FDOT District 1 FDOT District 1 ITS Project Update ITS Project Update Katherine Duvall ITS Project Manager
Transcript
Page 1: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

FDOT District 1FDOT District 1ITS Project UpdateITS Project Update

Katherine Duvall

ITS Project Manager

Page 2: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

OutlineOutline

RTMC and Related Projects

Future ITS Projects

Page 3: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

RTMC and Related ProjectsRTMC and Related Projects I-75 Collier & Lee Counties FMS and Regional

Transportation Management Center (RTMC) DB FPN: 416412-1, 416413-1, 414733-1 Under Construction (NTP Jan. 2, 2006) FMS

79 CCTV cameras, 111 microwave detectors, 26 dynamic message signs and 2 roadway weather information system units

Safety barrier cable system ITS improvements ~98 miles of fiber cable, Ethernet communications Video wall and integration of all control center and field

devices RTMC

Located in rest area off of I-75 and Daniels Parkway Multiple agencies: FDOT FMS Operations, FDOT MCCO,

FHP Dispatch and FHP District Building construction is almost complete

Completion of the Entire Project: Estimated end of this Summer

Page 4: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

SSouthouthWWest est IInteragency nteragency FFacility for acility for TTransportation (SWIFT) SunGuide™ Centerransportation (SWIFT) SunGuide™ Center

Page 5: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

SWIFT SunGuide™ CenterSWIFT SunGuide™ Center

Page 6: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

SWIFT SunGuide™ CenterSWIFT SunGuide™ Center

Page 7: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

SWIFT SunGuide™ CenterSWIFT SunGuide™ Center

Page 8: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

RTMC and Related ProjectsRTMC and Related Projects

SWIFT SunGuide™ Center Facilities Management Contract FPN: N/A Contract to be Advertised: April 2008 Building Management Support Services Contract Project Highlights:

Provides for general maintenance and services for SWIFT SunGuide™ Center including:

Air conditioning/heating Elevator and machine room equipment Janitorial services Pest control services Lawn maintenance Fire alarm monitoring and maintenance Security services

Page 9: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

Future ITS ProjectsFuture ITS Projects

Charlotte County I-75 FMS Design-Build Construction FPN: 414738-1 Letting Date: Scheduled November 2008 Project Highlights

Extension of the Lee-Collier FMS based on Conceptual ITS Plan for Charlotte County

Includes: Finalize design based on Preliminary Plans Package Fiber optic communication network deployment CCTV camera system (26) DMS system (10) HAR system RWIS Vehicle detection system (32) Integration at the RTMC

Page 10: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

Future ITS ProjectsFuture ITS Projects

Manatee County ATMS Design-Build Construction FPN: 416119-1 Letting Date: June 2008 Project Highlights

Finalize design based on Preliminary Plans Package Construction of ATMS Upgrade will include:

New central hardware and software New controllers and cabinets at 143 signalized

intersections 40 CCTV cameras

Existing communications upgraded to fiber with Ethernet communications

Integration at the TMC including video wall, consoles, work stations, and all other ITS equipment

Page 11: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

Future ITS ProjectsFuture ITS Projects

Sarasota County ATMS Construction FPN: 420974-1 & 420974-2 New Project – Transportation Regional Incentive

Program (TRIP) Growth Management Funds Upgrade Existing Signal System to be Compatible with

Manatee County ATMS Requirements Construction Letting to be Determined by Sarasota

County County Hiring System Manager

Page 12: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

Future ITS ProjectsFuture ITS Projects City of Winter Haven ATMS Design-Build Construction

FPN: 408043-2 Letting Date: March 2009 Construction Funding: 2010/2011

City will advance funds to start construction in Fiscal Year 08/09

Project Highlights Finalize design based on Preliminary Plans Package Construction of ATMS Upgrade will include:

New central hardware and software New controllers and cabinets at 48 signalized

intersections 15 CCTV cameras

Existing communications upgraded to fiber with Ethernet communications

Integration at the TMC including video wall, consoles, work stations, and all other ITS equipment

Page 13: FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.

Questions?Questions?Chris Birosak

FDOT District 1(863) 519-2507

[email protected]