+ All Categories
Home > Documents > Final Design Report - 2

Final Design Report - 2

Date post: 18-Feb-2017
Category:
Upload: cohen-poirier
View: 23 times
Download: 0 times
Share this document with a friend
59
Sol Searcher Team T3 Prepared For: Dr. Lukas Swan Prepared by: Cohen Poirier, Chris Newton, Bryan Ellis, and Qing Dong Due: April 6 th 2016
Transcript
Page 1: Final Design Report - 2

Sol SearcherTeam T3

Prepared For: Dr. Lukas SwanPrepared by: Cohen Poirier, Chris Newton, Bryan Ellis, and Qing Dong

Due: April 6th 2016

Page 2: Final Design Report - 2

Abstract

This report is intended to show the design process and results of the solar tracking system project completed. Referencing Dr. Lukas Swan's project introduction, the project purpose is defined as to build a solar tracking system operating on a condensed solar day while adhering to solar zenith, azimuth equations, and to use the final design in a class competition to pump as much water as possible. Unique to the final design referenced in this report is the solar azimuth tracking motion controlled by a compound gear system and solar altitude tracking motion controlled by a dual winch system. Through the design process, essential and important design requirements were created. Prototyping was an important part of the design process because it accelerated design reiteration and idea generation. Testing was completed in order to calibrate the mechanism of altitude motion and azimuth motion to be ready for competition. After competing, the final design was able to pump 1090 mL of water, finishing 12th place. These results are specific to solar tracking design referenced in the report. Upon completing the project, the final design was evaluated on how well it met the design requirements, and suggestions were made to improve the design. The final design was able to meet all of the essential requirements, but failed to meet some of the important requirements. It was suggested that more calibration be completed, and some tweaking to the compound gear system in order to improve the design.

i

Page 3: Final Design Report - 2

Table of Contents

List of Figures...............................................................................................................................iii

List of Tables.................................................................................................................................iv

1. Introduction................................................................................................................................1

1.1 Project Purpose....................................................................................................................1

1.2 Theoretical Background......................................................................................................2

2. Design Requirements.................................................................................................................4

3. Design Process............................................................................................................................5

3.1 Design Selection...................................................................................................................5

3.2 Data Collection.....................................................................................................................6

3.2.1 Altitude Rotation..........................................................................................................6

3.2.2 Azimuth Rotation..........................................................................................................8

3.3 Design Development............................................................................................................9

3.3.1 Support System.............................................................................................................9

3.3.2 Altitude Tracking........................................................................................................11

3.3.3 Azimuth Tracking.......................................................................................................13

4. Design Performance.................................................................................................................16

4.1 Design Evaluation..............................................................................................................16

4.2 Competition Performance.................................................................................................18

4.3 Proposed Corrections........................................................................................................18

5. References.................................................................................................................................19

Appendix A...................................................................................................................................20

ii

Page 4: Final Design Report - 2

List of FiguresFigure 1: Solar Azimuth and Altitude angle versus time………………………………………….3Figure 2: Solar Azimuth and Altitude angular velocity versus time……………………………...3Figure 3: Organization of Kit Contents…………………………………………………………...5Figure 4: Trigonometric Relationships of Altitude vs. Winch……………………………………7Figure 5: Comparison of Winch and Altitude……………………………………………………..8Figure 6: Half-Day Azimuth Angle vs Time……………………………………………………...9Figure 7: Panel Racking Assembly………………………………………………………...…….10Figure 8: Front view of the base support system assembly………………………..…………….10Figure 9: Top view of the base support assembly………………………………………………..11Figure 10: Altitude motor and winch assembly………………………………………………….11Figure 11: Detailed view of Altitude mechanism assembly…………………………………..…12Figure 12: Off-Set Winch………………………………………………………………………..13Figure 13: Gear Section Connection………………………………………………………..……13Figure 14: Azimuth System……………………………...………………………………………14Figure 15:Completed Azimuth System.......................................................................................15

iii

Page 5: Final Design Report - 2

List of TablesTable 1: Kit Contents……………………………………………………………………………...1Table 2: Desired Angular Velocity and Required Reduction…………………………………......9Table 3: Pinion and Gear Combinations………………................................................................14Table 4: Gear Section Arcs............................................................................................................15Table 5: Final Design Evaluation Based on Design Requirements and Performance...................16

iv

Page 6: Final Design Report - 2

1. Introduction1.1 Project PurposeWater is essential to everyday life from having showers, and washing dishes to the most basic aspects of survival. In remote locations access to this precious recourse is often limited, and off-grid power is required to transport water to the places it is needed. Photovoltaic modules are an excellent solution to produce electricity in remote locations for pumping water.

