

information tarmac road indicated as RDX 1/A and B on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0061

sheet 1 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

North Yorkshire

County Council, Selby

District Council

North Yorkshire

County Council, Selby

District Council

North Yorkshire For the purposes of Work No. 3B, Long Drax Footpath No. 35.47/1/1 in the

For the purposes of Work No. 3A, unnamed private farm track north of

Augustinian Priory (for information indicated as TX 0/2 on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0061 sheet 1 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0031 (sheet 1 of 25)

For the purposes of Work No. 3A, unnamed private farm track to Foreman’s

Cottage (for information indicated as TX 0/1 on access, rights of way and

temporary stopping up plans (drawing number 10-2574-GND-01-05-0061;

sheet 1 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

(2)

Street subject to street works

84

North Yorkshire

County Council, Selby

District Council

Page 173: Explanatory Memorandum (Rev D)

For the purposes of Work No. 3B, Long Drax Footpath No. 35.47/8/1 (or

such other footpath number or numbers for such footpath as may be specified

in the public path diversion order entitled “Footpath Nos. 35.47/1, 35.47/6 &

35.47/10, Long Drax and 35.6/12, Barlow, Drax Power Station, Long Drax

Diversion Order 2014”, under any other public path diversion order pertaining

to public footpath no. 35.47/8/1 or otherwise) (for information indicated on

access, rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0061 sheet 1 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3C, Long Drax Footpath No. 35.47/4/1

(for information indicated on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0061 sheet 1 of 25) where

crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

County Council, Selby

District Council

event that it is diverted under the public path diversion order entitled

“Footpath Nos. 35.47/1, 35.47/6 & 35.47/10, Long Drax and 35.6/12,

Barlow, Drax Power Station, Long Drax Diversion Order 2014”, under any

other public path diversion order pertaining to Public Footpath No. 35.47/1/1

or otherwise (which shall include such other footpath number or numbers (if

different) or such other route or routes for such footpath as may be specified in

the instrument by which the diversion is given effect) where crossed by the

authorised development within the Order limits (and for information (where

the proposed diversion routes are known but remain to be determined)

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0061 sheet 1 of 25).

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3D, Main Road, Long Drax (for information

tarmac road indicated as RDX 3/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0061

sheet 1 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3B, Unnamed private track north east of New

Close Plantation (for information indicated as TX 1/1 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0061

sheet 1 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3D, Drax Footpath No. 35.47/5/1 (for

information indicated on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0061 sheet 1 of 25) where

crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

(1)

Area

(2)

Street subject to street works

North Yorkshire For the purposes of Work No. 3D, Drax Footpath 35.26/7/1

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3C, Carr Lane, Long Drax (for information

tarmac road indicated as RDX 2/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0061

sheet 1 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)

85

North Yorkshire

County Council, Selby

District Council

Page 174: Explanatory Memorandum (Rev D)

(for information indicated on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25) where

crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3G and 5A, unnamed private concrete/ tarmac

track to fishing lake (for information indicated as TX 6/1 and TX 6/4 on

access, rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0062 sheet 2 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3E, Hales Lane unmade private track (for

information indicated as TX 4/1 on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3G and 5A, unnamed private unmade farm

track (continuation of Wade House Lane) (for information indicated as TX

6/2 and TX 6/3 on access, rights of way and temporary stopping up plans

drawing number 10-2574-GND-01-05-0062 sheet 2 of 25) where crossed by

the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

(1)

Area

(2)

Street subject to street works

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 5B, Brickhill Lane, tarmac track (for

information indicated as TX 7/1 on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3F, Brickhill Lane, Drax (for information

tarmac road indicated as RDX 5/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0062

sheet 2 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 5B, (Brickhill Lane track) Drax Footpath No.

35.26/9/1 (for information indicated on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3E, Church Dike Lane, Drax (for information

tarmac road indicated as RDX 4/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0062

sheet 2 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

North Yorkshire For the purposes of Work No. 5B, Hales Lane unmade private track (for

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 3G and 5B, A645, Drax (for information

tarmac road indicated as RDX 6 + 7/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0062

sheet 2 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

86

County Council, Selby

District Council

Page 175: Explanatory Memorandum (Rev D)

For the purposes of Work No. 5C, Barmby-on-the-Marsh Footpath No 3,

north of River Ouse (for information indicated on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0063

sheet 3 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

County Council, Selby

District Council

information indicated as TX 7/2 on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 5C, Bankfield Lane private stone surfaced

track (for information indicated as TX 8/1 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0063

sheet 3 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 5C, unmade path Scurff Cottages, Drax

Footpath No. 35.26/13/1 / Newland Footpath No. 35.49/1/2 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0062 sheet 2 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 5C, Gateland Field Lane unmade private farm

track (for information indicated as TX 8/2 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0063

sheet 3 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

(1)

Area

(2)

Street subject to street works

East Riding of

Yorkshire Council

For the purposes of Work No. 5C, unnamed private unmade track prior to

Fields Drain (for information indicated as TX 8/3on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0063

sheet 3 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 5C, unmade path Scurff Cottages, Newland

Footpath No.35.49/2/2 (for information indicated on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0062

sheet 2 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 5C, unnamed private unmade track from Fair

Field Farm (for information indicated as TX 8/4 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0063

sheet 3 of 25) where crossed by the authorised development within the Order

limits.

North Yorkshire

County Council, Selby

District Council

For the purposes of Work No. 5C, Church Dike Lane, Drax (for information

tarmac road indicated as RDX 8/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0062

sheet 2 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)

87

East Riding of

Yorkshire Council

Page 176: Explanatory Memorandum (Rev D)

East Riding of

Yorkshire Council

For the purposes of Work No. 5D, Asselby Footpath No.2 Side of Marsh

Lane track (for information indicated on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0064 sheet 4 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)

For the purposes of Work No. 5D, Barmby Road, Asselby (for information

tarmac road indicated as RDX 9/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0063

sheet 3 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

(1)

Area

East Riding of

Yorkshire Council

For the purposes of Work No. 5D, Asselby Footpath No.1 to Old Derwent

Drain (for information indicated on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0064 sheet 4 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 5D, unnamed private unmade track at the side

of New Drain (for information indicated as TX 9/3 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0064

sheet 4 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)

For the purposes of Work No. 5D, unnamed private unmade farm track north

east of Mount Pleasant bungalow (for information indicated as TX 9/1 on

access, rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0064 sheet 4 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)

For the purposes of Work No. 5C, unnamed private unmade track to RDX9,

Barmby Road (for information indicated as TX 8/5 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0063

sheet 3 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 5E, A63 Hull Road, Newsholme (for

information tarmac road indicated as RDX 10/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0064 sheet 4 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)

Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 5E, Wressle Footpath No.10 to Park Farm

(for information indicated on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0064 sheet 4 of 25) where

For the purposes of Work No. 5D, Marsh Lane private track (for information

indicated as TX 9/2 on access, rights of way and temporary stopping up plans

drawing number 10-2574-GND-01-05-0064 sheet 4 of 25) where crossed by

the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)

(2)

Street subject to street works

88

East Riding of

Yorkshire Council

Page 177: Explanatory Memorandum (Rev D)

East Riding of

Yorkshire Council

For the purposes of Work No. 5G, B1228 Wood Lane, Brind (for information

tarmac road indicated as RDX 12/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0065

sheet 5 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)

For the purposes of Work No. 5E, Wressle Footpath No 8 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0065 sheet 5 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)

(1)

Area

East Riding of

Yorkshire Council

For the purposes of Work No. 5G, Eastrington Bridleway No. 17 (western

end of Featherbed Lane) (for information indicated on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0066

sheet 6 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 5G, Featherbed Lane unmade private track

(western end of Featherbed Lane) (for information indicated as TX 12/1on

access, rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0066 sheet 6 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)

For the purposes of Work No. 5E, Wressle Footpath No 7 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0065 sheet 5 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)

For the purposes of Work No. 5E, Wressle Footpath No 6 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0065 sheet 5 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 5G, Featherbed Lane unmade private track

(eastern end of Featherbed Lane) (for information indicated as TX 12/2

on access, rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0066 sheet 6 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)

crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 5G, Eastrington Bridleway No. 17 (eastern end

of Featherbed Lane) (for information indicated on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0066

For the purposes of Work No. 5F, Brind Lane, Brind (for information tarmac

road indicated as RDX 11/A and B on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0065 sheet 5 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)

(2)

Street subject to street works

89

East Riding of

Yorkshire Council

Page 178: Explanatory Memorandum (Rev D)

(2)

Street subject to street works

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 5H, unnamed private unmade track to Sikes

Farm (for information indicated as TX 13/3 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0067

sheet 7 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)

For the purposes of Work No. 5H, unnamed private unmade farm track to

Chestnut farm (for information indicated as TX 13/1 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0067

sheet 7 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)

(1)

Area

East Riding of

Yorkshire Council

For the purposes of Work No. 5H, unnamed private unmade track to Welham

Bridge Farm (for information indicated as TX 13/4 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0067

sheet 7 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 5I, Bursea Lane, Holme Upon Spalding Moor

(for information tarmac road indicated as RDX 14/A and B on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0068 sheet 8 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0038 (sheet 8 of 25)

For the purposes of Work No. 5H, unnamed private unmade track to Taynton

Lodge (for information indicated as TX 13/2 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0067

sheet 7 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)

For the purposes of Work No. 5H, A614 Holme Road, Spaldington (for

information tarmac road indicated as RDX 13/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0067 sheet 7 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 5J, Drain Lane, Holme Upon Spalding Moor

(for information tarmac road indicated as RDX 15/A and B on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0068 sheet 8 of 25) where crossed by the authorised

development within the Order limits.

sheet 6 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)

East Riding of

Yorkshire Council

90

For the purposes of Work No. 5H, Spaldington Footpath No.12 - Combined

with TX 13/2 (for information indicated on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0067

sheet 7 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)

Page 179: Explanatory Memorandum (Rev D)

(2)

Street subject to street works

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 8D, unnamed private unmade farm track to Top

Cottages (for information indicated as TX 18/1 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0070

sheet 10 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0040 (sheet 10 of 25)

For the purposes of Work No. 8C, Lock Lane, Holme Upon Spalding Moor

(for information tarmac road indicated as RDX 17/A and B on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0069 sheet 9 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0039 (sheet 9 of 25)

(1)

Area

East Riding of

Yorkshire Council

For the purposes of Work No. 8D, Unnamed private unmade track from Long

Lane to Bellsbeck Farm (for information indicated as TX 18/2 on access,

rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0070 sheet 10 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0040 (sheet 10 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 8E, Cliffe Road, Market Weighton (for

information tarmac road indicated as RDX 19/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0071 sheet 11 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0041 (sheet 11 of 25)

For the purposes of Work No. 8C, unnamed private unmade track to the side

of Market Weighton Canal (for information indicated as TX 17/1 on access,

rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0069 sheet 9 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0039 (sheet 9 of 25)

For the purposes of Work No. 8B, Skiff Lane, Holme Upon Spalding Moor

(for information tarmac road indicated as RDX 16/A and B on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0069 sheet 9 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0039 (sheet 9 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 8E, Market Weighton Footpath No 11, between

Market Weighton Canal and Back Delfin Drain (for information indicated on

access, rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0071 sheet 11 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0041 (sheet 11 of 25)

Works plans drawing number 10-2574-GND-01-05-0038 (sheet 8 of 25)

East Riding of

Yorkshire Council

91

For the purposes of Work No. 8D, Sand Lane, North Cliffe (for information

tarmac road indicated as RDX 18/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0070

sheet 10 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0040 (sheet 10 of 25)

Page 180: Explanatory Memorandum (Rev D)

For the purposes of Work No. 8G, unnamed private unmade farm track to

Wold House Farm (for information indicated as TX 21/1 on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 8E, unnamed private unmade farm track from

Cliffe Road by the side of the reservoir (for information indicated as TX 19/1

on access, rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0071 sheet 11 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0041 (sheet 11 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 8G, Goodmanham Footpath No. 6 (for

information indicated on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0072 sheet 12 of 25) where

crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 8F, unnamed private unmade farm track to

Weighton Wold House (for information indicated as TX 20/1 on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 8H, Kiplingcotes Lane, Market Weighton (for

information tarmac road indicated as RDX 22/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0073 sheet 13 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0043 (sheet 13 of 25)

(1)

Area

(2)

Street subject to street works

East Riding of

Yorkshire Council

For the purposes of Work No. 8H, Etton Bridleway No. 5 Hudson Way (for

information indicated on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0073 sheet 13 of 25) where

crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0043 (sheet 13 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 8G, A1079 Arras Hill, Market Weighton (for

information tarmac road indicated as RDX 21/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 8I, Kiplingcotes Road, Etton (for information

tarmac road indicated as RDX 23/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0074

sheet 14 of 25) where crossed by the authorised development within the Order

East Riding of

Yorkshire Council

For the purposes of Work No. 8F, A1034 Sancton Road, Market Weighton

(for information tarmac road indicated as RDX 20/A and B on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)

92

East Riding of

Yorkshire Council

Page 181: Explanatory Memorandum (Rev D)

(2)

Street subject to street works

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 10A, Lund Footpath No. 2 path from Lund

Wold Road to Bulmer’s Triangle (for information indicated on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0075 sheet 15 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0045 (sheet 15 of 25)

For the purposes of Work No. 8K, Park Road, South Dalton (for information

tarmac road indicated as RDX 25/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0074

sheet 14 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0044 (sheet 14 of 25)

(1)

Area

East Riding of

Yorkshire Council

For the purposes of Work No. 10B, Lund Wold Road, Lund (for information

tarmac road indicated as RDX 27/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0076

sheet 16 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0046 (sheet 16 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 10C, Middleton Road, Lund (for information

tarmac road indicated as RDX 28/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0076

sheet 16 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0046 (sheet 16 of 25)

For the purposes of Work No. 8K, unnamed private unmade farm track (for

information indicated as TX 25/1 on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0075 sheet 15 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0045 (sheet 15 of 25)

For the purposes of Work No. 8J, Kiplingcotes Racecourse Road, Etton (for

information tarmac road indicated as RDX 24/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0074 sheet 14 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0044 (sheet 14 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 10D, B1248 Lund Road, Middleton on the

Wolds (for information tarmac road indicated as RDX 29/A and B on access,

rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0076 sheet 16 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0046 (sheet 16 of 25)

limits.

Works plans drawing number 10-2574-GND-01-05-0044 (sheet 14 of 25)

East Riding of

Yorkshire Council

93

For the purposes of Work No. 8L, Holme Wold Road, Holme on the Wolds

(for information tarmac road indicated as RDX 26/A and B on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0075 sheet 15 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0045 (sheet 15 of 25)

Page 182: Explanatory Memorandum (Rev D)

For the purposes of Work No. 10F, unnamed Road from Bracken Lane to

Burnbutts Lane, Watton (for information tarmac road indicated as RDX 31/A

and B on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 10E, Middleton Road, Kilnwick (for

information tarmac road indicated as RDX 30/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 10G, Burnbutts Lane, Hutton Cranswick (for

information tarmac road indicated as RDX 32/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 10E, unnamed private unmade track

(for information indicated as TX 30/1 on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0077 sheet 17 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 10G, Hutton Cranswick Footpath No. 12 to

Bustardnest Fox Covert (for information indicated on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0078

sheet 18 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0048 (sheet 18 of 25)

(1)

Area

(2)

Street subject to street works

East Riding of

Yorkshire Council

For the purposes of Work No. 10G, Hutton Cranswick Footpath No. 11 to

Bustardnest Fox Covert (for information indicated on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0078

sheet 18 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0048 (sheet 18 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 10E, Walton Footpath No 20 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 10H, Southburn Road, Hutton Cranswick (for

information tarmac road indicated as RDX 33/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0079 sheet 19 of 25) where crossed by the authorised

development within the Order limits.

East Riding of

Yorkshire Council

For the purposes of Work No. 10E, Walton Footpath No 2 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)

94

East Riding of

Yorkshire Council

Page 183: Explanatory Memorandum (Rev D)

East Riding of

Yorkshire Council

For the purposes of Work No. 10K, unnamed private unmade farm track to

Church Farm (for information indicated as TX 36/1 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0080

sheet 20 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0050 (sheet 20 of 25)

For the purposes of Work No. 10J, Jenkinson Lane, Hutton (for information

tarmac road indicated as RDX 35/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0079

sheet 19 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)

(1)

Area

East Riding of

Yorkshire Council

For the purposes of Work No. 13A, unnamed private unmade farm track to

Cooper Hall (for information indicated as TX 36/2 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0080

sheet 20 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0050 (sheet 20 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 13A, Skerne and Wansford Bridleway No. 7 to

Cooper Hall (for information indicated on access, rights of way and temporary

stopping up plans drawing number 10-2574-GND-01-05-0080 sheet 20 of 25)

where crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0050 (sheet 20 of 25)

For the purposes of Work No. 10J, Hutton Cranswick Footpath No.18 at the

side of Northfield Beck (for information indicated on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0079

sheet 19 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)

For the purposes of Work No. 10I, A164 Beverley Road, Hutton Cranswick

(for information tarmac road indicated as RDX 34/A and B on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0079 sheet 19 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 13A, Skerne and Wansford Bridleway and

Footpath No. 9 south of River Hull (for information indicated on access, rights

of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0081 sheet 21 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)

Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 13B, B1249 Frodingham Road, Wansford (for

information tarmac road indicated as RDX 37/A and B on access, rights of

For the purposes of Work No. 10K, Ricklepits, Skerne (for information

tarmac road indicated as RDX 36/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0079

sheet 19 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)

(2)

Street subject to street works

95

East Riding of

Yorkshire Council

Page 184: Explanatory Memorandum (Rev D)

For the purposes of Work No. 13C, Main Street, Great Kelk (for information

tarmac road indicated as RDX 38/A and B on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0082

sheet 22 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0081 sheet 21 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 13C, Foston on the Wolds Footpath No.11 (for

information indicated on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0082 sheet 22 of 25) where

crossed by the authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 13B, unnamed private track to South

Cattleholmes (for information indicated as TX 37/2 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0081

sheet 21 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 13C, unnamed private unmade track to

Gransmoor Quarry (for information indicated as TX 38/1 on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0082 sheet 22 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)

(1)

Area

(2)

Street subject to street works

East Riding of

Yorkshire Council

For the purposes of Work No. 13C, unnamed private unmade track to Manor

Farm (for information indicated as TX 38/2 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0083

sheet 23 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0053 (sheet 23 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 13B, unnamed private track South of Markham

Dale (for information indicated as TX 37/3 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0082

sheet 22 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 13D, Gransmoor Road, Gransmoor (for

information tarmac road indicated as RDX 39/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0083 sheet 23 of 25) where crossed by the authorised

development within the Order limits.

