+ All Categories
Home > Documents > FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an...

FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an...

Date post: 05-Oct-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
18
FDEP Springs Initiative FY2018 Final Evaluations
Transcript
Page 1: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

FDEP Springs Initiative FY2018 Final Evaluations

Page 2: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.
Page 3: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Table of Contents

Northern Region Springs Projects - Recommended

P134 - Springs - Citrus County AWT Upgrades to the Brentwood WWTF........................................ 1

P136 - Springs - Citrus Co. Brentwood to Meadowcrest Recl. Water Sys. Interconnection.............. 2

P137 - Springs - Citrus County Northwest Quadrant Sewer Extension............................................. 3

P138 - Springs-City of Brooksville Mtn. Prk Subd. Septic Tanks Abandonment to Cntrl Sewer Sys. 4

P139 - Springs - City of Brooksville Hernando Oaks Golf Course Reclaimed Water........................ 5

P140 - Springs - City of Crystal River Indian Waters Septic-to-Sewer Phase II................................ 6

P142 - Springs - City of Williston Northwood Estates Septic-to-Sewer............................................. 7

P143 - Springs - City of Williston WWTP AWT Upgrade................................................................... 8

P144 - Springs - Marion County Rainbow Springs Central Sewer Feasibility Study......................... 9

Northern Region Springs Projects - Not Recommended

P135 - Springs - Citrus Co. Chassahowitzka to Sugarmill Woods Wastewater Interconnection....... 10

P141 - City of Dunnellon Wastewater Collection SCADA System..................................................... 11

Tampa Bay Region Springs Projects - Recommended

N635 - Restoration-Pasco County Crews Lake Natural Systems Construction Phase..................... 12

P146 - Springs - Pasco Co. Septic Tank Abatement Feasibility Study in the Weeki Wachee Springshed. 13

Page 4: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.
Page 5: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P134

Citrus County

Springs - Citrus County AWT Upgrades to the Brentwood WWTF

Type 2 Multi-Year Contract: No

FY2018

Description

Construction upgrades to the existing Brentwood WWTF to advanced wastewater treatment

standards.

Description:

The contractual Measurable Benefit will be the installation of necessary components for a fully

operational municipal sanitary sewer system that will meet advanced wastewater treatment

standards.

Measurable Benefit:

Total Project Cost: $1,508,000 (Construction only);

Citrus County: $754,000;

District: $0;

FDEP: $754,000.

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI Guidelines.

District PM had to work with the Cooperator to obtain required information.

Medium

The benefit of the project is the reduction of pollutant loads to Kings Bay/Crystal River

springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will

be no monitoring or performance testing requirements.

Project Benefit: High

The $3.67 per pound of total Nitrogen removed is below the average cost of $224/lb of

previously funded stormwater projects.

Cost Effectiveness: High

Past Performance: Based on an assessment of the schedule and budget for the 3 ongoing projects.High

Complementary Efforts: The cooperator has a mandatory sewer connection ordinances, and enforces it.High

Project is not expected to begin until after March 1, 2018.Project Readiness: Low

Strategic Goals

Strategic Goals: High Strategic Initiative - Alternative Water Supplies: Increase development of

alternative sources of water to ensure groundwater and surface water sustainability.

Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project will result in water quality improvements to the Kings Bay/Crystal River springshed,

a SWIM Priority water body. Recommend forwarding project to FDEP for funding consideration

subject to Legislative Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$754,000$0 $754,000Citrus County

$0$754,000$0 $754,000FDEP

Total $0 $1,508,000 $0 $1,508,000

1

Page 6: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P136

Citrus County

Springs - Citrus County Brentwood to Meadowcrest Reclaimed Water System

Interconnection

Type 2 Multi-Year Contract: No

FY2018

Description

Construction of a reclaimed waterline to interconnect the Brentwood WWTF to the Meadowcrest

WWTF to increase reclaimed water availability for reuse or recharge.

Description:

The contractual Measureable Benefit will be the construction of approximately 29,000 feet of

reclaimed water line to interconnect the upgraded Brentwood WWTF to the Meadowcrest

WWTF.

