!^^-">^«r,s^^-'mmi KJTE. M.-;
V SDMS DocID 468497
VOLUME II OF II MOTTOLO SITE
FEASIBILITY STUDY REPORT APPENDICES
Submitted to:
United States Environmental Protection Agency Region I
John F. Kennedy Federal Building Boston, Massachusetts 02203
Prepared on behalf of:
K. J. Quinn & Company, Inc. 195 Canal Street
Maiden, Massachusetts 02148
Prepared by:
BALSAM ENVIRONMENTAL CONSULTANTS, INC. 5 Industrial Way
Salem, New Hampshire 03079
December 10, 1990 Balsam Project 6185/824
(S4368COV)
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TABLE OF CONTENTS
SECTION PAGE
1.0 INTRODUCTION MOTTOLO SUPERFUND SITE
FEASIBILITY STUDY 1-1
1.1 PURPOSE AND APPROACH 1-1
1.2 REPORT ORGANIZATION 1-2
1.3 BACKGROUND INFORMATION 1-3
1.3.1 Site History 1-3 1.3.2 Summary of Current Conditions 1-5
1.3.2.1 Site Geology 1-5 1.3.2.2 Site Hydrogeology 1-6 1.3.2.3 Nature and Extent of Contamination 1-7 1.3.2.4 Contaminant Fate and Transport 1-10 1.3.2.5 Summary of Potential Risks 1-11
2.0 REMEDIAL ACTION OBJECTIVES AND TECHNOLOGY SCREENING 2-1
2.1 REMEDIAL OBJECTIVES 2-1
2.1.1 Source Control 2-2 2.1.2 Management of Migration 2-6 2.1.3 ARARs 2-7
2.1.3.1 Development of Ground Water TCLs 2-8 2.1.3.2 Development of Soil Treatment Levels 2-14 2.1.3.3 Soil Remediation Volumes 2-17
2.2 GENERAL RESPONSE ACTIONS 2-19
2.3 IDENTIFICATION AND SCREENING OF TECHNOLOGIES 2-20
2.3.1 Technology Identification 2-20 2.3.2 Technology Screening 2-21
2.4 SELECTION OF PROCESS OPTIONS 2-22
3.0 DEVELOPMENT AND SCREENING OF REMEDIAL ALTERNATIVES 3-1
3.1 RATIONALE FOR ALTERNATIVE DEVELOPMENT 3-1
(S4368TOC)
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TABLE OF CONTENTS (continued)
3.1.1 Former Disposal Area 3-1
SECTION PAGE
3.1.1.1 Historical Information 3-1
3.1.1.1.1 Source History 3-1
3.1.1.1.2 Migration 3-3
3.1.1.2 Site Conditions 3-3
3.1.1.2.1 Source 3-3
3.1.1.2.2 Migration 3-5
3.1.2 Southem Boundary Area 3-7
3.1.2.1 Historical Information 3-7 3.1.2.2 Site Conditions 3-7
3.1.2.3 Migration 3-8
3.1.3 Leaching Study Results 3-9
3.1.3.1 Study Methods 3-10
3.1.3.2 Study Results 3-11
3.1.4 Altemative Development Basis 3-12
3.2 SCREENING CRITERIA 3-17
3.2.1 Eff'ectiveness 3-17 3.2.2 Implementability 3-17
3.2.3 Cost 3-18
3.3 ALTERNATIVE DEVELOPMENT AND INITIAL SCREENING 3-19
3.3.1 Source Control Altematives 3-19 3.3.1.1 Altemative SC-1: No Action 3-19 3.3.1.2 Altemative SC-2: Containment 3-20 3.3.1.3 Altemative SC-3: In Situ Vapor Extraction 3-22 3.3.1.4 Altemative SC-4: On-Site Aboveground Vapor,
Extraction 3-23 3.3.1.5 Altemative SC-5: Chemical Fixation 3-25 3.3.1.6 Altemative SC-6: On-Site Low Temperature
(S4368TOC) Thermal Stripping 3-26 3.3.1.7 Altemative SC-7: On-Site Thermal Destmction 3-28
3-35
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TABLE OF CONTENTS (continued)
SECTION PAGE
3.3.1.8 Altemative SC-8: Off-Site Thermal Destruction 3-31
3-33 3.3.1.9 Altemative SC-9: Off'-Site Disposal
3.3.2 Management of Migration Altematives
3-35 3.3.2.1 Altemative MOM-1: No Action 3-36 3.3.2.2 Altemative MOM-2: Limited Action 3-38 3.3.2.3 Altemative MOM-3: On-Site Treatment 3-42 3.3.2.4 Altemative MOM-4: Off"-Site Treatment
3.3.3 Site^Wide Altematives 3-43
4.0 DETAILED EVALUATION OF SITE-WIDE ALTERNATIVES 4-1
4.1 INTRODUCTION 4-1
4.1.1 Remedial Objectives 4-1 4.1.2 Analysis Criteria and Approach 4-1
4.1.2.1 ARARs Analysis 4-2 4.1.2.2 Reduction of Mobility, Toxicity, and Volume
Analysis 4.1.2.3 Short-Term Effectiveness Analysis 4.1.2.4 Long-Term Effectiveness Analysis 4.1.2.5 Protectiveness Analysis 4.1.2.6 Implementability Analysis 4.1.2.7 Cost Estimation 4-10
4.2 SITE-WIDE ALTERNATIVE 1 4-12
4.2.1 Description 4-12 4.2.2 Compliance with ARARs 4-13 4.2.3 Reduction of Toxicity, Mobility, or Volume 4-13 4.2.4 Short-Term Effectiveness 4-14 4.2.5 Long-Term Effectiveness 4-14 4.2.6 Protectiveness 4-14 4.2.7 Implementability 4-15 4.2.8 Cost 4-15
4.3 SITE-WIDE ALTERNATIVE 2
4.3.1 Description 4-16 4.3.2 Compliance with ARARs 4-19
(S4368TOC)
4-16
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
SECTION
•
4.4
4.5
4.6
4.7
TABLE OF CONTENTS (continued)
4.3.3 Reduction of Toxicity, Mobility, or Volume 4.3.4 Short-Term Effectiveness 4.3.5 Long-Term Effectiveness 4.3.6 Protectiveness 4.3.7 Implementability 4.3.8 Cost
SITE-WIDE ALTERNATIVE 3
4.4.1 Description 4.4.2 Compliance with ARARs 4.4.3 Reduction of Toxicity, Mobility, or Volume 4.4.4 Short-Term Effectiveness 4.4.5 Long-Term Effectiveness 4.4.6 Protectiveness 4.4.7 Implementability 4.4.8 Cost
SITE-WIDE ALTERNATIVE 4
4.5.1 Description 4.5.2 Compliance with ARARs 4.5.3 Reduction of Toxicity, Mobility, or Volume 4.5.4 Short-Term Effectiveness 4.5.5 Long-Term Effectiveness 4.5.6 Protectiveness 4.5.7 Implementability 4.5.8 Cost
SITE-WIDE ALTERNATIVE 5
4.6.1 Description 4.6.2 Compliance with ARARs 4.6.3 Reduction of Toxicity, Mobility, or Volume 4.6.4 Short-Term Effectiveness 4.6.5 Long-Term Effectiveness 4.6.6 Protectiveness 4.6.7 Implementability 4.6.8 Cost
SITE-WIDE ALTERNATIVE 6
4.7.1 Description4.7.2 Comphance with ARARs
PAGE
4-19 4-20 4-20 4-21 4-22 4-23
4-24
4-24 4-27 4-28 4-28 4-29 4-30 4-31 4-32
4-33
4-33 4-36 4-36 4-37 4-37 4-38 4-39 4-40
4-41
4-41 4-44 4-44 4-45 4-45 4-46 4-46 4-47
4-48
4-48 4-52
(S4368TOC)
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
SECTION
4.7.3 Reduction of Toxicity, Mobility, or Volume 4-52 4.7.4 Short-Term Effectiveness 4-53 4.7.5 Long-Term Effectiveness 4-53 4.7.6 Protectiveness 4-54 4.7.7 Implementability 4-54 4.7.8 Costs 4-55
TABLE OF CONTENTS (continued)
PAGE
4.8 SITE-WIDE ALTERNATIVE 7 4-56
4.8.1 Description 4-56 4.8.2 Compliance with ARARs 4-58 4.8.3 Reduction of Toxicity, Mobility, or Volume 4-58 4.8.4 Short-Term Eff'ectiveness 4-59 4.8.5 Long-Term Effectiveness 4-59 4.8.6 Protectiveness 4-60 4.8.7 Implementability 4-60
4.8.8 Cost 4-61
4.9 SITE-WIDE ALTERNATIVE 8 4-62
4.9.1 Description 4-62 4.9.2 Compliance with ARARs 4-70 4.9.3 Reduction of Toxicity, Mobility, or Volume 4-70 4.9.4 Short-Term Effectiveness 4-71 4.9.5 Long-Term Effectiveness 4-72 4.9.6 Protectiveness 4-73 4.9.7 ImplementabiHty 4-75 4.9.8 Cost 4-76
5.0 COMPARISON OF ALTERNATIVES 5-1
5.1 COMPLIANCE WITH ARARs 5-1
5.2 REDUCTION OF TOXICITY, MOBILITY, OR VOLUME 5-2
5.3 SHORT-TERM EFFECTIVENESS 5-4
5.4 LONG-TERM EFFECTIVENESS 5-6
5.5 PROTECTIVENESS 5-7
5.6 IMPLEMENTABILITY 5-9
(S4368TOC)
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TABLE OF CONTENTS (continued)
SECTION PAGE
5.7 COSTS 5-9
5.8 SUMMARY OF COMPARATIVE ANALYSIS 5-10
6.0 REFERENCES 6-1
TABLE 1-1
TABLE 1-2
TABLE 2-1
TABLE 2-2
TABLE 2-3
TABLE 2-4
TABLE 2-5
TABLE 2-6
TABLE 2-7
TABLE 2-8
TABLE 2-9
TABLE 2-10
TABLE 4-1
TABLE 4-2
TABLE 4-3
TABLE 4-4
(S43G8TOC)
TABLES
CHRONOLOGY OF MOTTOLO SITE ACTIVITIES
SATURATED THICKNESS AND TRANSMISSIVITY ESTIMATES IN OVERBURDEN
WATER SOLUBILITY DATA FOR INDICATOR VOCs
WATER QUALITY STANDARDS AND CRITERL^
COMPARISON OF SITE GROUND WATER QUALITY WITH ARARs
SOIL TREATMENT LEVELS
GENERAL RESPONSE ACTIONS FOR SOURCE CONTROL
GENERAL RESPONSE ACTIONS FOR MANAGEMENT OF MIGRATION
SOURCE CONTROL TECHNOLOGY SCREENING
POST-SCREENING REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MANAGEMENT OF MIGRATION TECHNOLOGY SCREENING
POST-SCREENING REMEDIAL TECHNOLOGY LIST FOR MANAGEMENT OF MIGRATION
SUMMARY OF ARARs ANALYSIS
SITE-WIDE ALTERNATIVE 1 COST ESTIMATE
SITE-WIDE ALTERNATIVE 2 COST ESTIMATE
SITE-WIDE ALTERNATIVE 3 COST ESTIMATE
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TABLE 4-5
TABLE 4-6
TABLE 4-7
TABLE 4-8
TABLE 4-9
TABLE 4-10
TABLE 5-1
FIGURE 1-1
FIGURE 1-2
FIGURE 2-1
FIGURE 2-2
FIGURE 2-3
FIGURE 3-1
FIGURE 3-2
FIGURE 3-3
FIGURE 4-1
FIGURE 4-2
FIGURE 4-3
FIGURE 4-4
FIGURE 4-5
TABLE OF CONTENTS (continued)
SITE-WIDE ALTERNATIVE 4 COST ESTIMATE
SITE-WIDE ALTERNATIVE 5 COST ESTIMATE
SITE-WIDE ALTERNATIVE 6 COST ESTIMATE
SITE-WIDE ALTERNATIVE 7 COST ESTIMATE
AVERAGE CONCENTRATIONS OF COMPOUNDS MEASURED IN GROUND WATER
SITE-WIDE ALTERNATIVE 8 COST ESTIMATE
COMPARISON OF ALTERNATIVES
FIGURES
SITE LOCUS PLAN
SITE AREA MAP
CONFIRMED SOURCE AREAS AND EXTENT OF CONTAMINATION
SOURCE CONTROL PROCESS OPTION EVALUATION
MANAGEMENT OF MIGRATION PROCESS OPTION EVALUATION
SITE AREA CONCEPTUAL GROUND WATER FLOW CROSS-SECTION
BROOK A VALLEY CONCEPTUAL GROUND WATER FLOW CROSS-SECTION F-F^
DEVELOPMENT OF REMEDIAL ALTERNATIVES
SITE-WIDE ALTERNATIVE 1 SITE LAYOUT
SITE-WIDE ALTERNATIVE 2 SITE LAYOUT
INTERCEPTOR TRENCH CONCEPTUAL CROSS-SECTION
MULTIMEDIA CAP CONCEPTUAL CROSS-SECTION
SITE-WIDE ALTERNATIVE 3 SITE LAYOUT
(S4368TOC)
FIGURE 4-6
FIGURE 4-7
FIGURE 4-8
FIGURE 4-9
FIGURE 4-10
FIGURE 4-11
FIGURE 4-12
FIGURE 4-13
FIGURE 4-14
FIGURE 4-15
FIGURE 4-16
FIGURE 4-17
FIGURE 4-18
FIGURE 4-19
FIGURE 5-1
APPENDIX A
APPENDIX B
APPENDIX C
APPENDIX D
APPENDIX E
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TABLE OF CONTENTS (continued)
CONCEPTUAL VAPOR EXTRACTION WELL CONSTRUCTION
VES PROCESS SCHEMATIC DIAGRAM
ABOVEGROUND VES PROCESS SCHEMATIC DIAGRAM
SITE-WIDE ALTERNATIVE 4 SITE LAYOUT
ABOVEGROUND VES CONCEPTUAL CROSS-SECTION
SITE-WIDE ALTERNATIVE 5 SITE LAYOUT
SITE-WIDE ALTERNATIVE 5 PROCESS SCHEMATIC DIAGRAM
SECURE CELL CONCEPTUAL CROSS-SECTION
SITE-WIDE ALTERNATIVE 6 SITE LAYOUT
LTTS PROCESS SCHEMATIC DIAGRAM
SITE-WIDE ALTERNATIVE 7 SITE LAYOUT
SITE-WIDE ALTERNATIVE 8 SITE LAYOUT
GROUND WATER COLLECTION TRENCH CONCEPTUAL CROSS-SECTION
GROUND WATER TREATMENT SYSTEM PROCESS SCHEMATIC DIAGRAM
SUMMARY ALTERNATIVES COMPARISON
APPENDICES
ACTION-SPECIFIC AND LOCATION-SPECIFIC ARARs
DEVELOPMENT OF SOIL TREATMENT LEVELS
SOIL LEACHING STUDY REPORT
REMEDIAL TECHNOLOGY DESCRIPTIONS
EVALUATION OF GROUND WATER CLEANUP TIMES
(S4368TOC)
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TABLE OF CONTENTS (continued)
APPENDIX F GROUND WATER COLLECTION TRENCH AND EXTRACTION WELL POINT SYSTEM FLOW RATE ESTIMATES
APPENDIX G EVALUATION OF SOUTHERN BOUNDARY AREA EXTRACTION WELL SYSTEM
(S4368TOC)
APPENDIX A
ACTION-SPECIFIC ARARs
ARAR
FEDERAL:
Standards for Owners and Operators of Permitted Hazardous Waste Facilities (40 CFR 264).
Manifesting, Record Keeping and Reporting (40 CFR 264.70 264.77).
Ground Water Protection (40 CFR 264.90 - 264.109).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
These regulations outline facility requirements including; general waste analysis, security measures, inspections, personnel training requirements, and location standards.
This regulation sets forth the operating records and biennial reporting required for on-site facilities.
This regulation sets forth the ground water monitoring program required for a RCRA permitted facility. In the facility permit, the Regional Administrator will specify the hazardous constituents, concentration limits, point(s) of compliance, and compliance monitoring period.
ACTION TO BE TAKEN TO COMPLY
Treatment systems will be constructed and operated in accordance with applicable provisions of these regulations. Operations personnel will be trained.
On-site remedial activities will comply with record keeping and reporting requirements. Treatment residuals and wastes sent to off'-site treatment and disposal will be managed in compliance with manifesting requirements.
A ground water monitoring program consistent with the requirements of this regulation will be developed and implemented.
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
RCRA Post-Closure Care Requirements (40 CFR 264.310).
RCRA Waste Pile Standards (40 CFR 264.250 - 264.269).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation sets forth the specific requirements for closure and post-closure of hazardous waste facilities. These requirements include but are not limited to: closure performance standards, a detailed closure plan, time allowed for closure, disposal or decontamination of equipment, structures and soils, certification of closure, survey plat, post-closure care and use of property, and post-closure notice.
This regulation sets forth design and operating requirements for owners and operators of facilities that store or treat hazardous waste in piles. In addition, this requirement includes provisions for dry storage, monitoring and inspection procedures, special requirements for incompatible wastes, and closure and post-closure care.
ACTION TO BE TAKEN TO COMPLY
Monitoring and maintenance programs will be implemented in compliance with applicable provisions of this regulation.
Stockpiles for altematives involving aboveground handling of contaminated soils will be managed in accordance with applicable provisions of this regulation.
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
RCRA Landfill Standards (40 CFR 264.300 - 264.339).
RCRA Standards for Tanks (40 CFR 264, Subpart J).
Clean Water Act (40 CFR Parts 122 and 125).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation sets forth the design and operational requirements for new landfills. More specifically, each facility must have, a double liner and incorporate a leachate detection and collection system. Monitoring and inspection requirements, surveying and recordkeeping and closure and post-closure care are also addressed in this regulation.
This regulation establishes design and operation standards for storage and treatment tanks.
Regulation 40 CFR Part 122 addresses permitting requirements for discharge of dredged or fill materials into waters of the United States. According to Part 122, waters of the United States include wetlands, bogs,-swamps and marshes. Regulation 40 CFR Part 125 establishes criteria and standards for the National Pollutant Discharge Elimination system and references the pretreatment standards established in 40 CFR Parts 401 through 464.
ACTION TO BE TAKEN TO COMPLY
Altematives involving replacement of contaminated residues on site will comply with applicable provisions of this regulation.
Altematives that involve management of contaminated media in tanks will comply with applicable provisions of this regulation.
Management of diverted and treated ground water will comply with applicable requirements of this regulation.
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
OSHA - Safety and Health Standards for Construction Sites (29 CFR 1926).
OSHA - Record Keeping, Reporting and Related Regulations (29 CFR Part 1904).
National Environmental Policy Act (40 CFR Part 6).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation sets forth the protective clothing and equipment to be used for work on Superfund sites. In addition, decontamination and heat stress procedures are addressed.
This regulation outlines the health and safety record keeping and reporting regulations for employers. More specifically, this regulation requires an employer to develop information regarding causes and prevention of occupational accidents and illnesses based upon past incidents.
This regulation directs all federal agencies to include in their decision making processes, careful consideration of all environmental effects. More specifically, this requirement outlines the conditions for which environmental impact statements are required.
ACTION TO BE TAKEN TO COMPLY
Appropriate safety equipment will be on site, and safety procedures will be observed.
Appropriate records will be maintained in compliance with this regulation.
The need for an environmental impact statement will be reviewed.
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
Clean Air Act - . National Ambient Air Quality Standards for Total Suspended Particulates. (40 CFR 129.105).
Clean Air Act National Emissions Standards for Air Pollutants (40 CFR 61).
D.O.T. Rules for the Transportation of Hazardous Materials (49 CFR Parts 107, 171.1 - 171.500).
