Date post: | 07-Jul-2018 |
Category: |
Documents |
Upload: | richard-nartey |
View: | 219 times |
Download: | 0 times |
of 20
8/18/2019 Feasibilty Report of Accra Sports Stadium
1/20
FtrA.SIBILITV
RtrPORT/ASSESSMENT
OF'
TI{E
ACCRA
SPORTS
STADIUM
CONSUI-TANTS:
Ar"chitectural
& Enginee
ng
Services
Ljmited,
Post
Office
Box
3969,
Accra -
Ghana
FEBRAARY,2O]4.
8/18/2019 Feasibilty Report of Accra Sports Stadium
2/20
Inspection
report
-Assessment,
Corrosion
Control
and
Treatment
to
Accra
Sports
Stadium
Facility
Background
During
the
period
of
July
to
September
2013,
AESL
carried
out
a
number
of
scheduled
inspections
on
the
structural
steel members,
as
well
as
the
concrete
framing
elements
(portion)
of
tie
Acera
Sports
Stadium
facihtg.
AESL
has
already
submitted
a
number
of inspection
reports
on t}Ie
corrosion
issue
of
tie
structural
steel
component
to
the
Ministr),
of
youth
and
Sports,
since
the
rehabilitation
works
in
2oo7.
In
the
last
irvitation
extended,
AESL
was
general
condition
of
the
facilitv
as
repair/replacement
cost.
asked
to provide
an
asses-innent
on
the
well
as
the
associated
estimated
AESL,
as
such was primarily
responsible
for
reviewing
the
condition
of
tie
va
ous
structurar
systems
supporting
the
different
seating
sections
of trre
stadium,
tl.e
current
condition
of the
primer/factory
steel
coating
system
on
the
facility,
since
erection
of members,
the
mechanical,
electrical,
plumbing,
as
well
as
the
fire
protection
systems.
The last
inspection
was
conducted
oD tie
31st
ofAugust,
2012.
In
carrying out
this
review
exercise,
information
was
gathered
by
condocting
visual
inspection,
reviewing
previous
studies
and
interviewing
stadium
operations
personnel.
In
addition
to t}Ie
review
of the coating
condition
throughout
the
stadium
bowl,
AESL perforrned
limited
in-depth
studies
of distressed
coating
areas.
These
studies
were
used
to
gain
a
better
assessment
ofthe particular
obsewed
condition.
It
must
be
emphasised
here that.
choosing
reinforced
concrete
as
a
construction
mate
al
would
have
perfor[red
better
as
compared
to
the
structural
steel
ooted
for
in
the
design
in view
ofthe
proximity
of
tie
facility
to the
sea.
The
stadium
is
situated
in
an
cnvironment
of
high
humidit"v
and
winds
laden
rvith
saits
which
are
congenial
to corrosion
ofthe
structural
steel
elements.
It
has
been
revealed
that
t}1e structrllal
steel
elements
were
not
given
another
anti_
rusL
coating
or
finish
after
assemblage,
hel,lce
the
pro{use
couosion
especially
at boll
heads
and
the
areas
facing
the
sea.
8/18/2019 Feasibilty Report of Accra Sports Stadium
3/20
The
service
life
of the present
factoq.
priminlcoating
is
essentially
exhausted
on
tie
obseryed
structural
steel
membereof
the
souttr
stand-
The
main
sb:uctural
steel
framing
members,
which support
pre_cast
slab
units
in
the
popular
stands
have
also
ileveloped
rusts-
Our
findings
from
the
recent
assessment,
revealed
that
most
of
tie
concems
raised
in
the previous
submitted
reports
are
yet
to
be
addressed,
with
the
exception
of tie
anti-rust
ziqc
coating which
had
been
applied
to
the
support
of
the
flood
light
sy.stem.
The
Lrspection
showed
si$s
ofad\.anced
corrosion
since
the
last
visit.
In
t}le
VIp
area,
the
rustine
had rc-e,lted
in
the
formatioo
ofpits,
and
perforations
ia
he
claddings]stem.