East Riding of

Yorkshire Council

For the purposes of Work No. 13B, unnamed private unmade track west of

White Dike (for information indicated as TX 37/1 on access, rights of way

and temporary stopping up plans drawing number 10-2574-GND-01-05-0081

sheet 21 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)

96

East Riding of

Yorkshire Council

Page 185: Explanatory Memorandum (Rev D)

East Riding of

Yorkshire Council

For the purposes of Work No. 13E, Barmston Footpath No.2 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)

For the purposes of Work No. 13D, unnamed private unmade track to fishing

pond (for information indicated as TX 39/1 on access, rights of way and

temporary stopping up plans drawing number 10-2574-GND-01-05-0085

sheet 25 of 25) where crossed by the authorised development within the Order

limits.

Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)

Works plans drawing number 10-2574-GND-01-05-0053 (sheet 23 of 25)

East Riding of

Yorkshire Council

For the purposes of Work No. 13E, Barmston Footpath No.3 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)

(2)

Street subject to street works

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

For the purposes of Work No. 15A, Barmston Footpath No.4 (for information

indicated on access, rights of way and temporary stopping up plans drawing

number 10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the

authorised development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)

For the purposes of Work No. 13E, A165 Bridlington Road, Barmston (for

information tarmac road indicated as RDX 40/A and B on access, rights of

way and temporary stopping up plans drawing number

10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the authorised

development within the Order limits.

Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)

(1)

Area

97

East Riding of

Yorkshire Council

Page 186: Explanatory Memorandum (Rev D)

Pear Tree Avenue,

Long Drax Temporary construction accessAt RDX 1/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0061 (Sheet 1 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

SCHEDULE 5 Article 11

STREETS SUBJECT TO ALTERATION OF LAYOUT

PART 1

STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT

(1)

Area

North Yorkshire County

Council

Selby District Council

Carr Lane, Long

DraxTemporary construction accessAt RDX 2/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0061 (Sheet 1 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge and the temporary fluming of the

ditch on each side of the road.

North Yorkshire County

Council

Selby District Council

New Road, Long

Drax

North Yorkshire County

Council

Selby District Council

Main Road, Long

DraxTemporary construction accessAt RDX 3/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0061 (Sheet 1 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming of the ditch on the western side of

the road (RDX3A).

Temporary construction accessAt RDX 0/A shown on access, rights of way and

temporary stopping up plan drawing number

10-2574-GND-01-05-0061 (Sheet 1 of 25) the

widening of an existing bellmouth access to create a

temporary access with sufficient size to

accommodate large articulated vehicle (15.4m

length) comprising an alteration of the splay,

hedgeline and verge on the north western side and

reinforcement of verge on south eastern side of New

Road approximately 150 metres from the junction

with Pear Tree Avenue. As depicted in drawing no.

10-2574-PLN-01-1044 and 10-2574-PLN-01-1054.

(2)

Street subject to

alteration of layout

(3)

Description of alteration

98

North Yorkshire County

Council

Selby District Council

Page 187: Explanatory Memorandum (Rev D)

North Yorkshire County

Council

Selby District Council

A645, Drax Temporary construction accessAt RDX 6+7/A and B shown on access, rights of

way and temporary stopping up plan drawing number

10-2574-GND-01-05-0062 (Sheet 2 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

kerb line and roadside verge on each side of the road.

Church Dike Lane,

Drax Temporary construction accessAt RDX 4/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0062 (Sheet 2 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming of the ditch on the northern side of

the road (RDX4/A).

North Yorkshire County

Council

Selby District Council

Church Dike Lane,

Drax Temporary construction accessAt RDX 8/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0062 (Sheet 2 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming of the ditch on the northern side of

the road (RDX 8/B).

(3)

Description of alteration

(1)

Area

East Riding of

Yorkshire Council

Barmby Road,

AsselbyTemporary construction accessAt RDX 9/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0063 (Sheet 3 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader omprising a temporary alteration of the

roadside verge on each side of the road.

North Yorkshire County

Council

Selby District Council

Brickhill Lane, Drax

East Riding of

Yorkshire Council

A63 Hull Road,

NewsholmeTemporary construction accessAt RDX 10/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0064 (Sheet 4 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

Temporary construction accessAt RDX 5/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0062 (Sheet 2 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming of the ditch on the eastern side of

the road (RDX 5/A).

(2)

Street subject to

alteration of layout

99

North Yorkshire County

Council

Selby District Council

Page 188: Explanatory Memorandum (Rev D)

(3)

Description of alteration

East Riding of

Yorkshire Council

A614 Holme Road,

SpaldingtonTemporary construction accessAt RDX 13/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0067 (Sheet 7 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge and the temporary fluming the ditch

on each side of the road.

East Riding of

Yorkshire Council

Brind Lane, Brind

East Riding of

Yorkshire Council

Bursea Lane, Holme

Upon Spalding MoorTemporary construction accessAt RDX 14/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0068 (Sheet 8 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming the ditch on the north-eastern side

of the road (RDX 14/B).

Temporary construction accessAt RDX 11/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0065 (Sheet 5 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge and the temporary fluming of the

ditch on each side of the road.

(1)

Area

East Riding of

Yorkshire Council

Drain Lane, Holme

Upon Spalding MoorTemporary construction accessAt RDX 15/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0068 (Sheet 8 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming the ditch on the north-eastern side

of the road (RDX 15/B).

kerb line and roadside verge on each side of the road.

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

Skiff Lane, Holme

Upon Spalding MoorTemporary construction accessAt RDX 16/A and B shown on access, rights of way

and temporary stopping up plan drawing number

B1228 Wood Lane,

BrindTemporary construction accessAt RDX 12/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0065 (Sheet 5 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming of the ditch on the western side of

the road (RDX 12/A).

100

(2)

Street subject to

alteration of layout

Page 189: Explanatory Memorandum (Rev D)

(3)

Description of alteration

East Riding of

Yorkshire Council

Cliffe Road, Market

Weighton Temporary construction accessAt RDX 19/A and B shown on Access, Rights of

Way and Temporary Stopping Up Plan drawing

number 10-2574-GND-01-05-0071 (Sheet 11 of 25)

the creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming the ditch on the eastern side of the

road (RDX 19/B).

East Riding of

Yorkshire Council

Lock Lane, Holme

Upon Spalding Moor

East Riding of

Yorkshire Council

A1034 Sancton

Road, Market

Weighton

Temporary construction accessAt RDX 20/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0072 (Sheet 12 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road, and the

tarmac pavement on the north-eastern side of the

road (RDX 20/B).

Temporary construction accessAt RDX 17/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0069 (Sheet 9 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming the ditch on the southern side of

the road (RDX 17/A).

(1)

Area

East Riding of

Yorkshire Council

A1079 Arras Hill,

Market WeightonTemporary construction accessAt RDX 21/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0072 (Sheet 12 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

kerb line and roadside verge on each side of the road.

10-2574-GND-01-05-0069 (Sheet 9 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

East Riding of

Yorkshire Council

East Riding of Kiplingcotes Lane, Temporary construction access

Sand Lane, North

CliffeTemporary construction accessAt RDX 18/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0070 (Sheet 10 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

101

(2)

Street subject to

alteration of layout

Page 190: Explanatory Memorandum (Rev D)

Temporary construction accessAt RDX 24/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0074 (Sheet 14 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

Market Weighton At RDX 22/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0073 (Sheet 13 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

East Riding of

Yorkshire Council

Park Road, South

DaltonTemporary construction accessAt RDX 25/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0074 (Sheet 14 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

(3)

Description of alteration

(1)

Area

East Riding of

Yorkshire Council

Holme Wold Road,

Holme on the WoldsTemporary construction accessAt RDX 26/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0075 (Sheet 15 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

East Riding of

Yorkshire Council

Kiplingcotes Road,

Etton

East Riding of

Yorkshire Council

Lund Wold Road,

Lund Temporary construction accessAt RDX 27/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0076 (Sheet 16 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

Temporary construction accessAt RDX 23/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0074 (Sheet 14 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

(2)

Street subject to

alteration of layout

East Riding of

Yorkshire Council

Middleton Road,

Lund Temporary construction accessAt RDX 28/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0076 (Sheet 16 of 25) the

creation of a temporary bellmouth access on each

Yorkshire Council

East Riding of

Yorkshire Council

102

Kiplingcotes

Racecourse Road,

Etton

Page 191: Explanatory Memorandum (Rev D)

(3)

Description of alteration

East Riding of

Yorkshire Council

Unnamed Road from

Bracken Lane to

Burnbutts Lane,

Watton

Temporary construction accessAt RDX 31/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0077 (Sheet 17 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

East Riding of

Yorkshire Council

B1248 Lund Road,

Middleton on the

Wolds

East Riding of

Yorkshire Council

Burnbutts Lane,

Hutton CranswickTemporary construction accessAt RDX 32/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0077 (Sheet 17 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

Temporary construction accessAt RDX 29/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0076 (Sheet 16 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

(1)

Area

East Riding of

Yorkshire Council

Southburn Road,

Hutton Cranswick Temporary construction accessAt RDX 33/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0079 (Sheet 19 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge and the temporary fluming of the

ditch on each side of the road.

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

A164 Beverley

Road, Hutton

Cranswick

Temporary construction accessAt RDX 34/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0079 (Sheet 19 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

kerb line and roadside verge and the temporary

Middleton Road,

KilnwickTemporary construction accessAt RDX 30/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0077 (Sheet 17 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

103

(2)

Street subject to

alteration of layout

Page 192: Explanatory Memorandum (Rev D)

(3)

Description of alteration

East Riding of

Yorkshire Council

Road to Skerne

(Main Street),

Wansford

Temporary construction accessAt RDX 37/B shown on access, rights of way and

temporary stopping up plan drawing number

10-2574-GND-01-05-0081 (Sheet 21 of 25) the

creation of a temporary bellmouth access on the

south-eastern side of the road between the canal

bridge and River Hull, with sufficient size to

accommodate a low loader comprising a temporary

alteration of the roadside verge, fencing and gate.

East Riding of

Yorkshire Council

Jenkinson Lane,

Hutton

East Riding of

Yorkshire Council

B1249 Frodingham

Road, Wansford Temporary construction accessAt RDX 37/A shown on access, rights of way and

temporary stopping up plan drawing number

10-2574-GND-01-05-0081 (Sheet 21 of 25) the

creation of a temporary bellmouth access on the

north-eastern side of the road, with sufficient size to

accommodate a low loader comprising a temporary

alteration of the roadside verge and the temporary

fluming of the ditch on the north-eastern side of the

road.

Temporary construction accessAt RDX 35/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0079 (Sheet 19 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming of the ditch on the southern side

of the road (RDX 35/A).

(1)

Area

East Riding of

Yorkshire Council

B1249 Frodingham

Road, Wansford Temporary construction accessAt RDX 37/C shown on access, rights of way and

temporary stopping up plan drawing number

10-2574-GND-01-05-0081 (Sheet 21 of 25) the

temporary widening of an existing bellmouth access

on the south-western side of the road, with sufficient

size to accommodate a low loader comprising a

temporary alteration of the roadside verge on the

western side of the road.

fluming of the ditch on each side of the road.

East Riding of

Yorkshire Council

East Riding of

Yorkshire Council

Main Street, Great

Kelk Temporary construction accessAt RDX 38/A and B shown on access, rights of way

and temporary stopping up plan drawing number

Ricklepits, Skerne Temporary construction accessAt RDX 36/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0079 (Sheet 19 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road and the

temporary fluming of the ditch on the western side of

the road (RDX 36/A).

104

(2)

Street subject to

alteration of layout

Page 193: Explanatory Memorandum (Rev D)

(1)

Area

10-2574-GND-01-05-0082 (Sheet 22 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

East Riding of

Yorkshire Council

A165 Bridlington

Road, Barmston Temporary construction accessAt RDX 40/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0085 (Sheet 25 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

(2)

Street subject to

alteration of layout

(3)

Description of alteration

East Riding of

Yorkshire Council

A614, Driffield Access to Driffield Construction Compound,

Former Alamein Barracks, opposite Mallard

House

The creation of a temporary access onto the A614

comprised in Work No. 12 (works plans drawing

number 10-2574-GND-01-05-0049; inset on sheet

19 of 25) and as shown on access, rights of way and

temporary stopping up plan drawing number

10-2574-GND-01-05-0079 (inset on Sheet 19 of

25), namely increase in width of existing bellmouth

access on the northern side of the road with sufficient

size to accommodate a maximum legal length

articulated vehicle (16.5m length) comprising a

temporary alteration of the pavement, roadside verge,

kerb line and carriageway on the northern side of the

road as depicted in drawing

no.10-2574-PLN-01-1053 and

10-2574-PLN-01-1061. Provision of new gate.

East Riding of

Yorkshire Council

Gransmoor Road,

Gransmoor

105

Temporary construction accessAt RDX 39/A and B shown on access, rights of way

and temporary stopping up plan drawing number

10-2574-GND-01-05-0083 (Sheet 23 of 25) the

creation of a temporary bellmouth access on each

side of the road, with sufficient size to accommodate

a low loader comprising a temporary alteration of the

roadside verge on each side of the road.

Page 194: Explanatory Memorandum (Rev D)

(3)

Description of alteration

North Yorkshire County

Council

Wade House Lane/

A645, DraxAccess to Camblesforth Multi-junction

Alteration of the existing junction between

Wade House Lane (South) and the A645 to

accommodate the creation of a permanent access

onto the A645 from Wade House Lane

comprised in Work No. 4C on Works Plans

(drawing number 10-2574-GND-01-05-0032;

sheet 2 of 25) and RDX6+7/C as depicted on the

access, rights of way and temporary stopping up

plans (drawing number

10-2574-GND-01-05-0062; sheet 2 of 25),

namely the upgrading of an existing bellmouth

access on the southern side of the A645, with

sufficient size to accommodate junction radii to

enable turning movements of a large articulated

vehicle (15.4m length) comprising an increase to

the width and alteration of the alignment of

existing adopted road junction, alteration of the

splay, kerb line, carriageway and adjoining

road-side verge and embankment on the southern

side of the A645 and upgrading of Wade House

Lane road surface as depicted in drawing no.

10-2574-PLN-01-1045 and

10-2574-PLN-01-1055 cutting back of

vegetation in highway verge to enable visibility

splay.

PART 2

STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT

(1)

Area

East Riding of Yorkshire

Council

Skiff Lane, Holme Upon

Spalding MoorAccess to Tollingham Block Valve

The creation of a permanent access onto Skiff

North Yorkshire County

Council

Wade House Lane,

DraxAccess to Camblesforth Multi-junction

The creation of a permanent access onto Wade

House Lane comprised in Work No. 4C on

Works Plans (drawing number

10-2574-GND-01-05-0032; sheet 2 of 25) and

RDX6+7/C as depicted on the access, rights of

way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0062; sheet 2 of

25), namely the creation of a permanent

bellmouth access on the eastern side of the road,

with sufficient size to accommodate junction

radii to enable turning movements of a large

articulated vehicle (15.4m length) comprising an

alteration of the existing adopted carriageway

and adjoining roadside verge and kerb line on

the eastern side of the road to create a junction

with a new access road as depicted in drawing

no. 10-2574-PLN-01-1045 and

10-2574-PLN-01-1055.

106

(2)

Street subject to

alteration of layout

Page 195: Explanatory Memorandum (Rev D)

Lund Wold Road, Lund Access to Dalton Block Valve

The creation of a permanent access onto Lund

Wold Road for comprised in Work No. 9C on

Works Plans (drawing number

10-2574-GND-01-05-0045; sheet 15 of 25) and

RDX27/C as depicted on the access, rights of

way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0075; sheet 15 of

25), namely the creation of a new permanent

bellmouth access on the southern side of the road

comprising an alteration of the existing adopted

carriageway and adjoining hedgeline and

roadside verge to accommodate a junction with a

new access road with sufficient size to

accommodate junction radii to enable turning

movements of a large articulated vehicle (15.4m

length), in and out of Lund Wold Road, as

depicted in drawing no. 10-2574-PLN-01-1047

and 10-2574-PLN-01-1057.

(1)

Area

Lane comprised in Work No. 6C on Works

Plans (drawing number

10-2574-GND-01-05-0039; sheet 9 of 25) and

RDX16/C as depicted on the access, rights of

way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0069; sheet 9 of

25), namely the creation of a new permanent

bellmouth access on the southern side of the road

comprising an alteration of the existing adopted

carriageway and adjoining hedgeline and verge

to accommodate a junction with a new access

road with sufficient size to accommodate

junction radii to enable turning movements of a

large articulated vehicle (15.4m length), in and

out of Skiff Lane as depicted in drawing no.