Rivers and Harbors Act (33 CFR 320 329).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation establishes standards for particulate emissions.
This regulation establishes emissions limitations for specific pollutants.
This regulation outlines requirements for lawful transportation of hazardous waste.
This regulation outlines requirements for discharging dredged or fill materials into waters of the United States. Furthermore, this regulation addresses dredge and fill operations with respect to protection of wetlands and floodplains.
ACTION TO BE TAKEN TO COMPLY
Monitoring and, if warranted, control measures will be employed to ensure compliance with this regulation.
Implementation of remedial altematives will comply with this regulation.
Treatment residuals and wastes sent to off-site treatment and disposal will be managed in compliance with this regulation.
Activities in the drainage swale and Brook A valley wetland areas will included measures to mitigate potential impacts. .
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
Guidelines for Specification of Disposal Sites for Dredged or Fill Material (40 CFR 230).
OSHA - General Industry Standards (29 CFR 1910).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation sets forth guidelines to restore and maintain the chemical and biological integrity of the waters of the United States through the control of discharges of dredged or fill materials.
This regulation sets forth health and safety procedures for employees working in industry. More specifically with respect to the subject site, it addresses personal protective equipment, hazardous materials handling procedures, fire protection, and medical and first aid preparation procedures.
ACTION TO BE TAKEN TO COMPLY
Mitigative measures, such as erosion and siltation controls will be used during activities in wetland areas to comply with this regulation.
Personal protective equipment and measures will be employed as required to comply with applicable provisions of this regulation.
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
STATE:
New Hampshire Hazardous Waste Act (RSA Ch.l47-A, NH Admin. Code He-P Ch.l905).
Hazardous Waste Facility Security Requirements (He-P 1905.08(d), incorporating by reference 40 CFR 264.14).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
These regulations establish standards applicable to the treatment, storage, transport and disposal of hazardous waste, and the operation and closure of hazardous waste facilities.
This regulation sets forth the responsibilities of owners of hazardous waste facilities.
ACTION TO BE TAKEN TO COMPLY
Treatment systems will be constructed and operated in accordance with applicable provisions of these regulations.
Access to remedial activities and facilities will be controlled in compliance with this regulation.
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
General Environmental Standards (He-P 1905.08(d)[l]).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation requires facilities to comply with specified state and federal environmental standards and to provide protection for workers in accordance with state and federal occupational health and safety requirements. Applicable occupational standards.include 29 CFR Ch. 1910 (industry standards); 29 CFR Ch. 1926 (safety and health standards); N.H. RSA Ch. 277-A (Worker's Right-to-Know Act); N.H. Admin. He-P Ch. 1800, Part 1803 (Toxic Substances in the work place.)
ACTION TO BE TAKEN TO COMPLY
Personal protection and training programs will be implemented as required to comply with the applicable provisions of this regulation.
December 10, 1990 Balsam Project 6185/824;S4368k
ARAR
Ground Water Protection (He-P 1905.08 [d][4][j], incorporating by reference 40 CFR 264, Subpart F).
Closure and Post-closure (He-P 1905.08 [d][4][k], incorporating by reference 40 CFR 264, Subpart G).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation, which incorporates federal RCRA standards and supplements N.H. Admin. Code Ws Ch. 410, establishes additional standards for ground water inonitoring and appropriate remediation at hazardous waste facilities. The provision prohibits the discharge of constituents into ground water above federal RCRA limits for such contaminants at the compliance point, which is defined as the boundary of each waste management unit under 40 CFR 264.95.
This regulation, incorporates federal RCRA requirements and sets forth design and performance standards for hazardous waste facility remediation and closure.
ACTION TO BE TAKEN TO COMPLY
A ground water monitoring program consistent with the requirements of this regulation will be developed and implemented.
Monitoring and maintenance programs will be implemented in compliance with applicable provisions of this regulation.
December 10, 1990 Balsam Project 6185/824:S4368k
ARAR
Transfer of Facility (He-P 1905.08 [d][5]).
Monitoring (He-P 1905.08 [d][6]).
Public Notification Plan (He-P 1905.08 [d][9]).
Additional Technical Standards for Treatment (He-P 1905.08 [fj[2][a]).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation .provides for notifying the Division and future owners or operators when a facility is transferred. In addition, upon closure of a facility, the owner is required to ensure that all future owners are aware of the previous land use and any restrictions that are necessary to preserve the integrity of contained waste.
These regulations establish monitoring requirements and authorize the Division to require appropriate environmental monitoring of such media as ground water, air, and leachate.
This regulation states that the WSPCC may require owners or operators to develop and follow a plan describing methods to inform the public of the status of facility activities.
He-P 1905.08[fJ[2][a] requires a demonstration that proposed treatment methods will meet specified design and construction requirements.
ACTION TO BE TAKEN TO COMPLY
Deed notifications and, if warranted, restrictions will be employed to comply with this regulation.
Monitoring programs will be developed and implemented to comply with applicable provisions of this regulation.
If required, a public notification plan will be prepared and implemented.
Remedial facilities will be constructed and operated to comply with applicable provisions of this regulation.
December 10, 1990 Balsam Project 6185/824:S4368k 10
ARAR
Technical Standards for Waste Piles (He-P 1905.08 [fj[l][d], incorporating by reference 40 CFR 264, Subpart L).
Technical Standards for Tanks (He-P 1905.08 [fl[l][b], incorporating by reference 40 CFR 264, Subpart J).
Manifesting Requirements (He-P 1905.04).^
Packaging and Labeling Requirements (He-P 1905.05, incorporating by reference N.H. Admin. Code Saf-C-600 and 49 CFR 172, 173, 178 and 179).
December 10, 1990
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
This regulation incorporates federal RCRA requirements for waste piles.
This regulation incorporates federal RCRA requirements for facilities using tanks to treat or store hazardous wastes.
This regulation stipulates that the transport of any hazardous wastes off-site must comply with the manifesting and record keeping requirements set forth in this provision.
These regulations stipulate that hazardous wastes transported off-site must be packaged and labeled in accordance with New Hampshire Department of Safety rules, and federal transportation requirements.
ACTION TO BE TAKEN TO COMPLY
Stockpiles for altematives involving aboveground handling of contaminated soils will be managed in accordance with applicable provisions of this regulation.
Altematives that involve management of contaminated media in tanks will comply with applicable provisions of this regulation.
Treatment residuals and wastes sent to off-site treatment and disposal will be managed in compliance with manifesting requirements. .
Treatment residuals and wastes sent to off'-site treatment and disposal will be managed in compliance with this regulation.
Balsam Project 6185/824:S4368k 11
ARAR
New Hampshire Solid Waste Management Act; RSA Ch. 149-M (N.H. Admin. Code He-P Ch. 1901).
New Hampshire Ground Water Protection Regulations (Ws 410) Ground Water Quality Criteria.
New Hampshire Air Regulations Toxic Air Pollutants (Chapter Env-A 1300).
Fugitive Dust Emission Control (N.H. Admin. Code Air Part 1002).
ACTION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
These regulations establish a permitting process which is applicable to the treatment, storage and disposal of solid waste and the closure of solid wa'ste facilities.
These regulations establish monitoring and intervention requirements and water quality standards for ground water discharges.
These regulations establish ambient air limits for toxic pollutants from new sources.
This regulation requires precautions to prevent, abate and control fugitive dust during construction and excavation activities. ,
ACTION TO BE TAKEN TO COMPLY
Remedial activities that involve management of solid waste will comply with applicable provisions of this regulation.
A monitoring program will be developed and implemented to comply with applicable provisions of this regulation.
Air monitoring and, if warranted, controls will be employed in compliance with applicable provisions of this regulation.
Monitoring and, if warranted, control measures will be employed to ensure compliance with this regulation.
December 10, 1990 Balsam Project 6185/824:S4368k 12
ARAR
Dredging and Control of Run-off; RSA 149:8-a: Dredging Rules (Ws Ch. 400 Part 415).
Fill and Dredge in Wetlands, Criteria and Conditions (RSA 483-A, Ws Ch. 300, and Wt Chapters 100 through 700).
Antidegradation Policy (Ws Ch. 400, Part 439).
LOCATION-SPECIFIC ARARs MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
SYNOPSIS
RSA 149:8-a and Ws Ch. 400 Part 415 establish criteria for conducting any activity in or near state surface waters which significantly alters terrain or may otherwise adversely affect water quality, impede natural runoff' or create unnatural runoff. Activities within the scope of these provisions include excavation, dredging, and grading of topsoil in or near wetland areas.
These regulations govern filling and other activities in or adjacent to wetlands, and establish criteria for the protection of wetlands from adverse impacts on fish, wildlife, commerce and public recreation.
Ws Ch. 400, Part 439 estabUshes the state policy against degradation of existing water quality, and requires protection of in-stream beneficial uses.
ACTION TO BE TAKEN TO COMPLY
Work performed in wetland areas and in the vicinity of Brook A will comply with applicable provisions of this regulation.
Activities in the drainage swale and Brook A valley wetland areas will included measures to mitigate potential impacts and comply with applicable criteria.
Activities in the drainage swale and Brook A valley wetland areas will included measures to mitigate potential impacts and prevent degradation.
December 10, 1990 Balsam Project 6185/824:S4368k
APPENDIX B
DEVELOPMENT OF SOIL TREATMENT LEVELS
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
A P P E N D K E
DEVELOPMENT OF SOIL TREATMENT LEVELS
1.0 ORGANIC LEACHING MODEL METHOD
A mass balance approach, taken from the Summers Model, was used to estimate
the leachate concentration from source a;rea soils corresponding to the TCE and
vinyl chloride TCLs in overburden groimd water in the former disposal and
southem boundary areas. This estimated leachate concentration was used in
conjunction with the Organic Leachate Model (OLM), developed by the EPA, to
estimate the soil treatment levels for TCE and vinyl chloride.
The input parameters for the mass balance in the former disposal area were: an
estimated influent grovmd water flow rate of 100 ftVday, based on hydrogeologic
data obtained in the RI, discussed below, and the cross sectional area ofthe flow
path beneath source area soils at a VOC concentration of zero; a leaching flow rate
through the source area soils estimated based upon an assumed infiltration rate of
5.4 in/yr and a sinface area ofthe source area soils of 4,200 ft^; and a contaminant
concentration downgradient of the mixing zone beneath the source area soils,
which was assigned a value equivalent to the appropriate ground water TCLs.
The influent ground water flow rate of 100 ft^day was based upon an average
overbiirden hydraulic conductivity of 1.13 feet per day, a hydraulic gradient and
saturated thickness upgradient ofthe source area of 0.16 and 8 feet, respectively,
and a width of the som*ce area soils perpedicular to the ground water flow
direction of approximately 70 feet. To provide a conservative basis for
development of soil treatment levels, a safety factor of 1,000 percent was applied
to the OLM output. With these input parameters and safety factor, the leachate
concentrations that would cause TCE emd vinyl chloride TCLs to exist in
overburden ground water downgradient of the former disposal area source soils
were estimated to be 100 ppb and 40 ppb, respectively. A similar analysis was
made for southern boimdary area soils; however, overbui-den ground water in that
December 10, 1990 DRAFT Balsam Project 6185/824:S4368o B - 1
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
a rea originates solely from recharge, so the leachate concentration from these soils
was set equal to the ground water TCL for TCE, the consti tuent of concem in this
area.
These leachate concentrations were used in conjunction with the EPA's OLM
model to determine the soil treatment levels in both areas. The model equation
used was of the form:
cO.373 C,, = 0.00221 C 0.678
SF
where: C^ = concentration of VOC in leachate (ppm);
Cg = concentration of VOC in soil (ppm);
S = solubility of VOC in water (pprd); and
SF = safety factor of 10 (1000%).
This model is an empirical equation developed from a best fit of a large data base,
made from obseirvations of a wide range of industrial wastes. The model is
expected to be representative of mid to long-term leaching from unsaturated soil.
The previously estimated leachate concentrations were input to the model in
conjunction with solubilities of 1,100 ppm, and 2,760 ppm for TCE and vinyl
chloride, respectively, to calculate soil treatment levels. In the former disposal
area, the soil treatment levels were estimated to be 0.6 ppm and 0.1 ppm for TCE
and vinyl chloride, respectively, and in the southem bovmdary area the TCE
treatment level was estimated to be 0.01 ppm. The following example calculation
was performed for TCE in the former disposal area soxu*ce soils to demonstrate the
approach. The specific mass balance equation from the Summers Model was:
QGW ^ G W + Qi^ i = (QGW + Qi) ^TCL
December 10, 1990 DRAFT Balsam Project 6185/824:S4368o B - 2
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
where: Q^w = influent ground water flow ra te (100 ftVday);
CGW = influent ground water TCE concentration (zero);
Qi = infiltration flow rate (5.2 ftVday);
Cj = leachate concentration (to be determined); and
CTCL = TCL for TCE (5 ppb).
Q, was calculated by multiplying the infiltration r a t e pf 5.4 in/yr (1,23 x 10'^ ft/day)
by the approximate area of the source area soils of 4,200 ft^. The leachate
concentration, Cj, was determined to be 100 ppb from this equation.
Cj was then input into the OLM, to obtain Cg, as follows:
0.00221 C°-^'^ S°-''^ SP
where: C = Cj = leachate concentration (0.1 ppm);
Cg = soil action level (to be determined);
S = TCE solubility (1,100 ppm); and
SF = safety factor of 10 (1,000 percent).
The soil action level calculated for TCE in the former disposal area was 0.6 ppm.
2.0 SUMMERS MODEL METHOD
The mass balance approach described in Section 1.0 was used to estimate the
leachate concentration from source area soils corresponding to the TCE and vinyl
chloride TCLs in overburden groimd water in the former disposal and southem
boundary areas. The same input parameters were also used in the mass balance
calculation. Using this approach, the leachate concentrations that were calculated
to result in TCE and vinyl chloride TCLs to exist in overburden groimd water
downgradient ofthe former disposal area source soils were estimated to be
100 ppb and 40 ppb, respectively. For the reasons discussed in Section 1.0, the
December 10, 1990 DRAFT Balsam Project 6185/824:S4368o B - 3
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
leachate concentration from southern boimdary area soils was set equal to the
TCL for TCE.
These leachate concentrations were then used to calculate soil concentrations that
would result in the leachate concentrations using the model:
Cg = K Q C I
where: Cg = concentration of VOC in soil (ug/Kg):
KQ = soil/water partition coefficient for VOC (cmVg); and
CI = leachate concentration (ug/L).
Use of the soil/water partition coefficient is based on the assimiption that
infiltrating precipitation water and soil establish equilibrium and that VOCs do
not partition into the vapor phase. For the unsaturated zone, soil-water
equilibrium is not uniformly established in the absence of saturation, and VOCs
will preferentially partition into the vapor phase in soil pore space air.
Accordingly, use of the Summers Model should overestimate VOC mass transfer to
water in the unsaturated zone and will result, in turn, in soil TCLs that are lower
than those representative of VOC transport mechanisms actually occtirring in the
unsaturated zone.
The soil-water partition coefficient is typically either determined from laboratory
batch tests or by calculation from K , the organic carbon-water partition
coefficient, which is, in turn, calculated from the octanol-water partition coefficient,
K„^. A Ko„ value of 2.72 was used for TCE along with the expression:
log (K„,) = 0.544 (log K„J + 1.377
to estimate a K ^ for TCE of 720 cmVg. Using the relationship:
KQ = K„ X (percent organic carbon content)
December 10, 1990 DRAFT Balsam Project 6185/824:S4368o B - 4
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
and the organic carbon content measured in the leaching study of approximately
0.1 percent, a K^ of 0.72 cmVg was estimated for TCE. Using the range of K^
values for TCE and the TCE influent concentration of 100 ppb, a soil treatment
level of 0.1 ppm was estimated for the former disposal area.
A similar analysis was performed to estimate treatment levels for vinyl chloride in
the former disposal area source soils and for TCE in the southem boundary area
soils. The estimated soil treatment level for vinyl chloride in former disposal area
soils was 0.005 ppb. For TCE in southem boundary area soils, the estimated
treatment level was 0.005 ppm.
According to EPA Manual SW-846, "Test Methods for Evaluating Solid Waste:
Physical/Chemical Methods," the practical quantitation limits on a wet weight
basis for TCE and vinyl chloride are 0.005 (ppm) and 0.01 ppm, respectively.
Accordingly, the soil treatment level for vinyl chloride in former disposal area
source soils was set at the practical quantitation limit of 0.01 ppm.
December 10, 1990 DRAFT Balsam Project 6185/824:S4368o B - 5
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
REFERENCES
Montogomery, J. H., and Welkom, L. M., "Groundwater Chemicals Desk Reference," Lewis Publishers, Chelsea, Michigan, 1990.
Dragun, James, "The Soil Chemistry of Hazardous Materials," Hazardous Materials Control Research Institute, Silver Spring, Maryland, 1988.
Howard, Philip H., "Handbook of Environmental Fate and Exposm-e Data for Organic Chemicals," Volume I, Lewis Publishers, Chelsea, Michigan, 1989.
December 10, 1990 DRAFT Balsam Project 6185/824:S4368o B - 6
APPENDIX C
SOIL LEACHING STUDY REPORT
A P P E N D K C
SOIL LEACHING STUDY REPORT MOTTOLO SUPERFUND SITE RI/FS
RAYMOND, NEW HAMPSHIRE
1.0 INTRODUCTION
1.1 OBJECTIVES
It has been more than 10 years since hazardous waste disposal activities occurred
on the Mottolo Superfund site in Rajmiond, New Hampshire, and approximately
10 years since the emergency removal action performed by the U.S. Environmental
Protection Agency (EPA). Dixring that time, it is expected that volatile organic
compounds (VOCs) present in site soils were transferred to grovmd water by
precipitation percolating through misaturated soils, by ground water flow through
affected saturated soils, and by temporal fluctuation of the ground water table.
Based upon available data, it appeared that the most heavily impacted soils
remaining in the former disposal area were located near or below the water table,
and it was expected that water table fluctuations result in satinration of most of
these soils during at least part of the year. These mechanisms appeared to have
resulted in the presence of VOCs in saturated soil and ground water beneath and
downgradient of the former disposal area, based upon the results of laboratory
analyses of grovmd water and soil samples and shallow ground water headspace
screening performed during the soil gas survey.
The results of source area investigations performed during the Remedial
Investigation (RI) indicated that highly affected soil was present in a relatively
small section of the former drum disposal area (see Figure C-1). It was
anticipated that both unsaturated and saturated soil in the aff'ected portion of the
former disposal area would be subject to remediation because of the relatively
December 10, 1990 Balsam Project 6185/824:S4368m C-1
limited volume of affected soil, the relatively shallow depth to bedrock (typically,
10 to 15 feet or less) in the area, and hydrogeologic conditions amenable to efforts
to lower the water table in the aff'ected area.
It is expected that VOCs migrating in ground water from the former disposal area
have been adsorbed to saturated soils downgradient of the source area, and that,
given the length of time for which migration and adsorption has occurred, these
soils may serve, in effect, as another source of VOCs released to less contaminated
ground water as it flows through the aff'ected soils, as well as contaminated
ground water itself in soil pore space. Additional information regarding the
relationship between soil quality and ground water quality downgradient of the
former disposal area appeared to be necessary to better characterize potential
impacts associated with these saturated soils and the effects of source remediation
on site ground water quality. Specifically, it was important to assess the potential
of downgradient saturated soil to continue to release VOCs to ground water after
remediation of directly affected soils in the former drum disposal area. The ability
of these downgradient soils to serve as a VOC source to ground water was
considered to be a potentially important factor affiecting the length of time
required to attain remedial goals for ground water, as well as the size of the area
within which soil remediation would be pursued. Accordingly, the objective of the
soil leaching study discussed herein was source area.definition, focused primarily
on downgradient saturated soils, and the related matter of the effects of soil
remediation on ground water quality. Because the mechanisms of interest were
desorption and flushing of VOCs from the saturated zone, the appropriate
approach was to evaluate the ability of ground water passing through these soils
to leach or transport VOCs present in this zone.
