FERC’s Hydropower Licensing Program November 7, 2012 Webinar Number: 1-877-857-1347 Meeting ID: 1088
Transcript
Page 1: FERC’s Hydropower Licensing Program

FERC’s Hydropower Licensing Program

November 7, 2012

Webinar Number: 1-877-857-1347

Meeting ID: 1088

Page 2: FERC’s Hydropower Licensing Program

10:00 AM • Who is FERC and What Do We Regulate? • Types of Authorizations • Licensing Processes • Basic Licensing Steps • Other Laws and Regulations 1:00 PM • Pumped Storage Developments • Web Resources

Planned Agenda

Page 3: FERC’s Hydropower Licensing Program

Mission: Reliable, efficient and sustainable energy for consumers

What Does FERC Regulate?

Electric Transmission

Hydroelectric Projects

Natural Gas

Oil Pipelines

Page 4: FERC’s Hydropower Licensing Program

Organizational Structure

Chairman Jon Wellinghoff

Commissioner John R. Norris

Commissioner Philip D. Moeller

Commissioner Cheryl A. LaFleur

Commissioner Tony Clark

Admin. Law

Judges

Executive Director

External Affairs

Admin. Litigation

Secretary General Counsel Enforcement

Energy Projects

Energy Market

Regulation

Energy Policy &

Innovation Electric

Reliability

Page 5: FERC’s Hydropower Licensing Program

Director Jeff C. Wright

Deputy Director Ann F. Miles

Division of Pipeline Certificates

Division of Gas- Environment &

Engineering Division of

Hydropower Licensing

Division of Hydropower Administration &

Compliance Division of Dam Safety

& Inspections

Energy Infrastructure Policy Group

Assistant Director

Management & Operations

Certificates Branch 1

Certificates Branch 2

Gas Branch 1 New England Branch

South Branch

Northwest Branch

West Branch

Land Resources

Branch

Engineering Resources

Branch

Environmental Review Branch

Washington Office

Atlanta Regional Office

Chicago Regional Office

New York Regional Office

Portland Regional Office

San Francisco Regional Office

Mid-Atlantic Branch

Midwest Branch

Gas Branch 2

Gas Branch 3

LNG Compliance Branch

LNG Engineering Branch

Project Review Branch

Aquatic Resources

Branch

Office of Energy Projects

Page 6: FERC’s Hydropower Licensing Program

• Commission authorization is required for non-federal hydropower projects: • located on navigable waters; • located on public lands of the United States; • using surplus water from a federal dam; OR • located on Commerce Clause waters, constructed after

1935, and connected to the interstate grid.

Hydropower Jurisdiction (Federal Power Act)

Page 7: FERC’s Hydropower Licensing Program

Hydropower Program

Licensees Resource agencies

Tribes NGOs

Local stakeholders LICENSE ADMINISTRATION & COMPLIANCE

Page 8: FERC’s Hydropower Licensing Program

Division of Hydropower Licensing •Efficiently process hydropower project applications •Prepare and issue environmental documents •Address agency, tribe, and public concerns fairly •Analyze recommendations and incorporate reasonable environmental conditions into licenses

Page 9: FERC’s Hydropower Licensing Program

Division of Hydropower Administration and Compliance

•Ensure timely and effective

compliance with license •Take enforcement action if needed, including penalties • Review and approve project changes • Handle license surrender

Page 10: FERC’s Hydropower Licensing Program

Division of Dam Safety and Inspections

•Implement dam and public safety •Ensure protection of life, property, and the environment •Develop policies, programs, and standards for assessing dam safety •Assess security measures SWIFT POWER CANAL

WASHINGTON 2002

Page 11: FERC’s Hydropower Licensing Program

• Conventional – Use head from a dam – Use conduit

• Pumped Storage – Upper and lower

reservoir

• Hydrokinetic – No dam – Generate from ocean waves, currents, or tides or

river flow of inland waterways

Types of Projects

Page 12: FERC’s Hydropower Licensing Program

U.S. Hydropower Capacity ~ 101,000 MW

U.S. Hydropower Capacity under FERC Regulation ~ 54,000 MW

Providing – 10% of U.S. Generating Capacity

Conventional U.S. Hydropower Federal and FERC-Regulated

Page 13: FERC’s Hydropower Licensing Program

• Preliminary permit – Maintains priority of application for three years – Requires feasibility studies and pre-filing activities – Does not authorize construction

• License – Authorizes construction and operation – Issued for up to 50 years (original) or 30-50 years (relicense)

• Exemption: 5 MW or conduit – Authorizes construction and operation – Issued in perpetuity

Types of Authorizations

Page 14: FERC’s Hydropower Licensing Program

Questions?

