25
Facilities Project Management Monthly Report by Building Monday, August 31, 2015 129 Approved Project ID PROJECT TITLE PM Accountable Project Code Project Number: 1 Leavitt Lane Projects in Building 3 2319 1 Leavitt Lane Warehouse Office, warehouse, and breakroom… 3IN CONSTRUCTION FCR WOODCOCK, JONATHAN 8/27/15_ Major construction complete, with punchlist being defined. New scope being scheduled with FCT. Design Firm: Contractor: FCT Contractor Name: 20152319 1542 1 Leavitt Lane HVAC Investigation and Evaluation 3IN CONSTRUCTION RR HENRY, PAUL A Scheduling recap Sept. 2015 Design Firm: Harriman Contractor: External Contractor Name: TBD 20131542 2714 1 Leavitt Lane Fire Suppression 3IN CONSTRUCTION FCR HOUDE, DONALD A Work is funded, FCT ordering material and setting up the work schedule.FCT and Simplex presenting to SFMO today. 82515 Design Firm: Contractor: FCT Contractor Name: 20152700 10 West Edge Drive Projects in Building 2 2762 10 West Edge Drive Renovation to support new Fujifilm LED 1600 printer 2.5IN PROCUREMENT FCR HENRY, PAUL A Reviewing project cost with team 821 Design Firm: Harriman Contractor: External Contractor Name: Milestone 20152747 2605 10 West Edge Drive Rm 102 Est. to install dishwasher 2.5IN PROCUREMENT FCR WOODCOCK, JONATHAN 8/27/15_ FCT exchanging equipment to suit the original intent. Scheduling construction window with contractors. Design Firm: Contractor: FCT Contractor Name: 20152605 121 Technology Drive Projects in Building 2 Monday, August 31, 2015 Page 1 of 25 University of New Hampshire Brenda Whitmore, Director Facilities Project Management
Transcript
Page 1: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

Facilities Project Management Monthly Report by Building

Monday, August 31, 2015 129Approved Project

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

1 Leavitt Lane Projects in Building 3

2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and breakroom…

3‐ IN CONSTRUCTION

FCRWOODCOCK, JONATHAN

8/27/15_ Major construction complete, with punchlist being defined.   New scope being 

scheduled with FCT.

Design Firm: Contractor: FCT Contractor Name:

2015‐2319

1542 1 Leavitt Lane ‐ HVAC Investigation and Evaluation

3‐ IN CONSTRUCTION

RRHENRY, PAUL A

Scheduling re‐cap Sept.  2015

Design Firm: Harriman Contractor: External Contractor Name: TBD

2013‐1542

2714 1 Leavitt Lane ‐ Fire Suppression

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

Work is funded, FCT ordering material and setting up the work schedule.FCT and Simplex 

presenting to SFMO today.  8‐25‐15

Design Firm: Contractor: FCT Contractor Name:

2015‐2700

10 West Edge Drive Projects in Building 2

2762 10 West Edge Drive ‐ Renovation to support new Fujifilm LED 1600 printer

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

Reviewing project cost  with team 8‐21

Design Firm: Harriman Contractor: External Contractor Name: Milestone

2015‐2747

2605 10 West Edge Drive ‐ Rm 102 Est. to install dishwasher

2.5‐ IN PROCUREMENT

FCRWOODCOCK, JONATHAN

8/27/15_ FCT exchanging equipment to suit the original intent.  Scheduling construction window 

with contractors.

Design Firm: Contractor: FCT Contractor Name:

2015‐2605

121 Technology Drive Projects in Building 2

Monday, August 31, 2015 Page 1 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 2: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2518 Madbury Commons ‐ IOL

2.5‐ IN PROCUREMENT

FCRHECKLER, BARBARA K

Award issued 8/3/2015. Showroom visit planned fro 8/27/2015.

Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name:

2015‐2518

2519 Madbury Commons ‐ UNH Innovation

2.5‐ IN PROCUREMENT

FCRHECKLER, BARBARA K

Award issued 8/3/2015. Showroom visit planned for 8/27/2015.

Design Firm: Manypenny Murphy Archite Contractor: Contractor Name:

2015‐2519

265 MAST ROAD ‐ MAIN HOUSE Projects in Building 1

2876 265/267 Mast Road ‐ Main House/Carriage House ‐ Demolition

1‐ ASSIGNED

FCRHENRY, PAUL A

Design Firm: Contractor: Contractor Name:

2016‐0078

5 Leavitt Lane Projects in Building 1

1387 5 Leavitt Lane ‐ Review of cooling system capacity

2‐ IN DESIGN

FCRCARTABONA, STEPHANI

8/27/15 Harriman is working on 50% design drawings for UNH review.  Pending funding 

approval this project would be ready for bid November / December 2015.

Design Firm: Harriman Associates Contractor: External Contractor Name: TBD

2013‐1387

6 Leavitt Lane Projects in Building 1

1567 6 Leavitt Lane ‐ Lock Shop and Facilities Office Renovation

3‐ IN CONSTRUCTION

FCRWOODCOCK, JONATHAN

8/27/2015_Punch list items, and controls being finalized for original scope.  New scope being 

estimated for funding procurement.

Design Firm: Loureiro Engineering Contractor: FCT Contractor Name:

2014‐1567

88 Commercial Street Projects in Building 1

Monday, August 31, 2015 Page 2 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 3: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2583 88 Commercial Street ‐ Installation of 5th Floor Science Labs

3‐ IN CONSTRUCTION

FCRWOODCOCK, JONATHAN

8/27/15_ Labs 95% looking to turn over occupancy by 8/28/15.  Final punch and misc scope to be 

finalized early September 2015.

