of 50
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
1/50
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
2/50
GENERAL
1. The test to be carried out in the presence of Owner's supervisor and Classification’s (NK)
surveyor, if necessary.
2. The test time to be notified to the Owners, Classification (NK) and Builder ’s relative sections by
the section, which conducts the test.
3. The test records to be prepared and offered to the Owner and Classification (NK) by design
section.
Witness
No. Test ItemOwner
Classification
(NK)
Page
1 Cargo Gear Handling System %Ë %Ë P.2 ~ P.4
2 Lifeboat Lowering & Lifting %Ë %Ë P.5 ~ P.9
3 Air-conditioning System
(Include Mechanical Vent. System)%Ë P.10 ~ P.18
4 Refrigerating Provision Plant %Ë P.19 ~ P.23
5CO2 Fire
Extinguishing System%Ë %Ë P.24 ~ P.35
6 Life-raft Installation %Ë %Ë P.36
7 Fire Fighting Equipment %Ë %Ë P.37
8 2.6T spare Parts Handling Crane %Ë %Ë P.38 ~ P.39
9 Emergency Engine Generator Set %Ë %Ë P.40 ~ P.41
10Water ingress alarm
& Dewatering system%Ë %Ë P.42
11 Bilge suction system %Ë %Ë P.43
12 Noise measurement %Ë P. 44 ~ P.49
1
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
3/50
1. Test of cargo gear handling system
1.1. System outline
System type : IHI Hydraulic Deck Crane
Hoisting load : 30.5Tons
Working angle : 20°
Max. Slewing radius : 24m
Min. Slewing radius : 3.5m
1.2. Test load and boom elevation angle
Test load : 35.5tons
Elevation angle : 20°
The weight of test load to be checked in the presence of Classification's (NK) surveyor, Owner's
supervisor and Inspection section's member.
1.3. Test
The following test to be carried out and to be checked whether each component of the deck
crane move normally.
(A) Crane & Jib strength test
Over load test : Rated load (30.5 Tons) + 5 tons = 35.5 tons
Slewing angle : 360° endless
Slewing zone : Refer to the following figure
; Brake test, lowering test to be carried out.
2
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
4/50
(B) Limit Switch Operation Test
To be ascertained whether the following switches will act surely.
1) Hoisting limit : Upper and lower limit of hoisting motion.
2) Luffing limit : Max. and min. Jib angle & jib lower position.
3) Differential limit : Distance limit between hook unit and jib top
4) Rope slack detector : For hoisting wire rope only
5) Starter interlock : Handle neutral position at starting
6) Emergency stop : All motion are stopped in case of emergency.
SLEWING ZONE
3
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
5/50
1.4. Test record of cargo gear handling system
1. Date and place
Date : 5th Oct. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. Ohki
Owner's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
Number of deck crane No.1 No.2 No.3 No.4
Type of deck crane 24M (R)
Test load (jib angle)35.5T
(20° )
Hoisting limit (upper / lower) GOOD GOOD GOOD GOOD
Luffing limit (lower position) GOOD GOOD GOOD GOOD
Luffing limit (max / min) GOOD GOOD GOOD GOOD
Differential limit GOOD GOOD GOOD GOOD
Rope slack detector GOOD GOOD GOOD GOOD
Starter interlock GOOD GOOD GOOD GOOD
S a f e t y d e v i c e
Emergency stop GOOD GOOD GOOD GOOD
Brake test GOOD GOOD GOOD GOOD
4
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
6/50
2. Test of lifeboat lowering & lifting
2.1. Principal particulars of lifeboat
No.1 No.2
Life/rescue boat. Lifeboat only
Length (mm) 5,300 5,300
Breadth (mm) 2,300 2,300
Depth (mm) 1,000 1,000
Complement (Lifeboat condition) 25 P 25 P
Complement (Rescue boat condition) 6 P -
Stowage S. side P. side
Weight of boat 1,800 1,800
Wb (kgs)
Weight of SLING, ROPE & etc. 150 150
Ws (kgs)
Weight of Equipment 235 235
We (kgs)
Weight of person : Lifeboat condition 1,875 1,875
(75kg/person × 25p)
Weight of person : Rescue boat condition (450) -
(75kg/person × 6p)
Total weight : Wb+We+Weight of person 3,910 3,910
( Rescue boat condition) (2,485)
5
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
7/50
2.2. Test load and condition
The weight used for the test to be checked accurately and provided in accordance with the following
table in the presence of Classification's (NK) surveyor, Owner's supervisor and Inspection Section's
member.