Page 15: FERC’s Hydropower Licensing Program

Licensing Processes

Integrated Licensing Process (ILP)

Alternative Licensing Process (ALP)

Traditional Licensing Process (TLP)

Default process Available upon request and FERC approval

Available upon request and FERC approval

Projects with complex issues and study needs; FERC oversight in pre-

filing

Projects that effectively promote a self-driven

collaborative pre-filing process; some FERC

involvement

Projects with less complex issues and study needs; no

FERC oversight in pre-filing

Predictable scheduling in both pre-filing and post-

filing stages

Collaboratively-determined schedule in pre-filing stage

Paper-driven process; no set timeframes

Post-filing elements of each process very similar

Page 16: FERC’s Hydropower Licensing Program

Basic Licensing Steps Pre-filing

Consultation Issue Identification

Information Gathering

• Discuss project proposal with relevant agencies and stakeholders.

• Identify issues, information gaps, and study needs regarding potential effects of the project proposal.

• Conduct studies to fill information gaps and develop license application that synthesizes results.

Proposal Document Filed

Page 17: FERC’s Hydropower Licensing Program

Basic Licensing Steps Post-filing

Formal Comments

Environmental Document

Agency Decision/ Record

• Agencies/stakeholders comment on license application and submit recommendations, prescriptions, and conditions.

• Commission staff analyzes effects of project proposal and alternatives, analyzes agency and other comments and conditions, and makes recommendations to the Commission.

• Commission makes licensing decision. License includes requirements based on record (analysis in environmental document and filings in docket).

License Application Filed

Page 18: FERC’s Hydropower Licensing Program

1 year 2-3 years

1.5 years

Pref

iling

Po

stfil

ing

Initial Proposal & Information Document

Scoping Meetings &

Public Comment

Study Plan Development

Conduct Studies & Prepare

Application

Application: Proposal, Effects & Mitigation Measures

FERC Review & Public Comment

FERC Environmental Document &

Public Comment

FERC Authorization

(License Order)

Integrated Licensing Process

Page 19: FERC’s Hydropower Licensing Program

1 year 2-3 years

Pref

iling

Initial Proposal & Information Document

Scoping Meetings &

Public Comment

Study Plan Development

Conduct Studies & Prepare

Application

Initial Steps

Page 20: FERC’s Hydropower Licensing Program

• Brings together all existing, relevant, and reasonably available information

• Provides basis for identifying issues, data gaps, and study needs

• Forms the foundation of future documents • Sets the schedule for the ILP

Purpose of the PAD

Page 21: FERC’s Hydropower Licensing Program

• Project description • River basin description • Description of existing environment and resource

impacts to the extent they are known • List of issues and information or studies proposed

to fill identified information gaps • List of relevant comprehensive plans • Process plan • Summary of contacts

Contents of the PAD

Page 22: FERC’s Hydropower Licensing Program

1 year 2-3 years

Pref

iling

Initial Proposal & Information Document

Scoping Meetings &

Public Comment

Study Plan Development

Conduct Studies & Prepare

Application

Scoping and Study Requests

Page 23: FERC’s Hydropower Licensing Program

Study Request Criteria

• Describe goals and objectives of study proposal • Explain relevant resource management goals • Explain relevant public interest considerations • Describe existing information and need for more info • Explain nexus to project operations and effects and

how study results would inform license requirements • Describe methodology and how it’s consistent with

accepted practice • Describe consideration of level of effort and cost of

study and why alternative study is needed

Page 24: FERC’s Hydropower Licensing Program

Why are the study criteria important?

