Department of Transportation Public Workshop #4 - 11/2/16 Matt Darrow, PE – Sacramento County Adrian Engel, PE – Fehr & Peers Fair Oaks Boulevard Complete Streets Project
Transcript
Page 1: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Department of TransportationPublic Workshop #4 - 11/2/16

Matt Darrow, PE – Sacramento CountyAdrian Engel, PE – Fehr & Peers

Fair Oaks Boulevard Complete Streets Project

Page 2: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Project Funding

• Project funding is provided by a grant from Sacramento Area Council of Governments (SACOG) 2014 Bicycle and Pedestrian Funding Program

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 2November 2, 2016

Page 3: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Project Area

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 3November 2, 2016

Page 4: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Project Objectives

• Improve mobility of pedestrian, bicyclists, motorists and transit

• Create a sense of place and center of activity• Strengthen neighborhood cohesiveness• Stimulate economic development

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 4November 2, 2016

Page 5: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

• Develop multimodal streetscape master plan for Fair Oaks Boulevard from Howe Avenue to Munroe Street

• Construct two signalized pedestrian crossings on Fair Oaks Boulevard as Phase 1

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 5November 2, 2016

Page 6: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Do Something

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 6November 2, 2016

Do you support making changes to the corridor?

Do Nothing

Minor changes

Neutral

Moderate changes

Substantial Changes

Page 7: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Concept 1

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 7November 2, 2016

• 6 Travel Lanes, Two-way Frontage• 3 New Pedestrian Crossings• Sidewalk Enhancements

• Bike Route with Frontage Roads• Bike Lanes on ends of Fair Oaks Blvd• Minimal Changes to Traffic Patterns

Page 8: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

November 2, 2016 Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 8

Do you support Concept 1 (6 lanes, pedestrian signals, bike routes, improved sidewalks)?

Do Not Support Little Support

Neutral Support

Strongly Support

Would you consider replacing auto trips with walking or

riding a bike with Concept 1?

Very Unlikely Unlikely

Neutral Likely

Very Likely

Concept 1

Page 9: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Concept 2

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 9November 2, 2016

• 6 Travel Lanes, One-way Frontage• 3 New Pedestrian Crossings• Sidewalk Enhancements

• Bike Lanes with Frontage Roads• Bike Lanes on ends of Fair Oaks Blvd• Moderate Changes to Traffic Patterns

Page 10: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

November 2, 2016 Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 10

Do you support Concept 2 (6 lanes, pedestrian signals, bike routes, improved sidewalks)?

Do Not Support Little Support

Neutral Support

Strongly Support

Would you consider replacing auto trips with walking or

riding a bike with Concept 2?

Very Unlikely Unlikely

Neutral Likely

Very Likely

Concept 2

Page 11: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Concept 3

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 11November 2, 2016

• 4 Travel Lanes, Two-way Frontage• 4 New Pedestrian Crossings• Sidewalk Enhancements

• Protected Bikeways on Fair Oaks Blvd• Major Changes to Traffic Patterns• Sierra Intersection Modifications

Page 12: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

November 2, 2016 Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 12

Do you support Concept 3(4 lanes, signals at Fulton and

University, protected bikeways, improved walks)?

Do Not Support Little Support

Neutral Support

Strongly Support

Would you consider replacing auto trips with walking or

riding a bike with Concept 3?

Very Unlikely Unlikely

Neutral Likely

Very Likely

Concept 3

Page 13: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Preferred Alternative

• Enhanced pedestrian environment• Two signalized pedestrian crossings• Two new all mode traffic signals

– University Ave and Fulton Ave

• Modified Sierra Blvd signal (Alt 3B)• Two-way frontage roads• 4 lanes on FOB with protected bikeway• Additional landscaping and trees

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 13November 2, 2016

Page 14: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Traffic Signals

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 14November 2, 2016

Fair Oaks Blvd / University Ave Fair Oaks Blvd / Fulton Ave / Fairgate Rd

Page 15: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Munroe and Sierra

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 15November 2, 2016

Improved 5-legged Intersection

Page 16: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Protected Bikeway

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 16November 2, 2016

Photo: Nick Falbo

Page 17: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Preferred Alt.

Non-PeakCondition Peak Conditions

Performance Measure Existing Existing Phase 1 Preferred

Alternative

Average Travel Time 1.5 minutes 2.1 minutes 2.7 minutes 3.3 minutes

Travel Speed 45 mph 33 mph 22 – 33 mph 20 mph

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 17November 2, 2016

Page 18: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Outside of FOB

• Sidewalk improvements along FOB east of Munroe St.

• Fill sidewalk gaps on Sierra Blvd• Bicycle Connections to American River

Parkway• Pedestrian crossing on Fulton Ave• Collaborate with City for pedestrian crossing

of Munroe St. near Latham Drive

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 18November 2, 2016

Page 19: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Phase 1

• Two new pedestrian crossings– Loehmann’s Plaza & Pavilions– Traditional signal heads (interim)– High visibility markings and bulb outs on frontage

roads– Maintain existing median openings and evaluate

operations

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 19November 2, 2016

Page 20: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Phase 1

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 20November 2, 2016

Near Talbots and McDonalds

Near Loehmann’s Plaza and Sierra Fair Apts

Page 21: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Costs

• Phase 1 – Two new pedestrian signals with related curb and sidewalk enhancements

$700,000

• Preferred Alternative – Pedestrian enhancements, two new signals, protected bikeway, Trees and median improvements

$6,500,000 - $8,000,000

Sacramento County Department of TransportationFair Oaks Boulevard Complete Streets Project 21November 2, 2016

Page 22: Fair Oaks Boulevard Complete Streets Project...roads – Maintain existing median openings and evaluate operations. Sacramento County Department of Transportation Fair Oaks Boulevard

Next Steps

• Finalize Draft of Master Plan• Environmental Clearance• Preliminary Engineering of Phase 1• Planning Commission and/or CPAC• Board of Supervisors