Series Title Value % of Point Estimate
200 Site Clearance £625,296.30 5%
300 Fencing £113,973.12 1%
400 Road Restraint Systems (Vehicle and Pedestrian) £30,547.20 0%
500 Drainage £1,277,720.34 10%
600 Earthworks £1,892,303.71 15%
700 Pavements £1,892,996.88 15%
1100 Kerbs, Footways & Paved Areas £442,303.37 4%
1200 Traffic Signs & Road Markings £36,311.09 0%
1300 Road Lighting £318,523.48 3%
1700 Structural Concrete £894.42 0%
2700 Accomodation Works, Works for Statutory Undertakers £715,283.09 6%
3000 Landscaping and Ecology £34,807.43 0%
Direct Construction Works (£) £7,380,960.41 60%
100 Preliminaries 25.0% £1,845,240.10 15%
- Overheads and Profit 13.7% £1,011,191.58 8%
Indirect Construction Costs (£) £2,856,431.68 23%
Total Base Construction Cost (£) £10,237,392.09 83%
- Design Team Fees 7.5% £767,804.41 6%
- Project Team Fees 11.1% £1,136,350.52 9%
- Survey costs £125,000.00 1%
- Land cost (assumed value)
Employer Indirect Costs £2,029,154.93 17%
Point Estimate (£) £12,266,547.02 100%
- Risk Allowance £306,587.50
Cost Limit Excluding Inflation (£) £12,573,134.52
- Inflation 2.5% £314,328.36
Cost Limit Including Inflation (£) £12,887,462.88
- Optimism Bias 44.0% £5,670,483.67
Total Captial Cost Estimate (£) £18,557,946.55
Ch 0 - 400 and Drainage West £3,317,787.93
Ch 400 - 510 £930,573.48
Ch 510-960 £3,306,635.00
Ch 960 - 1825 £4,372,126.53
Ch 1825 - 2200 £1,340,562.69
A388 Rounadbout and Drainage East £5,290,260.91
Notes:
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-006 Launceston Southern Loop Road
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Cost Summary
Bill of Quantities: Whole Route
Project Number: 70028324
Series Title Value % of Point Estimate
200 Site Clearance £121,454.65 6%
300 Fencing £22,943.40 1%
400 Road Restraint Systems (Vehicle and Pedestrian) £11,455.20 1%
500 Drainage £241,263.12 11%
600 Earthworks £418,384.07 19%
700 Pavements £257,690.56 12%
1100 Kerbs, Footways & Paved Areas £61,947.20 3%
1200 Traffic Signs & Road Markings £779.13 0%
1300 Road Lighting £60,725.70 3%
1700 Structural Concrete £5.07 0%
2700 Accomodation Works, Works for Statutory Undertakers £119,213.85 5%
3000 Landscaping and Ecology £6,883.57 0%
Direct Construction Works (£) £1,322,745.51 60%
100 Preliminaries 25.0% £330,686.38 15%
- Overheads and Profit 13.7% £181,216.13 8%
Indirect Construction Costs (£) £511,902.51 23%
Total Base Construction Cost (£) £1,834,648.02 84%
- Design Team Fees 7.5% £137,598.60 6%
- Project Team Fees 11.1% £203,645.93 9%
- Survey costs £20,833.33 1%
- Land cost (assumed value) £0.00
Employer Indirect Costs £362,077.87 16%
Point Estimate (£) £2,196,725.89 100%
- Risk Allowance £51,097.92
Cost Limit Excluding Inflation (£) £2,247,823.80
- Inflation 2.5% £56,195.60
Cost Limit Including Inflation (£) £2,304,019.40
- Optimism Bias 44.0% £1,013,768.54
Total Captial Cost Estimate (£) £3,317,787.93
Notes:
Cost Summary
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Ch 0 - 400m inc. Drainage West (No associated plot reference)
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Series Title Value % of Point Estimate
200 Site Clearance £0.00 0%
300 Fencing £5,289.84 1%
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00 0%
500 Drainage £47,435.13 8%
600 Earthworks £11,190.81 2%
700 Pavements £95,782.82 17%
1100 Kerbs, Footways & Paved Areas £35,660.64 6%
1200 Traffic Signs & Road Markings £3,377.09 1%
1300 Road Lighting £20,120.21 3%
1700 Structural Concrete £121.47 0%
2700 Accomodation Works, Works for Statutory Undertakers £119,213.85 21%
3000 Landscaping and Ecology £1,348.99 0%
Direct Construction Works (£) £339,540.85 59%
100 Preliminaries 25.0% £84,885.21 15%
- Overheads and Profit 13.7% £46,517.10 8%
Indirect Construction Costs (£) £131,402.31 23%
Total Base Construction Cost (£) £470,943.16 81%
- Design Team Fees 7.5% £35,320.74 6%
- Project Team Fees 11.1% £52,274.69 9%
- Survey costs £20,833.33 4%
- Land cost (assumed value) £0.00
Employer Indirect Costs £108,428.76 19%
Point Estimate (£) £579,371.92 100%
- Risk Allowance £51,097.92
Cost Limit Excluding Inflation (£) £630,469.84
- Inflation 2.5% £15,761.75
Cost Limit Including Inflation (£) £646,231.58
- Optimism Bias 44.0% £284,341.90
Total Captial Cost Estimate (£) £930,573.48
Notes:
Cost Summary
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Ch 400 - 510m (LAU-E2)
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Series Title Value % of Point Estimate
200 Site Clearance £119,430.93 5%
300 Fencing £20,597.52 1%
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00 0%
500 Drainage £253,174.30 12%
600 Earthworks £187,055.50 9%
700 Pavements £444,573.69 20%
1100 Kerbs, Footways & Paved Areas £90,684.07 4%
1200 Traffic Signs & Road Markings £7,785.74 0%
1300 Road Lighting £70,189.95 3%
1700 Structural Concrete £232.15 0%
2700 Accomodation Works, Works for Statutory Undertakers £119,213.85 5%
3000 Landscaping and Ecology £5,214.32 0%
Direct Construction Works (£) £1,318,152.03 60%
100 Preliminaries 25.0% £329,538.01 15%
- Overheads and Profit 13.7% £180,586.83 8%
Indirect Construction Costs (£) £510,124.84 23%
Total Base Construction Cost (£) £1,828,276.87 84%
- Design Team Fees 7.5% £137,120.77 6%
- Project Team Fees 11.1% £202,938.73 9%
- Survey costs £20,833.33 1%
- Land cost (assumed value) £0.00
Employer Indirect Costs £360,892.83 16%
Point Estimate (£) £2,189,169.70 100%
- Risk Allowance £51,097.92
Cost Limit Excluding Inflation (£) £2,240,267.61
- Inflation 2.5% £56,006.69
Cost Limit Including Inflation (£) £2,296,274.30
- Optimism Bias 44.0% £1,010,360.69
Total Captial Cost Estimate (£) £3,306,635.00
Notes:
Cost Summary