Measurable Benefit:

Total Project Cost: $5,260,000 (Construction only)

Citrus County: $2,630,000

District: $0.00

FDEP: $2,630,000

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI Guidelines.

District PM had to work with the Cooperator to obtain remaining information.

Medium

The benefit of this project is the reduction of pollutant loads to the Kings Bay/Crystal

River watershed, a SWIM priority water body, by an estimated 18,797 lbs/yr TN and

the supply of 0.50 MGD of reclaimed water. There will be no monitoring or performance

testing requirements.

Project Benefit: High

$10.52 per gallon per day of capital cost, which is below the $10 to $15 per gallon

average for alternative supplies. The $9.33 per pound of total Nitrogen removed is

below the average cost of $224/lb of previously funded stormwater projects.

Cost Effectiveness: High

Past Performance: Based on an assessment of the schedule and budget for the 3 ongoing project.High

Complementary Efforts: The cooperator has a mandatory sewer connection ordinance, and enforces it.High

Project is ready to begin on or before December 1, 2017.Project Readiness: High

Strategic Goals

Strategic Goals: High Strategic Initiative - Reclaimed Water: Maximize beneficial use of reclaimed

water to offset potable water supplies and restore water levels and natural systems .

Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Northern Region Priority: Ensure long-term sustainable water supply.

Overall Ranking and Recommendation

This project will result in water quality and water quantity improvements to the Kings

Bay/Crystal River springshed, a SWIM Priority water body. Recommend forwarding project to

FDEP for funding consideration subject to Legislative Appropriation .

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$2,630,000$0 $2,630,000FDEP

$0$2,630,000$0 $2,630,000Citrus County

Total $0 $5,260,000 $0 $5,260,000

2

Page 7: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P137

Citrus County

Springs - Citrus County Northwest Quadrant Sewer Extension

Type 2 Multi-Year Contract: No

FY2018

Description

Construction of a sewer main expansion located within the Northwest quadrant of Citrus County

primarily serviced by septic systems.This sewer main extension will route up to 2.00 MGD of

wastewater flows at build out to the Meadowcrest WWTF to produce additional high-quality

reclaimed water flows that will in turn be sent to the Duke Energy Crystal River Power Complex.

Description:

The contractual Measurable Benefit will be the construction of approximately 10,300 feet of

sewer main for the purpose of extending the County’s wastewater collection system to the

Northwest quadrant of the County.

Measurable Benefit:

Total Project Cost: $6,000,000 (Construction only)

Citrus County: $3,000,000

District: $0

FDEP: $3,000,000

Costs:

Evaluation

Application Quality: The application included most of the required information identified in the guidleines.

District PM had to work with the cooperator to obtain the remaining required

information.

Medium

The benefit of the project is the reduction of pollutant loads to the Kings Bay/Crystal

River springshed, a SWIM priority water body, by an estimated 87,791 lbs/ yr TN and

the supply of 2.0 MGD of reclaimed water. There will be no monitoring or performance

testing requirements.

Project Benefit: High

The $2.27 per pound of total Nitrogen removed is below the average cost of $224/lb of

previously funded stormwater projects and the $0.62 per gallon of capital cost is below

the $10 to $15 per gallon average for alternative supplies.

Cost Effectiveness: High

Past Performance: Based upon an assessment of the schedule and budget for 3 ongoing projectsHigh

Complementary Efforts: The cooperator has a mandatory sewer connection ordinance and enforces it.High

Project is ready to begin on or before March 1, 2018.Project Readiness: Medium

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project will result in water quality and water quantity improvements to the Kings

Bay/Crystal River springshed. a SWIM priority water body. Recommend forwarding project to

FDEP for funding consideration subject to Legislative Appropriation .

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$3,000,000$0 $3,000,000FDEP

$0$3,000,000$0 $3,000,000Citrus County

Total $0 $6,000,000 $0 $6,000,000

3

Page 8: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P138

City of Brooksville

Springs - City of Brooksville Mountain Park Subdivision Septic Tanks Abandonment to

Central Sewer System

Type 2 Multi-Year Contract: No

FY2018

Description

Design, permitting and construction to connect existing residential septic tank users in the

Weeki Wachee Springshed to the City of Brooksville wastewater collection system .

