North Terminal Redevelopment Project
Ferndale Electric Company
Project overview from September 2007 to present
The 10,000’ View
Project OverviewThe North Terminal
Redevelopment (NTR) Project was a planned 26-gate terminal complex designed to replace the airport’s older Davey, Berry & Smith terminal complex.
Airport Fun FactsThe new facility encompasses 824,000 square
feet and is about .75 miles in length or the equivalent of a 160 story building.
There are over 150 communication cabinets distributed between more than 36 telecommunication rooms (Special Systems Rooms).
Fiber Fun FactsThe backbone fiber consists
of both single-mode and laser optimized 50mm cables.There are almost 6000 SC
connectors terminating over 500 miles of fiber strands.
Sumitomo Airblown fiber isused for all major backbones.There are over 50 Siemon 72-port fiber panels in the Main SSR alone!
Network Electronics Fun FactsIn the base building
(supporting Wayne County Airport Authority only) there are over 50 Cisco switches providing 2400 ports of powered Ethernet connectivity.
Each switch is connected with redundant fiber connections back to 2 main core switches.
Copper Backbone Fun FactsThere are more than
9000 pairs of copper phone backbone pairs which equates into over 900 miles of copper pairs.Enough copper
pairs to go from the Detroit Metro Airport to the Dallas Airport!
Paging Fun Facts
•The paging system has over 1600 speakers throughout the project.•Speakers in the concourse are controlled with ambient sound sensors that adjust the volume based on the background noise.•Select gates utilize IP microphones for local announcements.
The Technology CablingEnd to end Siemon
connectivity utilizing MapIT patch panels for all category 6 data connections.
Voice connections are also category 6 and terminate on a Siemon S210 style block.
Over 700,000 feet of high performance Siemon Category 6 4-pair cable has been installed.
The Details!Fluke test equipment
was utilized for certification of both copper and fiber.
iTRACS software was utilized for as-builts and documentation.
Complete Rack to Jack!
Typical SSR / Raised Floor
Multi User Flight Information Display (MUFID)Over 150 displays are utilized
to inform the public as to flight schedule and to enhance the service level provided by the airlines.
MUFIDS are used for departure and arrival information in addition to baggage carousel identification.
Each gate has a 40” display for airline information.
MUFID Gate Podium Back Wall
40” LCD Mount Inspection
Outbound Baggage MUFID
Common Use Passenger Processing System (CUPPS)Ferndale has deployed all
the computers, printers and monitors for the Wayne County common use ticket counters and gates.
This includes baggage tags, airline tickets and scanners at each gate.
We also deployed CUSS (Common Use Self Service) kiosk stations.
Ground Transportation Center