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Ch 510 - 960m (LAU-E1)
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Series Title Value % of Point Estimate
200 Site Clearance £173,178.57 6%
300 Fencing £41,873.52 1%
400 Road Restraint Systems (Vehicle and Pedestrian) £10,023.30 0%
500 Drainage £360,385.04 12%
600 Earthworks £301,608.04 10%
700 Pavements £470,542.34 16%
1100 Kerbs, Footways & Paved Areas £157,114.64 5%
1200 Traffic Signs & Road Markings £4,967.51 0%
1300 Road Lighting £107,041.10 4%
1700 Structural Concrete £140.49 0%
2700 Accomodation Works, Works for Statutory Undertakers £119,213.85 4%
3000 Landscaping and Ecology £10,899.88 0%
Direct Construction Works (£) £1,756,988.28 60%
100 Preliminaries 25.0% £439,247.07 15%
- Overheads and Profit 13.7% £240,707.39 8%
Indirect Construction Costs (£) £679,954.46 23%
Total Base Construction Cost (£) £2,436,942.75 84%
- Design Team Fees 7.5% £182,770.71 6%
- Project Team Fees 11.1% £270,500.64 9%
- Survey costs £20,833.33 1%
- Land cost (assumed value) £0.00
Employer Indirect Costs £474,104.68 16%
Point Estimate (£) £2,911,047.43 100%
- Risk Allowance £51,097.92
Cost Limit Excluding Inflation (£) £2,962,145.35
- Inflation 2.5% £74,053.63
Cost Limit Including Inflation (£) £3,036,198.98
- Optimism Bias 44.0% £1,335,927.55
Total Captial Cost Estimate (£) £4,372,126.53
Notes:
Cost Summary
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Ch 960 - 1825m (LAU-H2)
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Series Title Value % of Point Estimate
200 Site Clearance £0.00 0%
300 Fencing £18,853.68 2%
400 Road Restraint Systems (Vehicle and Pedestrian) £9,068.70 1%
500 Drainage £81,794.73 10%
600 Earthworks £37,606.70 4%
700 Pavements £143,426.70 17%
1100 Kerbs, Footways & Paved Areas £47,946.75 6%
1200 Traffic Signs & Road Markings £429.76 0%
1300 Road Lighting £45,377.81 5%
1700 Structural Concrete £92.69 0%
2700 Accomodation Works, Works for Statutory Undertakers £119,213.85 14%
3000 Landscaping and Ecology £4,588.75 1%
Direct Construction Works (£) £508,400.13 59%
100 Preliminaries 25.0% £127,100.03 15%
- Overheads and Profit 13.7% £69,650.82 8%
Indirect Construction Costs (£) £196,750.85 23%
Total Base Construction Cost (£) £705,150.97 82%
- Design Team Fees 7.5% £52,886.32 6%
- Project Team Fees 11.1% £78,271.76 9%
- Survey costs £20,833.33 2%
- Land cost (assumed value) £0.00
Employer Indirect Costs £151,991.41 18%
Point Estimate (£) £857,142.39 100%
- Risk Allowance £51,097.92
Cost Limit Excluding Inflation (£) £908,240.30
- Inflation 2.5% £22,706.01
Cost Limit Including Inflation (£) £930,946.31
- Optimism Bias 44.0% £409,616.38
Total Captial Cost Estimate (£) £1,340,562.69
Notes:
Cost Summary
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Ch 1825m - Ch 2200 (LAU-H1)
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Series Title Value % of Point Estimate
200 Site Clearance £211,232.15 6%
300 Fencing £4,415.16 0%
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00 0%
500 Drainage £293,668.02 8%
600 Earthworks £936,458.58 27%
700 Pavements £480,980.77 14%
1100 Kerbs, Footways & Paved Areas £48,950.06 1%
1200 Traffic Signs & Road Markings £18,971.86 1%
1300 Road Lighting £15,068.69 0%
1700 Structural Concrete £302.55 0%
2700 Accomodation Works, Works for Statutory Undertakers £119,213.85 3%
3000 Landscaping and Ecology £5,871.92 0%
Direct Construction Works (£) £2,135,133.61 60%
100 Preliminaries 25.0% £533,783.40 15%
- Overheads and Profit 13.7% £292,513.30 8%
Indirect Construction Costs (£) £826,296.71 23%
Total Base Construction Cost (£) £2,961,430.32 84%
- Design Team Fees 7.5% £222,107.27 6%
- Project Team Fees 11.1% £328,718.77 9%
- Survey costs £20,833.33 1%
- Land cost (assumed value) £0.00
Employer Indirect Costs £571,659.37 16%
Point Estimate (£) £3,533,089.69 100%
- Risk Allowance £51,097.92
Cost Limit Excluding Inflation (£) £3,584,187.61
- Inflation 2.5% £89,604.69
Cost Limit Including Inflation (£) £3,673,792.30
- Optimism Bias 44.0% £1,616,468.61
Total Captial Cost Estimate (£) £5,290,260.91
Notes:
Cost Summary
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: A388 Roundabout and Drainage East (No associated plot reference)
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
% contribution to
Optimism Bias
Mitigation
Factor
(0-1)
Reduction in %
contribution to
Optimism Bias
Comments
Late Contractor Involvement in Design 3 0 0 Contractor involved after detailed design undertaken
Dispute & Claims Occurred 21 0 0 Contract not yet award
Environmental Impact 22 0 0 Recent EIA not carried out
Other 18 0 0
Inadequacy of the business case 10 0 0 Early stage of development
Poor project intelligence 7 0 0
Public Relations 9 0 0
Site Characteristics 3 0 0A sharp bend is present therefore causing issue of visibility and
stopping sight distances for design
External Economic 7 0 0
Total 100 0
Initial upper bound Optimism Bias 44%
Final Optimism Bias 44%
Client specific
Date: Q1 2017 - 18/04/2017
Project Number: 70028324
Procurement
Environment
Project Title: T5070-006 Launceston Southern Loop Road
Optimism Bias CalculationBased on Table 3 from Supplementary Green Book Guidance
Contributory Factor
Project Specific
12-Jan-15
£306,588
% Score Minimum Most Likely Maximum
001 GovernanceSteering Group actions not
completed on timeExceedance of tolerances 25% 3 1 1 3 3 9 15 £4,000 £8,000 £20,000 £2,000
Cornwall
Council
Project governance
established
Steering
Group
002 GovernanceScheme does not receive
Cabinet approvalDelay/cancel scheme 25% 3 1 1 3 3 9 15 £16,000 £25,000 £50,000 £6,250
Cornwall
Council
Scheme helps achieve LTP3
objectives. Engage with
councillors early to ensure they
are on board with scheme
proposals.