Design Firm: Contractor: Contractor Name:

2015‐2583

Babcock Hall Projects in Building 1

2784 Babcock Hall ‐ Volleyball Post

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15 Scheduled for week of 9/1

Design Firm: Contractor: FCT Contractor Name:

2016‐0005

Barton Hall and Cole Hall Projects in Building 4

1132 Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications

1.1‐ PLAN/EST

RRHOUDE, DONALD A

New, I will appropriate the aid of an engineer to provide a plan for this work.. Have to review 

Cole side again.  8‐25‐15

Design Firm: Contractor: Contractor Name:

2011‐1132

2614 Barton Hall and Cole Hall ‐ Bottle Fill Stations

2.5‐ IN PROCUREMENT

FCRHEALEY, RANDY L

8/24/15 Scheduled to begin 9/2/15

Design Firm: Contractor: FCT Contractor Name:

2015‐2614

2611 Barton Hall and Cole Hall ‐ Digital /Sign installation

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

Thompson school has sent notice they will proceed with the funding of the Cole Hall digital sign 

only, at this time. . Per request of the customer, work has been delayed to after 7‐27‐15,    There is 

a problem with the bracket provided. A replacement is being approved.Installation is for Friday   

8‐28‐15

Design Firm: Contractor: FCT Contractor Name:

2015‐2611

Monday, August 31, 2015 Page 3 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 4: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2740 Cole Hall ‐ Rms 141, 142 Carpeting & Electrical

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Carpent installed, working on small punch list. 8‐20

Design Firm: Contractor: External Contractor Name: Sprague Flooring

2015‐2730

Chase Ocean Engineering Lab Projects in Building 1

2668 Chase Ocean Engineering Building ‐ Sound Reduction HVAC‐1 and HVAC‐2

2‐ IN DESIGN

FCRCARDOSO, ANDRE W

Construction to take place in early fall 2015 and be completed by October 15, 2015.

Design Firm: Harriman Associates Contractor: TBD Contractor Name: TBD

2015‐2668

Childhood Study & Development Center Projects in Building 1

1428 Childhood Study & Development Center ‐ Playground Rubber Surface Repairs

2.5‐ IN PROCUREMENT

FCRJONES, KATHLEEN M

8/27/15: FCT to install sand slurry below rubber surface during the week of 8/31/15.

Design Firm: Contractor: FCT Contractor Name:

2013‐1428

Combined Heat and Power Plant Projects in Building 1

2582 Combined Heat and Power Plant ‐ Boiler # 4 Replacement

3‐ IN CONSTRUCTION

SIHOUDE, DONALD A

Boiler demolition is 100% complete. Ext, AST  removal is complete. Floor prep is complete. 

Staging for roof removal in place. #2 Oil piping to begin. New control work for Boiler 1,2,3 to 

start this week. . 8‐25‐15

Design Firm: Contractor: Contractor Name:

2014‐2582

Computing Analytics ‐ CHHS Projects in Building 1

2624 10 Pettee Brook Lane ‐ Fit Out Lease Space

2.5‐ IN PROCUREMENT

FCRCARDOSO, ANDRE W

As of August 25, awating pricing from contractor working for landlord. Space to be ready for 

occupancy in late October 2015.

Design Firm: Cowan‐Goudreau Contractor: External Contractor Name: Landlord

2015‐2624

Conant Hall Projects in Building 1

Monday, August 31, 2015 Page 4 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 5: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2551 Conant Hall ‐ Rm 204 Installation of Fume Hood Rm 204

3‐ IN CONSTRUCTION

FCRWOODCOCK, JONATHAN

8/27/2015_  Scope is under construction, with HVAC being scheduled once equipment lead times 

are defined.

Design Firm: Harriman Contractor: FCT Contractor Name:

2015‐2551

Dairy Teaching and Research Complex Projects in Building 1

2766 Dairy Teaching and Research Complex ‐ Paving

2.5‐ IN PROCUREMENT

FCRJONES, KATHLEEN M

8/27/15: Bell & Flynn is scheduled to begin preparing site for paving September 8, applying 

binder course by September 18, T&S will apply loam and seed on edges by September 22, and 

final top coat paving will occur by September 23. Invoices to be received from both companies 

no later than September 25 to meet funding requirements.

Design Firm: Contractor: External Contractor Name: Bell & Flynn; T&S Construction

2015‐2751

Demeritt Hall Projects in Building 2

1995 Demeritt Hall ‐ Rm 217 Safety Improvements

2.5‐ IN PROCUREMENT

FCRWOODCOCK, JONATHAN

8/27/2015_FCT hired,and defining schedule with subcontractor.

Design Firm: Harriman Associates Contractor: FCT Contractor Name: TBD

2014‐1995

2723 Demeritt Hall ‐ AV Work 251 & 253 etc.

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15 Majority of work completed, waiting on AV team to remove touch panels to complete 

our portion. Work is expected to be done over winter break

Design Firm: Contractor: FCT Contractor Name:

2015‐2711

Dimond Library Projects in Building 8

806 TEAL Classroom

1.1‐ PLAN/EST

SIHENRY, PAUL A

Submitted new budget to the Provost office, waiting for feed back. Still in holding 1‐7‐15

Design Firm: Contractor: Contractor Name:

2012‐0806

Monday, August 31, 2015 Page 5 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 6: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2215 Dimond Library ‐ Ground Lvl compact shelving capacity study

1.1‐ PLAN/EST

FCRWOODCOCK, JONATHAN

8/27/2015_ Scope defined and engineers proposal in for procurement.

Design Firm: Loureiro Engineering Contractor: External Contractor Name: TBD

2015‐2215

624 Dimond Library ‐ Space Repurposing ‐ Phase 2

2‐ IN DESIGN

SIHECKLER, BARBARA K

3/26/15: Per T. Lauder, internal Dimond group working on defining and/or redefining space 

uasge and needs. Outcome of those discussions will determine direction project will take.

8/20/2015: Status unchanged.

Design Firm: Contractor: Contractor Name:

2010‐0624

1833 Dimond Library ‐ Level III hall add lighting

2.5‐ IN PROCUREMENT

FCRHOUDE, DONALD A

Client has a quote and FCR, we are waiting on funding. . 8‐25‐15

Design Firm: Contractor: FCT Contractor Name:

2014‐1833

1359 Dimond Library ‐ Rm 301 Redesign and Relocation

2.5‐ IN PROCUREMENT

FCRHECKLER, BARBARA K

Scope increased to include minimal carpet repair.  Samples ordered 8/19 and receipt expected on 

or before 8/25/2015.  Additional scope will be covered by contingency.

