Facilities Project Management Monthly Report by Building Monday, March 1, 2021 131 Approved Project PROJECT TITLE PM Accountable Project Code Project Number: 1 Leavitt Lane Projects in Building 1 1 Leavitt Lane Convert boiler to natural gas 1.1PLAN/EST RR GEUTHER, MARK E 02242021: Project newly reassigned to me. Getting up to speed. Design Firm: OPA Contractor: Contractor Name: 20200055 Year Approved: 18 Waterworks Road Projects in Building 1 18 Waterworks Road Install 2 monitors connected to the UNH system 1.1PLAN/EST FCR PETERS, NICK E 26 Feb 2021 Permits received. Receiving materials first week fo March. Scheduling install dates upon arrival. Design Firm: N/A Contractor: External Contractor Name: Various 20200170 Year Approved: 2021 2 Leavitt Lane Projects in Building 1 2 Leavitt Lane new natural gas boiler 1.1PLAN/EST RR GEUTHER, MARK E 02242021: Project newly reassigned to me. Getting up to speed. Design Firm: Oak Point Assoc. Contractor: External Contractor Name: TBD 20200054 Year Approved: 6 Leavitt Lane Projects in Building 1 6 Leavitt Lane New Gas Line and Boiler 1.1PLAN/EST RR GEUTHER, MARK E 02242021: Project newly reassigned to me. Getting up to speed. Design Firm: OPA Contractor: Contractor Name: 20200056 Year Approved: 88 Commercial Street Projects in Building 1 Monday, March 1, 2021 Page 1 of 26 University of New Hampshire Facilities Project Management
Transcript
Page 1: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

Facilities Project Management Monthly Report by Building

Monday, March 1, 2021 131Approved Project

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

1 Leavitt Lane Projects in Building 1

1 Leavitt Lane ‐ Convert boiler to natural gas

1.1‐ PLAN/EST

RRGEUTHER, MARK E

02‐24‐2021: Project newly reassigned to me. Getting up to speed.

Design Firm: OPA Contractor: Contractor Name:

2020‐0055

Year Approved:

18 Waterworks Road Projects in Building 1

18 Waterworks Road ‐ Install 2 monitors connected to the UNH system

1.1‐ PLAN/EST

FCRPETERS, NICK E

26 Feb 2021 ‐ Permits received.  Receiving materials first week fo March.  Scheduling install dates 

upon arrival.

Design Firm: N/A Contractor: External Contractor Name: Various

2020‐0170

Year Approved: 2021

2 Leavitt Lane Projects in Building 1

2 Leavitt Lane ‐ new natural gas boiler

1.1‐ PLAN/EST

RRGEUTHER, MARK E

02‐24‐2021: Project newly reassigned to me. Getting up to speed.

Design Firm: Oak Point Assoc. Contractor: External Contractor Name: TBD

2020‐0054

Year Approved:

6 Leavitt Lane Projects in Building 1

6 Leavitt Lane ‐ New Gas Line and Boiler

1.1‐ PLAN/EST

RRGEUTHER, MARK E

02‐24‐2021: Project newly reassigned to me. Getting up to speed.

Design Firm: OPA Contractor: Contractor Name:

2020‐0056

Year Approved:

88 Commercial Street Projects in Building 1

Monday, March 1, 2021 Page 1 of 26University of New Hampshire

Facilities Project Management

Page 2: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

88 Commercial Street ‐ UNH Manchester ‐ Bio‐Manufacturing Innovation Center 

Tenant fit‐out

3.1‐ SUBSTANTIAL COMPLETION

FCRROULEAU, RICHARD A

2/26/2021 ‐ Working with Control Tech, Inc. and UNH IT to set up a virtual server for HVAC 

controls associated with the 6th floor and the 5th floor lab block.  Working with Milestone, 

Granite State Plumbing & Heating and Control Tech on adding one oxygen sensor and installing 

remote alarms for both oxygen sensors.  Otherwise, project is complete.  Use and occupancy of 

the space is increasing.  Lab is being used for COVID testing for UNH Manchester and UNH Law 

School.

Design Firm: John Jordan Contractor: External  Contractor Name: by landlord (using Milestone)

2018‐0210

Year Approved: 2019

Adams Tower Projects in Building 2

Adams Tower West ‐ Major AC System Repairs

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021: Project approved. Work to be scheduled after commencement.

Design Firm: N/A Contractor: External Contractor Name: Carrier

2021‐0083

Year Approved:

Adams Tower ‐ Verizon Wireless Antenna Upgrade

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

3‐2‐21 Version not ready for installation, will have to wait until after commencement.

Design Firm: Contractor: External Contractor Name: Verizon

2018‐0310

Year Approved: 2018

Babcock Hall Projects in Building 2

Babcock Hall ‐ Roof Access Hatch

2‐ IN DESIGN

FCRPETERS, NICK E

26 Feb  2021.  Issues with COVID testing has pushed contractors from the project.  Site conditions 

re‐evaluated, and determined the hatch will operate as functioned until summer.

Design Firm: N/A Contractor: External Contractor Name: Skyline Roofing

2021‐0090

Year Approved:

Babcock Hall ‐ Adams Tower ‐ Electrical Investigation COVID Preparation

3.1‐ SUBSTANTIAL COMPLETION

FCRWEBBER, TODD M

Investigation is complete, no instruction to move forward with the proposed work at this time.

Design Firm: Contractor: Contractor Name:

2021‐0001

Year Approved:

Barton Hall & Cole Hall Projects in Building 4

Monday, March 1, 2021 Page 2 of 26University of New Hampshire

Facilities Project Management

Page 3: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Barton Hall ‐ 2nd Floor Reno for Diagnostic Labs

2‐ IN DESIGN

SIMANCINI, MATTHEW E

3/1/2021: Design effort under way. Early permit review has begun to address egress. 

Construction Documents expected by April/May 2021.

Design Firm: H.L. Turner Group Contractor: External Contractor Name:

2020‐0091

Year Approved: 2020

Barton Hall ‐ Utility Distribution ‐ Transformer Replacement

2.5‐ IN PROCUREMENT

RRHEALEY, SCOTT M

1‐29‐21 ‐ Transformer should arrive in the middle of March, and need to be installed before June.

Ordered 10‐20 ‐ 23 week lead time.

Design Firm: Contractor: External Contractor Name: IC Reed

2021‐0040

Year Approved: 2021

Cole Hall ‐ Instructional Space Improvements

3.1‐ SUBSTANTIAL COMPLETION

SIMANCINI, MATTHEW E

3/1/2021: Project is substantially complete. HVAC scope will be deferred.

Design Firm: John L Turner Contractor: External Contractor Name: Multiple

2020‐0092

Year Approved: 2020

Barton Hall & Cole Hall ‐ Bus Shelter Install

3.1‐ SUBSTANTIAL COMPLETION

FCRRINES, DANIEL M

2‐24‐21: Project is substancially complete.

Design Firm: Contractor: External Contractor Name: T&S

2021‐0041

Year Approved:

Campus Projects in Building 9

FY21 Campus Envelope and Interior Painting

1.1‐ PLAN/EST

RRWEBBER, TODD M

Design Firm: N/A Contractor: FCT Contractor Name:

2019‐0369

Year Approved: 2021

Multi Housing Building‐ Hydration Station Installs

1.1‐ PLAN/EST

FCRPETERS, NICK E

26 Feb 2021 ‐ Received proposal from consultants and contractors.  Awaiting approval for 

funding.