Cornwall
Council
003 Interfaces Overall programme slips Delay scheme / additional cost 50% 3 1 1 3 3 9 15 £4,000 £8,000 £24,000 £4,000Cornwall
Council
Float incorporated into
programme. Scheme delivered
in funding timescales.
Designer /
Cornwall
Council
004 InterfacesAcquisition of third party land
needed to deliver the projectDelay/cancel scheme 90% 5 1 2 5 10 50 2 £5,000 £15,000 £75,000 £13,500 Designer
Spend greater 2D / 3D design
effort during the preliminary
design stage to identify land
requirements during Stage 1
Designer
005Planning
Approval
Project requires planning
approval rather than GPDODelay/cancel scheme 20% 2 2 3 4 6 24 8 £60,000 £95,000 £130,000 £19,000
Cornwall
Council
Early engagement with
planning officer
Cornwall
Council
006Planning
Approval
Failing to achieve planning
approval within time constraintsDelay/cancel scheme 30% 3 1 1 3 3 9 15 £5,000 £10,000 £50,000 £3,000
Cornwall
Council
Early engagement with
planning officer
Cornwall
Council
007 Design
Phase 1 Habitat survey reveal
requirement for further surveys
to be undertaken
Delay scheme / additional cost 5% 3 1 1 3 3 9 15 £2,500 £5,000 £50,000 £250 DesignerEarly engagement with
planning officerDesigner
008 DesignLack of accuracy in Topographic
SurveyDelay scheme / additional cost 40% 3 1 1 3 3 9 15 £10,000 £25,000 £50,000 £10,000 Designer
Ensure Tender includes for
provision of a "check" survey
during tender
Designer
009 Design Change of project staff Delay scheme / additional cost 20% 2 1 2 2 4 8 23 £500 £4,000 £8,000 £800Cornwall
Council
Ensure sufficient allowance for
handover
Cornwall
Council
010 Design Lack of project resources Delay scheme / additional cost 40% 3 1 2 3 6 18 9 £2,000 £5,000 £16,000 £2,000 DesignerIdentify resource requirements
earlyDesigner
011 DesignPotential Planning Mitigation
Actions (landscaping etc.)Delay scheme / additional cost 30% 3 1 1 3 3 9 15 £1,000 £5,000 £20,000 £1,500 Designer
Early engagement with
planning officerDesigner
012 Design
Grade II listed milestone needs
to be relocated/ protected as part
of the scheme development
Additional cost 90% 5 1 2 5 10 50 2 £5,000 £10,000 £100,000 £9,000Cornwall
Council
Engage with Historic
Environment officer asap to
understand issues and
processes involved and to
minimise costs and
programme impacts
Designer
013 Design
Scheme proposals impact on
Tree Preservation Order areas
requiring trimming of trees
Additional cost / Delay scheme 30% 5 1 2 5 10 50 2 £10,000 £25,000 £50,000 £7,500Cornwall
Council
Engage with tree officers in
development of scheme
proposals to minimise cost and
programme impacts
Designer
014 Design
Overconservative drainage
design due to lack of existing
drainage information
Delay scheme / additional cost 50% 5 1 1 5 5 25 7
Construction
cost considered
in additiion
£50,000 £75,000 £100,000 £37,500Cornwall
Council
Liaison with Regional
Highways team, commission a
drainage CCTV survey if
details are unclear
Designer
015 Design
Unfavourable Traffic Modelling
Outcomes requires further
design development to the
current proposal
Delay / cancel scheme /
additional cost50% 3 1 2 3 6 18 9 £4,000 £8,000 £20,000 £4,000
Cornwall
Council
Appropriate future modelling in
VISSIM or PARAMICSDesigner
016 Procurement Lack of interest in tender Delay scheme / additional cost 5% 1 1 2 1 2 2 39 £5,000 £10,000 £50,000 £500Cornwall
Council
Use CC framework. Hold
"Suppliers Day" meeting with
contractors to ensure they are
aware of bid coming out and
can plan their resources
accordingly
Cornwall
Council
017 Procurement Cost estimate too low Delay scheme / additional cost 20% 2 2 2 4 4 16 12 £30,000 £150,000 £300,000 £30,000 DesignerUpdate cost estimate at end of
each development StageDesigner
018 ProcurementContract options chosen
inappropriate for scheme
Client retains too much
construction risk5% 1 2 1 2 1 2 39 £30,000 £150,000 £300,000 £7,500
Cornwall
Council
Discuss any lessons learned
on recent contracts with Capital
Works team and use to
determine appropriate form of
contract
Cornwall
Council
019 Procurement Tender evaluation isn't robust Additional cost 5% 1 1 1 1 1 1 43 £30,000 £150,000 £300,000 £7,500Cornwall
Council
Evaluation of price and quality
submission. Modelling of
compensation events
Cornwall
Council
020 Procurement Delay in contract award Delay scheme / additional cost 5% 1 1 2 1 2 2 39 £500 £750 £4,000 £38Cornwall
Council
Incorporate committee dates
into programme and manageDesigner
Risk Allowance:
Project:
Displayed: Quantified Risk Assessment and Risk Management Strategy
Risk Review Date:
Cost
Assumptions
Risk Description Current Qualitative Scoring Current Quantitative Evaluation Action, Mitigation & Notes
Risk ID
NoRisk Category Risk Description Risk Consequence
Likelihood
Cost
Schedule
Cost Risk
Score
Schedule
Risk Score
Combined
Risk ScoreRisk Rank Notes
Cost Impact
Risk ValueRisk Owner/
ManagerCurrent Control Measures Action Owner
Target
Completion
Date
021 ConstructionStatutory undertakers diversion
works delaysDelay scheme / additional cost 20% 2 1 2 2 4 8 23 £50,000 £75,000 £150,000 £15,000
Cornwall
Council
Early engagement with SU
regarding programme and
procurement lead in. Organise
Co-ordination meeting with all
Statutory Providers and
Contractor prior to construction
phase
Designer
022 Construction Unforeseen ground conditions Delay scheme / additional cost 10% 2 1 2 2 4 8 23 £10,000 £25,000 £50,000 £2,500Cornwall
Council
Commission appropriate level
and extents of geotechnical
investigation is carried out
early in the scheme
development
Designer
023 ConstructionUnforeseen services found
during constructionDelay scheme / additional cost 10% 2 1 2 2 4 8 23 £20,000 £50,000 £100,000 £5,000
Cornwall
Council
Undertake NRSWA C2.