Design Firm: Contractor: FCT Contractor Name:

2013‐1359

2612 Dimond Library ‐ Digital Sign Upgrade

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

This work is funded the equipment is in. FCT should be complete on this work this week. 8‐25‐15

Design Firm: Contractor: FCT Contractor Name:

2015‐2612

2064 Dimond Library ‐ AHU 1E Replacement

3‐ IN CONSTRUCTION

RRCARDOSO, ANDRE W

 The new air handler arrived on August 18. As of August 25,  completion is on schedule for 

September 18.

Design Firm: Oak Point Contractor: FCT Contractor Name: Palmer and Sicard

2014‐2064

Monday, August 31, 2015 Page 6 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 7: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2325 Dimond Library ‐ Stack Lighting Modifications

3.5‐ WARRANTY REPAIRS

RRCARTABONA, STEPHANI

8/27/15 This work is complete, pending a warranty repair of an existing wattstopper controller 

for floor 4 stack lighting.

Design Firm: Rist Frost Shumway Contractor: External Contractor Name: Yates Electric

2015‐2325

Elizabeth Demeritt Projects in Building 1

2832 Elizabeth Demeritt ‐ Workspace Layout

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15 Estimate accepted, working with the customer to schedule after school starts.

Design Firm: Contractor: FCT Contractor Name:

2016‐0042

Field House Projects in Building 8

2469 Field House ‐  Rm 18 Space Reconfiguration/Remodelling

2‐ IN DESIGN

FCRJONES, KATHLEEN M

8/2715: Architect has submitted 4 conceptual designs for the space reconfiguration. PM has sent 

conceptual designs to Athletics for review and comment and direction on next steps from 

Athletics.

Design Firm: Harriman Contractor: Contractor Name:

2015‐2469

986 Field House ‐ HV Replacements Phase IV of VII ‐ Modifications to HV13

2‐ IN DESIGN

RRCARTABONA, STEPHANI

8/27/15  Harriman has provided plans for this project.  Working with athletics to determine 

schedule for installation.  Anticipate spring construction for this project.  Will issue to 

purchasing for bid October 2015.

Design Firm: Harriman Assoc. Contractor: External Contractor Name: TBD

2012‐0986

2011 Field House ‐ Room Renumbering

2.5‐ IN PROCUREMENT

FCRHECKLER, BARBARA K

Installation by Portsmouth Sign anticipated fro week of 8/24/2015.

Design Firm: Contractor: External Contractor Name: Portsmouth Sign Co.

2014‐2011

Monday, August 31, 2015 Page 7 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 8: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2596 Field House ‐ Heating Coil Replacements HV 25

3‐ IN CONSTRUCTION

RR

Emergency Repair

CARTABONA, STEPHANI

8/27/15 Granite State Plumbing Heating will schedule installation of this unit to occur during 

September 2015

Design Firm: Contractor: External Contractor Name: Granite State Plumbing Heating

2015‐2596

177 Field House ‐ Asphalt parking lot Reconstruction ‐ Design and Improvements

3‐ IN CONSTRUCTION

SIHENRY, PAUL A

Project Potentially back on schedule if the weather corporates.

1‐Base Paving 8‐7

2‐Curbing Starting 8‐11

3‐Final paving 8‐27

4‐Striping 8‐28

Design Firm: Tighe & Bond Contractor: External Contractor Name: Earth Construction

2009‐0177

2342 Field House ‐ Sprinkler Installation ‐ Phase IV

3‐ IN CONSTRUCTION

RRCARTABONA, STEPHANI

Will report with 1159

Design Firm: SFC Engineering Contractor: External Contractor Name: TBD

2015‐2342

1159 Field House ‐ Sprinkler Installation ‐ PHASE III

3‐ IN CONSTRUCTION

RRCARTABONA, STEPHANI

8/27/15 Awaiting submittal review comments from SFC Engineering to evaluate FM Global 

comments.  Fire pump has been released, anticipate construction to begin October 2015.

Design Firm: SFC Engineering Contractor: External Contractor Name: Careno Construction

2013‐1159

672 Driveway Repair ‐ Emergency Access‐ Field House

3‐ IN CONSTRUCTION

RRHENRY, PAUL A

Project Potentially back on schedule if the weather corporates.

1‐Base Paving 8‐7

2‐Curbing Starting 8‐11

3‐Final paving 8‐27

4‐Striping 8‐30

Design Firm: Tighe& Bond Contractor: External Contractor Name: TBD

2011‐0672

Gregg Hall Projects in Building 1

Monday, August 31, 2015 Page 8 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 9: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2831 Gregg Hall ‐ HVAC Engineering Evaluation

1.1‐ PLAN/EST

RRCARTABONA, STEPHANI

8/27/15 No actiivty at this time.

Design Firm: Contractor: Contractor Name:

2016‐0041

Hamilton Smith Hall Projects in Building 1

2785 Hamilton Smith Hall ‐ Major Renovation Project

3‐ IN CONSTRUCTION

SIROULEAU, RICHARD A

7/27/2015 Update: Abatement and demolition of the rear of the building continues and is 

expected to be completed prior to freshmen move‐in on August 28.  Bid documents for early 

release site/foundations/structural steel package were issued on 7/26 and the associated work is 

to occur during the fall semester.  Bid documents for the balance of the project are expected in 

late‐August.  The ESL program moved into swing space on 7/20.  The final move into swing 

space this summer will be the English Department office on August 17.  The balance of Hamilton 

Smith will be vacated the first week of January 2016, and the contractor will then fully mobilize.  

Construction is expected to be complete such that we can re‐occupy the building in time for fall 

2017 classes.

Design Firm: DiMella Shaffer Associates Contractor: FCT Contractor Name: Skanska USA, Inc.