The test to be carried out to apply same load on the lifeboats of both sides which will] be loaded on
the lifeboat.
(A) Swing out test & Brake test
Weight condition Test Load
4,466 kgs
Actual load
2,281 kgs
Test load = 1.1× ( Wb + We + Ws + 75Kg × 25p)
Actual load = Test load - (Wb+We+Ws)
(B) Lowering test
Case1
(Lifeboat lowering)
Test Load
4,060 kgs
Actual load
1,875 kgs
Test load = Wb + We + Ws + 75Kg × 25p
Actual load = Test load - (Wb+We+Ws)
Case2
(Rescue boat lowering)
Test Load
2,635 kgs
Actual load
450 kgsTest load = Wb + We + Ws + 75Kg × 6p
Actual load = Test load - (Wb + Ws)
Case3
(Lifeboat lowering)
Test Load
2,185 kgs
Actual load
0 kgs
Test load = Wb + We + Ws
(C) Lifting test
Only P. side Test Load
2,335 kgs
Actual load
150 kgs
Test load = Wb + We + Ws + 75Kg × 2p
Actual load = Test load - (Wb+We+Ws)
Only S. side
; Rescue boat condition
Test Load
2,635 kgs
Actual load
450 kgs
Test load = Wb + We + Ws + 75Kg × 6p
Actual load = Test load - (Wb+We+Ws)
6
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
8/50
2.3. Test and observation
The test to be carried as follows
(A) Swing out test & Brake test
Lifeboat to be swing out from stowing position and outreach to be measured.
Lifeboat to be lowered by loosing the brake.
During the lowering, the brake action by counter weight to be inspected.
(B) Lowering test
At loaded Case1, Case2 & Case3 condition, lowering speed to be measured.
Required lowering speed (m/s) S = 0.4 + 0.02 × H = 0.678 m/s
Where H = height in meters from davit head to the waterline at the lightest seagoing condition :
13.90rn (at Ballast condition)
Not more than 1. 3m/s (SOLAS required) 0.678 m/s < S "f 1.3 m/s
At loaded Case3, the rescue boat to be lowered, and lowering speed to be measured.
At this case required lowering speed (m/s)
S1 "g 0.7 × ( 0.4 + 0.02 × H ) = 0.475 m/s
(C) Lifting test
The lifeboat to be lifted and stowed / installed in the position by boat winch.
During this test, hoisting speed and recovery time of rescue boat to be measured.
Automatic cut-off appliance (limit switch) and manual handling of hoisting winch to be confirmed.
(D) Provision for hanging-off the rescue boat test
Confirm the installation of the hanging-off equipment.
(E) Release gear test
Confirm the release and the restoration of the release gear.
(F) Engine operation test
Confirm the engine starting and the clutch operation for forward, astern and neutral.
(G) Rescue boat launching at 5 knots test
Confirm that possible to be launching at 5 knots.
Required hoisting speed : Not less than 0.3 m/s on rescue boat condition
7
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
9/50
2.4. Test record of lifeboat / rescue boat lowering
1. Date and place
Date : 7 th Oct. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. Ohki
Owner ‘s representative : Mr. Matsumoto / Mr. Hoshi
Shipyard’s staff : Inspect. Sect. Tanaka
3. Measurement equipment
ITEM MANAGEMENT No.
Measurement tape DI - 72
Sounding tape DI - 43
Stop watch DI - 19
4. Condition of the Vessel
Draft (M) Fore 4.067 M Midship 5.275 M Aft. 6.593 M
Trim (M) 2.526 M
Heel (M) 0 M
5. Ability of lifeboat davit
A) Swing out test No.1 (Rescue boat) No.2 (Lifeboat)
Starting ability GOOD GOOD
Starting by hand brake GOOD GOOD
Outreach 760 mm 800 mm
Brake test GOOD GOOD
B) Lowering test
Case1 condition 1.00 m/sec. 0.91 m/sec.
Case2 condition 0.84 m/sec.
Case3 condition 0.59 m/sec. 0.67 m/sec.
C) Lifting test
Lifting ability of Lifeboat GOOD GOOD
Lifting speed of Rescue boat 0.41 m/sec.
Recovery time of Rescue boat 80 sec.
