+ All Categories
Home > Documents > FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at...

FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at...

Date post: 14-Sep-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
108
PERFORMANCE-BASED REMEDIATION Site SS023 Corrective Measures Implementation Report BEALE AIR FORCE BASE, CALIFORNIA Project No.: BAEY20147501PB Contract No.: FA8903-09-D-8557 Task Order: 0003 Submitted to: JULY 2015 Submitted by: EN0224151019SAC FINAL
Transcript
Page 1: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

P E R F O R M A N C E - B A S E D R E M E D I AT I O N Site SS023 Corrective Measures Implementation Report

BEALE AIR FORCE BASE, CALIFORNIAProject No.: BAEY20147501PB Contract No.: FA8903-09-D-8557 Task Order: 0003

Submitted to:

JULY 2015

Submitted by:

EN0224151019SAC

FINAL

Page 2: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Beale Air Force Base, California Final Site SS023 Corrective Measures Implementation Report  Distribution List 

  Electronic  Document Number Air Force 

Kent Hawley, P.E.    F_SS023_CMI‐001 (CD‐ROM) AFCEC/CZO    F_SS023_CMI‐002 (CD‐ROM) 6601 B Street, Bldg 2561    F_SS023_CMI‐003 Beale AFB, CA  95903‐1708 

Darren Rector  CD‐ROM AFCEC/CZO – Portage, Inc. 6601 B Street, Bldg 2561 Beale AFB, CA  95903‐1708 

David Leeson  CD‐ROM HQ AFCEC/CZRW, Bldg 171  Work Phone: (210) 395‐0641 3515 S. General McMullen San Antonio, TX  78226‐2018 

Ana Jimenez ([email protected])    Submittal letter only via e‐mail AFCEC/772 ESS/PKB Work Phone: (210) 395‐8761 2261 Hughes Avenue, Suite 163 JBSA Lackland, TX  78236‐9853 

Marc Trost ([email protected])    Electronic transmission via e‐mail AFLOA JACE/FSC, Bldg 171 Work Phone: (210) 395‐8973 3515 S. General McMullen San Antonio, TX  78226‐2018 

Bill Hall  CD‐ROM HQ AFCEC/CZRW, Bldg 171  Work Phone: (210) 395‐0703 3515 S. General McMullen San Antonio, TX  78226‐2018 

Lora Gaitwood‐Smith ([email protected])    Submittal letter only via e‐mail AFCEC/772 ESS/PKB Work Phone: (210) 395‐8723 2261 Hughes Avenue, Suite 163 JBSA Lackland, TX  78236‐9853 

ERPIMS Data Support Desk ([email protected])    Electronically by CDUT AFCEC/CZRA, Bldg 171 3515 S. General McMullen San Antonio, TX  78226‐2018 

Shannon Garcia, Ph.D.  CD‐ROM HQ AFCEC/CZTE, Bldg 171 Work Phone: (210) 395‐0668 3515 S. General McMullen San Antonio, TX  78226‐2018 

Page 3: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Beale Air Force Base, California Final Site SS023 Corrective Measures Implementation Report  Distribution List 

  Electronic  Document Number 

Maria Melendez ([email protected])    Submittal letter only via e‐mail AFCEC/CZRW, Bldg 171 Work Phone: (979) 968‐5554 2261 Hughes Avenue, Suite 163 Lackland, TX  78236‐9853 

Regulatory 

Dominique Forrester, P.E.  CD‐ROM  F_SS023_CMI‐004 Department of Toxic Substances Control Office of Military Facilities  Northern California Operations  8800 Cal Center Drive  Sacramento, CA  95826 

Mark W. Clardy, P.G.  CD‐ROM Regional Water Quality Control Board Central Valley Region 11020 Sun Center Drive, Suite 200 Rancho Cordova, CA  95670‐6114 

John R. Hart, P.E. ([email protected])    Submittal letter only via e‐mail Department of Toxic Substances Control Office of Military Facilities  Northern California Operations  8800 Cal Center Drive  Sacramento, CA  95826 

Terry Escarda, P.E. ([email protected])    Submittal letter only via e‐mail  Department of Toxic Substances Control Office of Military Facilities Northern California Operations 8800 Cal Center Drive Sacramento, CA  95826 

Page 4: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Beale Air Force Base, California Final Site SS023 Corrective Measures Implementation Report  Distribution List 

  Electronic  Document Number 

CH2M HILL 

Jay Wilburn/CH2M HILL, SAC    Submittal letter only via e‐mail Eric Burrell/CH2M HILL, ATL    Submittal letter only via e‐mail Martin Barackman/CH2M HILL, RDD    Submittal letter only via e‐mail Peggy Taylor/CH2M HILL, SAC (Library)  CD‐ROM  F_SS023_CMI‐005 Shandon Sands/CH2M HILL, Beale AFB Office   CD‐ROM   Kenna Hunt/CH2M HILL, RDD (Library)  CD‐ROM  F_SS023_CMI‐006 Brad Shearer/CH2M HILL, RDD  CD‐ROM  F_SS023_CMI‐007 Katie Rhoades/CH2M HILL, NJO    Submittal letter only via e‐mail Gail Rich/CH2M HILL, RDD    Submittal letter only via e‐mail Karen Kocher/CH2M HILL, AUS    Submittal letter only via e‐mail 

Page 5: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

CH2M HILL 

2485 Natomas Park Drive,  

Suite 600 

Sacramento, CA  95833‐2937 

Tel (916) 920‐0300 

Fax (916) 920‐8463 

July 14, 2015 

456998.09.22.CL.02 

Mr. David Leeson HQ AFCEC/CZRW 3515 S. General McMullen San Antonio, TX  78226‐2018 

Subject:  Beale Air Force Base, California Performance‐based Remediation Final Site SS023 Corrective Measures Implementation Report Sub‐CLIN: 0009CL Sub‐sub‐CLIN: NA Payment Milestone No.: 2 Payment Milestone: AF/Regulator Approval of Final CMI Report Project No.: BAEY20147501PB File Plan No.: 17‐A‐211 Contract No.: FA8903‐09‐D‐8557 Task Order: 0003 

Dear Mr. Leeson: 

This letter documents the submittal of the Final Site SS023 Corrective Measures Implementation Report for Beale Air Force Base, California. This submittal satisfies Sub‐CLIN: 0009CL, Sub‐sub‐CLIN: NA, Payment Milestone No.: 2 – AF/Regulator Approval of Final CMI Report, Task Order: 0003. 

Copies of this document have been delivered to the individuals included on the attached distribution list. 

Regulatory concurrence on this Final document is requested by Friday, August 14, 2015. 

If you have any questions concerning this submittal, you can contact me at (916) 286‐0248. 

Sincerely, 

CH2M HILL 

D. Jay Wilburn Project Manager 

Enclosures 

SAC\TO0003_SS023_CMI_SubmittalLetter.docx  

Page 6: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Final

Beale Air Force Base, California

Site SS023 Corrective Measures Implementation Report

Sub-CLIN: 0009CL Sub-sub-CLIN: NA

Prepared for

Air Force Civil Engineer Center

Contract No.: FA8903-09-D-8557 Task Order: 0003

Project No.: BAEY20147501PB

Prepared by

Document No.: F_SS023_CMI-elec

July 14, 2015

2485 Natomas Park Drive, Suite 600 Sacramento, California 95833

Page 7: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

REPORT DOCUMENTATION PAGE Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Washington Headquarters Services, Directorate for information Operation and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. 1. AGENCY USE ONLY (Leave blank) 2. REPORT DATE

July 14, 2015

3. REPORT TYPE AND DATES COVERED

Final Site SS023 Corrective Measures Implementation Report (June 2014 - March 2015)

4. TITLE AND SUBTITLE

Beale Air Force Base, California Performance-based Remediation Final Site SS023 Corrective Measures Implementation Report Sub-CLIN: 0009CL Sub-sub-CLIN: NA Payment Milestone No.: 2 Payment Milestone: AF/Regulator Approval of Final CMI Report Task Order: 0003

5. FUNDING NUMBERS

Contract No.: FA8903-09-D-8557

Project No.: BAEY20147501PB

6. AUTHOR(S)

CH2M HILL (Katie Rhoades) 7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES)

CH2M HILL 2485 Natomas Park Drive, Suite 600 Sacramento, CA 95833

8. PERFORMING ORGANIZATION REPORT NUMBER

456998.09.22.CL.02

9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES)

HQ AFCEC/CZRW 3515 S. General McMullen San Antonio, TX 78226-2018

10. SPONSORING/MONITORING AGENCY REPORT NUMBER

11. SUPPLEMENTARY NOTES

12a. DISTRIBUTION/AVAILABILITY STATEMENT

Statement A: “Approved for Public release: distribution is unlimited.”

12b. DISTRIBUTION CODE

13. ABSTRACT (Maximum 200 words) This Corrective Measures Implementation (CMI) Report for Site SS023, Beale Air Force Base, California, summarizes the optimization of the interim corrective measures and documents that the final remedy is in place at Site SS023. This work is being conducted at Beale AFB, California (Task Order 0003; Project No.: BAEY20147501PB; Contract No.: FA8903-09-D-8557). 14. SUBJECT TERMS

Final Site SS023 Corrective Measures Implementation Report

15. NUMBER OF PAGES

One volume 16. PRICE CODE

17. SECURITY CLASSIFICATION OF REPORT

Unclassified

18. SECURITY CLASSIFICATION OF THIS PAGE

Unclassified

19. SECURITY CLASSIFICATION OF ABSTRACT

Unclassified

20. LIMITATION OF ABSTRACT

Unlimited

Page 8: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

F i n a l

Site SS023 Corrective MeasuresImplementation Report

Beale Air Force Base, California

Prepared for

Air Force Civil Engineer Center

July 2015

2485 Natomas Park DriveSuite 600

Sacramento, CA 95833

Page 9: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT ES-1EN0224151019SAC/456998

Executive Summary

This Corrective Measures Implementation (CMI) Report for Site SS023, Beale Air Force Base, California,summarizes the optimization of the interim corrective measures and documents that the final remedyis in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordancewith the Site SS023 Statement of Basis / Corrective Measures Implementation Work Plan (Work Plan)(CH2M HILL, 2014). No further action was selected for soil and soil vapor. In situ chemical oxidation (ISCO),enhanced attenuation (EA), and land use controls (LUCs) were selected for groundwater. Trichloroethene(TCE) and tetrachloroethene (PCE) were identified as contaminants of concern (COCs) in groundwater.

This report is being prepared by CH2M HILL for the Air Force Civil Engineer Center under the WorldwideEnvironmental Restoration and Construction Contract No. FA8903-09-D-8557, Task Order 0003.

Corrective Measure ObjectivesThe site-specific objectives at Site SS023 are to reduce concentrations of COCs in underlyinggroundwater originating at Site SS023 (Figure ES-2) to support restoration of groundwater, to restrictpotential exposure to COCs in groundwater, and to comply with state Resource Conservation andRecovery Act requirements. TCE and PCE levels in underlying groundwater will be reduced to allow forunlimited use/unrestricted exposure, which support the restoration of groundwater to designatedbeneficial uses (domestic, municipal, agricultural, and industrial supply).

Corrective Measure ImplementationThe remedy implemented at Site SS023 consists of three main components: ISCO, EA, and LUCs.To implement the ISCO portion of the remedy, four injection wells were constructed and developed inJune 2014, baseline sampling was conducted, sodium permanganate was injected into new and existingwells, and monitoring was performed from November 5, 2014, to January 23, 2015. During the baselinesampling event (July 2014), the highest TCE concentration was detected in a groundwater samplecollected from injection well SWMU23C016IW with a TCE concentration of 564 micrograms per liter(µg/L) (Figure ES-3). Groundwater samples collected from the new injection wells near Doolittle Drive(SWMU23C015IW, SWMU23C016IW, and SWMU23C017IW) contained TCE concentrations ranging from54 to 564 µg/L. The detection of TCE in groundwater collected from these wells further confirms thatthere is a residual TCE mass in groundwater beneath Doolittle Drive (upgradient of the ozone/air spargesystem). EA involves groundwater monitoring downgradient from the ISCO treatment zone and will bedocumented in the Basewide Groundwater Monitoring Program Reports. LUCs were implemented toprevent exposure to groundwater containing COCs at concentrations greater than the cleanup levels.

Monitoring PlanAfter injection, performance monitoring will be conducted semiannually to assess the long-termeffectiveness of the ISCO and EA remedies. Compliance monitoring will be conducted for 1 year or untilobjectives of the Monitoring and Reporting Program (MRP) have been met. Exceedances of baselineconcentrations in a downgradient compliance monitoring well would indicate an adverse impact togroundwater outside the transition zone. A contingency plan has been developed to provide a generaloverview of efforts that the U.S. Air Force would take to address exceedances of dissolved chromium,dissolved manganese, or permanganate at concentrations greater than twice baseline concentrations indowngradient compliance monitoring wells.

Page 10: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

EXECUTIVE SUMMARY

ES-2 SITE SS023 CMI REPORTEN0224151019SAC/456998

Works CitedCH2M HILL. 2014. Site SS023 Statement of Basis / Corrective Measures Implementation Work Plan.Prepared for Beale Air Force Base, California. Final. September.

Page 11: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SIT E 3 3

UPPERBLACKWELDER

LAKE

FRISKY LAKE

PARKSLAKE

MILLERLAKE

NORTH BEALE ROAD

LOWERBLACKWELDER

LAKE

WARREN SHINGLE BLVD

GAVIN MANDERY DRIVE

DOOLITTLE DRIVE

BEAL

E H

WY

S D 2 3

SIT E 3 3

UPPERBLACKWELDER

LAKE

FRISKY LAKE

PARKSLAKE

MILLERLAKE

NORTH BEALE ROAD

LOWERBLACKWELDER

LAKE

WARREN SHINGLE BLVD

GAVIN MANDERY DRIVE

DOOLITTLE DRIVE

BEAL

E H

WY

S D 2 3

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIGES-01_SS023_VICINITYMAP.MXD 1/13/2015 12:09:49 PM FELHADID

FIGURE ES-1 SITE SS023 VICINITY MAPSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE PL582(LINCOLN RECEIVER SITE)

BEALEAIR FORCE

BASE

£«20£«70

£«193£«65

£«99

£«65

£«70

0 4,000 8,000 feet³

LEGEND_̂ LOCATION OF SITE SS023

SITE INVESTIGATION BOUNDARY

SURFACE WATER

ROAD

BASE BOUNDARY

Page 12: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

!.

!.

!<

!.!.

!.

!.

!.

!.!.

!.!.!.

!.

!.

!.

!.!.

!.!.

!.!.

!.!.

!.!.!.!.

!.!.

!.!.

!.

!.

!.

!.

!.

!.

!.

!<

!<

!<

!<

!<

!<

!<!<

!<

!<

!<

!<

!<!<

!<")

SWMU23C014IW

SWMU23C015IW

SWMU23C016IW

SWMU23C017IW

AS-01AS-02

AS-03 (A/B)

AS-10 (A/B)

AS-09 (A/B)

23L001MW

23L004MW

23SWMU1MW

23U001AMW23U001BMW

BAT-1MW

BAT-2MW

BAT-3MW

BAT-4AMW

BAT-4BMW

BAT-5AMWBAT-5BMW

BAT-8MW

BAT-9MW

OWSM-C001MW

SWMU23C002MW

SWMU23C004AMWSWMU23C004BMW

SWMU23C006AMWSWMU23C006BMW

SWMU23U001AMWSWMU23U001BMW

SWMU23U002AMW

SWMU23U003AMWSWMU23U003BMW

SWMU23U004AMWSWMU23U004BMW SWMU23U005AMW

SWMU23U005BMW

SWMU23U006AMWSWMU23U006BMW

SWMU23U007AMWSWMU23U007BMW

SWMU34U002MW

39C018MW

39C020MW

39C023MW

39C024MW

39C025MW

AS-08 (A/B)

AS-04AS-05 (A/B)

AS-07AS-06 (A/B)

SWMU23C008MW

SWMU23C009MW

AS-01AS-02

AS-03 (A/B)

AS-10 (A/B)

AS-09 (A/B)

SWMU23C006AMWSWMU23C006BMW

10-487M1MW

AS-08 (A/B)

AS-04AS-05 (A/B)

AS-07AS-06 (A/B)

SWMU23B (1,1-DCE SOURCE)

SITE SS508 (PCE SOURCE)

EXCAVATED AREA AND GREASE RACK

CIVIL ENGINEERING

YARD

A ST

REET

A ST

REET

26TH STREET

B ST

REET

DOOLITTLE DRIVE

M

BUILDIN

G

2539

BUILDING2532

BUILDING25608

BUIL

DING

2530

BUIL

DING

2537

BUILDING2540

BUIL

DING

2548

BUILDING2546

BUILDING2488

BUILDING2542

BUIL

DING

PB-1

62

BUILDING2541

BUIL

DING

2549

BUILDING2538

BUILDING2497

BUIL

DING

2489

BUIL

DING

2551

BUIL

DING

2535

BUILDING2544

BUIL

DING

2499

BUIL

DING

2496

BUILDING2545

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIGES-02_SS023_SITEMAP.MXD 6/8/2015 8:28:48 AM FELHADID

FIGURE ES-2SITE SS023 LOCATION AND FEATURES MAPSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE SS023

0 125 250

FEET

³

LEGEND!. GROUNDWATER MONITORING WELL

!< GROUNDWATER INJECTION WELL

!< OZONE/AIR SPARGE WELL

")M FORMER OIL/WATER SEPARATOR

UNDERGROUND CONVEYANCE FOR OZONE SPARGE SYSTEM

SANITARY SEWER/IWL CONVEYANCE

EXCAVATED AREA AND GREASE RACK (TN & ASSOCIATES, 2000)

NO FURTHER ACTION AREA FOR SOIL AND SOIL VAPOR

KEY MAP

Page 13: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

!.

!.

!<

!.!.

!.

!.

!.

!.!.

!.!.!.

!.

!.

!.

!.!.

!.!.

!.!.

!.!.

!.!.!.!.

!.!.

!.!.

!.

!.

!.

!.

!<

!<

!<

!<

!<

!

!

!

!!

!

!

!!

!

!

!

!

!

!

!

!

!

!

!

!

!

!!

!

!

!!!

!

!

!

!!

!

!

!

!

!

!

.

.

<

..

.

.

.

..

...

.

.

.

..

..

..

..

....

..

..

.

.

.

.

<

<

<

<

<

.

.

.

.

")

39C023MW112.3645.6 J

SWMU23C002MW115.59ND

SWMU23C004AMW114.28

ND

SWMU23C006AMW117.43ND

SWMU23U001AMW115.26NDSWMU23C004BMW

109.61ND

SWMU23C006BMW117.280.28 J

SWMU23U001BMW110.280.42 J

10-487M4MWND

SWMU23C008MW113.70

45.8

23L004MW112.17ND

23SWMU1MW117.45366

23U001AMW111.621.9

23U008AMW108.113.2

SWMU23U002AMW109.7374.3

SWMU23U004AMW115.52

35.2

SWMU23U005AMW116.5920.5

SWMU23U007AMW115.72

31

23L001MW111.59

0.95

23U001BMW100.677.1

BAT-3MW116.414

BAT-4BMW114.16

13.8BAT-5BMW113.87

3.2

SWMU23U002BMW97.8077.4

SWMU23U003AMW125.02NDSWMU23U003BMW120.55ND

SWMU23U004BMW114.07

2.7

SWMU23U005BMW114.4827.7

SWMU23U007BMW114.67

1.7

BAT-1MW57.7

BAT-8MW71.6

OWSM-C001MW16.7

SWMU23C014IW173

SWMU23C015IW204

SWMU23C016IW564

SWMU23C017IW54

SWMU23U006AMW82.2

SWMU23U006BMW2.3

BAT-9MW

SWMU34U002MW113.80182

SWMU34U001MW114.49

7.9

BAT-5AMW113.84

240

BAT-4AMW114.24

284

BAT-2MW115.93

SWMU23C008MW113.70

45.8

100

510

0

M

BUILDIN

G

2539

BUILDING25608

BUILDING2540

BUIL

DING

2548

BUILDING2488

BUILDING2541

BUILDING2538

BUILDING2497

BUIL

DING

2489

BUIL

DING

2535

BUILDING2545

A ST

REET

A ST

REET

26TH STREET

B ST

REET

DOOLITTLE DRIVE

109

111

121

119

113

117115

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIGES-03_SS023_TCE_GWE.MXD 6/8/2015 8:40:06 AM

FIGURE ES-3SITE SS023 TCE CONCENTRATIONSIN GROUNDWATERSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE SS023

0 125 250

FEET

³

LEGENDTCE CONCENTRATION IN GROUNDWATER (µg/L)! NOT DETECTED (ND)

! ND to 5

! 5 to 100

! >100

. GROUNDWATER MONITORING WELL

< GROUNDWATER INJECTION WELL

116.59MEASURED GROUNDWATER ELEVATION (feet NAVD88)(GREY TEXT INDICATES ELEVATION NOT USEDIN CONTOURING)

20.5 TCE CONCENTRATION IN GROUNDWATER (µg/L)

")M FORMER OIL/WATER SEPARATOR

TCE CONCENTRATION CONTOUR (µg/L)

GROUNDWATER ELEVATION CONTOUR (feet NAVD88)

GROUNDWATER FLOW DIRECTION

SANITARY SEWER/IWL CONVEYANCE

EXCAVATED AREA AND GREASE RACK (TN & ASSOCIATES, 2000)

NOTES:

DATA PRESENTED ON THIS FIGURE WAS COLLECTEDDURING THE 2014 ANNUAL BGMP SAMPLING EVENT.