The purpose of this project was to design and build a solar tracking system, with the intention to optimize the energy output from the photovoltaic modules. The project includes the design of a solar tracking system, PV module racking system, and accommodation for electrical interconnections. Maximum electricity generation is achieved when the photovoltaic modules are perpendicular to the sun.

While design process began in early February, the materials to complete the task were not revealed until February 22nd. Table 1, from Dr. Swan’s Design Kit Contents list 2016, shows the contents of the kit delivered. The kit is broken into categories with a range of structural components, a limited amount of rapid prototype material, 4 PV modules and two Tamiya 6-speed gearboxes.

Table 1: Kit Contents

1

Page 7: Final Design Report - 2

1.2 Theoretical Background Maximum electrical energy and efficiency is achieved when a PV module is

perpendicular to the sun rays. Electric powered pumps are used to push water through a pipe, usually against gravity. The sun tracks across the sky differently each day of the year. Photovoltaic modules directly convert sunlight into electrical energy in a quiet and

renewable manner

Solar Tracking is governed by a series of mathematical equations that specify the location of the sun in the sky at a given time. These equations were provided by Dr. Lukas Swan’s Project Introduction [2] they are as follows:

𝛿=23.45×sin(360*(284+𝑛)/365) (1)

Where the angle of declination, 𝛿, is dependent on day of year, 𝑛, from 1 to 365.

𝜃𝑧=acos[sin(𝛿)*sin(𝜙) + cos(𝛿)*cos(𝜙)*cos(𝜔)] (2)

2

Page 8: Final Design Report - 2

Where 𝜃𝑧 is the solar zenith angle, which is dependent on the angle of declination, 𝛿, the latitude, 𝜙, and the hour angle, 𝜔. For this problem, the angle of declination is 23.45 degrees, the latitude of Halifax is 45 degrees, and the hour angle of 15 degrees per hour has been reduced to 1.5 degrees per second.

𝛼𝑠=90°−𝜃𝑧 (3)

Where 𝛼𝑠 is the altitude angle measured from the horizon to the sun, which dependent upon the solar zenith angle, 𝜃z.

𝛾𝑠=[(+1 IF 𝜔≥0), (−1 IF 𝜔<0)]×|acos(cos(𝜃𝑧)*sin(𝜙)−sin(𝛿)*sin(𝜃𝑧)*cos(𝜙))| (4)

Where 𝛾𝑠 is the solar azimuth angle, which is dependent upon the sign (+/-) of the hour angle, 𝜔, the solar zenith angle, 𝜃𝑧, the angle of declination, 𝛿, and the latitude of the location, 𝜙.

In order the most water, a design that keeps the face of the solar panels perpendicular to the light source at the focal point 24” above the base plate is preferred. In order to achieve maximum efficiency, the design should be able to track the sun as accurately as possible to keep the solar panels perpendicular to the sun’s light at any given time.

Based on equations 1 through 4, an excel spreadsheet was plotted that condensed a 24 hour day into 4 minutes. Figure 1 shows a plot time vs. altitude angle and time vs. azimuth angle superimposed on one another. From the information provided Figure 1 specifications in the designs could be made to meet the requirements stated. The PV cells need to be facing the light source to produce maximum power output. Moreover, Figure 1 shows that while the day may be 240 seconds in duration, there is only 155 seconds of sunlight. Since competition only includes the time of sunlight, design was completed accordingly.

3

Page 9: Final Design Report - 2

Figure 1: Solar Azimuth and Altitude angle versus time

Figure 2: Solar Azimuth and Altitude angular velocity versus time

4

Page 10: Final Design Report - 2

Figure 2 shows azimuth and altitude angular velocity versus time. Based on figures 1 and 2, it was agreed upon that the best method to track the movement of the sun would be to approximate the speed of the altitude angle as linear, and to produce a variable speed system for the azimuth angle.

2. Design RequirementsDesign was conducted under the following constraints as provided in by Dr. Lukas Swan’s Project Introduction [2] these are the most basic requirements for the design parameters.