2012‐1851

Health Services Projects in Building 1

2647 Health Services ‐ Retro Commissioning

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Waiting for final report 8‐20

Design Firm: Contractor: Contractor Name:

2015‐2647

Hewitt Annex Projects in Building 1

2775 Hewitt Annex ‐ Site Restoration and Utility Isolation

3‐ IN CONSTRUCTION

RRCARTABONA, STEPHANI

8/27/15 Working with MannyPennyMurphy for site restoration and entrance to Hewitt basement.

Design Firm: MannyPennyMurphy Contractor: External Contractor Name: TBD

2016‐0003

Hewitt Hall Projects in Building 4

Monday, August 31, 2015 Page 9 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 10: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

1964 Hewitt Hall ‐ Carpet Investigation and Reinstallation

1.1‐ PLAN/EST

RRWOODCOCK, JONATHAN

8/27/15_Estimating costs asoociated with broadloom or carpet square installation.

Design Firm: Contractor: External Contractor Name: TBD

2014‐1964

2735 Hewitt Hall ‐ Rms 125, 115, 111 Painting

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/20/15  Shelves installed, remaining items scheduled to be complete 9/1/15

Design Firm: Contractor: FCT Contractor Name:

2015‐2722

2636 Hewitt Hall ‐ Rm 307 Wall Repairs/Painting

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15  Original order complete. CO work today and 8/28.  AdTech installing today

Design Firm: Contractor: FCT Contractor Name:

2015‐2636

2057 Hewitt Hall ‐ Rms 139, 141 Space Renovation

3‐ IN CONSTRUCTION

FCRWOODCOCK, JONATHAN

8/27/2015_Renovation complete…AV/Tech being installed and programmed.

Design Firm: TBD Contractor: FCT Contractor Name:

2014‐2057

Holloway Commons Projects in Building 2

2397 Holloway Commons ‐ Upgrade Digital Voice Evacuation System

3‐ IN CONSTRUCTION

FCRCARTABONA, STEPHANI

8/27/15 Norris has recommended smoke detectors throughout the building be replaced as they 

currently perform weekly inspection of the smoke detector.  This proposal will be submitted to 

OBA for review and approval.

Design Firm: Contractor: External Contractor Name: Norris Inc.

2015‐2397

Monday, August 31, 2015 Page 10 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 11: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

1657 Holloway Commons ‐ Expansion Project

3‐ IN CONSTRUCTION

CPROULEAU, RICHARD A

8/31/2015 Update: Phase 1 is substantially complete.  Holloway Commons is open for business 

and the changes implemented have been well‐received.  Next to be turned over is the condiment 

station south of the new Grill Station, which should be available by 9/11.  Work continues on the 

additions.  The balance of the entry addition including the new public stair and elevator is 

expected to be turned over in late‐September.  Construction on the dining room addition is to 

continue through early‐February 2016.

Design Firm: Miller Dyer Spears Contractor: FCT Contractor Name: North Branch Construction

2014‐1657

Horton Hall Projects in Building 2

2828 Horton Social Science Center ‐ Rm 315 Move Bulletin & White Board

1.1‐ PLAN/EST

FCRHEALEY, RANDY L

8/27/15 Estimate accepted.Working with the customer to schedule after school starts.

Design Firm: Contractor: FCT Contractor Name:

2016‐0038

2865 Horton Social Science Center ‐ A/C Installation 4th floor

3‐ IN CONSTRUCTION

FCRHealey

8/27/15 Project is 75% Complete. Expected to be complete 9/4.

Design Firm: Contractor: Contractor Name:

2016‐0068

Horton Social Science Center Projects in Building 2

2552 Horton Social Science Center ‐ Renovation of 1st Floor

2‐ IN DESIGN

FCRHENRY, PAUL A

Design Funded, first meeting 8‐11, will present egress optons to SFMO at Sept. meeting.8‐20

Design Firm: Harriman Contractor: External Contractor Name: TBD

2015‐2552

2475 Horton Social Science Center ‐ Renovation of 4th floor

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Project Substantially complete, furniture being installed. SFMO CO walk through 8‐25

Design Firm: Harriman Contractor: External Contractor Name: TBD

2015‐2475

Huddleston Hall Projects in Building 2

Monday, August 31, 2015 Page 11 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 12: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2808 Huddleston Hall ‐ 211 Door  & Painting

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/20/15 Lock on order. Expected to arrive Aug 31

Design Firm: Contractor: FCT Contractor Name:

2016‐0019

2585 Huddleston Hall ‐ Mechanical Room Repairs

3‐ IN CONSTRUCTION

RRHENRY, PAUL A

Area way completed, working on MEP 8‐20

Design Firm: Contractor: External Contractor Name: TBD

2015‐2585

Jackson Lab Projects in Building 1

2621 Jackson Lab ‐ Greenhouse Repair and Restoration

2‐ IN DESIGN

RR

Emergency Repair

WOODCOCK, JONATHAN

8/27/2015 Issued PO to engineer for design review.

Design Firm: Contractor: External Contractor Name: Orlando Greenhouse Sales Inc

2015‐2621

Kendall Hall Projects in Building 3

2360 Kendall Hall ‐ Abatement and Planning

1.1‐ PLAN/EST

RRCARDOSO, ANDRE W

 Next round of abatement on the third floor, basement level and in the stairwells is scheduled to 

begin on September 8.

Design Firm: TBD Contractor: FCT Contractor Name: Dec‐Tam

2015‐2360

2322 Kendall Hall ‐ Swing Space Renovations

2.5‐ IN PROCUREMENT

FCRCARDOSO, ANDRE W

Construction is scheduled to begin to September 8 and be complete by December 1, 2015.

Design Firm: Many‐Penny Murphy Contractor: External Contractor Name: Bauen Corp.

2015‐2322

55 Kendall Hall ‐ Fire Alarm and Emergency Lighting Replacement

3‐ IN CONSTRUCTION

RRCARTABONA, STEPHANI

8/27/15 Emergency battery back up lighting installed by FCT.  Scarponi Electric to begin fire 

alarm installation for completion prior to December 2015.

