+ All Categories
Home > Documents > Final Project Report - Hybrid Alternative Energy Solutions

Final Project Report - Hybrid Alternative Energy Solutions

Date post: 11-Jan-2017
Category:
Upload: kevon-campbell
View: 296 times
Download: 0 times
Share this document with a friend
65
i Hybrid Alternative Energy Solutions for the University of Guyana Turkeyen Campus KEVON CAMPBELL Submitted in partial fulfillment of the requirement for Bachelor of Engineering (Electrical Engineering) Electrical Engineering Faculty of Technology University of Guyana August 25 th , 2014
Transcript
Page 1: Final Project Report - Hybrid Alternative Energy Solutions

i

Hybrid Alternative Energy Solutions for the

University of Guyana Turkeyen Campus

KEVON CAMPBELL

Submitted in partial fulfillment of the requirement for Bachelor of

Engineering

(Electrical Engineering)

Electrical Engineering

Faculty of Technology

University of Guyana

August 25th, 2014

Page 2: Final Project Report - Hybrid Alternative Energy Solutions

i

DECLARATION

I declare that this thesis entitled “Hybrid Alternative Energy Solutions for the

University of Guyana Turkeyen Campus” is the result of my own research except

as cited in the references. The thesis has not been accepted for any degree and is

not submitted in candidature of any other degree.

Signature :…………………………….

Author : KEVON CAMPBELL

Date : 25th

August 2014

Page 3: Final Project Report - Hybrid Alternative Energy Solutions

ii

DEDICATION

I would like to specially dedicate this paper

to my loving Mother, Sister, Brother, Father

and God-Siblings.

Page 4: Final Project Report - Hybrid Alternative Energy Solutions

iii

ACKNOWLEDGEMENT

The researcher would firstly, like to thank God, the all Sufficient One, for health, strength and

guidance to complete this project.

Special thanks to project supervisor Ms. Verlyn Klass, for her willingness to work with and offer

assistance when needed to see this project completed. Her invaluable input was greatly

appreciated throughout the process. To Mr. Gary Munroe, a longtime friend and former

employer, thank you, our discussions helped to overcome hurdles whenever they were

encountered.

To my family and close friends your support and encouragement meant a great deal especially

when difficulties were encountered. Whether it was a call, text or a cup of tea, your efforts to

assist during the process of completing this report will forever be remembered.

A special thank you to members of staff from the Registrar’s office, Deputy Vice-Chancellor’s

Office and Bursary who facilitated the researcher to acquire the necessary information to aid in

the completion of this report.

Page 5: Final Project Report - Hybrid Alternative Energy Solutions

iv

ABSTRACT

The University of Guyana like all other consumers on the National electricity grid receives a

monthly utility bill from the Guyana Power & Light Inc (GPL). At present, this figure is

approximately GY $ 7 Million. With an annual rise in consumption and addition of new loads by

the University, a rise in this figure will undoubtedly be seen. Amidst growing electricity

demands, the university needs to tap into more economical and beneficial mediums for its

electricity supply while exploring electricity conservation mechanisms.

The project sought to assess and evaluate the University’s electricity needs, with the view of

substituting alternative energy sources; examine methods which can be utilized to reduce the

University’s electricity consumption and the development of an alternative energy

implementation guide. A system will be developed consisting of various alternative energy

sources, to cater for these energy needs and mechanisms will be explored to reduce the

University’s consumption.

Exploring these avenues will allow the University to be in a position to supplement its energy

needs, with the prospect of supplying energy to the National Grid in the event of minimal

demand. This will also allow the University to become a leader in local alternative energy

research, development and implementation.

Page 6: Final Project Report - Hybrid Alternative Energy Solutions

v

Table of Contents DECLARATION .......................................................................................................................................... i

DEDICATION ............................................................................................................................................ ii

ACKNOWLEDGEMENT ............................................................................................................................ iii

ABSTRACT .............................................................................................................................................. iv

LIST OF FIGURES ....................................................................................................................................viii

LIST OF TABLES ......................................................................................................................................viii

LIST OF ABBREVIATIONS ......................................................................................................................... ix

LIST OF APPENDICES ............................................................................................................................... ix

Chapter One: Introduction....................................................................................................................... 1

1.1 Chapter Introduction: .................................................................................................................... 1

1.2 Introduction ................................................................................................................................... 1

1.3 Background .................................................................................................................................... 1

1.4 Statement of Problem: ................................................................................................................... 2

Chapter Two: Literature Review .............................................................................................................. 3

2.1 Chapter Introduction: .................................................................................................................... 3

2.2 A Snapshot of Guyana’s Electricity Sector: .................................................................................. 3

2.3University of Guyana Electricity Consumption and Demand: ....................................................... 3

2.4 Alternative Energy: .................................................................................................................... 4

2.5 Sources of Alternative Energy: ................................................................................................... 5

2.6 Bio-Energy: ................................................................................................................................ 6

2.7 Solar Energy (Photovoltaic): ....................................................................................................... 7

2.8 Solar Energy (Concentrated Solar): ............................................................................................. 7

2.9 Wind Energy: ............................................................................................................................. 8

2.10 Geothermal Energy: ................................................................................................................. 9

2.11 Hydropower: .......................................................................................................................... 10

2.12 Clean Coal: ............................................................................................................................. 11

2.13 Hydrogen Fuel Cells: ............................................................................................................... 11

2.14 The Future of Alternative Energy: ........................................................................................... 12

2.15 Implementing Alternative Energy Systems: ............................................................................ 12

2.16 Basic Components of an Alternative Energy System: .............................................................. 12

2.17 Electricity Conservation: ......................................................................................................... 14

Page 7: Final Project Report - Hybrid Alternative Energy Solutions

vi

Chapter 3: Methodology........................................................................................................................ 16

3.1 Chapter Introduction ................................................................................................................... 16

3.2 Objective One: ......................................................................................................................... 16

3.3 Objective Two: ......................................................................................................................... 16

3.4 Objective Three:....................................................................................................................... 16

Chapter 4: Results and Analysis ............................................................................................................. 17

4.1 Chapter Introduction ................................................................................................................... 17

4.2 Objective One .............................................................................................................................. 17

4.2.1 Analysis of Feasible Alternative Energy Sources: ............................................................. 17

4.2.2 Determination of Monthly Campus Demand and Consumption ...................................... 18

4.2.3 Proposed Alternative Energy Systems: ............................................................................ 21

4.2.3.1 Single Source Systems: ................................................................................................... 21

4.2.3.1.1 Solar Energy: .............................................................................................................. 21

4.2.3.1.1.1 A Comparative Analysis: .......................................................................................... 21

4.2.3.1.1.2 Campus Photovoltaic System Sizing: ....................................................................... 25