Description:

The contractual Measurable Benefit will be the installation of approximately 8,000 linear feet of

sewer line and any necessary components for a fully operational municipal sewer system that

will allow for the connection of up to 64 residences.

Measurable Benefit:

Total project cost: $1,475,000 (Design, permitting and construction)

City of Brooksville: $33,696 (Water hook-up and connection fees)

District: $0

FDEP: $1,441,304

Costs:

Evaluation

Application Quality: Application included the required information identified in the CFI Guidelines.High

The benefit from this water quality project is the reduction of pollutant loads to the

Weeki Wachee Springshed, which is a SWIM Priority water body, by an estimated

1000 lb/yr TN. There will be no monitoring or performance testing requirements.

Project Benefit: High

The $49.17 per pound of total Nitrogen removed is below the average cost of $224/lb of

previously funded stormwater projects.

Cost Effectiveness: High

Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked

high.

High

Complementary Efforts: The City of Brooksville Code of Ordinances Sec. 86-103-- Connection with Sewer

States that, since sewer rates are based on water consumption, connection to the

City's water system shall be required at the same time as connection to the sewer

system is required under this subsection if the City's water system is also available.

High

Project is ready to begin on or before March 1, 2018.Project Readiness: Medium

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project will result in water quality improvements to the Weeki Wachee springshed , a SWIM

Priority water body. Recommend forwarding project to FDEP for funding consideration subject to

Legislative Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$33,696$0 $33,696City of Brooksville

$0$1,441,304$0 $1,441,304FDEP

Total $0 $1,475,000 $0 $1,475,000

4

Page 9: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P139

City of Brooksville

Springs - City of Brooksville Hernando Oaks Golf Course Reclaimed Water Project

Type 2 Multi-Year Contract: No

FY2018

Description

Design, permitting and construction of reclaimed water transmission mains and other necessary

appertenances to supply Reclaimed Water to Hernando Oaks Golf Course .

Description:

The contractual Measurable Benefit will be the installation of approximately 7,500 feet of

reclaimed water transmission mains, other necessary appurtenances and supply 0.225 MGD of

reclaimed water in the Weeki Wachee Springshed.

Measurable Benefit:

Total Project Cost: $490,000 (Design, permitting and construction)

City of Brooksville: $0

District: $0

FDEP: $490,000

Costs:

Evaluation

Application Quality: Application included the required information identified in the Springs guidelines.High

The benefit from this project is the supply of 0.225 MGD of reclaimed water for

irrigation use within the Weeki Wachee Springshed, a SWIM Priority waterbody. There

will be no monitoring or performance testing requirements.

Project Benefit: High

$2.88 per gallon of capital cost, which is below the $10 to $15 per gallon average for

alternative supplies.

Cost Effectiveness: High

Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked

high.

High

Complementary Efforts: Brooksville reclaimed water system includes metering and incentive based reuse rate

structures for high volume water users and has pro-active reclaimed water expansion

policies which maximize utilization, water resource benefits, and environmental

benefits.

High

Project is ready to begin on or before March 1, 2018. (Pending City's execution of

Customer Supply Agreement with golf course)

Project Readiness: Medium

Strategic Goals

Strategic Goals: High Strategic Initiative - Reclaimed Water: Maximize beneficial use of reclaimed

water to offset potable water supplies and restore water levels and natural systems .

Northern Region Priority: Improve northern coastal spring systems.

Northern Region Priority: Ensure long-term sustainable water supply.

Overall Ranking and Recommendation

This project will result in water quantity improvements to the Weeki Wachee Springshed , a

SWIM priority water body. Recommend forwarding to FDEP for funding consideration provided

cooperator submits executed reuse agreement by April 30, 2017 and subject to Legislative

Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$490,000$0 $490,000FDEP

$0$1$0 $1City of Brooksville

Total $0 $490,001 $0 $490,001

5

Page 10: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P140

Crystal River

Springs - City of Crystal River Indian Waters Septic-to-Sewer Phase II

Type 2 Multi-Year Contract: No

FY2018

Description

Design, permitting, and construction of municipal sewer system including connection fees, plant

demolition and tank abandonment, and necessary components. This project will allow for the

connection of private package wastewater package plant(s) and provide City central sewer to

areas currently served by septic systems within the Crystal River springshed.