Automatic cut-off appliance GOOD GOOD
Manual handing of winch GOOD GOOD
D) Provision for hanging-off
the rescue boat testGOOD
E) Release gear test GOOD GOOD
F) Engine operation test GOOD GOOD
8
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
10/50
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
11/50
10
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
12/50
: October 23, 2009
: Inspect. Sect. Tanaka
: Mr. Maeda
11
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
13/50
12
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
14/50
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
13
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
15/50
〃
〃
〃
〃
〃
〃
〃
〃
〃
〃
14
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
16/50
〃
〃
〃
〃
〃
〃
〃
15
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
17/50
〃
〃
〃
〃
〃
16
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
18/50
Current
IN (℃)
OUT(℃)
17
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
19/50
Current
IN (℃)
OUT(℃)
18
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
20/50
19
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
21/50
The regulation for a ゛NK"
・Water leak shall be checked passing high pressured water through cooling water piping system
・Leak check shall be carried out to inject N2 gas in the cooling medium piping system.
・Gas leak test shall be carried out with a soap water, at 6 hours after adjusting gas pressure.
・Heat shielding shall be carried out at low pressure side of cooling medium system following
20
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
22/50
・Operation of dual press switch and oil press switch, with manually operated valves, shall
舶用食糧冷蔵庫冷却装置の配管保冷工事施工標準
・Temperature of each chamber ・Temperature of atmosphere
0 ~ 30 minute 3 ~ 45 minute
3 ~ 15 minute
21
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
23/50
100 % 100 %
100 % 100 %
MEAT RM (-18℃)
FISH RM (-18℃)
40 %
70 % 30 % 40 %
+ 4 ℃
+ 1 ℃
100 %
70 % 30 %
100 %
22
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
24/50
D A T E
; O c t o
b e r
1 4
, 2 0 0 9
23
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
25/50
Messrs. Kanda Shipbuilding CO.,LTD.
On Board Test Method
CO2 Gas Fire Extinguishing System
Type : EAS-MSV
DAISHIN TECHNOS CO.,LTD.
Technical Department
TEL : 0898-23-2050 FAX : 0898-32-0659
On Board Test Method
24
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
26/50
CO2 Gas Fire Extinguishing System Type MSV
1. Date and place
Date : 9 Oct. 2009
Place : Alongside of Kanda’s wharf
2.Attendant
Class. (NK) surveyor : Mr. Ohki
Owner 's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
3. Test Items
(1) Pressure Test of Piping
(2) Air Blow Test of Piping
(3) Function Test of Actuating Line
(4) Function Test of Alarming
A. Pressure Test of Piping
A-a. Preparation of the test
1. Confirm that all the system, arrangement of CO2 cylinders and the piping, have
properly been installed.
A special attention should be given on the arrangement of Actuating line compose of
6mm-dia copper tube and the flow direction of non-return valves installed therein.
2. Disconnect the actuating line at the joint on the valve body of the non-return valves
which are fitted between guide pipes and CO2 manifold, as the Fig.1b shows.
3. Disconnect the actuating line connecting to the working cylinder of the selection valve
and plug-up its 2 connections by blind nuts.
4. Confirm surely that the whole of Selection valve and are closed and are closed andactuating lines disconnected and its connection blinded.
25
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
27/50
5. Take out all the gas discharge nozzles from pipe line and fit the blinds on the pipe end.
6. Remove the safety valve on the high pressure main line and connect the pressure gas
line there for the test, as Fig.1a shows. Install a pressure gauge, as well.
7. CO2 gas of a 30kg cylinder for general use or 7m3
N2 gas could be used as gas
pressure source for the test.
A-b. Pressure Test between Manifold pipe to Selection Valves.
1. Confirm the no-leakage in the above piping within 5 minutes under 3.43 Mpa gas
pressure.
2. After the test purge the gas, completely
A-c. Pressure Test between Selection valves and Gas Discharge nozzles.
1. Take out the safety delay lock of the manual operating valve in the selection valve box
for Each protected area and turn the valve handwheel to clockwise as full open.
2. Confirm that neither leak nor disorder in the above piping within 5 minutes under 0.98
Mpa gas pressure.
3. After the test, first, close the selection valve and then purge the gas completely from
the blinds on the pipe ends.
A-d. Restoration After Test
1. Take out all the blinds on the pipe ends and installed at the discharge nozzles.
Confirm that each discharge nozzles refitted at the correct position.
2. Install a delay safety lock in selection valve box.
3. Connect the actuating line at the J oint on the valve body of the non-return valves
which are fitted between guide pipes and CO2 manifold as the Fig.1b shows and
restore the system to normal condition.