Contractor to scan site prior to
commencing works
Cornwall
Council
024 Construction
Poor co-ordination and
programming of statutory
undertakers
Delay scheme / additional cost 30% 3 1 1 3 3 9 15 £10,000 £50,000 £75,000 £15,000Cornwall
Council
Early engagement with SU
regarding programme and
procurement lead in. Organise
Co-ordination meeting with all
Statutory Providers and
Contractor prior to construction
phase
Designer
025 Construction
Inappropriate contract
administration and supervision
staff
Additional cost / Delay scheme 5% 1 2 1 2 1 2 39 £10,000 £25,000 £75,000 £1,250Cornwall
CouncilEnsure appropriate staffing
Cornwall
Council
026 Construction
Impact on operations of hospital
or business park greater than
planned for
Additional cost / Delay scheme 50% 3 1 2 3 6 18 9 £30,000 £65,000 £100,000 £32,500Cornwall
Council
Ensure sufficient planning of
traffic management and
contingency plans for delays.
Consult with hospital and
emergency services during
scheme development to
minimise the impacts and
capture requirements for
Tender package. Include the
need for Contractor to continue
the liaison as part of the tender
package.
Designer
027 ConstructionKnotweed on site not adequately
managed prior to constructionAdditional cost / Delay scheme 10% 2 2 1 4 2 8 23 £50,000 £100,000 £150,000 £10,000
Cornwall
Council
Liaise with Knotweed officer
and agree best management
strategy to limit cost and
programme implications to
construction
Designer
028 Construction
Traffic Management required
proves to be more complicated
than envisaged during scheme
preparation
Additional cost / Delay scheme 10% 2 1 2 2 4 8 23 £20,000 £50,000 £100,000 £5,000Cornwall
Council
Early engagement with Street
works co-ordinator to fully
understand constraints and
ensure sufficient information
contained within the tender
package. Consider
development of early TM plan.
Liaise with other Truro corridor
projects to maximise
opportunities and limit impacts.
Designer
029 Construction
Night time working and traffic
management results in
excessive "disturbance" claims
for noise etc.
Additional cost 20% 2 1 1 2 2 4 35 £20,000 £50,000 £100,000 £10,000Cornwall
Council
Ensure the Tender package
CEMP contains suite of robust
noise and dust management
measures and other best
practice mitigation. Liaise with
Community Network officers to
ensure public is fully informed
and realises the benefits of the
scheme proposals.
Designer /
Cornwall
Council
030 Construction
Unknown archaeological finds
made during works causing
delays to the programme
Additional cost / Delay scheme 40% 3 2 3 6 9 54 1 £10,000 £20,000 £40,000 £8,000Cornwall
Council
Contact environment and
archaeology sections of CC as
part of further scheme design
Designer
031 Construction
Contaminated materials
encountered during ground
investigation and construction
works
Additional cost / Delay scheme 15% 2 2 1 4 2 8 23 £5,000 £10,000 £20,000 £1,500Cornwall
Council
Ensure suitable ground
investigation and
contamination testing of
samples
Designer
032 Construction
Extent of historic extraction
industries (mining / quarrying /
tin streaming) in relation to the
road corridor creating
underground instability
Additional cost / Delay scheme 20% 2 2 1 4 2 8 23 £5,000 £10,000 £20,000 £2,000Cornwall
Council
Review documentation and if
appropriate conduct
intrusive/geophysical
investigations
Designer
033 ConstructionUnrecorded buried
obstructions/voidsAdditional cost / Delay scheme 20% 2 2 1 4 2 8 23 £5,000 £10,000 £20,000 £2,000
Cornwall
Council
Unexpected ground conditions
to be reported immediately to
client/designer
Contractor /
Survey Team
034 Construction
Excessive total differenetial
settlement of the
highway/earthworks
Additional cost / Delay scheme 20% 2 2 2 4 4 16 12 £10,000 £20,000 £40,000 £4,000Cornwall
Council
Ensure suitable ground
investigation and testing of
samples
Designer
035 Construction
Shallow groundwater
destabilising or flooding shallow
excavations
Additional cost / Delay scheme 15% 2 1 1 2 2 4 35 £5,000 £10,000 £20,000 £1,500Cornwall
Council
Suitable ground investigation
including standpipes to
determine the level and
fluctuations of groundwater
Designer
036 Construction Soil Chemistry Additional cost / Delay scheme 15% 2 1 1 2 2 4 35 £5,000 £10,000 £20,000 £1,500Cornwall
Council
Chemical analysis to confirm
appropriate cut slope angles,
presence of faults, fracture
spacing, cohesion and swelling
clays
Designer
037 Construction
Hard rock encountered above
founding level - hard to
excavate/rip
Additional cost / Delay scheme 20% 2 2 2 4 4 16 12 £10,000 £20,000 £40,000 £4,000Cornwall
Council
Ensure suitable ground
investigationDesigner
038 ConstructionUnfavourable structural geology
causing rock/lsope failureAdditional cost / Delay scheme 40% 3 2 2 6 6 36 5 £10,000 £20,000 £40,000 £8,000
Cornwall
Council
Ensure suitable ground
investigationDesigner
039 ConstructionPresence of historcial landslip
materialAdditional cost / Delay scheme 5% 1 2 2 2 2 4 35 £10,000 £20,000 £40,000 £1,000
Cornwall
Council