10-2574-PLN-01-1046 and

10-2574-PLN-01-1056.

East Riding of Yorkshire

Council

Main Street, Skerne Access to Skerne Block Valve

Modification of existing junction of Church

Farm access road with Main Street, Skerne to

accommodate permanent access comprised in

Work No. 11C on Works Plans (drawing

number 10-2574-GND-01-05-0050; sheet 20 of

25) and RDX36/C as depicted on the access,

rights of way and temporary stopping up plans

(drawing number 10-2574-GND-01-05-0080;

sheet 20 of 25), namely the upgrading of an

existing bellmouth access on the southern side of

Main Street Skerne with sufficient size to

accommodate junction radii to enable turning

movements of a large articulated vehicle (15.4m

length) comprising an increase to the width and

alteration of the alignment of existing adopted

road junction, an alteration of the splay,

hedgeline and roadside verge, kerb line and

(2)

Street subject to

alteration of layout

(3)

Description of alteration

107

East Riding of Yorkshire

Council

Page 196: Explanatory Memorandum (Rev D)

(3)

Description of alteration

East Riding of Yorkshire

Council

Sands Road, Barmston Access to Barmston Pumping Station.

Permanent access from A165 Bridlington

Road/Sands Road, Barmston comprising—

the creation of two permanent accesses (a)

onto Sands Road (track), comprising

new permanent bellmouth accesses as

depicted in drawing no.

10-2574-PLN-01-1049, and an

increase to the width of the existing

adopted track with sufficient size to

accommodate junction radii to enable

turning movements of a large

articulated vehicle (15.4m length) as

depicted in drawing no.

10-2574-PLN-01-1059; and alteration

of the carriageway/ upgrading of the

road surface for approximately 100m;

modification of existing junction where (b)

Sands Road (track) meets the tarmac

road, an increase to the width of the

carriageway and alteration of the

adjoining roadside verge on the eastern

side of the existing bend. Provision of

new gate. As depicted in drawing

no.10-2574-PLN-01-1050;

an increase to the width of the (c)

carriageway and alteration of the

adjoining roadside verge for 630m

between the junction with Sands Road

(track) and A165. As depicted in

drawing no.10-2574-PLN-01-1051,

all comprised in Work No. 14C on Works Plans

(drawing number 10-2574-GND-01-05-0055;

sheet 25 of 25) and RDX40/C as depicted on the

access, rights of way and temporary stopping up

plans (drawing number

10-2574-GND-01-05-0085; sheet 25 of 25)

(1)

Area

carriageway as depicted in drawing no.

10-2574-PLN-01-1048 and

10-2574-PLN-01-1058

108

(2)

Street subject to

alteration of layout

Page 197: Explanatory Memorandum (Rev D)

Pear Tree Avenue, Long Drax

East Riding of

Yorkshire Council

Kiplingcotes Racecourse Road,

Etton

Between point ST7 and ST8 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0074; sheet 14 of

25)

Between point ST1 and ST2 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0061; sheet 1 of 25)

(2)

Street subject to temporary

stopping up

East Riding of

Yorkshire Council

Park Road, South Dalton Between point ST9 and ST10 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0074; sheet 14 of

25)

(3)

Extent of temporary stopping up

North Yorkshire

County Council

Selby District

Council

East Riding of

Yorkshire Council

Holme Wold Road, Holme on the

Wolds

Between point ST11 and ST12 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0075; sheet 15 of

25)

Brickhill Lane, Drax Between point ST3 and ST4 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0062; sheet 2 of 25)

East Riding of

Yorkshire Council

Unnamed Road from Bracken Lane

to Burnbutts Lane, Watton

Between point ST13 and ST14 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0077; sheet 17 of

25)

SCHEDULE 6 Article 14

STREETS AND PUBLIC RIGHTS OF WAY TO BE TEMPORARILY

STOPPED UP

PART 1

STREETS

(1)

Area

East Riding of

Yorkshire Council

Burnbutts Lane, Hutton Cranswick Between point ST15 and ST16 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0077; sheet 17 of

East Riding of

Yorkshire Council

Kiplingcotes Lane, Market

Weighton

Between point ST5 and ST6 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0073; sheet 13 of

25)

109

North Yorkshire

County Council

Selby District

Council

Page 198: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Footpath to be temporarily

stopped up

(3)

Extent of temporary stopping up

(2)

Street subject to temporary

stopping up

(3)

Extent of temporary stopping up

North Yorkshire County Council,

Selby District Council

Long Drax Footpath no.

35.47/6/1, running along track

from New Road west towards

Carr Dyke or, in the event that it

is diverted under the public path

diversion order entitled

“Footpath Nos. 35.47/1, 35.47/6

& 35.47/10, Long Drax and

35.6/12, Barlow, Drax Power

Station, Long Drax Diversion

Order 2014”, under any other

public path diversion order

pertaining to Public Footpath No.

35.47/6/1 or otherwise, such

other footpath number or

numbers (if different) and such

route or routes as may be

specified in the instrument by

which the diversion is given

effect so far as it or they fall

within the Order limits

Between point FP1 and FP2, as

depicted on the access, rights of

way and temporary stopping up

plans (drawing number

10-2574-GND-01-05-0061;

sheet 1 of 25) or, if diverted

under the application to North

Yorkshire County Council for a

diversion order with file

reference SEL/2012/05 or

otherwise, the extent of the route

or routes of the diverted footpath

or footpaths so far as it or they

fall within the Order limits

East Riding of

Yorkshire Council

Sands Road, Barmston

North Yorkshire County Council,

Selby District Council

Long Drax Footpath No.

35.47/1/1, in the event that it is

diverted under the public path

diversion order entitled

“Footpath Nos. 35.47/1, 35.47/6

& 35.47/10, Long Drax and

35.6/12, Barlow, Drax Power

Station, Long Drax Diversion

Order 2014”, under any other

public path diversion order

pertaining to Public Footpath No.

35.47/1/1 or otherwise (including

such other footpath number or

numbers (if different) and such

So far as the route or routes of

the diverted footpath or footpaths

fall within the Order limits

Between point ST17 and ST18 as depicted

on the access, rights of way and temporary

stopping up plans (drawing number

10-2574-GND-01-05-0085; sheet 25 of

25)

(1)

Area

PART 2

RIGHTS OF WAY

110

25)

Page 199: Explanatory Memorandum (Rev D)

(3)

Extent of temporary stopping up

North Yorkshire County Council,

Selby District Council

Drax Footpath No. 35.26/13/2,

running through agricultural land

east of Read School Playing

Field, and north-west of Scurff

Hall

Between point FP8B and FP9, as

depicted on the access, rights of

way and temporary stopping up

plans (drawing number

10-2574-GND-01-05-0062;

sheet 2 of 25

North Yorkshire County Council,

Selby District Council

Long Drax Footpath No.

35.47/8/1, running south-west

from Pear Tree Avenue, across

agricultural land (or such other

footpath number or numbers for

such footpath as may be specified

in the public path diversion order

entitled “Footpath Nos. 35.47/1,

35.47/6 & 35.47/10, Long Drax

and 35.6/12, Barlow, Drax

Power Station, Long Drax

Diversion Order 2014”, any

other public path diversion order

pertaining to Public Footpath No.

35.47/8/1 or otherwise )

North Yorkshire County Council,

Selby District Council

Drax Footpath 35.26/13/1,

running through agricultural land

north-west of Scurff Hall

Between point FP8B and FP10,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0062;

sheet 2 of 25)

Between point FP5 and FP6, as

depicted on the access, rights of

way and temporary stopping up

plans (drawing number

10-2574-GND-01-05-0061;

sheet 1 of 25)

route or routes as may be

specified in the instrument by

which the diversion is given

effect) so far as following such

diversion it or they fall within the

Order limits

North Yorkshire County Council,

Selby District Council

Newland Footpath No. 35.49/1/2,

running through agricultural land

north-west of Scurff Hall

Between point FP10 and FP11,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0062;

sheet 2 of 25)

(1)

Area

North Yorkshire County Council,

Selby District Council

North Yorkshire County Council,

Selby District Council

Newland Footpath No. 35.49/2/2,

running through agricultural land

north of Scurff Hall

Between point FP12 and FP13,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

Drax Footpath No. 35.26/7/1,

running east from Drax Main

Road along track at southern

edge of Read School Playing

Field and thence east and then

north-east through agricultural

land

Between point FP7 and FP8, and

between point FP8A and FP8B

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0062;

sheet 2 of 25)

111

(2)

Footpath to be temporarily

stopped up

Page 200: Explanatory Memorandum (Rev D)

North Yorkshire County Council,

Selby District Council

Newland Footpath No. 35.49/3/1,

running through agricultural land

to north-west of Scurff Hall

East Riding of Yorkshire Council Asselby Footpath No. 2, known

as Marsh Lane (Track), running

through agricultural land

Between point FP18 and FP19,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0064;

sheet 4 of 25)

Between point FP13 and FP14,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0063;

sheet 3 of 25)

(1)

Area

East Riding of Yorkshire Council Asselby Footpath No. 1, running

north from Asselby village,

across agricultural land

Between point FP20 and FP21,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0064;

sheet 4 of 25)

10-2574-GND-01-05-0062 and

0063; sheet 2 and 3 of 25)

North Yorkshire County Council,

Selby District Council

East Riding of Yorkshire Council Wressle Footpath No. 10,

running across agricultural land

north of Newsholme Parks

Between point FP22 and FP23,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0064;

sheet 4 of 25)

Newland Footpath No. 35.49/2/1,

running through agricultural land

north of Scurff Hall

Between point FP13 and FP15,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0063;

sheet 3 of 25)

East Riding of Yorkshire Council Wressle Footpath No. 6, running

across agricultural land north of

Newsholme Parks and south-west

of Brind

Between point FP24 and FP25,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0065;

sheets 5 of 25)

(2)

Footpath to be temporarily

stopped up

(3)

Extent of temporary stopping up

East Riding of Yorkshire Council Wressle Footpath No. 8, running

across agricultural land north of

Newsholme Parks and south-west

of Brind

Between point FP26 and FP27,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

North Yorkshire County Council,

Selby District Council

Drax Footpath No. 35.26/9/1,

known as Brickhill Lane

112

Between point FP16 and FP17,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0062;

sheet 2 of 25)

Page 201: Explanatory Memorandum (Rev D)

East Riding of Yorkshire Council Eastrington Bridleway No. 17,

known as Featherbed Lane

(Track). This is crossed twice,

toward the Lane’s western and

eastern ends

East Riding of Yorkshire Council Goodmanham Footpath No. 6,

running east from Rifle Butts

quarry, across agricultural land

Between point FP36 and FP37,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0072;

sheet 12 of 25)

Between point FP28 and FP29,

and from FP30 to FP31, as

depicted on the access, rights of

way and temporary stopping up

plans (drawing number

10-2574-GND-01-05-0066;

sheet 6 of 25)

(1)

Area

East Riding of Yorkshire Council Lund Footpath No. 2, running

south from Lund Wold Road,

along the edge of an agricultural

field, to Bulmers Triangle

plantation

Between point FP38 and FP39,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0075;

sheet 15 of 25)

10-2574-GND-01-05-0065;

sheet 5 of 25)

East Riding of Yorkshire Council

East Riding of Yorkshire Council Watton Footpath No. 2, running

across agricultural land north of

Bracken village

Between point FP40 and FP41,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0077;

sheet 17 of 25)

Spaldington Footpath No. 12,

along a track running south-east

from the A614 to Featherbed

Drain, across agricultural land

south of Sikes Farm

Between point FP32 and FP33,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0067;

sheet 7 of 25)

East Riding of Yorkshire Council Watton Footpath No. 20,

following track running north

from Bracken village through

agricultural land

Between point FP42 and FP43,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0077;

sheet 17 of 25)

(2)

Footpath to be temporarily

stopped up

(3)

Extent of temporary stopping up

East Riding of Yorkshire Council Hutton Cranswick Footpath No.

12, running north of and adjacent

to Bustard Nest Farm, across

Between point FP44 and FP45,

as depicted on the access, rights

of way and temporary stopping

East Riding of Yorkshire Council Market Weighton Footpath No.

11, running across agricultural

land at Crossfields Farm

113

Between point FP34 and FP35,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0071;

sheet 11 of 25)

Page 202: Explanatory Memorandum (Rev D)

Between point FP50 and FP51,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0080’

sheet 20 of 25)

(2)

Footpath to be temporarily

stopped up

East Riding of Yorkshire Council

East Riding of Yorkshire Council Skerne and Wansford Bridleway

No. 8, running along a track

south-west of Copper Hall,

through agricultural land

south-east of Skerne village

Between point FP52 and FP53,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0080;

sheet 20 of 25)

Hutton Cranswick Footpath No.

11, running north of Bustard Nest

Farm, across agricultural land

Between point FP46 and FP47,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0078;

sheet 18 of 25)

East Riding of Yorkshire Council Foston on the Wolds Footpath

No. 11, running through

agricultural land from Great Kelk

south to Gembling

Between point FP54 and FP55,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0082;

sheet 22 of 25)

(3)

Extent of temporary stopping up

agricultural land

East Riding of Yorkshire Council Barmston Footpath No. 2,

running across agricultural land

from Bridlington Road at

Stonehills to its junction with

Barmston Footpath No. 3, west

of Hamilton Hill

Between point FP56 and FP57,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0084;

sheet 24 of 25)

East Riding of Yorkshire Council Hutton Cranswick Footpath No.

18, running across agricultural

land north of Hutton village

East Riding of Yorkshire Council Barmston Footpath No. 3,

running north from Barmston

village, to west of Hamilton Hill,

through agricultural land

Between point FP58 and FP59,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0085;

sheet 25 of 25)

Between point FP48 and FP49,

as depicted on the access, rights

of way and temporary stopping

up plans (drawing number

10-2574-GND-01-05-0079;

sheet 19 of 25)

up plans (drawing number

10-2574-GND-01-05-0078;

sheet 18 of 25)

East Riding of Yorkshire Council Barmston Footpath No. 4,

running north from Barmston

village, to east of Hamilton Hill,

Between point FP60 and FP61,

as depicted on the access, rights

of way and temporary stopping

(1)

Area

East Riding of Yorkshire Council

114

Skerne and Wansford Bridleway

No. 7, running along a track from

Church Farm to Cleaves Farm,

through agricultural land

south-east of Skerne village

Page 203: Explanatory Memorandum (Rev D)

through agricultural land up plans (drawing number

10-2574-GND-01-05-0085;

sheet 25 of 25)

(1)

Area

(2)

Footpath to be temporarily

stopped up

115

(3)

Extent of temporary stopping up

Page 204: Explanatory Memorandum (Rev D)

116

Page 57 of 99 SCHEDULE 7 Article 16

Schedule FLand of which Only Subsoil More than 9 Metres Beneath Surface may be Acquired

(1) (2)

Area Number of land shown on land plan

Schedule GLand of which Temporary Possession may be Taken

(1) (2) (3) (4)

Area Number of land shown Purpose for which Relevant part of the

on land plan temporary possession

Authorised project may be taken

Schedule HDeemed Consent Under Coast Protection Act 1949

[Insert details of deemed consent]

Schedule IDeemed Licence Under the Food and Environment Protection Act 1985

[Insert details of deemed licence]

Schedule JTrees Subject to Tree Preservation Orders

(1) (2) (3)

Type of tree Number[reference] of tree shown Work to be carried out

on land plan

Page 205: Explanatory Memorandum (Rev D)

Schedule K Level Crossings

[Insert details of level crossings]

Schedule LProtective Provisions

Page 58 of 99

[Insert details of

protective provisions]

NOTES

Initial Commencement

Specified date

Specified date: 1 October 2009: see art 1.