4.2.3.1.1.3 Designed Campus PV System Specifications ............................................................ 28

4.2.3.1.1.4 Designed Campus PV System Land Requirements: .................................................. 29

4.2.3.1.1.5 Designed Campus PV System Mounting Requirements: .......................................... 31

4.2.3.1.1.6 Designed Campus PV System Angle of Tilt ............................................................... 32

4.2.3.1.1.7 Designed Campus PV Balance-Of-System Components: .......................................... 34

4.2.3.1.1.8 Designed Campus PV System Material Costing ........................................................ 36

4.2.3.1.2 Wind Energy: .............................................................................................................. 37

4.2.3.1.2.1 Wind Data: ............................................................................................................. 37

4.2.3.1.2.1.1 Logic Energy Windtracker: ..................................................................................... 37

4.2.3.1.2.1.2 Interpreting the Logic Energy data: ........................................................................ 37

4.2.3.1.2.1.3 The Hobo Micro Station: ........................................................................................ 39

4.2.3.1.2.1.4 Interpreting the Hobo Micro Station data: ............................................................. 39

4.2.3.1.2.2 Estimated Output Utilizing Wind Data: .................................................................... 40

4.2.3.1.2.3 Feasibility of Utilizing Wind Energy for Campus Power ............................................ 41

4.2.3.1.3 Bio-Energy: ................................................................................................................. 43

4.2.3.1.3.1 Potential Bio-Energy Avenues: ................................................................................ 43

4.2.3.1.3.1.1 Rice Husk: .............................................................................................................. 43

Page 8: Final Project Report - Hybrid Alternative Energy Solutions

vii

4.2.3.1.3.1.2 Bio-energy: ............................................................................................................ 45

4.3 Objective Two ........................................................................................................................ 45

4.3.1 Current Campus Consumption: ....................................................................................... 45

4.3.2 Suggested Consumption Reduction Measures: ............................................................... 45

4.4 Objective Three ...................................................................................................................... 47

4.4.1 Solar Power Implementing Guide ................................................................................... 47

4.4.2 Wind Energy Implementing Guide .................................................................................. 49

Chapter Five: Recommendations & Conclusion ................................................................................ 51

5.1 Chapter Introduction: ............................................................................................................. 51

5.2 Objective One: ....................................................................................................................... 51

5.2.1 Solar Energy: .................................................................................................................. 51

5.2.2 Wind Energy: .................................................................................................................. 51

5.2.3 Bio-energy: ..................................................................................................................... 51

5.2.4 Concluding Remarks: ...................................................................................................... 51

5.3 Objective Two: ....................................................................................................................... 52

5.4 Objective Three: ..................................................................................................................... 52

Bibliography .......................................................................................................................................... 53

End Notes .............................................................................................................................................. 55

Page 9: Final Project Report - Hybrid Alternative Energy Solutions

viii

LIST OF FIGURES Figure 1: Global Energy Consumption ...................................................................................................... 5

Figure 2: Components of an Alternative Energy System ......................................................................... 14

Figure 3: Worldwide annual direct normal irradiation in kWh/m2/y ....................................................... 24

Figure 4: Resulting map of the annual sum of direct normal irradiation for potential CSP sites .............. 24

Figure 5: University of Guyana Aerial View ............................................................................................ 29

Figure 6: Proposed Site for the Designed Campus PV System ................................................................. 30

Figure 7: Sun Position and Direction ...................................................................................................... 32

Figure 8: Site Coordinates ...................................................................................................................... 33

Figure 9: Adjustable Angle Calculation ................................................................................................... 33

Figure 10: PV System with Balance-of-System Components Shaded ...................................................... 34

Figure 11: Logic Energy Windtracker illustration of Campus Wind Data using a Histogram ..................... 37

Figure 12: Logic Energy Windtracker illustration of Campus Wind Data using Wind Rose Intensity......... 38

Figure 13: Typical Wind Turbine Power Curve ........................................................................................ 40

LIST OF TABLES Table 1: Sources of Alternative Energy ..................................................................................................... 5

Table 2: Bio-energy Technologies4 ........................................................................................................... 6

Table 3: Photovoltaic Technology [14] ..................................................................................................... 7

Table 4: Categories of Concentrated Solar Plants [15] .............................................................................. 8

Table 5: Categories of Wind Turbines ...................................................................................................... 9

Table 6: Types of Hydropower Systems ................................................................................................. 10

Table 7: Viability Table........................................................................................................................... 18

Table 8: Consumption Data ................................................................................................................... 19

Table 9: Initial Demand Determination .................................................................................................. 20

Table 10: Combined Estimated Demand ................................................................................................ 20

Table 11: Solar Energy Merit Comparison .............................................................................................. 23

Table 12: Energy Potential ..................................................................................................................... 41

Page 10: Final Project Report - Hybrid Alternative Energy Solutions

ix

LIST OF ABBREVIATIONS

UG University of Guyana

GPL Guyana Power and Light Inc

GEA Guyana Energy Agency

LCDS Low Carbon Development Strategy

kW Kilo-Watt

kWh kilo-Watt hrs

CIT Centre for Information Technology

CBJ Cheddi B. Jagan Lecture Theatre

IAST Institute of Applied Science and Technology

LIST OF APPENDICES

Request for Information 56

Letter of Response 57

GE 700 kW Solar Inverter Fact Sheet 58-59

Schneider Electric Xantrex Charge Controller Data Sheet 60-61

Page 11: Final Project Report - Hybrid Alternative Energy Solutions

1

Chapter One: Introduction

1.1 Chapter Introduction:

This chapter gives the reader a holistic overview of the project. After review of this chapter, the

reader will be poised to conceptualize the foundation elements of this paper.

1.2 Introduction

Alternative energy generation, although still thought to be an emerging technology, has

transformed the manner in which electricity is generated. Through the utilization of this

technology, one can reduce their carbon footprint, which is seen as being beneficial and

environmentally friendly. Although the initial implementation of alternative energy is seen as

costly, overtime, such systems pay for themselves and a price tag can’t be placed on the

environmental benefits [1] afforded by such systems.

1.3 Background

The issue of the University’s electricity consumption and resulting high utility bill can be

discussed from two perspectives:

Firstly, from the viewpoint of the University being self sufficient, relying solely on its own

generated electricity supply.

Globally, as State or Government funding is reduced, Universities are forced to increase tuition

fees as a stop-gap measure to recoup the shortfall in funds [2]. The University of Guyana

receives an annual subvention from the Government of Guyana (GoG). Despite this injection of

funds the University has recorded a deficit for a few years. Only last year, an approximate debt

of GY $ 482 Million Dollars was incurred which saw the University being unable to pay for

services rendered by various organizations, among which was GPL [3] [4].

With that said it becomes evident that the University needs to become a self sustaining entity and

this can be achieved in part by addressing its electricity consumption.

Secondly, from the viewpoint of the University being used as a pioneer for the local green

energy initiative and implementation strategy [5].

Guyana has long been and currently is pursuing a myriad of localized awareness and green

energy campaigns, namely the Low Carbon Development Strategy (LCDS), the Guyana Energy

Page 12: Final Project Report - Hybrid Alternative Energy Solutions

2

Agency (GEA) 8KW Grid-Tie Photovoltaic System, among others [5]. These initiatives are

geared at gaining an understanding of our local alternative energy capabilities, as well as raising

public awareness about alternative energy.