µg/L = MIGROGRAMS PER LITER.

J = THE ANALYTE WAS POSITIVELY IDENTIFIED, AND THEQUANTITATION IS AN ESTIMATE.

NAVD88 = NORTH AMERICAN VERTICAL DATUM OF 1988.

KEY MAP

Page 14: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

 

SITE SS023 CMI REPORT  i EN0224151019SAC/456998 

Contents 

Section  Page 

Executive Summary ......................................................................................................................... ES‐1 Corrective Measure Objectives ................................................................................................... ES‐1 Corrective Measure Implementation ......................................................................................... ES‐1 Monitoring Plan .......................................................................................................................... ES‐1 Works Cited ................................................................................................................................. ES‐2 

Acronyms and Abbreviations .............................................................................................................. iii 

1  Introduction ......................................................................................................................... 1‐1 1.1  Site Background ............................................................................................................... 1‐1 1.1.1  Hydrogeology ...................................................................................................... 1‐1 1.1.2  Site History and Response Actions ..................................................................... 1‐2 

1.2  Report Objectives ............................................................................................................ 1‐2 1.3  Report Organization ......................................................................................................... 1‐2 

2  Corrective Measure Objectives ............................................................................................. 2‐1 2.1  Corrective Measure Objectives ........................................................................................ 2‐1 2.2  Cleanup Levels for Groundwater ..................................................................................... 2‐1 

3  Corrective Measure Implementation .................................................................................... 3‐1 3.1  ISCO Implementation ....................................................................................................... 3‐1 3.1.1  Permitting ........................................................................................................... 3‐1 3.1.2  Hollow‐stem Auger Drilling and Injection Well Construction ............................. 3‐1 3.1.3  Injection Well Construction ................................................................................ 3‐2 3.1.4  Well Development .............................................................................................. 3‐2 3.1.5  Baseline Monitoring ............................................................................................ 3‐3 3.1.6  Hydrogeological Investigation ............................................................................ 3‐3 3.1.7  Updated Conceptual Site Model ......................................................................... 3‐4 3.1.8  Baseline Concentrations ..................................................................................... 3‐4 3.1.9  Waste Management ........................................................................................... 3‐5 3.1.10  Surveying............................................................................................................. 3‐6 3.1.11  Sodium Permanganate Injection ........................................................................ 3‐7 3.1.12  Deviations from the Work Plan......................................................................... 3‐10 

3.2  Enhanced Attenuation ................................................................................................... 3‐10 3.3  Land Use Controls .......................................................................................................... 3‐11 

4  Monitoring Plan .................................................................................................................... 4‐1 4.1  Recommended Changes to the Tentative MRP ............................................................... 4‐1 4.2  Performance Monitoring ................................................................................................. 4‐1 4.3  Compliance Monitoring ................................................................................................... 4‐3 4.4  Reporting ......................................................................................................................... 4‐3 4.5  Contingency Plan ............................................................................................................. 4‐3 

5  Conclusions and Recommendations ...................................................................................... 5‐1 5.1  Conclusions ...................................................................................................................... 5‐1 5.2  Recommendations ........................................................................................................... 5‐1 

6  Works Cited .......................................................................................................................... 6‐1 

Page 15: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

CONTENTS, CONTINUED

ii SITE SS023 CMI REPORTEN0224151019SAC/456998

Appendixes

A Fieldwork DocumentationB Site SS023 Baseline Groundwater Analytical DataC Injection Monitoring DocumentationD Response to Comments

Tables

2-1 Cleanup Levels for Contaminants of Concern...............................................................................2-1

3-1 Drilling and Well Construction Details ..........................................................................................3-23-2 Site SS023 Well Development Summary ......................................................................................3-33-3 Site SS023 Hydrogeological Investigation Summary.....................................................................3-43-4 Baseline Concentrations for Selected Analytes ............................................................................3-53-5 Summary of Site SS023 Survey Details .........................................................................................3-63-6 Summary of Site SS023 Injection ..................................................................................................3-73-7 Summary of Breakthrough Details................................................................................................3-93-8 Water Quality Parameters at Breakthrough.................................................................................3-9

4-1 Well Type and Designation for Site SS023 Monitoring.................................................................4-24-2 Schedule of Performance and Compliance Monitoring................................................................4-2

Figures

ES-1 Site SS023 Vicinity MapES-2 Site SS023 Location and Features MapES-3 Site SS023 TCE Concentrations in Groundwater

1-1 Site SS023 Vicinity Map1-2 Site SS023 Location and Features Map

3-1 Site SS023 Geologic Cross Section3-2 Site SS023 TCE Concentrations in Groundwater3-3 Site SS023 PCE Concentrations in Groundwater

4-1 Site SS023 Groundwater Monitoring Program

Page 16: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT iiiEN0224151019SAC/456998

Acronyms and Abbreviations

°C degree(s) Celsius

µg/L microgram(s) per liter

AFB Air Force Base

Air Force U.S. Air Force

Base Air Force Base

BGMP Basewide Groundwater Monitoring Program

bgs below ground surface

btoc below top of casing

BW background well

CCR California Code of Regulations

CE Civil Engineering

Central Valley Central Valley Regional Water Quality Control BoardWater Board

CMI Corrective Measures Implementation

CMW compliance monitoring well

COC contaminant of concern

DCE dichloroethene

DO dissolved oxygen

DTSC California Department of Toxic Substances Control

EA enhanced attenuation

EPA U.S. Environmental Protection Agency

gpd/ft gallon(s) per day per foot

gpm gallon(s) per minute

gpm/ft gallon(s) per minute per foot

ISCO in situ chemical oxidation

IW injection well

LAR limited access rig

LUC land use control

MCL maximum contaminant level

mg/L milligram(s) per liter

MRP Monitoring and Reporting Program

Page 17: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

ACRONYMS AND ABBREVIATIONS

iv SITE SS023 CMI REPORTEN0224151019SAC/456998

mS/cm milliSiemen(s) per centimeter

mV millivolt(s)

NaMnO4 sodium permanganate

NOI Notice of Intent

ORP oxidation reduction potential

PCE tetrachloroethene

PID photoionization detector

PMW performance monitoring well

PVC polyvinyl chloride

RAO remedial action objective

RCRA Resource Conservation and Recovery Act

ROI radius of influence

SOP standard operating procedure

State Water Board State Water Resources Control Board

Subtronic Subtronic Corporation

SWMU23 Solid Waste Management Unit 23

TCE trichloroethene

TDS total dissolved solids

TEFA Technical and Economic Feasibility Analysis

TW transition zone well

TZW treatment zone well

UCL upper confidence limit

UFP-QAPP Uniform Federal Policy Quality Assurance Project Plan

VOC volatile organic compound

WQO water quality objective

Yuba County Yuba County Environmental Health Department

WDR waste discharge requirement

Page 18: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT 1-1EN0224151019SAC/456998

SECTION 1

Introduction

This Corrective Measures Implementation (CMI) Report for Site SS023, Beale Air Force Base (AFB or Base),California, summarizes the optimization of the interim corrective measures and documents that the finalremedy is in place at Site SS023 (Figure 1-1) (figures are located at the end of each section). The finalremedy was selected and implemented in accordance with the Site SS023 Statement of Basis / CorrectiveMeasures Implementation Work Plan (Work Plan) (CH2M HILL, 2014a). No further action was selectedfor soil and soil vapor. In situ chemical oxidation (ISCO), enhanced attenuation (EA), and land use controls(LUCs) were selected for groundwater. Trichloroethene (TCE) and tetrachloroethene (PCE) were identifiedas contaminants of concern (COCs) in groundwater.

This report is being prepared by CH2M HILL for the Air Force Civil Engineer Center under the WorldwideEnvironmental Restoration and Construction Contract No. FA8903-09-D-8557, Task Order 0003.

1.1 Site BackgroundBeale AFB is located in the southeastern portion of the Sacramento Valley, approximately 40 miles northof Sacramento and 13 miles east of Marysville. Site SS023 is part of Solid Waste Management Unit 23(SWMU23) and is located in the central portion of Beale AFB in the Cantonment Area, northeast of theintersection at 26th and B Streets (Figure 1-1). Site SS023 is an electrical transformer storage area insidethe Civil Engineering (CE) yard. Site SS023 consists of two concrete pads measuring 52 by 60 feet, locatedapproximately 80 feet south of Building 2539. The concrete pads are both adjacent to the northern sideof the fence along Doolittle Drive. Electrical equipment, used transformers, and transformer oil werestored as part of operations and maintenance activities at the exterior electrical shop in Building 2539(URS, 2004). The site is currently used for storage by the 9th Civil Engineering Squadron. Materialscurrently stored at the site (such as transformers, gravel/sand, utility poles, and generators) do notcontain significant quantities of polychlorinated biphenyls or chlorinated solvents. Site SS023 is zonedfor industrial use (CH2M HILL, 2013). Figure 1-2 shows the site features located at Site SS023.

Solid Waste Management Unit 23 (SWMU23) has been classified as a Resource Conservation andRecovery Act (RCRA) facility because waste management practices resulted in a transformer spill in themid-1990s. The interim cleanup effort was conducted under the U.S. Air Force (Air Force) complianceprogram (URS, 2004). The sources of contaminants at SWMU23 are divided into three different sites.The COCs are TCE, PCE, and 1,1-dichloroethene (DCE). The 1,1-DCE plume (Site SS507) is west of SiteSS023, while the PCE plume (Site SS508) is north of Doolittle Drive and west of A Street (northeast ofSite SS023), within the CE yard. These two plumes are considered separate sites from Site SS023 and arenot addressed further as part of this CMI Report.

1.1.1 Hydrogeology

The depth to groundwater at Site SS023 is approximately 5 to 36 feet below ground surface (bgs), withan average depth of 19 feet bgs (CH2M HILL, 2014b). The horizontal hydraulic gradient at the site issouthwesterly. A groundwater trough is evident, which corresponds to a trough in the erosional surfaceof the marine siltstone layer. Overall, the hydraulic conductivity estimates ranged from 0.75 to 14.3 feetper day (Battelle and SteamTech Environmental Services, 2001). South of Doolittle Drive where theplume is migrating, the hydraulic conductivities ranged from 0.75 to 4.5 feet per day. For well BAT-5(shallow/deep), the hydraulic conductivity in the shallow well (25 to 30 feet bgs) was roughly twice thatof the deep well (35 to 40 feet bgs).

Page 19: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 1: INTRODUCTION

1-2 SITE SS023 CMI REPORTEN0224151019SAC/456998

1.1.2 Site History and Response Actions

Phased investigations and interim corrective measures conducted at Site SS023 from 1994 to 2014are summarized in the Work Plan (CH2M HILL, 2014a). Historical investigations at Site SS023 led to anumber of interim corrective measures, which included soil excavation, operation of a groundwatertreatment system, and operation of an ozone/air sparge system.

In 1998, maximum concentrations of TCE and PCE detected in groundwater were 1,600 and110 micrograms per liter (µg/L), respectively. From 2001 to 2003, a pilot-scale groundwater treatmentsystem was installed that used dynamic underground stripping with hydrous pyrolysis oxidationtechnology to degrade the chlorinated solvents. The TCE and PCE concentrations in groundwater werereduced 85 and 91 percent, respectively. An ozone sparge system was operated from 2005 to 2012.In 2013, monitoring wells SWMU23C008MW and SWMU23C009MW were constructed to define theextent of the 100-µg/L TCE plume to support optimization of the ISCO remedy. Groundwater samplesfrom well SWMU23C009MW contained 956 µg/L TCE and 47.2 µg/L PCE, indicating a need to optimizethe ISCO remedy (CH2M HILL, 2014a). The high TCE concentration in well SWMU23C009MW, locatedalong the shoulder of Doolittle Drive (Figure 1-2), showed that most of the TCE mass remains beneathDoolittle Drive, and remediation should be emphasized in this area.

1.2 Report ObjectivesThe objectives of this CMI Report are as follows:

• Document implementation of the corrective measures at Site SS023.

• Provide baseline concentrations prior to ISCO implementation.• Provide the monitoring plan for the ISCO remedy at Site SS023.

1.3 Report OrganizationThe organization of this report is as follows:

• Section 1: Introduction. Provides the Site SS023 background and the purpose and organization ofthis CMI Report.

• Section 2: Corrective Measure Objectives. Provides the objectives that the selected correctivemeasure will achieve.

• Section 3: Corrective Measure Implementation. Documents the implementation of the selectedcorrective measure and discusses deviations from the Work Plan. An updated conceptual site modelis included in this section.

• Section 4: Monitoring Plan. Describes the performance and compliance monitoring for the ISCOremedy at Site SS023.

• Section 5: Conclusions and Recommendations. Provides a summary of the work completed andconclusions from the implementation of the ISCO remedy.

• Section 6: Works Cited. Provides a list of the references used to prepare this report.

• Appendix A: Fieldwork Documentation.

• Appendix B: Site SS023 Baseline Groundwater Analytical Data.

• Appendix C: Injection Monitoring Documentation.

• Appendix D: Response to Comments.

Page 20: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SIT E 3 3

UPPERBLACKWELDER

LAKE

FRISKY LAKE

PARKSLAKE

MILLERLAKE

NORTH BEALE ROAD

LOWERBLACKWELDER

LAKE

WARREN SHINGLE BLVD

GAVIN MANDERY DRIVE

DOOLITTLE DRIVE

BEAL

E H

WY

S D 2 3

SIT E 3 3

UPPERBLACKWELDER

LAKE

FRISKY LAKE

PARKSLAKE

MILLERLAKE

NORTH BEALE ROAD

LOWERBLACKWELDER

LAKE

WARREN SHINGLE BLVD

GAVIN MANDERY DRIVE

DOOLITTLE DRIVE

BEAL

E H

WY

S D 2 3

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIG01-01_SS023_VICINITYMAP.MXD 1/13/2015 12:09:21 PM FELHADID

FIGURE 1-1 SITE SS023 VICINITY MAPSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE PL582(LINCOLN RECEIVER SITE)

BEALEAIR FORCE

BASE

£«20£«70

£«193£«65

£«99

£«65

£«70

0 4,000 8,000 feet³

LEGEND_̂ LOCATION OF SITE SS023

SITE INVESTIGATION BOUNDARY

SURFACE WATER

ROAD

BASE BOUNDARY

Page 21: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

!.

!.

!<

!.!.

!.

!.

!.

!.!.

!.!.!.

!.

!.

!.

!.!.

!.!.

!.!.

!.!.

!.!.!.!.

!.!.

!.!.

!.

!.

!.

!.

!.

!.

!.

!<

!<

!<

!<

!<

!<

!<!<

!<

!<

!<

!<

!<!<

!<")

SWMU23C014IW

SWMU23C015IW

SWMU23C016IW

SWMU23C017IW

AS-01AS-02

AS-03 (A/B)

AS-10 (A/B)

AS-09 (A/B)

23L001MW

23L004MW

23SWMU1MW

23U001AMW23U001BMW

BAT-1MW

BAT-2MW

BAT-3MW

BAT-4AMW

BAT-4BMW

BAT-5AMWBAT-5BMW

BAT-8MW

BAT-9MW

OWSM-C001MW

SWMU23C002MW

SWMU23C004AMWSWMU23C004BMW

SWMU23C006AMWSWMU23C006BMW

SWMU23U001AMWSWMU23U001BMW

SWMU23U002AMW

SWMU23U003AMWSWMU23U003BMW

SWMU23U004AMWSWMU23U004BMW SWMU23U005AMW

SWMU23U005BMW

SWMU23U006AMWSWMU23U006BMW

SWMU23U007AMWSWMU23U007BMW

SWMU34U002MW

39C018MW

39C020MW

39C023MW

39C024MW

39C025MW

AS-08 (A/B)

AS-04AS-05 (A/B)

AS-07AS-06 (A/B)

SWMU23C008MW

SWMU23C009MW

AS-01AS-02

AS-03 (A/B)

AS-10 (A/B)

AS-09 (A/B)

SWMU23C006AMWSWMU23C006BMW

10-487M1MW

AS-08 (A/B)

AS-04AS-05 (A/B)

AS-07AS-06 (A/B)

SWMU23B (1,1-DCE SOURCE)

SITE SS508 (PCE SOURCE)

EXCAVATED AREA AND GREASE RACK

CIVIL ENGINEERING

YARD

A ST

REET

A ST

REET

26TH STREET

B ST

REET

DOOLITTLE DRIVE

M

BUILDIN

G

2539

BUILDING2532

BUILDING25608

BUIL

DING

2530

BUIL

DING

2537

BUILDING2540

BUIL

DING

2548

BUILDING2546

BUILDING2488

BUILDING2542

BUIL

DING

PB-1

62

BUILDING2541

BUIL

DING

2549

BUILDING2538

BUILDING2497

BUIL

DING

2489

BUIL

DING

2551

BUIL

DING

2535

BUILDING2544

BUIL

DING

2499

BUIL

DING

2496

BUILDING2545

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIG01-02_SS023_SITEMAP.MXD 6/8/2015 8:27:26 AM FELHADID

FIGURE 1-2SITE SS023 LOCATION AND FEATURES MAPSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE SS023

0 125 250

FEET

³

LEGEND!. GROUNDWATER MONITORING WELL

!< GROUNDWATER INJECTION WELL

!< OZONE/AIR SPARGE WELL

")M FORMER OIL/WATER SEPARATOR

UNDERGROUND CONVEYANCE FOR OZONE SPARGE SYSTEM

SANITARY SEWER/IWL CONVEYANCE

EXCAVATED AREA AND GREASE RACK (TN & ASSOCIATES, 2000)

NO FURTHER ACTION AREA FOR SOIL AND SOIL VAPOR

KEY MAP

Page 22: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT 2-1EN0224151019SAC/456998

SECTION 2

Corrective Measure Objectives

This section provides the objectives that the selected corrective measure will achieve. This section alsoprovides the basis for cleanup levels and discharge limits that substantively comply with State RCRArequirements.

2.1 Corrective Measure ObjectivesThe site-specific objectives for the corrective measure at Site SS023 include the following:

• Reduce concentrations of COCs (TCE and PCE) in underlying groundwater originating at Site SS023 tosupport restoration of groundwater to designated beneficial uses (domestic, municipal, agricultural,and industrial supply).

• Restrict potential exposure to COCs in groundwater until concentrations are at such levels to allowfor unlimited use/unrestricted exposure.

• Comply with State RCRA requirements.

2.2 Cleanup Levels for GroundwaterThe final cleanup levels presented in Table 2-1 were established to achieve the site-specific objectives.Cleanup levels for restoring designated beneficial uses of groundwater are based on the lowest of eitherthe federal or state primary maximum contaminant levels (MCLs). In the case of TCE and PCE, federaland state primary MCLs are the same.

TABLE 2-1Cleanup Levels for Contaminants of ConcernSite SS023 Corrective Measures Implementation Report, Beale Air Force Base, California

Media: GroundwaterSite Area: SS023Available Use: Unrestricted use

COC Cleanup Level (µg/L)* Basis for Cleanup Level

TCE 5 Federal Primary MCL

PCE 5 Federal Primary MCL

* Cleanup levels are derived from the lowest of the state or federal primary MCLs referenced in Title 22, CCR, Section 64444and Title 40, Code of Federal Regulations, Part 300.430(e)(2)(l)(B). A TEFA will be conducted when these cleanup levels areachieved or when concentrations reach asymptotic levels as demonstrated by evaluation of monitoring data.

Notes:

CCR = California Code of RegulationsTEFA = technical and economic feasibility analysis

Page 23: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT 3-1EN0224151019SAC/456998

SECTION 3

Corrective Measure Implementation

This section documents construction and operation of the remedy implemented for groundwater atSite SS023. The remedy consists of three main components: ISCO, EA, and LUCs. The ISCO componentis the major component documented in this section. To implement the ISCO portion of the remedy,four injection wells were constructed and developed, baseline sampling was performed, sodiumpermanganate was injected into new and existing wells, and monitoring was performed. EA involvesgroundwater monitoring in the distal portion of the plume (downgradient from the ISCO treatmentzone) and will be documented in the Basewide Groundwater Monitoring Program (BGMP) reports.EA is discussed in Section 3.2, and LUCs are discussed in Section 3.3.

3.1 ISCO ImplementationThis section discusses the methods and details of the injection well construction, baseline monitoring,and sodium permanganate injection.