December 10, 1990 Balsam Project 6185/824:S4368m C-2
1.2 BACKGROUND
During the RI, a two-phase soil boring program was performed at the Mottolo site
to assess the approximate boundaries of the contaminated soil area associated
with the former container disposal area and to evaluate the t3rpes and levels of
contaminants present in this area. Four soil borings were advanced in the former
disposal area during the Phase I program, and sixteen additional soil borings were
advanced in and around the former disposal area during the Phase II program.
During the boring programs, soil samples collected from the borings were t3rpically
subjected to field screening analyses for the presence of VOCs and selected
samples were subjected to laboriatory analyses for the presence of Hazardous
Substance List (HSL) VOCs by EPA Method 8240. The methods employed and
results of this program are summarized in the RI report submitted to EPA in
September 1990. In conjunction with Phase I of the program, soil gas and shallow
ground water samples were collected and the sample headspace analyzed in the
field with a Photovac 10S50 portable gas chromatograph (GC) to preliminarily
assess the subsurface distribution of VOCs. The results of the soil gas survey
program are also summarized in the RI report. The information obtained from
these programs is briefly summarized in Section 1.3 to provide a general basis for
discussion of the soil leaching study objectives and approach.
1.3 SOILS INVESTIGATION RESULTS
In general, the soil gas survey results indicated the presence of VOCs in soil gas
and shallow ground water primarily in and downgradient ofthe former disposal
area, the location of which was estimated by review of maps from prior
investigations and aerial photographs. In addition, VOCs typically were not
detected or were detected at low levels (generally 8 ppb or less) in soil samples
collected from borings advanced in and around the former disposal area with the
exception of a relatively limited area in the center and northem side of the area
December 10, 1990 Balsam Project 6185/824:S4368m C-3
investigated. In this portion ofthe former disposal area, soil samples were found
to contain elevated levels (2.0 to 465 ppm) of VOCs. The VOCs detected at
elevated concentrations included primarily toluene, ethylbenzene, xylenes, and
methylene chloride. Chlorinated VOCs, including 1,1,1-trichloroethane (TCA),
trichloroethene (TCE), and tetrachloroethene (PCE), when detected, were typically
found at low concentrations in samples from the area of most heavily aff'ected soils.
Samples in which VOCs were detected at elevated concentrations were generally
collected in an interval extending from slightly above or at the water table to
several feet below the water table, as measured at the time of drilling. These
samples also appeared to generally contain higher levels of organic carbon, as
indicated by the results of total volatile solids (TVS) analyses performed during
the Phase I and II boring programs.
The results of the soil gas survey. Phase I and Phase II soils investigations, review
of aerial photographs, maps from previous investigations, and site observations
were used to identify the approximate boundaries of the former disposal area and
the portion of this area in which soil appeared to be most heavily impacted by
residual VOCs. The approximate boundaries ofthese areas are illustrated in
Figure C-1.
December 10, 1990 Balsam Project 6185/824:S4368m C-4
2.0 STUDY APPROACH DEVELOPMENT
A search of the scientific literature was performed of previous research regarding
leachability of VOCs from soils (see attached reference list). Review of available
information indicated that research on this subject was typically performed by
preparing experimental soil samples using uncontaminated materials, placement of
the soil samples in columns or other leaching apparatus, spiking the soil samples
with VOCs of interest, passing distilled, deionized water through the soil samples,
and monitoring leaching of VOCs from the soil samples into the water. 4
Alternatively, adsorption studies were performed by leaching VOC-spiked water
through similarly constructed experimental uncontaminated soil samples and
apparatus. The approach taken to these studies did not, however, address the
possible effects of long term interaction between a natural soil matrix and VOCs,
which was expected to be an important factor affecting leaching of VOCs from site
soils given the length of time that VOCs have been present in the ground at the
site. In addition, the characteristics of the experimental soils, such as grain size
distribution and organic carbon content, were generally controlled and relatively
uniform, and the leaching medium was usually deionized, distilled water, both
unrepresentative of conditions encountered in the site environment.
Based upon the assessment previously described, it appeared that performance of
leaching tests on VOC-contaminated soil samples collected from the site would
provide information more indicative of the processes likely to occur on site.
Several key factors affecting performance of such testing were identified including:
0 collection of relatively undisturbed soil samples from the areas and strata of identified contamination;
o establishment of a base line characterization of soil quality for samples to be tested;
0 minimization of, or control for, the possible loss of VOCs from soil samples during collection and transfer to the leaching apparatus;
December 10, 1990 Balsam Project 6185/824:S4368m C-5
I 0 the ability to estimate and control the rate of leaching or flushing;
0 the ability to periodically sample and analyze the leachate for the presence and concentrations of VOCs; and
0 use of a leaching medium more representative of site conditions than deionized, distilled water.
Accordingly, the conceptual study approach, described in the final leaching study
protocol transmitted to EPA on May 1, 1990, involved the collection of relatively
undisturbed soil samples from the site and placement in a controlled test
environment for leaching with ground water collected from the site. The actual
leaching test procedures used, including soil sample and ground water collection
methodologies, leaching apparatus and test specimen set up, leachate sampling
methodology and analytical protocols, are discussed in Section 3.0.
December 10, 1990 Balsam Project 6185/824:S4368m > C-6
A^
3.0 LEACHING TEST PROCEDURES
3.1 SOIL SAMPLE COLLECTION
3.1.1 Sampl ing Locat ions
In general, soil samples were collected from locations outside of the former
disposal area that were believed to be within the boundaries of the contaminated
ground water plume originating from that area. Initial selection of locations and
strata from which to collect samples was based upon results obtained from the
earlier soil boring programs and field observations. Locations were selected in an
effort to obtain samples representative of a range of conditions downgradient of
the former disposal area source soils, i.e., immediately downgradient of the source
area in the path of the main body of the ground water VOC plume and other
locations further downgradient or on the periphery ofthe plume. Final sampling
locations were adjusted in the field at the time of test pit excavation based upon
(1) field screening results, (2) apparent water table elevation, (3) test pit
excavation limitations (e.g., boulders), and (4) physical limitations of pushing
Shelby tube samplers (see Section 3.1.2). Field screening of soil samples from the
test pits and of ambient air along the test pit walls was performed using an HNu
Systems Model PI-101 Photoionization Detector (HNU).
Six test pits were excavated at the locations shown in Figure C-2. Soil samples
were collected from test pits TP-2, TP-3, and TP-6. Test pit TP-3 was located
immediately downgradient of the source area. Test pit TP-2 was excavated fiirther
downgradient and more toward the periphery of the plume. Test pit TP-6 was also
located in the vicinity of the source area, although more cross-gradient and, based
upon screening results, apparently toward the edge of the ground water VOC
plume. Excavation refiisal was encountered above the ground water table in test
pit TP-1, and field screening did not indicate the presence of VOCs in soil samples
December 10, 1990 Balsam Project 6185/824:S4368m C-7
collected from test pits TP-4 and TP-5. A summary of soil sample information is
presented in Table C-1. Test pit logs that include stratum descriptions, field
screening results, description of sampling locations within the test pits, and
limitations encountered during excavation, e.g., boulders and bedrock, are included
in Attachment A.
3.1.2 Sample Collection Method
Soil samples to be used in the leaching study were collected from the test pits by
pushing a thin-walled, 2.8-inch inside diameter (I.D.) Shelby tube, mounted on a
backhoe bucket, horizontally into the face of one of the test pit walls at the
elevation of interest. Samples were collected in this orientation, i.e., parallel to
the general direction of ground water flow, so that the flow of leaching medium
through the sample during testing would be in the same general direction that
ground water flows through the soil on site. The Shelby tubes were attached to
the backhoe bucket using a specially constructed adaptor consisting of a standard
Shelby tube attachment welded to a steel plate, which was bolted to the bucket at
the time of sampling. Figure C-3 illustrates the Shelby tube mounting
arrangement.
For each sampling attempt, a new Shelby tube was screwed on to the bucket
attachment. The tip of the tube was guided to the selected sampling location by
lowering the bucket, and the tube was pushed as smoothly and horizontally as
possible xmtil (1) the backhoe arm was fully extended (typically approximately
2 feet because ofthe equipment configuration and desired sampling depth); (2)
refusal was encountered due to an obstruction, which did not necessarily preclude
retrieval of a usable sample; or (3) the tube was severely bent, precluding
collection of a usable sample. The tubes were slowly and smoothly withdrawn
from the test pit face, and subsequently handled as described in Section 3.1.3. The
test pits were backfilled with the excavated material after sample collection was
December 10, 1990 Balsam Project 6185/824:S4368m C-8
completed or when it became apparent that samples would not be retrieved
because of physical limitations or because VOC contamination was not evident
based upon screening results.
The excavation equipment was decontaminated prior to and between use at test
pit locations to limit possible cross-contamination. To accomplish this
decontamination, the bucket of the backhoe was first rinsed with tap water, then
scrubbed with a solution of tap water and trisodium phosphate (TSP), and then
rinsed again with tap water. Personal protective equipment, primarily gloves, that
may have come in contact with contaminated materials, was either cleaned or
changed between sampling locations. Disposable equipment and clothing was
managed in accordance to the procedures established for these materials in
Section 4.4.1.2 ofthe Mottolo Sampling and Analysis Plan (SAP).
3.1.3 Sample Hand l ing
Upon retrieval from the excavation, the Shelby tubes were immediately removed
from the adapter on the backhoe bucket. The driven end ofthe tube (tip) was
immediately capped and taped to limit possible VOC loss. The soil recovery was
then immediately measured by placing a ruler inside the other end of the tube
(butt) and recording the distance from the end of the tube to the soil surface. This
measured length was later subtracted from the total tube length to give the
estimated soil recovery. A small amount of melted wax, enough to initially seal
the soil surface but not enough to cause wax penetration into the soil matrix, was
poured into the butt end of the tube to limit VOC loss. While this wax was
hardening, the tube tip was dipped several times into melted wax to augment the
cap and tape seal. Finally, additional melted wax was poured into the butt end of
the tube to an approximate thickness of 2 to 3 inches.
December 10, 1990 Balsam Project 6185/824:S4368m C-9
Once the sealing process was completed, the Shelby tubes were labeled in
accordance with the procedures established in Section 4.5 of the Mottolo SAP and
placed in an insulated cooler with ice for transport to the testing laboratory.
Chain-of-custody documentation was prepared in the field and maintained through
delivery to the laboratory in accordance with the procedures established in
Section 5.0 of the Mottolo QA/QC Plan.
3.2 GROUND WATER COLLECTION
Ground water used as the leaching medium was collected from an upgradient dug
well, DW-1, that is located on the Mottolo site (see Figure C-1). Site ground water
provided a leaching medium more representative of site conditions than would use
of deionized, distilled water. The ground water was collected with a 4-inch
diameter bailer and poured directly into 2-liter amber glass containers. The
collected water was immediately transported to the testing laboratory, where it
was transferred to the influent reservoirs of the leaching apparatus or stored for
refilling of reservoirs. Collected ground water to be used for leaching was stored a
maximum of 2 to 3 days in insulated coolers at ambient temperatiire. The water
in the reservoirs was replaced every 2 to 3 days to limit possible effects of changes
in ground water chemistry on leaching behavior. The ground water containers
were labeled in accordance with the sample coding system described in Section 4.5
of the SAP, and chain-of-custody was maintained and documented as specified in
Section 5.0 of the QA/QC Plan.
3.3 LABORATORY PROCEDURES
The collected soil samples were delivered to GEI Consultants, Inc. (GEI) of
Winchester Massachusetts, the testing laboratory, within 2 days of collection,
where they were stored in insulated coolers with ice until being set up in the
leaching apparatus. One sample was tested for physical characteristics only, i.e.,
December 10, 1990 Balsam Project 6185/824:S4368m C-10
permeability and specific gravity, in order to estimate the porosity and, therefore,
the pore volume ofthe leaching samples, as described in Section 3.3.1. This
infonnation was subsequently used to estimate the leaching test flow rates
required to model the desired leaching period (e.g., 1 to 4 years) in a practical time
period (e.g. 4 to 8 weeks). Subsequently, the soil samples selected for leaching
were set up in the modified triaxial permeameters, as described in Section 3.3.2.
3.3.1 Basel ine Physical Soil Character is t ics
A soil sample contained in Shelby tube MTL-ST-TP3-001 was set up in a standard
triaxial permeameter and tested for hydraulic conductivity in accordance with
ASTM Method D-2434(74). The porosity of the sample was estimated using an
assumed particle specific gravity of 2.69. As previously described, this information
was used to estimate the leaching test flow rates for the four leaching samples.
3.3.2 Leach ing Test Appa ra tu s
A flexible wall triaxial permeameter apparatus was modified to accommodate the
leaching procedure. Figure C-4 is a schematic ofthe leaching test system. In
general, the system consisted of a Incite influent reservoir, nylon 11 influent
tubing, a Nupro model SS-SS2-D precision flow meter, a brass or stainless steel
control block, scintered teflon porous end plates, a Incite pressure cell, an effluent
sampling port, nylon 11 effluent tubing, and a Incite effluent reservoir. Glass
burets were attached to the influent and effluent lines for flow measurement. The
control block was used to control flow through the influent and effluent lines and
was equipped with a pressure transducer to allow measurement of the pressure
differential across the sample (i.e., gradient). The lucite pressure cell surrounding
the sample in the flexible membrane was filled with site water and pressurized to
simulate the in situ cohfiining stress from overlying soil.
December 10, 1990 Balsam Project 6185/824:S4368m C-11
The leaching systems were tested for leaks and calibrated prior to set up of the
leaching specimens. The systems were first saturated with site water and placed
under a pressure greater than would be encountered during the test, and visible
leaks were repaired. The influent and effluent burets were calibrated by weighing
a volume of water discharged, calculating the volume from the weight, and
dividing the recorded buret reading by the calculated volume to obtain the volume
per buret demarkation. The volume of water in the tubing between the sampling
port and the effluent buret was determined similarly. In addition, the initial flow
rate was set without the sample in place, so that when leaching began, the
starting flow rate was close to the required test flow rate. This rate could be set
before the test because the pressure drop over the flow meter was very large
compared to the pressure drop across the soil sample. Because it is pressure
which drives flow, the relatively small change in head loss caused by the addition
of the sample to the system would cause little change in flow rate. The final step
in apparatus preparation was to drain the effluent side of the system leaving the
influent side saturated, so that when leaching began all fluid collected on the
effluent side was leachate.
3.3.3 Leach ing Specimen Handl ing
The Shelby tube was removed from the cooler immediately prior to test set up and
placed in a chain vise for cutting and trimming operations. Stifflening rings were
used during cutting operations to limit sample deformation.
The first step in soil sample removal was to remove the wax, tape, and cap from
the tip of the tube by cutting the tube. The exposed soil was trimmed level, and
the distance from the trimmed soil surface to the tube end recorded. This end of
the tube was then immediately resealed with a Teflon packer with o-rings to limit
VOC loss. The tube was then measured and cut so that a trimmed sample
approximately 12 centimeters (cm) long would be produced, i.e., a length of
December 10, 1990 Balsam Project 6185/824:S4368m C-12
approximately 15 cm was cut from the tube. When the tube was cut, the end of
the sample not immediately used was capped, taped, and put back in to the cooler
to be used for base line chemical analyses, as described in Section 3.3^4. The other
end of the tube was trimmed level to approximately 12 cm in length (the actual
length was measured and recorded), and the cut end of the tube was deburred to
prevent sample disturbance during extrusion. The end of the tube was resealed
with a Teflon packer seal until just before extrusion, which typically occurred
within 5 to 10 minutes of resealing.
The sample was extruded slowly and smoothly into a latex membrane, the
thickness of which was previously measured and recorded. During extrusion, the
soil sample traveled in the same direction inside the tube that it was travelling
relative to the tube when the sample was collected in the field. This process was
facilitated by a membrane expander, which consisted of a metal cylinder with an
inside diameter slightly greater than the sample outside diameter and equipped
with a vacuum port. The membrane was stretched over the inside of the expander
with the ends rolled over the outside, and a suction was placed on the vacuum port
to draw the membrane to the inner walls of the cylinder.
The extruded soil sample, now inside the membrane and expander, was
immediately placed on the bottom porous plate of the permeameter such that
leaching water would travel through the sample in the same general direction as
ground water flow at the site. The top porous plate was placed on the sample, the
expander vacuum released, and the membrane rolled over the endplates. To seal
the sample from the confining cell water, the edges of the endplates were lightly
greased with Dow Vacuum Grease, and two o-rings placed over the membrane at
each endplate. T3rpically, less than 6 minutes passed from the start of the
extrusion process to the time the sample was sealed on the permeameter.
December 10, 1990 Balsam Project 6185/824:S4368m C-13
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
The length and diameter of the sample on the permeameter was measured and
recorded before the confining lucite cell was placed on the permeameter. After
placement, the confining cell was filled with site ground water and pressurized to
0.27 kilograms per square centimeter (kg/cm^), which was approximately
equivalent to the in situ confining stress from overljdng soil. At this point in the
sample setup procedure, the influent valve was closed, and the effluent valve was
open to allow consolidation due to reinstitution of in situ confining stress. Once
the sample was consolidated, i.e., no further pore water movement out ofthe
sample was observed, the leaching procedure could begin. Back pressure
saturation would have introduced water not intrinsic to the sample; therefore, the
sample was not back pressure saturated in order to retain the in situ pore water
condition. The leaching protocol is described in Section 3.3.5.
3.3.4 Base Line Soil Sample Hand l ing
With the exception of the TP-2 sample, base line samples were removed from the
cooler immediately after the associated leaching samples were set up and were
subjected to handling similar to that used in setting up the leaching samples, as
described in Section 3.3.3, to the point of sample dimension measurements on the
permeameter. The base line sample was then removed from the permeameter, the
membrane was removed, and the soil placed on a clean metal plate. The sample
was immediately and rapidly divided into three portions: one sample for HSL
VOCs analysis by EPA Method 8240; one sample split for Total Volatile Solids
(TVS) analysis by Standard Method 209F and for Total Organic Carbon (TOC)
ana:lysis by U.S. Army Corps of Engineers Method IN847; and one sample for
grain size distribution and specific gravity analyses. The base line sainple for
TP-2 was prepared for analysis prior to setup of the TP-2 leaching sample to meet
holding time limitations for chemical analysis. The base line samples for TP-6
were collected from trimmings from the leaching sample because of insufficient
recovery in the Shelby tube to provide both leaching and base line samples. The
December 10, 1990 Balsam Project 6185/824:S4368m C-14
D
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
VOC and TOC/TVS samples were placed in 8-ounce glass sample jars, in a manner
which minimized headspace, labeled in accordance with the provisions of the
Mottolo SAP, and placed in an insulated cooler with ice. The elapsed time from
removal of the membrane to sealing the VOC sample in the sample jar was
typically less than 1 minute. The samples were shipped to the analytical
laboratory via overnight courier, and chain of custody was documented and
maintained in accordance with the Mottolo QA/QC Plan.
3.3.5 Leach ing and Leacha te Sampl ing Protocol
Immediately following sample consolidation, the influent valve was opened and the
leaching process initiated. The flow rate, initially set before the sample was
placed in the permeameter apparatus, was adjusted to accommodate the increased
head loss through the sample. Initially, sample pore volume estimates were made
using the sample dimensions and the measured porosity of the sample tested for
physical characteristics at the start of the program. These estimated sample pore
volumes were used to select sampling times for the, initial sampling schedule of
0.5, 1, 2, 4, and 10 pore volume exchanges, as well as subsequent sampling points
selected on the basis of prior results. The actual pore volumes sampled were
calculated at the end of the test using the measured porosity for the individual
samples.
