HEALTHY GLOVE CO., LTD
Factory Profile &
Glove Manufacturing
Agendas 2 /26
Factory information
Healthy glove products information
Certification and Registration
Glove manufacturing
Steam boiler
Water supply and waste water treatment
Hazards waste management
The drinking water, toilet and hostel
More benefit after Healthy growth
Question & Answers
Factory information
Krabi plant:
288, Moo.7
T. Lam-Thap
A. Lam-Thap
Krabi, 81190 Thailand
Tel/Fax: +66 75 626500
http://www.healthyglove.com
Total 5 lines double former
Hatyai plant:
119 Kanchanavanich Road,
T.Pathong,
A.Hatyai,
Songkhla 90230 Thailand
Tel: +66 (0) 74 536815
Fax: +66 (0) 74 536816
Total 52 lines single former
3 /26
Examination Gloves 4 /26
ISO 9001 : 2008 : TUV SUD (31-03-2015)
ISO 13485 : 2013 : TUV SUD (31-03-2015)
Health Canada : Medical Device License of Canada (17-07-2015)
Thai FDA : Thai FDA (01-12-2015)
CFS by Thai FDA : India, Columbia, Mexico, China( Ammex, Maoming) and HG
SFDA of Saudi Arabia :
TISI Mark : Pending for factory audit in the end of August 2016
GMP Thai Medical Devices : Thai FDA (16-12-15)
PPE Directive (89/686/EEC) by SATRA UK : Under Product testing
Certification and Registration
5 /26
Glove manufacturing: R&D
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
6 /26
Glove manufacturing (Cont.): Raw material
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
7 /26
Glove manufacturing (Cont.): Compounding
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
8 /26
Glove manufacturing (Cont.): Dipping
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
Rinse#3
2850
Acid
2850
Rinse#1
2850
Alka l i#1
2850
Alka l i#2
5850
Curcular
brush
Latex
dip#1
Coagulant
oven
Coagulant
oven
Cagulant dip
8500
Rinse#4
2850
Beading#2
Post-
cure#3
5850
Post-
cure#2
5850
Post-
cure#1
5850
Long
brush#1
Long
brush#2
Rinse#2
2850
Latex
dip#2
Latex
oven#2
Pre-cure#1
5850
Pre-cure#2
13750
Pre-cure#3
5850
Polymer
dip
Polymer
oven
Latex
oven#1 zone
2
Latex
oven#1 zone
1
Main zone oven 1-4 (Dry) Main zone oven 1-3 (Wet) Beading#2
Slurry
oven
Slurry dip
4000
Auto
s tacking &
counting 2
Auto
s tacking &
counting 1
Auto
s tripping#
2
Auto
s tripping#
1
Cuffing
brush#2
Cuffing
brush#1
Former cleaning process
9 /26
Glove manufacturing (Cont.): Dipping
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
Coagulant dipping >> Coagulant drying >> Latex dipping >>
Latex gel drying >> Polymer dipping >> Polymer drying
10 /26
Glove manufacturing (Cont.): Dipping
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
Auto stripping Auto stacking & courting
Beading Cuffing
11 /26
Glove manufacturing (Cont.): Dipping
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
Lab in-process testing
12 /26
Glove manufacturing (Cont.): Dipping
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
QC in-process & QA in-procss inspection
13 /26
Glove manufacturing (Cont.): Packing
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
On-line packing Off-line packing
QA pre-shipment inspection
14 /26
Glove manufacturing (Cont.): Finish good
Finish good testing
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
15 /26
Glove manufacturing (Cont.): Warehouse
Warehouse and loading
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
16 /26
Glove manufacturing (Cont.)
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
In front of lines production
17 /26
Glove manufacturing (Cont.)
Lab in-comingInspection
R&D process
Reveive raw ,aterial
Compounding
Lab in-processInspection
Dipping
QC in-processInspection
Packing
QA pre-shipment Inspection
Shipping
Back lines production
18 /26
Steam Boiler
Stack measurement (Boiler):
o Total Suspended Paticulate (TSP)
o Sulfur dioxide (SO2)
o Oxides of nitrogen as Nitrogen
dioxide (NO2)
o Carbon monoxide (CO)
o Opacity
19 /26
Water supply and treatment 20 /26
Hazards waste management 21 /26
The drinking water 22 /26
Tree unit for dipping and packing: Entrance dipping line and second floor
One unit for office and all: Office
One unit for compounding, PD and R&D and Laboratory: Compounding office
There are enough drinking water total 8 units.
One unit for all: Canteen
One unit for boiler and former: Boiler area
One unit for engineering: Maintenance shop
Toilet 23 /26
Office toilet
Female: 2 rooms
Male: 2 rooms
Toilet No. 1
Entrance in front of dipping line
Female: 4 rooms
Male: 4 rooms
Toilet No. 2
Entrance middle of dipping line
Female: 4 rooms
Male: 4 rooms
Toilet No. 3
In front of engineering office
Female: 2 rooms
Male: 2 rooms
Toilet No. 4
Canteen
Female: 10 rooms
Male: 4 rooms
There are enough toilet for our worker and staff total 38 rooms; 22 and 16 rooms
for female and male, respectively.
Canteen, Worker hostel and Staff hostel 24 /26
Canteen Worker hostel Staff hostel
More benefit
Fewer unemployed
Alternative source for internship
Stimulate the economy Local 79%
Foreign (Myanmar)
21%
Staff 30%
Worker 70%
Lumtup, 67.75
Khlong Thom, 6.78
Nuea Khlong,
0.54
25 /26
THANK YOU VERY MUCH
FOR YOUR KIND ATTENTION