Throughout
tie
whole
stadium,
widespread
rustiug
could
be
seen
in
members
Obsewing
the
steel
roof
trusses
liom
the
seating
arena
also
reveals
corrosion-
The
observed
corrosiol
had
led
to
loss
of material
ftom
the
steel
surface
leading
to
thinaer
sections,
and
6e
accumulation
ofrust.
sand/grit
blasting
such
members
may
further
reduce
the
section
thickness
of
ttre
structuial
steel
members,
as
such
they
must
be
replaced,
As
a
result
of such
coEosion,
irmediate
action
should
be
taken
to
rectiE/
the
situation
so
as
to
prevent
loss
ofsections
in
steel
membels,
Aside
the
issue
of
conosion,
cracks
had
developed
in
the
concrete
framing
members
in
the
lower
portions
of
the
stands
supporting
the pump
and
machlne
root.
The physical
condition
of the
stadium
varies
since
concrcte
elements
(precast
concrete
seating
anil
the
Reinforced
Concrete
Ma),grh
statd)
are
generally
in good
condition.
AESL
recommends
the
development
ofa
program
to
repair
the
structure
and
reinstate
tJre
comptomised,
corroded
steel
members-
8/18/2019 Feasibilty Report of Accra Sports Stadium
4/20
Recommended
remedial procedures.
1)
Re-construat
the
current
existing
steel
structure
supporting
the
score-board
with
a
Reinforceil
coucrete
frame
structure.
2)
Provide
treatment
to corroded
struch{al
steel
b}
a)
Power
washing
all
structural
steel framing
members,
to remove
soluble
saltslchlorides
and
builil
up
dirt
lrom
surface
of
existing
shop
primer
coating-
b)
Abrasive
Blast
clean
surface
of
steel
anil
apply three-coat
paint
slstem
witlr
the
following
layering
sequence;
primer
-
in
organic zinc
rich
primer
urdelcoat
(1.t
coat)
-
high
build
zinc
rich
paint
undercoat (2 d
coat)
-high
build
epoxy
undercoat (3rd
coat) high
build
epory
Ilrtermediate
coat
-
pol]rur:ethaue
Finish
coat
poly
ure&ane
Total
coating
thicloess
(Fm)
=
255
N.B.
The
total
thickness
of
paint
on a
steel
surface
(primer
plus
finishiog
coats)
should
be
within
the
range
ol 22o
-
260
pm
uorinated
resin
paint (2SUm)
Poll,urethaae/fl
uorinated
resin
paint
(25tlm)
Epory
resin
paint
(6opm)
Epory resin paint
(6opm)
Inorganic zinc-rich
paint
(75
pm)
Total
- 2So
lun
NOTET
i)
It
is
very
necessary
to
perform
coating
testing to
assess
coating
suitability
for
wo.k.
(e.g.
The
accelerated
exposure
test where
coatings
condition
is assessed
in terms
of
resistance
to
a
high
chloride
environment
can
be
done)
ii)
It
is
atso
strongiy
recorrmended,
that
a trial repair
be
installed
and
its
perflrmance
monitored
before
implementing
a
particular
system
throughout
the
stadium.
3
8/18/2019 Feasibilty Report of Accra Sports Stadium
5/20
c)
Eot-dip
galvanized
boltq
nuts
and
washers,
prefeEed
for
Epes
w-hich
must
be
rcplaced.
Provide
also,
full
coating
systems
to
exposed
surfaces
of
all existing
bolts,
nuts
and
w-ashers.
It
is
important
to
stnpe
coat
all
edgeq
ill
addition
to
ensure
an
appropriate
hlm
thickness
df
Due
-to_
the
observations
of
ongoing
corrosion
in
the
metal
cladding
to VIp
area-s,
it
will
be
more
cost effective
to
replace
deck
in-kind
(areas
of
modlrate
to severe
corosion,
showD
as
perforationsj
with
a
shop-applied
coating
system
on
a
new
claddedpanel.
ei
Spot
heat
for
areas
with
modeEte
corrosion,
and
apply
the
proposed
coating
sequence.
fepair
also,
all
localized
areas
of
concrete
spalling
as observed
in
the
concFete
fram
ing
beams
in
the
lower
seating
section"
oi
tf,"
,iu"f, in"]pr;;
;oo.m.
'
ln
dolng
this.