Use only the materials in the kit. Have a 12” by 12” by ¾” plywood baseplate with nothing protruding below, and nothing

on the upper edge to allow for clamping. Use only fixed voltages on DC power supplies. The panels must not translate in any direction (X, Y, Z) more than 4” from the focal

point. Design based on a 4 minute solar day. The effective competition day is Jun 21 in Halifax NS (𝝋 = 45°), which is day n = 172.

From these basic requirements, two categories were made to provide additional requirements to help in the design and construction phases. Broken into two categories, essential and important requirements.

Essential Requirements Important Requirements

Free standing on the provided base Variable speed about the altitude and azimuth directions

Two axis of rotation, independently or together

Simple design, for ease of construction and testing

Must have approximately 240 degrees of rotation about the azimuth

Accurate tracking of solar angles

Must have approximately 70 degrees of rotation about the altitude

Strong design that is robust and sturdy to account for possible real world weather conditions

Accommodation for electrical interconnections

Ascetics

5

Page 11: Final Design Report - 2

3. Design Process3.1 Design SelectionFrom the onset of design development, material usage was to be prioritized and initial design was conducted accordingly. Figure 3 shows the organization of the kit contents upon receiving the kit. Close attention to material availability and exhaustion was to be kept in mind through the building, and reiteration of the design process.

Figure 3: Organization of Kit Contents

From the beginning of the design process, three separate design categories were created, they are as follows: Azimuth motion, altitude motion, and support system. Several designs were produced for each category, and each design was evaluated based on a design selection matrix that corresponded to each category. The frame mount that was initially chosen for the frame design was a feasible design when the kit was received. However, the rack design still had to be slightly altered. The goal was to produce a support design that used the least amount of material to provide the most stable and clean design.

6

Page 12: Final Design Report - 2

To track the solar altitude motion, a system that allowed the panels to start in a vertical orientation, decline back to about 29 degrees from the horizontal, and then incline back to the vertical orientation was needed. The chosen winch design, after some alterations, was the most feasible choice with the items available in the kit. The theory of the altitude control is that each winch has a set amount of string, to start the string is fully wound around the spool and as it starts operation the string is let out, the counter force pulls the panels back keeping tension on the string. Once all the string has been released, as a result of it being fixed to the winches it begins winding itself up pulling the panels back down against the counter force.

In order to track azimuth motion, a variable speed system was required, preferably one that is able to mirror itself after midday as the function describing the azimuth motion is mirrored about the halfway point. The original selected design would make use of a rack and pinion system with different levels to mesh at specific times. After review, it was decided that this would require far too much material. Instead of having a long pinion system, a tree of gears would cause rotation of the azimuth. A compound pinion would require much less room and a rack and would still provide the same variability as the original idea.

3.2 Data CollectionImportant information to consider when designing the components for the solar altitude and azimuth tracking mechanisms are the specifications of the Tamiya 6-Speed Gearboxes provided. From the speeds at which the components need to operate in combination with the approximated RPMs found on a Tamiya specification sheet [1], the motors must turn as slow as possible. The recommended operating range of the motors is 1.5V – 4.5V, providing a range of 6300 to 9400 un-loaded RPMs. Therefore, the components should be designed to operate within these specifications with some room for adjustment. As an example at 1.5V if the motors are set up as intended on the ratio of 1300.9:1 the output will be close to 5 RPM without load.

3.2.1 Altitude RotationTo solve the altitude parameters a relationship between the height of the winch (L), length of the rope at given time (l), and altitude angle (a). As shown in Figure 4 the focal point is where the arrow hits the black line, and based on trigonometric relations the inside angle was also found to be the parameter (a).

7

Page 13: Final Design Report - 2

Figure 4: Trigonometric Relationships of Altitude and Winch

In order to relate the length of the string to the altitude angle it was necessary to introduce variables to find and equate relationships.

L = y + z (5)

Where L is the length of a PV module, y is the vertical distance from a tilted panel’s bottom edge to the focal point, and z is the difference between L and y.

b = Lsin(a) (6)

Where b is the horizontal distance from the vertical axis to the bottom edge of the title panel, and a is the altitude angle.

Y = Lcos(a) (7)

Where y is the vertical distance between the tilted panel’s bottom edge from the focal point, and a is the altitude angle.

L = √ z2+b2 (8)

Where l is the distance from the bottom edge of the tilted panel to its vertical projection.