Design Firm: McHenry Architecture Contractor: External Contractor Name: Charters Brothers

2021‐0084

Year Approved: 2021

Monday, March 1, 2021 Page 3 of 26University of New Hampshire

Facilities Project Management

Page 4: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Campus ‐ Parking Lot ‐ Sage Way Visitor Lot ‐ Parking Spot & Drop Box

1.1‐ PLAN/EST

FCRHENRY, PAUL A

3‐2‐21 Looking for more information

Design Firm: Contractor: Contractor Name:

2021‐0064

Year Approved:

Campus ‐ Bus Shelter Solar Lighting Upgrades

1.1‐ PLAN/EST

FCRPETERS, NICK E

26 Feb 2021 ‐ Initial expected contractor does not provide the services requested anymore.  

Soliciting to other product manufacturers to locate a source to submit for grant funding.

Design Firm: Contractor: Contractor Name:

2021‐0092

Year Approved:

Campus Wide ‐ OBA COVID Barrier Installations

3‐ IN CONSTRUCTION

FCRPETERS, NICK E

26 Feb 2021 ‐ OBA barriers installed.  Broken barriers found in Stillings and Philbrook, and to be 

repaired through contractor.  Another order to be placed to accommodate winter weather and 

expanded dining requirements.

Design Firm: N/A Contractor: External Contractor Name: Milestone / WB Mason / Malthouse

2021‐0008

Year Approved: 2021

Campus Wide ‐ Academic / E&G Hydration Stations

3‐ IN CONSTRUCTION

FCRPETERS, NICK E

28 Feb 2021 ‐Preliminary construction complete campus‐wide.  Awaiting arrival of water bottle 

fill stations.

Design Firm: N/A Contractor: External Contractor Name: Milestone / Charters Brothers

2021‐0009

Year Approved: 2021

Campus ‐ Main Street Paving and Crosswalks

3‐ IN CONSTRUCTION

FCRRINES, DANIEL M

2‐24‐21: Project is via the TOD contract with Continental. Main Street Paving will take place after 

South sidewalk road impacts are complete,continental and the town planning early June for 

paving to begin.

Design Firm: Contractor: Contractor Name: continental

2020‐0276

Year Approved: 2021

Campus – High Voltage Monitoring Sensor Installation

3‐ IN CONSTRUCTION

SIHOUDE, DONALD A

02‐19‐21 All 11 monitors and the 1 gateway are installed with satisfactory signal strength. I will 

log in all locations and plot on a UNH Map for the record.

Design Firm: Contractor: Contractor Name:

2021‐0024

Year Approved: 2021

Monday, March 1, 2021 Page 4 of 26University of New Hampshire

Facilities Project Management

Page 5: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Campus Wide ‐ Academic/E&G COVID Barrier Installations

3‐ IN CONSTRUCTION

FCRPETERS, NICK E

28 Feb 2021 ‐Shields have been installed through‐out Durham, Manchester, and Concord 

campuses.

Design Firm: Contractor: External Contractor Name: WB Mason, Milestone,

2020‐0279

Year Approved: 2020

Chase Ocean Engineering Laboratory Projects in Building 1

Chase Ocean Engineering Laboratory ‐ Rm S210 HVAC Recommendations and Repair

2‐ IN DESIGN

FCRROULEAU, RICHARD A

2/26/2021 ‐ Final review documents received and review is nearly complete.  Construction 

estimate received.  FCR to be prepared and forwarded to the customer, who has indicated that 

they intend to proceed.  Due to the fact that we are nearly into heating season, the intent is to 

replace RTU‐2 with a smaller unit next cooling season.  New RTU will be 100% recirc except 

when economizing, able to stage and will have reheat.  Energy Office put in place a temporary 

solution for this summer making RTU‐1 primary for the server room and RTU‐2 secondary 

during unit swap out.

Design Firm: H.L. Turner Group Contractor: External Contractor Name: TBD

2020‐0149

Year Approved: 2020

Child Study & Development Center Projects in Building 2

Child Study & Development Center ‐ Decks

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021: Waiting for estimate

Design Firm: Contractor: External Contractor Name: TBD

2020‐0250

Year Approved:

Child Study & Development Center ‐ Playground Repairs

3‐ IN CONSTRUCTION

FCRGEUTHER, MARK E

02‐24‐2021: On site construction has stopped until Spring 2021. Deck building will take place off 

site.

Design Firm: Ironwood Contractor: External Contractor Name: T&S Construction

2020‐0173

Year Approved: 2020

Christensen Hall Projects in Building 1

Christensen Hall ‐ T‐Mobile Antenna Upgrades ‐

1.1‐ PLAN/EST

FCRPETERS, NICK E

26 Feb 2021 ‐ Construction documents received and preparing permit applications.  EME or RF 

study requested from contractor.

Design Firm: Contractor: Contractor Name:

2021‐0093

Year Approved: 2021

Dimond Library Projects in Building 2

Monday, March 1, 2021 Page 5 of 26University of New Hampshire

Facilities Project Management

Page 6: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Dimond Library ‐ Interior Heating Distribution ‐ Design Only

2‐ IN DESIGN

RRMANCINI, MATTHEW E

3/1/2021: Wrapping up final design and material considerations. Construction Documents 

expected in April 2021.

Design Firm: Harriman Contractor: External Contractor Name:

2010‐0281

Year Approved: 2021

Dimond Library ‐  Minor Modifications to Shelving/Floor 301

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

3‐2‐21 going to remove shelving and paint room with gift funds

Design Firm: Contractor: Contractor Name:

2021‐0029

Year Approved:

Field House Projects in Building 7

Field House ‐ Indoor Pool North Wall Investigation

1.1‐ PLAN/EST

RR

Emergency Repair

RINES, DANIEL M

2‐24‐21: 

Project assigned, Pm to work with stakeholders to identify the trouble areas, and begin 

investigation with term structural firm.

Design Firm: Contractor: Contractor Name:

2021‐0101

Year Approved: 2021

Field House ‐ Glass Wall, Outdoor Deck/Roof and Door Replacement Design Only

2‐ IN DESIGN

RRGEUTHER, MARK E

02‐24‐2021: Preliminary to be reviewed by UNH. Goal is to have the design and cost estimate 

completed by the end of June. Construction planned FYʹ23.

Design Firm: LaVallee Brensinger Contractor: External Contractor Name: TBD

2013‐1044

Year Approved: 2021

Field House ‐ Pool Chemical Storage  ‐ Design Only

2‐ IN DESIGN

RRGEUTHER, MARK E

02‐24‐2021: Design is continuing.

Design Firm: Weston & Sampson Contractor: External Contractor Name: TBD

2020‐0181

Year Approved: 2020

Field House ‐ Indoor Pool Crack Repairs

3‐ IN CONSTRUCTION

RR

Emergency Repair

RINES, DANIEL M

2‐24‐21: Cracks  temporarily repaired so pool can be filled, AM to allocated funds for future long 

term repair.