Hack.
wirebrush,
add
additional
bars
if
necessary
and
coat
with
grout
admixture.
Re-cast
using
richer
mix
of concrele
t. 2,/2.
2v2
Plaster:
r:3
Replace
all
damaged
and
corroded
metal
doors
to
shops.
Conclusion
AXSL
concludes
that
the
facility
remained
safe
under
nomal
loadings,
and
tiat
there
was
no
danger
of stmctuml
failures
in the
near future.
However,
AESL
continues
to
emphasize
that,
If nothing
is
done
about
the
curent
situation,
the
manifestation
of
failed
or distressed
matings
will
bec(:me
more
prevaleut,
and
areas
currently
corrodiug
will
continue
to
do
so,
witl
the
severity
and
extent
of
corosion
increasing;
corrosion
being
time
depending
process"
Subsequently,
isolated
failure
ofsome
member
can
occur.
iJ:l:Y:,:.:j:,^l^:::l:.r
was
initiatl),
not
established,
the
first
maintenance
painrins
of
ule Staolum
ts
overdlle.
Further
delay
of
main
tencnce painting
could
resulL
in
greater
deterioration.
tor
example,
3reas
suitable
for
over
coating
at
this
ti;e
may
become
candidates
for
full
replacement
if
deterioration
continues
unabated-
8/18/2019 Feasibilty Report of Accra Sports Stadium
6/20
INSPECTION
TEAM
Eric
Nkansah
-
Dwamena
-
Chief Estate
Manage ,
National
Sports
Council, Accra-
Seth Nttfrah
-
Estate
Department,
Nationa.l
Sports
Council,
Accra
Richard
Ast
ey
-
Estate
Department,
Nationat
Sports Council,
Accra
Newton
AzuErah
-
Eleceic*l
Division,
National
Sporis
Counci},
Accra
JudeAndoh
-
Technician
(Electrical
Division),
.
John
Prempeh
-
Technician
(Electrical
Division),
"
Samuel
McCarthy
-
Plumber,
Natioual
Sports Council,
Accra
Samuel
Quaye
-
Plumber,
National
Sports
Council, Accra
Mr.
Ofori
-
plumber,
National
Sports
Council, Accra
Naa
Ayele
Hanson
-
Architect,
AE.S.L,
Heaal
Office, Accra
Walter
Semordzi
-
Assistant
Architect,
AE.S.L,
Head
Office,
Accra
Frederick
Owusu-.Addo
-
Structura}
Engineer,
A.E.S.L,Ilead
Of6cq
Accra
Redord
Atrong
-
Assistant
E[gineer
(Structures),
"dE-S.Ir
Kodwo
Duku
Wilson
-
Assistant
Enginee
(StructEes),
"A-E.S,L
ES,a
A-
Onwona
-Sarfo
-
Mechanical
Division,
A_ESL
Jasper
Dzade
-
Electrical
DivGion
Patrick
Essien
-
Electrieal
Division
Abdulai
Shiraz
-
euantier
Suweyor, AE.S.L,
Accra
Vigbedor
AE. Daniel
-
Quantity
Surveyor, AE.S.L,
Accm
8/18/2019 Feasibilty Report of Accra Sports Stadium
7/20
APPENDIX
-A
(PHOTO
DOCUMENTATION)
Fig.
7
l
8/18/2019 Feasibilty Report of Accra Sports Stadium
8/20
Fig. 3
corrosion
os
observed on
diogonol membeB of
ttuss
Fig. 4 wider view
ofthe
obseyed corrcsion
8/18/2019 Feasibilty Report of Accra Sports Stadium
9/20
Fig.
5
perforution
foilures,
obseNed inthis
ctodding
(Vtp
ored)
Fig,
6
Abserveel
cosmetic
corrosion
found
on the
metal
roof
deck
8/18/2019 Feasibilty Report of Accra Sports Stadium
10/20
Fig.
7
rust
spotting
ond cooting bliste ng,
nostly
widespreod
on
structurol
steel
Fiq-
8
fldnge
tips being notoble dreos of corrosion
and
codtina
loss
8/18/2019 Feasibilty Report of Accra Sports Stadium
11/20
Fig.
