+ All Categories
Home > Documents > FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements...

FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements...

Date post: 29-Mar-2015
Category:
Upload: emmanuel-revill
View: 218 times
Download: 1 times
Share this document with a friend
Popular Tags:
22
FERC ORDER 764 15 minute Scheduling
Transcript
Page 1: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC ORDER 76415 minute Scheduling

Page 2: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 764

Topics

Implementation timeline

FERC Requirements

WECC Requirements

Impacts PS, RT, ATF

WIT Displays

Page 3: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 764

November 12, 2013 implemented 15 minute scheduling FERC Order 764

Page 4: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 7644

15 minute Scheduling Intra-hour scheduling intervals: WECC scheduling intervals

shall be defined as: xx:00 – xx:15, xx:15-xx:30, xx:30-xx:45, and xx:45-xx:00.

Intra-hour profiling on a Request for Interchange (e-Tag) shall be in intervals with start and stop times of: xx:00, xx:15, xx:30, and xx:45. Schedules will be allowed in 15 minute, 30 minute, 45 minute, 1-hour or longer blocks provided the start and stop times are as above. (For example, a customer may have an e-Tag that starts at xx:15 and ends at xx:00, for a 45 minute e-Tag.)

The exception to this rule is the start/stop time for curtailed and re-loaded e-Tags which are determined by reliability related reasons.

Page 5: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 7645

15 minute Scheduling Requests for Interchange submitted within the

hour will allow the use of firm or non-firm Transmission Service Reservations, and Network Integration Transmission Service rights, including but not limited to the use of Point-to-Point Redirect reservations, Point-to-Point Resale reservations, or Original reservations.

The FERC order allows intra-hour scheduling to all transmission customers taking service under the OATT.

Page 6: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 7646

15 minute Scheduling Requests for Interchange submitted within the hour

will allow the use of new or existing Transmission Service Reservations.

The FERC order did not mandate that a customer only use transmission rights purchased prior to the hour, and also did not mandate that TSPs allow for the acquisition of transmission rights within the hour.

The recommendation allows a customer to purchase transmission service during the hour if there is Available Transfer Capability.

Page 7: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 7647

15 minute Scheduling Preemption of Requests for Interchange (e-Tags): e-Tags

utilizing firm transmission capacity would preempt an e-Tag utilizing non-firm transmission capacity if the e-Tag was submitted at least 20 minutes before the impacted scheduling interval.

E-Tags utilizing non-firm transmission capacity with a higher OATT transmission priority would preempt e-Tags utilizing a lower OATT transmission priority non-firm transmission capacity if the e-Tag was submitted at least 20 minutes before the impacted scheduling interval.

This recommendation eliminates the “no bumping” rule that many WECC Transmission Providers currently have in Business Practices.

Page 8: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 7648

15 minute Scheduling Requests for Interchange Timing: A Request for Interchange

(e-Tag) must be submitted at least 20 minutes prior to the start of the impacted WECC scheduling interval to be considered “On Time.”

A request submitted less than 20 minutes prior to the impacted WECC scheduling interval is considered “Late” and will be marked “Late” by the Interchange Authority. “Late” e-Tags may be accepted at the discretion of the Transmission Service Provider.

The current NERC INT Standards and companion NAESB Standards include Timing Tables that define when Requests for Interchange must be submitted to obtain an “On Time” classification by the Interchange Authority.

Page 9: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 7649

15 minute Scheduling Intra-hour scheduling profiles submitted

in Pre-Schedule: Requests for Interchange submitted in the Pre-Schedule horizon may be submitted using the WECC intra-hour scheduling intervals.

This is at the customer’s discretion and is not required.

Page 10: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76410

15 minute Scheduling Curtailments: If needed, Reliability Limits

(curtailments) will occur prior to the top of the hour (as they do today) for all scheduling intervals in the upcoming hour that exceed a path scheduling limit, and Reliability Limits (curtailments/reloads) will occur within the hour as needed.

Page 11: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76411

15 minute Scheduling ATC Calculation: At a minimum, ATC will

continue to be calculated as Transmission Service Providers currently calculate today.

Order 764 neither requires Transmission Service Providers to provide an intra-hour transmission product nor requires more frequent calculations of ATC than what occurs today.

Page 12: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76412

15 minute Scheduling However, FERC did not preclude a

Transmission Service Provider from offering a sub-hourly product if it chooses.

Transmission Providers should note that 15-minute scheduling may require more frequent calculation of their hourly transmission than the minimum current requirements due to schedules adjusted or transmission sold during the hour potentially impacting ATC on the path.

Page 13: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76413

15 minute Scheduling Ramp Rates: The top of the hour ramp will remain 20 minutes. Ramp duration for the intra-hour scheduling intervals will be a

10-minute straddle ramp. There was concern in the Task Force that if volume is heavy and there is a large NSI change for the intra-hour intervals, a 10-minute ramp may not be sufficient time to fully ramp in expected values.

It is recommended that a re-evaluation of the ramp duration be performed approximately 6 months after the implementation of 15-minute scheduling (or at such time as there is sufficient intra-hour scheduling volume to create a data sample set) to ensure the ramp rates are appropriately set.

Page 14: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76414

15 minute Scheduling Net Scheduled Interchange Accounting

and Sub-Hourly Schedule Integration: Net Scheduled Interchange will remain as it is today, integrating to an hourly value at the end of each hour. Schedules with duration of less than 1 hour will integrate using currently defined rounding rules per NAESB WEQ-004-19.1.

Page 15: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76415

15 minute Scheduling Coordinated Checkouts of Balancing

Authorities: The Task Force recommends that Balancing Authority Checkouts should occur for Net Scheduled Interchange values as reflected below:

Page 16: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

16

FERC Order 764Net Schedule Interchange

Horizon Value Check Out

Preschedule – 15:00 PPT Hourly MW Integrated Value Always check out

Real Time Before-the-Hour Hourly MW Integrated Value and non-integrated MW Values for each scheduling interval within the hour.

Only upon a value change

Real Time Intra-Hour XX:00-XX:15 Non-integrated MW Value Only upon a value change

Real Time Intra-Hour XX:15-XX:30 Non-integrated MW Value Only upon a value change

Real Time Intra-Hour XX:30-XX:45 Non-integrated MW Value Only upon a value change

Real Time Intra-Hour XX:45-XX:00 Non-integrated MW Value Only upon a value change

Real Time Reliability Curtailments Hourly Integrated Value Check after Hour Completes

Real Time After-the-Hour – Hrly NSI Hourly Integrated Value Always check out

After-the-Fact – Hourly NSI Hourly Integrated Value Only upon a value change

Page 17: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76417

15 minute Scheduling The Net Scheduled Interchange value being

checked out before and after the hour is the integrated hourly MW value we use today.

The Net Scheduled Interchange value being checked out for the individual intra-hour scheduling intervals will be a non-integrated 15-minute MW value.

This is to ensure the adjacent BAs are driving to the same NSI value for each schedule interval as required by NERC standards.

Page 18: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76418

15 minute Scheduling ATF checking of Net Actual Interchange

remains unchanged, conducted on the Hourly MW Value.

Page 19: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 76419

15 minute Scheduling Inter-hour schedules totals received by

WALC BA November 2013 39 December 2013 20 January 2014 12 February 2014 34 March 2014 47 April 2014 36

Page 20: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.
Page 21: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.
Page 22: FERC ORDER 764 15 minute Scheduling. FERC Order 764 Topics Implementation timeline FERC Requirements WECC Requirements Impacts PS, RT, ATF WIT Displays.

FERC Order 764

Questions


Recommended