+ All Categories
Home > Documents > Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling...

Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling...

Date post: 23-Dec-2015
Category:
Upload: vivian-rosaline-marsh
View: 213 times
Download: 1 times
Share this document with a friend
Popular Tags:
16
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1
Transcript

Fibres & copper Cabling activities

LIU meeting 27/09/2013

F Duval

27/09/2013 F Duval Cabling acxtivities LIU 1

What is cabling?

27/09/2013 F Duval Cabling acxtivities LIU 2

1. Contract Management2. Parc à Cable3. Cablotheque4. Preparation of the work

5. Cabling campaigns6. Infrastructure7. Radioprotection & radiation resistance

Contract management

27/09/2013 F Duval Cabling acxtivities LIU 3

• Based on a 3 years contract with one (or more) installation company

• Based on a DQE: every single operation and every single component are included in a price list.– Many options: tunnel, radioprotection, quantities– All administrative work is included

• Importance of the supervision (works and bills of quantities)

• New common infrastructure: who pays?• Strict control of the invoicing and payment process

Parc à Cable

27/09/2013 F Duval Cabling acxtivities LIU 4

• Providing cables needed for installation requests (CTRL & Power distribution)• Work together with CERN general store for standard cable procurement• Procurement of special (eg. radiation resistant) cables: 635 orders for LS1• Management of the cable transport (going to and coming from the work sites)• Rewinding in special drums (tunnel access, special lengths for specific work,

etc…)• Management of cable lifecycle (re-ordering levels, aging, copper recuperation,

etc.)

Cablotheque

27/09/2013 F Duval Cabling acxtivities LIU 5

• Database collecting all installed cables characteristics (length, type, routing, identification number, etc...)

• Interfaced with GESMAR (quotation, invoicing, etc...)• Updated by CERN and contractors (monitoring)• Essential tool for cleaning campaigns

Preparation of the work

27/09/2013 F Duval Cabling acxtivities LIU 6

• Defining (checking) the cable specification matching with the installation constrains (bending radius, UV resistance, radiation resistance, etc...)

• Defining (checking) the cable specification matching with the electrical requirements (current, voltage, etc.)

• Installing the necessary infrastructure (cable trays, ducts, etc…)• Setting up the necessary tooling and logistics.

Cabling campaigns

27/09/2013 F Duval Cabling acxtivities LIU 7

• Every user request is collecting by DIC or DIF, then site works have to be organised by geographical areas.

• Cost effective, easier scheduling, ALARA effective– Installation campaigns– Cleaning campaigns– Irradiated cable replacement campaigns

Infrastructure

27/09/2013 F Duval Cabling acxtivities LIU 8

• For fibres, the backbone (the common infrastructure) is now owned by EL

• The control cable business is not organized around a backbone Point-to-point installations Control cables (and related signals) are specific to each

system and therefore owned by users. • EL remains the expert for installation and removal.• Routing is defined by EL together with integration team

Radioprotection and radiation resistance

27/09/2013 F Duval Cabling acxtivities LIU 9

• EL is taking care of the whole radioprotection process (training, ALARA committee, dosimeter, protection suits, waste management) with RP and contractors

• EL is running research on radiation resistant components (e.g. fibres)

• EL is managing a WG (RIAC) on radiation effects on cables aiming at steering the future cable replacement campaigns.

Future: Constrains

27/09/2013 F Duval Cabling acxtivities LIU 10

• LS2 cabling activities will be much more than LS1

– Only small works or surveys can be done in the machines during Xmas breaks and technical stops

– Next step for bulky “underground” activities is LS2 – Cabling activities for LS1 were selected in a much

larger batch of requests– Postponed activities (mainly LIU, IT and EN/EL) +

already known projects for LS2 already represent more than a half of the LS1 workload

11

• SPS: regular replacement carried on until 2009 on a higher trend

Areas 1990 91 92 93 94 95 96 97 98 99 2000 01 02 03 04 05 06 07 08 09

TS1 All

TS2ZS/MST/

MSEAll

ZS/MST/Vac

Exc TCT Exc TCT

TCC2 All AA R

TDC2 All All

TS4 Part

TS6ZS/MST/

MSEExc TCT TCT Exc TCT

Vac exc TCT

TCT

TT60 All

TCC6 All

TNC All

TCT

Rem. ZS, Inst MKE

All

Cable volume

0

500

1000

1500

2000

2500

1992 93 94 95 96 97 98 99

2000 01 02 03 04 05 06 07 08

2009

Years

Cab

le q

uant

itie

s

0

50

100

150

200

Cable quantities

Tot length (km)

1 complete SPS point every shutdownReplacement foreseen every 5/6 years today every >10 years

TCT: Top cable tray, AA: Almost All, R: Rest, Part: Partial.

Future: irradiated cable replacement

27/09/2013 F Duval Cabling acxtivities LIU

12

Galleries

Shafts

Overloaded cable trays do not allow pulling cables in the proper technical way

This situation is general for SPS

In some cases, cables cannot be installed anymore

Future: Cleaning of overcrowded areas

27/09/2013 F Duval Cabling acxtivities LIU

13

PS ring centre

Gallery TP9Intersection Linac2-Linac4-PSB

Tunnel TT2

Future: Cleaning of overcrowded areas

27/09/2013 F Duval Cabling acxtivities LIU

14

Bld.361 (under the Booster), room BCER

Future: Cleaning of overcrowded areas

27/09/2013 F Duval Cabling acxtivities LIU

15

SPS machineCritical state 1:• Point 5 surface, shafts and underground• Point 4 surface, shafts and underground• Point 3 surface, shafts and underground

Critical state 3:• Point 6 surface, shafts and underground• Point 1 surface, shafts and underground• Point 2 surface, shafts and underground• Point 7 surface, shafts and underground

Critical state 5:• TT60, TT70

Shafts are the most critical areas for all points.

PS-Complex and Meyrin site Critical state 2: Bld.360-361 (under the Booster), rooms

BCER, BOR, BAT Bld.354, room CCR et MNR, gallery 815 Gallery TP9 between Bld.354 and Bld.361 Bld.353 (ring centre) and tunnel of PS Bld.350

accelerator TT2 entire tunnel (from Build. 269 to TT2A

towards nTOF)

Critical state 4: Bld.2001 (upstairs), cable connections from

Build.2008

Priorities for Cable Clean Up

Future: Cleaning of overcrowded areas

27/09/2013 F Duval Cabling acxtivities LIU

Future: requests

27/09/2013 F Duval Cabling acxtivities LIU 16

• Organising huge campaigns on a 5/6 year basis is a challenge (compentency management, Worlkload, contractors)– Having a LS1.5 (more than 4 months of actual

underground access) after only 1.5/2 years of operations will be very useful for EL

• Cleaning of SPS-P5 and Booster (mainly for LIU) areas is proposed by EL (TBC)

• Beyond the Cabling activities, the Low voltage distribution in PS/PSB has to be consolidated (e.g. safety issues)


Recommended