Prior to leachate sampling events, the sampling port was opened to allow the
stagnant water in the port to be flushed out. The volume of flush water required
to clear the port, typically approximately 1 ml, was measured either by the
calibrated buret or by weighing the flushed fluid on a Mettler 1200 balance. After
flushing the sampling port, a 14-milliliter (ml) glass vial was filled and capped
with a fluorocarbon resin-lined septum held in place by a screw cap. The sample
containers were labeled in accordance with the procedures established in
Section 4.5 of the Mottolo SAP.
December 10, 1990 Balsam Project 6185/824:S4368m C-15
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
The leachate samples were placed in insulated containers with ice and shipped by
overnight courier service to an analytical laboratory, Aquatec, Inc. of Burlington,
Vermont. Chain of custody was documented and maintained in accordance with
Section 5.0 of the Mottolo QA/QC Plan. The samples were analyzed for HSL VOCs
by EPA Methods 624. The first six leachate samples from each leaching test
sample were analyzed on an expedited basis to allow close tracking of leaching
behavior in the initial stages of the study. Data obtained from the expedited
analyses were used to select subsequent sampling times.
The volume of leachate water removed from the effluent reservoirs ofthe test
apparatus to prevent their overflow was measured and recorded. The leachate
volume records for the individual soil samples, which also included volumes
sampled and flushed, were used with the individual sample porosities to calculate
the actual pore volumes collected in the individual leachate samples. The leachate
volume records for the leaching samples are presented in Attachment B.
The leaching flow rate was checked periodically throughout the study. At the
onset of the test, it was adjusted until equilibrium was achieved at the desired .
flow rate and, subsequently, it was checked on a daily basis, excluding weekends.
If the flow rate for a given test system required adjustment, the influent valve was
adjusted appropriately and the flow rate re-checked after equilibrium was
achieved, generally within approximately 1 hour.
The influent reservoir water was changed approximately three times per week
with water collected from well DW-1 at the Mottolo site. On July 1, 1990, the test
pit TP-3 and TP-6 leaching specimens were shut down for approximately 1 day due
to a shortage of leaching fluid. Subsequently, additional ground water from site
was also stored in 2-liter amber glass jars to provide a reserve. The reserve water
was replaced when fresh water was brought from the site.
December 10, 1990 Balsam Project 6185/824:S4368m C-16
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
Two samples of leaching medium were collected from influent lines to the leaching
apparatus and analyzed for HSL VOCs by EPA Method 624 to assess possible back
diffusion of VOCs from the soil specimens. One sample was collected from the
sample TP-3 test apparatus and the other from the sample TP-3D apparatus prior
to a change of water in the influent reservoir. The samples were collected from
points immediately upstream of the leaching specimens.
3.3.6 Test Conclusion
To evaluate possible effiects ofthe test flow rates on desorption equilibria, the flow
rates for leaching specimens from test pits TP-2, TP-3, and TP-6 were reduced by a
factor of approximately five when VOCs were not detected or were detected at very
low concentrations (less than 10 ppb of total VOCs) in the leachate sample
analyses. Leaching was continued at the reduced rates until approximately
10 pore volumes were exchanged and leachate samples were collected after
exchange of an estimated 0.5, 1, 2, 5, and 10 pore volumes. When VOCs were not
detected in these leachate samples, the leaching tests were stopped. The results of
these analyses and assessment ofthe results are discussed in Section 4.3.
Samples of the confining cell water were collected from the apparatus for samples
TP-3 and TP-3D and analyzed for HSL VOCs by EPA Method 624, to assess
whether VOCs may have been transferred through the latex membrane during the
test. The results of these analyses are discussed further in Section 4.3.
The leaching specimens were removed from the apparatus, and sampled as
described in Section 3.3.4. The results ofthe soil VOC sample analyses are in
Section 4.2.
December 10, 1990 Balsam Project 6185/824:S4368m C-17
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
4.0 RESULTS
4.1 SOIL PHYSICAL CHARACTERISTICS
4.1.1 Base Line Soil Physical Charac ter i s t ics
A soil specimen 10.59 cm in length and 7.28 cm in diameter was cut from Shelby
tube MTL-ST-TP3-001, placed in a flexible wall triaxial permeameter, and tested
for hydraulic conductivity in accordance with ASTM Method D-2434(74). The
hydraulic conductivity determined from this test for the soil was 1.2x10"^
centimeters per second (cm/sec). Particle specific gravity was assumed to be 2.69,
and the water content, unit weight, and porosity were determined to be
13.4 percent, 137.4 pounds per cubic foot, and 0.28, respectively.
The hydraulic conductivity and porosity measured from this sample were used
with a representative field gradient, determined from RI data, to calculate a flow
rate indicative of conditions in the area from which the leaching samples were
obtained. This field flow rate was then multiplied by a scale factor to allow
modeling of a certain period of in situ flow in a shorter real-time period. The
representative field gradient was measured to be 0.14, which multiplied by the
measured hydraulic conductivity and divided by the porosity gave a field flow rate
of 6x10"^ centimeters per second.
4.1.2 Leaching Specimen Physical Charac te r i s t ics
Leaching specimens were obtained from Shelby tube samples MTL-ST-TP3-004,
MTL-ST-TP3-005, MTL-ST-TP2-002, and MTL-ST-TP6-001, referred to herein as
samples TP-3, TP-3D, TP-2, and TP-6, respectively. Sample TP-3D was a from an
area adjacent to sample TP-3, which was subjected to leaching flow at
December 10, 1990 Balsam Project 6185/824:S4368m C-18
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
approximately one half the test flow rate of the other three samples, as previously
described.
After completion of tbe leaching tests, the specific gravity, unit weight, porosity,
grain size distribution, and hydraulic conductivity were determined for each ofthe
tested specimens using the methods described in Section 4.1.1. The results of
these analyses are summarized in Table C-2. Grain size distribution curves of the
tested specimens are included in Attachment C.
4.2 SOIL CHEMICAL ANALYTICAL RESULTS
4.2.1 Base Line Resul ts
As discussed in Section 3.3.4, base line soil samples representative of the leaching
specimens were analyzed for HSL VOCs. The compounds and concentrations
detected in these analyses are summarized in Table C-3. The results obtained
from analyses of the base line soil samples were generally consistent with
analytical results for soil samples collected from the Phase I and Phase II soil
boring programs. Samples collected from borings BE-10 and BE-11, located on the
periphery of the source area (see Figure C-2), were found to contain levels of total
VOCs in the range of approximately 30 to 70 ppb (see Table C-4). The level of
total VOCs detected iii base line sample TP-3, also located on the periphery of the
source area and in the vicinity of boring BE-10 (see Figure C-2), was
approximately 63 ppb. HSL VOCs were not detected in the base line sample from
test TP-6, which was located slightly further away and cross-gradient from the
source area. Soil collected from boring BE-13, located in the immediate vicinity of
test pit TP-6, was found to contain only a trace (approximately 2 ppb) of TCE.
Test pit TP-2 was located further downgradient from the source area, and HSL
VOCs were also not detected in the base line sample from this test pit. Boring
BE-15 was located a similar distance downgradient to that of test pit TP-2, but
December 10, 1990 Balsam Project 6185/824:S4368m C-19
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
more directly in the path of the ground water plume. Soil sampled from this
boring was found to contain approximately 34 ppb of total VOCs. HSL VOCs were
not detected in base line sample TP-3D, which was obtained from test pit TP-3.
Based upon its collection from an adjacent locatiori to sample TP-3 and the
observation of VOCs in leachate from sample TP-3D, it appears that VOCs were
not detected in this base line sample because of subsurface heterogeneity,
limitations in anal3^ical sample preparation, or, possibly, VOC losses during
handling in the field or laboratory.
Results of soil sample analyses for TOC and TVS are summarized in Table C-5.
TOC levels in both base line and leaching samples were tjrpically less than 0.1
percent. TVS levels were in the range of 0.5 to 0.7 percent by weight, although
TVS levels in the soil samples from test pit TP-6 were slightly higher, 0.9 to 1.2
percent by weight.
4.2.2 Pos t -Leaching Resul ts
At the conclusion of the leaching tests, samples of leached soil specimens were
analyzed for HSL VOCs as described in Section 3.3.6. HSL VOCs were not
detected in these samples.
4.3 LEACHING TEST RESULTS
4.3.1 Flow Rates
Three of the leaching test flow rates were set to model approximately 1 year of in
situ flow in 2 weeks of real time by multiplying the field flow rate of 6x10^ cm/sec
by a factor of 26 to yield an approximate test flow rate of 1.56x10'^ cm/sec. The
design volumetric flow rates were then estimated by multiplying the test flow rate
by the net cross sectional area of the individual leaching specimens and the
porosity measured in the baseline sample (see Table C-6). The fourth leaching
December 10, 1990 Balsam Project 6185/824:S4368m C-20
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
specimen, a duplicate of one of the other three specimens, was set up to model
approximately 1 year of in situ flow in 4 weeks, approximately half the test flow
rate used for the other leaching samples, or 7.8x10"'' cm/sec. A slower test flow
rate was used for this sample to assess potential effects of the increased flow rate
relative to field conditions on VOC desorption behavior.
One concem associated with increasing the test flow rate over the natiu-al flow
rate is that laminar flow conditions may not be maintained, i.e., the flow might
become turbulent, and that the altered flow regime may affect VOC leaching and
flushing behavior. The type of flow condition is evaluated by the dimensionless
ratio of inertial forces to viscous forces, called the Reynolds number (R .). To check
the flow condition, a R is calculated for a given set of conditions, i.e., flow of water
through a soil specimen, and compared to some critical value. Bear (1972) found
that flow conditions remained laminar in porous media up to a critical R of
approximately 1, when using dgo of the porous media as the length parameter.
A conservative approach was taken to check the model flow conditions, specifically,
the largest dgg and the highest velocity were used to calculate the model R for
comparison to the previously described critical R of 1. The calculated R^ was
9.88x10'^, which is significantly less than the critical R , indicating that laminar
conditions were maintained in the leaching specimens at the accelerated test flow
rates.
Because of variability in the physical characteristics of individual leaching
specimens, the actual leaching test flow rates varied somewhat from the nominal
test flow rates estimated on the basis of the base line soil sample characteristics.
In addition, the test flow rates were changed during the tests to assess possible
equilibrium effects on VOC desorption associated with the accelerated test flow
rates relative to field flow rates. The leaching tests can be broken down into two
primary stages on the basis of the average test flow rates. Stage 1 was the initial
test flow rate as set according to the initial calculations. These initial flow rates
December 10, 1990 Balsam Project 6185/824:S4368m C-21
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
are summarized in Table C-6. The Stage 2 flow rate was slower than the initial
test flow rate by a factor of five to assess possible equilibrium effects, as previously
discussed.
The actual pore volumes from which leachate samples were obtained were
calculated at the conclusion of the leaching tests using the measured bulk soil
volumes and porosities of the individual leaching specimens in conjunction with
the leachate volume records, which were maintained as discussed in Section 3.3.5.
The calculated pore volumes for samples TP-3, TP-3D, TP-2, and TP-6 were
140.2 ml, 129.6 ml, 162.3 ml, and 175.5 ml, respectively.
4.3.2 Leacha te Da ta
Tables C-7 through C-9 are summaries of the HSL VOCs and levels detected in
leachate samples collected from leaching samples TP-3, TP-3D, and TP-2,
respectively. HSL VOCs were not detected in the leachate samples from leaching
sample TP-6. In addition to the compounds listed on these tables, carbon disulfide
was periodically detected in the leachate samples from three of the four leaching
samples (TP-3, TP-3D, and TP-6), and detected concentrations generally exhibited
an increasing trend, contrary to the generally decreasing trends exhibited by the
concentrations ofthe other VOCs detected. Carbon disulfide was also detected in
both of the confining cell water samples analyzed, but it was not detected in
influent samples. Based upon these results, it is possible that the presence of
carbon disulfide was a result of biodegradation of sulfur-containing compounds
present in the leaching soil samples or that it was associated with the latex
membranes used to hold the leaching samples. Changes in the leaching test flow
rates are also shown on these tables.
December 10, 1990 Balsam Project 6185/824:S4368m , C-22
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
4.3.3 QA/QC Data
A sample of influent leaching fluid was collected from the TP-3 and TP-3D test
systems to assess whether VOCs were diffusing hydraulically upgradient of the
sample. HSL VOCs were not detected in either of the collected samples, indicating
that VOCs were not diffusing hydraulically upgradient. In addition, a distilled
water rinse of the influent reservoir of TP-6 was performed and the rinse water
analyzed in an eff'ort to assess possible sources of carbon disulfide. HSL VOCs,
were not detected in this sample.
At the conclusion of the leaching tests, samples of the confining cell fluid were
collected from the sample TP-3 and TP-3D test systems, and analyzed for VOCs in
order to estimate the mass of VOCs that may have diffused through the latex
membrane surrounding the specimens or leaked through seals or fittings. VOCs
were not detected in the collected samples, with the exception of carbon disulfide,
indicating that VOCs were not lost from the specimens to the confining cell fluid.
Trip blank samples accompanied the empty sample vials shipped from the
analytical laboratory to the leaching laboratory, and were sent back to the
analytical laboratory periodically with the collected leachate samples. VOCs were
not detected in the trip blank samples, indicating that extraneous contamination
was not introduced into the sample containers duririg shipping and handling.
4.3.4 Discussion
As discussed in Section 2.0 ofthe FS, TCE and vinyl chloride were selected as the
principal constituents of concem in site ground water. Accordingly, analysis of the
leaching study results was focused on these constituents. Results for other
constituents of concern were found to be constituent with those for TCE and vinyl
chloride.
December 10, 1990 Balsam Project 6185/824:S4368m C-23
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
TCE was detected in leachate from only sample TP-3 at concentrations below the
TCL of 5 ug/l. Vinyl chloride was detected in one leachate sample collected from
leaching sample TP-3D and in four leachate samples from leaching sample TP-3; it
was not detected in leachate from samples TP-2 and TP-6. In leachate from
sample TP-3D, vinyl chloride was not detected aft er exchange of approximately
two pore volumes. In TP-3 leachate sample, vinyl chloride was detected at the
TCL of 2 ug/l after exchange of approximately five pore volumes and was not
detected subsequently. These results suggest that, after removal of the VOC
source in affected former disposal area soils, the combined mechanisms of pore
water flushing and desorption by ground water flow will reduce levels of the
constituents of concern to below ground water TCLs after exchange of less than
one to five pore volumes in soils containing similar levels of residual VOCs as the
samples tested. The fact that VOCs were not observed in leachate samples
collected after the test flow rates were slowed by a factor of five may indicate that
the VOCs originally in the leaching samples were present principally in pore water
and that significant amounts of VOCs were not sorbed to the soils. This
observation is consistent with the relatively low organic carbon content of the soil
samples, tjrpically less than 0.1 percent on a weight basis. Analyses of leaching
water from influent lines and of confining cell water did not detect VOCs, with the
exception of carbon disulfide, which appeared to be unrelated to site
contamination. These data suggest that significant, losses of VOCs from the
leaching samples and leachate did not occur.
Near the conclusion of the tests, when little or no VOC contamination was being
detected in leachate samples, the test flow rates were reduced by a factor of five,
and leachates samples subsequently collected and analyzed to assess desorption
equilibrium behavior. HSL VOCs were not detected in the leachate samples
collected after the test rates were reduced, suggesting that desorption equilibria
were not significantly affected by the test flow rate. Also, VOC concentrations in
leachate samples from sample TP-3D, which was tested at a flow approximately
December 10, 1990 Balsam Project 6185/824 :S4368m C-24
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
half that of an adjacent sample, TP-3, did not exhibit significantly different results
with regard to levels of VOCs in leachate, nor in the number of pore volume
exchanges required to desorb and flush the sample.
December 10, 1990 Balsam Project 6185/824:S4368m C-25
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
REFERENCES
1) American Public Health Association, et al.. Standard Methods for the Examination of Water and Wastewater, 16th ed., 1985.
2) Bouchard, D.C, et al., "Sorption Nonequilibrium During Solute Transport," Joumal of Contaminant Hydrology, Vol. 2, pp. 209-223, 1988.
3) Curtis, G.P., et al.,"A Natural Gradient Experiment on Solute Transport in a Sand Aquifer: 4. Sorption of Organic Solutes and its Influence on Mobihty," Water Resources Research, Vol. 22, No. 13, pp. 2059-2067, December 1986.
4) Fetter, C.W., Applied Hydrogeology, 2nd. ed., Merrill Publishing Company, Toronto, 1988, pp.397-400.
5) Freeze, R., and Cherry, J., Groundwater. Prentice-Hall, Inc., Englewood Cliff's, New Jersey, 1979, pp. 432-434.
6) Hunt, J.R., et al., "Nonaqueous Phase Liquid Transport and Cleanup," Water Resources Research, Vol. 24, No. 8, pp. 1247-1269, August 1988.
7) Hutzler, N.J., et al., "Transport of Organic Compounds With Saturated Groundwater Flow: Experimental Results," Water Resomrces Research, Vol. 22, No. 3, pp. 285-295, March 1986.
8) Lee, L.S., et al., "Nonequilibrium Sorption of Organic Contaminants During Flow Through Columns of Aquifer Materials," Environmental Toxicology and Chemistry, Vol. 7, No. 10, pp.779-793, 1988.
9) Oliver, E.G., "Desorption of Chlorinated Hydrocarbons from Spiked and Anthropogenically Contaminated Sediments," Chemosphere, Vol. 14, No. 8, pp. 1087-1106, 1985.
10) Schwarzenbach, R.P., and Westall, J., 'Transport of Nonpolar Organic Compounds from Surface Water to Groundwater. Laboratory Sorption Studies," Environmental Science & Technology, Vol. 15, No. 11, pp. 13601367, November 1981.
11) Staples, C.A., and Geiselmann, S.J., "Cosolvent Influences on Organic Solute Retardation Factors," Groundwater, Vol. 26, No.2, pp. 192-198, March-April 1988.
December 10, 1990 Balsam Project 6185/824:S4368m C-26
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
REFERENCES (continued)
12) U.S. Army Corps of Engineers Waterways Experiment Station, Procedures for Handling and Chemical Analysis of Sediment and Water Samples, May 1981.
13) U.S. Environmental Protection Agency, Determining Soil Response Action Levels Based on Potential Contaminant Migration to Ground Water: A Compendium of Examples, EPA/540/2-89/057, October 1989.
14) U.S. Environmental Protection Agency, Test Methods for Evaluating Solid Waste: Phvsical/Chemical Methods. 3rd. ed., SW-846, November 1986.
15) Wu, S., and Gschwend, P.M., "Sorption Kinetics of Hydrophobic Organic Compounds to Natural Sediments and Soils," Environmental Science & Technology, Vol. 20, No. 7, pp. 717-725, July 1986.
December 10, 1990 Balsam Project 6185/824:S4368m C-27
TABLE C-1 SOIL SAMPLING SUMMARY
Dep th (ft) Below
Sample G r o u n d S t ra tum HNu Test P i t Designat ion Date Surface Description (ppm) Recovery (in)
TP-1 Not sampled 6/12/90
TP-2 MLT-ST-TP2-001 6/12/90 5.0 Gray fine to medium 3.5 15.5 MLT-ST-TP2-002 6/12/90 5.0 sand. 19.5 MLT-ST-TP2-003 6/12/90 5.0 19.0
TP-3 MLT-ST-TP3-001 6/12/90 5.6 Gray fine to medium 40 16 MLT-ST-TP3-002 6/12/90 5.6 sand. 14 MLT-ST-TP3-003 6/12/90 5.6 12 MLT-ST-TP3-004 6/12/90 5.6 22 MLT-ST-TP3-005 6/12/90 5.6 18 MLT-ST-TP3-006 6/12/90 6.0 20
TP-4 Not sampled 6/15/90 4.0 Brown fine to medium ND sand.
TP-5 Not sampled 6/15/90 4.0 Gray fine to medium ND sand.