Implementing an alternative energy system at the University will allow the institution to become

a local pioneer in this sector. This would spark further interest in the field, as well present

opportunities for local research and study.

Essentially, combining the two perspectives highlights the importance of such a system and the

benefits with which its establishment can offer.

1.4 Statement of Problem:

On the global scale, the concept of green energy is constantly being perpetuated to the masses.

The driving force behind this ideological change is the holistic aim of reducing man’s

dependency on coal and oil for electricity generation. This is due to the fact that coal and oil

generation release greenhouse gases which pollute the environment. It should also be noted that

the cost of oil continues to fluctuate, to the point where in some cases it becomes unpredictable.

Presently, the UG has an approximate monthly electricity bill of GY $7 Million. This figure is a

reflection of the University’s consumption and utility’s implemented tariff. However, the harsh

reality is that this figure will undoubtedly increase unless smart energy decisions are made and

implemented. These decisions will lead to a reduction and possible elimination of this figure.

As the leading tertiary institution, the UG should be spearheading the local energy conservation

initiative. In an energy utopia, the University would be energy efficient; supplying its own power

to meet its consumption needs and when these needs are minimal, power could be supplied to the

National Electricity Grid.

Holistically, such an initiative would see the University being able to invest these savings in

other areas, resulting in institutional development. It would also undoubtedly lead to local

research in the field of alternative energy, which could be spearheaded by the University.

Page 13: Final Project Report - Hybrid Alternative Energy Solutions

3

Chapter Two: Literature Review

2.1 Chapter Introduction:

This section seeks to highlight literature examined throughout the duration of the project. Its

intent is to allow the reader to gain vital insight into the thought process utilized by the

researcher to develop the project outcomes.

2.2 A Snapshot of Guyana’s Electricity Sector:

In any electricity sector, power generation plays an integral role in ensuring consumer demand is

met, and presently this is the responsibility of GPL. From a historical stand point, Guyana’s

electricity sector saw staggered growth, which resulted in the country’s populace being faced

with prolonged power outages [6]. During this period of staggered growth electricity was

generated from bagasse, fuelwood and petroleum products.

The sector saw a turnaround through an Operation & Maintenance partnership with Wartsila [7],

Government investment and development, and international funding. This has moved the

electricity sector to its current position, one which sees the installation of new and the upgrading

of existing Substations, the implementation of a Supervisor Control and Data Acquisition

(SCADA) network, among others. At present, most of the electricity generated is produced from

Heavy Fuel Oils, Crude and Diesel; although a small percentage is produced from co-generation.

However, it should be noted that the electricity grid is more reliant on generation from fossil fuel

sources [8].

With an installed capacity of 156.9 MW and total availability of 125.7 MW to meet a total peak

demand of 104.8 MW [8], it becomes apparent that GPL is heavily reliant on its fossil fuel

generation. This heavy reliance on fossil fuel can pose challenges should the cost of fuel rise to a

point, where consumer tariffs being to increase. Currently, the company essentially absorbs fuel

cost fluctuations [9], thereby negating the need for tariff adjustment. However, it is envisioned

that these practices can’t be sustained unless changes are made or new sources of electricity

generation are utilized.

2.3University of Guyana Electricity Consumption and Demand:

By definition demand [10] refers to the “ratio of the maximum demand of a building to the total

connected load”. It can more or less be attributed to the amount of energy consumed at any

given time, and is expressed is Kilo-Watts. Similarly consumption [10] speaks of “the electrical

energy used over or consumed over time”. It is expressed in Kilo-Watt Hours (KWH).

Page 14: Final Project Report - Hybrid Alternative Energy Solutions

4

The University’s consumption1 for the period Aug, 2011 to May, 2012 was approximately

797412 KWh. When examined this figure postulates to a hefty annual payment to GPL. Like any

growing institution, it is envisioned that the University’s consumption will increase, resulting in

an increased utility bill. It should however, be mentioned that further research is needed to draw

concrete conclusions about the University’s electricity consumption and demand.

2.4 Alternative Energy:

The issues of climate change and global warming are said to be the greatest threats to civilization

and the environment. Caused by the release of green house gases e.g. carbon dioxide (CO2)

resulting from mankind’s daily activities. These activities range from the burning of fossil fuel

for electricity generation to emissions from automobiles. Climate change and global warming are

linked to the melting of the polar ice caps and glaciers, a rise in sea level, humidity and oceanic

temperature, altering of weather patterns, among others [11] [12].

According to oxforddictionaries.com renewable energy2 refers to “energy from a source that is

not depleted when used such as sunlight, wind, rain, tides, etc”. Similarly, alternative energy3

refers to “energy fueled in ways that do not use up the earth’s natural resources or otherwise

harm the environment”. The two concepts in essence go hand in hand, and are often called “free”

energy sources. With the continued depletion of fossil fuel sources, it has been predicted that by

2050 a third of the world’s energy will be produced from alternative sources [12].

It is as a result of carbon emissions and the need for continuous use as opposed to one time use,

that global concern has been raised. Consequently, initiatives have been launched at the local

level with the hope of reducing carbon emissions on a global scale. In Guyana, one such

initiative is the Low Carbon Development Strategy (LCDS) [5]. That said, at the local level this

has led to the birthing of alternative technologies and ideas which will essentially aid in the

global effort to combat climate change dioxide [12].

It must be underscored that although initial implementation costs for such systems are

considerable, technological advancement has seen them being more efficient and economical

when compared to years past.

Despite the fact that local initiatives are in motion, more needs to be done with regard to data

collection, research and public awareness in the arena of alternative energy.

1 See Kevon Grimmond’s “ENERGY AUDIT OF TECHNOLOGY BUILDINGS” (ELE401 – 2010/2011) 2 See http://www.oxforddictionaries.com/definition/english/renewable-energy 3 See http://www.oxforddictionaries.com/definition/english/alternative-energy?q=alternative+energy

Page 15: Final Project Report - Hybrid Alternative Energy Solutions

5

2.5 Sources of Alternative Energy:

Based on the definitions mentioned earlier a clear view of alternative energy sources becomes

clear. These sources are considered to be anything that doesn’t leave a carbon foot print, but

instead can be reused since they are naturally occurring. Some of which are [13]:

- Bio-energy

- Wind Energy

- Clean Coal

- Solar Energy (Photovoltaic)

- Geothermal Energy

- Hydrogen fuel cells

- Solar Energy

(Concentrated Solar)

- Hydroelectricity

Table 1: Sources of Alternative Energy

Figure 1: Global Energy Consumption

From a global perspective alternative sources are already playing an integral role in the

generation of electricity. An examination of the above image, illustrates that these sources are

slowly making a difference in the way electricity is generated.