Ensure suitable ground
investigationDesigner
040 Construction
Presence of unforeseen soil/rock
units requiring slacker cut slope
angles and increased land take
Additional cost / Delay scheme 20% 2 2 1 4 2 8 23 £5,000 £10,000 £20,000 £2,000Cornwall
Council
Ensure suitable ground
investigationDesigner
041 Construction
Made ground requiring
unexpected ground improvement
works/disposal
Additional cost / Delay scheme 20% 2 2 1 4 2 8 23 £5,000 £10,000 £20,000 £2,000Cornwall
Council
Ensure suitable ground
investigationDesigner
042 ConstructionInadequate CBR of natural/fill
materials at formation levelAdditional cost / Delay scheme 30% 2 2 1 4 2 8 23 £5,000 £10,000 £20,000 £3,000
Cornwall
Council
Ensure suitable ground
investigationDesigner
043 ConstructionUnrecorded mine features
(shafts/adits)Additional cost / Delay scheme 20% 3 2 2 6 6 36 5 £10,000 £20,000 £40,000 £4,000
Cornwall
Council
Ensure suitable ground
investigation, watching brief
during construction
Designer /
Contractor
£306,588Risk Allowance (Total):
Risk Probability Impact Diagram
> 75% 5 10 15 20 25
50-75% 4 8 12 16 20
20-50% 3 6 9 12 15
5-20% 2 4 6 8 10
< 5% 1 2 3 4 5
Very low Low Medium High Very High
Cost<£927.9k£927.9-1855.79k
Cost
£1855.79-
4639.49k Cost
£4639.49-9278.97k
Cost
Cost>£9278.97
k
Lik
eli
ho
od
/Pro
ba
bil
ity
Construction CostEstimate
£18,557,947
Overall ProgrammeTime Frame <4 weeks 8 - 20 weeks 20 - 40 weeks >40 weeks
80 WkCost/Time Impact
4 - 8 weeks
Ref Item Description Quantity Unit Rate Total
Series 200: Site Clearance
Site Clearance
General site clearance; open field site 12.55 ha 1,688.04 21,177.31
General site clearance; medium density wooded 9.88 ha 3,510.32 34,664.41
Dry Stone Boundary Wall 5,560 m³ 79.50 442,020.00
Take Up or Down and Set Aside for Re-Use or
Remove to Store or Tip Off Site
Take up or down and remove to tip off site;
precast concrete kerbs 298 m 298.00 88,804.00
Take up or down and remove to tip off site; traffic
signs 14 no 14.00 196.00
Take up or down and remove to tip off site; road
stud 10 no 10.00 100.00
Timber Post & Four Rail Fence 2,471 m 15.50 38,300.50
Gully grating & Frame 6 no 5.68 34.08Series 200 Total £625,296.30
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Ref Item Description Quantity Unit Rate Total
Series 300: Fencing
Fencing, Gates and Stiles
Timber rail fencing; 1.4m high, timber posts and
four rails 4,295 m 23.64 101,533.80
Steel tubular single field gate 1.175m high 5.02m
wide 24 no 262.70 6,304.80
Concrete foundation to gate posts for single field
gate 48 no 9.11 437.28
Soakaway/Attenuation Feature
Timber rail fencing; 1.4m high, timber posts and
four rails 241 m 23.64 5,697.24
Series 300 Total £113,973.12
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Ref Item Description Quantity Unit Rate Total
Series 400: Road Restraint Systems (Vehicles
and Pedestrians)
Beam Safety Barrier, Untensioned beams, single
sided open box beam, straight or curved
exceeding 120 m radius 640 m 47.73 30,547.20
Series 400 Total £30,547.20
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Ref Item Description Quantity Unit Rate Total
Series 500: Drainage and Service Ducts
Drainage and Service Ducts (excluding Filter
Drains, Narrow Filter Drains and Fin Drains)
300m internal diameter drain specified design
group * with Type S bed and surround in trench,
average depth to invert 3.00 metres 3,163 m 210.99 667,361.37
Chamber and Gullies
1200 dia x 2000 depth to invert, precast concrete
construction, inc. excavation, backfill and disposal 65 no 1,502.06 97,633.90
Precast concrete; set in concrete grade C20P,
150 mm thick; additional excavation and disposal,
Road gulley; trapped with rodding eye;
galvanized bucket; stopper, 450 mm
dia. × 900 mm deep, cast iron road gulley grating
and frame group 4, 434 × 434 mm, on Class B
engineering brick seating 301 no 527.49 158,774.49
Connections
150mm dia. drain average 2m deep gully
connection with Type S bed and surround 2,408 m 99.67 240,005.36
Excavation In Hard Material
Extra over excavation for excavation in Hard
Material in drainage, existing pavement 200 m² 24.97 4,994.00
Soakaway/Attenuation Feature
Complex control chamber, 2.4m dia x 3m depth to
invert, excavation, support, backfilling and
disposal, including control method 2 no 7,503.63 15,007.26
Valve chamber , 1.2m dia x 3m depth to invert,
excavation, support, backfilling and disposal,
including control method 2 no 2,160.18 4,320.36
Reinforced concrete headwall, 225mm thick 16 m² 125.00 2,040.00
Culverts
900mm dia. piped culvert in trench, depth to
invert, average 4.00m deep, Type A Concrete
surround 1500mm wide x 150mm 130 m 673.72 87,583.60
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Ref Item Description Quantity Unit Rate Total
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Series 500 Total £1,277,720.34
Ref Item Description Quantity Unit Rate Total
Series 600: Earthworks
Excavation of acceptable material Class 5A 9,705 m3
3.08 29,892.31
Excavation of acceptable material excluding Class