TP-6 MLT-ST-TP6-001 6/15/90 4.5 Gray fine to medium 10 sand.
Notes:
1) HNu screening results in parts per million (ppm) above background referenced to an isobytylene standard. 2) "-" = Sample not collected. 3) ND = Screening results at background. 4) VOCs = Volatile organic compounds.
Comments
Bedrock encountered at 6 feet. Soils unsaturated.
Ground water encountered at 4.5 feet below ground surface.
Ground water encountered at 3.3 feet below ground surface.
VOCs not detected.
VOCs not detected.
Ground water encoimtered at 3.5 feet below ground surface.
December 10, 1990 Balsam Project 6185/824:S4368m Page 1 of 1
TABLE C-2
SOIL SAMPLE PHYSICAL CHARACTERISTICS
Length Diameter Unit Weight Water Content Hydraul ic Specimen (cm) (cm) (pcf) (%) Porosi ty Conductivi ty (cm/s)
Baseline 10.59 7.28 137.4 13.4 0.28 1.2 X 10-4
TP-3 11.67 7.33 137.2 13.5 0.28 4.8 X 10-*
TP-3D 11.86 7.29 140.5 13.4 0.26 1.3 X 10-*
TP-2 11.78 7.28 132.5 18.3 0.33 2.8 X 10-3
TP-6 12.57 7.27 123.3 11.6 0.34 2.3 X 10-
Notes: 1) Baseline sample des igna ted MTL-ST-TP3-001 1) cm = centimeters. 2) pcf = pounds per cubic foot. 3) % = percent on weight/weight basis. 4) s = seconds.
December 10, 1990 Balsam Project 6185:824:S4368m Page 1 of 1
TABLE C-3
SUMMARY OF COMPOUNDS DETECTED IN BASE LINE SOIL SAMPLES
Compound 'l'P-3 TP-3D TP-2 TP-6
1,2-dichloroethene (total) 10 ND(5) ND(5) ND(5)
ethylbenzene 9 ND(5) ND(5) ND(5)
toluene 11 ND(5) ND(5) ND(5)
4-methyl-2-pentanone 4J ND(IO) ND(IO) ND(IO)
total xylenes 29 ND(5) ND(5) ND(5)
Notes:
1) Concentrations in micrograms per kilogram (ug/kg) or parts per billion (ppb). 2) ND(5) = compound not detected at specified detection limits. 3) J = compound present below limit of reliable quantitation, estimated concentration. 4) All other HSL VOCs not reported present at detectable levels.
December 10, 1990 Balsam Project 6185:824:S4368m Page 1 of 1
TABLE C-4 SUMMARY OF COMPOUNDS DETECTED
IN SELECTED RI SOIL SAMPLES
SOIL SAMPLE
Compound BE-10(002) BE-10(004) BE-11(002A) BE-13(003) BE-14(004) BE-15(002)
1,2-Dichloroethenes 4J ND ND ND ND ND
Chloroform 3J ND ND ND ND ND
Trichloroethene 4J 2J ND 2J ND ND
Tetrachloroethene 2J 15 ND ND ND ND
Toluene 3J ND SJ ND ND ND
Total Xylenes 7J 34 29J ND ND ND
2-Butanone ND 15 ND ND 310 ND
Ethylbenzene ND 3J 7J ND ND ND
Acetone ND ND ND ND ND 31
1,1-Dichloroethane ND ND ND ND ND 3J
Total VOCs 33(J) 69(J) 44(J) 2J 310 34(J)
Notes:
1) Concentration units are micrograms per kilogram (ug/kg) or parts per billion (ppb). 2) ND = Not detected. 3) VOCs = Volatile organic compounds. .
December 10,1990 Balsam Project 6185/824;S4368m Page 1 of 1
TABLE C-5
TOC AND TVS RESULTS FOR BASE U N E AND LEACHING
SOIL SAMPLES
Sample TOC TVS
TP-2 (B)
TP-2 (L)
TP-3(B)
TP-3 (L)
TP-3D (B)
TP-3D (L)
TP-6 (B)
TP-6 (L)
0.1
<0.1
<0.1
<0.1
<0.1
<0.1
0.2
<0.1
0.5
0.7
0.6
0.4
0.7
0.5
0.9
1.2
Notes:
1. TOC and TVS results in percent by weight. 2. (B) = Base line soil sample. 3. (L) = Leaching soil sample.
December 10, 1990 Balsam Project 6185/824:S4368m Page 1 of 1
TABLE C-6
SUMMARY OF DESIGN AND TEST FLOW RATES AND VOLUMETRIC FLOW RATES
SAMPLES
TP-3 TP-3D TP-2 TP-6
Design Flow Rate 1.56 x 10' 7.80 X i C 1.56 X 10" 1.56 X 10- (cm/s)
Initial Test Flow 1.18 X 10" 5.46 X 10-* 1.23 X 10- 8.47 X IO-:" Rate (cm/s)
Sample Cross Sectional Area 42.2 41.7 41.6 41.5 (cm^)
Design Volumetric Flow Rate 66 33 65 65, (cm%r)
Initial Test Volumetric Flow 50 21 61 43 Rate (cm^/hr)
Notes:
1) cm/s = centimeters per second. 2) cm^ = square centimeters. ' • 3) cm^/hr = cubic centimeters per hour. 4) Test flow rates from samples TP-3, TP-2 and TP-6 were reduced by a factor of five for a second
stage of tests.
December 10, 1990 Balsam Project 6185/824:S4368m Page 1 of 1
Table C-7: Summary of Compounds Detected in Sample TP-3 Leachate
Sample TP3-001 TP3-005 TP3-007 TP3-009 TP3-011 TP3-013 TP3-015 TP3-017 TP3-018 TP3-019 TP3-020 TP3-020a TP3-021 TP3-022 TP3-023
Date Collected 06/19/90 06/19/90 06/19/90 06/20/90 06/20/90 06/21/90 06/23/90 06/26/90 06/28/90 07/02/90 07/12/90 07/23/90 07/23/90 7/24/90 07/31/90
Pore Volumes 0.44 0.99 2.09 4.87 9.71 19.48 48.67 70.43 83.24 107.72 228.36 0.8 1.39 2.6 14.32
Concentration Units ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l
Flow Flow
Stage 1 Stage 2
Acetone 12
2-Butanone 16 12 7
Chloroform 4
1,2-Oichloroethenes 660 390 170 66 20 3
Ethylbenzene 110 83 75 40 29 16
4-Methyl-2-pentanone 32 21 8
Trichloroethene 3 2
Toluene 430 300 180 95 54 15 3
Vinyl Chloride 19 11 4 2
Xylene (total) 280 200 180 110 83 46 10
Total VOCs 1547 1017 631 327 195 80 16
TABLE C-8
SUMMARY OF COMPOUNDS DETECTED IN SAMPLE TP-3D LEACHATE
Sample TP3D-001 TP3D-003 TP3D-005 TP3D-007 TP3D-009 TP3D-011 TP3D-012 TP3D-013 TP3D-014 TP3D-015
Date Collected 06/22/90 06/22/90 06/22/90 06/22/90 06/24/90 06/26/90 07/01/90 07/05/90 07/12/90 07/17/90
Pore Volumes 0.48 0.79 1.7 4.2 11 17 41 53 85 134
Concentration Units ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l • ug/l
2-Butanone
1,1-Dichloroethane
1,2-Dichloroethenes
1,1,1-Trichloroethane
Ethylbenzene
4-Methyl-2-pentanone
Tetrahydrofuran
Toluene
Vinyl Chloride
Xylene (total)
Flow
Stage 1
120
320
90
62
87
28
310
10
45
20
250
20
22
32
4
24 62 60 41
340 260 56 17
50 83 100 120
Total VOCs 592 792 450 407 216 178
TABLE C-9
SUMMARY OF COMPOUNDS DETECTED IN SAMPLE TP-2 LEACHATE
Sample TP2-001 TP2-002 TP2-003 TP2-004 TP2-005 TP2-006 TP2-007 TP2-008 TP2-009 TP2-010 TP2-011 TP2-012 TP2-013 TP2-014
Date Collected 06/25/90 06/25/90 06/25/90 06/25/90 06/25/90 06/27/90 06/29/90 07/01/90 07/05/90 07/18/90 07/18/90 07/12/90 07/20/90 7/22/90
Pore Volumes 0.39 1.06 1.61 2.83 7.28 15.63 37.3 54.8 74.5 0.44 0.76 1.76 3.76 7.03
Concentration Units. ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l ug/l
Acetone
Flow
Stage 1
10
Flow
Stage 2
40 21
Chloroethane 10 6 3
1,1-Dichloroethane 440 260 180 74 10
1,2-Dichloroethenes 4 2 2
1,1,1-Trichloroethane 7 5 5 3 2
Toluene 1 2
Total VOCs 461 273 188 80 14 10 40 21
ATTACHMENT A
TEST PIT LOGS
TEST PIT FIELD LOG TEST PIT N0 ._ TP-1 A\ BAUAM PROJECT: Mottolo FS PROJECT N0 ._ i§5/e2(? ENVIRONUENTAL CONSULTANTS. INC Raymond, New Hampshire OATF 6/12/90
BALSAM ENGINEER/GEOLOGIST: CONTRACTOR Environmental D r i l l i n g GROUND ELEV. OPFRATOR Br ian Hayes TIMF STARTFn 0930
G. G a r f i e l d & F. F ied le r FQIIIPMFNT, MAKT l>j- MOHFl • Ford 555 TII^F C n U P I FTFn- ^UiO WFATHFR Clear 70 's
CAPACITY: 1 r., yH REACH: 12
FIELD BOULDER EXCAV. REMARK DEPTH STRATUM DESCRIPTION SCREENING COUNT EFFORT NO. (PPM)' NO.-SIZE
Brown, f i n e to medium SAND, l i t t l e S i l t , t race Gravel w i t h roo t M 1-A mat and p l a s t i c sheet f ragments. DRY. <1 1.2 1
1.0 M
<1 D 13-A Grayish brown, f i n e to coarse SAND, some Grave l , t race S i l t , w i t h approximately 5 - 10 % Cobbles. DRY. D
D ^ 3 . 0 —
• D D
— 4.0 — D
D
O.U <1 D
3 p. A Bottom of t e s t p i t a t 5.5 f e e t .
• D.U
7.0 - ^
— 8.0 —
, — 9.0 —
— 1 0 . 0 —
— 1 1 . 0 —
— 1 2 . 0 —
— 1 3 . 0 —
— 1 4 . 0 —
REMARKS: 1 . S o i l samples screened i n the f i e l d f o r VOCs using a HNu Pho to ion iza t ion d e t e c t o r .
2. S o i l samples co l l ec ted i n j a r s a t 1.0, 2.5 and 5 f e e t below ground su r face . 3. Backhoe r e f u s a l encountered a t 5.0 f ee t on bedrock.
TEST PIT PLAN BOULDER CLASSinCATION PROPORTIONS ABBREVIATIONS EXCAVATION USED EFFORT
h — 10 F = FINE SIZE RANGE CLASS TRACE(t.) 1-10%
M = MEDIUM E = EASY 6--18r A UTTLEO.) 10-20% mmm.
0 C = " ' ' M •» MorDERATE COARSE "
18"-36" B SOME(s.) 20-35% F-M - RNE TO MEDIUM D " DIF FICULT
>36" C AND 35-50% ro«ws/o«/Hr NORTH F-C •= RNE TO COARSE
3
TEST PIT FIELD LOG TEST PIT N 0 . _ TP-?, BALSAM P R O J E C T : M o t t o l o FS PROJECT N O . - ^185/826 # ^ ENVIRONUENTAL CONSULTANTS. I N t Raymond, New Hampshire OATF 6/12/90
BALSAM E N G I N E E R / G E O L O G I S T : C O N T R A C T O R E n v i r o n m e n t a l D r i l l i n g . GROUND ELEV. O P F R A T O R - B r i a n H a v e s . TIME STARTED: ^03°,,,,, ,
G. G a r f i e l d & F . F i e d l e r FOI I I P M F N T U A K F fr M O O F I F o r d 5 5 5 TIMF C O M P l F T F n - 1 ^ WFATHFR- C l e a r 7 0 ' s
C A P A C I T Y : 1 r . i yH R F A C H r 12
HELD BOULDER EXCAV. REMARK DEPTH STRATUM DESCRIPTION . SCREENING COUNT EFFORT NO. (PPM)' NO.-SIZE n
Dark brown, fine to medium SAND, l i t t l e S i l t , t r ace Gravel with M 2-A 1.2 heavy root mat. DRY. 0.5
— 1.0 5-A Brown, fine to medium SAND, l i t t l e Gravel, t r ace S i l t with
approximately 10% cobbles . DRY. y— 2.0 — - M 3
M L3.0 —
M 5 M
4.0 Gray, f ine to medium SAND, t race Gravel, t r ace S i l t . MOIST M\ 7
D 5 . 0 ' ^
3.5 D 1-C / C l a s s C N. / Boulder \ D
6.0 Bottom of t e s t p i t a t 6.0 f e e t . 2.5
— 7.0 —
8.0 — _
9.0 —
— 1 0 . 0 —
I 11.0 — •
12.0 —
13.0 —
—^14.0 — •
REMARKS: 1. Soil samples screened in the f i e ld for VOCs using a HNu Photoionization de t ec to r . 2. Soil samples col lected in j a r s a t depths of 0 . 5 , 5.0 and 6.0 f ee t . 3 . Ground water observed a t 4.5 f e e t . 4 . Three thin walled shelby tube sampels co l lec ted a t 5.0 f ee t . 5. TP-2 terminated a f te r c o l l e c t i o n of required number of samples.
BOULDER ClASSIFICATION TEST PIT PLAN PROPORTIONS ABBREVIATIONS EXCAVATION USED EFFORT
F = FINE SIZE RANGE CLASS TRACE(L) 1-10%
M «• MEDIUM E - EASY 6"-ier A LTTTLEO.) 10-20%
10 wmA C = "COARSE M Mor DERATE
18"-36" B S0ME(3.) 2 0 - 3 5 % F-M - RNE TO MEDIUM 0 DIF -ICULT
>36" C ANO 3 5 - 5 0 % •rr^o^/r^AKT NORTH F-C " FINE TO ( :OARSE
TEST PIT FIELD LOG TEST PIT N 0 . _ TP-3 A\ BALSAM P R O J E C T : M o t t o l o FS PROJECT N O . - ^185/826 ENVIRONUENTAL CONSULTANTS. INt Raymond, New Hampshire | PATF 6/12/90
BALSAM ENGINEER/GEOLOGIST: CONTRACTOR E n v i r o n m e n t a l D r i l l i n g . GROUND ELEV. 1 OPFRATOR B r i a n Hayes TllulF <;TARTFnr 1330
G. G a r f i e l d & F . F i e d l e r FOI IIPMFNT, MAKF fr. MOOFI Ford 5 5 5 . TIMF COMPI F T F n 1630 W/FATHFR- C l e a r 7 0 ' s
CAPACITY: i c u . yd . REACH: i^ |
FIELD BOULDER EXCAV. REMARK DEPTH STRATUM DESCRIPTION . I SCREENING COUNT
EFFORT NO. (PPM)' NO. -S IZE n Brown, f i n e t o c o a r s e SAND, l i t t l e S i l t , t r a c e Grave l w i t h r o o t M 2-A 1.2 ma t . DRY.
1 n 1 .(J Y 1-C
A5 M 2n n Gray , f i n e t o medium SAND, t r a c e S i l t , t r a c e G r a v e l w i t h t i m b e r , z .U • Mp l a s t i c and wheel r i m s . MOIST. FILL.
M" n Tl o . \ j • 50 M 3
Brown, f i n e t o c o a r s e SAND, l i t t l e S i l t , l i t t l e G r a v e l w i t h s c r a p m e t a l . WET. M 3-A
— 4.0 D
Gray f i n e t o medium SAND, t r a c e S i l t , t r a c e - G r a v e l . WET. M
5.0 — M A
M — 6.0 —
40 M M
7.0 5Bottom of t e s t p i t a t 7 . 0 f e e t .
8.0 —
n - 9 . 0 —
:—10.0 ^
11.0 —
12.0 —
^ 1 3 . 0 — )
' 14.0 —
REMARKS: 1. S o i l s amples sc reened i n t h e f i e l d f o r VOCs u s i n g a HNu P h o t o i o n i z a t i o n d e t e c t o r .
2 . S o i l s amples c o l l e c t e d in j a r s a t d e p t h s of 1 . 5 , 3 . 0 and 6 .0 f e e t . 3 . Ground wa te r encoun te red a t 3 . 3 f e e t . ^ . S ix t h i n wa l l ed she lby t ube sampels o b t a i n e d from 5 . 5 f e e t t o 6 . 0 f e e t . 5 . TP-3 t e r m i n a t e d a f t e r c o l l e c t i o n of r e q u i r e d number of s a m p l e s .
TFST PIT PI AN BOULDER ClASSinCATlON ABBREVIATIONS PROPORTIONS EXCAVATION USED EFORT I 1 — 12 - H F - RNE
SIZE RANGE CLASS TRACE(L) 1-10% 28 M = MEDIUM E = EASY
^ ^ ^ 6"-16" A LTTTLECl.) 10 -20% C - COARSE M - MO J t R A T t
18"-36" B S0ME(3.) 2 0 - 3 5 % MEDIUM D - Din F-M - RNE TO •ICULT
> 3 6 ' C AND 3 5 - 5 0 % \ . r ^ , ^ f ^ NORTH F-C - FINE TO (;OARSE
TEST PIT FIELD LOG TEST PIT NO. TP-4 A BAUAM PROJECT: Mot to lo FS PROJECT NO ^165/826 ^ K ^ w \ ENVIRONMENTAL CONSULTANTS. INC Raymond, New Hampshire DATE 6/15/99
5 WOUSTKIAL WAY, SALEM. NH 03079
BALSAM ENGINEER/GEOLOGIST: C O M T R A O T O R - Environmental D r i l l i n g GROUND ELEV.. • 0 8 3 r OPFRATOR- Brian Hayes TIME STARTED:.
G. Garfield & F. Fiedler EQUIPMENT, MAKE & MODFI ; Ford 555 TIME COMPLETED: _2§32_ WFATHFR- Sunny 60s
CAPACITY: _ J cu . yd . REACH: 12_
FIELD BOULDER EXCAV. REMARK DEPTH STRATUM DESCRIPTION SCREENING COUNT EFFORT NO. (PPM)' NO.-SIZE I 0
Dark brown, fine to medium SAND, little Silt, trace Gravel with 2-A root mat. MOIST.
1.0 —
<1 2.0
Gray, fine SAND, little Silt. MOIST.
3.0 <1 Brown, fine to medium SAND, little Silt, trace Gravel with
V - iron stains. WET. Changes to gray brown at 4 feet. — 4.0
•5.0 Bottom of test pit at 5.0 feet.
•6.0 —]
•7.0
•8.0 —
•9.0 —
•10.0
•11.0 —
•12.0 —
•13.0 —
•14.0
REMARKS: 1. Soil samples screened in the field for VOCs using a HNu Photoionization detector. 2. Ground Water observed at 3.8 feet. 3. TP-4 terminated due to VOCs not being present.