• Increased understanding of stakeholder information needs

• More focused studies • Better study plans and more

efficient use of time

Page 25: FERC’s Hydropower Licensing Program

Study Plan Development

1 year 2-3 years

Pref

iling

Initial Proposal & Information Document

Scoping Meetings &

Public Comment

Study Plan Development

Conduct Studies & Prepare

Application

Page 26: FERC’s Hydropower Licensing Program

Study Plan Development

Study Requests

Proposed Study Plan

Study Plan Meetings

Revised Study Plan

OEP Director’s Study Plan Determination

45 days

90 days

30 days

30 days

Page 27: FERC’s Hydropower Licensing Program

Study Dispute Resolution

• Mandatory conditioning agency may dispute the OEP Director’s determination for studies directly relating to the exercise of their conditioning authorities – A three-member panel of technical experts make

recommendation – OEP Director considers the panel findings and

makes decision with respect to study criteria and any applicable law or FERC policy

Page 28: FERC’s Hydropower Licensing Program

Conduct Studies & Prepare Application

1 year 2-3 years

Pref

iling

Initial Proposal & Information Document

Scoping Meetings &

Public Comment

Study Plan Development

Conduct Studies & Prepare

Application

Page 29: FERC’s Hydropower Licensing Program

Studies (1 to 2 years)

• Initial Study Report (within 1 year), modify plan if show good cause – Document study was not conducted according

to approved study plan – Document anomalous environmental conditions

• Updated study report (within 2 years) – Same process as for initial study report

Page 30: FERC’s Hydropower Licensing Program

Preliminary Licensing Proposal

• Contents – Describes existing and proposed facilities, operation,

and environmental measures – Includes draft environmental analysis

• Draft license application optional • Draft BA, EFH Assessment, and Historic

Properties Management Plan • Comments/additional studies due within 90 days

Page 31: FERC’s Hydropower Licensing Program

Post-filing: Application Filed

1.5 years

Post

filin

g Application: Proposal, Effects & Mitigation Measures

FERC Review & Public Comment

FERC Environmental Document &

Public Comment

FERC Authorization

(License Order)

Page 32: FERC’s Hydropower Licensing Program

Ready for Environmental Analysis (REA)

1.5 years

Post

filin

g Application: Proposal, Effects & Mitigation Measures

FERC Review & Public Comment

FERC Environmental Document &

Public Comment

FERC Authorization

(License Order)

Page 33: FERC’s Hydropower Licensing Program

Environmental Document

1.5 years

Post

filin

g Application: Proposal, Effects & Mitigation Measures

FERC Review & Public Comment

FERC Environmental Document &

Public Comment

FERC Authorization

(License Order)

Page 34: FERC’s Hydropower Licensing Program

Licensing Decision

1.5 years

Post

filin

g Application: Proposal, Effects & Mitigation Measures

FERC Review & Public Comment

FERC Environmental Document &

Public Comment

FERC Authorization

(License Order)

Page 35: FERC’s Hydropower Licensing Program

License Order

• Document compliance with applicable requirements

• Include license articles • Approve/modify resource plans • Approve design drawings