By finding angular velocity and because it was known that the winch will have some radius, R, rotating at a frequency f , in revolutions per second, the length of rope as a function of time could be found.

l=2 πfRt (9)

8

Page 14: Final Design Report - 2

From equations (5), (6), (7), and (8) altitude angle in terms of length was found to be;

a=cos−1(¿1− (2 πfRt )2

2 L2 )¿(10)

Figure 5: Comparison of Winch and Altitude

By plotting this equation in excel variables could be manipulated in order to find a frequency and radius that fit the requirements. Taking into account the need to be operating around 5 rpm, the winch will have a diameter of 2cm, placed 30 cm down the stand from the focal point. Figure 5 shows the approximated altitude position of the sun as a function of time (in red), compared to the actual altitude position of the sun as a function of time (in blue).

3.2.2 Azimuth RotationThe azimuth pathing of the sun presents a different set of challenges; requiring more variable speeds but only in one direction. Also, the azimuth path function mirrors itself beginning at noon. This means that to determine required angular velocities only half of the graphs shown in figure 1 and 2 need to be considered. Analyzing the first half of the solar day, it was determined that there were three distinct regions where the velocity could be approximated as linear without significant losses in accuracy. Figure 6 shows the plot of azimuth angle vs time for the first half of the solar day. Also shown are the linear approximations for the three distinct sections.

9

Page 15: Final Design Report - 2

40 50 60 70 80 90 100 110 120

-140

-120

-100

-80

-60

-40

-20

0

20

f(x) = 3.31520469828467 x − 398.932733579389

f(x) = 1.88008344419194 x − 245.895221203326

f(x) = 1.02672701914146 x − 168.575821774539

Time (s)

Azim

uth

Angl

e (d

eg)

Figure 6: Half-Day Azimuth Angle vs Time

Rounding the velocities to one decimal place, estimates of 1, 1.9 and 3.3 deg/s were used for design purposes. Using an estimated motor input of 5 deg/s the input reduction from motor to shaft was calculated and is presented in Table 2.

Table 2: Desired Angular Velocity and Required Reduction

Motor Speed (deg/s) Desired Shaft Speed (deg/s) Required Reduction5 1 55 1.9 2.635 3.3 1.52

3.3 Design Development3.3.1 Support System To support the combined weight of the PV modules a mount made of the ½” plywood (Figure A-11) was used in the center. This support reached up higher on panels above and below the center axis offering back support this was connected to the existing holes in the PV panels. Additional panel connection wood was added made of ¼” plywood (Figures A-8, A-9) connected along the central axis fastening the panels above and below together. On the top and bottom of the modules two slender basswood panel connection (Figure A-10) pieces were used that served dual purposes. Each piece fastened adjoining left and right panels together, the bottom piece also severed as an attachment for the altitude string and the top for the elastic band counter pull. Basswood was used as altitude pivot joint (Figure A-12) connecting the modules to the PVC

10

Page 16: Final Design Report - 2

shaft. In order for the modules to rotate around the shaft about the altitude direction the small PVC was used as an axel fitting through the shaft that was centered between both basswood pivots. Figure 7 shows the assembly of the racking components.

Figure 7: Panel Racking Assembly

For the base support system shown in figures 8 and 9, three triangle legs (Figure A-16) optimized stability while leaving room for the azimuth motor to be installed and driven. The three support legs attached to a square guide (Figure A-15) a portion of the way up the shaft to prevent the structure from tipping from the weight of the panels. Attached to the baseplate (Figure A-6), was a circular guide (Figure A-7) which would contain ball bearings allowing for ease of rotation about the vertical axis.

Figure 8: Front view of the base support system assembly

11

Page 17: Final Design Report - 2

Figure 9: Top view of the base support assembly

3.3.2 Altitude TrackingAs dictated by the calculations for the altitude system the winch control is mounted on the ABS shaft (Figure A-1) the same distance down as the height of a single PV cell. The winch system contains two spools that are mounted directly to either side of the drive shaft of the Tamiya motor. The motor is mounted onto a small piece of ¼” plywood screwed directly into the ABS shaft, the assembly of the altitude system can be seen below in Figure 10. The Altitude system contains two parts, a counter force in the form of two elastic bands and the winch control, both can be seen below in Figure 11.

Figure 10: Altitude motor and winch assembly

12

Page 18: Final Design Report - 2

Figure 11: Detailed view of Altitude mechanism assembly

The counter force mechanism is a long piece of basswood (Figure A-4) mounted off the back of the shaft near the top, the length of the basswood functions as a moment arm. Two elastic bands are mounted to the end of the basswood which are secured by squeezing the elastic bands between two pieces of ¼” plywood (Figure A-5) on either side of the moment arm by tightening two nuts. The same method of connection is used to fasten the elastic bands to the top of the panels.