Design Firm: SFC Engineering Contractor: FCT Contractor Name: Scarponi Electric

2009‐0055

Monday, August 31, 2015 Page 12 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 13: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Kingsbury Hall Projects in Building 3

2263 Kingsbury Hall ‐ Roof Safety Restraint System Phase II of II

2‐ IN DESIGN

RRWOODCOCK, JONATHAN

8/27/2015 Out for design with ARM & Safe Approach.

Design Firm: ARM Contractor: External Contractor Name: TBD

2015‐2263

2849 Kingsbury Hall ‐ TV Installation 2nd Floor Lobby

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15 Scheduled to begin and be completed the same day, Monday 8/31/15.

Design Firm: Contractor: FCT Contractor Name:

2016‐0059

1933 Kingsbury Hall ‐ Area of Refuge Project

3‐ IN CONSTRUCTION

FCRWOODCOCK, JONATHAN

8/27/15_ Door modifications complete. Remaining scope is isolated to signage & phones… 

Scheduling scope around building programming.

Design Firm: HL Turner Contractor: FCT Contractor Name:

2014‐1933

MacFarlane Greenhouse Projects in Building 1

2538 MacFarlane Greenhouse ‐ Fume Hood Alarm Upgrades

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Project funded waiting for FCT 8‐20

Design Firm: Contractor: FCT Contractor Name:

2015‐2538

McConnell Hall Projects in Building 1

2810 McConnell Hall ‐ Rm 202 Additional Power Strips

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27//15 Approved 8/12, Scheduling week of 8/31

Design Firm: Contractor: FCT Contractor Name:

2016‐0021

Memorial Union Building Projects in Building 6

Monday, August 31, 2015 Page 13 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 14: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2748 Moving CO2 tank from PPC to MUB

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

Scheduled for 8‐20

Design Firm: Contractor: FCT Contractor Name:

2015‐2733

2607 Memorial Union Building ‐ Rm 18 est to replace lighting fixtures

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15 Additional electrical requested. Expected completion this week

Design Firm: Contractor: FCT Contractor Name:

2015‐2607

2299 Memorial Union Building ‐ New Deck Railings (rev 3)

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Stairs under construction 8‐20

Design Firm: Contractor: External Contractor Name: Milestone

2015‐2299

1475 Memorial Union Building ‐ Lactation Room Floor 3

3‐ IN CONSTRUCTION

FCRCARTABONA, STEPHANI

8/27/15 Signage ordered from Portsmouth Sign.  Work order issued to FCT for automatic door 

opener.

Design Firm: Mannypenny Murphy Contractor: FCT Contractor Name: Milestone

2013‐1475

2606 Memorial Union Building ‐ Refinish 45 Doors

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15 Approved.  Reviewing list of doors and scheduling with customer

Design Firm: Contractor: FCT Contractor Name:

2015‐2606

2816 Memorial Union Building ‐ Rms 221G, 223B Electrical Work

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15  Scheduled to begin 8/31

Design Firm: Contractor: FCT Contractor Name:

2016‐0026

Mills Hall Projects in Building 1

Monday, August 31, 2015 Page 14 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 15: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2225 Mills Hall ‐ Chiller Plant Retrocommissioning

1.1‐ PLAN/EST

FCRROULEAU, RICHARD A

8/31/2015 Update: Retrocommissioning is complete.  With the students back, Holloway in full‐

swing and hot weather expected, final verification should occur the first week of September.  

Related Projects: Portal ID#s 1443 and 1657

Design Firm: RFS Commissioning Contractor: External Contractor Name: Rist‐Frost‐Shumway Engineering (commissioning)

2015‐2225

Morrill Hall Projects in Building 2

2864 Morrill Hall ‐ Rm 4 Renovations

1.1‐ PLAN/EST

FCRHENRY, PAUL A

Sent FCR to Stakeholders. 8‐13

Design Firm: Contractor: Contractor Name:

2016‐0067

2609 Morrill Hall ‐ 1st Floor Window Replacement‐ Ice Damage

1.1‐ PLAN/EST

RR

Emergency Repair

WOODCOCK, JONATHAN

8/27/2015_Currently estimating repairs, building secure.

Design Firm: Contractor: Contractor Name:

2015‐2609

Morse Hall Projects in Building 1

2384 Morse Hall ‐ Rm 345 Renovations

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Project under construction, expected completion Mid Sept. 8‐20

Design Firm: Harriman Contractor: External Contractor Name: TBD

2015‐2384

Nesmith Hall Projects in Building 2

1972 Nesmith Hall ‐ Exterior Brick Wall and Parapet Repointing

2.5‐ IN PROCUREMENT

RRWOODCOCK, JONATHAN

8/27/2015_ Scheduling work with vendor during off hours.

Design Firm: TBD Contractor: External Contractor Name: TBD

2014‐1972

Monday, August 31, 2015 Page 15 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 16: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

1716 Nesmith Hall ‐ Repair and Renovate 8 Classrooms

3‐ IN CONSTRUCTION

RRWOODCOCK, JONATHAN

8/27/2015_ Under construction through FCT.  Expected completion by 8/31/15

Design Firm: Contractor: FCT Contractor Name:

2013‐1716

New England Center Projects in Building 2

1683 New England Center ‐ Relocation of Photo Video Department

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Move is complete, waiting for some furniture items due in August, working on punch list 8‐20

Design Firm: Harriman / Many Penny Contractor: External Contractor Name: Milestone

2014‐1683

2827 New England Center ‐ Picnic Tables

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

Ordered picnic tables on 7/27/15. Expected arrival 9/25/15

Design Firm: Contractor: FCT Contractor Name:

2016‐0037

New Hampshire Hall Projects in Building 1

940 New Hampshire Hall ‐ Major Roof Replacement

2‐ IN DESIGN

RRWOODCOCK, JONATHAN

8/27/2015_ Project to be re‐bid in late fall for a May 2016 start.

