Date post: | 12-Jan-2016 |
Category: |
Documents |
Upload: | wilfred-tobias-carroll |
View: | 215 times |
Download: | 0 times |
f
Fermilab’sFermilab’s
Muon Collider Task Force:Muon Collider Task Force:
Overview, Status and PlansOverview, Status and Plans
Vladimir ShiltsevFermilab AAC, August 08, 2007
AAC meeting, August 6-8, 2007 - Shiltsev 2
f ContentContent
Muon R&D – Strategic Context Muon R&D at the APC MCTF activities and plans Next steps Budget Muon R&D Coordination
AAC meeting, August 6-8, 2007 - Shiltsev 3
f FNAL Steering Group : SubgroupsFNAL Steering Group : Subgroups
Advice/Oversight (additional constituents) Make sure that roadmaps being developed are consistent with
EPP2010 and P5 recommendations – J. Bagger, S. Dawson, A. Seiden, M. Shochet (chair)
Neutrino Physics (additional constituents) Develop roadmap for neutrino physics based on NuSAG studies
Flavor Physics: quarks, charged leptons, ... (additional constituents) Develop 10-year plan with reconfiguring existing accelerator
complex Accelerator Facilities (based on technical and resources
feasibilities) Develop options of a roadmap that supports ILC R&D for early start,
supports Fermilab as a potential host site, and provides an accelerator-based high energy physics program in case of delayed start – H. Edward, T. Himel, S. Holmes (chair), D. McGinnis, S. Nagaitsev, T. Raubenheimer, V. Shiltsev, M. Tigner, (YKK)
High Energy Colliders beyond the ILC Develop steps necessary to explore higher energy colliders that
might follow ILC or be needed should results from LHC point toward a higher energy than that planned for ILC – H. Edward, V. Shiltsev, M. Tigner (chair), (YKK)
AAC meeting, August 6-8, 2007 - Shiltsev 4
f Excerpts from the Steering Group Excerpts from the Steering Group ReportReport
“…
”
AAC meeting, August 6-8, 2007 - Shiltsev 5
f Main points of the Report: Muon ColliderMain points of the Report: Muon Collider
Muon Collider: In contrast to the electron and hadron colliders, demonstrating the viability of a muon collider will require many steps: exploration of various possible overall schemes, a specialized proton driver, various targeting and capture and phase rotation schemes, various possible six-dimensional (6D) ionization cooling
configurations, various methods of acceleration to high energy of the cooled muons, storage ring designs and detector configurations.
Each of these steps may involve development of more than one technology. Given the many unknowns, it is not possible to predict with confidence when these explorations could be complete. In a technically limited schedule, the overall result would be paced by the 6D cooling exploration. Significant trial of the current ideas could be in hand on the five-to-ten year time scale.
AAC meeting, August 6-8, 2007 - Shiltsev 6
f Main points of the Report (cont.)Main points of the Report (cont.)
Current Activities: international MERIT experiment at CERN and MICE at RAL Neutrino Factory and Muon Collider Collaboration (NFMCC) Muon Collider Task Force at Fermilab
Schedule and Cost: significant evaluation of cooling and other feasibility items might be carried out in approximately five to seven years given support for a technically limited schedule. A rough comparison with the U.S. ILC development intensity prior to the ITRP decision would indicate the need for a minimum of $20M annually and 100 FTE of appropriate skills.
It would be very advantageous to have more than one muon test facility where cooling and the associated technologies can be carried out…
AAC meeting, August 6-8, 2007 - Shiltsev 7
f Leading Organization: APCLeading Organization: APC
AAC meeting, August 6-8, 2007 - Shiltsev 8
f Fermilab’s Accelerator Physics CenterFermilab’s Accelerator Physics Center
Accelerator
Physics
Center
Technical
Division
Associate
Director
for Accelerators
Accelerator
Division
Director
APC Mission: Coordinate and conduct accelerator R&D
aimed at next-generation and beyond accelerator facilities
AAC meeting, August 6-8, 2007 - Shiltsev 9
f Accelerator Physics CenterAccelerator Physics Center
Experimental
AARD
US Particle
Accel.School
Accelerator
PhD Program
Peoples
Fellows
HINS
Group
Muon Collider
R&D Group
APC DirectorAdmin Support
Summer
Student
AccPhysProgr
am
Energy
Deposition
LHC
Accel.Syst.
