Chernobyl Safe Containment ArchEstablished as a response to the deteriorating sarcophagus hastily built to contain the aftermath of the world‘s worst nuclear accident, the Safe Containment Arch is the result of a collaboration of two global construction giants backed by 27 nations.
Our contribution to the construction of the world‘s largest movable land-based structure, covering the remains of reactor 4, is a complete seismically tolerant HVAC package for the main arch and associated support facilities.
Hargreaves‘ work in the project included the design review, engineering documentation, factory acceptance testing and supply of the Chernobyl New Safe Confinement (NSC) Arch Main Volume, Arch Annular Space, MCS
maintenance garage, TEC, FSAL and EEB Ventilation Systems and Air Conditioning Systems, including all related necessary documentation and accessories for this purpose. This also includes
design and manufacture of Seismically qualified steel supports.
The Manufacture of the Arch Main Volume, Arch Annular Space, MCS maintenance
Nuclear Energy
Exyte HargreavesC
ASE
STU
DY
exyte-hargreaves.net
PROJECT DETAILSProject Name: Chernobyl
Location: Ukraine
Value: £9.9 million
Date: 2016
a complete seismically tolerant HVAC package for the main arch and associated support facilities
03/2
019
exyte-hargreaves.net03/2
019
garage, TEC, FSAL and EEB Ventilation Systems and Air Conditioning Systems and Related Services, including all related necessary
documentation and accessories.
Procurement and final design of all plant and equipment including air handling units, fans, etc.
Exyte Hargreaves LimitedLord Street, BuryLancashire BL9 0RGT: +44(0) 161 764 5082E: [email protected]