The winch system is made up of two spools, each comprised of two spool caps (Figure A-14), and one spool center (Figure A-15). Initially it was intended to reduce torqueing the motor on the PVC shaft left or right but after construction it was found they served a better purpose. At the top of the altitude cycle when the panels are in the fully declined position, because of the size of each spool, as the string winds there was a section of delay causing the panels to pause at the top. The string would release tension and take half a turn to return to tension in order to pull the panels down. To fix this problem the string was off set on each winch, one at the top and one at the bottom. Figure 12 illustrates the off-set, the blue dots represent where the strings are fixed to each winch. This resulted in the string of one spool being under tension on the way out while the other’s string was slack being half a rotation ahead. When maximum altitude was reached, the spool that was initially slack immediately started to pull back down effectively eliminating the delay. To fasten the string to the bottom of the panel two small pieces of ¼” plywood were used to fix two pulleys off of the panels. This was done in order to cause the string to always pull downward, instead of at an angle, reducing torque on the motor.

13

Page 19: Final Design Report - 2

3.3.3 Azimuth TrackingTo estimate the azimuth path, a system of gears was developed to provide three unique speeds that were mirrored halfway through the run. To do this, three pinions (Figures A-18 to A-20) would be used to mesh at specific points with gear sections (Figures A-21 to A-23) attached to central ABS shaft of the structure. Since the gear sections share a center point with the pipe they

also have the same angular velocity. To attach the gear sections to the pipe, 1564 inch holes were

drilled into the pipe which allowed a tight fit for the section plug as seen in Figure 13.

Figure 13: Gear Section Connection

The holes were spaced so that the gear sections would not overlap vertically or horizontally. Vertical spacing allowed for the gears to only mate with the desired pinions and avoid contacting

Figure 12: Off-Set Winch Representation

14

Page 20: Final Design Report - 2

larger pinions as seen in Figure 14, horizontal spacing can prevent sticking when transitioning to the next gear section.

Figure 14: Azimuth System

Because the sections are extensions of the shaft, they needed to be able to fit inside the structural supports. This meant that the gear sections would have a maximum outer radius equal to the radius of the central support circle (Figure A-7) and a minimum base radius equal to the radius of the ABS shaft (Figure A-1). The system designed accomplishes this, with a maximum size gear section having an outer radius of 47 mm and the smallest gear having a base radius of 23.81 mm. Gears and pinions design were driven by the results of the first section consisting of the smallest pinion (Figure A-18) and largest gear section (Figure A-21). Since the center to center distance for all levels of the gear system had to be the same the lower sections had to adhere to this restriction, requiring the system to deviate from the desired velocity reductions. Table 3 highlights the resulting gear and pinion combinations as well as the desired reduction and designed reduction.

Table 3. Pinion and Gear Combinations

Tier Pinion Diameter (mm)

Gear Diameter (mm)

Desired Reduction

Actual Reduction

1 (Figure A-18 and A-21)

18 90 5 5

2 (Figure A-19 and A-22)

32 76 2.63 2.375

3 (Figure A-20 and A-23)

42 66 1.52 1.57

The length of each tier section was determined by referencing the half day angle vs time graph (Figure 6). From this the desired amount of rotation at each speed can be determined. For example, the first speed rotates the shaft for the first ~53 deg and so the desired arc of the gear

15

Page 21: Final Design Report - 2

section for speed one is 53 degrees. To ensure proper functioning, angles were adjusted so that there were full gear teeth for each section. Table 4 summarizes the final gear section arcs for the three speeds.

Table 4. Gear Section Arcs

Section Desired Arc (deg) Actual Arc (deg)1 53 55.62 26 203 44 45Total 123 120.6

All values in Table 4 represent half of the solar day; Sections one and two were doubled by using two separate but identical gear sections (Figures A-21 and A-22) and section three was created as one gear section (Figure A-23). This resulted in a total rotation capability of roughly 241 degrees

Because the output speed motor was much higher than 5 deg/s a separate pinion (Figure A-24) and gear (Figure A-25) were developed. The motor reduction pinion was attached directly to the motor shaft using a nut and epoxy. The motor reduction gear was glued to the bottom of the compound gear tree and served as the base as seen in figure 14. This reduction system had fewer restrictions and was able to reduce the angular velocity from 1/3 of the motor shaft speed.