5A in cutting and other excavation 13,913 m3
4.11 57,182.85
Extra over for excavation in cutting and other
excavation in hard material; using backacters and
tractor loader with ripper, rock 2,000 m3
72.49 144,980.00
Deposition of acceptable material Class 1C/6B in
embankments and other areas of fill 39,758 m³ 1.19 47,311.95
Imported graded granular fill, DfT Class 2A/B/C/D
[1.8 t/m³]; using tractor loader, Imported
acceptable material in embankments and other
areas of fill 30,696 m³ 23.73 728,412.47
Disposal of acceptable material Class 5A 2,912 m3
113.89 331,600.88
Compaction of granular fill material, in
embankments and other areas of fill 39,758 m3
0.63 25,047.50
Excavation of soft spots and other voids using
motorised scrapers and/or dozers, excavate
below cuttings or under embankments 1,000 m3
8.68 8,680.00
Topsoiling 150 mm thick to surfaces at 10° or less
to horizontal 6,834m² 6.08
41,550.72
Breaking up and perforation of redundant
pavements, Breaking up of redundant flexible
pavement, 100mm deep 421 m² 6.45 2,715.45
Imported graded granular fill, DfT Class 6F
(1.9t/m³); using tractor loader Imported
acceptable material in embankments and other
areas of fill 5,581 m³ 37.16 207,382.53
Imported graded granular fill, DfT Class 6F
(1.9t/m³); using tractor loader extra for aggregate
Tax 5,581 m³ 4.99 27,848.19
Compaction of fill, Compaction of granular fill
material in embankments and other areas of fill 5,581 m³ 2.50 13,952.00
Perforation of redundant flexible pavement, 100-
200mm deep 4,052 m² 0.95 3,848.99
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Ref Item Description Quantity Unit Rate Total
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Soakaway/Attenuation Feature
Excavation of acceptable material Class 5A 1,463 m3
3.08 4,505.42
Excavation of acceptable material excluding Class
5A in cutting and other excavation 3,557 m3
4.11 14,620.09
Disposal of acceptable material to landfill
including Class 5A using 10-15 tonne capacity
tipping lorry for on site or off site use 400 m³ 113.89 45,556.00
Deposition of acceptable material Class 1C/6B in
embankments and other areas of fill 1,092 m³ 1.19 1,299.48
Lining of new watercourse 4,350 m² 34.10 148,335.00
Gabion walling with headwall with heavily
galvanised woven wire mesh, wire laced; filled
with 50mm Class 6G material, 2.0 x 1.0 x 1.0m
modules sizes 19 m³ 118.17 2,245.23
Mattress with plastic coated galvanized wire
mesh; filled with 50 mm Class 6G material
installed at 10° or less to the horizontal. 48 m³ 112.35 5,336.63
Series 600 Total £1,892,303.71
Ref Item Description Quantity Unit Rate Total
Series 700: Pavements
Sub-Base
Granular Type 1 sub-base in carriageway,
hardshoulder and hardstrip, 150mm deep 5,922 m3
34.23 202,697.81
Pavement
Dense Bitumen Macadam Base to DfT Clause
903: 200mm deep 26,617 m2
30.93 823,268.20
Dense Bitumen Macadam Binder course to DfT
Clause 904 50mm deep 26,617 m2
11.90 316,743.99
Dense Bitumen Macadam Surface course to DfT
Clause 909 50mm deep 26,617 m2
13.06 347,619.87
Cold Milling (Planing)
Milling pavement; 100mm 4,797 m2
15.18 72,819.04
Tack Coat
Bituminous spray; BS 434 K1–40, Tack coat to
DfT Clause 920, large areas; over 20 m² 53,234 m2
0.73 38,861.03
Anti Skid Surfacing System
High friction surfacing to DfT Clause 924,
Proprietary resin bonded surfacing system,
colours (Buff, Grey, Red, Green) 4,037 m2
21.00 84,768.66
Soakaway/Attenuation Feature
Granular Type 1 sub-base in carriageway,
300mm deep 166 m³ 37.55 6,218.28
Series 700 Total £1,892,996.88
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Ref Item Description Quantity Unit Rate Total
Series 1100: Kerbs, Footways and Paved
Areas
Kerbs
Precast concrete kerbs, half battered, laid straight
or curved exceeding 12 metres radius, 125 x
255mm 6,137 m 16.32 100,155.84
Precast concrete units; BS 7263; bedded jointed
and pointed in cement mortar. Quadrants
305x305x150 mm 48 no 22.89 1,098.72
Precast concrete units; BS 7263; bedded jointed
and pointed in cement mortar, drop kerbs, 125 x
255mm 96 no 27.91 2,679.36
Foundations to edging etc., Mass concrete,
200 × 100 mm 4,606 m 2.49 11,468.94
Foundations to edging, Mass concrete,
100 × 100 mm haunching, per side 4,606 m 0.79 3,638.74
Foundations to kerbs etc., Mass concrete,
450 × 150 mm 6,137 m 7.41 45,475.17
Bitumen macadam surfacing; BS 4987; binder
course of 20mm open graded aggregate to clause
2.7.1 tables 5-7; surface course of 6mm medium
ground aggregate to clause 2.7.6 tables 32-33;
excluding sub-base. Paved area 60 mm thick;
comprising binder course 40 mm thick surface
course 20 mm thick sloping at 10° of less to be
horizontal
13,222 m² 21.01 277,786.60
Series 1100 Total £442,303.37
Date: Q1 2017 - 18/04/2017
Drawing Reference: 70028324-101-103
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Ref Item Description Quantity Unit Rate Total
Series 1200: Traffic Signs and Road Markings
Traffic Signs
Standard one post signs; 600 × 450 mm type C1
signs fixed with aluminium clips to 76 mm dia.