Design Firm: Contractor: External Contractor Name: Guarinos Swimming pool service

2021‐0091

Year Approved: 2021

Monday, March 1, 2021 Page 6 of 26University of New Hampshire

Facilities Project Management

Page 7: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Field House ‐ UV Filter Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRGEUTHER, MARK E

02‐24‐2021: Working on close out documentation.

Design Firm: Weston & Sampson Contractor: External Contractor Name: Charters Brothers

2019‐0306

Year Approved: 2019

Field House ‐ 1st Floor AC Installation

3.1‐ SUBSTANTIAL COMPLETION

SIGEUTHER, MARK E

02‐24‐2021: Substantially Complete. Working on close out.

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

2011‐0653

Year Approved: 2019

Field House ‐ Indoor Pool Concrete Repairs

3.1‐ SUBSTANTIAL COMPLETION

RRRINES, DANIEL M

2‐24‐21: Work is sunbstancially complete. Campus Rec has added scope for pool maintinance 

items, which have been completed, few minor concrete fixes needed for punclist.then closeout.

Design Firm: Hoyle Tanner Contractor: External Contractor Name: Structural Preservation Systems

2020‐0129

Year Approved: 2021

Future Design and Planning Projects in Building 1

Health Sciences Initiative CHHS Building

3‐ IN CONSTRUCTION

FCRHEISNER, MICHELE

02/24/21 ‐  Simulation wing exterior framed, slab on grade first week of March; office wing 

exterior framed. Project scheduled to be complete 8/2021

Design Firm: LVBPA‐DB Contractor: External  Contractor Name: Wright Ryan

2020‐0231

Year Approved: 2020

Gregg Hall Projects in Building 2

Gregg Hall ‐ Boiler Plant Replacement

1‐ ASSIGNED

RRROULEAU, RICHARD A

Design Firm: Contractor: Contractor Name:

2018‐0254

Year Approved: 2022

Monday, March 1, 2021 Page 7 of 26University of New Hampshire

Facilities Project Management

Page 8: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Gregg Hall‐ Rm 337‐ Expanded COVID Testing Lab

3.1‐ SUBSTANTIAL COMPLETION

FCRHENRY, PAUL A

3‐2‐2 Lab is substancilly complete, occupants moviing and testing equipment, lab team is still 

waiting for some qupipment pror to operation. There is always some small issues to solve prior 

to going live.

Design Firm: Harriman Contractor: External Contractor Name: Charter Brothers

2021‐0081

Year Approved:

Haaland Hall Projects in Building 1

Haaland Hall – PVI Tank Replacement

3‐ IN CONSTRUCTION

FCRRINES, DANIEL M

2‐24‐21: Tank has been installed, Same issues with original flue and chimney as Handler Hall 

project cited by SFMO. PM working on solutions.

Design Firm: Harriman Contractor: External Contractor Name: United Mechanical

2020‐0253

Year Approved: 2020

Hamel Recreation Center Projects in Building 1

Hamel Recreation Center ‐ Covid‐19 Surge Facility

1.1‐ PLAN/EST

FCRRINES, DANIEL M

2‐24‐21:Site has been demobilized, but may need to be reopened in short notice.

Design Firm: Contractor: Contractor Name:

2020‐0245

Year Approved: 2020

Hamilton Smith Hall Projects in Building 2

Hamilton Smith Hall ‐ Bi‐Directional Amplifier Installation

1‐ ASSIGNED

SIROULEAU, RICHARD A

Design Firm: Norris Inc. Contractor: External Contractor Name: Norris Inc.

2016‐0116

Year Approved: 2021

Monday, March 1, 2021 Page 8 of 26University of New Hampshire

Facilities Project Management

Page 9: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Hamilton Smith Hall ‐ Rms G13, G15 Water Infiltration Investigation and Repair

1.1‐ PLAN/EST

FCRROULEAU, RICHARD A

2/26/2021 ‐ T&S Construction to develop budgetary construction estimate for UNH planning 

purposes. ‐ ON HOLD ‐ During recent heavy rain, it was confirmed that water is percolating up 

between the foundation wall and the floor slab.  This suggests too much water is coming off the 

roof for the perimeter drain to handle resulting in hydrostatic pressure pushing water under the 

foundation wall and/or footing and up between the wall and slab.  While this could possibly be 

considered a design error, it does not suggest improper construction by the original contractor.  

Logical solution is to intercept and divert roof run‐off rather than trying to upsize existing 

perimeter drain, which may not solve the underlying problem of simply too much water.  A 

solution is to line the perimeter drain with waterproof membrane and drain the resulting bathtub 

to an adjacent storm drain manhole.  This is the same approach used at Taylor Hall several years 

ago.  Reached out to term civil engineer Hoyle Tanner & Associates and received a proposal.  

However, project is on hold due to the Universityʹs cash flow limitations.

Design Firm: Contractor: External Contractor Name: tbd

2020‐0030

Year Approved: 2020

Handler Hall Projects in Building 1

Handler Hall ‐ Replacement of PVI Hot Water Tanks

3‐ IN CONSTRUCTION

FCRRINES, DANIEL M

2/24/21  ‐ Tanks have been installed, currently running on steam only, as SFMO tagged original 

building construction project code violations. PM, NPI and Harriman working on solutions to 

code issues from original construction in conjunction with the SFMO. Sizable remediation project 

planned for this summer.

Design Firm: Harriman Contractor: External Contractor Name: NPI

2019‐0324

Year Approved: 2020

Health & Wellness Building Projects in Building 1

Health & Wellness Building ‐ COVID‐19 Testing Instrumentation

2‐ IN DESIGN

FCRHENRY, PAUL A

3‐2‐21 Have approval for AC in Lab, CB ordering materials, coordinating with lab for installation 

dates, most likely after Gregg Hall Lab is on line.

Design Firm: Contractor: Contractor Name:

2020‐0281

Year Approved: 2020

Hewitt Hall Projects in Building 1

Hewitt Hall ‐ Duel Temperature Mechanical Tie‐In

3.1‐ SUBSTANTIAL COMPLETION

RRRINES, DANIEL M

2‐24‐21: . Commissioning and Balancing complete, minor punchlist, and document closeout 

underway.

Design Firm: Harriman Contractor: External Contractor Name: Anderson Welding

2019‐0338

Year Approved: 2020

Holloway Commons Projects in Building 1

Monday, March 1, 2021 Page 9 of 26University of New Hampshire

Facilities Project Management

Page 10: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Holloway Commons/MUB ‐ Verizon Wireless In‐Building Antenna System

3‐ IN CONSTRUCTION

FCRPETERS, NICK E

26 Feb 2021 ‐ Construction through kitchen complete.  Contractors are continuing with work as 

scheduled.

Design Firm: Verizon Wireless Contractor: Contractor Name: Verizon Wireless

2020‐0267

Year Approved: 2020

Horton Social Science Center Projects in Building 1

Horton Social Science Center ‐ G04 Auditorium – Air Conditioning

3.1‐ SUBSTANTIAL COMPLETION

SIHENRY, PAUL A

3‐2‐21  replaced faulty VFD drives, waiting for final commissioning report.