Description:

The contractual Measurable Benefit will be the installation of approximately 25,000 feet of sewer

line and any necessary components for a fully operational municipal sanitary sewer system that

will allow for the connection of a private package plant and parcels currently on septic system

that will be connected to the City's sewer system.

Measurable Benefit:

Total project cost: $4,000,000 (Design, permitting, construction)

City of Crystal River: $400,000

District: $0

FDEP: $3,600,000

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI guidelines.

District PM had to work with cooperator to obtain remaining required information.

Medium

The benefit of this water quality project is the reduction of pollutant loads to Crystal

River, a SWIM Priority water body, by an estimated 3,803 lbs/yr TN. There will be no

monitoring or performance testing requirements.

Project Benefit: High

The $35 per pound of total Nitrogen removed is below the average cost of $224/lb of

previously funded stormwater projects.

Cost Effectiveness: High

Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked

high.

High

Complementary Efforts: The City has a mandatory connection ordinance in place to ensure homes are

connected to the sewer system.

High

Project is ready to begin on or before March 1, 2018.Project Readiness: Medium

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project will result in water quality improvements to the Crystal River/Kings Bay, a SWIM

priority water body. Recommend forwarding to FDEP for funding consideration subject to

Legislative Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$3,600,000$0 $3,600,000FDEP

$0$400,000$0 $400,000Crystal River

Total $0 $4,000,000 $0 $4,000,000

6

Page 11: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P142

Williston

Springs - City of Williston Northwood Estates Septic-to-Sewer

Type 2 Multi-Year Contract: No

FY2018

Description

Design, permitting, and construction of a municipal sanitary sewer system for Northwood

Estates. This includes the sewer pipe to connect septic system users to the City's central

sewer system and all necessary components. This project will provide the infrastructure to allow

for the connection of approximately 35 septic tanks and allow for additional infrastructure

installation and septic removal in the future.

Description:

The contractual Measurable Benefit will be the installation of approximately 4,300 feet of sewer

line and any necessary components for a fully operational municipal sanitary sewer system that

will allow for the connection of approximately 35 residences.

Measurable Benefit:

Total project cost: $1,794,000 (Design, permitting, construction)

City of Williston: $21,000

District: $0

FDEP: $1,773,000

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI guidelines.

District PM had to work with cooperator to obtain remaining required information.

Medium

The benefit of this water quality project is the reduction of pollutant loads to Rainbow

Springs, a SWIM Priority water body, by an estimated 761 lbs/yr TN. There will be no

monitoring or performance testing requirements.

Project Benefit: High

The $79 per pound of total Nitrogen removed is below the average cost of $224/lb of

previously funded stormwater projects.

Cost Effectiveness: High

Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked

high.

High

Complementary Efforts: Northwood Estates residents support the effort and the City Council passed and

adopted a formal resolution also in support of this project.

Medium

Project is ready to begin on or before December 1, 2017.Project Readiness: High

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project will result in water quality improvements to Rainbow Springs, a SWIM Priority water

body. Recommend forwarding to FDEP for funding consideration subject to Legislative

Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$21,000$0 $21,000Williston

$0$1,773,000$0 $1,773,000FDEP

Total $0 $1,794,000 $0 $1,794,000

7

Page 12: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P143

Williston

Springs - City of Williston WWTP AWT Upgrade

Type 2 Multi-Year Contract: No

FY2018

Description

Design, permitting, and construction to upgrade the City's existing wastewater treatment plant

(WWTP) to advanced wastewater treatment standards.

Description:

The contractual Measurable Benefit will be the installation of necessary components to allow for

a fully operational municipal sanitary sewer system to meet advanced wastewater treatment

standards

Measurable Benefit:

Total project cost: $3,021,000 (Design, permitting, construction)

City of Williston: $0

District: $0

FDEP: $3,021,000

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI guidelines.