3.1.1 Permitting

During June 2014, four injection wells were drilled and constructed at Site SS023. Four well permits(WP0009910 to WP0009913) were obtained from the Yuba County Environmental Health Department(Yuba County) for the construction of injection wells SWMU23C014IW through SWMU23C017IW.A Base dig permit (14.073A), was obtained from Beale AFB Civil Engineering on June 9, 2014, for theconstruction of the four injection wells. The Yuba County well permit and the Beale AFB dig permit arepresented in Appendix A, Attachments A1 and A2, respectively. CH2M HILL contracted with SubtronicCorporation (Subtronic) to check the four proposed boring locations for underground utilities usinggeophysical methods. Subtronic performed utility locating on June 11, 2014.

A Notice of Intent (NOI) was submitted on July 8, 2014, requesting coverage under Waste DischargeRequirement (WDR) General Order R5-2008-0149 and the Central Valley Water Board prepared aNotice of Applicability on September 18, 2014, which contained a tentative Monitoring and ReportingProgram (MRP). No public comments were received. On October 29, 2014, approval to proceed withinjections was provided by the Central Valley Water Board via e-mail. The MRP (Order R5-2008-0149-054)is presented in Appendix A, Attachment A3.

A lane closure notification was required because it was necessary to close one lane of traffic onDoolittle Drive for drilling operations. The notification was submitted to Beale AFB 2 weeks prior tothe commencement of drilling. Flaggers were used to control traffic and a traffic count was conductedto record the number of vehicles inconvenienced by the lane closure. A copy of the lane closurenotification and traffic count sheets are presented in Appendix A, Attachment A4.

3.1.2 Hollow-stem Auger Drilling and Injection Well Construction

CH2M HILL contracted with National Exploration, Wells, & Pumps of Woodland, California, to pothole,drill, and construct four injection wells (SWMU23C014IW through SWMU23C017IW) at Site SS023.The drilling and well construction, which occurred from June 14 through 17, 2014, was completed usinghollow-stem auger drilling methods with a limited access rig (LAR) equipped with 8-inch-outer-diameteraugers. Prior to drilling each boring, the LAR rig, drilling tools, and downhole coring equipment weredecontaminated in accordance with the Basewide Uniform Federal Policy Quality Assurance Project Plan(Basewide UFP-QAPP) (CH2M HILL, 2014c). Drilling, well construction, and decontamination activities

Page 24: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION

3-2 SITE SS023 CMI REPORTEN0224151019SAC/456998

were continuously monitored by CH2M HILL personnel. Drill cuttings were temporarily contained in ahopper provided by the drilling subcontractor, then transferred to a roll-off bin provided by Intrinsic.Waste management information is discussed in Section 3.1.9.

Lithologic samples were obtained and logged at 5-foot intervals during drilling using a continuousdry-core sampling system. Soil cores were logged using the Unified Soil Classification System. Similar toprevious borings at Site SS023, a clay-dominated horizon underlain by sand and clay (23 to 35 feet bgs)was observed in the four borings (see Figure 3-1 for the geologic cross section). Field documentationincluding field notes, lithologic logs, and a photo log is presented in Appendix A, Attachments A5through A7, respectively.

Air monitoring was conducted during drilling and construction of the injection wells. Volatile organiccompounds (VOCs) were monitored in the breathing zone and in the head space of the lithologicsamples using a MultiRAE with a 10.6-eV lamp photoionization detector (PID). VOCs were not detectedin the breathing zone, but were detected in head space of the lithologic samples. The concentrationswere less than 0.2 parts per million by volume in the headspace samples. PID readings are shown on thelithologic logs in Appendix A, Attachment A6.

3.1.3 Injection Well Construction

Table 3-1 outlines well construction details for the injection wells. Well completion diagrams arepresented in Appendix A, Attachment A8. Each injection well was constructed with 2-inch-diameterSchedule 40 polyvinyl chloride (PVC) blank casing, 2-inch-diameter machine-slotted PVC screen with0.040-inch openings, filter pack material consisting of #6 sand, a transition seal consisting of hydratedmedium bentonite chips, and a sanitary seal consisting of cement grout with 3 to 5 percent (by weight)bentonite powder additive. The injection wells were constructed as single completions and screenedfrom 15 to 35 feet bgs, except for well SWMU23C014IW, which was screened from 30 to 50 feet bgs.Wells were completed as a flush mount set in a 24-inch-diameter concrete pad.

TABLE 3-1Drilling and Well Construction DetailsSite SS023 Corrective Measures Implementation Report, Beale Air Force Base, California

Well IDScreen Interval

(feet bgs)Filter Pack Interval

(feet bgs)Borehole Depth

(feet bgs)Well Casing Diameter

(inches)

SWMU23C014IW 30 to 50 28 to 51.0 51.0 2

SWMU23C015IW 15 to 35 13 to 36.5 36.5 2

SWMU23C016IW 15 to 35 13 to 36.5 36.5 2

SWMU23C017IW 15 to 35 13 to 36.0 36.0 2

Note:

Borehole diameter was 8 inches for each injection well.

3.1.4 Well Development

Following well construction, each injection well was developed to remove fines from the filter pack andwell screen in accordance with standard operating procedure (SOP)-72, included in Appendix A to theBasewide UFP-QAPP (CH2M HILL, 2014c). Table 3-2 contains the volume discharged during welldevelopment of the new injection wells.

Page 25: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION

SITE SS023 CMI REPORT 3-3EN0224151019SAC/456998

TABLE 3-2Site SS023 Well Development SummarySite SS023 Corrective Measures Implementation Report, Beale Air Force Base, California

Well ID Development Date Volume Discharged (gallons)

SWMU23C014IW 06/18/2014 124

SWMU23C015IW 06/18/2014 140

SWMU23C016IW 06/17/2014 225

SWMU23C017IW 06/17/2014 209

Total 698

Well development logs are included in Appendix A, Attachment A8. Wells were developed by acombination of swabbing, bailing, and overpumping until the discharge was clear. A truck-mountedelectric winch was used to operate the swab and the bailer. Pumping was conducted using an11-inch-long, 1.8-inch-outer-diameter Grundfos electric submersible pump.

During the overpumping phase of well development, grab samples of groundwater were collected every5 minutes by the field geologist, and water quality measurements (temperature, pH, conductivity,turbidity, dissolved oxygen [DO], and oxygen reduction potential [ORP]) were recorded. The averagedischarge rate ranged from 1.0 to 2.2 gallons per minute (gpm). The total quantity of water dischargedfrom well development was 698 gallons.

3.1.5 Baseline Monitoring

This section discusses the methods used for the baseline groundwater sampling conducted as part of theBGMP in July and August 2014, prior to ISCO treatment. Baseline sampling was performed to determinegroundwater conditions prior to injection. The baseline groundwater data included depth to water, pH, ORP,DO, turbidity, electrical conductivity, and permanganate concentration. Permanganate concentrationswere measured using a HACH DR890 colorimeter. Groundwater samples collected during the BGMP eventwere analyzed for VOCs (SW8260B), metals (SW6010/7199), and total dissolved solids (TDS) (E160.1)concentrations. Low-flow groundwater sampling methods were used in accordance with SOP-83 includedin Appendix A to the Basewide UFP-QAPP (CH2M HILL, 2014c). Groundwater samples were submitted toPEL laboratories, Tampa, Florida, for laboratory analyses.

3.1.6 Hydrogeological Investigation

A hydrogeological investigation (well recovery test) was conducted at injection wells SWMU23C014IWthrough SWMU23C017IW following well development to provide an indication of well performance andto obtain data for determining the specific capacity, transmissivity, and hydraulic conductivity of thescreened hydrogeologic unit. The well recovery test was conducted following SOP-72 (CH2M HILL,2014c). An initial water level was recorded, and then the wells were pumped at a constant rate until5 to 10 feet of drawdown (or the maximum drawdown for the well if 5 feet was not achievable) wasobserved. Water levels were monitored during recovery until the water level returned to within80 percent of the static water level. Recovery test logs are located in Appendix A, Attachment A10.

The results of the tests are presented in Table 3-3. The injection wells, in general, are screened in asandy clay unit (boring logs in Appendix A). The data presented in Table 3-3 are consistent with thegeology, and hydraulic conductivity measurements are within the range (0.75 to 4.5 feet per day)reported by Battelle and SteamTech Environmental Services (2001; Section 1.1.1).

Page 26: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION

3-4 SITE SS023 CMI REPORTEN0224151019SAC/456998

TABLE 3-3Site SS023 Hydrogeological Investigation SummarySite SS023 Corrective Measures Implementation Report, Beale Air Force Base, California

Well IDFlow Rate

(gpm)Maximum Drawdown

(feet)Specific Capacity

(gpm/ft)Transmissivity

(gpd/ft)Hydraulic Conductivity

(feet per day)

SWMU23C014IW 2 4.35 0.46 690 4.6

SWMU23C015IW 1 9.62 0.10 156 1.1

SWMU23C016IW 2 6.84 0.29 439 2.9

SWMU23C017IW 2.3 4.28 0.53 789 5.2

Average 1.8 6.27 0.35 519 3.4

Notes:

gpd/ft = gallon(s) per day per footgpm/ft = gallon(s) per minute per foot

3.1.7 Updated Conceptual Site Model

The following is an updated conceptual site model for the nature and extent of contamination ingroundwater at Site SS023 using the recent baseline monitoring data. Laboratory reports for thebaseline groundwater sampling are included in Appendix B, and a summary of baseline groundwateranalytical data is presented in Table B-1. TCE and PCE are the COCs for groundwater. The TCE and PCEdistributions in groundwater at Site SS023 are shown on Figures 3-2 and 3-3, respectively. During thebaseline sampling event (July and August 2014), the highest TCE concentration was detected in agroundwater sample collected from injection well SWMU23C016IW with a TCE concentration of564 µg/L (Figure 3-2). Twenty-three wells sampled as part of the baseline groundwater sampling eventcontained TCE concentrations greater than the groundwater screening level of 5 µg/L.

Historically, the highest TCE concentrations in groundwater are from samples collected fromwell 23SWMU1MW. Groundwater samples from the new injection wells near Doolittle Drive(SWMU23C014IW through SWMU23C017IW) contained TCE concentrations ranging from 54 to 564 µg/L.This further confirms that there is a residual TCE mass in groundwater beneath Doolittle Drive that wasnot treated by the ozone/air sparge ISCO system located to the west-southwest. Furthermore, the 2014TCE plume contours revealed that the 100-milligram-per-liter (mg/L) plume in the northern area islarger and extends further to the southwest (Figure 3-2).

During the baseline sampling event (July and August 2014), the highest PCE concentration was detectedin a groundwater sample collected from monitoring well BAT-3MW (located just north of Doolittle Drive)with a PCE concentration of 43.4 µg/L (Figure 3-3). Twenty-three wells sampled as part of the baselinegroundwater sampling event contained PCE concentrations greater than the groundwater screeninglevel of 5 µg/L. Groundwater samples collected from the new injection wells near Doolittle Drive(SWMU23C014IW through SWMUC017IW) contained PCE concentrations ranging from 18.4 to 27.2 µg/L.PCE from Site SS508 is impacting Site SS023.

3.1.8 Baseline Concentrations

Five analytes (chromium, manganese, permanganate, selenium, and TDS) will be used to comparepost-injection samples to baseline samples for compliance monitoring. It is anticipated that thesefive analytes will exceed baseline groundwater concentrations in the treatment zone wells (TZWs).Chromium, manganese, and selenium can be released via oxidation of natural metals in the formation.Sodium permanganate was injected into the groundwater, and therefore, permanganate concentrations

Page 27: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

SITE SS023 CMI REPORT  3‐5 EN0224151019SAC/456998 

are expected to be elevated where injections occurred. TDS is directly increased by injection of sodium permanganate. The baseline concentration for each analyte was calculated using a 95 percent upper confidence limit (UCL) (Equation 1), which assumes that all data are normally distributed, and the detection limit is used for nondetects: 

  95 percent UCL = Mean + Standard Deviation × T statistic / √(n‐1)  (1) Where:  

The T statistic is dependent on number of samples and n is the number of samples.  

Using the baseline data, the results of this calculation are presented in Table 3‐4 for the five analytes. In cases where the primary or secondary MCL is greater than the 95 percent UCL, the MCL is used as the baseline concentration. The trigger level is defined as the greater of twice the 95 percent UCL of the analyte or the analyte’s MCL. Trigger levels are only provided for chromium, manganese, and permanganate (see Contingency Plan in Section 4.5). The primary MCL for chromium will be used as the baseline concentration because the 95 percent UCL is less than the MCL. Twice the baseline concentration will be used as the baseline concentration for manganese. Permanganate was not detected in the 16 baseline samples and is not naturally occurring in the environment. Therefore, a concentration of 0.0 mg/L will be used as the baseline concentration. The trigger level for permanganate is the method detection limit of 1.0 mg/L. Selenium was not measured during the baseline event because selenium was not proposed as an analyte to monitor in the Work Plan (CH2M HILL, 2014a); however, selenium was added in the tentative MRP from the Central Valley Water Board. The MCL for selenium will be used as the baseline concentration. TDS exceeded the 95 percent UCL in wells BAT‐1MW and 23U001BMW with concentrations of 479 and 426 mg/L, respectively. However, TDS concentrations in these wells were less than the secondary MCL of 500 mg/L; therefore, the secondary MCL will be used as the baseline concentration. 

TABLE 3‐4 Baseline Concentrations for Selected Analytes Site SS023 Corrective Measures Implementation Report, Beale Air Force Base, California 

Analyte  Samples  Detects  Minimum Maximum Average Standard Deviation

95% UCL (mg/L) 

MCL (mg/L) 

Trigger Level (mg/L)d 

Chromium  10  10  0.001  0.014  0.005  0.005  0.008  0.05b  0.05 

Manganese  10  8  0.001  0.657  0.138  0.257  0.329  0.05c  0.66 

Permanganate  16  0  ‐‐  ‐‐  ‐‐  ‐‐  0a  ‐‐  1.0 

Selenium  ‐‐  ‐‐  ‐‐  ‐‐  ‐‐  ‐‐  ‐‐  0.05b  ‐‐ 

TDS  10  10  223  479  313  84  375  500c  ‐‐ 

a The method detection limit for permanganate is 1.0 mg/L. b Primary MCL c Secondary MCL d The trigger level is defined as the greater of twice the 95 percent UCL of the analyte or the analyte’s MCL. Trigger levels are only provided for chromium, manganese, and permanganate as stated in the contingency plan (Section 4.5). 

Notes: 

Bold indicates the chosen baseline concentration. 

‐‐ = data not available CMW = compliance monitoring well 

3.1.9 Waste Management 

Remediation waste generated during the Site SS023 ISCO implementation consisted of drill cuttings, decontamination and purge water, and general trash such as personal protective equipment. Drill 

Page 28: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

3‐6  SITE SS023 CMI REPORT   EN0224151019SAC/456998 

cuttings were placed in a hopper and then transferred to a 20‐cubic‐yard rolloff bin staged in a vacant parking lot south of the intersection of Doolittle Drive and B Street to await characterization. Approximately 15 cubic yards of soil were produced from drilling injection wells SWMU23C014IW through SWMU23C017IW. Approximately 838 gallons of decontamination and purge water were temporarily stored at Site LF013 in tanks. Soil and liquid wastes were characterized in accordance with the procedures in SOP‐91, Analysis and Characterization (CH2M HILL, 2014c). Personal protective equipment and disposable sampling equipment were disposed of in a trash bin at the CH2M HILL field office. All wastes were managed in accordance with applicable State of California and federal regulations and the Basewide UFP‐QAPP (CH2M HILL, 2014c). 

The soil waste characterization samples collected from the 20‐cubic‐yard rolloff bin were analyzed for metals (SW6010B) and VOCs (SW8260C). Analysis of analytical results indicates that the waste is classified as nonhazardous. 

Analytical results for drill cuttings were submitted with a waste profile to Hay Road Landfill for review and acceptance. Intrinsic transported the rolloff bin on August 27, 2014. The waste tracking log, analytical results, signed profile, weight ticket, and waste manifest are provided in Appendix A, Attachment A11.  

Liquid waste (decontamination and purge water) was managed at the CG041‐013 Groundwater Treatment System. Drilling and development activities at Site SS023 generated approximately 838 gallons of liquid waste. The combined water was analyzed for metals (SW6010B) and VOCs (SW8260C). Analysis of analytical results indicates that the waste is classified as nonhazardous. The liquid waste was discharged to the CG041‐013 Groundwater Treatment System on August 28, 2014. 

3.1.10 Surveying A survey of the new injection wells was conducted on October 23, 2014, using the global positioning system satellite technology with real‐time kinematic surveying instruments to provide horizontal and vertical positions for the locations listed in Table 3‐5. The horizontal datum for wells and soil borings is the California Coordinate System, North American Datum of 1983, Zone 2; and the vertical datum used is the North American Geodetic Vertical Datum of 1988. The survey originated from the monuments established at Beale AFB by the National Aeronautics and Space Administration in their geodetic control survey performed in 1999, which was intended to be the basis for all future surveys performed on the Base. All results are reported in United States survey feet. The work was performed under the direct supervision of a California Professional Land Surveyor. Survey coordinates and elevations are provided in Table 3‐5.  

TABLE 3‐5 Summary of Site SS023 Survey Details Site SS023 Corrective Measures Implementation Report, Beale Air Force Base, California

Well Northing (feet)a 

Easting (feet)a 

Ground Surface Elevation (feet NAVD88)b 

Top of Casing Elevation (feet NAVD88)b,c 

SWMU23C014IW  2169921.51  6735083.96  133.23  133.12 

SWMU23C015IW  2170076.76  6735274.83  131.97  131.77 

SWMU23C016IW  2170139.69  6735196.79  133.07  132.79 

SWMU23C017IW  2170099.96  6735344.08  131.55  131.32 

a North American Datum of 1983 (NAD83/1992 HPGN), California State Plane Zone 2, U.S. survey feet. b North American Vertical Datum of 1988 (NAVD88), U.S. survey feet. c Measuring point is a black marking on the north side on the top of the PVC casing for injection wells. 

Note: 

Locations were surveyed on October 23, 2014. 

Page 29: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

SITE SS023 CMI REPORT  3‐7 EN0224151019SAC/456998 

3.1.11 Sodium Permanganate Injection 

The ISCO Design Tool was used to calculate the volume and mass of permanganate to inject into each injection well (input and output worksheets are listed in Appendix C of the Work Plan [CH2M HILL, 2014a]). Table 3‐6 lists the design and actual injection volumes for each injection well. Injection was split into three phases because of the location of wells and ability to monitor the wells during injection. Injections began upgradient of the TCE plume at wells SWMU23C017IW and SWMU23C009MW.  

TABLE 3‐6 Summary of Site SS023 Injection Site SS023 Corrective Measures Implementation Report, Beale Air Force Base, California 

Injection Wella  Injection Dates 

Total Volume (gallons) 

NaMnO4 Volume  (gallons 40 percent 

NaMnO4) 

NaMnO4 Concentration 

(mg/L)  Average Flow Rate (gpm) Design   Actual   Design  Actual   Design  Actual  

Phase 1  

SWMU23C009MWb  11/5/14 to 01/06/15  8,100  9,319  243  287  16,314  16,748  3.5 

SWMU23C017IW  11/5/14 to 11/17/14  8,100  6,886  243  196  16,314  15,479  3.4 

Phase 2 

SWMU23C015IW  11/19/14 to 12/18/14  11,340  12,817  227  241  10,876  10,225  2.7 

SWMU23C016IW  11/19/14 to 12/18/14  11,340  12,296  227  232  10,876  10,261  2.7 

23SWMU1MW  11/19/14 to 12/18/14  10,080  9,884  202  212  10,876  11,664  2.2 

Phase 3 

SWMU23C014IW  01/8/15 to 01/23/15  17,280  15,665  173  182  5,438  6,318  3.9 

Total    66,240  66,867  1,315  1,350       

a Screen length is 20 feet except for well 23SWMU1MW, which is 19 feet. b Injection into well SWMU23C009MW was completed in two parts: (1) November 5 to 17, 2014, and (2) January 5 to 6, 2015. 

Note: 

NaMnO4 = sodium permanganate 

Before and during injections, water quality monitoring (temperature, pH, conductivity, turbidity, DO, and ORP) was conducted at wells that were screened within the treatment zone (15 to 50 feet bgs) and within the expected radius of influence (ROI) of wells with active injection. During Phase 1 (injection into wells SWMU23C009MW and SWMU23C017IW), wells BAT‐1MW, BAT‐3MW, SWMU23C015IW, SWMU23C016IW, and 23SWMU1MW were monitored. During Phase 2 (injection into wells SWMU23C015IW, SWMU23C016IW, and 23SMU1MW), wells BAT‐4AMW, BAT‐4BMW, and BAT‐8MW were monitored. After breakthrough was observed at BAT‐4AMW, BAT‐5AMW was monitored. During Phase 3 (injection into well SWMU23C014IW), wells SWMU34U002MW, SWMU23U004AMW, and SWMU23C008MW were monitored. Water levels were recorded in the select wells each day of injection before injections, midday, and before the system was flushed. 