Figure 15. Completed Azimuth System

16

Page 22: Final Design Report - 2

Once complete, the motor reduction gear and the three tier pinions were aligned with a 3/16 piece of dowel placed through a hole in their respective centers and glued together with epoxy as seen in Figure 14 and 15. The dowel was glued into a structural support which also held the motor in the proper position to transmit power as seen in figure 15. The base is positioned so that the center of the pinions is the required 54 mm from the center of the ABS pipe.

4. Design Performance4.1 Design Evaluation

Criteria Azimuth Altitude Structural Components

Overall Build

Simplicity 2 4 4 3.3Size 5 4 4 4.3Robustness 4 3 4 3.7Accuracy 3 3 N/A 3

Performance N/A N/A N/A 1090 mL67% of maximum

Table 5: Final Design Evaluation Based on Design Requirements and Performance

Table 5 shows how the design was evaluated based on the requirements that were outlined as important at the beginning of the project, evaluated by 4 categories simplicity, size, robustness and accuracy. The requirements are restated from section 2 below. Each criteria is weighted evenly and the score given in the overall build category is an average of the three scores given each design category of azimuth, altitude and structural components.

Essential Requirements Important Requirements

Free standing on the provided base Variable speed about the altitude and azimuth directions

Two axis of rotation, independently or together

Simple design, for ease of construction and testing

Must have approximately 240 degrees of rotation about the azimuth

Accurate tracking of solar angles

Must have approximately 70 degrees of rotation about the altitude

Strong design that is robust and sturdy to account for possible real world weather conditions

Accommodation for electrical interconnections

Ascetics

17

Page 23: Final Design Report - 2

Of the essential requirements, every goal was met. The design had dual axis tracking in the azimuth and the altitude, it was free standing and had the ability to support the weight of the solar panels with ease. Accommodation was also made for the electrical interconnections. Each aspect support system, altitude and azimuth met the important requirements differently and are as follows.

The rack and support system design is strong, while using minimal materials. Each panel has three connections of support resulting in a sturdy design without the need to drill into the aluminum to attach the panels together. The basswood panel connection supports (Figure A-10) at the top and bottom are an efficient use of material as they serve to as structural pieces and are essential in the performance of the altitude. The base could be more stable by adding a fourth leg, this was a tradeoff made because the space was needed to mount and drive the azimuth control. The design was created with a smart use of materials and even without the fourth leg, it was an extremely robust end product. The support system was simple, clean and ascetically pleasing.

The winch design was simple taking up minimal room on the shaft of the ABS pipe. The spools were relativley easy to construct and the elastic counter force mechanism proved to be a simple solution instead of using springs or a counter weight. By mounting the spools directly to the motor, space was reduced, but at a tradeoff. The tradeoff being that the only way to slow down the altitude tracking was to change the voltage supplied to the motor or to change the size of the spools, as the design provdied no room for gear reduction. Another aspect of this tradeoff is that because there was no reduction, the motor was required to handle all the torque directly. Secondly, two spools were initially introduced to reduce the force on one side or the other of the motor so that it could pull and release evenly. However, since there was a delay section at noon in the solar day, it was found that accuracy could be improved if the points where the strings were fastened were offset one at the top and bottom. Despite these concerns, the design proved strong enough to handle the uneven stresses. For the accuracy the altitude had full the full range of motion required, but only accunted for linearly approximated speed. Because of this aspect some accuracy was sacraficed.

The lack of accuracy in following the azimuth is likely due to a mix of some tradeoffs to the design process as well as limitations of motor speeds available for competition. During the design process some errors were predicted because the gear system can only produce linear speeds. It was predicted that this would cause some error but that the approximations would not cause significant losses to production. The problem with the linear speeds was increased by the design decision to only use one diametric pitch for the gears for simplicity. Because of this limitation and the limitation of center to center distance there was designed error between the three estimated speeds for the path and the ones produced from the design. Finally, the gear design requires a specific motor output in order to function correctly. The designed system was produced before fully determining what speeds would be available over the range of voltages to the motor. This oversight meant that there needed to be a decision about whether to rotate slightly too fast or too slow, resulting in more error during competition.