26
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
28/50
B. Air Blow Test of Piping
B-a. Preparation of the test
1. Confirm that whole of the system is in original normal condition, except the actuating
copper pipe to selection valve and the valve body of the non-return valves as the
Fig.1b shows is remained unconnected.
B-b. Air Blow Test
The system for each protected area to be tested respectively.
Engine room
1. Take out the safety delay lock of the manual operating valve in the selection valve box
for Each protected area and turn the valve handwheel to clockwise as full open.
2. Supply the test air from the connection valve and confirm the free air flow from the
selection valve to the gas discharge nozzle in protected area.
3. After the test, stop the test air and then close the selection valve for protected area.
Cargo hold
1. Turn the selection valve handwheel to unclockwise as full open.
2. Supply the test air from the connection valve and confirm the free airflow from the
selection valve to the gas discharge nozzles in protected area.
3. After the test, stop the test air and then close the selection valve for protected area.
B-c. Restoration After Test
1. Install a delay safety lock in selection valve box.
2. Connect the actuating line at the joint on the non-return valves, as the Fig.1b shows
and restore the system to normal condition.
27
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
29/50
C. Function Test of Actuating Line
C-a. Preparation of the test
1. Confirm that whole of the system is in normal condition, expect the valve body of the
non-return valves as the Fig.1b shows is remained unconnected.
2. Confirm once more that the actuating line has properly been connected, as Fig.4
indicated.
3. Remove 2 cylinder valve releases on the starting cylinders remaining their actuating
copper pipes connected as Fig.2 indicated.
4. Remove one of the 2 working actuating cylinders in the actuator box and fit a small test
cylinder instead.
C-b. Actuating Test
Push down the starting lever of a test cylinder and confirm that valve releasers and
selection valve work appropriately.
C-c. Restoration After Test
1. Loosen the actuator line connection and purge the gas surely remained in the piping.
2. Remove the emptied small test cylinder and put back the working actuating cylinder.
3. Make the selection valve at its normal close position following the same process asnoted in paragraph A-d2.
4. Connect the actuator line at the non-return valves installed between guide pipes of the
starting cylinders and manifold pipe.
5. Put back the valve releasers into 2 Starting cylinder valves leaving actuating pipeline
unconnected.
6. Final connection of the above actuating line is recommended to be done Just before
28
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
30/50
ship’s delivery.
D. Function Test of Alarming
1. Confirm that when the door of actuator box or selection valve switch box is opened
warning for gas discharge starts and ventilating fan and F.O. pumps stop
automatically.
2. Close the door and put back all the system in normal condition.
E. Caution
1. When N2 gas is used as gas pressure souse never press the cylinder valve beyond
vaporize pressure of CO2 gas.
2. Due to the fact that the vaporize pressure of CO2 gas at 0! is as low as 3.43Mpa
special attention should be given in winter.
3. Foreign material in the piping such as dust, rubbish and welding slug could be cause of
trouble on the cylinder valve, selection valve. To avoid this, before the testing blow out
the piping carefully.
29
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
31/50
30
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
32/50
31
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
33/50
32
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
34/50
33
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
35/50
34
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
36/50
N o z z l e ( p c s )
35
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
37/50
6. Confirmation of life-raft installation
1. Date and place
Date : 21 Oct. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. Ohki
Owner 's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
3. Procedure
Confirms the installation condition of the life-raft by the watching.
4. Record
CONDITION
P. SIDE GOOD
S. SIDE GOOD
36
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
38/50
7. Test record of f ire fighting equipment
1. Date and place
Date : 22 Oct. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. OhkiOwner 's representative : Mr. Matsumoto / Me. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
3. Condition of the Vessel
Draft (M) df= M dm= M da= M
Trim (M) M
Height of emergency fire pump room flat : 9.5m above B.L.
4. Ability of f ire pump
No.1 Fire Pump ・・・・・ Fire & G.S. Pump 120M³/h × 0.64Mpa
No.2 Fire Pump ・・・・・ Fire & B.B. Pump 120M³/h × 0.64Mpa
No.3 Fire Pump ・・・・・ Emergency Fire Pump 72M³/h × 0.64Mpa
The minimum pressure (0.27 N/mm²) is to be maintained at all hydrants.
Required pump capacity is to be capable of delivering two jet of water which are reachable
not less than 12m in distance.
5. Jet water test of No.1 & No.2 fire pump
Pressure (MPa)
Pump Number Pump
Deli. SideNav. Dk F’cle Dk
Upp. Dk
(Fore)
Upp. Dk
(Aft.)