TEST PIT PLAN BOULDER CUSSIFICATION PROPORTIONS . ABBREVIATIONS EXCAVATION iiSED F-FFORT f— 9 - H F " RNE
SIZE RANGE CLASS TRACE(t) 1-10% 4 M = MEDIUM E - EASY
er-ier A LTTTLEO.) 10-20% mm. 0
C = COARSE M - MODERATE 18"-36" B S0ME(3.) 20-35%
F-M - FINE TO MEDIUM D - DIFFICULT >36" . C AND 35-50%
NORTH F-C - RNE TO COARSE fORUS/tXC/PfT
TEST PIT FIELD LOG TEST PIT N 0 . _ TP-5 A\ BALSAM PROJECT: Mottolo FS PROJECT N 0 . _ $185/826 ENVIRONMENTAL CONSULTANTS. INC. Raymond, New Hampshire PATF 6/15/90
BALSAM ENGINEER/GEOLOGIST: CONTRACTOR Env i ronmen ta l D r i l l i n g GROUND ELEV. OPFRATOR B r i a n Hayes TIME STARTED: 0900
G. G a r f i e l d & F . F i e d l e r FQIIIPUFMT MAKF fr. M O D F I - Ford 555 . TIME COMPLETED: "^^^ Vl/FATHFRr Sunny 6 0 ' s
CAPACITY: 1 n , yH.RFACH: 12
DEPTH
n
— 1.0
2.0 —
^ 3 . 0 — 2 _
4.0 —
5.0 —
6.0 —
S T R A T U M D E S C R I P T I O N .
Dark brown, fine to medium SAND, l i t t l e S i l t , t r a ce Gravel with reminents of a hay ba le . MOIST.
Grayish brown, f ine to medium SAND, t r ace S i l t , t r a ce Gravel . MOIST.
Gray, fine to medium SAND, t race S i l t . WET.
Bottom of t e s t p i t a t 5.4 f ee t .
FIELD SCREENING
(PPM)'
<1
•
<1
<1
EXCAV. EFFORT
E E
E
t : E
E
E
E
E
E
E
BOULDER COUNT
NO.-SIZE
REMARK NO.
.1
2
3
7.0 —
8.0 —
9.0 —
10.0 —
11.0 —
12.0 —
13.0 —
14.0 —
REMARKS: 1. Soil samples screened in the f ie ld for VXs using
2. Ground water observed a t 3.8 fee t . I 3 . TP-5 terminated due to VOCs not being present .
a HNu Photoionizat ion de tec to r .
TEST PIT PIAN BOULDER CLASSinCATION PROPORTIONS ABBREVIATIONS EXCAVATION USED EFFORT 1 K- 12 -H F = RNE
SIZE RANGE CLASS TRACE(L) 1-10% 4 / / / / / / / / M « MEDIUM E - E^SY
6'-18" A LTTTLEO.) 10-20% ^ZT/AA///.
© C - COARSE 3ERATE M - Mor
ier-36" B SOME(s.) 20-35% F-M - RNE TO 'ICULT MEDIUM D = OlFf
>36" C ANO 35-50% P,>m«/e>»/Pa NORTH F-C - RNE TO ( :OARSE
TEST PIT FIELD LOG TEST PIT NO. TP-6 ABALSAM PROJECT: Mottolo FS PROJECT NO. 6185/826 T R S W \ ENVIRONMENTAL CONSULTANTS, INC. Raymond, New Hampshire DATE ^/1^/90
5 INDUSTRIAL WAY. SALEU, NH (U078
BALSAM ENGINEER/GEOLOGIST: COMTRArTOR- Environmental D r i l l i ng GROUND ELEV. OPFRATOR- Brian Hayes TIME STARTED:. 0925
G. Garfield & F. Fiedler EQUIPMENT. MAKE & MOOFI - Ford 555 TIME COMPLETED: l£30_ WFATHFR- Sunny 60 s
CAPACITT: _ J cu. yd. REACH: _ 1 L
FIELD BOULDER EXCAV. REMARK DEPTH STRATUM DESCRIPTION SCREENING COUNT EFFORT NO. (PPM)' NO.-SIZE <1 Black and dark brown, fine SAND, l i t t l e S i l t . MOIST.
Black Gravel. 1.0
<1
T<1 5+-A _Grayish brown, fine to medium SAND, trace Silt, trace Gravel.
<1 2.0
-Orangish brown, fine to coarse SAND, little Silt, trace Gravel.
3.0 Gray, fine to medium SAND, trace Silt, trace Gravel, <1
4.0 —\
5.0 —
6.0 Bottom of test pit at 5.8 feet.
7.0
• 8 .0 —
•9 .0 —
•10.0
•11.0 —
•12.0 —
•13.0 —
•14.0 —
REMARKS: 1. Soil samples screened in the field for VOCs using a HNu Photoionization detector. 2. Ground water observed at 3.5 feet. 3. TP-6 terminated after obtaining one thin walled shelby tube.
TEST PIT PLAN BOULDER CLASSIFICATION PROPORTIONS ABBREVIATIONS EXCAVATION iiSED EFFORT I f * - 20.5 F » RNE
SIZE RANGE CLASS TRACE(L) 1-10% M = MEDIUM E = EASY
6--18" A UTTLEO.) 10-20% ^ C - COARSE M «- MODERATE
18'-36" B S0ME(3.) 20-35% T © F-M - RNE TO MEDIUM D - DIFRCULT >36" C AND 35-50%
NORTH F-C " RNE TO COARSE rORUS/ENC/PtT
ATTACHMENT B
LEACHATE VOLUME RECORDS
CONSTANT- FLOW RATE LEACHABILITY TEST o o o-o to
o o o-o in
o o o -o-*•
Stage 2: o Avera ge flow rat^ = 89 ccj^hour
^o
o -c o
Ld O O
o Stage 1: (N Average fl 3w rate = 50 c c / h o u r
tage 3: /Iverage flow rate = IC c c / h o u r
100 200 300 400 500 600 700 800 900 Flow Duration (Hours)
LEI BORING: M T L - S T - T P 3 - 0 0 4 MOTTOLO LEACHABILirr STUDY SPECIMEN: 1 PROJECT 90221 August 16. 1990 Structure: Undisturbed tube sample Initial water content = 13.52S5, density = 137.22 pcf _ GEI Consultants. Inc. Specific Gravity = 2.699. Volume of Voids = 140.2 cm Winchester Massachusetts
CONSTANT FLOW RATE LEACHABILITY TEST o o o o
O O o — Stage 3: m - * CN Averog e flow rat J = 16 c : / h o u r
O . - - ' ' ^ O / - O
/ • /Stage
Average flow rate = 52 CC / h o u r * /
-•
o Stage 1: ^ /Average •low rate ^ = 22 c c / l lour^^ ' ' ' * ' ^
o o _ j • . ^ ^ ' ' ^ o ^
\ ' 1 1 1 1 . 1 I 1 1 1
100 200 300 400 500 600 700 800 900 1000 Flow Duration (Hours)
LE2 BORING: M T L - S T - T P 3 - 0 0 5 MOTTOLO LEACHABILITY STUDY SPECIMEN: 1 PROJECT 90221 August 20, 1990 Structure: Undisturbed tube sample Initial water content = 13,39s8. density = 140.54 pcf GEI Consultants, Inc. Specific Gravity = 2 . 6 9 1 , Volume of Voids =• 129.6 cm^ Winchester Massachusetts
Eff
lue
nt
(cc)
)0
0 1
50
00
1
CONSTANT FLOW RATE LEACHABILIIY TEST o o o o
o o . o — m f ^ ^ ^ o o o
O O
St age 2: Av srage flow rote •• = 75 c c / h o u r ^ - ' o — y ^
c o o 5/-^
s§Stage 1:
u Average flow ra :e = 61 c c / h o u i o * . y^^ o o — o
s_ O 1 Stage 3:
— • — Average flow -ate = 9 cc /hou r . * *
o — r 1 1 1 1 1 1 1 1 l - l 1 1 C) 100 200 300 400 500 600
Flow Duration (Hours)
BORING: M T L - S T - T P 2 - 0 0 2 _ MOTTOLO LEACHABILITT STUDY SPECIMEN: • PROJECT 90221 August 16. 1990 Structure: Undisturbed tube sample Initial wateir content = 18.31$c, density = 132.5 pcf GEI Consultants, Inc. Specific G ravity =• 2.682, Volume of Voids = 162.3 cm^ Winchester Massachusetts
CONSTANT FLOW RATE LEACHABILITY TEST o o o-o rO
O O O — m CN
O O o-O OJ Stage 2:
Average flow rate = 61 c c / h o u r o
J-. o C lO 15 .
. UJ
Stage 1:
Stage 3: Average flow 'ate = 15.5 c c / lour
200 Flow
300
Duration (Hours) 400 500 600
BORING: SPECIMEN:
M T L - S T - T P 6 - 0 0 1 1
Structure: Undisturbed tube sample Initial water content = 11.5655, density = 123.3 pcf Specific Gravity = 2.670, Volume of Voids = 175.5 cm^
LE4 MOTTOLO LEACHABILITY STUDY
PROJECT 90221 August 17. 1990
GEI Consultants, Inc. Winchester Massachusetts
ATTACHMENT C
GRAIN SIZE ANALYSIS RESULTS
GRAIN SIZE niSTRIEUTION TEST REPORT
— " T — T rr iT"" :T r" r r r r j : | rrr 1 i ! ! I •44:. i j ! i 1
i • • - : M L.J. -— ' i _ ! —- i-i 4-- '
-"' r1
!! ii 7-
i 1 ; ! i 1r
i 1 f : li-. 1; i I ... 80 • j Ji 1 : : • ; T •
70
cc . _ s1 . — —\ 1- :
^ ^ 50 K I
1 LU
•
\ :
\30
20 '. j i: i
10 •
\ 0 200 100 10.0 1.0 0.1 0.01 0.001
GRAIN SIZE - mm
y. +3^ y. GRAVEL y. SAND y. FINES O 0.0 6.5 79.: 14.0
LL PI ^ l D60 I'50 I>30 KlS Dl0 C,
1.08 0.29 0. 17 0. 100 0.075;
MATERIAL DESCRIPTION AASHTO uses Silty sand
Pr-eject No.: 90221 Remarks: Project: Mottolo Leachability
O Location: MTL-ST-TP2-002
|Dc.,te: .August 2, 1990
GRAIN SIZE DISTRIBUTIOtl TEST REPORT
GEI CONSULTANTS, INC., WINCHESTER, M li F i g ur e H o .
i GRAIN SIZE DISTRIBUTION TEST REPORT
l o u ,_.r.. i " ^TTT"" — \ — ' T l • ^^ I
rA I 1 —.— •
I i • ^ • i i ;
: ; ! • :•?o .. . y — 1 ' V ^ 1 1 !""
1 \ , • . '••
8 0 • . ;
1 ; j
I ' ^ i 1
7Q .i ;
LU c-kf
»—* LL
• ' .
H; 5 0 LU
o h ui 4 0
3 0 1:
2 0
\: : '.10 H^ - . "TJ >a. " ^ 0
2 0 0 100 1 0 . 0 1 .0 0 . 1 0 . 0 1 0 . 0 0 1 GRAIN SIZE mm
y. + 3 ' y. GRAVEL y. SAND y. F INES 0 . 0 0 . 0 50 .6 4 9 . 4
LL P I DsR1^5 D60 D30 D l 5 D10 Cu
o 0 . 16 0.09 0 . 0 7 0 . 0 4 0 0 . 0 1 2 0 0 . 0 0 6 S -54 1 3 . 4
MATERIAL DESCRIPTION AASHTOuses O Silty sand iM
Project No.: 90221 jRemarks: Project: Mottolo Leachability Sample +rom LE2 io Location: MTL-ST-TP3-0e5
test spec imen
Date: August 10, 1990
GRAIN SIZE DISTRIBUTION TEST REPORT
GEI CONSULTANTS, INC., WINCHESTER, MA jj Figure Ho..
GRAIN SIZE DISTRIBUTION TEST REPORT
... ^ r• r- r'-X 'n :.) • 5. 1 - ' 1 0 U
9 0
se :
i
I
^ „ _
' : : • :
T"1 ' " "
• T • •
•
N i
:
•
•
]
S
: 1
• l i ! J i I ! i : ; - ! • •
s ! T - . •• !
f] ! 1I I I! 1
- i
•
! i
r!!
i
1 1
I I
i l 1 i 1
1 i
...
i i
:
70 ••
: az LU 6 0 - \ U- ; j -iz: LU
£
5 0
40
3 0
2 0
10
;
\
:
'•
.
j
:
I
\
\ \
;
1
K >S
V ^ kVN
h
i r. : - s 3« «*t)i : > > -«o0
200 100 10.0 1.0 0. 1 0.01 0.001 GRAIN SIZE - mm
y. +3' y. GRAVEL y. SAND y. FINES 0.0 0.2 50.6 49.2
LL PI D-r1^5 % 0 D50 '50 Dl5 I'10 c., 0.20 0. 10 0.0s 0.033 0.010s 0.006S 1.71 14.0o
MATERIAL DESCRIPTION AASHTOuses o Silty sand SM
Project No.: 90221 Remarks: Project: Mottolo Leachability
O Location: MTL-ST-TP-03-004
Date: August 14, 1990
GRAIN SIZE DISTRIBUTION TEST REPORT
GEI CONSULTANTS, INC., WINCHESTER, MA Figure Ho.
GRAIN S IZ E DISTRIBUTION TEST REPORT r
.100
90
80
!|I;\ i l i i
! I ' i ! 1 ! i ! 1 • !
" """"1: i
- • • : - ^
••; v T :
- } ' •
s s
1 i: i
• - - Is
i ? i11
i I 1 I \~ ' : 1!(
_
'is
-
i i li
iJ.i... ] ; ; i . 1
' : 1
i : i i 1 ;
1 r I
i „ . !
1
I
!
70
i '
•
•
i 'N^ V^ i I I
UJ 6W *—* Lu
.1 i
:
" \ s VL, ^V \ i
i i
i-i :l
I 1- 5 0 \ ; LU
o : ]
S40 : D-
: ;\; ; ;30 -
20 i> S V:
1 Nn. ^
10 'G* :> •<> 0 "
200 100 10.0 1.0 0.1 0.01 0 .001 GRAIN SIZE - mm
y. + Z " y. GRAVEL y. SAND y FINES C- 0.0 8.5 68.1 23.4
LL P I ifes D60 D50 D30 Dl5 D10 Cc c,. o 2.37 0.26 0.16 0.091 0.0427 0.0226 1.43 11 .4
MATERIAL DESCRIPTION USCS AASHTO
o Silty sand j SM
i
i Project No.: 90221 :| Remarks: Project: Mottolo Leachability O Location: MTL-ST-TP6-001
Date: August 10, 1990
GRAIN SIZE DISTRIBUTION TEST REPORT
1 GEI CONSULTANTS, INC., WINCHESTER, f-"H "F 1 cIJ.r-e r \ o . ....
BACKHOE ARM
ADAPTOR
SHELBY TUBE . . o - •
.•.•.o-.°-/ 0 I O
DRIVEN DRIVE END (TIP) END (BUTT)
• • • o EXCAVATtQK •
FACE. . . . .O .
Q. s^/.'p/.y.'&.y.'' O
ifl^Mlf: K.J. QUINN &
COMPANY. INC. . ENVIRONMENTAL CONSULTANTS, WC WE SHELBY TUBE
S INDUSTRIAL WAY, SALEU, NH 03079 ATTACHED TO BACKHOE BUCKET
0A1E: BRXBT PROJECTi
MOTTdLO 12 /7 /90 T.E.S. G.M.G. RI/FS SOME FILE NOi APPftOVHk HOUKNOs Ut6]iki Hi "
N.T.S. FS47 J.A.G. C-3 6185/826
PRESSURE GAGE (TYPICAL)
cc PRESSURE REGULATOR < (TYPICAL)
Q LU in CO UJ Q :
CL
O
o
LEACHING MEDIUM
RESERVOIR
BACK PRESSURE
^
AIR/WATER INTERFACE (TYPICAL)
PRECISE CONTROL ONE-WAY
VALVE 14-MLGLASS VIAL
LEACHATE COLLECTION
VESSEL
A iALSA M ° ^ . J QUINN &
COMPANY INC.
^ B S w \ EMV1R0NWENTAL CONSULTANTS, INC
B INOUSTKIAL WAY, SALEK NH 03079
TT^ LEACHING
STUDY APPARATUS
SCHEMATIC
DATE
12/7/90 DRAWN BY
F.R.F. CHECKED
G.M.G. PROJECT
MOTTOLO RI/FS
SCALE HLE N a APPROVED FIGURE N a PROJECT N a
N.T.S. 6185A J.A.G. C-4 6185/826
APPENDIX D
REMEDIAL TECHNOLOGY DESCRIPTIONS
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
NO ACTION Site Security
Monitoring
CONTAINMENT Capping - Single or Multi-Layer Systems
Surficial Stabilization or Sealing
Bottom Seal Grouting
Installation of security measures to inhibit access to site or contaminated areas, e.g., fencing with locking access.
Performance of periodic monitoring of appropriate environmental media, e.g., ground water, surface water, soil, air.
Placement of low permeability cover to limit direct contact with wastes or contaminated soils and to limit precipitation infiltration. Multi-layer systems incorporate drainage layer(s), weathering layer(s), gas migration layer(s), and impermeable layer(s) with grading, re-vegetation, and other runon/runoff controls.
Sealing of surficial sediments using grouts, chemical sealants, or paving techniques (e.g., asphalt or cement) to form a low permeability cover over wastes or contaminated soils.
Construction of a horizontal barrier beneath wastes or contaminated soils using steam and grout injection to limit contact of waste constituents with ground water.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDLy;. TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
Dewatering
IN SITU TREATMENT PHYSICAL/CHEMICAL:
Aeration
Soil Flushing
Vapor or Vacuum Extraction
Lowering the water table beneath contaminated areas by diversion (e.g., slurry wall), interception (e.g., drainage trench), or extraction, thereby reducing physical contact of the ground water with contaminated soils or wastes. Treatment of extracted ground water may be required.
Mechanical mixing of soils with tilling or excavation equipment to promote volatilization of contaminants, or to improve contact of air with contaminated soils to enhance biodegradation processes.
Introduction of solvents that selectively dissolve wastes and recovery of the solvent containing dissolved wastes firom the ground for treatment and disposal. When water is the solvent, selected additives (e.g., acids, bases, surfactants, and chelating agents) may be used to enhance removal of waste constituents.
Removal of contaminants in the vapor phase by vacuum extraction of air or gases present in waste or soil interstices.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
IN SITU TREATMENT Vegetational Uptake (continued)
Reduction of Soil Vapor Pore Volume
Aerobic Biodegradation
Enzymatic Degradation
Augmentation
Uptake and translocation of ionized contaminants fi"om soils to growing plants followed by harvesting and disposal of the plants, generally requiring a number of growth and harvesting cycles.
Controls rate of waste constituent volatilization by reducing air-filled pore space in soils, typically through compaction and addition of water. Generally intended for use in conjunction with other in situ treatment techniques.
Detoxification or decomposition of waste constituents by indigenous microbial populations. May involve adjustment of various soil characteristics (e.g., oxygen content, pH, moisture content).
Degradation of wastes by injection of synthetic purified enzymes into the ground, which decompose or transform waste constituents.
Addition of exogenously grown microorganisms to soils to enhance degradation of waste constituents by native microbial populations.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES
IN SITU TREATMENT (continued)
Neutralization
Oxidation
Reduction
Hydrolysis
In Situ Heating
SUMMARY DESCRIPTION
Treatment of wastes by adjustment of corrosive properties through addition of acids or bases to alter pH.
Addition of oxidizing agents (e.g., hydrogen peroxide, ozone, hypochlorite) to the ground to degrade waste constituents.
Addition of reducing agents (e.g., sodium borohydride and catalyzed metal powders) to the ground to immobilize or degrade waste constituents.
Degradation of waste constituents typically by displacement of functional groups by water or hydroxyl ion. Preference is for base-catalyzed hydroloysis because acid catalysis can result in mobilization of trace metals.
Destruction or mobilization of contaminants (typically, volatile organic compounds) through thermal decomposition, vaporization, or distillation using heat generated by steam injection or radio wave excitation of conductors placed on or in the ground. Temperatures range from 200 to 400 °F.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
IN SITU TREATMENT Dehalogenation (continued)
Addition of Proton Donors
Attenuation
IMMOBILIZATION:
Soil Cooling
Artificial Ground Freezing
Detoxification of wastes by chemical treatment with reagents, such as alkali metals and polyethylene glycols, that remove halogens (e.g., chlorine, bromine). Dechlorination of PCBs is an example.