UK Parliament SIs 2000-2009/2009/2251-2300/Infrastructure Planning (Model Provisions) (England and Wales) Order 2009 (SI 2009/2265)/SCHEDULE 3 Model Provisions for Harbours

SCHEDULE 3

MODEL PROVISIONS FOR HARBOURS

Article 2

117

Page 206: Explanatory Memorandum (Rev D)

CONTENTS

Preliminary

1

ACCESS TO WORKS

PART 1

TEMPORARY ACCESS

(1)

Area

(2)

Access details

North Yorkshire County Council,

Selby District Council

Temporary access from any point within the Order limits on New

Road, RDX0/A as indicatively shown on the access, rights of way and

temporary stopping up plans (drawing number

10-2574-GND-01-05-0061; sheet 1 of 25)

North Yorkshire County Council,

Selby District Council

Temporary access from any point within the Order limits on Pear

Tree Avenue, (RDX1/A and RDX1/B indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0061; sheet 1 of 25)

North Yorkshire County Council,

Selby District Council

Temporary access from any point within the Order limits on Carr

Lane, RDX2/A and RDX2/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0061; sheet 1 of 25)

North Yorkshire County Council,

Selby District Council

Temporary access from any point within the Order limits on Main

Road, RDX3/A and RDX3/B as indicatively shown on the access,

rights of way and temporary stopping up plans drawing number

10-2574-GND-01-05-0061; sheet 1 of 25)

North Yorkshire County Council,

Selby District Council

Temporary access from any point within the Order limits on Church

Dike Lane, RDX4/A and RDX4/B as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0062; sheet 2 of 25)

North Yorkshire County Council,

Selby District Council

Temporary access from any point within the Order limits on Brickhill

Lane, RDX5/A and RDX5/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0062; sheet 2 of 25)

North Yorkshire County Council,

Selby District Council

Temporary access from any point within the Order limits on the

A645, RDX6&7/A and RDX6&7/B as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0062; sheet 2 of 25)

North Yorkshire County Council, Temporary access from any point within the Order limits on Church

118

Page 207: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Access details

Selby District Council Dike Lane, RDX8/A and RDX8/B as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0062; sheet 2 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Barmby

Road, Asselby, RDX9/A and RDX9/B as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0063; sheet 3 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Barmby

Road, Asselby, RDX9/C as indicatively shown on the access, rights of

way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0063; sheet 3 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on A63 Hull

Road, RDX10/A and RDX10/B as indicatively shown on the access,

tights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0064; sheet 4 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Brind

Lane, Brind, RDX11/A and RDX11/B as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0065; sheet 5 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Wood

Lane, Brind, RDX12/A and RDX12/B as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0065; sheet 5 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on the A614

Holme Road, RDX13/A and RDX13/B as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0067; sheet 7 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Bursea

Lane, RDX14/A and RDX14/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0068; sheet 8 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Drain

Lane, RDX15/A and RDX15/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0068; sheet 8 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Skiff

Lane, RDX16/A and RDX16/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0069; sheet 9 of 25)

East Riding of Yorkshire Council Temporary access from Skiff Lane, RDX16/D as depicted on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0069; sheet 9 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Lock

Lane, RDX17/A and RDX17/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0069; sheet 9 of 25)

119

Page 208: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Access details

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Sand

Lane, RDX18/A and RDX18/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0070; sheet 10 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Cliffe

Road, RDX19/A and RDX19/B as indicatively shown on the access,

rights of way and temporary stopping up plans (drawing number

10-2574-GND-01-05-0071; sheet 11 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on the

A1034, Sancton Road, Market Weighton, RDX20/A and RDX20/B

as indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0072; sheet

12 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on the

A1079 Arras Hill, Market Weighton, RDX21/A and RDX21/B as

indicatively shown on the access, tights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0072; sheet

12 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Kiplingcoates Lane, Market Weighton, RDX22/A and RDX22/B as

indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0073; sheet

13 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Kiplingcoates Road, Market Weighton, RDX23/A and RDX23/B as

indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0074; sheet

14 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Kiplingcoates Racecourse Road, Etton, RDX24/A and RDX24/B as

indicatively shown on the access, rights of way and temporary

stopping up plans; (drawing number 10-2574-GND-01-05-0074;

sheet 14 of 25)

East Riding of Yorkshire

Council

Temporary access from any point within the Order limits on Park

Road, South Dalton, RDX25/A and RDX25/B as indicatively shown

on the access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0074; sheet 14 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Holme

Wold Road, South Dalton, RDX26/A and RDX26/B as indicatively

shown on access, rights of way and temporary stopping up plans

(drawing number 10-2574-GND-01-05-0075; sheet 15 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Lund

Wold Road, South Dalton, RDX27/A and RDX27/B as indicatively

shown on the access, rights of way and temporary stopping up plans

(drawing number 10-2574-GND-01-05-0076; sheet 16 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

120

Page 209: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Access details

Middleton Road, Lund, RDX28/A and RDX28/B as indicatively

shown on the access, tights of way and temporary stopping up plans

(drawing number 10-2574-GND-01-05-0076; sheet 16 of 25)

East Riding of Yorkshire

Council

Temporary access from any point within the Order limits on the

B1248, Lund Road, Middleton on the Wolds, RDX29/A and

RDX29/B as indicatively shown on the access, rights of way and

temporary stopping up plans (drawing number

10-2574-GND-01-05-0076; sheet 16 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Middleton Road, Kilnwick, RDX30/A and RDX30/B as indicatively

shown on the access, rights of way and temporary stopping up plans

(drawing number 10-2574-GND-01-05-0077; sheet 17 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Road

between Bracken Lane and Burnbutts Lane, Watton, RDX31/A and

RDX31/B as indicatively shown on the access, rights of way and

temporary stopping up plans (drawing number

10-2574-GND-01-05-0077; sheet 17 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Burnbutts Lane, Hutton Cranswick, RDX32/A and RDX32/B as

indicatively shown on the access, rights of way and Temporary

Stopping Up Plan drawing number 10-2574-GND-01-05-0077; sheet

17 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Southburn Road, Hutton Cranswick, RDX33/A and RDX33/B as

indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0079; sheet

19 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on the A164

Beverley Road, Hutton Cranswick, RDX34/A and RDX34/B as

indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0079; sheet

19 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Jenkinson Lane, Hutton Cranswick, RDX35/A and RDX35/B as

indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0079; sheet

19 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Ricklepits, Skerne, RDX36/A and RDX36/B as indicatively shown

on the access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0079; sheet 19 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on the

B1249 , Frodingham Road RDX37/A as indicatively shown on the

access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0081; sheet 21 of 25)

East Riding of Yorkshire Council Temporary access from Road to Skerne (Main Street), RDX37/B as

121

Page 210: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Access details

indicatively shown on access, rights of way and temporary stopping up

plans drawing number 10-2574-GND-01-05-0081; sheet 21 of 25)

East Riding of Yorkshire Council Temporary access from B1249, Frodingham Road RDX37/C as

indicatively shown on access, rights of way and temporary stopping up

plans (drawing number 10-2574-GND-01-05-0081; sheet 21 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on Main

Street, Great Kelk RDX38/A and RDX38/B as indicatively shown on

the access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0082; sheet 22 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on

Gransmoor Road, Gransmoor, RDX39/A and RDX39/B as

indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0083; sheet

23 of 25)

East Riding of Yorkshire Council Temporary access from any point within the Order limits on the

A165, Bridlington Road, Barmston, RDX40/A and RDX40/B as

indicatively shown on the access, rights of way and temporary

stopping up plans (drawing number 10-2574-GND-01-05-0084; sheet

24 of 25)

East Riding of Yorkshire Council Temporary access from the A614, Driffield as indicatively shown on

the access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0079; sheet 19 of 25)

PART 2

PERMANENT ACCESS

Refer to access rights of way and temporary stopping up plan, drawing number

10-2574-GND-01-05-0061 to 0085

(1)

Area

(2)

Access details

North Yorkshire County Council,

Selby District Council

Permanent access from the A645 / Wade House Lane, RDX6&7/C as

depicted on the access, rights of way and temporary stopping up plans

(drawing number 10-2574-GND-01-05-0062; sheet 2 of 25)

East Riding of Yorkshire Council Permanent access from Skiff Lane, RDX16/C as depicted on the

access rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0069; sheet 9 of 25)

East Riding of Yorkshire Council Permanent access from Lund Wold Road, South Dalton, RDX27/C as

depicted on the access, rights of way and temporary stopping up plans

(drawing number 10-2574-GND-01-05-0075; sheet 15 of 25)

East Riding of Yorkshire Council Permanent access from Main Street, Skerne, RDX36/C as depicted

on the access, rights of way and temporary stopping up plans (drawing

number 10-2574-GND-01-05-0080; sheet 20 of 25)

East Riding of Yorkshire Council Permanent access from A165 Bridlington Road / Sands Road,

122

Page 211: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Access details

Barmston RDX40/C as depicted on the access, rights of way and

temporary stopping up plans (drawing number

10-2574-GND-01-05-0085; sheet 25 of 25)

123

Page 212: Explanatory Memorandum (Rev D)

SCHEDULE 8 Article 40

RECORD OF THE SATISFACTION OF THE SECRETARY OF STATE

PURSUANT TO SECTION 132 OF THE 2008 ACT

The Secretary of State in exercise of his powers under subsection 132(2) of the 2008 Act hereby

records that he is satisfied that subsections 132(3) and 132(4B) of that Act apply to the open space

land described in this Schedule (by reference to the corresponding plot numbers in the book of

reference) because either—

that land, when burdened with the rights authorised to be compulsorily acquired under this (a)

Order, will be no less advantageous than it was before to the persons in whom it is vested,

other persons, if any, entitled to rights of common or other rights, and the public; or

that land forms part of an open space, none of it is of any of the other descriptions in (b)

subsection 132(1) and order rights are being acquired for a temporary (although possibly

long-lived) purpose.

(1)

Plot

number

(2)

Description of plot

Plot 1102 1,712.78 square metres or thereabouts of agricultural land situated to the West of the

River Hull at Wansford shown on sheets 20 and 21 of the land plans

Plot 1106 1,429.88 square metres or thereabouts of land forming part of the riverbed and banks

of the River Hull at Wansford shown on sheets 20 and 21 of the land plans

Plot 1277 3,397.66 square metres or thereabouts of land forming part of the beach known as

Barmston Sands, Barmston shown on sheet 25 of the land plans

Plot 1280 23,649 square metres or thereabouts of land forming part of the beach known as

Barmston Sands, Barmston shown on sheet 25 of the land plans

124

Page 213: Explanatory Memorandum (Rev D)

SCHEDULE 9 Article 28

LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)

Area

(2)

Plot number of land shown

on land plans

(3)

Purpose for which

temporary possession

may be taken

(4)

Relevant part of the

authorised

development

North

Yorkshire

County

Council; Selby

District

Council

Plot 1 Plot 60 Plot 124

Plot 2 Plot 61 Plot 125

Plot 4 Plot 62 Plot 128

Plot 5 Plot 63 Plot 129

Plot 8 Plot 64 Plot 132

Plot 10 Plot 65 Plot 133

Plot 11 Plot 70 Plot 136

Plot 12 Plot 72 Plot 140

Plot 13 Plot 76 Plot 141

Plot 14 Plot 79 Plot 144

Plot 17 Plot 80 Plot 145

Plot 22 Plot 83 Plot 148

Plot 23 Plot 88 Plot 150

Plot 24 Plot 89 Plot 151

Plot 30 Plot 90 Plot 153

Plot 31 Plot 92 Plot 155

Plot 33 Plot 94 Plot 157

Plot 34 Plot 96 Plot 159

Plot 35 Plot 100Plot 163

Plot 39 Plot 101Plot 164

Plot 42 Plot 102Plot 167

Plot 45 Plot 105Plot 170

Plot 46 Plot 106Plot 173

Plot 49 Plot 109Plot 174

Plot 50 Plot 114Plot 179

Plot 52 Plot 117Plot 180

Plot 53 Plot 120Plot 184

Plot 56 Plot 121Plot 185

Plot 57 Plot 187

Plot 58 Plot 188

Construction and

carrying out of the

authorised development

Work No. 2A

Work No. 3A

Work No. 3B

Work No. 3C

Work No. 3D

Work No. 3E

Work No. 3F

Work No. 3G

Work No. 4C

Work No. 4D

Work No. 5A

Work No. 5B

Work No. 5C

North

Yorkshire

County

Council; Selby

District

Council

Plot 4

Plot 76

Temporary construction

compounds, stores and

office areas for the

construction and carrying

out of the authorised

development

Work No. 2A

Work No. 4D

North

Yorkshire

County

Council; Selby

District

Council

Plot 7 Plot 73 Plot 135

Plot 9 Plot 74 Plot 137

Plot 16 Plot 77 Plot 139

Plot 19 Plot 81 Plot 142

Plot 20 Plot 82 Plot 146

Plot 25 Plot 97 Plot 147

Plot 26 Plot 99 Plot 156

Construction and

carrying out of the

drainage works

The drainage works

(which has the

meaning given in

article 2

(interpretation)

125

Page 214: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Plot number of land shown

on land plans

(3)

Purpose for which

temporary possession

may be taken

(4)

Relevant part of the

authorised

development

Plot 27 Plot 103Plot 160

Plot 29 Plot 107Plot 162

Plot 36 Plot 110Plot 168

Plot 37 Plot 111Plot 169

Plot 40 Plot 112Plot 171

Plot 41 Plot 115Plot 175

Plot 43 Plot 116Plot 176

Plot 47 Plot 119Plot 177

Plot 55 Plot 123Plot 178

Plot 66 Plot 127Plot 183

Plot 68 Plot 131

Plot 69 Plot 134

East Riding of

Yorkshire

Council

Plot 190Plot 580Plot 904

Plot 191Plot 582Plot 908

Plot 192Plot 584Plot 912

Plot 194Plot 585Plot 913

Plot 196Plot 587Plot 914

Plot 197Plot 588Plot 915

Plot 199Plot 589Plot 916

Plot 201Plot 592Plot 921

Plot 203Plot 593Plot 925

Plot 205Plot 597Plot 930

Plot 207Plot 598Plot 931

Plot 209Plot 599Plot 932

Plot 211Plot 602Plot 935

Plot 213Plot 603Plot 936

Plot 214Plot 605Plot 938

Plot 217Plot 610Plot 939

Plot 219Plot 611Plot 943

Plot 220Plot 612Plot 944

Plot 221Plot 613Plot 948

Plot 222Plot 616Plot 949

Plot 223Plot 617Plot 953

Plot 224Plot 619Plot 954

Plot 225Plot 620Plot 955

Plot 227Plot 622Plot 959

Plot 228Plot 623Plot 960

Plot 231Plot 624Plot 961

Plot 234Plot 629Plot 964

Plot 237Plot 633Plot 965

Plot 238Plot 634Plot 966

Plot 241Plot 636Plot 970

Plot 242Plot 638Plot 971

Plot 244Plot 639Plot 972

Plot 247Plot 641Plot 973

Plot 249Plot 642Plot 977

Plot 253Plot 644Plot 980

Construction and

carrying out of the

authorised development

Work No. 5C

Work No. 5D

Work No. 5E

Work No. 5F

Work No. 5G

Work No. 5H

Work No. 5I

Work No. 5J

Work No. 6C

Work No. 6D

Work No. 7

Work No. 8A

Work No. 8B

Work No. 8C

Work No. 8D

Work No. 8E

Work No. 8F

Work No. 8G

Work No. 8H

Work No. 8I

Work No. 8J

Work No. 8K

Work No. 8L

Work No. 9A

Work No. 9B

Work No. 9C

Work No. 9D

Work No. 10A

Work No. 10B

Work No. 10C

Work No. 10D

Work No. 10E

Work No. 10F

Work No. 10G

Work No. 10H

East Riding of

Yorkshire

Council

Plot 254Plot 645Plot 983

Plot 257Plot 647Plot 984

Plot 261Plot 648Plot 986

Plot 262Plot 649Plot 988

Work No. 10I

Work No. 10J

Work No. 10K

Work No. 11C

126

Page 215: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Plot number of land shown

on land plans

(3)

Purpose for which

temporary possession

may be taken

(4)

Relevant part of the

authorised

development

Plot 264Plot 651Plot 989

Plot 266Plot 653Plot 992

Plot 269Plot 657Plot 993

Plot 270Plot 662Plot 995

Plot 663

Plot 275Plot 664Plot 996

Plot 276Plot 668Plot 999

Plot 280Plot 669Plot 1000

Plot 281Plot 675Plot 1002

Plot 284Plot 676Plot 1003

Plot 285Plot 679Plot 1004

Plot 289Plot 682Plot 1005

Plot 290Plot 684Plot 1007

Plot 293Plot 688Plot 1008

Plot 295Plot 689Plot 1009

Plot 298Plot 692Plot 1010

Plot 302Plot 696Plot 1011

Plot 303Plot 700Plot 1016

Plot 308Plot 701Plot 1020

Plot 309Plot 702Plot 1021

Plot 310Plot 706Plot 1024

Plot 318Plot 707Plot 1026

Plot 321Plot 710Plot 1027

Plot 324Plot 712Plot 1030

Plot 325Plot 713Plot 1031

Plot 329Plot 714Plot 1032

Plot 332Plot 715Plot 1037

Plot 333Plot 716Plot 1038

Plot 334Plot 717Plot 1040

Plot 335Plot 718Plot 1041

Plot 338Plot 720Plot 1042

Plot 339Plot 721Plot 1043

Plot 341Plot 723Plot 1047

Plot 343Plot 724Plot 1048

Plot 345Plot 726Plot 1050

Plot 347Plot 727Plot 1051

Plot 348Plot 728Plot 1052

Plot 351Plot 729Plot 1055

Plot 353Plot 730Plot 1057

Plot 354Plot 732Plot 1058

Plot 357Plot 734Plot 1059

Plot 359Plot 736Plot 1060

Plot 360Plot 737Plot 1062

Plot 362Plot 738Plot 1063

Plot 363Plot 739Plot 1064

Plot 364Plot 742Plot 1067

Plot 365Plot 743Plot 1068

Plot 369Plot 744Plot 1069

Plot 370Plot 746Plot 1075

Plot 373Plot 747Plot 1076

Plot 374Plot 749Plot 1077

Plot 376Plot 750Plot 1078

Plot 378Plot 752Plot 1079

Work No. 11D

Work No. 12

Work No. 13A

Work No. 13B

Work No. 13C

Work No. 13D

Work No. 13E

Work No. 14B

Work No. 14C

Work No. 14D

Work No. 15B

127

Page 216: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Plot number of land shown

on land plans

(3)

Purpose for which

temporary possession

may be taken

(4)