Sodium permanganate (RemOx ISCO Reagent) was purchased from Carus Chemical Company and delivered to the site in five 300‐gallon‐capacity totes. Each tote held approximately 270 gallons of 40 percent sodium permanganate for a total of 1,350 gallons. The certificate of analysis for the sodium permanganate is presented in Appendix C, Attachment C1. An injection trailer with a Dosatron (40 gpm: D8RE5) was used to mix the correct proportion of potable water (obtained from fire hydrants) 

Page 30: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

3‐8  SITE SS023 CMI REPORT   EN0224151019SAC/456998 

and sodium permanganate. The design and actual volume of water, sodium permanganate, and percent solution of 40 percent sodium permanganate for each injection well are provided in Table 3‐6.  

Phase 1 injections (injection into wells SWMU23C009MW and SWMU23C017IW) were completed between November 5, 2014, and January 6, 2015, using approximately 3 percent permanganate solution. Injections were completed at injection well SWMU23C017IW on November 17, 2014, but the Dosatron malfunctioned at low flow rates when only injecting into well SWMU23C009MW. Flow rate into well SWMU23C009MW was restricted by injection pressure (injection pressure was maintained at less than 15 pounds per square inch to avoid fracturing the aquifer formation and possibly causing surface breakout at the injection point). A new Dosatron (11 gpm: D25RE5) capable of lower flow rates was ordered, and injections were moved to Phase 2. After completing Phase 2 injections, injection into well SWMU23C017IW was completed on January 5 and 6, 2015, using the new Dosatron. 

Phase 2 injections (injection into wells SWMU23C015IW, SWMU23C016IW, and 23SWMU1MW) were completed between November 19 and December 18, 2014, using approximately 2 percent permanganate solution. The total reagent injected into each well was greater than the design volume because the Work Plan assumed a total of 1,315 gallons were needed to complete injections. However, 1,350 gallons of sodium permanganate were delivered to the site; therefore, the excess 35 gallons of sodium permanganate were split between the Phase 2 and Phase 3 injections. Additional water was injected to maintain the desired permanganate concentrations. 

Phase 3 injection into well SWMU23C014IW was completed between January 8 and 23, 2015, using approximately 1 percent permanganate solution. Efforts were made to control the injection at 1 percent sodium permanganate solution, but the Dosatron kept drifting. Sodium permanganate was injected at a concentration between 1.3 and 1.5 percent solution and flush water was used to dilute the injection after sodium permanganate injection was completed. 

Injection logs, depth to water records, water quality monitoring, and permanganate test results collected during injections are provided in Appendix C, Attachments C2 through C5, respectively. 

Breakthrough was identified by visual observation of permanganate (pink to purple colored water) in an observation well. Breakthrough can also be observed in water quality parameters such as depth to groundwater (decrease in depth to groundwater), DO (significant increase to near saturation levels), ORP (significant increase to greater than 300 millivolts [mV]), and permanganate readings (significant increase from baseline conditions). The volume injected at the time of breakthrough was used to estimate the ROI of the nearest injection well. Breakthrough was noted in all observations wells within 43 feet of an injection well. Table 3‐7 presents breakthrough information, including the estimated mobile porosity and ROI, for wells monitored during injections. Table 3‐8 presents water quality monitoring data recorded at the time of breakthrough.  

One week after initiating Phase 1 injections, breakthrough occurred at monitoring well BAT‐3MW (located 30 feet north of injection well SWMU23C017IW) as evidenced by pink purge water, an ORP increase to 540 mV, and elevated permanganate concentration (13.6 mg/L). During Phase 1 injections, breakthrough was also observed in monitoring wells BAT‐1MW (located 25 feet north of injection well SWMU23C017IW) and 23SWMU1MW (located 55 feet downgradient of injection well SWMU23C009MW) 12 and 14 days after initiating injections, respectively. Injection at well SWMU23C017IW contributed to breakthrough at two wells; therefore, two ROIs were estimated for this well. Table 3‐7 shows the estimated mobile porosity is between 1.2 and 2.0 percent and the estimated ROI is between 25 and 36 feet for injection well SWMU23C017IW.  

Page 31: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

SITE SS023 CMI REPORT  3‐9 EN0224151019SAC/456998 

TABLE 3‐7 Summary of Breakthrough Details Site SS023 Corrective Measures Implementation Report, Beale Air Force Base, California 

Calculation Reference (in Notes section):  A  B  C  D  E 

Breakthrough Well 

Injection Well 

Date of Breakthrough

Distance from Injection 

Point (feet) 

Total Volume Injected (gallons) 

Volume at Breakthrough 

(gallons) 

Estimated  Mobile Porositya

(percent) 

Estimated ROIb 

(feet) 

BAT‐3MW  SWMU23C017IW  11/12/2014  30  6,886  4,892  1.2  36 

BAT‐1MW  SWMU23C017IW  11/17/2014  25  6,886  6,636  2.0  25 

23SWMU1MW  SWMU23C009MW  11/19/2014  55  9,319  7,435  1.0  62 

BAT‐4AW  SWMU23C016IW  12/16/2014  45  12,296  10,650  1.0  48 

SWMU34U002MW  SWMU23C014IW  1/8/2015  30  15,665  817  0.2c  131c 

  Average  1.3d  43d 

a Porosity was estimated using the following equation: D = C / (π × A2 × 20 × 7.48); where 20 represents the well screen length in feet and 7.48 represents gallons per cubic foot. 

b ROI was estimated by using the following equation: E = (B / C)0.5 × A 

c Value is not an accurate representation of estimated mobile porosity or ROI. A preferential pathway between injection well SWMU23C014IW and SWMU34U002MW is believed to have caused the immediate breakthrough. 

d Average does not include value from well SWMU34U002MW.  

 

TABLE 3‐8 Water Quality Parameters at Breakthrough Site SS023 Corrective Measures Implementation Report, Beale Air Force Base, California 

Well ID  Date  Time Water Level(feet btoc) 

DO (mg/L) 

ORP (mV) 

Conductivity (mS/cm) 

Temperature (°C)  Color 

NaMnO4 

(mg/L) 

BAT‐3MW  11/12/2014  13:21  8.95  1.2  540  0.276  21.51  Pink  13.6 

BAT‐1MW  11/17/2014  14:19  10.54  1.5  509  0.399  20.72  Pink  2.7 

23SWMU1MW  11/19/2014  8:17  ‐‐  2.4  477  0.477  19.36  Pink  121.2 

BAT‐4AMW  12/16/2014  11:55  15.76  8.0  505  0.311  17.03  Pink  2.1 

SWMU34U002MW  1/8/2015  12:04  18.11  6.4  645  0.827  22.47  Dark pink  98.8 

Notes: 

‐‐ = data not recorded °C = degree(s) Celsius btoc = below top of casing mS/cm = milliSiemen(s) per centimeter 

During Phase 2 injections, injection into well SWMU23C016IW contributed to breakthrough at well BAT‐4AW (located 45 feet south of injection well SWMU23C016IW) after injection was 87 percent completed. The ROI of SWMU23C016IW is approximately 48 feet. Monitoring well BAT‐5AMW (located 112 feet downgradient from injection well SWMU23C016IW) was added to the list of Phase 2 monitoring wells after breakthrough was observed at well BAT‐4AMW; however, as expected, no breakthrough was observed at well BAT‐5AMW during injections. 

Page 32: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

3‐10  SITE SS023 CMI REPORT   EN0224151019SAC/456998 

Four hours after Phase 3 injections began at injection well SWMU23C014IW, breakthrough was observed in monitoring well SWMU34U002MW (30 feet west of injection well SWMU23C014IW). Because breakthrough occurred after injections were only 5 percent complete, the ROI was estimated to be 131 feet. The permanganate reading from purge water collected at well SWMU34U002MW on January 7, 2015, one day prior to injection, was 0.0 mg/L, and the permanganate reading after 4 hours of injection was 98.8 mg/L. The immediate breakthrough at monitoring well SWMU34U002MW is likely because of a preferential pathway between wells SWMU23C014IW and SWMU34U002MW, and therefore, the estimated mobile porosity and ROI are likely overestimated. 

3.1.12 Deviations from the Work Plan 

Several changes were required throughout ISCO implementation to complete the injections. The following summarizes the deviations from the Work Plan: 

In response to the low baseline TCE concentration (54 µg/L) in SWMU23C017IW and breakthrough observed in monitoring well BAT‐3MW, the volume injected at SWMU23C009MW was increased from 8,100 to 9,500 gallons and decreased from 8,100 to 6,700 gallons at SWMU23C017IW.  

Phase 1 injections (SWMU23C017IW and SWMU23C009MW) were completed in two parts (November 2014 and January 2015) because the Dosatron was not reliable for injection at flow rates less than 5 gpm. A new Dosatron was ordered, and injections were completed at well SWMU23C009MW on January 5 and 6, 2015. 

The Work Plan assumed a total of 1,315 gallons were needed to complete injections; however, 1,350 gallons of sodium permanganate were delivered to the site. The excess 35 gallons of sodium permanganate were split between the Phase 2 and Phase 3 injections.  

The Dosatron used for injection at well SWMU23C014IW was not reliable at the design value of 1 percent permanganate solution at a flow rate less than 4 gpm. Injections were performed with the lowest possible setting on the Dosatron (approximately 1.3 to 1.5 percent permanganate), and flush water was injected after permanganate injection to dilute the solution. 

3.2 Enhanced Attenuation In conjunction with treatment, naturally occurring processes will reduce concentrations of COCs in groundwater within the treatment area (after hot spots are treated with ISCO) and outside of the treatment area. Naturally occurring physical and chemical processes are enhanced by the reduced influx of COCs following ISCO.  

The plume will continue to be monitored in accordance with the BGMP using the Beale AFB monitoring well network. Frequency of monitoring for each well will be evaluated annually in accordance with the BGMP Decision Tree (Figure 2‐1 in BGMP Annual Reports). The enhanced attenuation monitoring is in addition to the monitoring program described in Section 4. 

When the cleanup level for TCE and PCE for the plume are achieved or when asymptotic conditions are achieved, whichever occurs first, a TEFA will be prepared to evaluate the technical and economic feasibility of continuing remediation. After three consecutive monitoring events confirm that the RAOs are satisfied, groundwater monitoring of the plume will stop, and a plan to decommission remedy infrastructure, including monitoring and injection wells, will be developed.  

Page 33: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

SITE SS023 CMI REPORT  3‐11 EN0224151019SAC/456998 

In the event of potential plume migration beyond downgradient wells (defined by the BGMP), additional monitoring, modeling, or treatment may be implemented as a corrective action. It should be noted that the Site SS023 plume is commingled with plumes from upgradient (Site SS508) and downgradient (CG041‐039). Therefore, not all trends in site monitoring wells can be attributed to Site SS023. 

3.3 Land Use Controls To prevent exposure to groundwater containing COCs above MCLs, LUCs restricting access to groundwater are in place and the potential exposure pathway to COCs is incomplete. 

The LUC objective applicable to the corrective measure is to ensure that no withdrawal or use of groundwater or land uses occurs that would result in human or ecological exposures to contaminants or adversely affect implementation of the selected remedy. No water supply wells or residential land uses will be allowed at Site SS023 without prior approval from the Air Force and appropriate regulatory agencies until the concentrations of COCs in the groundwater are at such levels to allow for unlimited use/unrestricted exposure. 

Successful implementation includes adequate documentation, communication, and controls to protect human health and the environment. The following implementation measures are in place: 

Area subject to LUCs is delineated on the master planning maps. 

Geographic information system database layers with LUCs are updated and maintained, including information on the types of restrictions and monitoring and management requirements. 

LUCs were incorporated into the site approval, well installation, and dig permit process (used for well installation) for groundwater development, excavation, and construction projects. 

LUCs communicated to Base offices that are responsible for well installation approval/permitting. 

The following maintenance measures are being conducted to ensure that LUCs remain effective: 

Conduct periodic inspections. 

Conduct periodic training and post internal notices to keep personnel updated on the presence of LUCs. 

Review the integrity and effectiveness of LUCs during annual reporting.  

The Air Force continues to be committed to and responsible for the following:  

Implementing, maintaining, monitoring, reporting, and enforcing LUCs. Although the Beale AFB commander is ultimately responsible for implementing and enforcing all LUCs summarized above in accordance with RCRA, the Beale AFB restoration program manager is responsible for the day‐to‐day implementation, operation, maintenance, monitoring, and reporting of those LUCs. 

Informing, monitoring, enforcing, and binding, where appropriate, authorized lessees, tenants, contractors, and other authorized occupants of the site regarding LUCs impacting the site.  

Monitoring and inspecting all LUCs every 6 months (or more often if site‐specific risks and conditions warrant it) to ensure compliance and to assess their effectiveness. 

Providing to the California Department of Toxic Substances Control (DTSC) and the Central Valley Water Board an annual report of monitoring and inspection activities that the Air Force has conducted.  

Notifying DTSC and the Central Valley Water Board as soon as practical, but no later than 10 days after discovery, of any LUC violation or deficiency or of any other action that interferes with LUC effectiveness. The notification will also describe corrective measures taken or planned and the 

Page 34: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 3: CORRECTIVE MEASURE IMPLEMENTATION 

3‐12  SITE SS023 CMI REPORT   EN0224151019SAC/456998 

timeframe expected to accomplish the measures. For subsequent corrective measures, the Air Force will provide further notice when these measures have been completed. 

Ensuring that the Air Force will not modify or terminate LUCs, implementation actions, or modify land use without prior approval by DTSC and the Central Valley Water Board. 

Providing notice to the State of California at least 6 months prior to any transfer or sale of property. This ensures that the State of California can be involved in discussions to ensure that appropriate provisions are included in the transfer terms or conveyance documents to maintain effective LUCs. If such notification cannot be accomplished 6 months prior, it will occur no later than 60 days prior to the transfer or sale. 

Whenever the Air Force transfers real property that is subject to LUCs and resource use restrictions to another federal agency, the transfer documents will require that the federal transferee include the LUCs and applicable resource use restrictions in its resource use plan or equivalent resource use mechanism. The Air Force will advise the recipient federal agency of all obligations contained in the Work Plan, including the obligation that a state land use covenant will be issued and recorded pursuant to 22 CCR Section 67391.1 if the federal agency transfers the property to a nonfederal entity. 

Whenever the Air Force proposes to transfer real property subject to resource use restrictions and LUCs to a nonfederal entity, it will provide information to that entity in the draft deed and transfer documents regarding necessary resource use restrictions and LUCs, including the obligation that a state land use covenant will be executed and recorded pursuant to 22 CCR Section 67391.1. The signed deed will include LUCs and resource restrictions equivalent to those contained in the state land use covenant. 

Page 35: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

FIGURE 3-1SITE SS023 GEOLOGICCROSS SECTIONSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SOURCE:

SOLID WASTE MANAGEMENT UNIT 23 REMEDIAL PROCESSOPTIMIZATION DATA GAPS INVESTIGATION INFORMAL TECHNICALINFORMATION REPORT (URS, 2008).

\\ODIN\Proj\Beale\FIGURES\SS023\AI\FIG02-03_XSection.ai

Page 36: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

!.

!.

!<

!.!.

!.

!.

!.

!.!.

!.!.!.

!.

!.

!.

!.!.

!.!.

!.!.

!.!.

!.!.!.!.

!.!.

!.!.

!.

!.

!.

!.

!<

!<

!<

!<

!<

!

!

!

!!

!

!

!!

!

!

!

!

!

!

!

!

!

!

!

!

!

!!

!

!

!!!

!

!

!

!!

!

!

!

!

!

!

.

.

<

..

.

.

.

..

...

.

.

.

..

..

..

..

....

..

..

.

.

.

.

<

<

<

<

<

.

.

.

.

")

39C023MW112.3645.6 J

SWMU23C002MW115.59ND

SWMU23C004AMW114.28

ND

SWMU23C006AMW117.43ND

SWMU23U001AMW115.26NDSWMU23C004BMW

109.61ND

SWMU23C006BMW117.280.28 J

SWMU23U001BMW110.280.42 J

10-487M4MWND

SWMU23C008MW113.70

45.8

23L004MW112.17ND

23SWMU1MW117.45366

23U001AMW111.621.9

23U008AMW108.113.2

SWMU23U002AMW109.7374.3

SWMU23U004AMW115.52

35.2

SWMU23U005AMW116.5920.5

SWMU23U007AMW115.72

31

23L001MW111.59

0.95

23U001BMW100.677.1

BAT-3MW116.414

BAT-4BMW114.16

13.8BAT-5BMW113.87

3.2

SWMU23U002BMW97.8077.4

SWMU23U003AMW125.02NDSWMU23U003BMW120.55ND

SWMU23U004BMW114.07

2.7

SWMU23U005BMW114.4827.7

SWMU23U007BMW114.67

1.7

BAT-1MW57.7

BAT-8MW71.6

OWSM-C001MW16.7

SWMU23C014IW173

SWMU23C015IW204

SWMU23C016IW564

SWMU23C017IW54

SWMU23U006AMW82.2

SWMU23U006BMW2.3

BAT-9MW

SWMU34U002MW113.80182

SWMU34U001MW114.49

7.9

BAT-5AMW113.84

240

BAT-4AMW114.24

284

BAT-2MW115.93

SWMU23C008MW113.70

45.8

100

510

0

M

BUILDIN

G

2539

BUILDING25608

BUILDING2540

BUIL

DING

2548

BUILDING2488

BUILDING2541

BUILDING2538

BUILDING2497

BUIL

DING

2489

BUIL

DING

2535

BUILDING2545

A ST

REET

A ST

REET

26TH STREET

B ST

REET

DOOLITTLE DRIVE

109

111

121

119

113

117115

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIG03-02_SS023_TCE_GWE.MXD 6/8/2015 8:40:45 AM

FIGURE 3-2SITE SS023 TCE CONCENTRATIONSIN GROUNDWATERSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE SS023

0 125 250

FEET

³

LEGENDTCE CONCENTRATION IN GROUNDWATER (µg/L)! NOT DETECTED (ND)

! ND to 5

! 5 to 100

! >100

. GROUNDWATER MONITORING WELL

< GROUNDWATER INJECTION WELL

116.59MEASURED GROUNDWATER ELEVATION (feet NAVD88)(GREY TEXT INDICATES ELEVATION NOT USEDIN CONTOURING)

20.5 TCE CONCENTRATION IN GROUNDWATER (µg/L)

")M FORMER OIL/WATER SEPARATOR

TCE CONCENTRATION CONTOUR (µg/L)

GROUNDWATER ELEVATION CONTOUR (feet NAVD88)

GROUNDWATER FLOW DIRECTION

SANITARY SEWER/IWL CONVEYANCE

EXCAVATED AREA AND GREASE RACK (TN & ASSOCIATES, 2000)

NOTES:

DATA PRESENTED ON THIS FIGURE WAS COLLECTEDDURING THE 2014 ANNUAL BGMP SAMPLING EVENT.

µg/L = MIGROGRAMS PER LITER.

J = THE ANALYTE WAS POSITIVELY IDENTIFIED, AND THEQUANTITATION IS AN ESTIMATE.

NAVD88 = NORTH AMERICAN VERTICAL DATUM OF 1988.

KEY MAP

Page 37: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

!.

!.

!<

!.!.

!.

!.

!.

!.!.

!.!.!.

!.

!.

!.

!.!.

!.!.

!.!.

!.!.

!.!.!.!.

!.!.

!.!.

!.

!.

!.

!.

!<

!<

!<

!<

!<

!

!

!

!

!!

!

!

!

!

!

!!

!

!!

!!

!

!

!

!

!!

!

!!

!

!

!

!

!

!

!

!

!!!

!

!

.

.

<

..

.

.

.

..

...

.

.

.

..

..

..

..

....

..

..

.

.

.

.

<

<

<

<

<

.

.

.

.