District PM had to work with cooperator to obtain remaining required information.

Medium

The benefit of this water quality project is the reduction of pollutant loads to Rainbow

Springs, a SWIM Priority water body, by an estimated 3,082 lbs/yr TN. There will be

no monitoring or performance testing requirements.

Project Benefit: High

The $33 per pound of total Nitrogen removed is below the average cost of $224/lb of

previously funded stormwater projects.

Cost Effectiveness: High

Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked

high.

High

Complementary Efforts: City Council is adopting a formal resolution in support of this project.Medium

Project is ready to begin on or before December 1, 2017.Project Readiness: High

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project will result in water quality improvements to Rainbow Springs, a SWIM Priority water

body. Recommend forwarding to FDEP for funding consideration subject to Legislative

Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$1$0 $1Williston

$0$3,021,000$0 $3,021,000FDEP

Total $0 $3,021,001 $0 $3,021,001

8

Page 13: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P144

Marion County

Springs - Marion County Rainbow Springs Central Sewer Feasibility Study

Type 2 Multi-Year Contract: No

FY2018

Description

This project is for a feasibility study to investigate and determine the most feasible options to

reduce septic tanks and achieve central wastewater collection and treatment for properties in the

Rainbow Springs/River Springshed.

Description:

The contractual Measurable Benefit will be a feasibility study that identifies potential projects

and associated costs to convert from OSTDS to a central sewer system within a springs

protection zone in the Rainbow Springs/River Springshed, a Class I Outstanding Florida Water

System, first magnitude spring system, and SWIM priority waterbody.

Measurable Benefit:

Total project cost: $150,000 (Feasibility study)

Marion County cost: $20,000

District cost: $0

FDEP cost: $130,000

Costs:

Evaluation

Application Quality: Application included all of the required information identified in the CFI guidelines.High

The benefit of this water quality project will be the identification of projects for

implementation of reducing OSTDS in the Rainbow River Springshed, a SWIM priority

water body. If a central sewer program is fully implemented, approximately 250,000

lbs/yr of total nitrogen could be eliminated from the springshed.

Project Benefit: High

Study costs are comparable to similar projects such as N771 (Hernando County

Advanced Wastewater Treatment Master Plan Feasibility Study).

Cost Effectiveness: High

Past Performance: Based on an assessment of the schedule and budget for the two ongoing projects.High

Complementary Efforts: Marion County has a Spring Protection Resolution and comprehensive environmental

program. The County also has several ordinances that restrict irrigation, fertilizer use,

and OSTDS installation.

High

Project is ready to begin on or before March 1, 2018.Project Readiness: Medium

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project is a study to take septic tanks offline, which would improve springshed water quality

for Rainbow Springs and River, a SWIM priority waterbody and Outstanding Florida Water

System. Recommend forwarding to FDEP for funding consideration subject to Legislative

Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$20,000$0 $20,000Marion County

$0$130,000$0 $130,000FDEP

Total $0 $150,000 $0 $150,000

9

Page 14: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P135

Citrus County

Springs - Citrus County Chassahowitzka to Sugarmill Woods Wastewater

Interconnection

Type 2 Multi-Year Contract: No

FY2018

Description

Design, permitting and construction of a force main on County Road 480 to allow diversion of

wastewater currently treated at the Meadowcrest Wastewater Treatment Plant to the Sugarmill

Woods Wastewater Treatment Plant. Allows decrease in pumping costs due to decrease in

distance and operational flexibility between the two plants.

Description:

The contractual Measurable Benefit will be the installation of approximately 16,645 linear feet of

sewer line and any necessary components for a fully operational municipal sanitary sewer

system that will result in optimizing flow to Sugarmill Woods Wastewater Treatment Plant .

Measurable Benefit:

Total project cost: $1,000,000 (Design, permitting and construction)

Citrus County: $500,000

District: $0

FDEP: $500,000

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI guidelines.

District PM had to work with cooperator to obtain remaining required information.