Enhancement of photodegradation of soil contaminants by addition of proton donor materials to the soil.
Mixing of contaminated soil or wastes with clean soil to reduce concentrations of hazardous constituents to acceptable levels.
Reduction of volatilization by cooling of surface soils by application of solid or liquid carbon dioxide, liquid nitrogen, or ice.
Stabilization of wastes by freezing the ground using a refrigeration system circulating coolant through coils installed in the ground.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATE(X)RY
IN SITU TREATMENT (continued)
REMEDIAL TECHNOLOGIES
Vitrification
Thermoset Fixatives and Polymerization
Cement and Silicate Based Fixatives and Grouting
Thermoplastic Fixation
Surface Macro-encapsulation
SUMMARY DESCRIPTION
Transformation of wastes into a molten glass or crystalline form by passing electric current through electrodes installed in the ground to obtain temperatures above 2,400 to 2,900 "F.
Mixing of wastes with organic fixatives followed by heating to form a solid mass, which is then containerized.
Fixation of wastes by formation of hydration products of the wastes in the interstices of silicate matrices. Fixatives include such materials as Portland cement and lime.
Mixing of wastes with heated organic fixatives (e.g., asphalt, paraffin, polyethylene, polypropylene) and cooling of the product in containers. Containerization is necessary because thermoplastic materials can re-liquify if heated.
Sealing stabilized or microencapsulated wastes (i.e., monolithic mass) with an organic coating (e.g., polyethylene, vinyl).
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDML TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
REMOVAL Excavation/Dredging
ON-SITE STORAGE Waste Pile
Storage Vault
Storage Bins
Storage Bags
Tank/Drum Storage
Physical removal of contaminated wastes,soils or sediments using various types of excavating or dredging equipment, such a:s backhoes, bulldozers, draglines, etc.
Storage of waste piles on a structurally sound base covered with an impermeable liner. Runon/runofF controls, protection fi*om wind dispersion, ultraviolet light and precipitation and a ventilation and leachate collection system are generally provided.
Storage of waste in reinforced concrete vaults with an impermeable flexible cover or fixed roof and possibly a liner and leachate collection system.
Storage of wastes in roll off containers which may be lined with impermeable liners.
Storage of wastes in thick polyethylene bags.
Storage of wastes in tanks or drums placed on a diked platform, which may be covered with an impermeable liner and cover structure.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY
ON-SITE TREATMENT
REMEDIAL TECHNOLOGIES
PHYSICAL/CHEMICAL:
Classification
Screens and Sieves
Classifiers
Filtration
Granular Filtration/ Drying Beds
Vacuum Filtration
Pressure Filtration
SUMMARY DESCRIPTION
Separation of different sized particles by filtration through screens or sieves of appropriate mesh sizes.
Separation of particles from liquid streams using sedimentation tanks, cyclones, or spiral classifiers.
Physical separation of solids from liquids by passage through porous media (e.g., anthracite coal or sand) in a contained unit or open bed.
Physical separation of solids from liquids in which liquids are drawn under vacuum through permeable material that retains the solids.
Physical separation of solids from liquids in which the liquids are forced under pressure through permeable material that retains the solids.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE TREATMENT Carbon Adsorption (continued)
Evaporation
Low Temperature Thermal Stripping
Vapor or Vacuum Extraction
Mechanical Aeration
Removal of waste constituents by contact with activated carbon.
Use of heat energy to vaporize volatile waste constituents which have low vapor pressures.
Heating of affected soils to temperatures above 350 °F. with countercurrent air flow to remove volatile organic compounds.
Removal of contaminants in the vapor phase by passive release or vacuum extraction of air or gases present in waste or soil interstices. Involves placement of waste or soil in piles with perforated pipe laid internally and exposed to air or connected to a vacuum system.
Forcing contact of waste constituents with affinities for the vapor phase with ambient air by mechanical mixing to induce volatilization.
December 10, 1990 Balsam Project 6185/824:s4386L
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE TREATMENT Solvent Extraction Mixing of soils or wastes with solvents that selectively (continued) dissolve waste constituents and separation and recovery of
the solvent containing dissolved constituents for treatment and disposal. When water is the solvent, selected additives (e.g., acids, bases, surfactants, and chelating agents) may be used to enhance removal of waste constituents.
Supercritical Extraction Similar to. solvent extraction, but performed at elevated temperatures and pressures to facilitate separation of solvent from soil.
Addition of Agricultural Mechanical mixing of wastes with agricultural materials Products and By (e.g., animal manure, straw, sawdust, peanut hulls) to products absorb waste constituents.
Anaerobic Digestion Bacterial digestion and stabilization of wastes in an atmosphere void of oxygen.
Composting Degradation of wastes by mixing with large quantities of organic matter which decomposes and emits heat thereby promoting aerobic thermophylic digestion of waste constituents by indigenous microorganisms.
December 10, 1990 Balsam Project 6185/824:s4386L 10
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE TREATMENT Landfarming (continued)
Enzymatic Degradation
Neutralization
Oxidation
Reduction
Hydrolysis
Biodegradation of wastes by applying them to the land via spray irrigation with the addition of nutrients, oxygen, acids and bases, heat and acclimated microorganisms or purified enzymes, as appropriate.
Degradation of waste constituents by addition of synthetic purified enzymes, which decompose or transform waste constituents.
Treatment of wastes by adjustment of corrosive properties through addition of acids or bases to alter pH.
Addition of oxidizing agents (e.g., hydrogen peroxide, ozone, hypochlorite) to degrade waste constituents.
Addition of reducing agents (e.g., sodium borohydride and catalyzed metal powders) to degrade waste constituents, typically by lowering oxidation states.
Degradation of waste constituents typically by displacement of functional groups by water or hydroxyl ion. Preference is for base-catalyzed hydroloysis because acid catalysis can result in mobilization of trace metals.
December 10, 1990 Balsam ^Project 6185/824:s4386L 11
REMEDLVL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE TREATMENT Catalytic Oxidation (continued)
Dehalogenation
IMMOBILIZATION:
Chemical Fixation
Cement and Silicate Based Fixatives and Grouting
Thermoplastic Fixation
Detoxification of wastes through oxidation by ozone, hydrogen peroxide, or other oxidant catalyzed by ultraviolet light.
Detoxification of wastes by chemical treatment with reagents, such as alkali metals and polyethylene glycol, that remove halogens (e.g., chlorine, bromine). Dechlorination of PCBs is an example.
Stabilization of wastes by chemical fixation in soil. Fixative agent reacts with waste constituents and chemically binds them to soil.
Fixation of wastes by formation of hydration products of the wastes in the interstices of silicate matrices. Fixatives include such materials as Portland cement and lime.
Mixing of wastes with heated organic fixatives (e.g., asphalt, paraffin, polyethylene, polypropylene) and cooling of the product in containers. Containerization is necessary because thermoplastic materials can re-liquify if heated.
December 10, 1990 Balsam Project 6185/824:s4386L 12
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE TREATMENT (continued)
Thermoset Fixatives and Polymerization
Surface Macro-encapsulation
Absorbents
Vitrification
THERMAL:
Rotary Kiln
Multiple Hearth Incineration
Mixing of wastes with organic fixatives followed by heating to form a solid mass, which is then containerized. Thermoset materials cannot re-liquify if heated.
Sealing stabilized wastes (i.e., monolithic mass) with an organic coating (e.g., asphalt, polyethylene, vinyl).
Improvement of waste handling characteristics by addition of bulking agents (e.g., fly ash, kiln dust, vermiculite) to reduce free water content.
Transformation of wastes into a molten glass or crystalline form by passing electric current through electrodes inserted in the wastes to obtain temperatures above 2,900 °F.
Destruction of wastes in a rotating, cylindrical refractory lined vessel by combustion at temperatures of 1,500 to 3,000 "F.
Destruction of wastes in a refractory lined steel shell with zones of increasingly higher combustion temperatures between 1,400 and 1,800 "F.
December 10, 1990 Balsam Project 6185/824:s4386L 13
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE TREATMENT High Temperature Fluid (continued) Wall
Infrared Incineration
Fluidized Bed
Molten Glass
Molten Salt
Destruction of wastes in a reactor consisting of a porous core surrounded on the outside by carbon electrodes, a heat shield, insulation, and a double wall cooling jacket and surrounded on the inside by an inert gas (fluid wall). Combustion temperatures are between 4,000 and 5,000 °F.
Destruction of wastes by passing them under infrared heating elements in a ceramic insulated furnace (operating temperatures of 500 to 1,850 °F.), sometimes fitted with an afterburner for combustion of gases (operating temperatures of approximately 2,300 °F.).
Destruction of wastes by injection into fluidized bed of inert media (e.g., sand expanded by forced air) and combustion at temperatures of 1,300 to 2,100 "F.
Destruction of wastes by injection onto molten glass and resulting combustion at temperatures of 1,800 to 2,200 °F. Ash is entrained in glass.
Destruction of wastes by contacting with molten salt at temperatures of 1,000 to 1,200 °F. in an insulated reactor. Ash is incorporated in molten salt bath.
December 10, 1990 Balsam Project 6185/824:s4386L 14
REMEDL\L TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE TREATMENT PjTolysis (continued)
Advanced Electric Reactor
Plasma Arc
Circulating Bed Combustor
Supercritical Water Oxidation
Thermal conversion of organic waste constituents into solid, liquid, and gaseous compounds in an oxygen-deficient environment at temperatures of 900 to 1,600 "F. and subsequent incineration of volatile (gaseous) pyrolysis products at 1,800 to 3,000 °F. in a second stage fume incinerator.
Destruction of finely divided wastes by pyrolysis at approximately 4,000 °F. in an electrically heated fluid wall reactor.
Destruction of wastes through pyrolysis by contact with ultraviolet radiation emitted by decaying gas plasma at approximately 10,000 °F.
Similar to fluidized bed except high turbulence within unit provides greater destruction efficiency with more compact unit. Operating temperatures up to 1,500 to 1,600 °F.
Destruction of aqueous wastes by mixing with compressed air and heating to temperatures above 740 °F. at pressures of 3,200 to 3,600 psi. At these conditions, contaminants insoluble in water become soluble and vice versa, resulting in precipitation of inorganic materials and dissolution and destruction of organic materials.
December 10, 1990 Balsam Project 6185/824:s4386L 15
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
ON-SITE DISPOSAL
OFF-SITE TREATMENT
RCRA Landfill
PHYSICAL/CHEMICAL:
RCRA Hazardous Waste Treatment/Storage/ Disposal Facility
Dehalogenation
THERMAL:
Wet Air Oxidation
Placement of wastes in a contained cell or fill area designed in accordance with RCRA 40 CFR 264 regulations for landfill design.
Repackaging and treatment or disposal of wastes at off-site permitted hazardous waste facilities.
Detoxification of wastes by chemical treatment with reagents, such as sodium metal or polyethylene glycols, that remove halogens (e.g., chlorine, bromine). Dechlorination of PCBs is an example.
Mixing of aqueous wastes with compressed air and heating them to temperatures of 350 to 650 °F. at pressures of 300 to 3,000 psi to enhance degradation via oxidation.
December 10, 1990 Balsam Project 6185/824:s4386L 16
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
OFF-SITE TREATMENT (continued)
Supercritical Water Oxidation
Rotary Kiln
Cement, Lime and Aggregate Kiln Coincineration
Multiple Hearth Incineration
High Temperature Fluid Wall
Destruction of aqueous wastes by mixing with compressed air and heating to temperatures above 740 °F. at pressures of 3,200 to 3,600 psi. At these conditions, contaminants insoluble in water become soluble and vice versa, resulting in precipitation of inorganic materials and dissolution and destruction of organic materials.
Destruction of wastes in a rotating, cylindrical refractory lined vessel by combustion at temperatures of 1,500 to 3,000 °F.
Destruction of wastes in kilns by countercurrent injection to material feed as an auxiliary fuel. Combustion is typically at temperatures of 2,500 to 2,900 °F.
Destruction of wastes in a refractory lined steel shell with zones of increasingly higher combustion temperatures between 600 and 1,000 " F.
Destruction of wastes in a reactor consisting of a porous core surrounded on the outside by carbon electrodes, a heat shield, insulation, and a double wall cooling jacket and surrounded on the inside by an inert gas (fluid wall). Combustion temperatures are between 4,000 and 5,000 °F.
December 10, 1990 Balsam Project 6185/824:s4386L 17
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
OFF-SITE TREATMENT Infrared Incineration (continued)
Fluidized Bed
Molten Glass
Molten Salt
Pyrolysis
Destruction of wastes by passing them under infrared heating elements in a ceramic insulated fumace, sometimes fitted with an afterburner for combustion of gases.
Destruction of wastes by injection into fluidized bed of inert media (e.g., sand expanded by forced air) and combustion at temperatures of 1,300 to 2,100 °F.
Destruction of wastes by injection onto molten glass and resulting combustion at temperatures of 1,800 to 2,200 "F. Ash is entrained in glass.
Destruction of wastes by contacting with molten salt at temperatures of 1,000 to 1,200 "F. in an insulated reactor. Ash is incorporated in molten salt bath.
Thermal conversion of organic waste constituents into solid, liquid, and gaseous compounds in an oxygen-deficient environment at temperatures of 900 to 1,600 °F. and subsequent incineration of volatile (gaseous) pyrolysis products at 1,800 to 3,000 °F. in a second stage fume incinerator.
December 10, 1990 Balsam Project 6185/824:s4386L 18
REMEDIAL TECHNOLOGY LIST FOR SOURCE CONTROL
MOTTOLO SUPERFUND SITE
RESPONSE CATEGORY REMEDIAL TECHNOLOGIES SUMMARY DESCRIPTION
OFF-SITE TREATMENT (continued)
OFF-SITE DISPOSAL
Advanced Electric Reactor
Plasma Arc
Circulating Bed Combustor
RCRA Landfill
Resource Recovery Facility
Asphalt Batch Plant
Destruction of finely divided wastes by pyrolysis at approximately 4,000 "F. in an electrically heated fluid wall reactor.
Destruction of wastes through pjrrolysis by contact with ultraviolet radiation emitted by decaying gas plasma at approximately 10,000 °F.
Similar to fluidized bed except high turbulence within unit provides greater destruction efficiency with more compact unit.
Transport of wastes off-site to a RCRA-permitted landfill.
Processing of wastes at an off-site facility to extract reusable materials.
Destruction, fixation, or stabilization of wastes in asphalt matrix by incorporation of wastes or contaminated soil in asphalt batching process.
December 10, 1990 Balsam Project 6185/824:s4386L 19
APPENDKE
EVALUATION OF GROUND WATER CLEANUP TIMES
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
A P P E N D K E
EVALUATION OF GROUND WATER CLEANUP TIMES MOTTOLO SUPERFUND SITE RAYMOND, NEW HAMPSHIRE
1.0 SOIL CONDITIONS
During the Remedial Investigation (RI), efforts to identify and characterize the
sources of volatile organic compounds (VOCs) at the Mottolo site included a review
of historical data, a soil gas and shallow ground water headspace screening survey,
advancement and sampling of soil borings, field screening of surface and
subsurface soils, and laboratory analyses of boring soil samples. Information
obtained from these activities indicates that soils heavily impacted by VOCs
released as a result of activities in the former disposal area are limited to a
relatively small area. In this area, and coincidental with the location of borings
BE-3, BE-4 and BE-9 (see Figure E-1), levels of total VOCs in the heavily impacted
unsaturated and saturated soils appear to be on the order of tens to hundreds of
thousands of parts per billion (ppb) on a weight basis, based upon consideration of
laboratory analytical, soil gas, and soil screening data. These findings are
consistent with the RI report, which concluded that the former disposal area
contained areas of very localized and highly contaminated soils due to the nature
of non-catastrophic releases from some of the drums bimed in the area. As
evidenced by other data, such as a soil sample from boring BE-2 (see Figure E-1),
also advanced within the former disposal area, some soils within the area have'
lower levels of total VOCs ranging between hundreds and thousands of ppb. Such
data further support conclusions regarding the dispersed, and thus limited, areal
extent of soils that have been directly and heavily impacted by VOC releases.
At locations toward the edges of this heavily impacted area, and coincidental with
the location of borings BE-10, BE-13 and BE-14, soil gas, field screening, and
December 10, 1990 Balsam Project 6185/824:S4368V E-1
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
laboratory analytical data indicate that VOC levels in soils are significantly lower,
on the order of tens to hiindreds of ppb. Laboratory soil analytical data showed
some variability, although detected levels were within this total VOC
concentration range, which could be expected due to soils heterogeneity and
variable soils organic carbon content. These soil VOC levels correlated with field
headspace analysis of samples collected from these same borings showed total VOC
sample headspace levels of hundreds of parts per million (ppm) on a volume basis.
The hydrogeologic flow regime described in the RI report, as well as site ground
water quality data indicate adyective transport of high levels (i.e., scores of
thousands of ppb) VOCs through these soils by grotmd water. Thus, although
impacted by elevated levels of VOCs in ground water, the soils adjacent to and
downgradient of the former disposal area appear to be only minimally impacted by
the VOCs with total VOC concentration in the tens and hundreds of ppb. As
discussed in Appendix C, the leaching study report, soils data collected during that
program are also consistent with this conclusion in that the total VOC levels
detected in soil samples from test pits excavated in close proximity to but
downgradient of the former disposal area ranged from low ppb to scores of ppb.
Farther downgradient from the former disposal area soiirce soils, available data
indicate that VOC levels in soils are on the order of tens of ppb. Headspace
analysis of samples from boring BE-15 showed total VOC concentrations of
approximately 300 ppm in headspace, whereas laboratory analytical data for a
saturated soil sample from this same boring was reported to contain less than
40 ppb total VOCs. Farther still downgradient from the former disposal area, at
well 0W-2SR, headspace analyses of soil samples from the well boring were in the
range of 10 to 50 ppm, significantly less than the headspace levels observed in
samples from boring BE-15 located approximately 30 feet upgradient. In
accordance with this apparent trend of decreasing soil and headspace VOC
concentrations as well as soil gas survey data, it is expected that levels of VOCs in
soil in the Brook A valley are on the order of 10 ppb or less.
December 10, 1990 Balsam Project 6185/824:S4368V E-2
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
As stated above, laboratory analyses and field screening of soil samples collected
during the soil leaching study described in Appendix C yielded results consistent
with the general trend of VOC distribution previously discussed. As discussed in
Section 4.2 of Appendix C, sample TP-3 was collected from a location immediately
downgradient of the former disposal area source and in the general vicinity of
boring BE-10. The level of total VOCs detected in this sample was consistent with
the levels detected in soil samples from boring BE-10 and other borings advanced
on the periphery of the source area. Sample TP-3 was collected from a location
selected based upon data from prior investigation activities to be representative of
more heavily impacted non-source area soils. Accordingly, results for this sample
are expected to be representative of the higher end of the range of residual VOC
levels in downgradient non-source area soils, i.e., soils which were not directly
impacted by VOC release but rather by ground water containing dissolved VOCs.
Soils from areas farther downgradient of the former disposal area are expected to
contain lower levels of VOCs than those observed in sample TP-3 and samples
from borings similarly located in the immediate vicinity of the source area soils.
This assessment is consistent with the fact that VOCs were not detected in soil
samples collected from test pits TP-2 and TP-6, which were located farther
downgradient from the source area and more toward the edge of the grotmd water
plume than test pit TP-3.
In the southem boundary area, the area of VOC-affected soils appears very limited
in nature. Both soil gas sampling and field screening of soil samples collected
from aroimd a concrete pad previously used for waste material drum storage did
not indicate the presence of VOCs in soils above trace levels. Furthermore, ground
water quality data from wells MW-8S, MW-21S and MW-20S show the extent of
VOCs in overburden ground water emanating from this source to be limited to an
area in close proximity to and downgradient of the concrete pad. Based on these
and other data, the RI report concluded that the area of VOC-affected soils was
December 10, 1990 Balsam Project 6185/824:S4368V E-3
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
highly localized and most probably existing beneath or immediately adjacent to the
concrete slab.