Design Firm: Harriman Contractor: External Contractor Name: Structuretone

2010‐0411

Year Approved: 2019

James Hall Projects in Building 3

James Hall ‐ Suite 364 Fire Alarm Strobes

1.1‐ PLAN/EST

FCRHEISNER, MICHELE

02/24/21 ‐ Due to the uncertainty and fluctuation of contractor availability and schedule 

constraints related to covid, recommend this work be rescheduled

Design Firm: Contractor: Contractor Name:

2020‐0251

Year Approved:

James Hall ‐ Suite 364 Lab Repairs

1.1‐ PLAN/EST

FCRHEISNER, MICHELE

02/24/21 ‐ Due to the uncertainty and fluctuation of contractor availability and schedule 

constraints related to covid, recommend this work be rescheduled. Cleanroom lab schedules to 

be coordinated with end users.

Design Firm: Contractor: Contractor Name:

2020‐0252

Year Approved:

James Hall ‐ HVAC Modifications Investigation and Design

3.1‐ SUBSTANTIAL COMPLETION

RRROULEAU, RICHARD A

2/26/2021 ‐ No change.  Repairs and adjustment complete.  The Energy Office is addressing 

unrelated hood air flow and hood alarm issues.  They have pulled in Cx Agent I.C.O. for 

assistance.  Once the building has been recommissioned and issues identified have been 

corrected, we will run the kiln and, hopefully, confirm no transfer from the exhaust air stream to 

the intake/supply air.  Failing that, the correct solution and what probably should have been 

done originally will be a dedicated hood exhaust.

Design Firm: Contractor: Contractor Name:

2018‐0270

Year Approved: 2018

Kendall Hall Projects in Building 5

Monday, March 1, 2021 Page 10 of 26University of New Hampshire

Facilities Project Management

Page 11: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Kendall Hall ‐ Rms 506 & 506A Improvements rms 506 & 506A

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021 ‐ Space not appropriate for the intended use per SFMO.

Design Firm: Contractor: Contractor Name:

2021‐0094

Year Approved:

Kendall Hall ‐ Rm 517 Improvements

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021: Space not appropriate for the intended use per SFMO. PI might modify his intent, 

waiting to hear.

Design Firm: N/A Contractor: External Contractor Name: TBD

2021‐0095

Year Approved:

Kendall Hall ‐ Rm 409 Sink Installation

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021: Met with client, waiting to hear back on need.

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

2021‐0097

Year Approved:

Kendall Hall ‐ 3rd Floor Repurposing

3.1‐ SUBSTANTIAL COMPLETION

SIGEUTHER, MARK E

02‐24‐2021:  Occupancy approved by SFMO. Working on close out documentation. Hydronic 

balancing ongoing.

Design Firm: Manypenny Murphy Contractor: External Contractor Name: Charters Brothers

2019‐0158

Year Approved: 2019

Kendall Hall ‐ 4th Floor Repurposing

3.1‐ SUBSTANTIAL COMPLETION

SIGEUTHER, MARK E

02‐24‐2021: See 2019‐0158

Design Firm: Manypenny Murphy Contractor: External Contractor Name: Charters Brothers

2019‐0161

Year Approved: 2019

Kingsbury Hall Projects in Building 4

Kingsbury Hall ‐ Room Improvements rm W136

1.1‐ PLAN/EST

FCRMANCINI, MATTHEW E

3/1/2021: Scheduling to meet with stakeholders to define scope and then develop an RFP for 

Term Contractors.

Design Firm: Contractor: Contractor Name:

2021‐0099

Year Approved:

Monday, March 1, 2021 Page 11 of 26University of New Hampshire

Facilities Project Management

Page 12: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Kingsbury Hall ‐ Retro‐Commissioning

3‐ IN CONSTRUCTION

FCRKOHLER, ADAM S

Design Firm: Contractor: Contractor Name:

2020‐0187

Year Approved: 2020

Kingsbury Hall ‐ Compressor and Air Dryer Replacement

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

HENRY, PAUL A

3‐2‐21 New compressor arrived last week, operations starting installation, will veriify with 

oiperations, but believe it is complete.

Design Firm: Contractor: Contractor Name:

2020‐0049

Year Approved: 2021

Kingsbury Hall ‐ Career Services Center

3.1‐ SUBSTANTIAL COMPLETION

FCRPETERS, NICK E

28 Feb 2021 ‐  Tabletops being replaced.  Room Signage being ordered.

Design Firm: Placework Contractor: External Contractor Name: Charter Brothers

2020‐0216

Year Approved: 2020

Leavitt Cntr Transportation Center Projects in Building 2

Leavitt Cntr Transportation Center‐ Installation of Safety Harness System

2‐ IN DESIGN

FCRHENRY, PAUL A

3‐2‐21 Awaitng final design and installation schedule, we has provided some dimention 

verification two weeks ago.

Design Firm: DFP Contractor: External Contractor Name: DDP

2021‐0006

Year Approved: 2021

Leavitt Cntr Transportation Center ‐ Partial EPDM Roof Replacement

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

PETERS, NICK E

27Feb 2021 ‐ Purchase Order issued.  Working with Viking for scheduling.

Design Firm: N/A Contractor: External Contractor Name: Viking

2020‐0287

Year Approved: 2021

Marine Research Facility Projects in Building 1

Monday, March 1, 2021 Page 12 of 26University of New Hampshire

Facilities Project Management

Page 13: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Coastal Marine Lab ‐ Fire Clean‐Up and Repairs

3.1‐ SUBSTANTIAL COMPLETION

FCRROULEAU, RICHARD A

2/26/2021 ‐ No Change ‐ Project suspension due to COVID‐19 said to have been lifted on 4/27; 

however, spending restrictions are preventing this project from moving forward.  Next steps are 

to assemble roofing package for bidding and line up window repairs.

Design Firm: Contractor: External Contractor Name: Careno Construction

2018‐0336

Year Approved: PROJECT SUSPENDED

McGregor Memorial EMS Projects in Building 1

McGregor Memorial EMS ‐ Envelope and Interior Repairs

3‐ IN CONSTRUCTION

RRPETERS, NICK E

26 Feb 2021:  Roofing and exterior water treatment completed.  Abatement completed.  Design 

fees accepted and approved.  Design package received and submitted to contractor.  Awaiting 

proposal.

Design Firm: N/A Contractor: External Contractor Name: Careno Const

2020‐0196

Year Approved: 2021

Memorial Union Building Projects in Building 2

Memorial Union Building ‐ 110 Ton Rooftop Chiller ‐ Design Only

2‐ IN DESIGN

FCRROULEAU, RICHARD A

2/26/2021 ‐ 75% complete review documents from SMRT are in hand for review.  Comments 

received from Adam Kohler and Scott Lindquist.

Design Firm: SMRT Contractor: External Contractor Name: tbd

2021‐0070

Year Approved: 2021

Memorial Union Building ‐ Accessing Systems

3.1‐ SUBSTANTIAL COMPLETION

FCRMANCINI, MATTHEW E

3/1/2021: Project is substantially complete.