Relevant part of the

authorised

development

Plot 379Plot 753Plot 1080

East Riding of

Yorkshire

Council

Plot 381Plot 754Plot 1081

Plot 382Plot 755Plot 1082

Plot 385Plot 757Plot 1084

Plot 386Plot 759Plot 1085

Plot 390Plot 760Plot 1086

Plot 391Plot 762Plot 1088

Plot 396Plot 765Plot 1089

Plot 397Plot 769Plot 1091

Plot 405Plot 770Plot 1094

Plot 406Plot 772Plot 1095

Plot 409Plot 773Plot 1096

Plot 413Plot 776Plot 1098

Plot 414Plot 777Plot 1100

Plot 418Plot 778Plot 1104

Plot 419Plot 779Plot 1108

Plot 422Plot 781Plot 1111

Plot 423Plot 782Plot 1112

Plot 426Plot 784Plot 1114

Plot 431Plot 785Plot 1117

Plot 433Plot 787Plot 1119

Plot 434Plot 788Plot 1122

Plot 436Plot 790Plot 1125

Plot 437Plot 791Plot 1128

Plot 439Plot 793Plot 1129

Plot 440Plot 794Plot 1132

Plot 443Plot 796Plot 1133

Plot 445Plot 797Plot 1134

Plot 448Plot 798Plot 1135

Plot 451Plot 799Plot 1139

Plot 452Plot 801Plot 1140

Plot 453Plot 802Plot 1141

Plot 455Plot 804Plot 1142

Plot 458Plot 805Plot 1146

Plot 459Plot 807Plot 1148

Plot 463Plot 808Plot 1150

Plot 464Plot 809Plot 1156

Plot 467Plot 811Plot 1157

Plot 469Plot 812Plot 1159

Plot 470Plot 814Plot 1160

Plot 472Plot 815Plot 1163

Plot 473Plot 816Plot 1164

Plot 476Plot 818Plot 1167

Plot 477Plot 819Plot 1168

Plot 478Plot 821Plot 1172

Plot 479Plot 822Plot 1173

Plot 481Plot 824Plot 1174

Plot 482Plot 825Plot 1176

Plot 484Plot 827Plot 1177

Plot 485Plot 828Plot 1180

Plot 487Plot 829Plot 1181

Plot 488Plot 830Plot 1183

128

Page 217: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Plot number of land shown

on land plans

(3)

Purpose for which

temporary possession

may be taken

(4)

Relevant part of the

authorised

development

Plot 490Plot 832Plot 1184

Plot 491Plot 833Plot 1185

Plot 494Plot 834Plot 1190

Plot 499Plot 836Plot 1191

Plot 500Plot 837Plot 1192

Plot 501Plot 839Plot 1196

Plot 503Plot 840Plot 1197

Plot 504Plot 842Plot 1200

East Riding of

Yorkshire

Council

Plot 506Plot 843Plot 1201

Plot 507Plot 846Plot 1202

Plot 509Plot 847Plot 1204

Plot 510Plot 848Plot 1205

Plot 511Plot 849Plot 1206

Plot 515Plot 851Plot 1213

Plot 516Plot 852Plot 1214

Plot 517Plot 854Plot 1219

Plot 518Plot 856Plot 1220

Plot 519Plot 857Plot 1224

Plot 520Plot 859Plot 1225

Plot 524Plot 860Plot 1227

Plot 525Plot 862Plot 1228

Plot 526Plot 863Plot 1230

Plot 530Plot 865Plot 1231

Plot 531Plot 866Plot 1233

Plot 534Plot 867Plot 1234

Plot 535Plot 869Plot 1237

Plot 538Plot 870Plot 1238

Plot 539Plot 872Plot 1241

Plot 541Plot 873Plot 1244

Plot 542Plot 874Plot 1245

Plot 543Plot 875Plot 1248

Plot 546Plot 877Plot 1249

Plot 547Plot 879Plot 1250

Plot 550Plot 880Plot 1251

Plot 553Plot 882Plot 1252

Plot 554Plot 883Plot 1256

Plot 558Plot 885Plot 1257

Plot 559Plot 886Plot 1260

Plot 564Plot 888Plot 1261

Plot 565Plot 889Plot 1262

Plot 566Plot 891Plot 1264

Plot 568Plot 892Plot 1266

Plot 572Plot 893Plot 1267

Plot 573Plot 894Plot 1269

Plot 574Plot 896Plot 1272

Plot 575Plot 900Plot 1275

Plot 576Plot 901Plot 1278

Plot 578Plot 902Plot 1279

Plot 579Plot 903Plot 1281

Plot 1282

East Riding of Plot 572 Temporary construction Work No. 6D

129

Page 218: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Plot number of land shown

on land plans

(3)

Purpose for which

temporary possession

may be taken

(4)

Relevant part of the

authorised

development

Yorkshire

Council

Plot 592

Plot 593

Plot 847

Plot 1059

Plot 1060

Plot 1068

Plot 1261

Plot 1262

Plot 1272

compounds, stores and

office areas for the

construction and carrying

out of the authorised

development

Work No. 7

Work No. 9D

Work No. 11D

Work No. 12

Work No. 14D

East Riding of

Yorkshire

Council

Plot 204Plot 493Plot 963

Plot 216Plot 495Plot 968

Plot 218Plot 496Plot 969

Plot 229Plot 498Plot 974

Plot 232Plot 505Plot 975

Plot 235Plot 512Plot 976

Plot 239Plot 514Plot 979

Plot 243Plot 521Plot 982

Plot 245Plot 523Plot 987

Plot 251Plot 527Plot 991

Plot 252Plot 529Plot 998

Plot 258Plot 532Plot 1006

Plot 260Plot 536Plot 1012

Plot 265Plot 540Plot 1014

Plot 268Plot 544Plot 1015

Plot 271Plot 548Plot 1018

Plot 272Plot 549Plot 1019

Plot 274Plot 552Plot 1023

Plot 277Plot 555Plot 1029

Plot 279Plot 557Plot 1034

Plot 283Plot 560Plot 1035

Plot 286Plot 561Plot 1036

Plot 288Plot 563Plot 1044

Plot 292Plot 567Plot 1045

Plot 297Plot 590Plot 1053

Plot 299Plot 591Plot 1054

Plot 301Plot 595Plot 1065

Plot 304Plot 596Plot 1070

Plot 305Plot 601Plot 1092

Plot 307Plot 606Plot 1093

Plot 311Plot 607Plot 1099

Plot 312Plot 608Plot 1101

Plot 313Plot 609Plot 1103

Plot 314Plot 614Plot 1105

Plot 316Plot 625Plot 1107

Plot 317Plot 626Plot 1109

Plot 319Plot 628Plot 1116

Plot 323Plot 630Plot 1118

Plot 326Plot 631Plot 1121

Plot 327Plot 632Plot 1123

Plot 331Plot 635Plot 1126

Plot 336Plot 646Plot 1130

Plot 349Plot 652Plot 1136

Construction and

carrying out of the

drainage works

The drainage works

(which has the

meaning given in

article 2

(interpretation)

130

Page 219: Explanatory Memorandum (Rev D)

(1)

Area

(2)

Plot number of land shown

on land plans

(3)

Purpose for which

temporary possession

may be taken

(4)

Relevant part of the

authorised

development

Plot 350Plot 654Plot 1138

Plot 355Plot 656Plot 1143

Plot 356Plot 658Plot 1144

Plot 361Plot 659Plot 1145

Plot 366Plot 660Plot 1147

Plot 367Plot 661Plot 1149

Plot 372Plot 666Plot 1151

Plot 375Plot 667Plot 1152

Plot 383Plot 671Plot 1154

Plot 387Plot 672Plot 1155

Plot 389Plot 673Plot 1162

Plot 392Plot 674Plot 1166

Plot 393Plot 678Plot 1169

Plot 395Plot 680Plot 1170

Plot 398Plot 681Plot 1171

Plot 399Plot 685Plot 1178

Plot 400Plot 687Plot 1186

Plot 401Plot 691Plot 1188

Plot 402Plot 693Plot 1189

Plot 404Plot 695Plot 1193

Plot 407Plot 697Plot 1195

Plot 408Plot 699Plot 1198

Plot 410Plot 703Plot 1207

Plot 412Plot 705Plot 1209

Plot 415Plot 709Plot 1210

Plot 417Plot 711Plot 1212

Plot 420Plot 850Plot 1215

Plot 905

Plot 424Plot 906Plot 1216

Plot 425Plot 910Plot 1217

Plot 427Plot 911Plot 1218

Plot 428Plot 917Plot 1221

Plot 429Plot 919Plot 1222

Plot 430Plot 920Plot 1232

Plot 441Plot 923Plot 1235

Plot 442Plot 924Plot 1236

Plot 444Plot 927Plot 1239

Plot 446Plot 928Plot 1240

Plot 447Plot 929Plot 1243

Plot 450Plot 934Plot 1246

Plot 457Plot 941Plot 1247

Plot 460Plot 942Plot 1253

Plot 462Plot 946Plot 1255

Plot 466Plot 947Plot 1259

Plot 474Plot 951Plot 1270

Plot 475Plot 952Plot 1273

Plot 492Plot 957Plot 1274

Plot 958 Plot 1276

Plot 1283

Plot 1284

Plot 1285

131

Page 220: Explanatory Memorandum (Rev D)

SCHEDULE 10 Article 42

DEEMED MARINE LICENCE UNDER PART 4 (MARINE

LICENSING) OF THE MARINE AND COASTAL ACCESS ACT 2009

PART 1

INTERPRETATION AND DETAILS OF LICENSED MARINE ACTIVITIES

Interpretation

2 Incorporation of the Harbours, Docks and Piers Clauses Act 1847

Principal Powers

3 Development consent etc granted by the Order4 Period for completion of work5 Limits of harbour6 Maintenance of authorised project7 Subsidiary works8 Benefit of Order9 Consent to transfer benefit of Order

Streets

10 Street works11 Stopping up of streets12 Temporary stopping up of streets13 Access to works14 Agreements with street authorities

—a) In this Schedule—1.

“the 2009 Act” means the Marine and Coastal Access Act 2009(jj);

“authorised deposits” means the substances and articles specified in sub-paragraph 2(4) of Part

I of this Schedule;

“Cefas” means the Centre for Environment, Fisheries and Aquaculture Science or any

replacement body or successor to its functions;

“commence” means beginning to carry out any material operation (as defined in section 56(4)

of the 1990 Act) other than operations consisting of archaeological investigations,

investigations for the purpose of assessing ground conditions, remedial work in respect of any

contamination or other adverse ground conditions and “commencement” is to be construed

accordingly;

(jj) 2009, c.23.

132

Page 221: Explanatory Memorandum (Rev D)

“enforcement officer” means a marine enforcement officer within the meaning of section 235 of

the 2009 Act (marine enforcement officers);

“English Heritage” means the Historic Buildings and Monuments Commission for England or

any successor to its statutory functions;

“the English inshore region” has the same meaning as that given in section 322 (interpretation)

of the 2009 Act;

“the Environment Agency” means the body established under the Environment Act 1995(kk) or

any successor to its statutory functions;

“the environmental statement” means the document(s) certified as the environmental statement

by the Secretary of State for the purposes of the Order together with any supplemental or

additional environmental statement submitted for the purposes of complying with and/or

discharging the Requirements in Schedule 3 (requirements) of the Order or conditions in

this licence;

“the Health and Safety Executive” or “HSE” means the body established under section 10

of the Health and Safety at Work etc. Act 1974(ll) or any successor to its statutory functions or

other authority performing, carrying out or having the same regulatory functions as the

HSE has at the date of the Order;

“the intertidal area” means the area between mean high water spring tide and mean low water

spring tide;

“the Kingfisher Fortnightly Bulletin” means the bulletin published by the Humber Seafood

Institute or such other alternative publication approved in writing by the MMO for the purposes

of this Schedule;

“the licence conditions” means the conditions set out in Part 2 of this Schedule;

“licensed activity” means a licensable marine activity listed in paragraph 2 of Part 1 of this

Schedule;

“licensed location” means the area set out at paragraphs 2(3)(a) and 2(3)(b) of Part 1 of this

Schedule;

“licensed works” means any works constructed in the course of a licensed activity;

“maintain” includes inspect, examine, monitor, test, repair, set up, configure, dismantle and/or

reconstruct the authorised development and/or replace part or a section of the authorised

development with a part or section which materially serves the same purpose and—

does not include maintenance activities which give rise to any materially new or materially (a)

different significant environmental effects from those assessed in the environmental

statement; and

“maintaining” and “maintenance” must be construed accordingly;(b)

“the Marine Management Organisation” or “the MMO” means the body of that name created

under the 2009 Act which is responsible for the monitoring and enforcement of this licence or

any successor to its functions;

“the Maritime and Coastguard Agency” or “MCA” means the executive agency of the

Department for Transport or any successor to its functions;

“mean high water spring tide” or “MHWS” means the highest level which spring tides reach on

average over a period of time;

“mean low water spring tide” or “MLWS” means the lowest level which spring tides reach on

average over a period of time;

“Natural England” means the body established by section 1 of the Natural Environment and

Rural Communities Act 2006 or any successor to its statutory functions;

(kk) 1995 c.25.

(ll) 1974 c.37; section 10 of the Health and Safety at Work etc. Act 1974 is substituted by S.I. 2008/960.

133

Page 222: Explanatory Memorandum (Rev D)

“notice to mariners” includes any notice to mariners which may be issued by the Admiralty,

Trinity House, Queen's harbourmasters, government departments and harbour and pilotage

authorities;

“the Order” means the Yorkshire and Humber (Carbon Capture and Storage Cross Country

Pipeline) Order 201[●];

“the project design statement” means the document certified as the project design statement by

the Secretary of State for the purposes of the Order;

“regulatory authorities” means any government department, public, local or regulatory or any

other authority or institution having regulatory functions, powers, duties and obligations having

the full force of law;

“sea” has the same meaning as that given at section 42(3) of the 2009 Act;

“stage” means for the purposes of this Schedule (in no order of construction phasing) either—

those elements of Work No. 5C of Schedule 1 (authorised development) of the Order, and (a)

any further associated development listed in items (a) to (n) in Schedule 1 in connection

with that Work No., which fall within the English inshore region; or

those elements of Work No. 15B of Schedule 1 (authorised development) of the Order, (b)

and any further associated development listed in items (a) to (n) in Schedule 1 in

connection with that Work No., which fall within the English inshore region;

Trinity House” means the Corporation of Trinity House of Deptford Strond;

“the UK Hydrographic Office” means the Hydrographic Office of the Ministry of Defence,

Taunton, Somerset TA1 2DN or any replacement body or successor to its functions;

“the undertaker” has the same meaning as that given in article 2 (interpretation) of the Order;

“vessel” means every description of vessel, however propelled or moved, and includes a

non-displacement craft, a personal watercraft, a barge, a jack up barge, a seaplane on the

surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any

other thing constructed or adapted for movement through, in, on or over water and which is at

the time in, on or over water;

“VHF” means very high frequency; and

“working day” means a day which is not a Saturday, Sunday, Bank Holiday or other public

holiday.

Unless otherwise indicated all geographical co-ordinates contained within this licence are in (2)

latitude and longitude degrees and minutes to three decimal places and the datum used for such

co-ordinates is WGS84.

Except where otherwise notified in writing by the relevant organisation, the primary point of (3)

contact with the organisations listed below and the address for returns and correspondence is—

Marine Licensing Team(a)

Marine Management Organisation

Lancaster House

Hampshire Court

Newcastle upon Tyne NE4 7YH

Tel: 0300 123 1032

Email: [email protected]

Northern Marine Area(b)

Marine Management Organisation

Unit 2a

Newchase Court

Hopper Hill Road

134

Page 223: Explanatory Memorandum (Rev D)

Eastfield

Scarborough

North Yorks YO11 3YS

Tel: 01723 580040

Email: [email protected]

Trinity House(c)

Tower Hill

London EC3N 4DH

Tel: 020 7481 6900

The United Kingdom Hydrographic Office (d)

Admiralty Way

Taunton

Somerset TA1 2DN

Tel: 01823 337 900

Maritime and Coastguard Agency Navigation Safety Branch(e)

Bay 2/04

Spring Place

105 Commercial Road

Southampton S015 lEG

Tel: 023 8032 9191

Centre of Environment, Fisheries and Aquaculture Science(f)

Pakefield Road

Lowestoft

Suffolk NR33 OHT

Tel: 01502 562 244

The Environment Agency (g)

8 City Walk

Leeds

West Yorkshire LS11 9AT

0370 8506506

Natural England(h)

Foundary House

3 Millsands

Riverside Exchange

Sheffield S3 8NH

Tel: 0845 600 3078

English Heritage(i)

Eastgate Court

195-205 High Street

Guildford GU1 3EH

135

Page 224: Explanatory Memorandum (Rev D)

Details of licensed marine activities

—a) Subject to the licence conditions this licence authorises the undertaker (and any agent or 2.

contractor acting on their behalf) to carry out the following licensable marine activities pursuant to

section 66(1) of the 2009 Act—

the deposit at sea of the substances and articles specified in sub-paragraph (5);(a)

the construction of works in, under or over the intertidal area;(b)

the inspection and maintenance of works in, under or over the intertidal area; (c)

the construction of works under the River Ouse;(d)

the inspection and maintenance of works under the River Ouse; and(e)

sampling or investigative works required in connection with paragraphs (a) and (e). (f)

The activities set out in sub-paragraph (1) are authorised in relation to the construction and (1)

operation of those elements of Work No. 5C and Work No. 15B of Schedule 1 (authorised

development) of this Order, and any further associated development listed in items (a) to (n) in

Schedule 1 in connection with those Work Nos., which fall within the English inshore region.

The undertaker (and any agent, contractor or subcontractor acting on its behalf) may engage in (2)

the licensed activities in—

the area bounded by the coordinates set out in this sub-paragraph; and(a)

any area within the Order limits (as defined in article 2 (interpretation) of this Order) (b)

which falls outwith the area bounded by the coordinates set out in this sub-paragraph but

which falls below mean high water spring tide when the licensed activities are carried out.