3.5 m long aluminium post
23 no 96.01 2,208.23
Standard two post signs; 1200 × 400 mm, signs
fixed back to back to another sign with steel clips,
two 76 mm dia. 3.5 m long aluminium post
13 no 327.12 4,252.56
600 x 450mm type C1 signs fixed with aluminium
clips to existing post4 no 39.87 159.48
Allowance for two post signs; sign >6m² with
aluminium clips, two 40mm dia. 4.0m long
aluminium post
2 no 1,693.34 3,386.68
Allowance for two post signs; sign 4-6m² with
aluminium clips, two 40mm dia. 4.0m long
aluminium post
4 no 1,544.95 6,179.80
Allowance for Permanent Bollards Solar
Illuminated24 no 600.00 14,400.00
Road Markings
Continuous line in white thermoplastic screed with
applied solid glass beads, 200mm wide. As
TSRGD Diagram No. 1001
466 m 1.34 624.68
Intermittent line in white thermoplastic screed with
applied solid glass beads, 100mm wide with
4000mm line and 2000mm gap. As TSRGD
Diagram No. 1004
2,154 m 0.89 1,917.23
Roundabout Junction lines As TSRGD Diagram
No. 1003.1142 m 1.55 220.10
Give Way Triangle 3.75m As TSRGD Diagram
No.10231 no 16.59 16.59
Keep left direction arrows As TSRGD Diagram
No.10144 no 26.21 104.84
200 mm wide with 600 mm line and 0.30 m gap
TSRGD Diagram No. 1008755 m 1.55 1,169.55
Date: Q1 2017 - 18/04/2017
Drawing Reference: 70028324-101-103
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Ref Item Description Quantity Unit Rate Total
Date: Q1 2017 - 18/04/2017
Drawing Reference: 70028324-101-103
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Double Give way lines - TSRGD 1003 6 m 1.55 9.30
Single give way line - TSRGD 1009 8 m 1.14 8.89
Reflecting road studs 140x254mm rectangular bi-
directional reflecting road stud with white catseye
reflectors
103 no 16.05 1,653.15
Series 1200 Total £36,311.09
Ref Item Description Quantity Unit Rate Total
Series 1300: Road Lighting Columns and
Brackets, CCTV Masts and Cantilever Masts
Steel road lighting column of 10m nominal height
with flange plate base and with single bracket arm
having a projection of 2.0m incorporating a 250W
SON (P426) lantern; to suit 8 m, 10 m and 12 mcolumns 142 no 1,683.84 239,105.28
Steel road lighting column of 8m nominal height
with flange plate base and with single bracket arm
having a projection of 1.5m incorporating a 250W
SON (P426) lantern; to suit 8 m, 10 m and 12 mcolumns 20 no 1,470.91 29,418.20
Allowance for electrical connections 1 no 50,000.00 50,000.00
Series 1300 Total £318,523.48
Date: Q1 2017 - 18/04/2017
Drawing Reference: 70028324-101-103
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Ref Item Description Quantity Unit Rate Total
Series 1700: Structural Concrete
In Situ Concrete
In situ grade C30/20 for sign posts. Bases,
footings, pile caps and ground beams; thickness
300-500mm 2.889 m³ 119.22 344.43
In situ grade C30/20 for sign posts. Bases,
footings, pile caps and ground beams; thickness
exceeding 500mm 4.680 m³ 117.52 549.99
Series 1300 Total £894.42
Project Number: 70028324
Bill of Quantities: Preliminary Design
Project Title: T5070-006 Launceston Southern Loop Road
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Ref Item Description Quantity Unit Rate Total
Series 2700: Accommodation Works, Works
For Statutory Undertakers
BT 1 no 75,283.09 75,283.09
WPD 1 no 640,000.00 640,000.00
W&W 1 no 0.00 0.00
SWW 1 no 0.00 0.00
Series 2700 Total £715,283.09
Project Number: 70028324
Bill of Quantities: Preliminary Design
Project Title: T5070-006 Launceston Southern Loop Road
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Ref Item Description Quantity Unit Rate Total
Series 3000: Landscaping and Ecology
Seeding and Turfing
Wild flower seeding; Wild Flora mixture BSH ref
WF1 combined with Low maintenance
conservation grass BSH ref A4 (20%:80%); at a
rate of 80 g/m2; by conventional sowing at 10° or
less to the horizontal 4,534 m2
0.91 4125.94
Planting
Excavate trench by machine for hedge and
deposit soil alongside trench, 300 wide × 300 mm
deep 2,300 m 2.77 6371.00
Supply and plant hedging plants; backfill with
excavated topsoil, single row plants at 500 mm
centres 2,300 m 4.45 10235.00
Seeding and Turfing
Grass seeding; by conventional sowing at 10o or
less to the horizontal 13,404 m² 0.77 10320.97
Soakaway/Attenuation Feature
Grass seeding; by conventional sowing at 10o or
less to the horizontal 4,876 m² 0.77 3754.52
Series 3000 Total £34,807.43
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Rates used have been taken from Spon's Civil Engineering & Highway Works Price Book 2015
29th Edition
Assumptions
General
Optimism Bias taken from Green Book Supplementary Guidance, Table 1 Recommended Adjustment Rates -
Standard Civil Engineering Project
Assumed that land costs will be 0 as all land will be provided by developers
200 Series
Timber post & Four rail fence : Fence runs parallel to hedge line. No item exist for timber post - Chain link with
one wire string.
Dry stone boundary wall: Assume 1.5mx1.5m wide stone boundary wall
Gully grating & frame: No tip off site used higher rate i.e Re-use
Assumed that site clearance for Ch 400-510 will be undertaken during works for Ch0-400
Assumed that site clearance for Ch 1825-2200 will be undertaken during works for A388 Roundabout
300 Series
Timber fencing to be used to delineate boundary of highway land and fields
400 Series
Vehicle restraint barrier to be used where the proposed road crosses the watercourse. The VRS is to span in this
area for the duration of the steep earthworks.
500 Series
A price for a polypropylene pipe was not available, hence the price for a vertified clay play was used.
Valve chamber includes a price for the chamber (labour, plant and material) and valve (material only) combined.
Price build up for drain pipe includes trench construction to a chosen depth, as well as bedding and surround
material.
An average of 8m lengths have been used for the 150mm dia. gully connections.
There is no specified price within SPONS for a complex control chamber, therefore the cost has been accounted
for by utilising a 2.4m dia. chamber and two penstocks.
Assumed that carrier drainage for Ch 400-510 will be undertaken during works for Ch0-400
Assumed that carrier drainage for Ch 1825-2200 will be undertaken during works for A388 Roundabout
600 Series
Excavation of the Class 5A material is assumed to be 300mm.
It is assumed that 75% of the excavated non-class 5A material is acceptable as fill material
It is assumed that 70% of the excavated class 5A material is acceptable as fill material
It is assumed that where the existing highway is made redundant and will be in the verge , it will be perforated
ready for topsoiling.
The class 6F capping layer has been given a 200mm overspill each side of the pavement.
The capping layer assumed to be150mm thick for 75% of the site and 350mm thick for the remaining 25%
The waste disposed from site is assumed to go to the landfill in Vidor Lean Quarry, Liskeard. Using A roads to the
site this distance is 57km from the scheme.
Due to no price being available for the bentonite liner of the pond, the cost has been accounted for by using a
precast concrete lining.
Assumed that earthworks exc capping for Ch 400-510 will be undertaken during works for Ch0-400
Assumed that earthworks exc capping for Ch 1825-2200 will be undertaken during works for A388 Roundabout
700 Series
It is assumed that the access track for the ponds is to be made using a 300mm dp sub-base construction.
Project Title: T5070-006 Launceston Southern Loop Road
Project Number: 70028324
Bill of Quantities: Preliminary Design
Drawing Reference: 70028324-101-103
Date: Q1 2017 - 18/04/2017
Rates used have been taken from Spon's Civil Engineering & Highway Works Price Book 2015
29th Edition
AssumptionsThe pavement construction for a 40mm surface and 60mm binder course was not available for pricing within
SPONS thus 50mm layers were used for both suface and binder courses.