ILC Beam
Physics
Theory &
Modeling
AAC meeting, August 6-8, 2007 - Shiltsev 10
f Muon R&D in APC (06/01/07)Muon R&D in APC (06/01/07)
AAC meeting, August 6-8, 2007 - Shiltsev 11
f Muon Collider Task ForceMuon Collider Task Force Formed in July’06 by FNAL Director:
“… the Muon Collider represents a possible long term path for extending the energy frontier in lepton collisions beyond 1 TeV…”
MCTF formed “…to develop a plan for an advanced R&D program aimed at the technologies required to support the long term prospects of a Muon Collider…”
leaders: S.Geer and V.ShiltsevSept’2006: MCTF report delivered outlining a plan for
developing the Muon Collider concept based on recent ideas in the realm of ionization cooling, and an associated cooling R&D plan that can be implemented starting in FY2007 (available via AAC Web-page)
MCTF people: FNAL(35), BNL(6), JLab (5), Muons Inc(5), LBNL(4), ANL (1)
AAC meeting, August 6-8, 2007 - Shiltsev 12
f 1.5 TeV c.o.m. Muon Collider1.5 TeV c.o.m. Muon Collider
Low emittance scenario * :
Energy per beam 750 GeV
Average luminosity 3e34
cm-2s-1
Repetition rate 65 Hz
Total # of muons 1e11
# bunches 10
β* at IP 0.5 cm
Transverse emittance 2.1
mmmrad
Proton driver power 1.1 MW
* more in talks by R.Johnson and E.Wendt
AAC meeting, August 6-8, 2007 - Shiltsev 13
fThe plan focuses on revisiting the overall Muon Collider design, and on developing and testing the cooling channel components that are needed (beyond those needed for a Neutrino Factory).
1. Muon Collider Design and Simulations design studies of all collider systems
to establish the required cooling parameters
2. Component Development.Helical Magnets (Muons Inc. concept)HTS High-Field Solenoids (NFMCC&Muons Inc
Designs)Pressurized RF Cavities (Muons Inc. concept)
3. Beam Tests and Experiments.High intensity proton beam testsMuon cooling experiments and beam tests
MCTF ActivitiesMCTF Activities
AAC meeting, August 6-8, 2007 - Shiltsev 14
f MCTF Report (https://mctf.fnal.gov)MCTF Report (https://mctf.fnal.gov)
FY07: 0k$ MCTF + 750k$ total for MTA p-line and NFMCC experiments FY08 guidance: 2.1M$ M&S (MCTF and NFMCC) + ~3.9M$ SWF
2006
AAC meeting, August 6-8, 2007 - Shiltsev 15
f Major Next StepsMajor Next Steps
MCTF ’07 report (Fall’07) :Theory/design/simulations (talk by E.Wendt)Magnet design/development (talk by M.Lamm) MANX experiment and MTA beamline construction
(talks by K.Yonehara and F.Garcia) Build p-line to MTA (Shutdown ’07 Jan’08) Propose 6DMANX experiment (by Jan-Mar’08) Build and test a section of HCC magnet
(FY’08) Start fabrication, tests (FY08-09) and
installation (FY09-10) of 6DMANX experiment MC simulation and design work (FY’08-’11) HTS magnets conductor and design work (08-
12)
AAC meeting, August 6-8, 2007 - Shiltsev 16
f Muon Cooling is the Key Muon Cooling is the Key 6D Cooling 6D Cooling Experiment Experiment
6D MANX experiment:6D MANX experiment: Preparation of the proposal
coordinated by A.Jansson and R.Johnson
See talks by R.Johnson, K.Yonehara, A.Jansson and M.Lamm
HCC section model Design FY07 Test in FY08
AAC meeting, August 6-8, 2007 - Shiltsev 17
f Illustrative Muon Collider R&D Long-Range Illustrative Muon Collider R&D Long-Range PlanPlan
2007-2011 2012-2016 2017-2021 2022-2026
RF DevelopmentCavities ----MTA----Power Source -------------------------
Cooling ExptsMICE -------RAL--------6DMANX ------FNAL------6DICEwRF ------FNAL--------Guggenheim -------TBD---------HTS --------FNAL----------Brand Z ---------TBD-----------
HTS DevelopmentConductor ------------------------------Magnet --------------------------------Studies#1: feasibility --------------#2: performance --------#3: cost -----------
S.GeerA.TollestrupV.ShiltsevA.Bross
AAC meeting, August 6-8, 2007 - Shiltsev 18
f Muon Collider R&D FacilitiesMuon Collider R&D Facilities
S.Geer
Muon Test Area:MuCool and HCC
AAC meeting, August 6-8, 2007 - Shiltsev 19
f
mu2eLength 25 m (with Target solenoid)Width 11 m
Helical Cooling ChannelLength 25 mWidth 1 m
Beam dumper
Target Solenoid
8 GeV proton beam
Helical cooling channel
Spectrometer Solenoid
mu2e Experiment and Muon R&D Hallmu2e Experiment and Muon R&D Hall
S.Geer
K.Yonehara
DEBUNCHER
ACCUMULATOR
Synergy 6D Muon Cooling test:
6D ionization cooling channel: 1/10 full scale With RF, HCC, absorber, etc emittance 1/2x1/2x1/2 RF capture
AAC meeting, August 6-8, 2007 - Shiltsev 20
f FY’08 MCTF M&S Funds (plan)FY’08 MCTF M&S Funds (plan)
HCC magnet development 230k$
Collider magnet 200k$
6D Cooling experiment 140k$
Muon beamline 120k$
HTS R&D 550k$
Proton beamline MTA 220k$
MCTF RF tests 120k$
total 1,580k$
AAC meeting, August 6-8, 2007 - Shiltsev 21
f MCTF and NFMCC Co-ordinationMCTF and NFMCC Co-ordinationMar’07: S. Holmes has asked that a NFMCC & MCTF coordinating committee be formed to coordinate the NFMCC & MCTF Muon Collider activities & ensure the overall R&D is coherent & effective
The Muon Collider Coordinating Committee (MCCC) had been formed and had its first meeting March 19th, 2007
Meets ~1/month, in addition to working weekly meetings of NFMCC and MCTF, annual workshops, etc.