18

Page 24: Final Design Report - 2

4.2 Competition PerformanceDuring competition, each group was given two attempts to pump the most water possible. The final design referenced in this report pumped 790 mL on the first attempt, followed by 1090 mL on the second attempt, placing 12th in the competition. For the first run the panels’ electrical connections were improperly done resulting in only three panels working for the first attempt. This is a result of not testing with the water pump prior to the competition day. In the second attempt the voltages used allowed the design to more accurately track the sun with all four panels producing electricity. Overall the design could have performed better if more testing had been done. In the last column of Table 5 the evaluation of the final design based on the initial design requirements and competition performance is shown. The last category is for overall performance and presents how the outlined design did in competition.

4.3 Proposed CorrectionsIn order to improve the final design especially performance, more testing and calibration was needed. Additionally, tracking accuracy was limited due to minor inconsistencies between the azimuth and altitude components compared to the theoretical goals. Moreover, because of the nature of the design for each component only linear approximations for the speeds were provided. An average score of 3 for accuracy in the overall build category of Table 5 reflects these aspects. Extensive calibration and testing would have helped to mitigate these issues, providing more time to change the tracking components accordingly. Since both aspects were approximated however even with extensive testing the design never had the capacity to achieve perfect results, the only way to change this would be to go with a different design.

For the azimuth system the most significant improvement to be made to the design would be to further explore different diametric pitch options to better match the calculated estimates for angular velocity. Changes to the diametric pitch allows for more potential reductions while maintaining the same center to center distance to the pipe. Another improvement to the azimuth would be to further explore output speeds of the motor and creating a different set of gears for an initial reduction that produced a compound pinion angular velocity of 5 degrees per second. Finally, adding more tiers to the compound pinion and gear section design may produce a more accurate model as more linear divisions of the curve will be closer to following the true curve. The main constraint of the number of tiers is that the transitions between levels can be difficult to produce consistently and more tiers would require more materials compared to minimal increases in performance.

19

Page 25: Final Design Report - 2

5. References[1]  Mabuchi Motors. RE-260RA Data Sheet [Online]. https://www.pololu.com/file/download/re_260ra.pdf?file_id=0J17 [2]  Dr. Lukas Swan. 2016. Project Introduction - 2016.docx. 

20

Page 26: Final Design Report - 2

Appendix A

Figure A-1: ABS Support Rod

21

Page 27: Final Design Report - 2

Figure A-2: Azimuth Motor Support block

22

Page 28: Final Design Report - 2

Figure A-3: Azimuth Motor Triangle Support

23

Page 29: Final Design Report - 2

Figure A-4: Band Extension Wood

24

Page 30: Final Design Report - 2

Figure A-5: Band Securing Wood

25

Page 31: Final Design Report - 2

Figure A-6: Baseplate

26

Page 32: Final Design Report - 2

Figure A-7: Circular Base Support

27

Page 33: Final Design Report - 2

Figure A-8: Panel Connection Wood 1

28

Page 34: Final Design Report - 2

Figure A-9: Panel Connection Wood 2

29

Page 35: Final Design Report - 2

Figure A-10: Panel Connection Wood 3

30

Page 36: Final Design Report - 2

Figure A-11: Plywood Mount

31

Page 37: Final Design Report - 2

Figure A-12: Altitude Pivot Joint

32

Page 38: Final Design Report - 2

Figure A-13: Spool Center

33

Page 39: Final Design Report - 2

Figure A-14: Spool Cap

34

Page 40: Final Design Report - 2

Figure A-15: Square Support Wood

35

Page 41: Final Design Report - 2

Figure A-16: Triangular Wooden Supports

36

Page 42: Final Design Report - 2

Figure A-17: PVC Altitude Pivot Axis

37

Page 43: Final Design Report - 2

Figure A-18: Tier One Pinion

38

Page 44: Final Design Report - 2

Figure A-19: Tier 2 Pinion

39

Page 45: Final Design Report - 2

Figure A-20: Tier 3 Pinion

40

Page 46: Final Design Report - 2

Figure A-21: Tier One Gear Section

41

Page 47: Final Design Report - 2

Figure A-22: Tier Two Gear Section

42

Page 48: Final Design Report - 2

Figure A-23: Tier Three Gear Section

43

Page 49: Final Design Report - 2

Figure A-24: Motor Reduction Pinion

44

Page 50: Final Design Report - 2

Figure A-25: Motor Reduction Gear

45

Page 51: Final Design Report - 2

Figure A-26: Fully Assembled Solar Tracking System

46


Recommended