Pip
eli
ne
s
1
Farm Taps
DIMP or Not
Could It Be Any More Messed UP?
3
You know – the OQ Rule Without the OQ
Amdt. 192-123, 82 FR 7972, January 23, 2017
Miscellaneous II Rule
4
� Amdt. 192-113, 74 FR 63905, December 4, 2009
� FAQ’s• C.3.7 Are operators required to include “farm taps” in their distribution
integrity management plan?
• “… The vast majority of “farm taps” meet the definition of a distribution line given that they do not meet the criteria to be classified as a gathering line or a transmission line. …”
• “… Operators of distribution, gathering, and transmission lines with “farm taps”
must have a distribution integrity management program meeting the
requirements of Subpart P for this distribution pipeline. …”
Distribution Integrity Management Rule
5
� Intent • Was intended only for those
operators that didn’t otherwise have DIMP plan
� Cost / Benefit
• In this provision, farm taps would be removed from the DIMP program in favor of a less stringent set of inspection activities and over-pressurization protection equipment. This change would yield cost savings for operators.
• However, it was previously estimated that implementing a DIMP program and conducting required mitigation would cost the affected industry approximately $78 million per year after start-up. Removing farm taps from DIMP would relieve a small portion of these costs.
Unintended Consequences
6
� Individual service lines directly connected to production, gathering, or transmission pipelines
�A New Code Section -§192.740
Pressure regulating, limiting, and overpressure protection
� Inspect and Test … equipment every 3 years NTE 39 mos., to determine;
• Mechanical condition• Adequate• Set to function correctly• Properly installed
7
� Cost Savings for Removal From DIMP
� Cost to Rebuild for Testing and Inspection???
(no consideration in RFA)
Costs
8
� Interpretation 192.739 14 - October 22, 1992
• “… Regulator stations must be inspected and tested to comply with §192.739 using any practicable method that will demonstrate the presence or absence of the listed qualities. Set-point, lock-up, and full-stroke-operation would be part of the inspection and testing if such tests are practicable at the station concerned. …”
Rebuild to Facilitate Testing??
9
� Interpretation 192.739 15 – April 28, 1993
• “… In addition, to us, practicable inspections and tests do not require the operator to disassemble the regulator, re-pipe the regulator, or cut off the supply of gas to the system. Instead, we suggest that, as a minimum, these service-type regulators be visually inspected, be checked for leaks (including the regulator vent), and be checked for correct set-point. Verifying the correct set-point on a service-type regulator can be done by measuring the pressure of the gas (downstream of the regulator) with a pressure gauge. …”
Rebuild to Facilitate Testing ??