Medium

Low or no resource benefit expected.Project Benefit: Low

Project is not cost effective, due to no Resource Benefit to compare it to.Cost Effectiveness: Low

Past Performance: Based on an assessment of schedule and budget of 3 ongoing projects.High

Complementary Efforts: The cooperator has a mandatory sewer connection ordinance and enforces it.High

Project is ready to begin on or before October 1, 2017.Project Readiness: High

Strategic Goals

Strategic Goals: Low Strategic Initiative: None

Region Priority: None

Overall Ranking and Recommendation

This project will not result in water quality improvements to the Chassahowitzka Springshed, a

SWIM priority water body. Do not recommend forwarding to FDEP for funding consideration

subject to Legislative Appropriation.

Not recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$500,000$0 $500,000Citrus County

$0$500,000$0 $500,000FDEP

Total $0 $1,000,000 $0 $1,000,000

10

Page 15: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P141

Dunnellon

City of Dunnellon Wastewater Collection SCADA System

Type 2 Multi-Year Contract: No

FY2018

Description

Install supervisory control and data acquisition(SCADA) system at three wastewater treatment

plants and 34 wastewater lift stations to allow continuous electronic monitoring of sanitary flows

to minimize overflows.

Description:

The Contractual Measurable benefit will be installation of a complete SCADA system for the

Dunnellon wastewater collection and treatment system.

Measurable Benefit:

Total Project Cost: $530,000, design, permitting & construction

City of Dunnellon: $ 53,000

District: $0

FDEP: $477,000

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI Guidelines.

District PM/CM had to work with cooperator to obtain remianing information.

Medium

Low or no resource benefit expected.Project Benefit: Low

Project is not cost effective, due to no Resource Benefit to compare to.Cost Effectiveness: Low

Past Performance: Based on an assessment of one FY2016 project.Medium

Complementary Efforts: The City has extended sewer services to replace septic tank systems in a number of

low areas. Lift stations constructed as part of that septic tank elimination effort would

be improved with the completion of the proposed SCADA project .

Low

Project is not expected to begin until after March 1st of the fiscal year the funding is

being requested.

Project Readiness: Low

Strategic Goals

Strategic Goals: Low

Overall Ranking and Recommendation

This project will not result in measurable water quality improvements. Do not recommend

forwarding to FDEP for funding consideration subject to Legislative Appropriation

Not recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$477,000$0 $477,000FDEP

$0$53,000$0 $53,000City of Dunnellon

Total $0 $530,000 $0 $530,000

11

Page 16: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. N635

Pasco County

Restoration-Pasco County Crews Lake Natural Systems Construction Phase

Type 2 Multi-Year Contract: No

FY2018

Description

Construction of infrastructure to provide reclaimed water to restore approximately 200 acres of

wetlands in and adjacent to Crews Lake. The FY18 funds are requested to complete

construction. The FY16 funds were budgeted to complete third party preview, final design and

permitting services. The FY15 funds were budgeted for 30% design, environmental monitoring,

and permitting services. This project has a conceptual construction estimate greater than $5

million dollars and the District is requiring a third party review of 30% design plans to confirm

construction costs and resource benefits. A feasibility study was completed by Pasco County in

2011.

Description:

The contractual Measurable Benefit will be the enhancement and restoration of approximately

200 acres of freshwater wetlands.

Measurable Benefit:

Total project cost $8,497,770 (environmental monitoring, design and permitting, third party

review, and construction).

Pasco County $2,124,443

District $2,124,442 with $365,885 budgeted in previous years, $1,758,557 requested for FY2018.

FDEP $4,248,885

Costs:

Evaluation

Application Quality: Application included all the required information identified in the CFI GuidelinesHigh

The benefit of this project is the reduction of pollutant loads to the Upper Floridan

Aquifer by an estimated 53,272 lbs/year TN and will create and enhance an area of

freshwater wetlands using reclaimed water.

Project Benefit: High

$2.36 per gallon of capital cost, which is below the $10 to $15 per gallon average for

alternative supplies. The $77.54 per pound of total Nitrogen removed is below the

average cost $224/lb and the $42,489 per acre restored is below the average cost of

$53,326.