136

Page 225: Explanatory Memorandum (Rev D)

Latitude Longitude

Work No. 15B at the intertidal

54° 01.734’ N 0° 12.975’ W

54° 01.741’ N 0° 12.814’ W

54° 01.522’ N 0° 12.807’ W

54° 01.523’ N 0° 12.951’ W

Latitude Longitude

Work No. 5C at the river Ouse

53° 44.178’ N 0° 57.109’ W

53° 44.131’ N 0° 56.976’ W

53° 44.096’ N 0° 57.070’ W

53° 44.125’ N 0° 57.255’ W

53° 44.084’ N 0° 56.866’ W

53° 44.080’ N 0° 56.857’ W

53° 44.076’ N 0° 56.859’ W

53° 44.079’ N 0° 56.867’ W

For the avoidance of doubt, the licence in this Schedule does not authorise the (3)

decommissioning of the licensed works for which a separate marine licence may be required.

The substances or articles authorised for deposit at sea are—(4)

metal;(a)

gravel;(b)

concrete;(c)

sand; (d)

bentonite and grout; and(e)

rock backfill from a recognised source, containing minimum fines.(f)

In the application of section 72 of the 2009 Act to this licence, subsection 72(8) of the 2009 (5) Act does not apply to a transfer made in accordance with article 9 (transfer of benefit of Order) of

this Order.

137

Page 226: Explanatory Memorandum (Rev D)

PART 2

LICENCE CONDITIONS

Application of licence conditions

This Part does not apply to any part of Work No. 5C and Work No. 15B of Schedule 1 1.

(authorised development) which falls outside the English inshore region.

Licensed location

The licensed works must be located within the licensed location.2.

Notifications and inspections

—a) The undertaker must ensure that a copy of this Schedule and any subsequent amendments 3.

or revisions to it are provided prior to commencement of a stage of the licensed activities to—

all agents and contractors notified to the MMO in accordance with the licence conditions; (a)

and

the masters and transport managers responsible for the vessels notified to the MMO in (b)

accordance with the licence conditions,

who are to be engaged in the carrying out of that stage.

Only those persons and vessels notified to the MMO in accordance with the licence conditions (1)

are permitted to carry out the licensed activities.

Copies of this Schedule must also be available for inspection by an enforcement officer at all (2)

times during construction of a stage of the licensed works at the following locations—

the undertaker's registered address;(a)

any site office for that stage located at or adjacent to the construction site and used by the (b)

undertaker or its agents and contractors responsible for the loading, transportation or

deposit of the authorised deposits and works; and

on board each vessel or at the office of any transport manager with responsibility for (c)

vessels from which authorised deposits are to be made or authorised works undertaken for that

stage.

The undertaker must provide access to the construction site for licensed activities or any other (3)

associated works or vessels to facilitate any inspection that the MMO considers necessary to inspect

the works during the carrying out of the licensed activities.

The undertaker must inform the MMO in writing of the commencement of a stage of the (4)

licensed activities at least five working days in advance of that stage.

At least seven days prior to the commencement of a stage of the licensed activities the (5)

undertaker must publish in the Kingfisher Fortnightly Bulletin details of the vessel routes, timings

and locations relating to the carrying out of that stage.

The undertaker must ensure that—(6)

a notice to mariners is issued at least ten days prior to the commencement of a stage of the (a)

licensed activities advising of the commencement of that stage within the licensed location;

and

a second notice to mariners is issued advising of the commencement of a stage of the (b)

licensed activities within the licensed location.

The notices to mariners must be updated and reissued not less frequently than weekly during (7)

construction of a stage of the licensed works.

The undertaker must notify—(8)

138

Page 227: Explanatory Memorandum (Rev D)

the UK Hydrographic Office within ten days of the completion of a stage of the licensed (a)

works in order that all necessary amendments to nautical charts are made;

the MMO of completion of a stage of the licensed works within ten days of completion of (b)

those works; and

the MMO of any marking of the route of a stage of the licensed works (if any) within ten (c)

days of completion of that stage.

The undertaker must ensure that prior to the commencement of a stage of the licensed (9)

activities the following suitably qualified and experienced liaison officers are appointed for that

stage and their identity and credentials notified to the MMO as part of the project environmental

management plan required by paragraph 5(1)(c) (pre-construction plans and documentation) for

that stage—

a Fisheries Liaison Officer or Officers; and(a)

an Environmental Liaison Officer or Officers.(b)

The responsibilities of the Fisheries and Environmental Liaison Officer(s) must be provided (10)

to the MMO no later than twelve weeks prior to the commencement of a stage of the licensed

activities for comment.

The undertaker must—(11)

notify the MMO in writing of an application made by it to the Secretary of State for (a)

consent pursuant to article 9(1) (transfer of benefit of Order) of the Order no later than 14

days after the making of such an application where the application includes a request for

consent for the whole of the benefit of this licence to be transferred or granted to another

person; and

notify the MMO in writing of any transfer or grant of the whole of the benefit of this (b)

licence to another person made pursuant to article 9(1) (transfer of benefit of Order) of

the Order no later than 14 days after that transfer or grant has been effected.

Chemicals, drilling and debris

—a) All chemicals used in the construction of the licensed works, including any chemical 4.

agents placed within the void comprised in the construction of Work No. 5C and Work No. 15B,

must be selected from the List of Notified Chemicals approved for use by the offshore oil and gas

industry under the Offshore Chemicals Regulations 2002(mm) unless otherwise agreed in writing

by the MMO.

The undertaker must ensure that any coatings and/or treatments are suitable for use in the (1)

marine environment and are used in accordance with relevant Pollution Prevention Guidelines

issued by the Environment Agency and/or relevant guidelines issued by the Health and Safety

Executive; and any accidental spillages of such coatings and/or treatments in the marine

environment must be reported to the MMO marine pollution response team within six hours of such

spillage.

The storage, handling, transport and use of fuels, lubricants, chemicals and other substances (2)

must be undertaken so as to prevent releases into the marine environment including bunding of

110% of the total volume of all reservoirs and containers.

Where drilling works are proposed as the trenchless crossing technique for the purposes of a (3)

licensed activity, and any system other than water-based mud is proposed for such drilling works,

the MMO's written approval in relation to the proposed disposal of any arisings from such drilling

works must be obtained prior to the commencement of such drilling works; and if the disposal of the

arisings at sea does not fall within the scope of the environmental statement a separate marine

licence for such drilling is required.

The undertaker must ensure that any—(4)

waste and/or debris arising from construction of a stage of the licensed activities;(a)

equipment used for the purposes of carrying out a stage of the licensed activities; and(b)

(mm) S.I. 2002/1355; the regulations are amended by S.I. 2011/982.

139

Page 228: Explanatory Memorandum (Rev D)

works placed below MHWS temporarily for the purposes of carrying out a stage of the (c)

licensed activities,

are removed within four weeks of completion of that stage.

Pre-construction plans and documentation

—a) At least four months prior to the commencement of a stage of the licensed activities 5.(unless such longer period is agreed in writing by the MMO) the undertaker must submit for the

approval of the MMO—

a construction and monitoring programme to include details of— (a)

the proposed construction start date for the licensed works comprised in that stage;(i)

timings for mobilisation of plant, delivery of materials and installation works for that (ii)

stage; and

the methodologies for, and timings for preparing and submitting, survey (iii)

specifications, data collection and analysis for that stage to the MMO in accordance

with paragraphs 8 (pre-construction baseline) to 10 (post construction),

and where compliance with a construction and monitoring programme agreed under this

paragraph (a) is not possible, the undertaker must notify the MMO in writing and

submit a revised programme for approval; and, in circumstances where the revised

programme affects other plans or documents agreed by the MMO under this paragraph,

the MMO may require construction works to cease until it has approved the revised

programme;

a construction method statement for that stage which is in accordance with the project (b)

design statement and environmental statement and which includes (where relevant to that

stage) details of—

reception pit construction;(i)

trenchless crossing method(s);(ii)

pipeline installation;(iii)

works associated with sub-paragraphs (b)(i), (b)(ii) and (b)(iii) above;(iv)

contractors; and(v)

vessels.(vi)

a project environmental management plan for that stage to include details of— (c)

a marine pollution contingency plan to address the risks, methods and procedures to (i)

deal with any spills and collision incidents during construction and operation of that

stage of the licensed works in relation to all licensed activities carried out between

mean low water springs and mean high water springs in that stage;

a chemical risk analysis to include information regarding how and when chemicals (ii)

are to be used, stored and transported in that stage;

waste management and disposal arrangements for that stage;(iii)

the appointment and responsibilities of any officers required in connection with the (iv)

carrying out of that stage of the licensed activities; and

locations of any archaeological exclusion zones for that stage agreed as part of a (v)

written scheme of investigation approved under sub-paragraph (d);

a written scheme of archaeological investigation for that stage to include— (d)

details of responsibilities of the undertaker, archaeological consultant and contractor (i)

for that stage;

a methodology for any site investigation for that stage including any specifications (ii)

for geophysical and geotechnical;

140

Page 229: Explanatory Memorandum (Rev D)

analysis and reporting of survey data for that stage to be submitted to the MMO (iii)

within three months of survey completion and to be agreed in writing with the MMO

following consultation with English Heritage;

delivery of any mitigation for that stage including, where necessary, archaeological (iv)

exclusion zones;

monitoring during and post construction of that stage, including a conservation (v)

programme for finds;

archiving of archaeological material for that stage with a public archive in (vi)

accordance with the Online AccesS to the Index of archaeological investigationS

(OASIS) system; and

a reporting and recording protocol for that stage, including reporting of any wreck or (vii)

wreck material during construction, operation and decommissioning of the authorised

development.

No stage of a licensed activity is to commence until the relevant programme, statement, plan, (1)

protocol or scheme required to be approved for that stage under sub-paragraph (1) has been

submitted to and approved in writing by the MMO; and a stage of a licensed activity must be

carried out in accordance with the plans, protocols, statements, schemes and details approved in

relation to it under sub-paragraph (1), unless otherwise agreed in writing by the MMO.

A construction compound comprised in an area in which either Work No. 5C or Work No. (2)

15B of Schedule 1 (authorised development) of this Order are to be carried out and which is to be

located within the intertidal area may not be established until a statement specifying—

the materials to be stored in that construction compound;(a)

proposed arrangements for the management of stored materials in that construction (b)

compound; and

the distance between the stored materials in that construction compound and the relevant (c)

water body in the area to which the relevant Work No. relates,

has been submitted to and approved in writing by the MMO; and the undertaker must comply with

that statement whilst that construction compound remains established, unless otherwise agreed in

writing by the MMO, and in this sub-paragraph “construction compound” means the temporary

compounds needed to store equipment, materials and site accommodation during the construction of

the authorised development.

Works comprised in Work No. 15B of Schedule 1 (authorised development) of the Order (3)

(insofar as they are within the licensed location) must not be commenced until a detailed piling

method statement (which shall include details of the construction and removal of a cofferdam (if

proposed) and whether, and if so how, any cofferdam sheet piles are to be left in place after

construction) for those works has been submitted to and approved by the MMO.

The cofferdam comprised in Work No. 15B must not be commenced until a method statement (4)

for the monitoring and management of sediment arising from use of the cofferdam has been

submitted to and approved in writing by the MMO.

Hydrostatic testing activities in the River Ouse the undertaker must not be carried out until (5)

details of any pipe to be placed temporarily in the River Ouse for purposes connected with those

hydrostatic testing activities have been submitted to and approved in writing by the MMO.

Reporting of engaged agents, contractors and vessels

—a) The undertaker must provide to the MMO— 6.

the name and function of any agent or contractor appointed to engage in a stage of the (a)

licensed activity at least five working days before that agent or contractor engages in that

stage; and

a listing of the vessels currently and to be used in relation to the a stage of the licensed (b)

activities each week during the carrying out of that stage.

141

Page 230: Explanatory Memorandum (Rev D)

Any changes to the details supplied to the MMO under this paragraph must be notified to and (1)

agreed with the MMO in writing prior to the agent, contractor or vessel in question engaging in a

stage of the licensed activities.

Equipment and operation of vessels engaged in licensed activities

—a) All vessels employed to perform the licensed activities must be constructed and equipped 7.

to be capable of the proper performance of such activities in accordance with the licence conditions

and must comply with sub-paragraphs (2) and (3).

Subject to sub-paragraph (3) all motor powered vessels must be fitted with—(1)

electronic positioning aid to provide navigational data;(a)

radar;(b)

echo sounder; and(c)

multi-channel VHF.(d)

No vessel is to engage in the licensed activities unless all the equipment specified in (2)

sub-paragraph (2) is fully operational.

Pre-construction baseline

—a) Any pre-construction baseline report for a stage of the licensed activities must take 8.

account of any existing environmental data, assessments and reports prepared by or on behalf of the

undertaker and relevant to the relevant part of the licensed location for that stage.

A stage of the licensed activities may not commence until a pre-construction baseline report (1)

for that stage has been submitted to and approved in writing by the MMO; and the form and content

of a report, including any environmental monitoring, must be agreed in writing by the MMO.

A pre-construction baseline report in respect of the area to which works comprised in Work (2)

No. 15B of Schedule 1 (authorised development) of the Order (insofar as they are within the

licensed location) relate must include—

a Phase l survey of the intertidal area;(a)

data concerning existing marine fish and shellfish populations and marine spawning (b)

activity within five kilometres of that part of the licensed location comprising the

intertidal area;

data concerning existing marine ornithological activity within five kilometres of that part of (c)

the licensed location comprising the intertidal area; and

a desk based assessment of known and predicted archaeology and paleo-archaeological (d)

deposits.

In the event that a pre-construction baseline report for a stage of the licensed activities (3)

contains sufficient information regarding the effects of that stage on individual matters listed at

sub-paragraphs (3)(a) to (3)(d) the stage may be commenced (subject to any ongoing monitoring

requirements notified by the MMO to the undertaker in writing).

Construction monitoring

—a) During construction of a stage of the licensed works the undertaker must submit 9.

environmental monitoring reports to the MMO in accordance with the construction and monitoring

programme approved for that stage under paragraph 5(1)(a) (pre-construction plans and

documentation) which must include (where relevant to that stage)—

the monitoring of suspended sediment concentrations in seawater within the jetting (a)

area for that stage and at a suitable reference site, should jetting be used for pipeline

installation in that stage;

measurements of noise and vibration generated by the installation of any piled pits and (b)

trenchless crossing in that stage.

142

Page 231: Explanatory Memorandum (Rev D)

A cofferdam comprised in Work No. 15B of Schedule 1 (authorised development) of the (1)

Order may not be of dimensions such that the amount of material subsequently excavated for the

purposes of placing the pipeline gives rise to any materially new or materially different significant

effects from those assessed in the environmental statement, unless otherwise agreed in writing with

the MMO.

Post construction

—a) Following construction of a stage of the licensed works the undertaker must submit 10.

environmental monitoring reports to the MMO in accordance with the construction and monitoring

timetable approved under 5(1)(a) (pre-construction plans and documentation).

As built drawings of a stage of the licensed works must be submitted to the MMO no later (1)

than 56 days after completion of construction of that stage.

Aids to navigation

—a) The undertaker must during the whole period of the construction, operation, alteration, 11.

replacement or decommissioning of the licensed works exhibit such lights, marks, sounds, signals

and other aids to navigation, and take such other steps for the prevention of danger to navigation, as

directed by Trinity House from time to time.

The undertaker must submit reports quarterly to Trinity House detailing the working condition (1)

of aids to navigation. Reports may be submitted more frequently as specified by Trinity House.

The undertaker must notify Trinity House and the MMO of any failure of the aids to (2)

navigation including timescales and plans for remedying such failures, as soon as possible and no

later than 24 hours following the undertaker becoming aware of any such failure.

Amendments to approved details

With respect to any condition of this Schedule which requires the licensed activities to be 12.

carried out in accordance with plans, programmes and reports approved by the MMO, the approved

plans, programmes and reports include any amendments that may subsequently be approved in

writing by the MMO to the extent that the MMO may lawfully do so.

143

Page 232: Explanatory Memorandum (Rev D)

SCHEDULE 11 Article 48

PROTECTIVE PROVISIONS

PART 1

FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE

UNDERTAKERS

Application

For the protection of the undertakers referred to in this Part of this Schedule the following 1.

provisions, unless otherwise agreed in writing at any time between the promoter and the undertaker

concerned, have effect.

Interpretation

In this Part of this Schedule—2.

“alternative apparatus” means alternative apparatus adequate to enable the undertaker in

question to fulfil its statutory functions in a manner not less efficient than previously;

“apparatus” means—

in the case of an electricity undertaker, electric lines or electrical plant (as defined in the (a)

Electricity Act 1989(nn)), belonging to or maintained by that electricity undertaker for the

purposes of electricity supply;

in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or (b)

maintained by that gas transporter for the purposes of gas supply;

in the case of a water undertaker, mains, pipes or other apparatus belonging to or (c)

maintained by that water undertaker for the purposes of water supply; and

in the case of a sewerage undertaker—(d)

any drain or works vested in the undertaker under the Water Industry Act 1991(oo) (i)

and Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011(pp);

and

any sewer which is so vested or is the subject of a notice of intention to adopt given (ii)

under section 102(4) of that Act or an agreement to adopt made under section 104 of

that Act,

and in each case includes a sludge main, disposal main (within the meaning of (iii)

section 219 of that Act) or sewer outfall and any manholes, ventilating shafts, pumps

or other accessories forming part of any such sewer, drain or works,

and includes any structure in which apparatus is or is to be lodged or which gives or (iv)

will give access to apparatus;

“commence” has the same meaning as in paragraph 1 of Schedule 3 (requirements);

“functions” includes powers and duties;

“in” in a context referring to apparatus or alternative apparatus in land includes a reference to

apparatus or alternative apparatus under, over or upon land;

(nn) 1989 c. 29.

(oo) 1991 c. 56.

(pp) S.I. 2011/1566.