") BAT-9MW

BAT-2MW115.93

23L004MW112.170.26 J

23SWMU1MW117.4526.5

23U001AMW111.621.6

23U008AMW108.11

7.4

39C023MW112.36

24.1

SWMU23C002MW115.59

1.9

SWMU23C004AMW114.28

1

SWMU23C006AMW117.432

SWMU23U001AMW115.260.98

SWMU23U002AMW109.7310.7

SWMU23U004AMW115.52

2.1 SWMU23U005AMW116.599

SWMU23U007AMW115.72

1.8

23L001MW111.59

21.9

23U001BMW100.673.4

BAT-3MW116.4143.4

BAT-4BMW114.16

0.56BAT-5BMW113.87

ND

SWMU23C004BMW109.61

ND

SWMU23C006BMW117.287

SWMU23U001BMW110.280.86

SWMU23U002BMW97.80

11.8

SWMU23U003AMW125.02NDSWMU23U003BMW120.559.4

SWMU23U004BMW114.07

7.5 SWMU23U005BMW114.4811.8

SWMU23U007BMW114.67

2

10-487M4MW13.9

BAT-1MW25.4BAT-8MW

3.9OWSM-C001MW

6.3

SWMU23C014IW18.4

SWMU23C015IW22.3

SWMU23C016IW22

SWMU23C017IW27.2

SWMU23U006AMW4.9

SWMU23U006BMW2.7

SWMU34U002MW113.8016.8

BAT-4AMW114.24

13.9

BAT-5AMW113.84

13

SWMU34U001MW114.49

18 M

BUILDIN

G

2539

BUILDING25608

BUILDING2540

BUIL

DING

2548

BUILDING2488

BUILDING2541

BUILDING2538

BUILDING2497

BUIL

DING

2489

BUIL

DING

2535

BUILDING2545

A ST

REET

A ST

REET

26TH STREET

B ST

REET

DOOLITTLE DRIVE

100

100

109

111

121

119

113

117115

300

5

55

5

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIG03-03_SS023_PCE_GWE.MXD 6/8/2015 8:26:09 AM

FIGURE 3-3SITE SS023 PCE CONCENTRATIONSIN GROUNDWATERSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE SS023

0 125 250

FEET

³

LEGENDPCE CONCENTRATION IN GROUNDWATER (µg/L)! NOT DETECTED (ND)

! ND to 5

! 5 to 100

! >100

. GROUNDWATER MONITORING WELL

< GROUNDWATER INJECTION WELL

116.59MEASURED GROUNDWATER ELEVATION (feet NAVD88)(GREY TEXT INDICATES ELEVATION NOT USEDIN CONTOURING)

9 PCE CONCENTRATION IN GROUNDWATER (µg/L)

")M FORMER OIL/WATER SEPARATOR

PCE CONCENTRATION CONTOUR (µg/L)(DASHED WHERE INFERRED)

GROUNDWATER ELEVATION CONTOUR (feet NAVD88)

GROUNDWATER FLOW DIRECTION

SANITARY SEWER/IWL CONVEYANCE

EXCAVATED AREA AND GREASE RACK (TN & ASSOCIATES, 2000)

NOTES:

DATA PRESENTED ON THIS FIGURE WAS COLLECTEDDURING THE 2014 ANNUAL BGMP SAMPLING EVENT.

µg/L = MIGROGRAMS PER LITER.

J = THE ANALYTE WAS POSITIVELY IDENTIFIED, AND THEQUANTITATION IS AN ESTIMATE.

NAVD88 = NORTH AMERICAN VERTICAL DATUM OF 1988.

KEY MAP

Page 38: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT 4-1EN0224151019SAC/456998

SECTION 4

Monitoring Plan

This section describes the baseline performance and compliance monitoring for the ISCO remedy atSite SS023. Performance monitoring occurs in the treatment and transition zones, while compliancemonitoring is designed to show the impact on groundwater quality outside the transition zone.The Central Valley Water Board prepared a tentative MRP (Appendix A, Attachment A3) for the ISCOremedy, outlining objectives for performance and compliance monitoring. The monitoring plan forSite SS023 complies with MRP Order R5-2008-0149-054.

4.1 Recommended Changes to the Tentative MRPThe following changes to the Tentative MRP are recommended:

• BAT-1MW should be changed from a compliance well to a treatment zone well. The ROI of thesodium permanganate injected at SWMU23C017IW extended beyond BAT-1MW during thepermanganate injection. BAT-1MW was proposed as a background well (BW) (upgradient of thetreatment zone), but the actual treatment zone is larger than the design.

• SWMU23U005BMW should be removed from the monitoring program as a transition zone well (TW)because the screen interval of this well (45 to 50 feet bgs) is deeper than the injection interval (15 to35 feet bgs) in this area.

• Injection wells constructed in 2014 are labeled as SWMU23C014IW, SWMU23C015IW,SWMU23C016IW, and SWMU23C017IW.

• Background concentrations section should be revised to require background concentrations of TDSand dissolved metals. Sulfide, sulfate, carbon dioxide, methane, ethane, and dissolved organiccarbon (filtered) should be removed because these analytes are applicable to anaerobicbioremediation (not applicable to ISCO).

• Monitoring of total chlorides will be measured by U.S. Environmental Protection Agency (EPA)Method E300 instead of EPA Method 6010B.

• Monitoring of dissolved selenium instead of total selenium.

• Monitoring of dissolved sodium will be performed instead of total potassium because injection ofsodium permanganate occurred rather than potassium permanganate.

4.2 Performance MonitoringThe purpose of performance monitoring is to assess the long-term effectiveness of the ISCO and EAremedies. Semiannual performance sampling will be conducted for 1 year or until objectives of the MRPhave been met to determine whether TCE concentrations decreased from baseline conditions aftertreatment. Additionally, annual sampling of the injection wells will be performed. Performancemonitoring will be performed as part of the semiannual BGMP sampling event in February and theannual BGMP sampling event in July.

Performance monitoring wells (PMWs) were selected based on screen interval (similar interval to theinjection well intervals) and elevated TCE concentration (greater than 100 µg/L). The PMWs are furtherseparated into four TZWs and six TWs depending on whether they are located within the ROI of the

Page 39: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 4: MONITORING PLAN

4-2 SITE SS023 CMI REPORTEN0224151019SAC/456998

injection wells. Figure 4-1 displays the locations of the PMWs. The goal of the first year of post-injectionsampling will be to evaluate the performance of the ISCO remedy and the need for subsequent injection.Post-injection sampling will be conducted and reported under the BGMP. A list of wells and theirdesignated uses is included in Table 4-1.

TABLE 4-1Well Type and Designation for Site SS023 MonitoringSite SS023 Corrective Measures Implementation Report, Beale Air Force Base, California

Well Type DesignationNumberof Wells Well Names

Treatment zone well TZW 4 BAT-1MW, BAT-4AMW, BAT-4BMW, and SWMU34U002MW

Transition zone well TW 6 BAT-5AMW, SWMU23C008MW, SWMU23U004AMW,SWMU23U005AMW, SWMU23U006AMW, and SWMU23U007AMW

Injection well IW 6 23SWMU1MW, SWMU23C009MW, SWMU23C014IW,SWMU23C015IW, SWMU23C016IW, and SWMU23C017IW

Compliance monitoring well CMW 2 23U001BMW and 39C023MW

Background well BW 1 SWMU23U003AMW

The groundwater samples collected as part of the BGMP will be analyzed in the field for temperature,conductivity, turbidity, pH, ORP, DO, and permanganate concentrations. Permanganate concentrationswill be measured using a Hach colorimeter. Groundwater samples will be submitted to a contractlaboratory for analysis of VOCs (SW8260B), TDS (E160.1), total chlorides (E300), and dissolved chromium,dissolved manganese, dissolved selenium, and total sodium (SW6010B). Groundwater VOC samples withvisible permanganate (pink to purple water) will be neutralized with ascorbic acid in accordance with theBasewide UFP-QAPP (CH2M HILL, 2014c) because of the effect of binary mixtures. In a binary mixture,the oxidant may reduce concentrations of organic contaminants in the sample container prior to analysisby the laboratory (Saebomet al., 2012). A list of analytical methods and sampling frequency is includedin Table 4-2.

TABLE 4-2Schedule of Performance and Compliance MonitoringSite SS023 Corrective Measures Implementation Report, Beale Air Force Base, California

Analysis Method

Sampling Frequency –Long-term Operation

Semiannual Annual

Field parameters (pH, DO, ORP, conductivity, turbidity, and temperature) Field electrodes PMW, CMW IW, BW

Groundwater elevation Field probe PMW, CMW IW, BW

VOCs SW8260B PMW, CMW IW, BW

TDS 160.2 PMW, CMW IW

Total chlorides E300 PMW, CMW BW

Dissolved manganese, selenium, sodium, and chromium SW6010B PMW, CMW BW

Permanganate Colorimetric Ag Sol Standard PMW, CMW IW

Page 40: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 4: MONITORING PLAN

SITE SS023 CMI REPORT 4-3EN0224151019SAC/456998

4.3 Compliance MonitoringCompliance monitoring will be completed in accordance with the requirements outlined in WDROrder R5-2008-0149 and MRP Order R5-2008-0149-054 (Appendix A, Attachment A3). Semiannualcompliance sampling will be conducted post-injection for 1 year or until objectives of the MRPhave been met. Two CMWs located downgradient from the plume and outside the transition zonewere selected because of their location to the injection wells and screen intervals. One BW,SWMU23U003AMW was identified in the MRP as an upgradient well for the development ofbackground concentrations of sulfide, sulfate, carbon dioxide, methane, ethane, dissolved organiccarbon (filtered), TDS, and metals. Figure 4-1 displays the locations of the CMWs.

The samples will be analyzed in the field for temperature, conductivity, turbidity, pH, ORP, DO, andpermanganate concentrations. Permanganate concentrations will be measured using a Hach colorimeter.Groundwater samples will be submitted to a contract laboratory for analysis of VOCs (SW8260B),TDS (E160.2), total chlorides (E300), and dissolved chromium, dissolved manganese, total selenium,and total sodium (SW6010B). The groundwater compliance monitoring will confirm that sodiumpermanganate injections are not adversely affecting the area outside the target treatment zone.A list of analytical methods and sampling frequency is included in Table 4-2.

4.4 ReportingFour reporting requirements are included in the WDR:

1. Baseline Summary/Implementation Report2. Phase II Evaluation Report (if a second phase of injections is performed)3. Semiannual and Annual Data Reports (Monitoring Report)4. Corrective Action Work Plan (if corrective action is required)

This document satisfies the Baseline Summary/Implementation Report requirement. The semiannualand annual reports will be submitted as part of the semiannual and annual BGMP reports. If analysis ofTCE concentrations in groundwater show a decreasing trend and ISCO byproducts are at or approachingbaseline conditions, then monitoring and reporting may be discontinued.

A change in the MRP involves submitting a recommendation to the Central Valley Water Board in astand-alone document. Requests will also be presented in the recommendations section in the BGMPreport. A meeting shall be held with the Air Force and Central Valley Water Board to gain concurrenceon the proposed changes. The Central Valley Water Board staff shall recommend the proposed changesto the MRP to the Executive Officer.

4.5 Contingency PlanThis section describes a contingency plan to meet report provisions specified by the Central ValleyWater Board in the WDR Order R5-2008-0149. The contingency plan provides a general overview ofefforts that the Air Force would take to address exceedances of dissolved chromium, dissolvedmanganese, or permanganate at concentrations greater than baseline concentrations indowngradient CMWs.

A concentration of the selected analyte greater than a trigger level (defined as the greater of twice thebaseline concentration of the analyte or the analyte’s MCL) in a downgradient CMW would constitutean adverse impact to groundwater outside the transition zone. If dissolved manganese, dissolved

Page 41: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SECTION 4: MONITORING PLAN

4-4 SITE SS023 CMI REPORTEN0224151019SAC/456998

chromium, or permanganate exceeds a trigger level in a downgradient CMW, a confirmation sample willbe collected. If the exceedance is confirmed, the Central Valley Water Board will be notified in writing.

If an exceedance in a downgradient CMW is confirmed, a corrective action work plan will be submittedto the Central Valley Water Board for approval. One or more of the following corrective action would beconsidered:

• Increased monitoring frequency

• An expanded monitoring network

• Enhanced in situ bioremediation to reduce concentrations of any oxidants or dissolved metalsmobilized during ISCO treatment

• Hydraulic control of amendments in the target treatment zone

Page 42: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

!.

!.

!.

!.

!.

!.!.

!.

!.

!.

!.!.

!.!.

!.!.

!.

!.!.

!.

!.

!<

!.

!.

!.!.

!.

!.

!.!.

!.

!.

!.

!.

!.

!<

!<

!<

!<

!<

23SWMU1MW

23U001BMW

BAT-1MW

BAT-4AMWBAT-4BMW

BAT-5AMW

SWMU23U003AMW

SWMU23U004AMW SWMU23U005AMW

SWMU23U006AMW

SWMU23U007AMW

SWMU34U002MW

39C023MW

SWMU23C008MW

SWMU23C009MW

SWMU23C014IW

SWMU23C015IW

SWMU23C016IW

SWMU23C017IW

23L001MW

23L004MW

23U001AMW

BAT-2MW

BAT-3MWBAT-5BMW

BAT-8MW

BAT-9MW

OWSM-C001MW

SWMU23C002MW

SWMU23C004AMWSWMU23C004BMW

SWMU23C006AMWSWMU23C006BMW

SWMU23U001AMWSWMU23U001BMW

SWMU23U003BMW

SWMU23U004BMWSWMU23U005BMW

SWMU23U006BMW

SWMU23U007BMW

BUILDIN

G

2539

BUILDING25608

BUILDING2540 BUIL

DING

2548

BUILDING2488

BUILDING2541

BUILDING2538

BUILDING2497

BUIL

DING

2489

BUIL

DING

2535

BUIL

DING

2496

BUILDING2545

A ST

REET

A ST

REET

26TH STREET

B ST

REET

DOOLITTLE DRIVE

O:\BEALE\FIGURES\SS023\MXD\CMI_RPT\FIG04-01_SS023_MRP_WELLS.MXD 2/18/2015 10:46:48 AM

FIGURE 4-1SITE SS023 GROUNDWATER MONITORING PROGRAMSITE SS023 CORRECTIVE MEASURES IMPLEMENTATION REPORTBEALE AIR FORCE BASE, CALIFORNIA

SITE SS023

0 125 250

FEET

³

LEGEND!< INJECTION WELL

!. COMPLIANCE MONITORING WELL

!. TREATMENT ZONE MONITORING WELL

!. TRANSITION ZONE MONITORING WELL

!. BACKGROUND MONITORING WELL

!. GROUNDWATER MONITORING WELL

GROUNDWATER FLOW DIRECTION

SANITARY SEWER/IWL CONVEYANCE

NOTE:

MONITORING REPORTING PROGRAM (MRP) WELLS SHOWN IN BOLD TEXT.

KEY MAP

Page 43: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT 5-1EN0224151019SAC/456998

SECTION 5

Conclusions and Recommendations

5.1 ConclusionsThe following conclusions were determined by baseline monitoring, ISCO injection, and LUCimplementation:

• Most of the TCE mass remains beneath Doolittle Drive as evidenced by the baseline groundwatersampling event. The highest TCE concentration in groundwater (564 µg/L) was observed in a samplecollected from injection well SWMU23C016IW, located along Doolittle Drive.

• ISCO was successfully implemented in the treatment area as evidenced by breakthrough in theobservation wells. The estimated ROI, excluding the ROI calculated for injection wellSWMU23C014IW, ranged from 25 to 62 feet.

5.2 RecommendationsThe following activities are recommended to optimize the remedy for Site SS023:

• Visually observe groundwater from BAT-9MW during the February 2015 BGMP. If water has visiblepermanganate, then analyze the sample for permanganate. BAT-9MW is between BAT-4AMW andBAT-5AMW. Breakthrough of permanganate was observed in BAT-4AMW, and BAT-5AMW was thedowngradient extent of the 100-µg/L TCE plume as of July 2014. Visual inspection of groundwaterfrom BAT-9MW will refine the extent of the ISCO treatment zone.

• Evaluate TCE and permanganate concentrations from BAT-5AMW. If BAT-5AMW has not shown animpact from ISCO injections (decrease in TCE or visible permanganate) by the 2015 Annual BGMPevent, then permanganate injection directly into BAT-5AMW is recommended to treat the entire100-µg/L TCE plume.

Page 44: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

SITE SS023 CMI REPORT 6-1EN0224151019SAC/456998

SECTION 6

Works Cited

Battelle and SteamTech Environmental Services. 2001. Demonstration Work Plan: Dynamic UndergroundStripping with Hydrous Pyrolysis Oxidation Technology at Beale Air Force Base. Final Draft. December.

Central Valley Regional Water Quality Control Board (Central Valley Water Board). 2009. The WaterQuality Control Plan (Basin Plan) for the California Regional Water Quality Control Board, Central ValleyRegion: The Sacramento River Basin and San Joaquin River Basin. Fourth Edition. Revised. September.

CH2M HILL. 2014a. Site SS023 Statement of Basis / Corrective Measures Implementation Work Plan.Prepared for Beale Air Force Base, California. Final. September.

CH2M HILL. 2014b. Basewide Groundwater Monitoring Program 2013 Annual Report. Prepared forBeale Air Force Base, California. June.

CH2M HILL. 2014c. Basewide Uniform Federal Policy Quality Assurance Project Plan. Prepared forBeale Air Force Base, California. Revised Final. October.

CH2M HILL. 2013. Site SS023 Data Gap Investigation Work Plan. Prepared for Beale Air Force Base,California. Final. June.

Saebom, Ko, Scott G. Huling, and Bruce Pivetz. 2012. Ground Water Sample Preservation at In-SituChemical Oxidation Sites – Recommended Guidelines. U.S. Environmental Protection Agency.Ground Water Issue. August.

URS. 2004. SWMU 23 Corrective Measures Study Report, Beale Air Force Base, California. December.

Page 45: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Appendix AFieldwork Documentation

Page 46: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Attachment A1Site SS023 Yuba County Well Permits

Page 47: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098

YUBA COUNTY ENVIRONMENTAL HEALTH DEPARTMENT 915 8TH STREET, SUITE 123 MARYSVILLE, CA 95901 (530) 749-5450 FAX (530) 749-5454

09:37:57 a.m. 06-11-2014

PERMIT TO CONSTRUCT. REPAIR. INACTIVATE. OR DESTROY A WELL

FEE: 414.00 PAID: 414.00

PERMIT# WP0009910 to WP0009913 RECEIPT It 100003655

SITE LOCATION: SS023

APN#:

CROSS STREET: A STREET

OWNER: US AIR FORCE

MAILING ADDRESS: 6601 B STREET BEALE AFB CA 95903-

DRILLING CONTRACTOR: NATIONAL EWP INC

MAILING ADDRESS: 630 LINCOLN AVENUE WOODLAND CA 95695-

CONSULTING FIRM: CH2M HILL

MAILING ADDRESS: PO BOX 9004 BEALE AFB CA 95903-

PERMITTED ACTIVITY

TYPE OF WORK: CONSTRUCT NEW WELL

INTENDED USE: MONITORING DRILLING METHOD: ROTARY

CONSTRUCTION SPECIFICATIONS

CASING DIAMETER: 2" CASING MATERIAL: PVC

ANNULAR SEAL MATERIAL: NEAT CEMENT

WELL DESTRUCTION

DIAMETER: DEPTH: MATERIAL USED:

PHONE: 5306343856

LICENSE #: 953646

PHONE: 5306684080

LICENSE #:

PHONE: 5307889131

GAUGE/THICKNESS:

SEAL DEPTH: 9-36'

1. Contractor will comply with all codes, rules, and regulatloM of the State of california and County of Yuba pertaining to or regulating well construction.

2. Contractor will call for a grout/destruction Inspection at least 24 hours prior to pouring, 3. Contractor will submit a water well driller's report to the Yuba County Environmental Health Department within 15 days of completion. 4. Contractor will maintain the required minimum setbacks to all existing or proposed sewage disposal areas and to all other sources of

contamination. 5. Owner wlll obtain final approval befor!'! placing the well in service. 6. All materials used shall meet manufacturer's speclflcations. 7. All required water sample results will be submitted to Yuba County Environmental Health prior to final approval.

ADDITIONAL COMMENTS:

PERMIT ISSUED BY: JODI BIRD

530- 035-37.-7~ Permit expires 1 year from date of issue

111

Page 48: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Attachment A2Site SS023 Beale Air Force Base Dig Permit

Page 49: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

02:22: 52 p.m. 02-06-2014 1/1

DP -l:4:- 14 . 07 3 A-BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST OATEFREPAREO

(SH lnslructklns on Ravlf'Se} 6/3/2014

( I . Citllflfl~ I• rtq\:ttltd 10 proc:ttd wllh wort~ II SS023

on Worlt Orcttt llo. Conlract No. _F/16903-0~0-9557 , Involving excavalfon or utility dls1ultllnca p&r

allllchld slce tet\, This aroe X hat hn not b"n staked or au rty rna rktd.

Z. TYPE OF FACILITY/WORK NVOLVEO .. o A. PAVEMENTS o D. FIREDETECTION &PROTECTIONSYSTEMS oG.AIRCRAFT ORVEHICULAR TRAFFIC FLOW o 8. DRAINAGE SYSTEMS o E. l/TIUTY a OVERHEAD o UNDERGROUND o H. SECURITY o C. RAILROPD TRACKS o F.COMM o OVERHEAO o U NOERGROUNO XlOTHER • 3.DATECLEARANCE REQUIRED, 4. DATE OF Cl.EAAANCE

5. SIGNATURE OF REQUESTING OFFICIAL 6. TELEPHONE NO. 7. ORGANIZATION Ct-:2MHILL Shandon Sands 788 - 9131

ORGANIZA TlON REMARKS (Use RtVITSt fw 1ddlrJon1l commtnls) REVIEWER'S NAME AND NmALS B. A. ELECTRICAL DISTR1Bl1110N Wr~ ~l{Q(tlv..~ ~~ ti. &}S~~J\ ~ <t\lM\ ~~ B A ....