MEMBERS:
Alan Bross: NFMCC co-spokesperson, MCTF Str.Grp. Member
Steve Geer: MCTF co-leader, NFMCC Exec. Board Member
Harold Kirk: NFMCC co-spokesperson
Vladimir Shiltsev: MCTF co-leader
Mike Zisman: NFMCC Project Manager
AAC meeting, August 6-8, 2007 - Shiltsev 22
f Management of Current R&DManagement of Current R&D
NFMCC(Project Manager)
US MICE
MUCOOL component R&D(rf, absorbers)
MERIT (& targetry R&D)
Design studies (NF + MC)
MCTF(APC Management)
HCC magnet
6D Manx
HTS magnet
MTA beams
Design studies (MC)
Present emphasis on design work & International Activities
Present emphasis on designwork & activities where FNALplays major role as host lab.
CROSS-PARTICIPATION
AAC meeting, August 6-8, 2007 - Shiltsev 23
f NFMCC-MCTF ProtocolNFMCC-MCTF Protocol
1. The NFMCC and its members are invited to participate in the MCTF program.
2. If the mutually agreed upon activities require MCTF resources, the resources,
milestones and deliverables would be defined by an MOU between Fermilab
and the NFMCC.
3. NFMCC institutions receiving support for MCTF activities would do so within
the framework of the NFMCC (i.e., through the process defined in point 2).
4. Institutions participating in the MCTF that are not presently part of the NFMCC
would be encouraged to join the NFMCC if this seems appropriate (decided
by mutual discussion between the MCTF and NFMCC leadership).
It seems natural that the MCTF manages those activities that requireFermilab to play a significant role as a host laboratory, and the NFMCC manage those activities with an international character
We desire and expect NFMCC participation in MCTF managed R&D. To facilitate this, we have formulated a protocol to follow:
AAC meeting, August 6-8, 2007 - Shiltsev 24
f Collaboration with OthersCollaboration with Others
Muons Inc: excellent collaborator (has $$) pioneering contributions to LEMC
concept and physics of HCC (talk by R.Johnson)
carries out HPRF experiments in MTA (talk by M.BastaniNejad )
contribute to the helical magnet design and MANX design and simulation
AAC meeting, August 6-8, 2007 - Shiltsev 25
f Collaboration with Others (cont)Collaboration with Others (cont)
Other Labs and Universities:JLab BNL IIT
Workshops, meetings, etc: LEMC Workshop (February ‘07)PIC mini-workshop (May ‘07)NFMCC MC workshop (Fall ‘07)
AAC meeting, August 6-8, 2007 - Shiltsev 26
f SummarySummary FNAL Steering Group report calls for increase of Muon Collider and Neutrino Factory R&D Since formation of the Accelerator Physics Center, all Muon
Collider and Neutrino Factory R&D programs are being coordinated by the APC’s Muon Accelerator R&D Department
1-yr old MCTF progressed along three lines: Theory and simulations (cooling simulations, collider optics, etc) Hardware development (HCC section design, HTS conductor, etc) Experimental beam research (MTA p-line, MANX preparations).
MCTF efforts in near future will be concentrated on Construction and commissioning of MTA beamline Experimental studies with proton beam in MTA (HPRF, MuCool) Development of HCC magnet and HTS conductor studies Planning, design, construction for 6D MANX experiment
These efforts involve effective collaborations: With NFMCC: MCCC has made a good start Muons Inc; other Labs and Universities