Design Firm: Contractor: External Contractor Name: Yates Electric

2021‐0021

Year Approved: 2021

Morse Hall Projects in Building 10

Morse Hall ‐ Rm 331 Renovations

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021: Project approved to move forward. Design kick off meeting scheduled for 02‐25‐2021

Design Firm: Harriman Contractor: External Contractor Name: Milestone

2021‐0022

Year Approved: 2021

Monday, March 1, 2021 Page 13 of 26University of New Hampshire

Facilities Project Management

Page 14: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Morse Hall ‐ Rm 119 Fire Suppression ‐ Self Made Room Fabrications

1.1‐ PLAN/EST

FCRROULEAU, RICHARD A

2/26/2021 ‐ No change since last update.  The EMI/RFI‐sheilded room, which is used for welding, 

was constructed shortly after the original construction due to concerns about electrical issues the 

welding might cause the computers of the mid‐80s.  At this point, they rarely do any welding.  I 

asked Phil Demaine whether it could be removed, which would make the issue go away.  Mr. 

Demaine was to check with his superiors.  I pinged him again via email but still no response.

Design Firm: Contractor: External Contractor Name: Johnson Controls, possibly Norris

2021‐0014

Year Approved:

Morse Hall ‐ Rm A132 Fire Suppression ‐ Self Made Room Fabrications

1.1‐ PLAN/EST

FCRROULEAU, RICHARD A

2/26/2021 ‐ No change since last update.  The chamber is a small constant temperature room.  It 

appears that it may not be in use except maybe for storage.  I have reviewed it with Phil Biron.  It 

will need a sprinkler head, not frost free because researcher Joe Salisbury tells me it does not go 

down below freezing.  Given the room is so small, Phil thinks it unlikely anyone would work 

inside the room and, therefore, it doesnʹt need a fire alarm notification appliance.  I have a price 

from Johnson Controls and can now prepare an FCR.

Design Firm: Contractor: External Contractor Name: Johnson Controls

2021‐0018

Year Approved:

Morse Hall ‐ Rm 249 Fire Suppression ‐ Self Made Room Fabrications

1.1‐ PLAN/EST

FCRROULEAU, RICHARD A

2/26/2021 ‐ No change since last update.  The chamber in this room requires clean room attire.  I 

have received a sketch of the chmber from  Marc Lessard and am waiting for photos and 

response to other questions.  There are two rooms within the chamber.  One is a control room 

and one is an optical calibration room for highly‐sensitive devices used in space.  Sprinkler and 

fire alarm AV notification are required.  Phil Biron suggested an AV in Room 249 itself and 

strobe only devices in the rooms within the chamber.  However, Marc Lessard tells me any 

unplanned light in the enclosure during calibration could damage the equipment being 

calibrated.  Storage on top of the unit is also an issue.  Signage can probably address that issue.  

Once scope is established, I will reach out to term sprinkler and fire alarm contractors for pricing.

Design Firm: Contractor: External Contractor Name: Johnson Controls, Norris

2021‐0019

Year Approved:

Morse Hall ‐ Rm 118 Fire Suppression ‐ Anechoic Chamber

1.1‐ PLAN/EST

FCRROULEAU, RICHARD A

2/26/2021 ‐ No change since last update ‐ Room 118:  This EMI/RFI‐shielded room is an anechoic 

chamber that also needs sprinkler coverage.  Per discussion with Phil Biron (SFMO), it does not 

need a fire alarm notification appliance because no one is ever enclosed in the chamber with the 

door closed as per Nick Kirsh, the researcher responsible for the room,.  There are ports in the 

top of the chamber for sprinkler and there are specialty extending sprinkler heads made by a 

company in Seabrook specifically for this application.  I have spoken with Nick Kirsh and 

requested information on the foam and coating.  I am working with Johnson Controls to get 

pricing for the speciality sprinkler heads.

Design Firm: Contractor: External Contractor Name: Johnson Controls

2021‐0025

Year Approved:

Monday, March 1, 2021 Page 14 of 26University of New Hampshire

Facilities Project Management

Page 15: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Morse Hall ‐ Former Clean Rm Renovation

2‐ IN DESIGN

SIMANCINI, MATTHEW E

3/1/2021: Design is under way to support Spaulding swing space. EOS will be primary occupant 

when finished. Have funding for Design 2021 and Construction FY2022

Design Firm: Harriman Contractor: External Contractor Name: tbd

2020‐0189

Year Approved: 2020

Morse Hall ‐ Rm 419 Adding New Equipment

3‐ IN CONSTRUCTION

FCRHEISNER, MICHELE

02/24/21 ‐  Temporary utility connections made to allow for partial utilization of lab equipment 

and early experimentation for customer to meet early March deadline. Timing of full ʹbuild outʹ 

TBD.

Design Firm: SMRT Contractor: Contractor Name:

2020‐0190

Year Approved: 2020

Morse Hall ‐ Emergency Eyewash Installation

3.1‐ SUBSTANTIAL COMPLETION

FCRPETERS, NICK E

28Feb 2021 ‐ Construction completed.  Working on commissioning and closeout documentation.

Design Firm: N/A Contractor: External Contractor Name: Milestone Eng & Const, Inc

2020‐0150

Year Approved: 2020

Morse Hall ‐ Interior Main Heating Line Connections

3.1‐ SUBSTANTIAL COMPLETION

RRROULEAU, RICHARD A

2/26/2021 ‐ Work is complete.  Final inspection letter received from SFMO.  Once this letter and 

other project documentation is put into Meridian, this project will be complete and ready to be 

closed out.

Design Firm: Harriman Contractor: External Contractor Name: United Mechanical

2020‐0271

Year Approved: 2021

Morse Hall ‐ Stand By Generator and Distribution ‐ Design ONLY

3.1‐ SUBSTANTIAL COMPLETION

SIHOUDE, DONALD A

02‐19‐2021 ‐ Report received on January 22nd. From Harriman A&E.Phase 1 completed.

Design Firm: Contractor: Contractor Name:

2020‐0214

Year Approved: 2020

New England Center Projects in Building 1

New England Center ‐ Boiler Replacement and BAS Controls

3.1‐ SUBSTANTIAL COMPLETION

RRHENRY, PAUL A

3‐2‐21  complete, waiting for final commissioning report, finalizing close out.

Design Firm: Harriman Contractor: Contractor Name:

2016‐0403

Year Approved: 2020

Monday, March 1, 2021 Page 15 of 26University of New Hampshire

Facilities Project Management

Page 16: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Parsons Hall Projects in Building 1

Parsons Hall ‐ Set up Lab Space W202

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

3‐2‐21 have CPR and funding, workign with contractor to start.

Design Firm: Contractor: External Contractor Name: Charter Brothers

2021‐0028

Year Approved: 2021

Paul College Projects in Building 2

Paul College ‐ Roof Membrane and Flashing Investigation  ‐ Corrective Plan/Design

1.1‐ PLAN/EST

RRROULEAU, RICHARD A

2/26/2021 ‐ No Change ‐ ARM recommends water testing to determine where/how the water is 

getting in.  Proposal for testing is in hand.  P.O. request will be submitted now that Covid‐19 

suspension has been lifted.  Depending on the results, we will pursue a warranty claim and/or 

involve PC Construction and the roofer.  Using remaining funds from original construction for 

this effort (ref. 2009‐0980 / 1XT955)

Design Firm: ARM, LLC (roofing consultan Contractor: Contractor Name:

2019‐0331

Year Approved: 2019

Paul College ‐ Investigation of Voltage Fluctuations

3‐ IN CONSTRUCTION

RR

Emergency Repair

HOUDE, DONALD A

02‐19‐2021 ‐ Paul College‐ the Electrical Service for this building from the Hi Voltage 34,500 to 

the low 120V has beeen checked and tested. We are still looking at different issues and checking 

system loads. We have asked IT to look into the equipment programming and Telecom to check 

the LAN..We think the issue has gone away.