Cost Effectiveness: High

Past Performance: Based on an assessment of the schedule and budget for the 12 ongoing project.High

Complementary Efforts: The County has an active environmentally sensitive land purchase program and

maintains nature parks and open spaces within the park system. The County operates

Adopt-a-Pond and Adopt-a-Road programs. Additionally, Pasco County has an active

stormwater utility that collects fees.

High

Project is ready to begin on or before December 1, 2017.Project Readiness: High

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Strategic Initiative - Conservation and Restoration: Identify critical

environmentally sensitive ecosystems and implement plans for protection or

restoration.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project will result in water quality and natural systems improvements to the combined

Aripeka/Weeki Wachee BMAP area. Recommend forwarding to FDEP for funding consideration

subject to Legislative Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$1,758,558$365,885 $2,124,443Pasco County

$0$1,758,557$365,885 $2,124,442District

$0$4,248,885$0 $4,248,885FDEP

Total $731,770 $7,766,000 $0 $8,497,770

12

Page 17: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

Risk Level:

Project No. P146

Pasco County

Springs - Pasco County Septic Tank Abatement Feasibility Study in the Weeki Wachee

Springshed

Type 2 Multi-Year Contract: No

FY2018

Description

Feasibility study on the sewer system expansions necessary to take 3,000 residential septic

tanks offline in the Weeki Wachee Springshed.

Description:

The contractual Measurable Benefit will include the completion of a feasibility study that

identifies projects to convert from septic systems to a central sewer system within the Weeki

Wachee Springshed.

Measurable Benefit:

Total project cost: $500,000 (Feasibility study)

Pasco County: $250,000

District: $0

FDEP: $250,000 requested in FY18, and $59,550,000 anticipated to be requested in future

years. The conceptual construction cost estimate is $119,100,000.

Costs:

Evaluation

Application Quality: Application included most of the required information identified in the CFI guidelines.

District staff had to work with cooperator to obtain remaining required information .

Medium

The benefit of this water quality project will be the identification of projects for

implementation of reducing septic systems in the Weeki Wachee River springshed , a

SWIM priority water body, and Aripeka Springshed. If a central sewer program is fully

implemented, approximately 47,000 lbs/yr of total nitrogen could be eliminated from

the springshed.

Project Benefit: High

Study costs are high when compared to similar projects such as N771 (Hernando

County Advanced Wastewater Treatment Master Plan Feasibility Study).

Cost Effectiveness: Low

Past Performance: Based on an assessment of schedule and budget for 12 ongoing projects.High

Complementary Efforts: Pasco County currently has a reclaimed water system includes metering and incentive

based reuse rate structure for high volume water users and has pro-active reclaimed

water expansion policies which maximize utilization, water resource benefits and

environmental benefits.

High

Project is ready to begin on or before December 1, 2017.Project Readiness: High

Strategic Goals

Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop

and implement programs, projects and regulations to maintain and improve water

quality.

Northern Region Priority: Improve northern coastal spring systems.

Overall Ranking and Recommendation

This project is a study to take septic tanks offline, which would improve springshed water quality

for the Weeki Wachee River, a SWIM priority waterbody and Outstanding Florida Water

System, and the Aripeka springshed. Recommend forwarding to FDEP for funding consideration

subject to Legislative Appropriation.

Recommended.

Funding

TotalFutureFunding Source Prior FY2018

$0$250,000$0 $250,000Pasco County

$0$250,000$0 $250,000FDEP

Total $0 $500,000 $0 $500,000

13

Page 18: FDEP Springs Initiative FY2018 Final Evaluations...springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will be no monitoring or performance testing requirements.

The Southwest Florida Water Management District (District) does not discriminate on the basis of disability. This nondiscrimination policy involves every aspect of the District's functions, including access to and participation in the District's programs and activities. Anyone requiring reasonable accommodation as provided for in the Americans with Disabilities Act should contact the District's Human Resources Director, 2379 Broad Street, Brooksville, Florida 34604-6899; 1-352-796-7211 or 1-800-423-1476 (Florida only), extension 4702; TDD (Florida only) 1-800-231-6103; or email to [email protected]


Recommended