J/IA s B. STEAM OISTR1Bl1110N ..-....... E I

I~ , C. WATER DISTRIBUTION MfrlltLL-~ Tf'lcD~ B o v t( t( c ,. I

D. POL OSTRI6U110N ./111/T ~~~ v I 'fflPI -g ~ v er l\ ,1'~ ~ l ESEWEROISTRIBUTION t-IA~·Jfll... E F .ENV RONMEJIITAL

~ sc:.omPt>( Wrrti ~~ ~Vl~N- lr ~---~ N l t.A.IiNTI\&... "\>e()n:t:no~ M~~ 1 IM-P 1"- / c. ...,.. -"""t G L v c; ...., I G. PAVEMENTS/ GROUNDS N /_.... E H. FIRE PROTECTION ICd~"P'y "fFr. NFF" ,tA.FC, f Tl- ~/~ E ~ ~r ~vr:r-

( R I I. ZONE

.. !"'-. Ill /'\ G

J. OTHER (Specify) N /tTvff(.kJ...- G 4f: M 4--ll. rct;J) Tll-()r ?;o,~-g_ i ~-~ X.L"' -9. SECURITY POLICE r ~ ~-...>-r-- (~-~- ~ 10. SAFETY (_ ~~ t:_ ~J'.-..Nil}

AJ" tlC (u..cf .)'fuC!. J-............ -

/J 11.COMMUNICATIONS - ......... 12. BASE OFERA TIONS C tlft-r /her-'-£.--13.C.ABLE 1V I -14. COMMERCIAL UllUTY COMPANY

~ r r

(]n,J r 11 I ~. ' .. ,

oTEI.iPHONE l(raPflc, Pi11l ( ~lJ~1ttift~{ cGAS oELECTRIC

15. OiliER (Specify) Ll~ ~ "'" ~~d. ~q,~

16 . REQUESTED CLEARANCE ~PROVED ;}~ ; u.Av. lOjl.,

,.,, ..... ~ 'teiCUA,Pielol Opll~lrJh/'!'$-). Flight) 17a.OATESIGNED fv - ~ ::r:,..,.. '(... /

Af IMT 103, 19940801, V3 / Lerl r

PREVIOUS EDITIONS ARE OBSOL e---------

Page 50: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 02:22: S2 p.m. 02-06-2014 111

-.... ...-

( I

BASE CIVIL ENGINEERJNG WORK CLEARANCE REQUEST DATE PREPARED

(See ltlsfnlaiolls on Rmrse} 6/3/2014

1. Cl.e1r111ce Is requllsled to proeetd wlfll worll a! SS023

on Work Order No. Cootrac1 No. _FM903~D-8557 ,lnvolvitlgucavationorutilitydisturbuc:e per

attached sktleh, This area X has has not been staked or eleatfy marked.

2. TYPE OF FACilfTYIWORK tNOlVED

o A. PAVEMENTS a 0 . FIRE DETECTION & PROTECTIONSYSTEMS oG.AIRCRAFTORVEHICULAR TRAFFIC FLOW o 8.D~NAGESYSTEMS o E. UTILfTY o OVERHEAD a UNDERGROUND o H. SECURITY o C. RAILROAD TRACKS o F.COMM oOVERHEAO aU NOERGROUND XlOTHER-

3.DATECLEARANCEREQUIREO, 4. DATE OF CLEARANCE

5. SIGNATURE OF REOUESnNG OFFICIAL 6. TaEPHONE NO. 7.0RGANIZATION CH2MHILL Shandon Sands 788-9131

ORGANIZAnON REMARXS (Us• Revr~• fgr •ddirJGnill 'ommtnls} REVIEWER'S NAME AND tlmALS

B. 8

A. ELECTRICAL DISTRIBUTION

A s B. STEAM DISTRIBunON E

C. WATER DISTRIBUTION c I

0. POL DISTRIBVTlON v I L ESEWERDISTRIBUTION

E N

F.ENVIRONMENTAL

G I G. PAVEMENT~ GROUNDS N E H. FIRE PROTECTION ~t\'( '-P"lT\... Go..\\ \\~'"1,\..\f'C.I ~rVA1 &.{7... ~~LAUY~ E ....................... c R I !.ZONE N G J. OTHER (Sp~)

9. SECURITY POLICE C-e,--.. ~ L'/ ~. ---.::::::.. - r---I--

ctEA-C- ( ~ JO. SAFETY L:ThtJJlJ. ~_//j~U)~. '- JY<;-~'1 ~ - /

1 1 COMMUNtCATlONS A~ ',_ .21~ ~ '3 fo("'

12. BASE OPERA nONS () II} \

j .. ~tr.lLqc/L'~ 13.CABLETV

14. COMMERCIAL l1TlUTY COMPANY

oTELEPHONE oGAS oELECTRIC

15. OTHER (Specify)

16. REQUESTED CLEARANCE oAPPROVED oD\SAPPROVED

17. TYPED NAME AND SIGNATURE OF APPROVING OFFICER (Chief of Operations Fligllt or Chief eiE.nginesring Flight) 17a. DATE SIGNED

( Af IMT103, 19~801, V3 PREVIOUS ED mONS ARE OBSOLETE

Page 51: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

N

BealeAFB A 100 200

Feet

Legend

vemal pool

swale

seep

wetland

- ditch

- deepwater A M "t. ~ II "' on• onr:~g d~L

Q ProjectArea

DP# 14.073A Title: Correc1ive Measures tmplemeliltatlon ss.e~~

w"''-''''"'w Environmental ll t->r·ote!Ctlc>n Measures before

.. t,r-t•nn work. Keep a copy of Environmental Protection

.IIJV1ealsures and this map at the site while work is being Any questions may be

...... ·-•~· ... to the Environmental d Inspector at 530-634·

The only work allowed 2 hours before, during, or 12

after a rain event is the and/or

rosion control

Page 52: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

v

l.EOEND

,., -~~~~TI~IoiO.OlOII*V.U.l

CJ ~CIICJ>IR I""RO£ WfU.

.!!.] ~.,:~~:'.C:~~l --UIICU~DtC~

• • • • SINITAKI' ~~-/\. C()t<v£\'AIICE

eza~~'!'=t:a~~~~SI!RAU

§ TtAWIMI!Oi'l (I :If ftoll

-~IQWOAAEA(Miool)

I!UffEII (7~ to.~)

0T~W<OmOH(l$CI1M)

NOTii

err to P I • » Wll.tl'fR 1<01111

VllOlMll'o\ • •2flrT

l'RA.NSJflOH: Lf NOlM(U•WX &'leo • JU F'!iltr

FIGUREA·1 SITE SS023 TRAFFIC CONTROL. ZONES SITE SSD23 TRAFFIC CONTROL PLAN sm; SSD23 STATEMI!NT OF BAliiSICORRECTIIIE MEAliURES IMPI..f'N.e.NTA 1lOtl WORK PLAN BEAlE AIR FORCE BASE, CAUFORNIA

Page 53: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

v

• PAOP()(IfDMU.lcx:AOON !HOlLOW SJOMAUO~R)

.:J ICOS'n>IG eM!PUNO ~(X)A'nON

--uN~OA<l'JjjD CCINf."''N4CE

• • • • !WIRARV -COIIVtVANCE

... 1--...... ......, • ... ,_

l"-ltO

• ... --

DIG PERMIT MAP FIGURE 1 SITE SS023

--..... ...

PROPOSED WELL LOCATIONS SHE SS023 ST ... 'TEMENT OF IIIISIS/CORRECTTVE ME!ISURES IMPLEMENT" TlON WORK PUIN SEAL£ "IR FOR(;E BASE, CAUFORNII\

--~ ... .. .

N

A

1

Page 54: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance
Page 55: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Attachment A3Site SS023 Regulatory Documents

Page 56: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

CALIFORNIA REGIONAL WATER QUALITY CONTROL BOARD CENTRAL VALLEY REGION

TENTATIVE MONITORING AND REPORTING ORDER NO. R5-2008-0149-054

FOR UNITED STATES AIR FORCE

BEALE AIR FORCE BASE IN-SITU GROUNDWATER REMEDIATION OF VOLATILE ORGANIC COMPOUNDS

USING IN-SITU CHEMICAL OXIDATION AT SITE SS023 YUBA COUNTY

This Monitoring and Reporting Order (MRP) describes requirements for providing groundwater monitoring of an enhanced in-situ bioremediation (Bioremediation) system at Beale Air Force Base. This MRP is necessary to evaluate and determine whether the in-situ treatment of groundwater pollutants is effective. This MRP is issued pursuant to Water Code Section 13267. The United States Air Force (Discharger) shall not implement any changes to this MRP unless and until a revised MRP is issued by the Executive Officer. Prior to construction of any new groundwater monitoring or injection wells, and prior to destruction of any groundwater monitoring or injection wells, the Discharger shall submit plans and specifications to the Central Valley Water Board staff for review and approval. Once installed, any new groundwater monitoring wells or injection wells added to the monitoring program shall be sampled semi-annually according to Table 2 of this Order. All samples should be representative of the volume and nature of the discharge or matrix of material sampled. The time, date, and location of each grab sample shall be recorded on the sample chain of custody form.

GROUNDWATER MONITORING As shown on Figure 1, the monitoring and reporting for Site SS023 consists of 6 injection locations. Two existing monitoring wells, (SWMU23C009MW and 23SWMU1MW) and four new injection wells will be used as injection locations to provide coverage of the target treatment area. The monitoring network for this treatability study will consist of three treatment zone monitoring wells, seven transition zone monitoring wells, three compliance monitoring wells and one background well. The injection locations, which will also be monitored, will provide a treatment area covering approximately 2500 square feet. The injection depth will extend from 15 to 50 feet below ground surface. Monitoring wells with free phase petroleum product or visible sheen, if present, shall be monitored, at a minimum, for product thickness and depth to water. Sample collection and analysis shall follow standard USEPA protocol. The monitoring wells shall be sampled according to the schedule in Table 1, and the samples analyzed by the methods in Table 2, as follows:

Page 57: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

TENTATIVE MONITORING AND REPORTING ORDER NO. R5-2008-0149-054 -2- BEALE AIR FORCE BASE YUBA COUNTY

Table 1: Sampling Frequency and Constituent Suite

Well Number 1 Frequency Constituent Suite(s) 2

Monitoring Objective

SWMU23U003AMW Annual A,B Background Well 23U001BMW Semiannual A,B,C Compliance Monitoring 39C023MW Semiannual A,B,C Compliance Monitoring BAT-1MW Semiannual A,B,C Compliance Monitoring SWMU23U005AMW Semiannual A,B,C Transition Zone

Monitoring SWMU23U005BMW Semiannual A,B,C Transition Zone

Monitoring BAT-5AMW Semiannual A,B,C Transition Zone

Monitoring SWMU23U006AMW Semiannual A,B,C Transition Zone

Monitoring SWMU23U007AMW Semiannual A,B,C Transition Zone

Monitoring SWMU23U004AMW Semiannual A,B,C Transition Zone

Monitoring SWMU23C008MW Semiannual A,B,C Transition Zone

Monitoring SWMU34U002MW Semiannual A,B,C Treatment Zone

Monitoring BAT- 4AMW Semiannual A,B,C Treatment Zone

Monitoring BAT-4BMW Semiannual A,B,C Treatment Zone

Monitoring 23SWMU1MW Annual A,C Injection well Monitoring SWMU23C009MW Annual A,C Injection well Monitoring SWMU2314IW Annual A,C Injection well Monitoring SWMU2315IW Annual A,C Injection well Monitoring SWMU2316IW Annual A,C Injection well Monitoring SWMU2317IW Annual A,C Injection well Monitoring 1 Well numbers as shown on Figure 1 2 Constituent suite components (see Table 2)

Page 58: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

TENTATIVE MONITORING AND REPORTING ORDER NO. R5-2008-0149-054 -3- BEALE AIR FORCE BASE YUBA COUNTY

Table 2: Analytical Methods

Constituent Method 1 Maximum Practical Quantitation Limit (µg/L)2

Suite A VOCs SW8260B 0.5 Suite B total chlorides, total selenium, total potassium, dissolved manganese, dissolved chromium

EPA Method 6010B various

Suite C Total Dissolved Solids3, Permanganate

EPA 160.1 Hach Colorimeter

10,000 1.0 mg/L

1 Or an equivalent USEPA Method that achieves the maximum Practical Quantitation Limit 2 All concentrations between the Method Detection Limit and the Practical Quantitation

Limit shall be reported as trace levels. 3 Total Dissolved Solids (TDS) data should be correlated with electrical conductivity

data. Conduct TDS analysis on 10 percent of samples to confirm correlation

FIELD SAMPLING In addition to the above sampling and analysis, field sampling and analysis shall be conducted each time a monitoring well or extraction well is sampled. The sampling and analysis of field parameters shall be as specified in Table 3.

Table 3: Field Sampling Requirements

Parameters Units Type of Sample

Groundwater Elevation Feet, Mean Sea Level

Measurement

Oxidation-reduction potential Millivolts Grab Electrical Conductivity uhmos/cm Grab Dissolved Oxygen mg/L Grab pH pH Units (to 0.1

units) Grab

Page 59: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

TENTATIVE MONITORING AND REPORTING ORDER NO. R5-2008-0149-054 -4- BEALE AIR FORCE BASE YUBA COUNTY

Field Test instruments (such as those used to test pH and dissolved oxygen) may be used provided that:

a. The operators are trained in proper use and maintenance of the instruments;

b. The instruments are calibrated prior to each monitoring event; and c. Instruments are serviced and/or calibrated by the manufacturer at the

recommended frequency

DISCHARGE MONITORING The Discharger shall monitor daily the discharge of water and amendments that are injected into the groundwater according to the requirements specified in Table 4. Each amendment addition shall be recorded individually, along with information regarding the time period over which the amendment was injected into the aquifer.

Table 4: Discharge Monitoring Requirements

Parameters Units Type of Sample

Injected Volume gallons per day Meter Amendment(s) Added kilograms per day Measured

ESTABLISHMENT OF BACKGROUND CONCENTRATION VALUES The Discharger shall develop background values for concentrations of sulfide, sulfate, carbon dioxide, methane, ethane, dissolved organic carbon (filtered), TDS and metals (as noted in Table 2). Background values in groundwater should be developed by averaging the respective concentrations reported in background well SWMU23U003AMW. Alternatively, the Discharger shall develop background values for respective concentrations reported in monitoring wells listed in Table 1.

REPORTING

When reporting the data, the Discharger shall arrange the information in tabular form so that the date, the constituents, and the concentrations are readily discernible. The data shall be summarized in such a manner as to illustrate clearly the compliance with this Order. In addition, the Discharger shall notify the Central Valley Water Board within 48 hours of any unscheduled shutdown of groundwater extraction wells associated with the bioreactor.

Page 60: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

TENTATIVE MONITORING AND REPORTING ORDER NO. R5-2008-0149-054 -5- BEALE AIR FORCE BASE YUBA COUNTY

As required by the California Business and Professions Code Sections 6735, 7835, and 7835.1, all reports shall be prepared by a registered professional or their subordinate and signed by the registered professional. The Discharger shall submit semi-annual and annual electronic data reports, which conform to the requirements of the California Code of Regulations, Title 23, Division 3, Chapter 30. The semi-annual report and annual report shall be submitted electronically over the internet to the Geotracker database system by 1 June and 1 December, respectively, of each calendar year until such time as the Executive Officer determines that the reports are no longer necessary. Hard copies of semi-annual and annual reports shall be submitted to the Central Valley Water Board by 1 June and 1 December of each year, respectively, until such time as the Executive Officer determines that the reports are no longer necessary. Semi-annual reports shall include the following minimum information:

(a) A description and discussion of the groundwater sampling event and results, including trends in the concentrations of pollutants and groundwater elevations in the wells, how and when samples were collected, and whether the pollutant plume(s) is delineated;

(b) Field logs that contain, at a minimum, water quality parameters measured

before, during, and after purging, method of purging, depth of water, volume of water purged, etc;

(c) Groundwater contour maps for all groundwater zones, if applicable;

(d) Isocontour pollutant concentration maps for all groundwater zones and all

major constituents of concern, if applicable;

(e) A table showing well construction details such as well number, groundwater zone being monitored, coordinates (longitude and latitude), ground surface elevation, reference elevation, elevation of screen, elevation of bentonite, elevation of filter pack, and elevation of well bottom;

(f) A table showing historical lateral and vertical (if applicable) flow directions

and gradients;

(g) Cumulative data tables for all major constituents of concern containing the water quality analytical results and depth to groundwater for all monitoring wells for the past five years, if applicable. Raw laboratory data shall be provided on CD or DVD and included in the report. The Central Valley Water Board may request additional data as necessary;

Page 61: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

TENTATIVE MONITORING AND REPORTING ORDER NO. R5-2008-0149-054 -6- BEALE AIR FORCE BASE YUBA COUNTY

(h) A copy of the laboratory analytical data report;

(i) If applicable, the status of any ongoing remediation, including cumulative

information on the mass of pollutant removed from the subsurface, system operating time, the effectiveness of the remediation system, and any field notes pertaining to the operation and maintenance of the system; and

(j) If applicable, the reasons for and duration of all interruptions in the

operation of any remediation system, and actions planned or taken to correct and prevent interruptions.

Annual Reports shall contain an evaluation of the effectiveness and progress of the investigation and remediation. Annual Reports shall contain the following minimum information:

(a) Both tabular and graphical summaries of all data obtained during the year;

(b) Groundwater contour maps and pollutant concentration maps containing

all data obtained during the previous year;

(c) A discussion of the long-term trends in the concentrations of the pollutants in the groundwater monitoring wells;

(d) An analysis of whether the pollutant plume is being captured by an

extraction system or is continuing to spread; (e) A description of all remedial activities conducted during the year, an

analysis of their effectiveness in removing the pollutants, and plans to improve remediation system effectiveness;

(f) An identification of any data gaps and potential deficiencies/redundancies in the monitoring system or reporting program; and

(g) If desired, a proposal and rationale for any revisions to the groundwater sampling plan frequency and/or list of analytes.

The results of any monitoring done more frequently than required at the locations specified in the MRP shall also be reported to the Central Valley Water Board. The Discharger shall implement the above monitoring program as of the date of the Order.

Page 62: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

TENTATIVE MONITORING AND REPORTING ORDER NO. R5-2008-0149-054 -7- BEALE AIR FORCE BASE YUBA COUNTY

Ordered by:

________________________ __________ PAMELA C. CREEDON, Executive Officer

_________________________________ (Date) 09/17/2014:RRR

Page 63: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Attachment A4Site SS023 Lane Closure Notification

Page 64: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

“One Team … One Fight”

• WHO: National Drilling with oversight by CH2M HILL

• WHAT: Close westbound lane of Doolittle Drive and sidewalk along north side of Doolittle Drive

• WHEN: 14-15 JUN 2014 (Weekend)

• WHERE: Doolittle Drive between A and B Street

• WHY: Install an injection well on the north side of Doolittle Drive

• IMPACT: Work will be conducted on the weekend to reduce impact. Flaggers will be used to control vehicle and pedestrian traffic in working area.

Road Lane Closure

1

Page 65: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 08:12:28p.m. 06-15-2014

'------· "---·--~---------~·-~-----------------.-

0 C• TRAFFIC COUNT ALONG DOOLITLE DRIVE (East Bound) -

0 c

SITE 55023, BEALE AFB yil""

Date/Start time: lo/IY. /11.\-Name ofF/agger: fu-tciC¥- IJ,V.\\e0

Time Vehicle count s- ,c:; {I~ \ 6['AL\ '>6\).tlnJ

~·L/OPr- I fJ~/( Ll riJ CGt<~J '3 ' y? ll~ I ' g l :,.:vclc "8'·VBA.- I 'BLL>i'- t<.t-1. -rcvo+A t.J '?:so Jtt1 1 -p,-,e 7"'-{:,f

6- ; _, f' """ I WJ~ 1-r-e CL<--1--

9 oa /4-hJ l fJi=h -.=or

qo2 ,1JA>1 I '!,r•y r,-<-C h,

<f, ;J-c) A-~ I .:::;"' ~ u- t,eo Cl'tR q ~ o-s J>'l·- I t.lf-1! t[ .:;"e \)A ,_j

'7: 30 j!i ,~ l IV\v>to't/'--0 f'..(lf'C\ I ')H-

cr;:,c;i+~ I ~~~~~t 5""'l L C."iL

CJ ::?'A·- I {-:tA ,.,_,L . . W f-\ • \--!" q\5o A-~ ~ I II f'i> C.f\ (L I C.ll-<'•1 ('#-

q:sgAfl-1 ()-_ S ""-A L l c 1'.-1'- ':> jo· ?-I A- I J<:'«'P ( wH,t~

!>:>

r6·. -s<: 'J. " ' ·I ..... "1lob(,C C.:..l\A%e" I - ~"""" s Jo~IL _c

/CJ.~b t a \1."'-\ cc."' liD v {0: 'f3 [ C<LV~ 4 \):,/(L

I o• Y ") I ..,."'"ll C:frR ~f 5o1wt' s.,tL\

ro:rr, I (vLL ·wu: 1:b \)~6

- ----~-~-------- --

11/26

Page 66: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098

0

0

08:13:03p.m. 06-15-2014

TRAFFIC COUNT ALONG DOOLITLE DRIVE (East Bound) -

SITE 55023, BEALE AFB I 0

, s-'> fl>-"

Name o!Fiagger:?~l(/L !Y)ulL!'r- . Date/Start time: {;-;{/=) '/

Time Vehicle count I O: '5'7 Pw /(..,alP M•)..fi C<l!f>~

f/ ', o I P"" r f!.!-<tv~ I · · ' • """- f.{a r-1> A

1{10'7,~ \vl},;~ ~l>il-. ' ,_,, '2j• \J I v

II' 1/4,. 1lL 1tt1L T-0'/Jt-/f 1 Q_,Jtj/..