Design Firm: TBD Contractor: External Contractor Name: TBD

2013‐0940

Outdoor Pool Projects in Building 1

2059 Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility

3‐ IN CONSTRUCTION

CPHAGSTROM, DONALD P

Working through some DES issues.     Construction scheduled for 8/2015

Design Firm: water technologies Contractor: External Contractor Name: Shawmut

2014‐2059

Parking and Transit Center Projects in Building 3

Monday, August 31, 2015 Page 16 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 17: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2718 Parking and Transit Center ‐ Mast Road Gate Replacement

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15 Our work complete, gate activation due Friday 8/28

Design Firm: Contractor: FCT Contractor Name:

2015‐2705

2379 Parking and Transit Center ‐ Install & Activate CNG Refueling Equipment

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

Project plan has been presented to the SFMO. Work will progress with the understanding 

engineering to back up any progress will be provided before final inspections.Work is 

progressing, we are working on a punch list.   8‐25‐15

Design Firm: Contractor: FCT Contractor Name: Badger Rand / Yates & others

2015‐2379

2396 Parking and Transit Center ‐ Fire Alarm System/Replacement

3‐ IN CONSTRUCTION

FCRCARTABONA, STEPHANI

8/27/15 Norris Inc is preparing submittals and coordination drawings.  Anticipated installation 

to occur during Holiday break 2015‐2016 due to building occupancy.

Design Firm: SFC Engineering Contractor: External Contractor Name: Norris Inc.

2015‐2396

Parsons Hall Projects in Building 5

2845 Parsons Hall ‐ Rm S106 Laboratory Air Dryer Installation

1.1‐ PLAN/EST

RR

Emergency Repair

CARDOSO, ANDRE W

Work to be performed in September, 2015.

Design Firm: TBD Contractor: Contractor Name: TBD

2016‐0055

2626 Parsons Hall ‐ Processed Chiller Modifications

2‐ IN DESIGN

RR

Emergency Repair

CARTABONA, STEPHANI

8/27/15 EYP provided location of pressure sensors, awaiting confirmation from zone 3 if these 

have been verified and adjusted.

Design Firm: EYP Contractor: External Contractor Name: TBD

2015‐2626

1704 Parsons Hall ‐ Mechanical Penthouse Waterproofing DESIGN ONLY

2‐ IN DESIGN

RRWOODCOCK, JONATHAN

8/27/2015_ Schematics in for review and estimating.

Design Firm: EYP/ARM Contractor: TBD Contractor Name:

2014‐1704

Monday, August 31, 2015 Page 17 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 18: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

1030 Parsons Hall ‐ Hallway Ductwork Insulation / Ceiling Repairs

2.5‐ IN PROCUREMENT

RRJONES, KATHLEEN M

8/27/15: Adjustments have been made to temperature controls with input from energy office and 

mechanical enigneer. We will continue to monitor the ductwork. FCT to seal doorways in 

September to prepare for next summer.

Design Firm: Contractor: FCT Contractor Name:

2014‐1030

2751 Parsons Hall ‐ Rm S234 Installation of Drying Racks

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15  One Installed, counter modification required for the 2nd one.

Design Firm: Contractor: FCT Contractor Name:

2015‐2736

Paul Creative Arts Center Projects in Building 3

46 Paul Creative Arts Center ‐ Sprinkler Installation and Egress Modifications DESIGN

2.5‐ IN PROCUREMENT

RRCARTABONA, STEPHANI

8/27/15 Awaiting confirmation from Port City Architecture, if less 20% wall coverage installed 

tack board solution may be modified.

Design Firm: Port City Architecture/ SFC E Contractor: FCT Contractor Name:

2009‐0046

1157 Paul Creative Arts Center ‐ Egress Modifications Phase 1 of 2

2.5‐ IN PROCUREMENT

RRCARTABONA, STEPHANI

Please refer to ID 46 for ongoing updates ‐ All work will be reported and tracked ID 46.

Design Firm: Port City Architecture / SFC  Contractor: FCT Contractor Name: TBD

2013‐1157

2866 Paul Creative Arts Center ‐ Water Line Replacement

2.5‐ IN PROCUREMENT

RR

Emergency Repair

JONES, KATHLEEN M

8/27/15: Small repair was made on August 19, and date of final repair is TBD. This work will be 

scheduled for a Saturday in September, exact date TBD.

Design Firm: Contractor: External Contractor Name: RH White

2016‐0069

Pettee Hall Projects in Building 1

Monday, August 31, 2015 Page 18 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 19: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2631 Pettee Hall ‐ Restoration and Recommissioning HV‐1 and HV‐2

3‐ IN CONSTRUCTION

RR

Emergency Repair

CARTABONA, STEPHANI

8/27/15 Determined building dual temp system needs to be fully flushed, valves inspected.  

Potentially winter 2015 make ready for summer 2016 building flush.  emergency lighting 

inverter failed due to moisture in mechanical room, this work will be added to the scope.  

Emergency batter back up units in place for emergency lighting.  FCT has cleaned and painted 

mechanical room.  Work near complete on mechanical room.

Design Firm: RFS Contractor: FCT Contractor Name: TBD

2015‐2631

Philbrook Hall Projects in Building 1

2492 Philbrook Hall ‐ Refrigeration Rack System

2.5‐ IN PROCUREMENT

FCRCARTABONA, STEPHANI

8/27/15 FCR submitted to OBA/Dining for funding, awaiting authorization to proceed.

Design Firm: Harriman Assoc. Contractor: External Contractor Name: TBD

2015‐2492

Presidentʹs House Projects in Building 1

2650 Presidents House ‐ Porch Enclosure and ADA Modifications

3‐ IN CONSTRUCTION

RRGEUTHER, MARK E

8‐20: Porch stairs in place, new door installed, flooring complete, ready for paint and millwork. 

Completion scheduled for 8/25.

