Final plans for renovations to
Central Campus
5th floor
Board Meeting
January 6, 2015
Career Tech Upgrades
• Security upgrades
• Improved learning environment
• Direct freight elevator access to CT programming
• Opportunities for sharing resources
CT Project Highlights
Des Moines Alternative
Program Upgrades
Project Highlights
Des Moines Alternative
• Improved learning environment
• Multipurpose room
• Space designed for alternative learning
• Increased student support
• Sharing programs
Timeline
• January 6, 2015– Board review and approval of final
plans
• February 3, 2015–Award of bid
• February 16, 2015 – Construction start
• January 30, 2016 – Substantial completion. Work will be
performed in phases so some areas complete earlier.
$6,700,000
Project budget
QUESTIONS AND COMMENTS