9
the
conosive
attack on
the
obseNec diagonal
bracing
fienberc
Fig. 70
observed reinforce
conctete
ftuning
elements
ofthe may
9th
which
is
in
good
condition
os
comporcd to the
sttucturdlsteel
component
ofthe
focility
10
8/18/2019 Feasibilty Report of Accra Sports Stadium
12/20
Fiq. 77
rusting
of steel members of support to score
boord
Fig. 72
ctoser
copture
of the erteft of domoge
coused by the
corrosion
11
8/18/2019 Feasibilty Report of Accra Sports Stadium
13/20
Fig.
13
conoded ond
domoged
metoldaarto
shop
12
8/18/2019 Feasibilty Report of Accra Sports Stadium
14/20
ACCRA
SPORTS
STADIUM
This
report
is
to
idcntify all
the problems relating
to
electrical
system
at
the
Accra
Stadium.
The
arcas
covered
are as
follows:
a)
High
Voltage
'l'ransmission/Energy
Serving
Unit
(Capacitor
Banks)
b)
Low Voltage
Distribution
System
c)
Floodlights
d) r.rPS
e)
Scorc
Board
0
PA
Systcm
g)
Fire
Alarm
System
Sports
OBSERVATIONS
High
Voltage
Transmission/Energy
Serying
Unit
(Capacitor
Banksl
have no
problem,
but the
i[formatlon
gathcred
from
the
officer
in charge
was
that,
since
the
installation
of
the two
transformers
which rated
B0OKVA
and the
capacitorbank
which
rated
310KVAR
and 210KVAR
for
East and
West
wings
respectively
have
not
been
serviced.
However,
there
was
water
coming
from underground
attransformer
room
which
made
the
feeder
and
sub fceder
cables
submerge in
water.
LOW
VOLTAGE
DISTRIBUTION
SYSTEM
The
two
distribution
cubicles
manufactured
by
Schneider
Electlic Merlin
Gerin
both
rated
800.4were
functioning
satisfactoril,
however
the
one atthe
westwingcould
not
change
automatically
to
the
Generator
Breakerwhen
the
Gen Set started.
The
Beka
Stadium
Controller
for
the
floodlights
is
nottvorking;
therefore
the
stadium
floodlight
cannot
be
control
bythe Beka
controller
and
need
to
be
controlled
manually
from
the
mast
panel.
8/18/2019 Feasibilty Report of Accra Sports Stadium
15/20
The
fibre
control for
security
light
was
not functioning,
the
following
specification
for this
item was
observed, that
is signal
detector SD-10D1
10
digital input
module,
battery
rating
of
l2v-7.5A
Karsun Rcchargeable
sealed Ied
acid
battery.
Breaker ratinss
164
10A and 6A
ENFRGY
UNITS
SPECIFICATION
Merlin
Gerin
10
(63
A)
3x23O
/4OOv
50
/6OHZ
FLOOD
I
IGHTS
The
flood lights
were
working
but there were
some bulbs that are
not
iunctioniig.
Also
the
fixture
fittings
also
collect
water
and this affects the
lights.
Out
of295
lights,
15g
number
were
not
working.
Further
observation
from
the
inspectioll
conducted
shows some
ofthe
bumt
capacitoas
and
chokes
which
may also
pertain
to the non-functioning
of
some
floodlights.
The
following
technical
details
ofthe
choke
and
capacitor
were
observe4
CAPACTTOR
AFCAP
60LrF
+
50%
440y
-s|HZ
-25t+70C
400v
-
HSFNT,
450V
-
HSFPV rEC
60252-1
CHOKE
2000W
Metal
Halide lamp,
cat
no
Mll 2000Y 10.3A
0,B5PF'
1-2
400V
1-3 415V
MAIN
UPS
SYSTEM
The
UPS Systcm supporting the
score
board PA
system and
clean
power
socket outlet
was
faulry.
The type
ofUPS
is
Gala-xy3ooo/Single
Unit/CF
20KVA.