Design Firm: ManyPenny‐ Murphy Archit Contractor: External Contractor Name: Milestone Construction

2015‐2650

Ritzman Lab Projects in Building 1

1794 Ritzman Lab ‐ Conference Room Technology

3‐ IN CONSTRUCTION

FCRCARTABONA, STEPHANI

8/27/15 Furniture to be delivered September 2015,   AV technology to be installed September 

2015.  Floor 1 and floor 2 conference room to have upgrade.

Design Firm: Contractor: FCT Contractor Name: Adtech / Creative Office Pavillion

2014‐1794

Roads/Grounds Projects in Building 6

184 Signs ‐ Campus wayfinding and University building sign improvements

1.1‐ PLAN/EST

SIBENCKS, DOUGLAS C

Design Firm: Contractor: Contractor Name:

2008‐0184

Monday, August 31, 2015 Page 19 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 20: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

295 Campus ‐ Bike Rack Installations

1.1‐ PLAN/EST

SIPESCI, STEPHEN T

Design Firm: Contractor: Contractor Name:

2010‐0295

1142 Memorial Union Building ‐ Ravine Walkway Replacement ‐ DESIGN ONLY

2‐ IN DESIGN

RRHENRY, PAUL A

Heating Line SOW added to project, and now requires changes in building, Harriman added to 

design team, Design will resume this summer ,  construction Summer 2016. Design back on track 

7‐28

Design Firm: Tigh & Bond Contractor: External Contractor Name: TBD

2013‐1142

2767 Ravine Culvert Replacement

2‐ IN DESIGN

RR

Emergency Repair

JONES, KATHLEEN M

8/27/15: Design of culvert repair to be completed and engineer to meet with Durham 

Conservation Commission on September 10, then submit application for NHDES wetlands 

permit by September 18, then we will wait to receive the necessary permits to continue with 

construction of repair. Culvert has a temporary steel plate over it for pedestrian access.

Design Firm: Hoyle Tanner Contractor: External Contractor Name: T&S Construction

2016‐0002

1115 South Drive ‐ Design Advancement

2‐ IN DESIGN

SIHENRY, PAUL A

Permits approved, this phase of the design complete. CP looking for funding options, nothing 

scheduled for 2014.

Design Firm: Tigh & Bond Contractor: External Contractor Name:

2013‐1115

75 University Campus Exterior Lighting Improvements

3‐ IN CONSTRUCTION

SIHOUDE, DONALD A

 All the exterior lighting has been installed. It needs to be reviewed. , There is a small punch list. 

8‐25‐15

Design Firm: Contractor: Contractor Name:

2008‐0075

Rollins Water Treatment Bldg Projects in Building 1

Monday, August 31, 2015 Page 20 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 21: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

38 UNH R&R Water Treatment Plant Improvements

2‐ IN DESIGN

SIHAGSTROM, DONALD P

spring pilot test complete.Met with state.  fall testing to start 10/15. will do subsurface 

investigation at waterworks site this  8/26

Design Firm: Wright‐Pierce Contractor: External Contractor Name:

2008‐0038

Rudman Hall Projects in Building 4

764 Rudman/Spaulding Hall ‐ Replacement of built in Glass Washers  Phase II of II

1.1‐ PLAN/EST

RRHOUDE, DONALD A

The dept has to choose the product, I expect a decision this week will plan on a Winter break 

installation. . 8‐25‐15

Design Firm: Contractor: Contractor Name:

2011‐0764

2352 Rudman Hall ‐ Fire Alarm Replacement

1.1‐ PLAN/EST

RRCARTABONA, STEPHANI

Fire alarm installation will occur following design. Coordinate acitivity with building occupants 

prior to construction schedule.

Design Firm: Contractor: Contractor Name:

2015‐2352

1149 Rudman Hall ‐ Fire Alarm Replacement

2‐ IN DESIGN

RRCARTABONA, STEPHANI

7/27/15 SFC to provide 50% drawings by end of July 2015

Design Firm: SFC Engineering Contractor: External Contractor Name: TBD

2013‐1149

1787 Rudman Hall ‐ Fume Hood / HVAC Modifications and Repairs

3‐ IN CONSTRUCTION

RRCARTABONA, STEPHANI

8/27/15 Installed new controls in floor 3 labs, reviewing all mechanical equipment in each lab 

after controller installation.

Design Firm: RFS Contractor: FCT Contractor Name: TBD

2014‐1787

Service Building Projects in Building 4

Monday, August 31, 2015 Page 21 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 22: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2593 Service Building ‐ Ice Melt System Fire Dept Roof

1.1‐ PLAN/EST

RRWOODCOCK, JONATHAN

8/27/2015_ Ice melt in proposal phase.

Design Firm: Contractor: FCT Contractor Name:

2015‐2593

1465 Service Building ‐ Replacement and Installation of Isolation valves

2‐ IN DESIGN

RRCARDOSO, ANDRE W

Please see ID #  2358 for updates associated with this project.

Design Firm: N/A Contractor: External Contractor Name: TBD

2013‐1465

2358 Service Building ‐ Heating Line Replacement Design

2‐ IN DESIGN

RRCARDOSO, ANDRE W

Harriman Associates has been selected as the design firm. Design is underway with 90% 

documents due for review by October 1.

Design Firm: Harriman Associates Contractor: External Contractor Name: TBD

2014‐2358

2331 Service Building ‐ DFD Kitchen new vent hood rm F214

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Instillation under way, FCT has an issue with the Hood, bad electronics, part on order. 8‐20

Design Firm: Contractor: FCT Contractor Name:

2015‐2331

SPAULDING HALL Projects in Building 3

2878 Spaulding Hall ‐ Steam Condensate Line Replacement

2‐ IN DESIGN

RR

Emergency Repair

JONES, KATHLEEN M

8/27/15: PM has met with mechanical engineer to begin design process. New condensate return 

line to be installed between Spaulding and Rudman in lieu of replacing existing line in Conant 

Courtyard. Project is procuring design services, then once design is complete a term contractor 

will be hired to make the repair, likely in October or November 2015.

Design Firm: Harriman Contractor: Contractor Name:

2016‐0080

2480 Spaulding Hall ‐ Renovations rms 232, 234, 234A

3‐ IN CONSTRUCTION

FCRCARDOSO, ANDRE W

Work is ongoing with completion scheduled for September 25.