144

Page 233: Explanatory Memorandum (Rev D)

“pipeline” means the whole or any part of a pipeline belonging to or maintained by an

undertaker and includes any ancillary works and apparatus;

“plan” includes a section and description of the works to be executed;

“promoter” means the undertaker as defined in article 2 (interpretation) of this Order;

“undertaker” means—

any licence holder within the meaning of Part 1 of the Electricity Act 1989;(a)

a gas transporter within the meaning of Part 1 of the Gas Act 1986(qq);(b)

a water undertaker within the meaning of the Water Industry Act 1991; and(c)

a sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991,(d)

for the area of the authorised development, and in relation to any apparatus, means the (e)

undertaker to whom it belongs or by whom it is maintained.

On-street apparatus

This Part of this Schedule does not apply to apparatus in respect of which the relations between 3.

the promoter and the undertaker are regulated by the provisions of Part 3 of the 1991 Act.

Acquisition of apparatus

Regardless of any provision in this Order or anything shown on the land plans, the promoter 4.

must not acquire any apparatus otherwise than by agreement.

Removal of apparatus

—a) If, in the exercise of the powers conferred by this Order, the promoter acquires any 5.

interest in any land in which any apparatus is placed, that apparatus must not be removed under this

Part of this Schedule and any right of an undertaker to maintain that apparatus in that land must not

be extinguished until alternative apparatus has been constructed and is in operation to the

reasonable satisfaction of the undertaker in question.

If, for the purpose of executing any works in, on or under any land purchased, held, (1)

appropriated or used under this Order, the promoter requires the removal of any apparatus placed in

that land, it must give the undertaker in question written notice of that requirement, together with a

plan of the work proposed.

If alternative apparatus or any part of such apparatus is to be constructed as a consequence of (2)

the removal of apparatus placed on the land referred to in sub-paragraph (2), the undertaker in

question must, on receipt of a written notice to that effect from the promoter, as soon as reasonably

possible use its best endeavours to obtain the necessary facilities and rights in other land in which

the alternative apparatus is to be constructed.

The undertaker in question must, after the alternative apparatus to be provided or constructed (3)

has been agreed or settled by arbitration in accordance with article 51 (arbitration), and after the

grant to the undertaker of any such facilities and rights as are referred to in sub-paragraph (3),

proceed without unnecessary delay to construct and bring into operation the alternative apparatus

and subsequently to remove any apparatus required by the promoter to be removed under the

provisions of this Part of this Schedule.

Regardless of anything in sub-paragraph (4), if the promoter gives notice in writing to the (4)

undertaker in question that it desires itself to execute any work, or part of any work in connection

with the construction or removal of apparatus, that work, instead of being executed by the

undertaker, must be executed by the promoter without unnecessary delay under the superintendence,

if given, and to the reasonable satisfaction of the undertaker.

(qq) 1986 c.44.

145

Page 234: Explanatory Memorandum (Rev D)

Retained apparatus: protection

—a) Not less than 28 days before starting the execution of any works of the type referred to in 6.

sub-paragraph 5(2) that are near to, or will or may affect, any apparatus the removal of which has

not been required by the promoter under sub-paragraph 5(2), the promoter must submit to the

undertaker in question a plan of the works to be executed.

Those works are to be executed only in accordance with the plan submitted under (1)

sub-paragraph (1) and in accordance with such reasonable requirements as may be made in

accordance with sub-paragraph (3) by the undertaker for the alteration or otherwise for the

protection of the apparatus, or for securing access to it; and the undertaker is entitled to watch and

inspect the execution of those works.

Any requirements made by an undertaker under sub-paragraph (2) must be made within a (2)

period of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to

it.

If an undertaker in accordance with sub-paragraph (2) and in consequence of the works (3)

proposed by the promoter, reasonably requires the removal of any apparatus and gives written

notice to the promoter of that requirement, paragraphs 1 to 5 apply as if the removal of the

apparatus had been required by the promoter under sub-paragraph 5(2).

Nothing in this paragraph precludes the promoter from submitting at any time or from time to (4)

time, but in no case less than 28 days before commencing the execution of any works, a new plan,

instead of the plan previously submitted, and having done so the provisions of this paragraph apply

to and in respect of the new plan.

The promoter is not required to comply with sub-paragraph (1) in a case of emergency but in (5)

that case it must give to the undertaker in question notice as soon as is reasonably practicable and a

plan of those works as soon as reasonably practicable subsequently and must comply with

sub-paragraph (2) in so far as is reasonably practicable in the circumstances.

Cathodic protection testing

Where in the reasonable opinion of the promoter—7.

the authorised development might interfere with the existing cathodic protection forming (a)

part of a pipeline; or

a pipeline might interfere with the proposed or existing cathodic protection forming part of (b)

the authorised development,

the undertaker to whom the pipeline belongs, or who maintains that pipeline, and the (c)

promoter must co-operate in undertaking the tests which the promoter considers reasonably

necessary for ascertaining the nature and extent of such interference and measures for

providing or preserving cathodic protection.

Expenses

—a) Subject to the following provisions of this paragraph, the promoter must repay to an 8.

undertaker the reasonable expenses reasonably incurred by that undertaker in, or in connection

with—

the inspection, removal, alteration or protection of any apparatus; or(a)

the construction of any new apparatus,(b)

which may be required in consequence of the execution of any such works as are required (c)

under this Part of this Schedule.

The value of any apparatus removed under the provisions of this Part of this Schedule is to be (1)

deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.

If in accordance with the provisions of this Part of this Schedule—(2)

146

Page 235: Explanatory Memorandum (Rev D)

apparatus of better type, of greater capacity or of greater dimensions is placed in (a)

substitution for existing apparatus of worse type, of smaller capacity or of smaller

dimensions; or

apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is (b)

placed at a depth greater than the depth at which the existing apparatus was situated,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of

apparatus at that depth, as the case may be, is not agreed by the promoter or, in default of

agreement, is not determined by arbitration in accordance with article 51 (arbitration) to be

necessary, then, if such placing involves cost in the construction of works under this Part of this

Schedule exceeding that which would have been involved if the apparatus placed had been of the

existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which

apart from this sub-paragraph would be payable to the undertaker in question by virtue of

sub-paragraph (1) is to be reduced by the amount of that excess.

For the purposes of sub-paragraph (3)—(3)

an extension of apparatus to a length greater than the length of existing apparatus must not (a)

be treated as a placing of apparatus of greater dimensions than those of the existing

apparatus; and

where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, (b)

the consequential provision of a jointing chamber or of a manhole must be treated as if it

also had been agreed or had been so determined.

An amount which apart from this sub-paragraph would be payable to an undertaker in respect (4)

of works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided

in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the

undertaker any financial benefit by deferment of the time for renewal of the apparatus in the

ordinary course, be reduced by the amount which represents that benefit.

Co-operation

Where in consequence of the proposed construction of any of the authorised development, the 9.

promoter requires the removal of apparatus under sub-paragraph 5(2)) or an undertaker makes

requirements for the protection or alteration of apparatus under paragraph 6(2), the promoter must

use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and

the efficient and economic execution of the authorised development; and each undertaker must use

its reasonable endeavours to co-operate with the promoter for that purpose.

Arbitration

Any difference or dispute arising between the promoter and an undertaker under this Schedule 10.

is, unless otherwise agreed in writing between the promoter and that undertaker, to be determined

by arbitration in accordance with article 51 (arbitration).

PART 2

FOR THE PROTECTION OF OPERATORS OF ELECTRONIC

COMMUNICATIONS CODE NETWORKS

Effect

For the protection of any operator, the following provisions, unless otherwise agreed in writing 1.

between the promoter (as defined in Part 1 of this Schedule) and the operator, have effect.

147

Page 236: Explanatory Memorandum (Rev D)

Interpretation

In this part of this Schedule—2.

“the 2003 Act” means the Communications Act 2003(rr);

“conduit system” has the same meaning as in the electronic communications code and

references to providing a conduit system is to be construed in accordance with paragraph 1(3A)

of that code;

“electronic communications apparatus” has the same meaning as in the electronic

communications code;

“the electronic communications code” has the same meaning as in Chapter 1 of Part 2 of the 2003

Act(ss);

“electronic communications code network” means—

(a) so much of an electronic communications network or conduit system provided by an

electronic communications code operator as is not excluded from the application of the

electronic communications code by a direction under section 106 of the 2003 Act; and

(b) an electronic communications network which the Secretary of State is providing or

proposing to provide;

“electronic communications code operator” means a person in whose case the electronic

communications code is applied by a direction under section 106 of the 2003 Act; and

“operator” means the operator of an electronic communications code network.

On-street apparatus

The exercise of the powers of article 34 (statutory undertakers) are subject to paragraph 23 3.

of Schedule 2 to the Telecommunication Act 1984(tt) as if the promoter were a “relevant

undertaker” for the purposes of that paragraph.

Enactments and agreements in respect of apparatus in the promoter’s land

Nothing in this Part of this Schedule affects the provisions of any enactment or agreement 4.

regulating the relations between the promoter and an undertaker in respect of any apparatus laid or

erected in land belonging to the promoter on the date on which this Order is made.

Arbitration

Any difference or dispute arising between the promoter and an operator under this Part of this 5.

Schedule is, unless otherwise agreed in writing between the promoter and that operator, to be

referred to and settled by arbitration under article 51 (arbitration).

(rr) 2003 c.21.

(ss) See section 106.

(tt) 1984 c.12.

148

Page 237: Explanatory Memorandum (Rev D)

SCHEDULE 12 Article 3

MISCELLANEOUS CONTROLS

PART 1

PUBLIC GENERAL LEGISLATION

Introduction

This Part 1 of this Schedule applies, modifies and excludes statutory provisions which relate to 1.

matters for which provision may be made in this Order.

—a) This Order—2.

fulfils the condition specified in section 28E(3)(a) of the 1981 Act (duties in relation to (a)

sites of special scientific interest); and

is a permission for the purposes of section 28I of the 1981 Act (statutory undertakers, etc: (b)

duty in relation to authorising operations),

in respect of an operation or operations referred to in sections 28E and 28I(2) of the 1981

Act which are carried out pursuant to this Order and, including the requirements in

Schedule 3 (requirements), subject to its provisions.

In this paragraph “the 1981 Act” means the Wildlife and Countryside Act 1981(uu).(1)

—a) To the extent provided in sub-paragraph (2) but subject to sub-paragraphs (3) and (4), the 3.

authorised development is to be treated as a major accident hazard pipeline as if carbon dioxide

were a dangerous fluid under Part III (Major Accident Hazard Pipelines) of the Regulations.

The following Regulations and Schedules of the Regulations apply to the authorised (1)

development—

Regulation 20 (Notification before construction);(a)

Regulation 21 (Notification before use);(b)

Regulation 22 (Notification in other cases);(c)

Regulation 23 (Major accident prevention document);(d)

Regulation 24 (Emergency procedures); (e)

Schedule 4 (Particulars to be Included in Notification Relating to Construction of a (f)

Major Accident Hazard Pipeline); and

Schedule 5 (Particulars to be Notified Before Certain Events Relating to Major Accident (g)

Hazard Pipelines).

The following Regulations and Schedule of the Regulations do not apply to the authorised (2)

development—

Regulation 19 (Emergency shut-down valves);(a)

Regulation 25 (Emergency plans in case of major accidents);(b)

Regulation 26 (Charge by a local authority for a plan); and(c)

Regulation 27 (Transitional provision);(d)

Schedule 3 (Requirements for Emergency Shut-down Valves on Certain Major Accident (e)

Hazard Pipelines Connected to Offshore Installations).

(uu) 1981 c.69.

149

Page 238: Explanatory Memorandum (Rev D)

The following sections and schedule of the Health and Safety at Work etc. Act 1974 do not (3)

apply to any breach of Part III (Major Accident Hazard Pipelines) of the Regulations by the

undertaker as a result of the application of Part III (Major Accident Hazard Pipelines) of the

Regulations by this paragraph—

Sections 18 (Authorities responsible for enforcement of the relevant statutory provisions) (a)

to 28 (Restrictions on disclosure of information) (inclusive);

Sections 33 (Offences) to 42 (Power of court to order cause of offence to be remedied or, (b)

in certain cases, forfeiture) (inclusive); and

Schedule 3A (Offences: Mode of Trial and Maximum Penalty).(c)

In this paragraph “the Regulations” mean the Pipeline Safety Regulations 1996(vv) and, (4)

subject to the provisions of this paragraph, “major accident hazard pipeline” and “dangerous fluid”

have the same meanings as those given in the Regulations.

PART 2

LOCAL LEGISLATION

Table of byelaws

Row Year Short Title

(1) 1980 Yorkshire Land Drainage Byelaws

(2) 1999 Selby Area Internal Drainage Board Byelaws

(3) 2013 Ouse and Humber Drainage Board Byelaws

(4) 2014 Beverley and North Holderness Internal Drainage Board Byelaws

Applications and modifications

The Byelaws specified in rows (1) to (4) of the Table of byelaws shall have effect in 1.

accordance with and subject to the provisions below (and, subject to those provisions, are also

subject to the provisions of article 3 (Application, modification and disapplication of legislative

provisions)).

In so far as it applies or would apply in relation to anything done for the purposes of this 2.

Order, for Byelaw 4 (Control of Sluices etc.) of the Selby Area Internal Drainage Board Byelaws,

Ouse and Humber Drainage Board Byelaws and Beverley and North Holderness Internal Drainage

Board Byelaws there shall be substituted—

“A person shall use and maintain any sluice, water control structure or appliance for

introducing water into any watercourse in the District or for controlling or regulating or

affecting the flow of water in, into or out of any watercourse in accordance with a scheme for

the mitigation of flood risk arising from such use and maintenance submitted by that person

to the Board and approved by it; and if that person causes any damage to the watercourse by

such use and maintenance that person shall make good such damage to the reasonable

satisfaction of the Board.”

In so far as it applies or would apply in relation to anything done for the purposes of this 3.

Order, for Byelaw 7 (Detrimental Substances not to be Put into Watercourses) of the Selby Area

Internal Drainage Board Byelaws, Ouse and Humber Drainage Board Byelaws and Beverley and

North Holderness Internal Drainage Board Byelaws there shall be substituted—

“No person shall, so as directly or indirectly to obstruct, impede or interfere with the flow

of water in, into or out of any watercourse or so as to damage the bank—

(vv) S.I. 1996/825.

150

Page 239: Explanatory Memorandum (Rev D)

(a) discharge or put or cause or permit to be discharged or put or negligently or wilfully

cause or permit to fall into any watercourse any object or matter of any kind whatsoever

whether solid or liquid;

(b) allow any such object or matter as is referred to in sub-paragraph (a) of this Byelaw to

remain in proximity to any watercourse in such manner as to render the same liable to drift or

fall or be carried into any watercourse,

without the consent of the Board to which the Board may attach reasonable conditions.

Provided that nothing in this Byelaw shall be deemed to render unlawful the growing or

harvesting of crops in accordance with normal agricultural practice.”

In so far as it applies or would apply in relation to anything done for the purposes of this 4.

Order, for Byelaw 14 (Vehicles not to be Driven on Banks) of the Selby Area Internal Drainage

Board Byelaws, Ouse and Humber Drainage Board Byelaws and Beverley and North Holderness

Internal Drainage Board Byelaws there shall be substituted—

“No person shall use or drive or permit or cause to be used or driven any cart, vehicle or

implement of any kind whatsoever on, over or along any bank of a watercourse in such

manner as to cause damage to such bank without the consent of the Board and, if such

damage is caused by a person in such a manner, that person shall at their own cost make

good such damage to the reasonable satisfaction of the Board.”

In so far as it applies or would apply in relation to anything done for the purposes of this 5.

Order, for Byelaw 15 (Banks not to be Used for Storage) of the Selby Area Internal Drainage

Board Byelaws, Ouse and Humber Drainage Board Byelaws and Beverley and North Holderness

Internal Drainage Board Byelaws there shall be substituted—

“No person shall use or cause or permit to be used any bank of any watercourse for the

purpose of depositing or stacking or storing or keeping any rubbish or goods or any material

or things thereon in such a manner as by reason of the weight, volume or nature of such

rubbish, goods, material or things causes or is likely to cause damage to or endanger the

stability of the bank or channel of the watercourse or interfere with the operations or access

of the Board or the right of the Board to deposit spoil on the bank of the watercourse without

the consent of the Board and, if such damage is caused by a person in such a manner, that

person shall at their own cost make good such damage to the reasonable satisfaction of the

Board.”

In so far as it applies or would apply in relation to anything done for the purposes of this 6.

Order, for Byelaw 23 (Damage to Property of the Board) of the Selby Area Internal Drainage

Board Byelaws and Byelaw 24 (Damage to Property of the Board) of the Ouse and Humber

Drainage Board Byelaws and Beverley and North Holderness Internal Drainage Board Byelaws

there shall be substituted—

“If a person interferes with or damages any bank, bridge, building, structure, appliance or

other property of or under the control of the Board that person shall at their own cost make

good any damage they have caused to the reasonable satisfaction of the Board.”

In so far as it applies or would apply in relation to anything done for the purposes of this 7.

Order, for Byelaw 24 (Defacement of Notice Boards) of the Selby Area Internal Drainage Board

Byelaws and Byelaw 25 (Defacement of Notice Boards) of the Ouse and Humber Drainage Board

Byelaws and Beverley and North Holderness Internal Drainage Board Byelaws there shall be

substituted—

“If a person defaces or removes any notice board, notice or placard put up by the Board

that person shall at their own cost replace it to the reasonable satisfaction of the Board.

Any other provision in the Byelaws specified in rows (1) to (4) of the Table of byelaws 8.

prohibiting, restricting or controlling any action continues to apply in relation to anything done for

151

Page 240: Explanatory Memorandum (Rev D)

the purposes of this Order, except where the Authority or Internal Drainage Board that makes the

Byelaws consents to the action.