Page 16: Final Project Report - Hybrid Alternative Energy Solutions

6

2.6 Bio-Energy4:

Said to be the product of biomass and biofuel, bio-energy4 is referred to as energy from organic

matter. This organic matter can either be plant or animal based [13]. This form of alternative

energy has actually been used for many years, however sustainable properties are only now

being realized.

However, its sustainability is likened to a double-edged sword. On one hand, the CO2 produced

by bio-energy is similar to that of fossil fuel. On the other hand, the fast growing plants such as

food crops, trees, grassy and woody plants remove CO2 from the atmosphere. Hence, in order for

bio-energy to be truly sustainable a balance must exist, resulting in zero net CO2 emissions. It is

therefore vital that this cycle continues.

Some bio-energy technologies [14] used to produce electricity are:

Direct-fired systems:

These systems burn feedstock to produce

steam which is harnessed by turbines to

generate electricity

Anaerobic Digestion:

This technique utilizes bacteria to decompose

organic matter in an oxygen deprived

environment. This results in the production of

methane, which is burned to produce

electricity.

Co-firing:

This process combines fossil fuel and bio-

energy feed stock in high efficiency boilers to

generate electricity.

Pyrolsis:

This occurs when biomass is heated in the

absence of oxygen producing pyrolsis oil. This

oil is burned like petroleum to produce

electricity.

Gasification:

Such systems consist of an oxygen deprived

environment fed by high temperatures to

convert biomass in to gas. This gas consisting

of Hydrogen, carbon monoxide and methane,

is in turn fed to a gas turbine which produces

electricity.

Small Modular systems:

This is the terminology used to classify bio-

energy systems that produce 5MW or less of

electricity.

Table 2: Bio-energy Technologies4

Mention must be made of local efforts with regard to the production of bio-ethanol. A

demonstration plant was established in 2013 at the Albion Sugar Estate [5]. The plant can

produce 1000 litres of bio-ethanol daily. Locally the technology still has to be advanced,

however based on international studies5, bio-ethanol can be utilized to produce electricity

through combustion, and this indicates the potential for local bio-ethanol.

4 See http://www.renewableenergyworld.com/rea/tech/bioenergy/biopower 5 See http://www.thegreenage.co.uk/tech/bioethanol-electricity/

Page 17: Final Project Report - Hybrid Alternative Energy Solutions

7

2.7 Solar Energy (Photovoltaic):

This refers to energy released from the sun, namely in the form of light and heat. It is considered

to be the cleanest and most inexhaustible energy source known to mankind [15]. First observed

by French Scientist Becquerel in 1839, Photovoltaic cells or panels convert the sun’s energy into

direct current. This occurs when the energy makes contact with the panel’s surface material,

causing the electrons to become free. Once free the electrons flow in a specific direction owing

to the presence of an electric field. It is this flow of electrons that produces the direct current.

Owing to the rapid growth of the photovoltaic industry in recent years6, a variety of methods are

available for obtaining the sun’s energy. This has been achieved through advances in materials

used to make the PV panels, as well as the panel technology.

Technology Efficiency Use

Thermal non concentrating

45% - 75% Heating systems

Thermal Solar Pond (Saltwater) 10%

Uses an Organic Rankine

Cycle turbine or Stirling

engine to produce electricity

without steam

Photovoltaic

Crystalline Silicon wafer

18% - 23% Electricity generation

Thin film silicon

12% Electricity generation

Thin film non-silicon

16% - 20% Electricity generation

Table 3: Photovoltaic Technology [14]

2.8 Solar Energy (Concentrated Solar):

Concentrated Solar (CS) [14] refers to the use of mirrors or lenses to focus the sun’s rays and

heat to produce electricity via steam turbine connected to a generator. CS Plants are being

established around the world with a typical 250 MW station costing US $600 Million. Despite

the benefits, technological development is seen as the driving force behind these plants,

especially in the area of heat storage. This essentially allows CSP’s to generate electricity after

sunset and on cloudy days. This is achieved through the utilization of liquids with a high thermal

capacity. Concentrated Solar Plants consist of four categories:

6 See http://www.energytrendsinsider.com/wp-content/uploads/2013/10/insert-3.png?00cfb7

Page 18: Final Project Report - Hybrid Alternative Energy Solutions

8

Category Description Efficiency

Parabolic Trough

Consisting of a series of polished parabolic reflectors,

either mirrors or metals. These reflectors focus the

sun’s energy onto an absorption tube, containing a

high thermal capacity liquid (usually oil), which runs

along the focal point of the reflector. The heated fluid

drives a steam turbine.

25%

Linear Fresnel

Reflector

Consisting of long, thin segments of flat mirrors to

focus the sun’s energy onto a fixed absorber located

at a focal point common to all the reflectors. The

absorber can contain multiple heat transfer tubes,

usually containing water, which drives a steam

turbine.

20%

Dish Stirling

Consisting of dish parabolas that focus light onto a

single point. At the focal point, a stirling engine is

positioned, which converts the heat to mechanical

energy. Using a Dynamo, the mechanical energy is

converted to electricity. Unlike the previous

categories, the Dish Stirling utilizes dual axis to

follow the sun.

31.25%

Solar Power Tower

Consisting of ground mirrors which track the sun’s

position and focus its energy onto a collector, fixed

atop a tower. The collector contains tubes with the

high capacity liquid, usually molten salt. This

transfers the heat to water which drives a steam

turbine.

25%

Table 4: Categories of Concentrated Solar Plants [15]

Since Guyana falls within the “sun belt”, the country has untapped solar generation capabilities.

2.9 Wind Energy:

Wind is a resultant of the earth’s rotation, its irregular surface and heating from the sun. In

ancient times wind energy was utilized to drive water pumps and to grind grain. Utilizing these

ancient principles has seen the development of the modern wind turbine [15]. Wind energy is

considered to be the fastest growing energy technology in existence, partly due to improvements

in cost and efficiency. Wind turbines have an average life span of 20 to 25 years, thus making

investment worthwhile.

Page 19: Final Project Report - Hybrid Alternative Energy Solutions

9

Wind energy is generated when wind moves over the turbine blades, usually two or three

depending on the configuration, and a lift is generated. The blades are attached to a shaft and the

lift caused the blades to rotate, resulting in the shafts rotation. The rotating shaft drives a

magnetic field in a generator, which results in the production of electricity.

Categories of Wind

Turbines Description Efficiency

On-Shore Horizontal Axis

Wind Turbine (HAWT)

The axis of the horizontal axis wind turbine is

parallel to the wind stream and ground. The main

rotor shaft and electrical generator are at the top of

the tower and must be pointed in the direction of

the wind stream. A gearbox is used to translate the

slow blade motion into a faster motion to drive the

generator.

0 – 40%

Off-Shore Horizontal Axis

Wind Turbine (HAWT)

These turbines take advantage of strong oceanic

wind patterns and utilize a large area. Since off-

shore wind is more consistent the output from such

wind farms is maximized.