The remedial altematives proposed for the Mottolo site are designed to isolate or
treat heavily impacted source area soils, in effect eliminating releases from those
soils. The soil treatment altematives considered for the site are expected to
remove 99 percent or more of the VOCs present. Treatment to this level will
reduce the levels of VOCs present in the heavily impacted portion of the source
area from on the order of thousands of ppb to the order of tens of ppb, with
concomitant reductions in soil VOC levels in downgradient areas as releases of
VOCs from the source area decline. These predicted post-remedial total VOC soil
concentrations are well below the soil target clean up levels (TCLs) presented in
Section 2.0 of the feasibility study (FS) report. Accordingly, after source isolation
or treatment, levels of VOCs in saturated soils in the zone between the
downgradient edge of the source area and the top of the valley wall near well
0W-2SR (Zone A) should be similar to or lower than the levels observed in the soil
samples from test pit TP-3 and boring BE-15, approximately 10 to 100 ppb,
assuming no treatment or containment of these soils. After remediation, saturated
soil VOC concentrations in the vicinity of well 0W-2SR and the zone between the
top and bottom of the valley wall (Zone B) should be on the order of 10 ppb, if they
are not already in this range. Soil concentrations in the Brook A valley in the
zone between the base ofthe valley wall and the brook (Zone C) are expected to be
on the order of less than 10 ppb.
Unlike the former disposal area, little overburden VOC ground water
contamination is associated with the southem boundary area. As such, the levels
of VOCs expected to exist in southem boundary area soils that are not contained
or treated as part of the site remedial program should range from below detectable
levels to up to 10 ppb.
December 10, 1990 Balsam Project 6185/824:S4368V E-4
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
2.0 ATTAINMENT OF GROUND WATER TARGET CLEANUP LEVELS
As discussed in Section 2 of the Feasibility Study Report, TCE and vinyl chloride
were selected as the principal constituents of concem for ground water
downgradient of the former disposal area because they are relatively more difficult
to treat as compared to other VOCs on site and the TCLs for these two
constituents are significantly lower than those for the other indicator compounds.
Similarly, TCE was selected as the constituent of concem for ground water
downgradient of the southem boundary area. The results of the leaching study
discussed in Appendix C of the FS indicated that the leaching behavior of the
other seven indicator constituents from overburden was consistent with that of
TCE and vinyl chloride, and that attainment of TCE and vinyl chloride ground
water TCLs should result in attaining other ground water TCLs. Accordingly, the
discussion of attainment of ground water TCLs focused on TCE and vinyl chloride.
Based upon the results of the leaching study, in the area of test pit TP-3 located
immediately downgradient of the source area, exchange of approximately 1 to
5 pore volumes of ground water will result in levels of TCE and vinyl chloride, the
identified constituents of concern, that are below the ground water TCLs once the
concentrated source area soils have been remediated. Due to the low total VOC
levels observed in soils samples collected from leachability study test pits and
boring BE-15, it is believed that pore water exchange was the principal mechanism
responsible for VOC reduction observed during the study. In practical terms, it is
estimated that 2 to 3 pore volumes would have to be exchanged to fiilly flush a
given volume of pore water from the soil matrix, and with it, dissolved VOCs
present in the pore water. Accordingly, it is assumed that 3 to 5 pore water
volume exchanges will result in TCE and vinyl chloride concentrations below the
TCLs in Zone A. Following remediation, VOC levels in saturated soils in Zone B
should be less than levels currently present in the vicinity of test pit TP-3.
Accordingly, it is assumed that a similar exchange of 3 to 5 pore volumes of water
December 10, 1990 Balsam Project 6185/824:S4368V E-5
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
will result in TCE and vinyl chloride levels below TCLs in ground water in this
zone. Because levels of VOCs in soils in Zone C are expected to be considerably
less than those in Zones A and B, it is assumed that removal of VOCs from these
soils will involve primarily flushing of VOCs in pore water, an estimated exchange
of 2 to 3 pore volumes.
In the southem boundary, data obtained during the RI indicate that VOCs
released from overbin-den soil enter bedrock ground water directly and do not
migrate significantly in overburden ground water. After remediation of soil in this
area, it is anticipated that VOCs currently present in bedrock ground water in this
area will be flushed by ground water flowing through this zone. VOC sorption in
bedrock systems is typically much less than that in overburden because of the lack
of organic carbon, reactive materials, and fine-grained sediments. Evidence of
these materials was not observed in site bedrock during the RI bedrock well
installation program. Accordingly, because the leaching study results indicate that
levels of TCE in overburden ground water will decline to below the TCL within
3 to 5 pore water volume exchanges after remediation, it is expected that fewer
pore volume exchanges in bedrock will result in TCE levels below the TCL. It is,
therefore, assumed that exchange of 2 to 3 pore volumes in bedrock in the
southem boundary area will result in acceptable levels of TCE.
3.0 ESTIMATED CLEANUP TIMES
Hydrogeologic data obtained during the RI were used together with the estimated
number of pore water volume exchanges to estimate the time within which ground
water concentrations of TCE and vinyl chloride will attain TCLs after source area
soils containment or treatment. Because ground water flows at different rates in
the three previously identified zones downgradient from the former disposal area,
individual cleanup times were estimated for the three zones. Overburden ground
water flow rates for Zones A, B and C downgradient of the former disposal area
December 10, 1990 Balsam Project 6185/824:S4368V E-6
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
were described in Section 3.0 ofthe RI and are summarized in Table E-1. The
number of pore volume exchanges per year to each zone was estimated by dividing
the flow rate by the length of the zone in the direction of ground water flow. This
factor was then divided into the estimated number of pore volume exchanges
resulting in attainment of TCLs to obtain the estimated cleanup time for the zone.
The estimated cleanup times and data used in the estimation are summarized in
Table E-1.
For the southem boundary area, the average bedrock hydraulic conductivity for
the site (4.6x10"^ cm/sec) was used in conjunction with a range of values for
near-smface bedrock porosity used in the RI of 0.005 to 0.10 and a gradient of 0.01
estimated from potentiometric data for bedrock wells in the southem boundary
area to estimate a groimd water flow rate of from 480 to 9,500 feet per year. This
range of flow rates was divided by the distance to the expected discharge zone for
shallow bedrock ground water from this area,~the Brook A headwaters, to estimate
the number of pore volumes exchanged in one year. This factor was then used in
conjiuiction with the estimated number of pore volume exchanges resulting in TCE
levels at or below TCLs to estimate a cleanup time (see Table E-1).
The results of these analyses indicate that the area located downgradient of the
former disposal area between the base of the Brook A valley wall and Brook A
(Zone C), the discharge point for overburden and shallow bedrock ground water
flowing beneath the former disposal area will achieve groimd water TCLs from 0.5
to 6.0 years after source area remediation, with a calculated average expected time
of 1.1 years. In Zone B, the western Brook A valley wall, the analysis indicated
ground water TCLs would be achieved in 0.3 to 2.2 years after source area
remediation, with a calculated average expected time of 0.6 years. In Zone A,
located between the former disposal area and the crest of the western Brook A
December 10, 1990 Balsam Project 6185/824:S4368V E-7
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
valley wall, the analysis indicated that ground water target cleanup levels would
be achieve in 0.5 to 5.0 years, with a calculated average expected time of 1.1 years.
In the southem boundary area, it is estimated that approximately 0.1 to 1.9 years
will be required to attain the TCL for TCE.
December 10, 1990 Balsam Project 6185/824:S4368V E-8
TABLE E-1
SUMMARY OF GROUND WATER FLOW RATES . AND ESTIMATED CLEANUP TIMES
ESTIMATED CLEANUI
(yr)
0.5 - 5.0
(Ll)
0.3 - 2.2
(0.6)
0.5 - 6.0
(Ll)
0.1 - 1.9
(0.1)
Page 1 of 1
ZONE
Zone A (overburden)
Zone B (overburden)
Zone C (overburden)
Southem Boundary Area (bedrock)
NOTES: 1) 2)
- 3)
FLOW RATES (ftyyr)
70 - 440
(260)
170 - 840
(500)
30 - 220
(130)
480 - 9,500
(5,000)
ft == feet yr = year Values in parentheses
DISTANCE (ft)
70
70
75
75
60
60
300
300
are averages.
PORE VOLUMESPER YEAR
1.0 - 6.3
(3.7)
2.3 - 11
(6.7)
0.5 - 3.7
(2.2)
1.6 - 32
(17)
REQUIREDPORE VOLUMES
3 - 5
(4)
3 - 5
(4)
2 - 3
(2.5)
2 - 3
(2.5)
December 10, 1990 Balsam Project 6185/824:S4368V
APPENDIX F
GROUND WATER COLLECTION TRENCH AND EXTRACTION WELL POINT
SYSTEM FLOW RATE ESTIMATES
APPENDIX F
GROUND WATER COLLECTION TRENCH AND EXTRACTION WELL POINT
SYSTEM FLOW RATE ESTIMATES
1.0 INTRODUCTION
Recovery of overburden ground water at this site is limited by the low
transmissivities exhibited by the overburden deposits. To effect overburden
ground water recovery in the three zones downgradient of the former disposal
area, a ground water collection trench was selected for the Brook A valley wall
area. Because of the low overburden transmissivity in Zone C, the extent of •
influence of the trench was not expected to extend to the west much beyond the
base of the Brook A valley wall. To effect capture of overburden ground water,
along the valley wall, a system of extraction wells was proposed because of the
impracticability of trench construction due to slopes and surface soil material. The
proposed system included four wells in the upland area in the vicinity of well
0W-2SR and eight wells at the base of the valley wall. The analyses used to
estimate overburden ground water flow rates from the collection trench and well
point system are discussed in the sections that follow.
December 10, 1990 Balsam Project 6185:824/S4368p
2.0 GROUND WATER COLLECTION TRENCH FLOW RATE ESTIMATES
Two methods were used to estimate ground water flow into the downgradient
collection trench adjacent to Brook A. In each method, it was assumed that the
hydraulic head within the trench was to be maintained approximately 2 feet above
the base of the trench and that the bottom of the trench was located approximately
2 feet above the overburden-bedrock interface. A second assumption was that
ground water inflow from the east side of the trench was minimized due to the
placement of an impermeable barrier along this side. This assumption could result
in significantly underestimating flow into the trench and would be further
evaluated as an element of remedial design. Ground water inflow due to bedrock
discharge was also not considered at this level of design.
The first method is illustrated in Figure F-1. Flow from one side ofthe trench was
estimated as:
a = Kdf - h ) X 2L
where H = 10 feet, h = 2 feet, X = 100 feet, and K ranged from 0.57 to 1.5 feet per
day based upon the range of hydraulic conductivities observed in Brook A valley
overbiu-den during the RI. Assuming that L ranges from approximately 5 to 25
feet based on the overburden transmissivity values estimated during the RI, the
ground water inflow to the trench from the western side was estimated to range
between 1 and 6 gallons per minute (gpm).
This approach \yas also used assuming that the stress to overburden ground water
occurred for a distance, L, of approximately 300 feet, or between the upland
portion of the site and the trench. This approach was used to provide a range of
estimated ground water inflow volumes since the area affected by the trench in
December 10, 1990 Balsam Project 6185:824/S4368p
terms of a change in the hydraulic gradient was not assessed at this level of
design. In this case, H = 10 feet, h = 2 feet, L = 300 feet and the other parameters
are as described above. Based upon this approach, the ground water inflow into
the western side of the trench was estimated to be less than 1 gpm.
The second method used is based upon the equation (McWhorter and Sunada,
1977):
So = Q((3.14) (a) (t))°' 3.14(T)
where SQ is the drawdown, q is the specific discharge per unit length of trench, T
is transmissivity, t is time, and a is a ratio of transmissivity to specific yield. The
drawdown was assumed to be 8 feet and the specific yield"was assumed to be 0.2.
Assuming the trench to be 100 feet long, T ranging from 4 x 10' . to
1.6 x 10"* ftVsec, and the other parameters as described previously, the
ground water inflow was estiniated for times ranging from 0.5 to 5 days, a range
in time judged to be a reasonable approximation for equilibrium conditions to
occur. Based upon this approach, the inflow into the western side of the trench
was estimated to range between approximately 2 and 17 gpm.
Therefore, based upon the approaches discussed the range of ground water inflow
to the western side of the interceptor trench was estimated to range from 1 to
17 gpm.
December 10, 1990 Balsam Project 6185:824/S4368p
3.0 EXTRACTION WELL POINT SYSTEM
3.1 UPLAND AREA
Assuming a saturated thickness in the vicinity of monitoring well 0W-2SR of
12 feet, the maximum desirable drawdown was estimated to be 6 feet. The
transmissivity in this area was estimated to ramge from 4.2 to 20 ftVday and the
storativity was estimated to be 0,2. Assuming approximately 180 days of
continued operation as a conservative approach to establishing equilibrium
conditions, the estimated pumping rate from a 4-inch diameter extraction well
installed in this upland area was 0.1 to 0.6 gallons per minute using the modified
non-equilibrium well equation:
s = 0.183 Q log 2.25 Tt T r^S
As an example, using T = 20 ftVday and solving for Q:
Q= (sTO 0.183
log L
2.25 Tt i^S ] • •
Q = (1.83m) (1.9 mVdav) flog (2.25) (1.9 mVday) (180 davs)] "' 0.183 L (0.051m)'(0.2) J
Q = 3.1 mVday
Q = 0.6 gallons per minute
iere, s = drawdown (m) S = storativity Q = pumping rate (mVday) T = transmissivity (mVday) t = time (days) r = radius of influence (m)
December 10, 1990 Balsam Project 6185:824/S4368p
The radius of influence of the weU was estimated using the equilibrium well equation:
Q = K (If - h') 1055 log R/r
where, K = 13.7 gpd/ft' based upon satiorated thickness of approximately 12 feet in upland area.
H = 12 feet h = 6 feet Q = 0.6 gallons per day r = 0.167 feet
Solving for the radius of influence, R = 36 ft.
Allowing for the effects of such factors as aquifer heterogeneity, the presence of
low permeability zones, cobbles, boulders, and the effect of decreasing
transmissitivity, it was conservatively assumed that the well radius of influence
would equal approximately 20 feet. On this basis, a net yield of approximately 0.4
to 2.4 gallons per minute was estimated for the four upland wells.
3.2 BASE OF VALLEY WALL
Using the same approach as taken in the upland area, a saturated thickness of
approximately 10 feet was assumed and the desirable drawdown was estimated to
be 6 feet. Based upon RI data, the transmissivity in this area was estimated to
range from approximately 4.2 to 15 ft'/day, the storativity was assumed to be 0.2,
and the hydraulic conductivity was assumed to be 10 gal/day/ft'. Using the
remaining variables as defined for the upland area, the estimated pumping rate at
equilibrium was 0.1 to 0.4 gallons per minute with a corresponding radius of
influence of approximately 10 feet. On this basis, a net. yield of approximately
0.8 to 3.2 gallons per minute was estimated for these eight wells.
December 10, 1990 Balsam Project 6185:824/S4368p
3.3 TIME TO EQUILIBRIUM CONDITIONS
Using the non-equilibrium well equation previously discusised, drawdown estimates
were made as a function of time for the extraction wells in both areas. Results
indicated that significant changes in drawdown did not occur and that equilibrium
was approached for wells in both areas after approximately 60 to 90 days.
Therefore, this is the anticipated time period for which the well system would be
cycled on and off. Actual effective cycle times would be further analyzed during
remedial design and refined by field testing following system installation.
Individual air pressure controls would also be installed on each well point so that
regulation of the suction applied to each well could be adjusted independently of
other wells in the two systems.
December 10, 1990 Balsam Project 6185:824/S4368p
BROOK A
. ^ _ = STATIC POTENTIOMETRIC SURFACE
CLEKT
K.J. QUINN & COMPANY, INC.
- ^
n
=
=
POTENTIOMETRIC SURFACE
IMPERMEABLE BARRIER
BEDROCK
DURING TRENCH OPERATION , ENMRONUEHTAL CONSULTANTS, INC
9 BeUSTRAL WAY, SAtEU. m 03070
DATE
9/25/90 DRAWI BY
E.S.W,
CHECKED
G.M.G.
INTERCEPTOR TRENCH GROUND WATER INFLOW
ESTIMATE PROJECT
MOTTOLO SITE RI/FS
NONE FS46 JAG F-1 6185/824
APPENDIX G EVALUATION OF SOUTHERN BOUNDARY
AREA EXTRACTION WELL SYSTEM
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
APPENDIX G EVALUATION OF SOUTHERN BOUNDARY
AREA EXTRACTION WELL SYSTEM
A modified non-equilibrium well equation was used to estimate the available yield
of a typical 8-inch diameter (r„=4 inches) ground water well placed in the southem
boundary area. This yield was then used as input to a steady-state well equation
to estimate the radius of influence ofthe tj^pical well. In addition, the radius
influence was estimated by two empirical equations as a check of the analytical
method. The estimated radius of influence was then used to select well locations
to capture the plume as defined by a 5 ppb action level contour.
The available yield, Q, was estimated using the equation:
s = 0.183Q X log 2.25 Tt T r^S
J
where: T = transmissivity of the formation, square meters per second (mVs)
t = time, seconds r = distance from center of well to point where drawdown is
measured s = drawdown at radius (r), meters S = storativity
Assuming a well depth of 50 feet (15 m), and operating space in the well for a
pump, the maximum desirable drawdown, s, in a t3rpical recovery well would be
approximately 67 percent of 14 m, or 9.4 m. The average hydraulic conductivity,
K, of wells MW-20D and MW-21D was determined to be 2.2 x 10" m/s, which when
multiplied by an assumed saturated thickness, D, of 15 m, 3rields a transmissivity
value of 3.4 x 10" mVs. The storativity, S, was assumed to be 0.005. Using these
values in conjunction with an assumed reasonably long time of pumping of 180
days, Q was determined to be approximately 20 m^/day (3.6 gpm).
December 10, 1990 Balsam Project 6185/824:S4368r G-1
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
Q was then used in the steady-state equation:
Q = 3.14159K [D^ - (D-S.,)^ In (R/rJ.
where: S^ = drawdown in the well, m
r^ = radius of the well, m
Rj = radius of influence, m
to estimate the radius of influence, R . The previously described input parameters
resulted in an estimate of Rj equal to approximately 36 m.
The assumptions associated with the development of both these equations are:
0 the aquifer is infinite in areal extent; 0 the aquifer is homogeneous, isotropic, and of uniform thickness over
the area influenced by pumping; 0 the aquifer is pumped at a constant rate; 0 the pumped well penetrates the entire aquifer and thus receives
water from the entire thickness of the aquifer by horizontal flow; 0 leakage and recharge do not exist; 0 flow within the radius of influence is laminar; 6 the pumping well is 100 percent efficient; 0 water is instantaneously released from storage; and 0 the potentiometric surface has no slope before pumping.
Two empirical equations, developed by Siechardt and Kusakin, were used to check
Rj as estimated by the analytical method. These equations were:
Siechardt: Rj = 3,000 S„K^ and
Kusakin: R; = 575 S^T*'',
Where the variables are the same as previously described. The range of
estimations by these equations were 30 m to 40 m, which were in the range
calculated by the analjrtical method.
December 10, 1990 Balsam Project 6185/824:S4368r G-2
BALSAM ENVIRONMENTAL CONSULTANTS, INC.
Based on the estimated Rj and 5 ppb action level plume, two ground water
recovery wells may be required in the southem boundary area. The exact
placement of these wells would determine the amount of interference between the
wells; accordingly, the total ground water recovery rate was estimated to be
between 4 and 8 gpm.
December 10, 1990 Balsam Project 6185/824:S4368r G-3