Byelaws 5, 6, 10 and 15 of the Byelaws specified in row (1) of the Table of byelaws have 9.

effect subject to article 3(2) (application, modification and disapplication of legislative

provisions).

152

Page 241: Explanatory Memorandum (Rev D)

SCHEDULE 13 Article 24

MODIFICATION OF COMPENSATION AND COMPULSORY

PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

Compensation enactments

The enactments for the time being in force with respect to compensation for the compulsory 1.

purchase of land apply, with the necessary modifications as respects compensation, in the case of a

compulsory acquisition under this Order of a right by the creation of a new right as they apply as

respects compensation on the compulsory purchase of land and interests in land.

—a) Without prejudice to the generality of paragraph 1, the Land Compensation Act 1973(ww) 2.

has effect subject to the modifications set out in sub-paragraphs (2) and (3).

In section 44(1) (compensation for injurious affection), as it applies to compensation for (1)

injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—

for the words “land is acquired or taken” there are substituted the words “a right or (a)

restrictive covenant over land is purchased from or imposed on”; and

for the words “acquired or taken from him” there are substituted the words “over which the (b)

right is exercisable or the restrictive covenant enforceable”.

In section 58(1) (determination of material detriment where part of house etc. proposed for (2)

compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as

substituted by paragraph 5—

for the word “part” in paragraphs (a) and (b) there are substituted the words “a right over (a)

or restrictive covenant affecting land consisting”;

for the word “severance” there is substituted the words “right or restrictive covenant over (b)

or affecting the whole of the house, building or manufactory or of the house and the park or

garden”;

for the words “part proposed” there are substituted the words “right or restrictive covenant (c)

proposed”; and

for the words “part is” there are substituted the words “right or restrictive covenant is”.(d)

Application of the 1965 Act

—a) The 1965 Act has effect with the modifications necessary to make it apply to the 3.

compulsory acquisition under this Order of a right by the creation of a new right, or to the

imposition under this Order of a restrictive covenant, as it applies to the compulsory acquisition

under this Order of land, so that, in appropriate contexts, references in that Act to land are read

(according to the requirements of the particular context) as referring to, or as including references

to—

the right acquired or to be acquired; or(a)

the land over which the right is or is to be exercisable.(b)

Without prejudice to the generality of sub-paragraph (1), Part 1 of the 1965 Act applies in (1)

relation to the compulsory acquisition under this Order of a right by the creation of a new right with

the modifications specified in the following provisions of this Schedule.

For section 7 of the 1965 Act (measure of compensation) there is substituted the following 4.

section—

“7. In assessing the compensation to be paid by the acquiring authority under this Act,

regard must be had not only to the extent (if any) to which the value of the land over which

the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the

(ww) 1973 c. 26.

153

Page 242: Explanatory Memorandum (Rev D)

acquisition of the right or the imposition of the covenant but also to the damage (if any) to be

sustained by the owner of the land by reason of its severance from other land of the owner, or

injuriously affecting that other land by the exercise of the powers conferred by this or the

special Act.”.

The following provisions of the 1965 Act (which state the effect of a deed poll executed in 5.

various circumstances where there is no conveyance by persons with interests in the land), that is to

say—

section 9(4) (failure by owners to convey);(a)

paragraph 10(3) of Schedule 1 (owners under incapacity);(b)

paragraph 2(3) of Schedule 2 (absent and untraced owners); and(c)

paragraphs 2(3) and 7(2) of Schedule 4 (common land),(d)

are modified to secure that, as against persons with interests in the land which are expressed to be

overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant

which is to be imposed is vested absolutely in the acquiring authority.

Section 11 of the 1965 Act (powers of entry) is modified to secure that, as from the date on 6.

which the acquiring authority has served notice to treat in respect of any right, it has power,

exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the

purpose of exercising that right or enforcing that restrictive covenant (which is deemed for this

purpose to have been created on the date of service of the notice); and sections 12 (penalty for

unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act are

modified correspondingly.

Section 20 of the 1965 Act (protection for interests of tenants at will, etc.) applies with the 7.

modifications necessary to secure that persons with such interests in land as are mentioned in that

section are compensated in a manner corresponding to that in which they would be compensated on

a compulsory acquisition under this Order of that land, but taking into account only the extent (if

any) of such interference with such an interest as is actually caused, or likely to be caused, by the

exercise of the right or the enforcement of the restrictive covenant in question.

Section 22 of the 1965 Act (protection of acquiring authority’s possession where by 8.

inadvertence an estate, right or interest has not been got in) is modified as to enable the acquiring

authority, in circumstances corresponding to those referred to in that section, to continue to be

entitled to exercise the right acquired, subject to compliance with that section as respects

compensation.

154

Page 243: Explanatory Memorandum (Rev D)

SCHEDULE 14 Article 53

PROCEDURE IN RELATION TO CERTAIN APPROVALS ETC.

Determination of applications for specified consents

—a) Where an application has been made to the discharging authority for any specified 1.

consent, the discharging authority must give notice to the undertaker of its decision on the

application within a period of 8 weeks (or in respect of a COPA application or byelaw application

28 days) beginning with—

where no further information is requested under sub-paragraph (2), the day immediately (a)

following that on which the application is received by the discharging authority;

where further information is requested under sub-paragraph (2), the day immediately (b)

following that on which further information has been supplied by the undertaker; or

such longer period as may be agreed in writing by the undertaker and the discharging (c)

authority.

Where an application has been made under sub-paragraph (1) the discharging authority may (2)

request such reasonable further information from the undertaker as it considers is necessary to

enable it to consider the application.

If the discharging authority considers further information is necessary and this Order does not (3)

specify that consultation with a consultee is required, the discharging authority must, within 10

business days of receipt of the application, notify the undertaker in writing specifying the further

information required.

If a provision of this Order relating to a specified consent specifies that consultation with a (4)

consultee is required the discharging authority must—

issue the consultation to the consultee within 2 business days of receipt of the application;(a)

notify the undertaker in writing specifying any further information requested by the (b)

consultee within 2 business days of receipt of such a request; and

in any event, within 21 business days of receipt of the application, specify to the undertaker (c)

in writing any further information required.

If the discharging authority does not give the notification mentioned in sub-paragraph (3) or (5)

(4) it is deemed to have sufficient information to consider the application and is not thereafter

entitled to request further information without the prior agreement of the undertaker.

Fees

—a) Where an application is made to a relevant planning authority for any consent, agreement 2.

or approval required by a requirement listed in Schedule 3 (requirements) to this Order, a fee of

£97 (or such other fee as may be prescribed in regulations made pursuant to sections 303 (fees for

planning applications etc.) and 333(2A) (regulations and orders) of the 1990 Act for the

confirmation by a local planning authority of compliance with a condition attached to a planning

permission) must be paid to the discharging authority.

Any fee paid under this Schedule must be refunded to the undertaker within 4 weeks of—(1)

the application being rejected as invalidly made; or(a)

the discharging authority failing to determine the application within 8 weeks from the date (b)

on which it is received,

unless within that period the undertaker agrees in writing that the fee may be retained by the

discharging authority and credited in respect of a future application.

Appeals

—a) The undertaker may appeal if—3.

155

Page 244: Explanatory Memorandum (Rev D)

the discharging authority refuses an application for any specified consent or grants it (a)

subject to conditions (or in respect of a COPA application limits or qualifies it in any way);

the discharging authority does not give notice of its decision to the undertaker within the (b)

period specified in paragraph 1(1);

having received a request for further information under sub-paragraph 1(2) the undertaker (c)

considers that either the whole or part of the specified information requested by the

discharging authority is not necessary for consideration of the application;

having received any further information requested, the discharging authority notifies the (d)

undertaker that the information provided is inadequate and requests additional information

which the undertaker considers is not necessary for consideration of the application;

the discharging authority serves a COPA notice; or(e)

the discharging authority by or under a specified byelaw requires the undertaker to carry (f)

out any activity (to its satisfaction or otherwise) or to comply with any direction (referred

to in this Schedule as a “byelaw requirement”); and the undertaker may not be required to

comply with the byelaw requirement until the appointed person has decided the appeal or

any claim for judicial review in respect of the appeal has been finally determined.

The procedure for appeals is as follows—(1)

the undertaker must submit to the Secretary of State—(a)

a copy of the application submitted to the discharging authority;(i)

in respect of an appeal of a byelaw requirement such details of the relevant (ii)

requirement as have been provided to the undertaker by the discharging authority; or

where a COPA notice has been served a copy of that notice,(iii)

and any supporting documents which the undertaker may wish to provide (referred to in

this Schedule as “the appeal documents”);

the undertaker must on the same day provide copies of the appeal documents to the (b)

discharging authority and (if applicable) the consultee;

as soon as is practicable after receiving the appeals documents the Secretary of State must (c)

appoint a person to determine the appeal (referred to in this Schedule as “the appointed

person”) and notify the appeal parties of the identity of the appointed person and the

address to which all correspondence for the appointed person should be sent;

the discharging authority and (if applicable) the consultee may submit any written (d)

representations in respect of the appeal to the appointed person within 10 business days

beginning with the first day immediately following the date on which the appeal parties are

notified of the appointment of the appointed person and must ensure that copies of their

written representations are sent to each other and to the undertaker on the day on which

they are submitted to the appointed person;

the appeal parties may make any counter-submissions to the appointed person within 10 (e)

business days beginning with the first day immediately following the date of receipt of

written representations pursuant to paragraph (d) above; and

the appointed person must make a decision and notify it to the appeal parties, with reasons, (f)

as soon as reasonably practicable.

If the appointed person considers that further information is necessary to consider the appeal, (2)

the appointed person must as soon as practicable notify the appeal parties in writing specifying the

further information required, the appeal party from whom the information is sought, and the date by

which the information must be submitted.

Any further information required pursuant to sub-paragraph (3) must be provided by the party (3)

from whom the information is sought to the appointed person and to other appeal parties by the date

specified by the appointed person.

The appeal parties may submit written representations to the appointed person concerning (4)

matters contained in the further information.

156

Page 245: Explanatory Memorandum (Rev D)

Any such representations must be submitted to the appointed person and made available to all (5)

appeal parties within 10 business days of the date mentioned in sub-paragraph (3).

Outcome of appeals

—a) On an appeal under paragraph 3, the appointed person may—4.

allow or dismiss the appeal; (a)

reverse or vary any part of the decision of the discharging authority (whether the appeal (b)

relates to that part of it or not); or

determine that the undertaker should or should not comply with a byelaw requirement,(c)

and may deal with the application as if it had been made to the appointed person in the first instance

(which may include applying conditions to any approval or byelaw requirement).

The appointed person may proceed to a decision on an appeal taking into account only such (1)

written representations as have been sent within the time limits prescribed or set by the appointed

person under this paragraph.

The appointed person may proceed to a decision even though no written representations have (2)

been made within those time limits if it appears to the appointed person that there is sufficient

material to enable a decision to be made on the merits of the case.

The decision of the appointed person on an appeal is final and binding on the parties, and a (3)

court may entertain proceedings for questioning the decision only if the proceedings are brought by

a claim for judicial review within 6 weeks of the date of the decision.

Any approval given by the appointed person pursuant to this Schedule is deemed to be an (4)

approval for the purposes of this Order and any other enactment which required the specified

consent as if it had been given by the discharging authority.

The discharging authority may confirm any determination given by the appointed person in (5)

identical form in writing but a failure to give such confirmation (or a failure to give it in identical

form) does not affect or invalidate the effect of the appointed person’s determination.

Except where a direction is given pursuant to sub-paragraph 8 requiring the costs of the (6)

appointed person to be paid by the discharging authority, the reasonable costs of the appointed

person must be met by the undertaker.

On application by the discharging authority or the undertaker, the appointed person may give (7)

directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal

are to be paid.

In considering whether to make any such direction and the terms on which it is made, the (8)

appointed person must have regard to Communities and Local Government Circular 03/2009 or any

circular or guidance which may from time to time replace it.

Application of this Schedule

Where the undertaker appeals under paragraph 3—5.

this Schedule applies instead of article 51 (arbitration); (a)

in respect of any specified consent required pursuant to sections 54 to 106 of the 1991 Act, (b)

this Schedule applies instead of section 99 (arbitration) of that Act;

in respect of any COPA notice or COPA application this Schedule applies instead of (c)

sections 60(7) or 61(7) of the 1974 Act; and

in respect of any specified consent required pursuant to a specified byelaw this Schedule (d)

applies instead of—

byelaw 28 (arbitration) of the Selby Area Internal Drainage Board Byelaws 1999;(i)

byelaw 29 (arbitration) of the Beverley and North Holderness Internal Drainage (ii)

Board Byelaws 2014;

byelaw 29 (arbitration) of the Ouse and Humber Internal Drainage Board Land (iii)

Drainage Byelaws 2013; or

157

Page 246: Explanatory Memorandum (Rev D)

any provision of byelaws made by the East Riding of Yorkshire Council in its (iv)

capacity as lead local flood authority which relates to arbitration (or any other form of

dispute resolution) or appeals,

as applicable.

Interpretation of this Schedule

In this Schedule—6.

“1974 Act” means the Control of Pollution Act 1974(xx);

“the appeal parties” means the discharging authority, the consultee (if applicable) and the

undertaker;

“business day” means Monday to Friday excluding bank holidays;

“byelaw application” means an application made pursuant to a specified byelaw;

“byelaw requirement” has the meaning given in paragraph 3(1)(f);

“consultee” means any body named in a provision of this Order relating to a specified consent

which is the subject of an appeal as a body to be consulted by the discharging authority in

determining that specified consent;

“COPA application” means an application made pursuant to section 61 of the 1974 Act (prior

consent for work on construction sites);

“COPA notice” means a notice served pursuant to section 60 of the 1974 Act (control of noise

on construction sites);

“discharging authority” means the body responsible for determining whether a specified consent

should be given or the local authority in the exercise of functions set out in sections 60 or 61 of

the 1974 Act;

“specified byelaw” means any byelaw in—

the Selby Area Internal Drainage Board Byelaws 1999;(a)

the Ouse and Humber Internal Drainage Board Land Drainage Byelaws 2013; (b)

the Beverley and North Holderness Internal Drainage Board Byelaws 2014; and/or(c)

any byelaws made by the East Riding of Yorkshire Council in its capacity as lead local (d)

flood authority;

“specified consent” means any—

agreement, certificate, consent, permission, expression of satisfaction or other approval (a)

required by—

a requirement listed in Schedule 3 (requirements) of this Order;(i)

a document referred to in any requirement listed in Schedule 3 of this Order; (ii)

a term of the deemed marine licence listed in Schedule 10 (deemed marine licence) (iii)

under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009);

article 44(3)(b) (felling or lopping of trees or shrubs); (iv)

a specified byelaw; or(v)

agreement, certificate, consent, permission, expression of satisfaction or other approval of (b)

the highway authority, street authority (where it is also the highway authority for the same

area) or traffic authority required pursuant to articles—

10 (street works) (including pursuant to sections 54 to 106 of the 1991 Act as (i)

applied by article 10(3));

11 (power to alter layout, etc. of streets);(ii)

12 (construction and maintenance of new, altered or diverted streets);(iii)

15 Public 14 (temporary stopping up of streets and public rights of way);(iv)

(xx) 1974 c.40.

158

Page 247: Explanatory Memorandum (Rev D)

13 (permanent stopping up of streets);(v)

17 (traffic regulation); or(vi)

21 (authority to survey and investigate the land); or(vii)

a consent pursuant to a COPA application.(c)

159

Page 248: Explanatory Memorandum (Rev D)

EXPLANATORY NOTE

(This note is not part of the Order)

The Order

This Order authorises National Grid Carbon Limited (referred to as “the undertaker”) to construct

and operate a pipeline transportation network and associated infrastructure to support the provision

of carbon capture and storage technology in the Yorkshire and Humber region.

The Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in

land and to use land for this purpose. The Order also makes provision in connection with the

maintenance of the network.

A copy of the Order plans and the book of reference mentioned in this Order and certified in

accordance with article 49 of this Order (certification of plans, etc.) may be inspected free of

charge during working hours at the [Planning Reception Desk], of East Riding of Yorkshire Council

[insert address] and Selby District Council [insert address].

160

Page 249: Explanatory Memorandum (Rev D)

http://www.lexisnexis.com/uk/legal/delivery/PrintDoc.do?jobHandle=2826%3A2917... 20/06/2011

161

Supplemental Powers

S T A T U T O R Y I N S T R U M E N T S

201[●] No. [●]

INFRASTRUCTURE PLANNING

ENERGY

The [Draft] Yorkshire and Humber (Carbon Capture and

Storage Cross Country Pipeline) Order 201[●]

BERWIN LEIGHTON PAISNER LLP

Adelaide House

London Bridge

London EC4R 9HA

Solicitors

Page 250: Explanatory Memorandum (Rev D)

Document comparison by Workshare Compare on 04 March 2015 16:10:29

Input:

Document 1 ID interwovenSite://VRT-DMS-01/Legal/35920325/1

Description #35920325v1<Legal> - Model provisions for railways

Document 2 ID interwovenSite://VRT-DMS-01/Legal/33733591/34

Description#33733591v34<Legal> - Humber CCS Draft DevelopmentConsent Order (DCO) (March 2014)

Rendering set no change numbers no summary

Legend:

Insertion

Deletion

Moved from

Moved to

Style change

Format change

Moved deletion

Inserted cell

Deleted cell

Moved cell

Split/Merged cell

Padding cell

Statistics:

Count

Insertions 5219

Deletions 994

Moved from 0

Moved to 0

Style change 0

Format changed 142

Total changes 6355


Recommended