    ENGINEERING MANAGEMENT

    Project Name : AMHS INSTALATION

    Team Members:Ponnusamy Rajkumar (P1147117)

    Parameshwarn Prabhu ( P1147188)

    Nataraj Ranjithkumar (P1147360)

  • 8/13/2019 Final AMHS Project

    4/33

    ENGINEERING MANAGEMENT

    AUTOMATIC MATERIAL HANDING SYSTEM

    (AMHS)

    INSTALLATION OF AMHS IN SEMICONDUCTORINDUSTRY TO INCREASE PRODUCTIVITY

  • 8/13/2019 Final AMHS Project

    5/33

  • 8/13/2019 Final AMHS Project

    6/33

    Project Synopsis

    Initially with 200mm production capability of 4.3B,after we move 300mm increased our capacity by16% to reach 5B because 300mm can yield morechips at low cost.

    This project is to install AMHS in semiconductor fabdue to difficult in handling, transportation betweendepartment and storage of 300mm wafer

    This project budget is $800k

    With in 90days

  • 8/13/2019 Final AMHS Project

    7/33

    MISSION

    To install AMHS for easy handlingtransportation and storage in ThreeMonths period

    Challenges With out effecting current production Space Machines

  • 8/13/2019 Final AMHS Project

    8/33

    Introduction for Manufacturingprocess in Semiconductor

    Semiconductor Manufacturing is furtherdivided into two major steps

    Front End (45-60days to complete) Back End ( 15 days)

  • 8/13/2019 Final AMHS Project

    9/33

    Manufacturing steps at front end

    Cleanup

  • 8/13/2019 Final AMHS Project

    10/33

    Project Objects A) Build in Team B) Plan & Schedule C) Find Place and Clear Place D) Vendor E) Laying Electrical Ducts & Control Panels F) AMHS Erection F) Testing G) Sample Run H) Handover to Production

  • 8/13/2019 Final AMHS Project

    11/33

    Organize a Team

  • 8/13/2019 Final AMHS Project

    12/33

  • 8/13/2019 Final AMHS Project

    13/33

    Responsibility Matrix

  • 8/13/2019 Final AMHS Project

    14/33

    Plan & Schedule

    ACTIVITY TASKDURATION IN

    (DAYS) PREDECESSOR

    A PLAN 3

    B FIND AND CLEAR PLACE 5 A

    C SOURCE FOR VENDOR 10 B

    D PLACE ORDER AND SHIPMENT 16 B & C

    E FOUNDATION FOR AMHS 7 D

    FERECTION OF POWER DUCTS &

    DATA CONTROL PANNELS 10 E

    G AMHS INSTALLATION 20 E & F

    H TESTING AND COMMISIONING 5 G

    I SAMPLE RUN 7 H

    J RELEASE TO PRODUCTION 3 I

  • 8/13/2019 Final AMHS Project

    15/33

    AON (Activity-On-Node)

    0 3 3 A

    4 4 7

    3 5 8 B

    7 4 12

    8 10 18 C

    12 4 22

    18 16 34 D

    22 4 38

    34 7 41 E

    38 4 45

    41 10 51 F

    45 4 55

    51 20 71 G

    55 4 75

    71 5 76 H

    75 4 80

    76 7 83 I

    80 4 87

    83 3 86 J

    87 4 90

  • 8/13/2019 Final AMHS Project

    16/33

    Microsoft Excel Project Schedule

    TaskDuration in

    DaysStartDate

    End Date

    AMHS INSTALLATION 86 5-Mar-12 5-Jul-12

    Plan 3 5-Mar-12 7-Mar-12

    Find & Clear Place 5 8-Mar-12 14-Mar-12Source Vendor 10 15-Mar-12 28-Mar-12

    Order and Shipment 16 29-Mar-12 20-Apr-12

    Foundation for AMHS 7 23-Apr-12 2-May-12

    Erection of Electrical, Data & ControlPanels

    10 3-May-12 17-May-12

    AMHS Installation 20 18-May-12 14-Jun-12

    Testing and Commissioning 5 15-Jun-12 21-Jun-12

    Sample Run 7 22-Jun-12 2-Jul-12

    Release to Production 3 3-Jul-12 5-Jul-12

  • 8/13/2019 Final AMHS Project

    17/33

    Work breakdown structure(WBS)

  • 8/13/2019 Final AMHS Project

    18/33

    Costing Find place and clear $10k New machine $300K

    Installation $140K Contractor $100K Materials $200K Buffer $50K

  • 8/13/2019 Final AMHS Project

    19/33

    SWOT ANALYSIS

    Strength

    Good Teamwork Collogues with

    good Experience R&D No complaints

    form customer

    Weakness

    Lack of Machines Lack of quality

    staffs Not Globally

    recognized

    Opportunities

    New Leadership UP grading skills To expand

    company

    Treats

    Resignation ofstaffs Natural disaster Lose orders Economical crisis

  • 8/13/2019 Final AMHS Project

    20/33

  • 8/13/2019 Final AMHS Project

    21/33

    Layout : Over head tracks and storage

  • 8/13/2019 Final AMHS Project

    22/33

    Foundation For AMHS

  • 8/13/2019 Final AMHS Project

    23/33

  • 8/13/2019 Final AMHS Project

    24/33

    Tracks and Travelling units

    Over head Travelling vehicleOver head travelling tracks

  • 8/13/2019 Final AMHS Project

    25/33

    Over head Storage Racks along tracks

    Control

    Storage Location

  • 8/13/2019 Final AMHS Project

    26/33

    Integrated AMHS control system

  • 8/13/2019 Final AMHS Project

    27/33

    AMHS Control Units

    AMHS Storage and Processing Unit

  • 8/13/2019 Final AMHS Project

    28/33

    Project Achievement Lot Handling

    Before

    After

  • 8/13/2019 Final AMHS Project

    29/33

    Project Achievement Transportation between departments

    Before

    After

  • 8/13/2019 Final AMHS Project

    30/33

  • 8/13/2019 Final AMHS Project

    31/33

    Project Closing

    The close-out responsibilities of each team member

    Details of the tasks to avoid missing out

    Follow-up on the outstanding matters

    Check on the quality of the various jobs

    Perform final inspection with the team or contractors

    involved.

  • 8/13/2019 Final AMHS Project

    32/33

    We successfully converted to hi-tech fab with goodteam work and strength to achieve our goal with in90 days and within budget

    AMHS reduced human error and increasedproductivity

    With new investments 300 mm fab with hi-techcapacity expected to increase by 20% 2013

    Globally recognized

    Conclusion