Design Firm: Contractor: Contractor Name:

2021‐0079

Year Approved: 2021

Paul Creative Arts Center Projects in Building 6

Paul Creative Arts Center ‐ Building Life Safety Report Update

1.1‐ PLAN/EST

RRHENRY, PAUL A

3‐2‐21 Need to review report and finilize

Addendum to Life Safety plan to be reviewed and approved with the SFMO.

Design Firm: Contractor: Contractor Name:

2019‐0241

Year Approved: 2019

Paul Creative Arts Center ‐ Art Museum ‐ HVAC Design

1.1‐ PLAN/EST

FCRROULEAU, RICHARD A

2/26/2021 ‐ RFS Engineering has walked the site.  They are preparing a proposal that will include 

a hard number for a study, potential solutions and recommendations and 

conservative/budgetary numbers schematic, DD and CD.

Design Firm: RFS Engineering Contractor: Contractor Name:

2021‐0098

Year Approved:

Monday, March 1, 2021 Page 16 of 26University of New Hampshire

Facilities Project Management

Page 17: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Paul Creative Arts Center ‐ Fire Alarm Design Only

2‐ IN DESIGN

RRHENRY, PAUL A

3‐2‐21 design uder review, then handing off to Matt, meeting with Harriman to review.

Design Firm: TBD Contractor: External Contractor Name: TBD

2019‐0055

Year Approved: 2020

Paul Creative Arts Center ‐ Sprinkler Installation ‐ Design Only

2‐ IN DESIGN

RRMANCINI, MATTHEW E

3/1/2021:  Design Draft review scheduled for March 4th.

Design Firm: Contractor: Contractor Name:

2016‐0032

Year Approved: 2021

Paul Creative Arts Center ‐ High Voltage Electrical Service Replacement

3‐ IN CONSTRUCTION

RRHOUDE, DONALD A

02‐19‐21   95% of the conduit is in place. I have been asked to complete this work this winter. I 

expect to have the transformer base and transformer set in place next Tuesday (2‐23‐21) then 

install Hi V cables shortly after and the secondary loads at the same time .

Design Firm: Harriman Contractor: External Contractor Name:   ICR

2017‐0106

Year Approved: 2021

Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation

3.5‐ WARRANTY REPAIRS

RRROULEAU, RICHARD A

2/26/2021 ‐ No change.  Complete pending equipment list update and O&M upload.

Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.

2018‐0249

Year Approved: 2019

Philbrook Hall Projects in Building 2

Philbrook Hall ‐ Steam Study and Investigation

2‐ IN DESIGN

RRHENRY, PAUL A

3‐2‐21  need to reiew final report and finilize 

RFS provided three (3) options for steam study.  UNH has decided to proceed with using the 

steam boiler at Philbrook for hot water make up, this will allow the local steam boiler to operate 

between August ‐ May with continuation operation.  During Summer when Philbrook is not 

open the boiler will be put in dry layup with service assistance from Blake Engineering.  Intend 

to have local boiler online January 2019.

Design Firm: RFS Contractor: External Contractor Name: Eckhardt Johnson

2018‐0162

Year Approved: 2019

Monday, March 1, 2021 Page 17 of 26University of New Hampshire

Facilities Project Management

Page 18: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Philbrook Hall ‐ Boiler Replacement

3.1‐ SUBSTANTIAL COMPLETION

FCRHENRY, PAUL A

3‐2‐21  working on final closeout

Design Firm: RFS Contractor: External Contractor Name: Eckardt & Johnson

2019‐0304

Year Approved: 2019

Putnam Hall Projects in Building 2

Putnam Hall ‐ Spaulding Hall Swing Space

1.1‐ PLAN/EST

SIHEISNER, MICHELE

02/24/21 ‐ McGregor EMS to vacate Putnam by mid, late June. Planning is back in motion for 

collections temporary relocation from Spaulding. Updated and toured Putnam with new 

herbarium collections manager, insectarium collections manager and Chris Neefus.

Design Firm: Contractor: Contractor Name:

2020‐0204

Year Approved:

Putnam Hall ‐ EMS ‐ Covid‐19 Preparations

2‐ IN DESIGN

FCRRINES, DANIEL M

2‐24‐21:  EMS to move back to College Road. Code study, and feasibility underway for long term 

build out of Putnam.

Design Firm: McHenry Contractor: External Contractor Name: T&S Construction

2020‐0244

Year Approved:

Roads/Grounds Projects in Building 8

South Drive ‐ Design Advancement

2‐ IN DESIGN

SIHENRY, PAUL A

3‐2‐21 Tighe & Bond working on updating the wetland permits with NH DES, looking at 

mitigation locations for application.

Design Firm: Tighe & Bond Contractor: External Contractor Name:

2013‐1115

Year Approved: 2013 PROJECT SUSPENDED

FY21 Major Road Repairs ‐ Under Town of Durham Contract

3‐ IN CONSTRUCTION

RRRINES, DANIEL M

2‐24‐21: Paving work complete pending closeout and final invoicing.

Design Firm: Contractor: External Contractor Name: Continental

2019‐0371

Year Approved: 2021

Monday, March 1, 2021 Page 18 of 26University of New Hampshire

Facilities Project Management

Page 19: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Campus ‐ Main Street South Sidewalk

3‐ IN CONSTRUCTION

SIRINES, DANIEL M

2‐24‐21: Project is tracking funding for grant, please see 2017‐0384 for updates on project.

Design Firm: Contractor: Contractor Name:

2019‐0228

Year Approved: 2019

Campus ‐ A‐Lot Fencing Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRHOUDE, DONALD A

02‐19‐2021   Last section of fence to be installed when good weather comes. All tree clearing 

completed.

Design Firm: Contractor: Contractor Name:

2021‐0037

Year Approved: 2021

FY21 Sidewalk and Walkway Repairs

3.1‐ SUBSTANTIAL COMPLETION

RRRINES, DANIEL M

2‐24‐21: List complete, keeping open for any pedestrian hazards identified.

Design Firm: N/A Contractor: External Contractor Name: Top Quality Construction

2017‐0275

Year Approved: 2021

FY21 Site Stair Repairs

3.1‐ SUBSTANTIAL COMPLETION

RRRINES, DANIEL M

2‐24‐21; List complete, project remains open in case of pedestrian hazards identified over winter 

months.

Design Firm: N/A Contractor: External Contractor Name: Top Quality Construction

2019‐0368

Year Approved: 2021

Campus ‐ South Drive ‐ Temporary Connection to Colovos Road

3.1‐ SUBSTANTIAL COMPLETION

SIGEUTHER, MARK E

02‐24‐2021: Substantially Complete.

Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports

2018‐0267

Year Approved: 2019

Campus ‐ Main Street South Sidewalk

3.1‐ SUBSTANTIAL COMPLETION

SIRINES, DANIEL M

2‐24‐21:  Project is underway, punchlist to be completed in the spring.