1( ~ f( fl/1'-' 1?t J4"1L fJ fv Jtl:>.iv

}}! 13 Jtl\.. I Ci~vt>2- '\{ 1'-,J

/(:r<:; (\'"' I Go"Di< fi ....::; M~!..1-- c~ f-

I I :;z (j> \ - :) "'" C-L '-'-' 1+ l ~ eJ'r(2_

J ~)I' Wt-1, +-c T\Lvc.-(L / ?;:, I 1 co

' &0 I IZ~ eM- S"-' ~\.l-•

It '').q I c,a.e:-J \}~;J

f('JJ I P.t.v6 '})o\;)66

12/26

~

}{!J/ I Grwsq I~ Nl-klt/ l-cM o ,-6 1'-E-\ c ,._ s 1 b 1

I f&l Ll ( bP~~\ I

Clu Ill

/[:'!'\ I i28b <::.ll cfj (' t'-'156

II :y'J ( GRf:'1 .,.~~

l f:'·l q /lj'll'tcJI- --10v tifF {I :<Jc I U!l.tYI(~ C•IWI'c- Hvii>Y>

I 1'-S'J \ /JI'fv lh\l6 e-f/; 5'6 w!l,J.e. cUt "''-'v I'}.:,_,.--, b 0 J!_ [', C(-i<Oy r•~ fi'LA-

1 ~''\ 'f..~\l rvo-t> fU~-·~

Ci Flogger's signature/Company/Date/Time: ~tl.?.t.~f.. .. ~.~-~-':.s.&! ........ 6 . .C::!.~1. Lf /.?-' 1\ f'!-

····-········~~~

Page 67: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 08:20:53 a.m. 06-17-2014 16125

SSot.-7, lf')VlCf't; .09. '2.:2.. <..L-. 0 1

. ' .. Xiti '~-- ) .. ~;:'';1 TRAFFIC COUNT ALONG DOOLITLE DRIVE (East Bound)-

SITE 55023, BEALE AFB

if I Name o F agger: A~~ q N\ . • Lf£}\} Date Start time: - I . I v: .=-:· --:.:J. ,( = . .f -· (A-);:.-~ Tine /1 7 ).:;.&~i'" ( A-X'~·vehicle rnunt( ~)

g:5b,._ \...._/ ~ l;,l: J.l 1 ~

Cj· o3/l. }:).' 3 \ l q: d-o A-·• 1):3f' ~

q:~'l fh>t f').! 'JOJ I q.·~c,t'li" j): '-1 b 'I q:~j lh~ /;)! 5 s I ID ; o I l I :I fJ I j0'/-1 I! n ?-

0 !D•:n ,A ~v() . 1

Ia {h I ;y;· I

I 0 •. 6 I ?- 17- ~ ;}-.~ ~-

I : I I ;)'1o ~ I & 9'-3_5 1

wn I .;;._:.YO I \ I, y J )- '3'-o/ I I ~~(, 3 "..0,: . t I ~ ~~ I 3-. or • I

1:)-~1'-1 ?- j; -. 10 '5 J:f,,/6 3' tq I

117-\ I B if- 3·· '). 3 ld.'.d-\ ) J.'·]/

';:' & 'If ::::=: if (:;, L~\ ·' .1 .l'r

0 1 _c ............... t .... -.. r .. --ri.~ ... · .. ! .. L/ .. • Flogger's signature1 Campany1 Date1 , ime: ./.~·:.::: ..... ?.: ~ .. ;,... .. ~ ~;:-:==="'---~

101 A" 7 5''/ Fv«- "'H d ((Met" 3 I 3 I f!>'

Page 68: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 08:21:22 a.m. 06-17-2014 17125'

SSD7..:'2,

LfS"lJ:>9'1 'i>.OY. ?.-7- .u_, 0\

'('; TRAFFIC COUNT ALONG DOOLITLE DRIVE (East Bound)->,_-/

SITE 55023, BEALE AFB

Name of Flogger: 7fl+~1 C-1'- ,N')t;LJ..{(,J Date/Start time: ~-1 c; '1t}

~-TIME' ~ JGii.cLr: Vehicle count

'- ! rJ!} L ; 15 ~ :3( / ?o6'1cJ~ s~o5 I 5': Dl I :>: ~ <; 1 5' $b )

' ..

- . ,'!

•' •• ~ ' '"'' ,,

() Flogger's signature/Company/Date/Time: .. r...~ .. ~ ..... f..~ .. !;s..: f L/ Gf~r--

Page 69: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 08:13:33 p.m. 06-15-2014 13/26

'<:"---- , __ -

/j

}C!P3 \ .

,... TRAFFIC COUNT ALONG DOOLITTLE DRIVE (West Bound)-(

SITE 55023, BEALE AFB (1,- I'(- /'f

Name of Flogger· . .-h-0 t e; f-, .vJ

Date/Start Time· 8 o o r/r1f7

Time Vehicle count

r

c 9: ol II-"'- r C( '• I ~ 1\'\ I

4'.1) "'" 1

1 Oll • L -t'O>

rr

. Flogger's signature/Company/Date/Time: f .. k ... N?.":.I~ ........ 6/f.1/19.... (;.stJ f.

c

Page 70: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 08:13:57p.m. 06-15-2014

..

(--; t · . TRAFFIC COUNT ALONG DOOLITTLE DRIVE (West Bound)-

• • "~ -'

SITE 55023, BEALE AFB

Name of Flogger: J o!Z. {., e_, /-j;'~ {; C<f- y I,_)\,;_ ' ~ (;,_,

Date/Start Time: '0: DcJ !A-'?

Time Vehicle count

4~ tr~" ~~-t> .::::u.r-I C?J•"f.t.'{ ca..--

~ -~ "~ I 0 0 A-"' I p:l'e M''-"-1< • 1. T"n 7 "e/'

/(') ~[ ;.~ J ~r£L.\.i Ccv-,O(J 111'1 i j,j,:J;c ,,,<.!< vrJ

~!." 'P'.' I /31~'<-tc c•' I 0"-/ d-i1J ' ~cav ca·"

,_;~; ;;,' I.:'JIU<ir_ 'SUJ/

1 S 'tfl'-t!r CCtY-

tD3~ nftJ i "' q c; . In'\

I wl1 1"7 f(c..t·, VI I will'~ t~V

~.'0~ .!i ')-. ='3 I C<l\r

,o s,- t,"' ; '8 r:;;r' c~r

105(, "'- T f'V'

t"~) """ ·~u( 11-M I ~<I< 1 ~~ r~r

< l: {Z ·1"" 1/ '.() 1/-C

t~cy v='-I ,'_p .< «. V

i\ \'t ";'"' I 6~~~ -1-<ij- 'I:: I I.e f.t VI I -z. 3 ~ lfl'-\

. zi;' ,._...... 1 tut...;f-e- cQ..r ~--"<~ I ""~l+<- +n<'

. .J, e:_ar It'. G7 1 6rB-Y car rt ~ 7./f lr 'C, .~ 1 I C.( f 1 fl(«c: ca..(

I ,(, cY ;ar II· J b II ·,, C''<V

'!t~ 1 ....,t.lt_ Cr:IJ~-.. I j f!Jx~ . ,Ji<l, vf'

.~~~PI'l 1 R,t:J Cll~"'-

1 &~r """ 12 :).~ ~"' I ,VV: I iJ. 9, > 1'1 1 "'' ,/e c ... -

,'il~ '?":, J l~ecJ CVj

J ;, '"·'· c,.... .. m I T'~~ '!J{ To lo~ 'In t tv I Y"

Fl ' . t "C ·'D 'IT· 1/li) n friel.v'f.~ (;- tl(-/4 agger s Signa urel' ompony1, ate1 <~me: 0

_ .. &, ............... ................... ;. ........ ..

14/26

Page 71: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 08:20:10 a.m. 06-17-2014 14125 -:J.:>Ut-:>

( TRAFFIC COUNT ALONG DOOLITTLE DRIVE (West Bound) -

SITE 55023, BEALE AFB

Name of Flogger: 1 oE. t e ,f.•~;;, Date/Start Time: C--15'-''1 (o01fi11

Time Vehicle count

'11' 0 /1"'1 I (. (l ,-'

'b -. o;; ltM l Cqr

')s. : tb lbfl I CIV

't, "' '-l I A-Y'I I Cq_r

"!' "J--.1 ~Yfl I C.<~.<

. ,.,. I - .. ~"h

:~~cl '"" j.ltvYl /!-"' I ~- 'fl

I Ct '/J ,<fl"l ~ ~vc~

'//I~ n B. f" ' A-,

·~· ,,,

c ~'tt,_ ~~ I ;«ecJ· W'"!J/111 .

..

f/3<J ft/1) )_ ~'(V"

""' ,-, r •

:~\~ ~,::: .P.. <Jc ";' c.L v . · .. * /{ JO P'~ ~ car .

. V/0 2i11 C.llY

(1.'(/• ""' l c .:tY I~ ,, p,t) •

1 cqf

I). :)o lil ,.., ~~ I c"-"'

1 -r,.~<-A

I. ,~o ·, ) P.'; ~7,';" I , rvr-

:,or t;,'1 1 "( rvc.

m 1 r•"" ! ~ ~ ~';;; h ';,.":; ,_.,. p:> fl'l ' C<V

'J.,I'} rm I fir« rr~lt,

Fl ' · t 'C .!D (T' _j,,, /L Mfw£ 6-lf-IY agger ss1gna ure1 • ompany1 , ate tme: (j.w...&.:2 ..... '" ..... .................................. .

\

Page 72: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

530-788-1098 08:20:33a.m. 06-17-2014 15125

':::i';::,DI..-:'>

!fS\9qq '6. o"L 1.-1.-. LL--. o I

( TRAFFIC COUNT ALONG DOOLITTLE DRIVE (West Bound) -

SITE 55023, BEALE AFB

Name of Flogger: J o/Z. l..eAfs'~~

Time Vehicle count

ft~ ~~ R "'c:l' ~¥0 p.~ J G<sr ~I /V1 I ar

3 °.$ Prr, . ->. n;, 1 co// I Cq

.H- ~~ I C<tr f. ' I 'rv<

.3~ P/71 1 ~~::: 11 ~o ?m.' " car "f'fo p':rtt 'ac-"Y

C<O)

ft f/11 I C<tY I rJ;J~

(' "-·

{~~ /71>\ ~ c;::;. ~ l1~ ~~ b revck

cA.Y .5 '/0 '{'M /).. '"(rVC~

Flogger's signature/Company/Date/Time: ~~ .... fi/..~.~f.. ..... (,.c.J{:!..i...

c

\

Page 73: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Attachment A5Site SS023 Field Notes

Page 74: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Location 'S:>-f.V 5J0?..'3 ...:JSV\U:. -.;(fjl Date nq\:.. Z.,(J

Protect/ Client S-;, <>1.3 Wei' (,At - A.ff;({.J.._

SL!W/!fl1 J:.jll\J w.~·•L.5 /.{<;,'l'!O-OC).~-C\L,01.-

H-J~--"::r-~~-=-~.:.~-::::~·~r':"""-'-=-·=---·----·-··------T• • ·, -~- N~C.- I.Dt-JviO (~

.'j---~'--'--'-'-, 'i-;-"--- ---·-•-·- --- -----·:--·-·--L-,. ------------------- .... -

!1'-!o f"' S!T~ ) HoLPLN&j "TII:;:.J..Cm,t:. 1'1<\IC~T:!N(;. , t:.,fi.VJ:; ----~-------·-----------~------------ ~----· --------------------

lfNl>lt""-. ~11.01... "c"!- HAU I> l f-1.>1..> TO. A•.;.'{) ltflLl--- -t:.ful,-,t\~r;~;.,,z~-:;-t._~~~--.i~i-Tit~-Ll.~~ - --

---·-- ·- -- ··---·- -· _____ , _________ ------- - ······- - ._ ___ ------llfL-A.tD (,.Kr£ . · ..

(-·--------·-- ... ---- -- ----- ........

\\;;Q Jli'&;:"J.N. Sc'<VV<!'"'SNC.. i· iJ'if.'viC.. Sl.tMIIJ''-/tJ®l.Mc;...t

--- -~~~ ~~v.rv.;o4~~W-~Uw~-: - - -1-...zv OoiVI!- >-.13TH .fl.i"''UZ.'J ~ Jr""-if l\.vWN G, .!"1'1[) · . ------·---- -- -----·-----~--------·---1"--------------- --