40%

Vertical Axis Wind Turbine

(VAWT)

When compared to HAWT’s, VAWT’s have a

lower start up wind speed and can be positioned

closer to the ground. Unlike HAWT’s, VAWT’s

can be placed in closer proximity to each other

therefore increasing the overall efficiency of the

installation.

40%

Concentrated Wind

Seen as an improvement to the HAWT, the

Concentrated Wind utilizes a cone to focus wind

towards its blades. This causes the wind’s velocity

to increase as it passes over the blades of the

turbine. This results in an improved efficiency.

56 - 90%

Blade Tip Power Systems

(BTPS)

Designed to operate at low speeds, with rotating

blades that carry magnets. Electricity is generated

when these magnets pass through coils housed in

the perimeter ring. Its design allows for reduced

resistance and easy maintenance. BTPS is

designed by WindTronics and made by

Honeywell.

0 – 56%

Table 5: Categories of Wind Turbines

2.10 Geothermal Energy:

This type of energy is produced by utilizing steam and hot water trapped below the earth’s

surface [13]. In order to reach these reservoirs one must drill between 500 – 2000 meters. After

drilling the steam is forced to the surface in a controlled manner to drive steam turbines, thus

producing electricity. Geothermal energy can be essentially harnessed from any part of the

worldi.

Page 20: Final Project Report - Hybrid Alternative Energy Solutions

10

Methods of Geothermal Energy Generation7:

- Dry Steam: Steam of 150oC or greater is used to drive steam generators.

- Flash Steam: Steam occurring at 180oC or greater is fed to a low pressure separator,

resulting in the production of flash steam, which is then fed to a steam

generator.

- Binary Cycle: Low temperature water (usually 57oC) is used to feed a second liquid with

lower boiling point. The interaction of the two liquids produces steam,

which is fed to a steam generator.

2.11 Hydropower:

This refers to electricity produced from the action of falling water. The water’s force causes

turbine blades to turn and a connecting shaft transfers this rotation to a generator. The shafts

rotation causes a magnetic field to develop within the generator, producing electricity [13]. It is

estimated that 20% [15] of the world’s electricity is produced from hydropower, illustrating its

reliability. Hydro systems provide demand flexibility, during periods of high demand water

intake can be increased to meet the increased demand, and likewise, intake can be reduced

during periods of minimal demand.

Types of hydro systems:

Type of Hydro System Description Efficiency

Dammed Reservoir

Water is limited and impounded behind a dam

structure. Using an intake system, the water is fed

through a penstock to turbines which are

connected via a shaft to a generator.

80 – 95%

Run- of-River

This type of installation is an alternative to

“damming” a waterway. Instead, a portion of the

water is diverted to the generator, while the

remainder is allowed to flow naturally. It should be

noted that for such an installation to be efficient, a

constant flow rate is required.

80 – 95%

Micro(<100KW) &

Pico(<5KW) Hydro

A penstock pipe diverts water from the river to the

turbine generator and it is then channeled

downstream back to the river. Either the dammed

or run-of-river method can be employed. Such

installations are considered ideal for small

communities.

50-85%

Table 6: Types of Hydropower Systems

7 See http://www.ucsusa.org/clean_energy/our-energy-choices/renewable-energy/how-geothermal-energy-

works.html#Energy_Capture

Page 21: Final Project Report - Hybrid Alternative Energy Solutions

11

Based on studies and assessments8 conducted of locations countrywide, Guyan has an estimated

hydropower generation capacity of 7600MW.

2.12 Clean Coal:

Electricity generation from coal satisfies the power needs of many developed countries.

Globally, coal generation is said to be the largest contributor of generated electricityii. However

coal generation releases tremendous amounts of pollutants9, some of which are SO2, NOx,

particulates and mercury, into the atmosphere. Clean coal technologies have however been

developed to reduce these emissions, particularly due to concerns about global warming and

climate change. Consequently, power plants built today are said to release approximately 90%

less pollutants [16].

Some clean coal technologies are:

- Liquidized-Bed Combustion: During combustion limestone and dolomite are added to

coal to reduce sulfur dioxide formation.

- Integrated Gasification Combined Cycle: The coal is converted to a gas or liquid via

heat and pressure. After refining, the coal can be utilized.

- Electrostatic Precipitators: These devices charge particles in the plume stack and

collection plates remove them, thus reducing the content of the emissions.

Essentially, clean coal generation employs a variety of technologies to maximize emission

reduction.

2.13 Hydrogen Fuel Cells:

A fuel cell is similar to a battery, however it doesn’t require charging. It electrochemically

converts chemical energy into DC electricity, heat and water, provided that fuel is supplied [17].

An electrolyte solution separates an anode and cathode. Hydrogen is passed to the anode while

oxygen is passed to the cathode. The hydrogen reacts with the electrolyte ion, producing water

and electrons. These electrons travel along wires and are a representation of the current

generated by the cell. A continuous cycle is formed, where water and electricity are created.

Advantages of fuel cell use are:

8 See http://www.gea.gov.gy/energy-development/hydropower 9 See http://www.ucsusa.org/clean_energy/coalvswind/c02c.html

Page 22: Final Project Report - Hybrid Alternative Energy Solutions

12

- High Efficiency - Simplicity - Quietness

- Low emissions - No moving Parts

2.14 The Future of Alternative Energy:

The future of alternative is extremely promising. With advances in technology alternative energy

systems will see output maximization and the reduction of implementing costs [15]. Essentially,

a cap or limit cannot be placed on the future of alternative energy since its benefits are

exceptional.

In Guyana, we have only scratched the surface of our green energy potential. In order to make

sufficient strides in this arena, more local research is required as well as capital investment and

incentives.

2.15 Implementing Alternative Energy Systems:

Alternative energy systems are implemented utilizing two schemes [18]. These are:

Off-Grid: This relates to a system that is independent of a utility company. The system

produces and stores its own power and utilizes a stand-by generator should a short fall in

generation occur. For such systems to be effective proper load analysis and adequate storage

provisions must be made. Off-Grid systems are ideal for remote areas where utility supply is

absent and they are designed to be self sufficient. However, batteries and generators require

periodical maintenance to preserve their longevity.

Grid-Tie: Similar to the off-grid scheme, except, the utility company replaces the backup

generator. During periods of excess generation where demand is low, excess power is fed

back to the grid and the opposite happens when a short fall occurs and demand is high.

Special energy meters are utilized to monitor such systems. Grid-Tie systems also remove the

need to have a battery bank and backup generator; however a power outage will highlight

this need.

2.16 Basic Components of an Alternative Energy System10

:

Charge Controller: Utilized to prevent batteries from over charging, by diverting

excess power to a “diversion load”.

10 See http://www.absak.com/library/home-power-system-diagram

Page 23: Final Project Report - Hybrid Alternative Energy Solutions

13

Diversion load: Consumers excess power to prevent damage to batteries. The diversion

load, usually a large resistor, must be designed to handle maximum power output from the

power source.

Battery Bank: Used to store electricity until it is needed. Deep cycle batteries are

preferred since they can be charged and discharged for years.