Design Firm: CMA Engineering Contractor: Contractor Name:

2017‐0384

Year Approved: 2018

Rudman Hall Projects in Building 7

Monday, March 1, 2021 Page 19 of 26University of New Hampshire

Facilities Project Management

Page 20: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Rudman Hall ‐ Steam Absorber #1 Replacement

1.1‐ PLAN/EST

RRMANCINI, MATTHEW E

3/1/2021: A site visit for engineering term contractors has been set for March 4th. Design 

documents to be furnished for Besign‐Build delivery.

Design Firm: Contractor: Contractor Name:

2013‐0865

Year Approved: 2022

Rudman Hall ‐ Conversion to DDC Controls

3‐ IN CONSTRUCTION

RRMANCINI, MATTHEW E

3/1/2021: Reference ID 2010‐0479 for updates. Work expected to continue with conversion of 

office wings following completion of overall HVAC project.

Design Firm: SMRT Contractor: External Contractor Name: StructureTone

2015‐2336

Year Approved: 2018

Rudman Hall ‐ DDC Controls Backstop

3‐ IN CONSTRUCTION

RRMANCINI, MATTHEW E

3/1/2021: Backstop project to support relocation of mass spectrometer. General exhaust to be 

added to room per SMRTʹs direction. Additional direct‐exchange cooling to be included. 

Awaiting final design. Refer to Project 2017‐0288

Design Firm: SMRT Contractor: External Contractor Name: Structuretone

2021‐0013

Year Approved: 2021

Rudman Hall ‐ Retro‐Commissioning of ARO HVAC System

3‐ IN CONSTRUCTION

FCRMANCINI, MATTHEW E

3/1/2021: Reference ID 2010‐0479 for updates. Project to continue.

Design Firm: SMRT Contractor: Contractor Name: Structuretone

2019‐0305

Year Approved:

Rudman Hall ‐ Laboratory Fume Hood Control System Replacement

3‐ IN CONSTRUCTION

RRMANCINI, MATTHEW E

3/1/2021: Project continues. Currently, Phase 15 of 18 Labs are under way. HVAC work 

completion projected for June 2021.

Design Firm: SMRT Contractor: External Contractor Name: StructureTone

2010‐0479

Year Approved: 2017

Rudman Hall ‐ AHU‐3 Replacement

3‐ IN CONSTRUCTION

RRMANCINI, MATTHEW E

3/1/2021: Project to replace air handler is nearing completion.

Design Firm: SMRT Contractor: External Contractor Name: MB Mechanical Contractors Inc.

2020‐0128

Year Approved: 2021

Monday, March 1, 2021 Page 20 of 26University of New Hampshire

Facilities Project Management

Page 21: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Rudman Hall ‐ Fire Alarm Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRMANCINI, MATTHEW E

3/1/2021: Project is substantially complete.

Design Firm: SFC / SMRT Contractor: External Contractor Name: StructureTone

2015‐2352

Year Approved: 2016

Service Building Projects in Building 5

Service Building ‐ Fire Department Sprinkler Installation and Building Envelope 

Repairs

2‐ IN DESIGN

RRRINES, DANIEL M

2/24/21 : Design efforts underway.

Design Firm: McHenry Architecture Contractor: External Contractor Name:

2010‐0356

Year Approved: 2021

Service Building – DFD Expansion / SPA renovations

2‐ IN DESIGN

FCRRINES, DANIEL M

2‐24‐21: Code study and design efforts underway, quick transition into permitting and 

construction under term contact anticipated.

Design Firm: McHenry Architecture Contractor: External Contractor Name: TBD

2021‐0085

Year Approved: 2021

Service Building ‐ Fire Dept New Vehicle Exhaust Extraction System

2.5‐ IN PROCUREMENT

FCRRINES, DANIEL M

2‐24‐21: PM working with DFD to secure electrical firm contract, work anticipated to begin by the 

end of March.

Design Firm: Contractor: Contractor Name:

2021‐0089

Year Approved:

Service Building ‐ Dispatch Center Keltron System

3.1‐ SUBSTANTIAL COMPLETION

FCRHOUDE, DONALD A

01‐27‐21 ‐  Contractors have POʹs and incumbrances. Norris has prepared all new digital circuits. 

A schedule with dispatch has been set up to verify transfer of lines. Project progressing about 

99% complete. 1 circuit to be relocated.

Design Firm: Contractor: External Contractor Name: Norris / UNH Telecom

2016‐0123

Year Approved: 2018

Monday, March 1, 2021 Page 21 of 26University of New Hampshire

Facilities Project Management

Page 22: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Service Building ‐ Interior Heating Main Connections

3.1‐ SUBSTANTIAL COMPLETION

RRROULEAU, RICHARD A

2/26/2021 ‐ All work complete.  Rough and final mechanical inspections complete.  Electrical 

demo and SFMO final inspections can be scheduled.  Somewhat related work in Zais pending 

electronic valve replacement by Facilities Operations.

Design Firm: Harriman Contractor: External Contractor Name: Careno / NPI

2020‐0272

Year Approved: 2021

Spaulding Hall Projects in Building 3

Spaulding Hall ‐ Move Coordination and Support

1.1‐ PLAN/EST

FCRHEISNER, MICHELE

02/24/21 ‐Project is part of Spaulding and in support of swing space and move coordination.

Design Firm: Contractor: Contractor Name:

2020‐0249

Year Approved:

Spaulding Hall ‐ Utility and Infrastructure

3‐ IN CONSTRUCTION

FCRBRICKETT, ALEXANDER J

2/26/2021‐ Please see Project #2016‐0278 for updates.

Design Firm: Contractor: Contractor Name:

2020‐0246

Year Approved: 2020

Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative

3‐ IN CONSTRUCTION

CPBRICKETT, ALEXANDER J

2/26/2021‐ Building envelope completed. Final exterior trim in progress. Interior mechanical, 

electrical, plumbing , framing, elevator,  and sprinkler work in progress.

Design Firm: Ellenzweig Contractor: External Contractor Name: Skanska USA Building

2016‐0278

Year Approved: 2016

Stoke Hall Projects in Building 2

Stoke Hall ‐ Space Improvements in BIP Program Space

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021: Met with client and Milestone to define scope. Estimate in progress.

Design Firm: TBD Contractor: External Contractor Name: Milestone

2021‐0096

Year Approved:

Monday, March 1, 2021 Page 22 of 26University of New Hampshire

Facilities Project Management

Page 23: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Stoke Hall ‐ Gas Code Violations

2‐ IN DESIGN

FCRHENRY, PAUL A

3‐2‐21  Looking at reducing the foot print in the laundry rooms, considering an ouside MAU and 

ducted into the laundry rooms. Team currently looking into.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2020‐0012

Year Approved: 2021

Telecommunications Center Projects in Building 2

Telecommunications Center ‐  Convert Old Staff Area

1.1‐ PLAN/EST

FCRGEUTHER, MARK E

02‐24‐2021: Requesting approval to move forward with design in FYʹ21 with funds remaining 

from the addition.

