February 1, 2012 Casino Facility Progress Report
Transcript
Page 1: February 1, 2012 Casino Facility Progress Report.

February 1, 2012

Casino Facility Progress Report

Page 2: February 1, 2012 Casino Facility Progress Report.

Construction Progress – February 1, 2012

Contract sum to date: 164,372,575

Total project completed to date:

85%

MBE / WBE awarded to date: $ 35,900,000 *

Average daily # of construction workers on-site:

300

Note: * - MBE/WBE amount exceeds original goal by over $14,000,000.

Page 3: February 1, 2012 Casino Facility Progress Report.

Arial View

Page 4: February 1, 2012 Casino Facility Progress Report.

January 26, 2012 Tour

• Team member Training Room.

Page 5: February 1, 2012 Casino Facility Progress Report.

January 26, 2012 Tour – Team Member Dining Room

Page 6: February 1, 2012 Casino Facility Progress Report.

January 26, 2012 Tour – Epic Buffet

Page 7: February 1, 2012 Casino Facility Progress Report.

January 26, 2012 Tour – Gaming Floor

Page 8: February 1, 2012 Casino Facility Progress Report.

Comparative Photos (Final Cut Steak & Seafood House – photo #1)

Page 9: February 1, 2012 Casino Facility Progress Report.

Comparative Photos (Final Cut Steak & Seafood House – photo #2)

Page 10: February 1, 2012 Casino Facility Progress Report.

Comparative Photos (Epic Buffet)

Page 11: February 1, 2012 Casino Facility Progress Report.

Comparative Photos (Skybox Restaurant & Bar)

Page 12: February 1, 2012 Casino Facility Progress Report.

Comparative Photos (Serpentine Sign)

Page 13: February 1, 2012 Casino Facility Progress Report.

Comparative Photos (Poker Room)

Page 14: February 1, 2012 Casino Facility Progress Report.

Summary Timeline• Surveillance:

– System Programming/Testing: January 3-15, 2012– System Turnover to Property: January 16, 2012

• Food & Beverage:– Epic Buffet & Final Cut Steakhouse Partial Certificate of Occupancy: December 27, 2011– Team Member Dining Room Open: January 6, 2012

• Slots:– Carpet Installation: December 14, 2011 to February 10, 2012– Slot Bases Installation: December 19, 2011 to March 2, 2012– Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval)– Estimated Installation: TBD (30 day duration)

• Table Games:– Artwork/layouts submitted to Commission for review & approval: December 21, 2011– Carpet Installation (Pit areas): To be completed by February 29, 2012– Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval)– Estimated Installation: March 1-5, 2012

• Final Inspection/Certificate of Occupancy:– Certificate of Occupancy: March 15, 2012

Page 15: February 1, 2012 Casino Facility Progress Report.

Staffing Update

Status Number

Active Team Members 69

Future Dated Offers 228

Completed Offers in 2 Weeks 700

Total 997

• All employees identified as key employees to date have submitted a complete key license application (14 in total).

Page 16: February 1, 2012 Casino Facility Progress Report.

Vendor Update

Status Number Percentage

MBE/WBE Vendors 23 10.50

All Other Vendors 197 89.50

Total 220 100.00

Page 17: February 1, 2012 Casino Facility Progress Report.

Public Safety Outreach• Most recent meeting held on January 30, 2012 with the following

attendees:– Captain Brad Weis – Toledo PD (Strategic Response – Hollywood Contact

person for opening– Thomas Wiegand – Toledo PD (Area Commander)– Chief Mark Hetrick – Perrysburg Township PD– Chief Thomas Cairl – Northwood PD– John Altman – Ohio Highway Patrol– Eric Reynolds – Deputy Chief, Wood County– Seven (7) other members of local law enforcement

• Topics included: Team member & guest safety, Traffic flow, Natural Disasters, Gangs, Miscellaneous crimes & threats.

• Bi-weekly meetings to occur going forward.