Energy Meter: This monitors the system and can indicate how much power is being

produced and consumed, the battery condition, system voltage and amperage flow. Modern

meters allow for PC based interfacing.

Breaker Box: Whether it is DC or AC, the breaker box allows for safe transfer of

electricity to the load.

Inverter: An inverter converts DC to AC to allow household loads/appliances to be

connected to the system.

Generator: This is backup measure should any aspect of the system fail.

Page 24: Final Project Report - Hybrid Alternative Energy Solutions

14

Figure 2: Components of an Alternative Energy System

2.17 Electricity Conservation:

Electricity conservation, by definition11

, relates to the reduction of energy consumed during a

process or by a system, through the elimination of wastage and rational use. In a nutshell it refers

utilizing electricity in a manner that would equate to prolonged use and saving. It is also

concerned with avoiding wastage of non renewable energy sources such as fossil fuel and heavy

fuel oil. Energy conservation goes hand in hand with energy efficiency, which refers to utilizing

less energy to carry out the same process or taskiii

.

The global shift in the direction of renewable energy has emphasized and propelled the need for

energy conservation and efficiency. It is thus evident that the University’s annual consumption,

as at Aug 2011 to May 2012, of 797412 kWh can be attributed to some amount of inefficiency

and wastage. However, to quantify this detailed energy study of the campus will have to be

11 See http://www.businessdictionary.com/definition/energy-conservation.html

Page 25: Final Project Report - Hybrid Alternative Energy Solutions

15

conducted. This project however, will only examine and suggest areas where conservation

methods can be applied, namely:

- Smart metering

- Lighting

- Air conditioning

- Office Equipment

Page 26: Final Project Report - Hybrid Alternative Energy Solutions

16

Chapter 3: Methodology

3.1 Chapter Introduction

This chapter explains and highlights the methods and approaches used to undertake the

objectives of this project. These objectives will be implemented in four stages, namely research,

design, implementation and testing/debugging. The researcher thought it best to elaborate on

each objective and its corresponding implementing stages so as to give a clear and holistic view

of the project.

3.2 Objective One: “Examine energy alternatives such as Hydro, Wind, Solar and Biofuel

for campus wide power”

Research will encompass appropriate literature such as sources of alternative energy, energy

modeling and predictive software, UG’s monthly electricity consumption and utility bill,

alternative energy systems, to name some. With an understanding of the relevant literature, an

alternative energy system will be designed. Of the sources examined, in the research phase12

,

only those deemed feasible will be utilized in the system design. The design will consider the

University’s current and estimated future demand. A software model will be used to implement

and test the designed system. Should any issues arise; the designed system will be adjusted.

3.3 Objective Two: “Explore the utilization of energy saving technologies to reduce the

overall campus monthly electricity consumption”

Research will be carried out to gain an understanding of energy conservation technologies and

methods used to implement these technologies. From the research, those technologies which are

applicable to the University will be utilized to outline an energy conservation scheme(s). These

scheme(s) will be implemented and tested against real world scenarios.

3.4 Objective Three: “Develop a model which would serve as a basic guide for implementing

Alternative Energy”

Research will be undertaken into implementing the feasible sources of alternative energy

indicated under objective one. With knowledge gained an implemention guide will be developed.

The developed guide will take practical and realistic scenarios into consideration.

12 See “Sources of Alternative Energy” in the Literature Review Section

Page 27: Final Project Report - Hybrid Alternative Energy Solutions

17

Chapter 4: Results and Analysis

4.1 Chapter Introduction

This Chapter seeks to quantify the project’s objectives and expound on their results. Its aim is to

give the reader insight into the thought processes used by the researcher to achieve the project

objectives.

4.2 Objective One

4.2.1 Analysis of Feasible Alternative Energy Sources:

The table below examines the viability of the alternative energy sources, mentioned in the

literature review portion of this document. Those sources deemed feasible will be used to

develop the alternative energy system(s). This system will be designed to cater for campus

demand among other factors.

Energy Source Feasibility Reason

Geothermal Energy No

Guyana doesn’t fall within the known geothermal

region (or ring of fire). However, exploration by

means of drilling can determine, definitively

whether any geothermal energy can be harnessed

in Guyanaiv.

Hydro-Electricity No

No falling water exists around or near the

University campus. However, a number of

locations with hydro potential have been

identified, with development they can be utilized

for addition to the national grid.

Clean Coal No

Coal exploration hasn’t been conducted in

Guyana. However, peat deposits have been

discovered and its viability is currently being

examinedv.

Hydrogen Fuel Cells Maybe

Can be utilized to replace to conventional lead

acid battery, thus making the developed

power system more stable.

Large cells act as power generators and only a

constant fuel source is required to generate

electricity. Fuels such as methanol, ethanol,

LPG and hydrogen are currently being utilized

internationally.

Wind Energy Yes

The University lies on Guyana’s coastline and is

therefore exposed to considerable wind

conditions. It can therefore be postulated that

wind power can be harnessed to supply power to

Page 28: Final Project Report - Hybrid Alternative Energy Solutions

18

the University’s electricity network.

Solar Energy (PV) Yes

Owing to the fact that Guyana is within the “Sun

Belt”, the harnessing of solar energy becomes

plausible.

Photovoltaic systems are being implemented

in various locations country wide.

Concentrated Solar Plants have not been

implemented in Guyana; however an

assessment of its potential will be done.

Solar Energy (Concentrated) Yes

Bio-Energy Maybe

The fuel sources (plant or animal based) needed

to produce bio-energy are not native to the

University’s campus and would therefore have to

be transported (e.g. Rice Husk) to be utilized in

any bio-energy based system. This would see an

added cost to the operation of such a system.

It is worth mentioning that plasma gasifier

technology has been improved to allow

everyday garbage to be utilized to produce

electricity. For on campus use, an assessment

of the daily garbage generated must be done

prior to the establishment of such a system.

It should also be noted that bio-energy

systems require some amount of safeguards to

ensure optimum output is achieved. For

instance, when using rice husk, its moisture

content must carefully be controlled to ensure

it can be utilized effectively. Table 7: Viability Table

4.2.2 Determination of Monthly Campus Demand and Consumption

The University of Guyana’s electricity network consists of several load centres which are

metered to allow for billing from GPL. The meters used are of the energy and demand type. Both

record kWh, however the demand meter also allows for kW readings to be measured over preset

intervals. The load centers used to obtain a general representation of the campus demand and

consumption are Centre for Information Technology (CIT), Cheddi B. Jagan Lecture Theatre

(CBJ), General Campus and Bursary, Personnel and Admin. All of these centres use the demand

type meter except CBJ. In order to develop this representation, utility bills of these load centers

were examined. This proved to be the best and less labor intensive method owing to fact that

time wouldn’t permit the installation of the University’s sole power analyzer at these centers for

prolonged periods.