1100 Series
Traffic islands to consist of 4 quadrants
The footpath surfacing in line with CC HCD 11/107 should have a 60mm binder and 25mm surface course. As no
price exists within SPONS for this construction, a 40mm binder and 20mm surface courses has been used.
1200 Series
Traffic signs accounted for are flags on traffic islands at the roundabouts, repeating footway/cycleway signs @
183m c/c and also on the A388, roundabout advance direction signs and new roundabout ahead signs
Two bollards assumed per roundaboy
New roundabout signs assumed to fix on post of roundabout advanced direction sign.
Road studs to tie into existing A388 road along with double solid white lines
Existing junction will be repainted this includes, give way triangle, double give way lines and a give way line.
4 Deflection arrows have been used within Ch960 - 1820, due to two hazardous areas within this section. These
are on the approach to the roundabout and on the approach to the bend.
1300 Series
Street lighting assumed to be placed at 30m intervals on both sides of the carriageway.
Street lighting columns assumed to be 10m nominal height for the new loop road and have a 8m height where the
new road intercept the existing on both Landlake and Hurdon Road.
1700 Series
Footway/cycleway and speed limit signs assumed to have 300mmx300mmx650mmdp foundations
Flags on roundabouts assumed to have 1000mmx650mmx600mmdp foundations
Advance direction signs assumed to have 350mmx350mmx1800mmdp foundations
3000 Series
Rates for Wild Flora seeding seems high therefore have used Hydraulic mulch seed rate used i
Assumed that the northen verge will be planted with hedging plantsAssumed that the southern verge will have wild flora seeding
Footway
Traffic Island
Uncontrolled Buff Tactile
Verge
Embankment Slope
Cutting Slope
Buff Strip
1 2
3
NOTES:
1. All dimensions are in metres unless otherwise stated.
2. Do not scale from this drawing.
3. The information contained in this drawing has been
reproduced from plans which have no guarantee or
warranty as to their correctness or accuracy.
Therefore information should be used as a general
guide only.
KEY:
This drawing is Copyright. It should not be relied on
or used in circumstances other than those for which it
was originally prepared and for which Cornwall Council
was originally commissioned. Cornwall Council accepts
no responsibility for this drawing to any party other than
the person(s) by whom it was commissioned.
REV DATE NATURE OF REVISION
REVISIONS
- FIRST ISSUE
SOLUTIONS
Filename: \\uk.wspgroup.com\central Data\Projects\700283xx\70028324 - Launceston Loop Road\E Models And Drawings\ACAD\Working\70028324-0101.dwgPlot Date: 18.02.16
DRAWING NO: REVISION:
SCALE:
DRAWN BY:
CHECKED: APPROVED:
PROJECT MANAGER:
DRAWING TITLE:
PROJECT:
T5070-006
LAUNCESTON SOUTHERN LOOP
ROAD
GENERAL ARRANGEMENT
SHEET 1 OF 3
1:1000 @ A1
TP SB
TP 06/04/17 TP 06/04/17
70028324-0101 A
23/03/17
A 06/04/17DRAINAGE PONDS ADDED
Crown copyright and database rights 2017 Ordnance Survey 100049047.
1 2
3
Footway
Traffic Island
Uncontrolled Buff Tactile
Verge
Embankment Slope
Cutting Slope
Buff Strip
NOTES:
1. All dimensions are in metres unless otherwise stated.
2. Do not scale from this drawing.
3. The information contained in this drawing has been
reproduced from plans which have no guarantee or
warranty as to their correctness or accuracy.
Therefore information should be used as a general
guide only.
KEY:
This drawing is Copyright. It should not be relied on
or used in circumstances other than those for which it
was originally prepared and for which Cornwall Council
was originally commissioned. Cornwall Council accepts
no responsibility for this drawing to any party other than
the person(s) by whom it was commissioned.
REV DATE NATURE OF REVISION
REVISIONS
- FIRST ISSUE
SOLUTIONS
Filename: \\uk.wspgroup.com\central Data\Projects\700283xx\70028324 - Launceston Loop Road\E Models And Drawings\ACAD\Working\70028324-0102.dwgPlot Date: 18.02.16
DRAWING NO: REVISION:
SCALE:
DRAWN BY:
CHECKED: APPROVED:
PROJECT MANAGER:
DRAWING TITLE:
PROJECT:
T5070-006
LAUNCESTON SOUTHERN LOOP
ROAD
GENERAL ARRANGEMENT
SHEET 2 OF 3
1:1000 @ A1
TP SB
TP 06/04/17 TP 23/03/17
70028324-0102 -
23/03/17
A 06/04/17DRAINAGE PONDS ADDED
Crown copyright and database rights 2017 Ordnance Survey 100049047.
1 2
3
Footway
Traffic Island
Uncontrolled Buff Tactile
Verge
Embankment Slope
Cutting Slope
Buff Strip
NOTES:
1. All dimensions are in metres unless otherwise stated.
2. Do not scale from this drawing.
3. The information contained in this drawing has been
reproduced from plans which have no guarantee or
warranty as to their correctness or accuracy.
Therefore information should be used as a general
guide only.
KEY:
This drawing is Copyright. It should not be relied on
or used in circumstances other than those for which it
was originally prepared and for which Cornwall Council
was originally commissioned. Cornwall Council accepts
no responsibility for this drawing to any party other than
the person(s) by whom it was commissioned.
REV DATE NATURE OF REVISION
REVISIONS
- FIRST ISSUE
SOLUTIONS
Filename: \\uk.wspgroup.com\central Data\Projects\700283xx\70028324 - Launceston Loop Road\E Models And Drawings\ACAD\Working\70028324-0103.dwgPlot Date: 18.02.16
DRAWING NO: REVISION:
SCALE:
DRAWN BY:
CHECKED: APPROVED:
PROJECT MANAGER:
DRAWING TITLE:
PROJECT:
T5070-006
LAUNCESTON SOUTHERN LOOP
ROAD
GENERAL ARRANGEMENT
SHEET 3 OF 3
1:1000 @ A1
TP SB
TP 06/04/17 TP 06/04/17
70028324-0103 -
23/03/17
A 06/04/17DRAINAGE PONDS ADDED
Crown copyright and database rights 2017 Ordnance Survey 100049047.