Design Firm: TBD Contractor: FCT Contractor Name: Shawmut Design and Construction

2015‐2480

Monday, August 31, 2015 Page 22 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 23: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2539 Spaulding Hall ‐ Fume Hood Alarm Upgrades

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

Project funded waiting for FCT 8‐20

Design Firm: Contractor: FCT Contractor Name:

2015‐2539

Thompson Hall Projects in Building 2

2727 Thompson Hall ‐ Presidents/Lubow Conference Rooms AC

2‐ IN DESIGN

RRCARTABONA, STEPHANI

8/27/15  Harriman will review chilled water capacity in the building to install ductless split 

system in both conference room.

Design Firm: Harriman Contractor: FCT Contractor Name:

2015‐2714

2764 Thompson Hall ‐ Rm 102C Office Painting

3‐ IN CONSTRUCTION

FCRHEALEY, RANDY L

8/27/15  Original SOW complete. Working on expanded SOW

Design Firm: Contractor: FCT Contractor Name:

2015‐2749

Utility Distribution Projects in Building 2

2362 Quad Way ‐ Utility Line Replacement (Design Only)

2‐ IN DESIGN

RRJONES, KATHLEEN M

8/27/15: Project is in design stage for construction in summer 2016. Design is under contract and 

will be completed by October 31, 2015.

Design Firm: Tighe & Bond Contractor: Contractor Name:

2015‐2362

2658 Ravine Electrical Circuit 11B Extension

3‐ IN CONSTRUCTION

SIHOUDE, DONALD A

This project is 70% complete. Temp power has been installed, Ravine work MH & Ducts 

complete.  To do, HS extend perm ducts instal bases, Install cableing. . 8‐25‐15

Design Firm: Contractor: External Contractor Name: IC Reed & Sons Inc.

2015‐2658

Veterinary Diagnostic Lab Projects in Building 2

Monday, August 31, 2015 Page 23 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 24: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2053 NHVDL ‐ Campus Deferred Repair Costs

3‐ IN CONSTRUCTION

RRCARTABONA, STEPHANI

reported with ID 1537

Design Firm: Port City Architecture Contractor: External Contractor Name: Allied Cook

2014‐2053

1537 NHVDL ‐ Relocation

3‐ IN CONSTRUCTION

SICARTABONA, STEPHANI

7/27/15 Interior finishes ongoing.  Lab casework scheduled to arrive early August.  Unitil gas line 

installation to begin 8/3.  Schedule completion / move in August 2015.

Design Firm: Port City Architecture Contractor: External Contractor Name: Allied Cook

2013‐1537

West Stadium Projects in Building 1

1947 West Stadium ‐ Design and Construction of New Facility

3‐ IN CONSTRUCTION

SIGEUTHER, MARK E

8‐20: Utility crossings for tel/data and natural gas scheduled for the week of 8/24 (Colovos Rd & 

Sage Way respectively). Building foundations complete and bridge foundations started. Field 

light poles have been placed/relocated. Steel erection crane to mobilize on site the week of 8/24, 

first shipment of structural steel scheduled for on or about Sept 1st.

Design Firm: Populous/LaVallee Brensinge Contractor: External Contractor Name: PC Construction

2014‐1947

Whittemore Center ‐ Arena Projects in Building 6

2724 Whittemore Center ‐ Arena ‐ Lighting Controller Replacement

2‐ IN DESIGN

FCRHOUDE, DONALD A

Harriman has PO. Working on the Study, should be ready for presentation the first week of 

Sept.  8‐25‐15

Design Firm: Harriman A&E Contractor: External Contractor Name: Unknown

2015‐2709

2581 Whittemore Center ‐ Arena ‐ Ice Sensor System Back Up Power

2‐ IN DESIGN

FCRHOUDE, DONALD A

The study has been provided, I am setting up a meeting to review the study.. . 8‐25‐15

Design Firm: OPA Contractor: Contractor Name:

2015‐2581

Monday, August 31, 2015 Page 24 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 25: Facilities Project Management Monthly Report Building · PDF fileFacilities Project Management Monthly Report by ... 2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and ... approval

ID PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

2578 Whittemore Center ‐ Arena ‐ Generator Upgrade

2‐ IN DESIGN

FCRHOUDE, DONALD A

The pre ‐ final study report just arrived.I am setting up a meeting to review discuss the Study 

results.  8‐25‐15 .

Design Firm: OPA Contractor: Contractor Name:

2015‐2578

2720 Whittemore Center ‐ Arena ‐ Ice Making System Mechanical Replacements

3‐ IN CONSTRUCTION

FCRCARTABONA, STEPHANI

8/27/15 Chiller installation is complete.  Start up / test chiller 8/31/15 for operations to begin 

making ice 8/6/15.  Temporary chiller will be removed from site following new chiller start up 

and run time.  Operations office reconstruction to begin 9/8 with completion on or before 10/1.

Design Firm: Hoyle Tanner Contractor: FCT Contractor Name: American Refrigeration Company, Inc. / Milestone 

2015‐2707

2584 Whittemore Center ‐ Arena ‐ Videoboard

3‐ IN CONSTRUCTION

FCRWOODCOCK, JONATHAN

8/27/15_Ribbon displays installed.  Center hung installed between 8/30 ‐9/3/2015.  Production 

room continues itʹs remodel.

Design Firm: AJP Contractor: External Contractor Name: Daktronics

2015‐2584

2721 Whittemore Center ‐ Arena ‐ Block Wall Removal and Structural Support Installation

3‐ IN CONSTRUCTION

FCRCARTABONA, STEPHANI

6/30/15 ‐‐ Please refer to 2720 for updates

Design Firm: Contractor: Contractor Name:

2015‐2708

Whittemore Center ‐ Hamel Projects in Building 1

1176 Hamel Recreation Center ‐ Renovation and Expansion Project

3‐ IN CONSTRUCTION

CPHAGSTROM, DONALD P

GMP approved. Grade beams complete in August.  Steel starting in September.

Design Firm: HGA Contractor: External Contractor Name: Shawmut

2013‐1176

Monday, August 31, 2015 Page 25 of 25University of New Hampshire

Brenda Whitmore, Director Facilities Project Management


Recommended