Facilities Update
(as required by Policy 4:150 – Facility Management and Building Programs)
May 13, 2019
Presentation Overview
2
• Deferred Maintenance Plan (9/4/18)
• Our Buildings – Another Year Older
• FY19 Construction Timeline
• Facility UpdatesRoofing
Elementary Air Conditioning
Wheatland Academy
Crouse Education Center
Energy Management Initiatives• Next Steps
Goal for Deferred Maintenance Plan
3
• Reduce deferred maintenance projects as fast as possible• Focus on building envelope, heating/cooling, and safety
• Ensure quality work through manageable pace • Proactively maintaining existing projects• Use available resources from
• Capital Outlay Account• Developer Contributions
• Sale of Property• Prior Year Fund Balance
Buildings Another Year Older
4
2018-19 School Year:
20 Years:
GombertKendall
Crouse Education Center
2019-20 School Year:
90 Years:
Indian Plains
40 Years:
Clow
30 Years
McCartySpring Brook
20 Years:
Builta WelchYoung Still
10 Years:
Metea Valley
Projects Start Date
Substantial Completion
Phase IV – Elementary A. C. Special 10/1/17 8/10/18
Flat Roof Replacement @ Graham Scheduled 6/12/18 8/10/18
2018 Masonry Restoration @ 3 Schools Scheduled 6/12/18 8/10/18
2018 Hardscape Projects @ 6 Schools Scheduled 6/12/18 8/10/18
Vinyl tile replacement @ WVHS Scheduled 6/12/18 8/10/18
Cabling & Security Camera replacement @ NVHS & WVHS
Scheduled 3/1/18 10/1/18
Varsity Softball Fence Replacement @ WVHS Scheduled 12/1/18 3/1/19
Phase V – Elementary A. C. Special 12/1/18 8/2/19
BAS Replacement @ Birkett Deferred 2/20/19 6/30/19
FY 19 Construction Timeline
5
Projects Start Date
Substantial Completion
Classroom Lock Modifications @ 34 Schools Special 5/14/19 9/27/19
Asphalt Repair @ Wheatland Scheduled 5/27/19 8/2/19
Resilient Gym Floor Installation @ Wheatland Scheduled 5/27/19 8/2/19
Upgrade Fire alarm @ White Eagle Deferred 6/10/19 6/30/19
Slope roof replacement @ Fischer & Graham Deferred 6/10/19 8/3/19
2019 Hardscape Projects @ 4 Schools Deferred 6/10/19 8/3/19
2019 Masonry Restoration @ Fischer & 7 Schools Deferred 6/10/19 8/3/19
Gym Flooring & Bleacher Improvements @ WVHS Deferred 5/28/19 8/12/19
FY 19 Construction Timeline
6
Varsity Softball Field Fence at WVHS
7
Roof Expenses
8
$705,200
$592,500
$399,869
$641,200
$786,459
$1,478,800
$424,686
$547,500
$1,919,885
$1,811,868
$137,894
$223,620
$127,911
$102,214
$205,455
$126,867
$208,415
$0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
EMG yearly Ave.
Roof Repairs Roofing Replacement
Flat Roof Repairs/Replacement
9
Elementary Air Conditioning
10
• Began installing air conditioning in phases 5 years ago• Funding from delayed state payments• By August 2019 the project will have installed air conditioning in all of our large elementary
classrooms• $3.3 million needed to complete finish the project (LMC area)
BrookdaleBrooks
Wheatland Academy
11
• South classrooms have been painted
• MPR and new staff offices constructed in lower level
• Gym Renovation has begun (8/1/19 completion date)
• North classrooms & Organic Life offices (8/5/19 completion date)
Wheatland Academy
South Classroom South Classroom Hallway
12
Wheatland Academy
Lower Level Offices Gym Painting Begins
13
CROUSE EDUCATION CENTER
14
Energy Management Initiatives
• 1st year participation in the EnerNOC Demand Response
Incentive Program (ComEd territory only) results in the district
receiving $52,600. This year anticipate receiving over
$72,000. (Fischer, Granger, Still, MVHS & WVHS)
• Transitioning outside lighting to LED.
• Evaluating a proposal for installation of solar panels at MVHS.
(Power Purchase Agreement)
15
Next Steps
• Prioritize capital improvement and other district needs based on the following hierarchy:
1. Safety Related Items
2. Approved Curriculum Related needs
3. Necessary Repairs
4. State required Life Safety Projects (building code changes)
5. Aesthetic
• Explore grant and other cost savings opportunities
16