i--------~~'l.-0_':' _r:_NL-. _P_'-'_"'<1.1.~7 (..<15 '! ~!.-' _:_ ____ -------

~~~ _R',<J5f'_lf~. S"'LV~1-Jt;._~":'_~\V~I ~rz.i"'l ~ .__ _ , l!j 6P 'Z.:?S'i.J"t u U'1 w A'-'<D 10-'f 8ii'~Nt'"/eotW.

·- ---------- ---- -------·---------•---- -------- ·- -------------- ---- ---

lA:~Av<>U:;i S7.fc . ' . "''""'------ --- _,_ ----- ______ _L_ __ . __ - -' . -- --. :. -- --- -- -

~C, 7V ftr/6. tr.rz. 7!" UCF!TIC l-.----~~ -·--- __ : . -- ___ , --- --- ------

J'I'IW

----1------~

----- ----- - -- - ___ , _____ _

Locat;on Y,..,.\o..../.'i;j, > 5',\<- "'i')<>! • ."!> Date C. b\ {\ '-\ -Project/ Cl~€flt S5o.Z..~ -"f;;ce:..J A;: Gf:~

lA ..._., 'i,4., ·\ • ......-....... <!~""" ........ "" n ... c '- ... \ '

Page 75: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance
Page 76: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

" 0 N

I ~

I

"' 0

E <i

0 M

;; ro 0

ro

"' 0

I 00 00 ,...

I 0 M ~

Location Q-€0.\<2. A 'r- '6 -'S\Je :----Date (p / B I JY ProJect 1 c;;ent ;:£:o2:~- \Sro I B£Gec.'

f\e\c\ ?ceq Y.'5lo"f!S.Q9.-z..'Z..GL· OJ

Locat1on~\f:. ArO-~?~ Date!J21l!:t{I'T

Project i Cl!ent5{-DZ.'3 \'Sc D /ArC. ec.. 1'><\o'ci\\:zn..\j 0 a !f'Sio'l'ffl. 0"1. '2.7.-GL-~l

Page 77: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

" 0 N

I ~

I

"' 0

E <i

"' 0

m 0

ro 0

ro

"' 0

I 00 00 ....

I 0 m ~

Location oc;a.1e;. Mro- ;:;:>;;::;ut-2 Date {JJ-\"t-\'1" Date fo-1'-t- IY.

Project/Client ~~0-z.¢ \S,CQ /Prr-C6C-'ISID '1~. o'\.u. u.. o \

Page 78: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

" 0 N

I ~

I

"' 0

E <i

N ~

'i 0

00 0

ro

"' 0

I 00 00 ....

I 0 m ~

LUl-Ct!UI! '\ .,...........,,_ f •1 V

ProJect I Client ?$)7 ·3 \S C.o J. AfcEi G

i::><\\\\ne, · SWMIJ 2 5Cl>\1l W 45l.T\S.o<\ .22. .ct. .o\

LocationQt::XA\=t:< n~ p-~1:>0-Go ~ Date V(l'":'1'fl'-t

Project I Client ~$02. "0 \~C.O JAfC'G G

. ~rl\\iD~ S'f'l MU 2.3<.0\1 \VJ 1/-SID~B. o't·'2-2.d-·D\

Page 79: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

" 0 N

I ~

I

"' 0

ro

"' 0

I 00 00 ,...

I 0 m ~

~7

Location~ AfB ·'S"E£)"2.2 DateU!I!'411'3 • Project I Cllent ~"2..'?:> \<;.,c 0 / A Ff.,GC.

W\~£t '<SN\J\1)2:6C.QD IW . 't§\tl'I'O. o'I.'Z.Z. c(..O l

LocationE:faa.\e A~'B- ~'S.o2'3oate ~/1'-l/1'+ project 1 Client SJ;:,c:a... 0 \<;.c,o ./Af(C6G

C.0 (\'Ss\ruc:\"\01lb'f\M\l1.:~.o n 1\tJ

Page 80: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

" 0 N

I ~

I

"' 0

E <i m N

00 0

ro 0

ro

"' 0

I 00 00 ....

I 0 m ~

36 Location2etA\e ~·fe,- SS.<:::Sl-"3 Date !.o/l'-f/ \'t LocationBea\e Af"S!>-SS{)'2."3 Date LriLf-14

'S\.lte SSO"Z-.3/A fc..66 Project/CiientS'So2?, \SCb / AfC.E!f.(,,

Page 81: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

"' m 0

I 00

"' .... I

0 m ~

,,"._

0

38 Location '6eQ.\e Affj-..:£023 boteJr II.\ ~ I~ Project/Client 'i.SD'l. '3 \S(,p //>sfcEG

0 0

Page 82: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

"' m 0

I 00

"' .... I

0 m ~

40 ~.,.;J'U~ L:::'\ Location @le AFB - €;1 IZI~ I h-.::!!! Date Co-IS"- 14

. ~ect_JCiic:t ~0 · \S(.O / Af(£(.,

~ nmtt of o~ l.f~IQ.o"'. 21-· c..~.- -o}

0 0

Location BeNe Afn --fficrl-3. Date (r !S-Jt-1-

Project/ Client "'-C..O"l-3 l~C..O /Af(£C. •

41

tf€>lp <J'lS.O'I-1-Z 'Ct..ol

0

Page 83: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

"' m 0

I 00

"' .... I

0 m ~

42 Locotion £!.e::.\p, A:EB~ S.$r)'2 3 .·· · · . Date ( u- \ 5- \ "i Project/Client S<;o2? \Sed f&f'GE:;: G

' l><H\\n~ 5'V"{!IAU=t..~GO\u IUJ

--,-- ... ----.- ----

0 u

Page 84: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

"' m 0

I 00

"' .... I

0 m ~

0

Location '?fo\e f's1"'6 · S.<;.o7. 3 Date {o- \'i -l'-t 45

• ' J

~-

' ' : ·........,r

Page 85: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

" 0 N

I .... I

'"' 0

E <i

"' 0

"' N .... 0

ro

"' 0

I 00 00 ....

I 0 m ~

Location 13,e..t.,._ tl~l? 1 S'SCizo Date {./{ (../ ( 4 t:so=• /A Pc.E.c:...

Page 86: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

" 0 N

I .... I

'"' 0

ro

"' 0

I 00 00 ....

I 0 m ~

location ~--vz.. A""<G!. v S~o>'l.. "} Date !./ !4!/t..i

Pro)ect I Client 5Jio'l...1;> _$L<.(.li!:>>-(1-'A.,t;:..4.c:'-:_ ______ _

1 __,.,..-_"1 LJ .c;""(, "\4\~' o1 ''/.. 't., (..t..,;:, l

Location b4l .. l.. -1>-~ 1 S<,o'L--, Date S.( l l../1 o.j

. . <)"j~'t.~ ').c,<.."O (At:~ t..

145-IIJ

Page 87: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Location ~\.t_ A~'Q 5$<>"t-:7 Date Cc./14"!-\ )~fC'it····i L;,catiOO . '~-~ p.:ti:!z I ',"><Ot.-7 Date 6 { \1 r! <l

Project I Cliont 55 .. "t-'? -1~,.._(_,<>;,:(f_I_A~f=~C~f!i...:'-:_ ______ _ .·.iJ!'••pc~;i f'roi<>cl/ Client 5561 ... :} 'S.SC.c (-f. r; U. c.

c. ,....e\:..4-w~• r.~so:;..,_4.i' . ..s :t:r .... c L. o \ t~•'it:~"· W:...11 ,~-,lc-41\..\-\<¥\

Page 88: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Date ~(~lf.l ~\.._M'5 1 5Sot...j Date~,/r:t(il\

Project i Client "i.,=•.:;. '\_<, '-~ /Ac1c- '-'f.'- Project; C!ient _:S'r:'Sl!CI-~c!~.![~·"'f)=C::".J.(_£.~~,_ . ..:'-::.E=._<....,_ _______ _

:"'"'=<.=t=\=,~·ss:'-,;"'l[u=<:s:w~-=..._=c.~;=, ~r.=r=u~:t="'O."'::::''~~.;~It:":"'="'~'.C:""=::to="-~·=c._='-=· "=:''=:=:.__ __ ;[Jc. ,· w,g,l\ \,..<,\: ... \\ (~ w ..... J.nc.., \-l\,~ 2

Page 89: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Location &:!_ak.... ~}~! 1 <;,",c"1C..'J>o Date fo /1-:j,//'-' kOCation ee:A~ ARJ .)~ rE ·JJ 0~"' Project/Client S'So"t....-2 1-S '-"' / A~L

I ~~~~. ~~~s~o~~~7~·~~s~~~~· ~~~~------

wc:..l! ,n5..1o<>ll It~""' 1.\S"'(. '\"t <(. 0'\ :1.."- • CL.'. to\

Page 90: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

56 Location«~ A.Pll' ,\"tn SSlltZ? oate6bta 11211.1

Project/ Client sso~'3 .((t-o IAEa;c Project/ Client 5£1:>'7./I '.I:SC-0 /4:1=-t-iJ(_,

I.J£<LI:?€t4!Lbf'i!\t;.tt ttr(."1'1(- 0,. 'L'Z.•CI .D·l J.f!bf2qr'.69. u -CL . 0 I

Page 91: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

< 58 LocationiJeA~.A. Ae«. .tm- sso"lJ\ Date OGI3-'UI'1 Project I Client Sj~':i' :I.fCD (A>"'C.£L

l.vax,.. @v.t.uo'l"~ 4n.q9!(-Pf,.(Vl.u.-. o-t

59 Location flf:AL~ ArU S't.TL S:fD 1£-'1 · Date 0~ !3-'tol'1

Project i Client 5' I" 'Z./l 'L!C.b /Af:v&..

W.u.L Ob/£LD,<It\.CJ\!r ~.r'6'7'1C.Q'\.--L'l..CL...O\

Page 92: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Location fl,blJ...,.e Al=f? .Ci7'4: .ff"¢73. Date 06 [":f 'h!Vf

Project I Client s roll.-'1 uw /A fbEC.. •

Wi.u. O~V£\..J>PMtN.t= 4'rl.q9f'.:o1.'V'Z-CLo'

~;Ch.cication ffEAL.£ 4<='11 '.1)'1".,(. lfo?.r-:1 > Date'"6 If' 'h1&.)

,Prc,ject/Ciient Sso-z.:'J 'IJCO /Af"'£-~L.

krt:' 'I[. ac), ?,;z,- u ..... oJ

Page 93: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

52 Location ~EAt-(. Af€ !I'Tf ffOv""J Date'Oii IJ" 'ZDI't . Project I CiieHtS>A"L? VIZ» #(,::=~

' Pro;ed I CIH;nt ~St> Z(] "fS(,o {A{:O~

ww=.u... O.t..II<Ut~P/'W\I!Art- 4fk~~ o9. n. t-t...o 1 w(M, ot-<fi(IAI"~tN\ "fr6:J'!Y,ci,.VLCL.C I

Page 94: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Lacatio0f6£1.11..£AFI7 SIT£ S'.fo~:g DatG ol!:> !Yzol"\ Project/ Client 5 S'o.Z. '7 XS:-C.C> /A~<-

1-J £t.L t?te vt:~.Pe~ W" ~tn;,qqlf. o9. '7!'Z-.tJ-. et

\'1.-1 0

rur-

d.-~, ..J'A~li ~--'-' '1G .. :J Dote .e>{:, /V'P<llvl Location D ,.,_..._.,.,.c "• ~ >! v -

Pm1ect 1 Client S'Stn::r ''tS'CO ,IP~£ C--

~ ASV&UI"ME:"--T ~s-61.,LD"J."Z'Z..CL·Lll

Page 95: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

66 A LocationrEAJ..£ fg SIT6 ssoz-3 Date 06 IK .Z0.\11

Project i Client <;!; O'Z-~ "!Sl.£> /A f:-{jU,>

ltl£u., 0.t.V£LDY'~ ~ i.(f;69f{~. 0~. 'L:z .... vL.., 0 l

Location 6/?AL-f. Affr S't'T"l.ff~>~"J' Date OG I&'~!~'~

-Pmject 1 Client )Jo-z-'7 :r.IC6 /APt;.U

'-.l£M... pu~~b-1,.. 4S"611J(. o,:z:~.c,L,..,Q\

Page 96: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

5S Location~j :1:(' £i"D23=- ·&41£ ·••Aft) · Projectif_.~J~+·~J._.g(,.o"'-'-/cA~.~:Fo><LF.:;·,_,c.~-------

Page 97: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Date iO/l-3jltJ

' -I ~ -~r-

Page 98: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

~ 72 Location ~AfJl SfR. SJoZll Date II Ot' !fl'=f

ProJect I Cl1ent S~O'Z--::1 .$((.Q /A FC.f.L . f€~<41'/47L TAQ'U,"'It4N, /.f$121V:dl.'Z-1 . CL.Ot

o=h::Jo CN'j;"tn Pt,.q f4f'J,~" uAr> U-Cl'Jr --+ - ~

-rAil!. : rec.r~V ~~ ~~ I _

p~,q~: ~ ,Z..~~J /J'flC ~ __f#-A'-"0~ I .&tt. (rc"-ctr4)

J,J•rrllte~ : NAt / Hr'lf -,r-1 tr.:f'o ~~e-or~rp- Au ~11 1 ,

~Lr;t,.• i+oJ,r~A #cl(J4Tr - yH ~ tJ/ t»>Jt:> -t t-- 4 / -

Lt. v y ... s/c- "' -rv~a (J.f) .IV1V Oo 8'.ttr liNt /L .£ . ~ -+ ·v

~ ~ '$1JI.IN Lbr tt~Atf"7t ~.t ~6~/•r

6Voo A-rk S;4<t,7 , .r:rt~ wAZ1 ~- T~.ttfh~_ lfit~t:-rtw4 - ~.xrc~~~ j!_P HA~ffA>J / -sy.rr6#'1

~~r1~JIV ~~e.pl)·~~ "' cl1~:re:;,tu. Hd~os~

sl't4 ""ed f't~JI~ f'tAoN .. 1 · o~ a"k})J t,~ ~11«4- wt JvJt~~ . -P~~-~10 ~v r:~~ ~n:. "'''0-H>

-t - - .. -r lOIS Cd~:x9 S4""wt'U: F,~ wtu.. ITA"[_ ~-rw 1'0~ ~~4N . Pt. tLD ~r . o/tU... IJIS!r£lt.

C1VALIC"'f1 ~ ftT(Jtl) ~ ~ P F ffl...

lt4ft_v~lt WNf rd.Jl/Livb. ~ Ss~ 'PIJ..U.(, ~ _

.SHEt---r0~P ~~(,I> 7~T J'~J--n! fo~ Je-4:JMC- _ 1\zrt ~p J4 ~l ~ ~ tr~4~""'\,J Fr/"

-!-- - ~ -

P~~,oltl.t~f'( F-"1.» 7tf!.JT .· .r~~ ~l-- U'C4 - :::~ -- . - -

~w-e;er. AI\JD Hk'-1> 7.td"f !H&er j /PtJ"- Y(,t.rt.lt;I.J _

~~~~ t-~~ t.JA147'1 J40410~l-T~Jf· - .

Page 99: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Location ;;..., 1\ Z-..S t.ocatiOn Date n J (C I tt= ProJeCt I Client S $.Az;:5 x~c.ot I ""a« =tbv.&

~~~~I t> ;?Jc..., ~ .. j, ~Ltl ~ lP i .. I t':. .... t! l. /_ I

--'

I I I d) - ·- · ..... -- 1--- -- --# I. p ~ <: '3 ~ 7 . G

. ~~ ~tl ' -- !

-- C!~ ·-~ ~·,c;); ~0' ;-t' 7 ~~

~ ~ - 1 ' ~ ~4'\.lP ;; [,__....& +- ~ rz, 4 c$ ~~ ·- _}: vt. ,........; \

fo t~~ 0 u

. - - .. - f--

i

i- - --1---

I ,-~- ··.

i !

·- 1-f--·

I · -·

I-- I -

I 1-

1- 1-

-I

' i -·· . '

-,.

Page 100: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

~c...4i=§, :5""; J..:: :ss:en-3 ~1.,(1 [ t'-1

_ 55o:£3 ;!:Sc<::>/AF<;£c,..

4r>"J"'.,_.J_·-_<>4:5 q::. ;;-r_'i'. ""t.l.L- Gt.... () t

~ £5<=> :5: ?.;_I tS-4 c. <>:rr' ...e s .._,t. +r-o: 1-K-. ?r<r :j;o<'

d'7-

~; Cc.,....j- '. ~-- :~J ~ d· '<>'IS ~..- pl..«s..<. 1..

'-'"' "':f-4<:- ·. '> ""''l- < "'"'i J.lk .of 'i'S"~ I ,..J a s-a~ ?~· ~- F'<i-1/SA<...

O'"loo Pr~ ~J· -r,.a«>.J ~ rk.-..;...-.,

For d<l)-';rki-J. <-!~ .of Yu,.,'S<:.~. ~z;;...~f'~ <r~V'-'""f•-# G.l<>'t.c"\o

1-forr-1 '<To.. (A- I C> 1

#: L I OL(, t'S' if4c.i-. C,; !<>r ~ ,.-_J..:r-

1

VcJ<r ~v<:-1 ~ f\Cn>"' Jt. &'0\'!>b'L­

cq.c.f:;' D~ {/,:;<'., :r-.r '>"io'1-7

0""1-<;1- 0""- 'S ;J.<._ 151-.~ cellev+--) r 1'<...-: ~·J "-d--­w,.X.. l<a.>-(..is.

a!? 1'9 P'rc .;r .,J.... -,J..,r.J.~U >y"'>k.---, :.f. C?f'~«-5 ~I/-,_ <>+ a f'er"""c:r""''""JA.. "•k ~~ '>'~ :~ ..lk ....,.., 1/s ~~"-"X 1...!'-. .::.....'qs ,....,s-t-rv<-1-&J 0').-- /<. As,...o,....l-s ...... (N:ru -h, <>-l-'fr.J.. <:ys~ <>v +- '--yp<S-s rl-- do-;.;..rro.-. .{ o -\;'I..-<;.!, : <. ov+ _

0~<::. '>y.,Je..., s+...-+ "'f

"'lr?'<> 5;-s.J4- S"~s J..:, f..R._ rv.-. '"'':J: ,.,..c..P""'>­c..f.j.....- <..>o,/J<- I i...rv;jl-..- /1/o dyl/ W.J or

Pr-< SSv~ ">f": ~S.

o 1?<t 'l? P..,_.- re't >A.::..'- oO:' f<:. As- .,~cJs.,_./;r.s c ":• ~~ lf/?/t'l '

\S_eck__ -1_,:'5, -:>:::..... ';Sc<.3 ll (-:t, f t4

<j") 0 1. '!:. .:!:S c <> jf, T- CE L

!...k.U ~ --.> ~ I I i.-e- p" ~ cl ~ r pr.rt ~,j..q-;. <i .f.

4u) a.(' d 9-- .

a<{";."" 'f<ilu-- _f.,-l.:.t,c<V {-f'k.--J re..e-d';:rS

1o~o 'i'GIL.e. ~"J'y:S. No d..:tyt~,-~ .. r'"~' 'i'""' ( 0 cJ

...,.pl~.l;~l-._-\IL'> -r~k ce.~.J'~

\t)c. ea1~.:.~ ;_,d-c.lcy w«~ ~~~k. fJo le_9.\<..s

Vfr<""' '~6-\. \<.,- ),.\.~\...

','L-)0 -<::4..\~ -r-,d'r . 1 -,~ ~'" fv'd ~ ';f <>--'<-tfs :;;:::,; p~-r~c.~<-

oi.,-.h>.. «~~ ..v.::kr -z:v-1~ ~ P.. ...... ~f.v::~ ,';p .. c; ~l<-L rc-~'"a~ .

{Lfq<- \,<k-L\ (N"J"-S u. ....... ptR..~. '0...4- ~ '"'l~~-f-f'l>.< ~

lLf~ re.~ ~,rseJ- t(v~l... volv.w<-.

l"n ys~ ~-sc:'f '5 :k ; ~ ~-H,.~.J:., .;.,"";., -1o.-- ~ft-.G,..cll.

\/e..-""'_... -\--- tr-<''-U' .fer P""~f'l<..

:G '! o &4. 8f d.9-

kasmunds
Text Box
injected 1,250 gallons of chase water into each well to dilute the 77 gallons of sodium permanganate that were siphoned into the wells overnight
Page 101: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

Locatton ::5\ t-C. L:5 .k$CD \

Project I Client \ .l..>-,.b< c_:t ~ cf) \.:J;:t

Date ll ( ff) / (P I

-

jux:L~an 14±~1; (P~±~· J7S

0

,

1 /Jf2.) 6 'rL -r"'c _

~'":Jl_ -j l : .s - ~ 12(;> ~~ Tr5_ ~ I -

1"~2 :?--i:!:"-:jw , r d'+-t f6»..S (o ~~ 0{/....t-- e:>£21·

J3:P~ ~) "rJ ~~ T4.tL.C, U'a>t t: <t ~. Ji;:::::.... ~(k; ~o.- I "''P'4r~~

-'SX2~ C"t'l~ ]6~~-fl... ~ ~4.,r-~t2 <f.' ~I'-.t.t C"-"-J~-f__,l)~ ~~A4t1:_~-tfT J.l..,~ 11 -r-"'-~ ~:t-1;!_~ \

-i-S Y.S: - ~ ~c. .... ~t.r - ~..--.. c:H> s!.fi t-~- 0

I

~~I ~(.._A_ ._:i d~ ~~ w~t7<~ - - -

--

- 1--

.. . '

I I I

Locatron S!if ~ ~ :> ::::ISCp ProJect I Client \ l.J <6 .e C.. ...Y't'>::x'\,.

Date I ~11/'f

Page 102: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

80 ' " 7t locatiOn s ' ±e. z :3 - ~eo Date 11 /I I I zAi ~ I I "'7-

Project I C!tent \ "-'..,& f? c.-+~:;.___~------

t

.-

-l -~-- - L -- t .

( ·~ . I I

- l - 2~

I

• -· f

T

r ! . .

.. -r - ----. r· - - -· -

i -i J -

--Location :5i- T e 32 J;Sc.t!> Date .Jijtz./1 'f 81

" ProJeCt I Client TAIJ~ c.$ otJ;.

Page 103: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

"' m 0

I 00

"' .... I

0 m ~

I'W~i!-• .{e(D . _ . , __

&of-lTo -t~ $\? h f h-, ht of.et zz.-k __ T41t.~<Ji -~-t-en ~y_e.L£ . -rve.J..) _o.O

{;'~e-. lt.t; JJ.e..~- s~Jf'~ -~----+erz.. -\10_J!-e-"":x Jb~ ...... (.!:> .. '-~'-/-~~-<

..... _~,.._.;)•_ ... 5-eccL~.JI .. ~re. -· ' '

'-'"'"~-·· ···-~~-----·- 83l ::: d'~ --------------------

-·------' L

.

j__

'

-,--~--- l

"

-l

. ;

' '

-i

ik~:C!:2'----- --"-- -'---'-- L__ ___._ _ __, __ _c. ___ _,_ _ _L_;_____c_ __ L _L_) j

Page 104: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

84 LocatiOn '5 ~- 2 '3 :X ~C.A:. Date J l{ t1 ( 11( ProJect I Client j N I R '- --f' ~ c> t Jj

".:2_ c :;;; Jg c~ L & I c/ J(.ae Zik '1' J - ----~-~ - -

_o·]~~u _c..kl~-<..'-v~--4-.:t'l~ ~~~·~ ----.-

1 ~ ~~Jlk-~ k4-~ ~c.o-d-r±4l.a ~c.~"C'(__ -

~IL~--­~02(& ~t4 it2t~ To !4)c7J ----+--1 -til Le~. ~- - -

- ___t;e ~~ -rk~ -r ~ - -

_ 0]3b_ 3:u.fl. Jr\ _ (A.l_s~....£)1'\_-r'O_ -r- J.NJ ec. :f'L'N __g..alf...u_"- __

_ 07!:/r. _ .Se_:t!-~ ~hs !!LT-<'.£_ .JJa uiS _ ~ 5W___L_'"t' ~~ J34-£.J<-..Io _

- - fu_ ~£_ LQJb._ ~ '0/-. .·c£, h~ _i{s;, ~/.f ~ ~~P2f.J4~ -c=._/~ -L.:t:r t:;_1,'3$ ~4-1..'"::}- lo /qy~

C2l:ioi:- _;5 e_~ .tJ _; ud~-r-,~d_$..._ .... _ _:th(._~~t{Q_...} _$/<Jf-5 oAJ

- 0...~ ~.t.f.} .;L- "'4'-' c Zb bti ~ -- __ &'-t CV\J_ df_ SWJ~c.b_ -e~r- .

- ~\!:) o+-r:e..l0 ro t<~::.f. __ /--1- ~~d~-

\2o'1 _B~i'-:- S\f¥-Tel~ :]3c_~ ~- -\rv J~" ..,..~~-<J 5 'f-er#)

Locat•on ~S -'23 I'bc o

ProJect I Client I h \;je c J'u=:o '

Page 105: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

86 Lo cation Ss- Z3 I~ eo

' Pro1ect I Client f .Vj~ C.. i:t~ tA

- ~-J~ ~~~~~~~

-l...-..--"=-f...:.LL..!....L-f---f--.L..-_,..-~ - . - ~~~ G'r;.£1 tJrzzs ~ ~Evto---:r-__ -- ~$- 6/ -tp ---t~-

1 ~-- ..,.-- --+---

1 I -+--_j_ -

Locat1on $S ··2.3 T$CCJ Pro ect I Client ::r"{je '- tiD II.){

Date /lfJ/¢

J

87

Page 106: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

I ProJect 1 Chent _1..!£ 1\,).~d...e.e~--- PrJ.~. •..J..<J ~~S --- ---

{2,. -;.~ 60 e

Locat1on _S-""<.:"S=---23~--'I=-..::::5C~D__ Date N/ Zc/t,P 89

1 J'r . ~~D ¢)0 I ~ ~ ,J . ----...;.-..+--

~/36. ~ ~lf'\-'b~ 1- V ctl~e. ~

i'2.:· 2.. "b

Page 107: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

90 Location D~ .... Z. ~ -:J:S<..C>

ProJect/Ciu:-nt ln)e.c..'t"io,..;?

Date 11/zo J l LJ

\1 ?'2 C,ne..e-t- t=l 0\,\..)~~~~J)r~l~ Ate 'r! l(.+ .. er _ ~~~ on f>f\T-4~. 5~ft1(.)~ 1M 12

1 :3_o \ Wa\t.._ -~QU_~,~ l2W-(jtic.~-hJ'.l~ . -.&bit.L f._~J.ti_t.K~ aJef (R-..;o.\ ~_ov ~, t_ \ '?ZS ~Glt--1 ~9&+-ru.--Wo.-kL~LLo.\~*'j clJ

B~-r .. ~f:lJ - ~ ~ 1333 __ ~a~s l l-\ ~..4ru (d- ~ 'v

j &.l 0 7- ll!.l...,IJC~e..._.J, IJ.o ~ l~~'}

-

}SCIC ,~~~ .~l""f'oc=-.,"'-"..L-f TZ> to w ---1----- _

1

Locat1on .5 S - '2.. '3 :rs t n Project I CIJent L..ll.s.je..c: ... :=tl0.Q,S

0(~ I

~7_~6

s>75-3

.,

Date J[/ ?P/r¢ 91

r '

Page 108: FINAL PERFORMANCE-BASED REMEDIATION Site SS023 … · CH2M HILL Jay Wilburn/CH2M ... is in place at Site SS023 (Figure ES-1). The final remedy was selected and implemented in accordance

92 c. Locat1on w.C)- Z3 'T~C>

Project I Chent \o)ec."1iON5

_\2\.D L.~fi"le.D ~ J)o_;;,~_,__~~9 Y'u~\-J;t.Jc,.

~~ ~\Jl..4e.A i=\u~hif.J(C :f'->(Yl.~ WQ.~l. ~-

r -- l / I --- -J v 1

I

LoCatiOn ~s .. 73 Io ft) ProJect I Chent :I IVjl!d"lO ,.1S

Date 1!/&tf/,Y 93 I


Recommended