Range
No.1 Fire Pump 0.64 0.40 0.40 - -
No.2 Fire Pump 0.64 0.40 0.40 - -
6. Jet water test of No.3 fire pump (Emergency fire pump) to be carried out at Sea Trial using the
electric power by the Emergency generator.
6.1. Date and place
Date : 22 Oct. 2009
Place : Sea Trial
6.2. Attendant
Class. (NK) surveyor : Mr. Ohki
Owner 's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
Pressure (MPa)
Pump Number Pump
Deli. SideNav. Dk F’cle Dk
Upp. Dk
(Fore)
Upp. Dk
(Aft.)
Range
No.3 Fire Pump 0.80 0.58 0.44 - -
37
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
39/50
8. Test of 2.6T spare parts handling crane
8.1. Principal particulars
Hoisting load : 2.6 T
Hoisting speed : Abt. 0.17 m/sec. (at 2 layer)
Hoisting height : 25.0 m
Slewing radius : 4.4 m
Slewing speed : Abt. 0.5 rpm
Slewing angle : 165°
Hoisting motor : 6.0 kW × 4p
Slewing motor : 1.5 kW × 4p
Electric source : AC440V 60Hz
Maker : MANSEI INDUSTRY CO.,LTD.
8.2. Test procedure
The following tests to be applied.
1) Limit switch test
The effective operation of the following limit devices to be confirmed at no load condition.
(1) Hoisting limit
(2) Slewing limit
2) Over load test
Test load 3.25 TON (2.6 × 1.25)
3) Brake test
This test to be carried out under the test load condition.
8.3. Observation
Following items to be measured and confirmed on over load condition.
(1) Effective operation of brake.
(2) Effective operation of limit switch.
(3) During test, crane to be inspected for any injuries, deformations on other indications of
unsatisfied operations.
38
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
40/50
8.4. Test record
1. Date and place
Date : 10 Oct. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. Ohki
Owner 's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
3. Test data
(1) Brake test
Hoisting / Lowering ・・・・・ GOOD
Slewing (R) ・・・・・ GOOD
Slewing (L) ・・・・・ GOOD
(2) Safety device (limit switch)
Hoisting ・・・・・ GOOD
Slewing (R) ・・・・・ GOOD
Slewing (L) ・・・・・ GOOD
(3) Operation condition ・・・・・ GOOD
39
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
41/50
9. Test of emergency engine generator
9.1. Particulars of emergency engine generator
(1) Engine
Maker : MITSUI DEUTZ DIESEL ENGINE CO., LTD.
Type : BF6L913
Number of cylinder : 6
Cylinder bore : 102 mm
Piston stroke : 125 mm
Rated out put : 99 kW (135 PS)
Rated speed : 1800 rpm
(2) Generator
Maker : TAIYO ELECTRIC CO., LTD.
Model : ATW25C
Number of phase : 3
Out put : 100 kVA
Frequency : 60 Hz
Voltage : 450 V
40
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
42/50
9.2. Test record
1. Date and place
Date : 25 Sep. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. Miyamoto
Owner 's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
3. Load test
Following items shall be confirmed at suitable load of emergency generator engine after
it's engine start.
Load (%) 0 25 50 75 100
Current 0 25.7 51.3 77.0 102.6
Frequency 60 60 60 60 60
Test condition GOOD GOOD GOOD GOOD GOOD
4. Starting test
Test procedure
(1) Start engine by pushing start button on the control panel.
(2) Stop engine after engine revolution steady by pushing stop button on the control
panel. Stop solenoid is kept (Abt. 30sec) on stop condition.
(3) Safety device working test
Specification Data Result
Cylinder head thermo switch 150± 5! "f “ON” 150 ! GOOD
Start failure 3 times 3 times GOOD
Oil pressure switch 0.15± 0.02 MPa"g“ON” 0.14 MPa GOOD
Over speed switch 115-3 %rpm"f ”ON” 2070 rpm GOOD
V-Belt out switch “ON” by V-Belt Cut ON GOOD
41
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
43/50
10. Water ingress alarm & Dewatering system
1. Date and place
Date : 7 Oct. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. Ohki
Owner 's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
3. Procedure
Water ingress alarm system
To be ascertained whether alarm lamp and buzzer on Alarm panel in W/H areactivated when wetted cloth into contact with sensor at following position.
Dewatering system
Remote controlled hydraulic driven valve in FPT to be operated from above Alarm
Panel, and to be confirmed dewatering by use Ballast pump in E/R.