8/18/2019 Feasibilty Report of Accra Sports Stadium
16/20
Conhact
no
projcct
name
A200822
Swiss
timing Ghana
Accra
Serial No
v24-72-3-A-00072
Display
type
V2+
/L2-3
/
320x240-rCb
/
s
Produced
in
cw2a/07
Dimension
in
mm 7680x5760x150
excluding
steel
construction
Power
connect
400v
-3phase
+
N+PE
Max
current 145A I=49AlPhase
Data
transmission
Software
Edit
pc
Brightness
Directly transmitted fiom Editvia
Galactica
by
FOC
(2fibreJ
Omega Galatica
6250
cdlm2
SCORE
BOARD
According
to the
Estate
Officer the whole
score
board was
not working.
Thc
technical
specifications
for
the score board was
as
follows
PA SYSTEM
It was confimred that thc
PA
system is working.
FIRE
ALARM
SYSTEM
The fire alarm systern occasionally
gives
false
alarm.
Some
ofthe
break
glasses
were broken.
The
lotal
numbcr
ofbreak
glasses
broke
were 42no
8/18/2019 Feasibilty Report of Accra Sports Stadium
17/20
CCTV
It
was
found
out
that
the
CCTV
cameras
were
controlled
by
National
Securiq,
and
as
our
team
wsnl
a.r.6,
we
could
find
out that,
some
of
the
CCTV
cables have
been
cut and
disconnected
at
the
junction
boxes.
GENERATOR
The geneBtor
system
is workidg.
I,IGHTING
SYS'TEM
Most
of the
outside
light
fixtures
were rusted
and
some
of the
bulbs
were
nor
functioning
LIGHTENING
PROTECTION
It
was realized
that
due
to
lightening.
a
lot
ofthe bulbs
are
going
offand
thus
affecting
the
expected
lumen
output
of
the
flood
lights.
Also, lightening protection
in
and
arourd
the
stadium
was
not
adequate.
RECOMMENDATIONS
UPS
1.
A new
IIPS
need
to
be
replaced.
FLOOD
LIGHTS
l.
All the
flood
lights
need
servicing
and also
making
drainage points
under
the lights
to
drain
water
collecting
in the
fixture fitting
due
to rain.
2.
The
electonic
ballast
olthe
bulbs
needs
to
be
changed and
defective
bulbs
replaced.
3.
Tools
and
safety
gears
will have
to be
provided
for
servicing the
flood lights.
8/18/2019 Feasibilty Report of Accra Sports Stadium
18/20
SCORE
BOARD
A
new
score
board
need
to
be
replaced
GENERATOR
l.
The
generator
needs
to
be
serviced.
PA SYSIIM
PA
system
needs
to
be
serviced
FIRE
ALARM
SYSTEM
The
contlol
panel
ofthe
fire
detection
and
alarm
systeft need
to
be serviced and
all
broken
break
glass
replaced
as well.
ccTv
A
new
CCTV
installation required
at the
whole stadium.
LIGHTING
SYSTEM
About
40
number
ofoutside security light
around the
stadium
need
to
be
replaced
LIGHTENING
PROTECTION
It is recommended that lightening
protection
in
and
arould
the Stadium must
be enhanced
by
introducing a DAT
Controller air terminal on
each
of the flood lights
suoh
that
their
coverage
of
protcction
will
out
across
each
other
to
protect
the entire
Stadium.
Also,
protection
due
to
over voltagc
must
be
done irl oth€r to
protect
all sensitive equipment.
8/18/2019 Feasibilty Report of Accra Sports Stadium
19/20
---^
sE\,v
EIiACll
AND
1/ATEIT
slIiAGE
sYS
I'ENI
SEWERAGE
AND
WATER
STORAGE
SYSTEM
A
f
THE ACCRA SPORTS
STADIUM
ABSIRACT
Thls report
considers
the
problerns,
observations
arld
recommendations
concerning the sewemge
sr.€l€Ennd
water
storage
systerl.at
the
Accra Sports
Stadium
1
,
DISCUSSION
The curent
sewerage
sifuation
at the
stadium,
according
to the
stadium
officials,
is
overwhelmed.
They complain
that
the septic
tank
at the
stadium
has
to be
desludged
about three times
each
year.
The
stadium
curiently
is
not comected
to
the
central
sewer system.