Page 29: Final Project Report - Hybrid Alternative Energy Solutions

19

Location Meter

Number Year Description

Consumption Total

Aug Sept Oct Nov Dec Jan Feb March April May June July

CIT IT

0001059

2011 Max Demand (kW) 44.1 47.44 56.14 43.03 46.84 47.35 52.07 47.84 59.56 67.72 58.81 39.12 610.02

Consumption(kWh) 6074.4 6360 6450 6460 5214 5114.48 7575.6 7408.88 9240 7844 6507.6 4724.4 78973.36

2012 Max Demand (kW)

51.8 39.62 55.68 51.56 60.35 55.57 48.29 362.87

Consumption(kWh) 3566.4 3922.8 6408 7183.2 7401.6 4934 4651.2 38067.2

2013 Max Demand (kW) 48.23 47.17

95.4

Consumption(kWh) 3562.8 4958.4 8521.2

CBJ

2011

Consumption(kWh)

1141 1577 1920 2145 2204 1695 2167 2267 2047 1346 1409 19918

2012 1968 1934 2461 2244 2252 2281 1690 14830

2013 1530 1530

General

Campus

IT

0001437

2012 Max Demand (kW)

317.64 325.32 366.72 367.92 361.88 356.4 312.72 2408.6

Consumption(kWh) 59400 75636 80460 89364 88740 90264 71808 555672

2013 Max Demand (kW) 274.68 320.28

594.96

Consumption(kWh) 50544 74195 124739

Bursary, Personnel

& Admin

IT

0002134

2012 Max Demand (kW) 57.04 66.13 67.09 63.38 65.84

319.48

Consumption(kWh) 10612.8 11240 12622.4 11552 8616 54643.2

2013 Max Demand (kW)

49.33 57.5

106.83

Consumption(kWh) 6723.2 9588.4 16311.6

Table 8: Consumption Data

Page 30: Final Project Report - Hybrid Alternative Energy Solutions

20

Using max demand readings from the General Campus, CIT and Bursary, Personnel and Admin

load centers, an initial demand determination of the campus load was made.

Year

Load Center

CIT General Campus Personnel, Bursary &

Admin

2011 67.72

2012 60.35 367.92 67.09

2013 48.23 320.28 57.5 Table 9: Initial Demand Determination

Owing to the fact that CBJ is metered by an energy type meter, an estimation of its demand was

made. It must, however be noted that this method will only yield an average demand value for a

particular period. To compensate for this, a percentage of the estimated demand value found and

used to make up the combined estimated demand.

Year CBJ Consumption

Data (August) Average Demand Combined Estimate

2011 2267 kWh 2267

(31 × 24)= 3.047 3.047 × 1.50 = 4.5705 ≅ 4.6

2012 2461 kWh 2461

(31 × 24)= 3.307 3.307 × 1.50 = 4.9605 ≅ 5

2013 1530 kWh 1530

(31 × 24)= 2.056 2.056 × 1.50 = 3.084 ≅ 3.1

Table 10: Combined Estimated Demand

Summing the initial demand and combined estimated demand allows for the campus demand to

be realized.

𝐶𝑎𝑚𝑝𝑢𝑠 𝐷𝑒𝑚𝑎𝑛𝑑 = (5 + 67.72 + 367.92 + 67.09) × 1.05

𝐶𝑎𝑚𝑝𝑢𝑠 𝐷𝑒𝑚𝑎𝑛𝑑 = 507.73 × 1.05

𝐶𝑎𝑚𝑝𝑢𝑠 𝐷𝑒𝑚𝑎𝑛𝑑 = 533.1165 𝑘𝑊 ≅ 535 𝑘𝑊

Campus monthly consumption attributed to this demand is determined by summing the

corresponding consumption readings from the load centers under examination.

𝐶𝑎𝑚𝑝𝑢𝑠 𝐶𝑜𝑛𝑠𝑢𝑚𝑝𝑡𝑖𝑜𝑛 = (7844 + 89364 + 12622.4 + 2461) × 1.05

𝐶𝑎𝑚𝑝𝑢𝑠 𝐶𝑜𝑛𝑠𝑢𝑚𝑝𝑡𝑖𝑜𝑛 = 112291.4 × 1.05

𝐶𝑎𝑚𝑝𝑢𝑠 𝐶𝑜𝑛𝑠𝑢𝑚𝑝𝑡𝑖𝑜𝑛 = 117905.97𝑘𝑊 kWh

Page 31: Final Project Report - Hybrid Alternative Energy Solutions

21

The figure 1.05 is used to factor in load growth into both demand and consumption

calculations owing to the fact only those utility bills made available where utilized. Load

growth is attributed to the installation of new AC units, security lights, among others.

4.2.3 Proposed Alternative Energy Systems:

As mentioned previously, alternative energy systems can be broadly categorized as either being

of the single source or hybrid type. Single source refers to an energy system that uses a single

renewable energy source, while the hybrid type combines two or more energy sources. With that

said, the researcher thought it best to design with both categories in mind. The proposed systems

are as follows:

Single Source Systems:

- Solar Energy

- Wind Power

- Bio-energy

Hybrid System:

- No hybrid systems will be examined.

4.2.3.1 Single Source Systems:

4.2.3.1.1 Solar Energy:

4.2.3.1.1.1 A Comparative Analysis:

Solar energy is categorized into Photovoltaic (PV) and Concentrated Solar (CS), and thus a

comparative analysis is required to determine which scheme is better suited to supply campus

power. Often Concentrated Solar and Photovoltaic technologies are said to be interchangeable,

however the analysis will examine the relative merits of each technology. Specific factors

required for optimum performance to be achieved will also be highlighted.

Page 32: Final Project Report - Hybrid Alternative Energy Solutions

22

Merit Photovoltaic

‘Monocrystalline’

Concentrated Solar

‘Parabolic Through’

Light Required

Direct and Diffused Direct only

Solar energy technologies, as the name suggest, utilize the sun’s radiated

energy (sun light) to produce electricity. The amount of light allowed to fall

upon the absorption surface (panel or through) must be taken into

consideration. The amount of light is dependent upon a number of factors,

some of which are angle of tilt, shade from nearby trees or obstructions,

cloud coverage, among others. Most of these factors are controllable, except

cloud coverage.

- Research [19] by the US DOE National Renewable Energy Laboratory

(NREL) has shown that 1MW or less PV systems are rapidly affected by

the presence of cloud cover. It found that the overall power output can

increase or decrease owing to the fact that PV panels respond rapidly to

changes in the available light. These fluctuations are instantaneous and

translate to power output instability, which needs consideration. To

adequately compensate for low light-production electricity storage, in

the form a suitably sized battery bank, is required.

- It is said that [20] a Concentrated Solar Plant requires scant or limited

cloud cover for the installation to be efficient. Guyana doesn’t have a

recognized cloud cover index, that is, whether the cloud cover is low,

medium or high. However, according to Encyclopedia Britannica, it is

said to be high average. Although a CSP offers thermal storage for “sun

down” generation, the absorption liquid being utilized must be first

brought to and kept at the required temperature for steam production to

occur. With that said, it is envisioned that this temperature will fluctuate

owing to persistent cloud cover experienced. These fluctuations equate

to output instability. To compensate for this, the designed system can be

oversized such that at low light conditions a percentage of the rated

output can be delivered to the campus or auxiliary (Utility) power can be

switched-in to make up the short fall.