Remote controlled motor driven valve in Boatswain store to be operated from the Alarm
panel, and to be confirmed dewatering by use ejector and fire main line drive water.
4. Record
Condition Remarks
Boatswain store GOOD 0.1m height
FPT GOOD 10% capacity height
No.1 Cargo hold GOOD 0.5m & 2m height
No.2 Cargo hold GOOD 0.5m & 2m height
No.3 Cargo hold GOOD 0.5m & 2m height
No.4 Cargo hold GOOD 0.5m & 2m height
W a t e r i n g r e s s a l a r m s y s t e m
No.5 Cargo hold GOOD 0.5m & 2m height
Valve GOODFPT
Dewater GOOD
Valve GOOD D e w a t e r i n g
s y s t e m
B’osn
store Dewater GOOD
42
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
44/50
11. Bilge suction system
1. Date and place
Date : 7 Oct. 2009
Place : Alongside of Kanda’s wharf
2. Attendant
Class. (NK) surveyor : Mr. Ohki
Owner 's representative : Mr. Matsumoto / Mr. Hoshi
Shipyard's staff : Inspect. Sect. Tanaka
3. Procedure
Bilge suction to be confirmed at following position.
4. Record
Condition Remarks
Boatswain store GOOD ejector
Chain locker GOOG ejector
No.1 Cargo hold GOOD
No.2 Cargo hold GOOD
No.3 Cargo hold GOODNo.4 Cargo hold GOOD
No.5 Cargo hold GOOD
Steering gear room GOOD incl. E. F. P. recess
43
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
45/50
The noise measurement test of M/V “ CRANE ISLAND” (SNo.522) was omitted in accordance
with mutual agreement.
Therefore this test data shall be referred to the result of noise measurement test of sister vessel
M/V“ ELLIOTT BAY ” (SNo.509).
12. Noise measurement
1. Date and place
Date : 19th Jan 2009
Place : Sea Trial
2. Attendant
Owner 's representative : Chief Officer
Shipyard's staff : Miyagi
3. Measuring method
During sea trial of the vessel, noise measurement to be carried out putting emphasis on
accommodation spaces and engine control room under the condition of normal revolution
of the main engine.
Door and window of the room to be shut during measurement.
4. Measurement positions
Center of the room and 1,200 mm height above the deck.
As for measurement points, refer to the following page.
5. Sound level meter
“RION” SOUND LEVEL METER (TYPE NA –29)
44
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
46/50
5. Noise Measurement Repot
Date : 19th Jan 2009
Place : SEA TRIAL
Attendant : Miyagi
Measured MeasuredNo. Room Name
A (dB)No. Room Name
A (dB)
1 WHEEL HOUSE (P) 59.0 21 OFF'S SMOK. ROOM 59.2
2 WHEEL HOUSE (S) 59.4 22 OFF'S MESS ROOM 63.9
3 CAPT. DAY ROOM 56.2 23 A DECK PASS. 65.4
4 CAPT. BED ROOM 56.2 24 SHIP'S OFFICE 62.1
5 CAPT. OFFICE 54.8 25 BOY 57.9
6 2ND OFFICER 53.5 26 C/COOK 58.6
7 3RD
OFFICER 54.4 27 CREW'S MESS & REC. ROOM 62.7
8 C DECK PASS. 61.9 28 GALLEY 73.1
9 C/ENG. DAY ROOM 52.6 29 HOSPITAL 67.9
10 C/ENG. BED ROOM 52.3 30 UPP. DECK PASS. 71.5
11 2ND ENGINEER 52.9 31 TALLY OFFICE 60.4
12 3RD ENGINEER 54.2 32 ENG. CONT. ROOM 70.1
13 CHIEF OFFICER 52.3 33 ENG. RM (3RD OECK) 98.3
14 BOS’N 53.0 34 GENERATOR FORE 101.5
15 O/SM 53.7 35 BOTTOM 98.5
16 B DECK PASS. 62.8 36
17 NO.1 OILER 55.0 37
18 1ST
ENGINEER 52.8 38
19 OFF’S SPARE (B) 54.1 39
20 CREW’S SPARE (2P) 51.4 40
45
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
47/50
C
D E C K
46
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
48/50
A
D E C K
B
D E C K
47
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
49/50
2 N D
D E C K
U P P E R
D E C K
48
8/18/2019 F-05 Test Result of Outfitiing Part.pdf
50/50
M A I N
F L O
O R
3 R D
D E C K
49