Page 36: FERC’s Hydropower Licensing Program

Traditional Licensing Process Pre-filing

NOI/PAD Request Use of TLP

FERC Approves Use of TLP Public Meeting

Consultation on Studies Needed for

Development of Application

Conduct Studies File License Application

Page 37: FERC’s Hydropower Licensing Program

Traditional Licensing Process Post-filing

REA Notice NEPA Scoping Notice of Filing Application Filed

Order Issue Final EA/EIS

Resolve Issues and Respond to

Comments

Issue EA/Draft EIS

Page 38: FERC’s Hydropower Licensing Program

Alternative Licensing Process Pre-filing

FERC Approves Use of

ALP

NOI/PAD and Request Use of

ALP

Prepare Communication

Protocol

Stakeholder Consultation

File License Application

Conduct Studies

Cooperative Scoping

Information Package

Page 39: FERC’s Hydropower Licensing Program

Alternative Licensing Process Post-filing

Issue EA/Draft EIS REA Notice Notice of Filing Application

Filed

Order Issue Final

EA/EIS Resolve Issues

and Respond to Comments

Page 40: FERC’s Hydropower Licensing Program

Process Comparison

TLP ALP ILP

Consultation Meetings and Paper Collaborative Integrated

Pre-filing FERC

Involvement Only for study

disputes Yes Yes

Deadlines

Pre-filing Some Process

Defined Post-filing

FERC/Process Defined

Pre-filing

Collaboratively defined

Post-filing FERC/Process

Defined

Pre-filing Process Defined

Post-filing Process Defined

Page 41: FERC’s Hydropower Licensing Program

TLP ALP ILP

Study Plan Development

Applicant

No FERC involvement

Collaborative workgroup meetings

FERC assistance

Study plan meetings

FERC approved

Study Dispute Resolution

Available Agencies

Tribes

paper

Available ALP participants

paper

Available

Mandatory Agency

Paper/panel

Process Comparison

Page 42: FERC’s Hydropower Licensing Program

TLP ALP ILP

Application Exhibit E May prepare

APEA or 3rd party EIS

PLP or Exhibit E follows EA format

Post-filing Additional

Information Requests

Yes limited No

Timing of Resource

Agency Terms and Conditions

60 days after REA

Schedule for final

60 days after REA

Schedule for final

60 days after REA

Modified 60 days after due date for comments

on draft NEPA document

Process Comparison

Page 43: FERC’s Hydropower Licensing Program

Questions?

Page 44: FERC’s Hydropower Licensing Program

CW

A

CZM

A

NH

PA

EFH

ES

A

MM

PA

NEP

A

FPA

Licensing

Other Laws & Regulations

• Information needs/gathering − Licensing process provides forum to address

information needs of other agencies • Mandatory conditioning authority

Page 45: FERC’s Hydropower Licensing Program

National Environmental Policy Act (NEPA)

• FERC conducts scoping – public process to identify substantive issues and alternatives, and eliminate unimportant issues

• FERC prepares environmental document (EA/EIS)

• FERC seeks public comments on EA/EIS

• FERC responds to comments in Final EA/EIS

Page 46: FERC’s Hydropower Licensing Program

Typical Issues Analyzed in NEPA Documents

• Water Quality • Fisheries • Soils/Geology • Wildlife/Vegetation • Historical/Archeological • Recreation/Land Use • Aesthetics • Socioeconomics

Page 47: FERC’s Hydropower Licensing Program

Typical Issues Analyzed in NEPA Documents

• Energy • Flood Control • Water Supply • Irrigation • Navigation

Page 48: FERC’s Hydropower Licensing Program

Licensing Standard Federal Power Act

• Equal consideration - section 4(e) – Equal consideration to environmental and

developmental values

• Comprehensive development - section 10(a) – License project that best serves the public

interest (best adapted to comprehensive plan for use of waterway)

Page 49: FERC’s Hydropower Licensing Program

Other Licensing Considerations

• Consider state and federal fish and wildlife agency recommendations [10(j)]

• Consider the extent to which the project is consistent with comprehensive plans [10(a)(2)]

• Mandatory conditions in FPA: – On reservations [4(e)] – For fishways [18]

Page 50: FERC’s Hydropower Licensing Program

Other Federal Laws

• Clean Water Act • Coastal Zone Management Act • Endangered Species Act • National Historic Preservation Act • Pacific Northwest Power Planning and

Conservation Act • Wild and Scenic Rivers Act • Fish and Wildlife Coordination Act

Page 51: FERC’s Hydropower Licensing Program

Special Designations

• Federal Reservation • CZMA • LWCFA Lands • Wild and Scenic River Act • Wilderness Act

Page 52: FERC’s Hydropower Licensing Program

How to Get Involved

• Participate in pre-filing – Comment on requested licensing process – Stay informed – File comments – Participate in meetings and study development

• Participate in post-filing – Review application – Review NEPA document – File comments and recommendations

• Become an official party to proceeding

Page 53: FERC’s Hydropower Licensing Program

Interventions

• Official party to proceeding – Participate in hearings – File briefs – File for rehearing on Commission decision – Legal standing to be heard by Court of Appeals

• Cannot be a cooperating agency • Must serve any filing on applicant and all

other intervenors • Status terminates when Commission has

issued order on rehearing and time for judicial review has expired

Page 54: FERC’s Hydropower Licensing Program

Conceptual Project

Development

Preliminary Project Proposal

Information Collection, Analysis,

and Dissemination

Evaluation Commission

Action on Application

Pre-filing Period Post-filing Period

Other Stakeholders

Indian Tribes

State Agencies

County/City Agencies Federal

Agencies

Pathway to License

Page 55: FERC’s Hydropower Licensing Program

Questions? Emily Carter

Hydropower Outreach Coordinator

202-502-6512

[email protected]