Design Firm: Oak Point Associates Contractor: External Contractor Name: TBD

2021‐0010

Year Approved: 2022

Telecommunications Center ‐ Addition and Renovation

3.1‐ SUBSTANTIAL COMPLETION

FCRGEUTHER, MARK E

02‐24‐2021: Permission to occupy received. Working on Punch List and close out documentation.

Design Firm: Oak Point Contractor: External Contractor Name: Charters Brothers

2019‐0292

Year Approved: 2019

Thompson Hall Projects in Building 1

Thompson Hall ‐ Rm 203 ‐ Add DW to mini kitchen

1.1‐ PLAN/EST

FCRHEISNER, MICHELE

02/24/21‐ Cost estimate and scope presented for approval. Awaiting approval.

Design Firm: Contractor: Contractor Name:

2021‐0059

Year Approved:

Transportation Garage Projects in Building 1

Transportation Garage ‐ Utility Distribution ‐ Replace Existing transformer

2.5‐ IN PROCUREMENT

RRHEALEY, SCOTT M

1‐29‐21 ‐ Transformer should arrive in the middle of March, and need to be installed before June.

Ordered 10‐20 ‐ 23 week lead time.

Design Firm: Contractor: Contractor Name: IC Reed

2021‐0039

Year Approved: 2021

Utility Distribution Projects in Building 5

Monday, March 1, 2021 Page 23 of 26University of New Hampshire

Facilities Project Management

Page 24: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Utility Distribution ‐ Tunnel Repairs and Utility Line Replacement Leaving Central 

Plant ‐ Design Only

2‐ IN DESIGN

RRRINES, DANIEL M

2‐24‐21: Design consulatant awarded to RMF. Inspection and report underway. Phase 2 of 

contract, and DD to begin.

Design Firm: RMF Engineering Contractor: Contractor Name:

2020‐0004

Year Approved: 2021

Utility Distribution ‐ Lee Circle Water Line Extension

2‐ IN DESIGN

FCRRINES, DANIEL M

 2‐24‐21  Consultant working on design, construction summer 2021 via the TOD

Design Firm: Underwood Eng Contractor: External Contractor Name: TBD

2018‐0256

Year Approved:

Utility Distribution ‐ Sector Cabinet Installation and Cable Replacement

2.5‐ IN PROCUREMENT

RRHEISNER, MICHELE

02/24/21‐ Location coordinated with 2020 0231 HSSC project site utility drawings. Equipment on 

order.  Installation work to be coordinated with HSSC.

Design Firm: Contractor: Contractor Name:

2021‐0082

Year Approved: 2021

Utility Distribution ‐ Dual Temp Interconnection

3‐ IN CONSTRUCTION

FCRROULEAU, RICHARD A

2/26/2021 ‐ Chilled water pump skid has been installed and has been piped.  Work in the 

McDaniel Drive Chiller Plant is essentially complete.  Other than some controls work and a floor 

drain installation, work to wind down until beginning of cooling season in late‐May.

Design Firm: Harriman Associates Contractor: External Contractor Name: Careno Construction

2019‐0022

Year Approved: 2019

Utility Distribution ‐ Piping Replacements from Heating Vault HVT086 to Handler Hall

3.1‐ SUBSTANTIAL COMPLETION

RRRINES, DANIEL M

2‐24‐21: working on minor punchlist, and project closeout. Warranty work identified in pit 4 as 

well as valve in Handler Hall to be repaired post commencement.

Design Firm: Harriman Contractor: External Contractor Name: Anderson Welding

2018‐0362

Year Approved: 2021

Verizon Head End Building Projects in Building 1

Monday, March 1, 2021 Page 24 of 26University of New Hampshire

Facilities Project Management

Page 25: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Verizon Wireless Head End Building ‐ Construction

1.1‐ PLAN/EST

FCRPETERS, NICK E

26 Feb 2021 ‐ Pre‐bid walk through with subcontractors held 5 Oct.  Contractor selection and 

preparing submittals.  Awaiting permitting information, which will fall through Town of 

Durham, not SFMO.  SFMO now responsible for connections between this building and campus.

Design Firm: Verizon Wireless Contractor: Contractor Name: Verizon Wireless

2020‐0270

Year Approved: 2020

Water Treatment Plant Projects in Building 1

Water Treatment Plant ‐ New Construction

3.1‐ SUBSTANTIAL COMPLETION

SIGEUTHER, MARK E

02‐24‐2021: Working on close out documentation.

Design Firm: Woodard & Curran Contractor: External Contractor Name: Waterline Industries

2008‐0038

Year Approved: 2014

Whittemore Center ‐ Arena Projects in Building 4

Whittemore Center ‐ Arena ‐ Section 112R ‐ Clean Air Compliance

1.1‐ PLAN/EST

RRGEUTHER, MARK E

02‐24‐2021: Project approved. Exception to Bid approved. Consultant schedule to be on campus 

03‐08‐2021.

Design Firm: HCG Associates Contractor: External Contractor Name: TBD

2021‐0087

Year Approved: 2021

Whittemore Center ‐ Arena ‐ Fire Alarm and Sound System Control Panel Repairs

2‐ IN DESIGN

RR

Emergency Repair

HENRY, PAUL A

3‐2‐21 Installed UPS in equipment rack a the Field House, Jeff Murphy is working on testing 

proceedure for training.

Design Firm: SFC Eng. Contractor: External Contractor Name: Norris ‐ Scarponi

2020‐0229

Year Approved: 2021

Whittemore Center ‐ Arena ‐ Verizon Wireless In‐Building Cellular Antenna System

3‐ IN CONSTRUCTION

FCRPETERS, NICK E

28 Feb 2021 ‐ Preliminary runs have been accomplished in telecom rooms.  Primary construction 

will begin late‐March to early‐April.

Design Firm: Contractor: External Contractor Name: Verizon Wireless

2020‐0269

Year Approved: 2020

Monday, March 1, 2021 Page 25 of 26University of New Hampshire

Facilities Project Management

Page 26: Facilities Project Management Monthly Report Building · 2021. 3. 4. · Facilities Project Management Monthly Report by Building Monday, March 1, 2021 Approved Project 131 PM PROJECT

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Whittemore Center ‐ Arena ‐ Dehumidification System

3.1‐ SUBSTANTIAL COMPLETION

FCRBRICKETT, ALEXANDER J

2/26/2021 ‐ New unit has been installed. Commissioning in progress, to be completed when hot 

weather returns

Design Firm: Harriman Contractor: External Contractor Name: Careno Construction

2017‐0308

Year Approved: 2019

Wildcat Stadium Projects in Building 1

Wildcat Stadium ‐ Verizon Wireless Distributed Antenna Installation

3‐ IN CONSTRUCTION

FCRPETERS, NICK E

28Feb 2021 ‐ Contractors have begun electrical permitting.  Installation has commenced.

Design Firm: Verizon Wireless Contractor: External Contractor Name: Verizon Wireless

2020‐0268

Year Approved: 2020

Woodside Projects in Building 1

Woodside ‐ Mechanical Room Exhaust ‐ Design Only

1.1‐ PLAN/EST

FCRHENRY, PAUL A

3‐2‐21 Submitted CPR for approval still waitng, Design only.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2021‐0086

Year Approved:

Monday, March 1, 2021 Page 26 of 26University of New Hampshire