It was
however
noticed ihat some
sewer lines
behind
the RLG Hall
which
have
been
blocked
oIf to
some
extent
but
continues furd1er to a
chamber
outside
the
stadium
whidr
then
joins
the
main
sewer
line cominS
from
the
Ministries area.
The pipes
used
in
tlLis
line, however,
are
4inch
asbestos
PiPes.
Concerninti
the
water
storage
sysh'rL
the
stadium
curently
has 21
Nos. 650gallons
(Zgsslitres)caPacity
Polytan-ks,
makin8
a
total
of
13,650
gallons
(62055
libes),
with
8
of them broken do r'n.
Currently
the
sitting
capacity
of
the
stadium
is
aPproximately
40,000
with tie following
diskibution:
.
North
Wing
seati r$
14,239
(36"/.')
wilJl
I tal*s
(1200
Saltons/
23,640litres),
.
Solrth
wing seating 14,524
(36%) with 5
tanks
(3,250
gallons/
14,755litres);
.
East wing seating
6,849
(17%)
with
2
tanks
(1,300
Sa.llons/
5,910
litres);
, .
West
Wing
seating
4,336
(11%)
with
6
tar*s
(3,900
gallons/ 12730
litres).
,
'
The
water stored
from these tanks
serve wash:rooms
at tle
vaious
wings
of the stadium
including the
dressing
rooms.
There
are also
no
water
hose
reel
sighted
in stadium
for
fire
figlrting
except
two fire
hydrants
with
one
fuictioning
at
the
moment.
The
stadium officials complained
Olat during
matches
where
the
stadium
is
at
full
capacity, they
-
experience
water
shortages
in the waskooms,
which ihen
makes
the
u/ashl:oorns
untidy.
ABSTRACT.l
8/18/2019 Feasibilty Report of Accra Sports Stadium
20/20
SEWEI'\CE
AND
WATEIT
S,fOItACE
SYSTEM
CONCLUS/ONS
AND
RECOMMENDAI/ONS
Conceming ihe
sewcr
systcm,
the
effluent
couiing into
dre
septic
tank
should
be reduced
in
order
not
to
overload
it,
tlcreby.
rcducing
the
pedods
in which
the
sep[c
tark
will be desludged.
h1
view
of
tlds,
seweragc
coming
from
the
\tp
section,
i.e. the West
Wing
and the Dressing
rooms,
strould
be
disco.nected and diverted
from
the
line
going
into
the
sepfic
tank in
the
stadium.
This
shor
d
be
divertcd inlo
the
lines
behind
the RLG
Hall,
which links
up with a
manlole
outside
tie
stadium. The
existing
pipcs
strourd
also
be
charged
ftom the
concrete
pipes
to
6
inch
HDPE
pipes
to
dccornmodate
tlre
llow corning
in.
The
cuEent water
storage capacity
for
the
stadium
is
woefulty
inadequate.
The
average
petson
uses
7
litres/cap/day
in such
commercial
facirittet
mearung
for
a
rotar
capacity
of
about
40,000
people, about
.,
385100
litres
(85,000
gallons)
woutd
be needed,
induding
fire-fighting.
Which
is far
more
ihan
the
current
62055
litres
(13,650
gallons)
serving
the
stadium.
The
distribution
of the
total
amount
of
water
needed for each
stand
is as
follows:
.
North wing,
140,000
litres
(30,800
ga
ons)
.
South
wing
-
14O000
lirres
(30.800
galons)
.
East
Wing
-
7O000
litres (1t400
gatlons)
.
West
wing
-
40,000litres (&800
galons)
Water storage
systen
extia tanks
should
be
provided
at the
various
wings
of
the
stadium.
The
distribution of
exha
water quantity
needed
for
each
wirrg
is
as follows:
.
North
yling
-
120,000
litres
(26400
gallons)
.
South wing-
125,000litres (27FOO
ga
ons)
.
East
Wing
-
65,000litres
(14,300
galons)
"
.
West
wing
-
23,000
lirres
(5,100
galloru)
-
,)
Itrese
capacities
include
water to
be
used
fot
fire fighting
as
well"
As
such,
fire
hose
reels
should
be
installed
and then corulected
to the
storage
tanks.
CI)NCI-USIONS
AND
ttECOMMENDATIONS"2