Land Use Negligible Considerable

Photovoltaic systems require a negligible amount of land area because they

are typically placed on existing structures. In contrast, solar-thermal

technologies may require a significant amount of land, depending upon the

specific solar-thermal technology used. Solar energy installations do not

usually damage the land they occupy, but they prevent it from being used

for other purposes. In addition, photovoltaic systems can negatively affect

wildlife habitat because of the amount of land area the technology requires.

Environmental

Impact

No direct impact unless panels are

broken, cracked or burnt in a fire.

- A Report compiled by Tetra

Page 33: Final Project Report - Hybrid Alternative Energy Solutions

23

Tech Inc [21] found that

leaching from cracked or

broken PV panels poises a

minimal risk to humans and the

environment. It also found that

the accidental burning of panels

can release vapors and fumes

into the environment, which can

be harmful, however this

depends on proximity.

To fully comprehend the environmental impact of a solar energy installation

on campus, an Environmental Impact Assessment (EIA) is required. As

mandated by the Environmental Protection Agency (EPA), an EIA is

needed as ascertain whether such a project could potentially threaten the

environment of the people therein and what measures should be put in place

to prevent or minimize this occurrence.

Water Use

Minimal

- Water is occasionally used in

PV installations to wash dust

off panels.

Large

- Water is used primarily for

cooling of the absorption liquid

which produces steam to drive a

turbine, which produces

electricity.

- Similar to PV installations water

is utilized to removed dust from

the through, since dust reduces its

reflective capability. Dust

removal is however done more

frequent.

Life span 20-25 years 20 years

Storage

Capability Battery Bank Thermal Storage

Table 11: Solar Energy Merit Comparison

The comparative analysis highlights the unfavorable nature of CS in Guyana. On the basis of

Solar daily irradiance only, a PV installation on campus would be more sustainable as opposed to

a CS plant. As a result, the researcher opted to only focus on Photovoltaic design. The images

below highlight the daily irradiance and potential concentrated solar locals. As can be seen

Guyana does not fall within this category. This may change with improvements in the

technology, however, only time will tell.

Page 34: Final Project Report - Hybrid Alternative Energy Solutions

24

Figure 3: Worldwide annual direct normal irradiation in kWh/m2/y

Figure 4: Resulting map of the annual sum of direct normal irradiation for potential CSP sites

Source:

http://www.dlr.de/tt/Portaldata/41/Resources/dokumente/institut/system/publications/Solar_Pace

s_Paper_Trieb_Final_Colour_corrected.pdf

Page 35: Final Project Report - Hybrid Alternative Energy Solutions

25

4.2.3.1.1.2 Campus Photovoltaic System Sizing:

1. Determine system power requirements:

- Total Campus Consumption: 117,905.97 kWh

As highlighted previously, this value represents the maximum calculated consumption for a

given month. However, the kWh/day must be determined in order to adequately meet the daily

needs of the campus.

- Assumed daily kWh: (117905.97

31) = 3803.418 𝑘𝑊ℎ/𝑑𝑎𝑦

- Total PV Panel energy needed: 3803.418𝑘𝑊ℎ

𝑑𝑎𝑦× 1.3 = 4944.443

𝑘𝑊ℎ

𝑑𝑎𝑦

The 1.3 figure is an industry standard used to consider energy lost in the system

2. Sizing of the PV Panels:

- Finding the Panel Generation Factor:

This location specific figure is the product of lowest insolation value in (kWh/m2/day) and the

corrected Wp value. Owing to the fact that a panel’s Wp can decrease owing to a number of

factors (e.g. dirt), some adjustment or correction to this figure is needed. The considerations are

as follows:

15% for temperature above 25˚C

5% for sunlight not striking the panel directly

5% for dirt, grime and dust considerations

10% for panel aging

𝐶𝑜𝑟𝑟𝑒𝑐𝑡𝑒𝑑 𝑊𝑝 = 0.85 × 0.95 × 0.95 × 0.90 = 0.69

It should be noted that a 10% consideration for power losses due to panels not receiving power at

the maximum power point was neglected owing to the fact that an MPPT controller will be

utilized.

𝐿𝑜𝑤𝑒𝑠𝑡 𝐼𝑛𝑠𝑜𝑙𝑎𝑡𝑖𝑜𝑛 𝑉𝑎𝑙𝑢𝑒 = 5.04 kWh/m2/day

𝑃𝑎𝑛𝑒𝑙 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝐹𝑎𝑐𝑡𝑜𝑟, 𝑃𝐺𝐹 = 5.04 × 0.69

𝑃𝑎𝑛𝑒𝑙 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝐹𝑎𝑐𝑡𝑜𝑟, 𝑃𝐺𝐹 = 3.4776 Wh/Wp/day

Essentially for every Wp of panel capacity, 3.4776 Wh/day can be expected during the lowest

insolation month.

Page 36: Final Project Report - Hybrid Alternative Energy Solutions

26

- Total Wp of Panel Capacity: 4944.44

3.4776= 1421.797 𝑘𝑊𝑝

- Number of Panels = 𝑘𝑊𝑝

𝑃𝑎𝑛𝑒𝑙 𝑀𝑎𝑥 𝑊𝑝⁄

Number of panels = 1421.797 𝑘𝑊𝑝

420⁄

Number of panels = 3.385232 = 3385.232 ≅ 3386

The 420 figure represents the rated Wp of the Canadian made Heliene 96M420 Monocrystalline

solar panel.

3. Inverter Sizing:

- Maximum Demand = 535 kW

For operational safety, the inverter will be sized at 25% above the maximum demand of the

campus.

Inverter rating = 535 𝑘𝑊 × 1.25 = 668.75 𝑘𝑊 ≅ 700 𝑘𝑊

4. Battery Sizing:

Off Grid Grid-Tie

- Assumed daily consumption = 3803.418 𝑘𝑊ℎ/𝑑𝑎𝑦

- System loss approximation = 85%

- Nominal Battery voltage = 48 V

- Days of autonomy = 3 - Days of autonomy = 4 hrs = 0.1666 Days

- Depth of Discharge = 20%

B.C

= (3803.418𝑘𝑊ℎ

𝑑𝑎𝑦× 3) (0.85 × 0.2 × 48)⁄

Battery Capacity = 1398.315 𝑘𝐴ℎ

B.C

= (3803.418𝑘𝑊ℎ

𝑑𝑎𝑦× 0.16) (0.85 × 0.2 × 48)⁄

Battery Capacity = 74.576 𝑘𝐴ℎ

For an off grid installation, the battery bank should be rated at 48 V, 1398.315 𝑘𝐴ℎ for 3 days of

autonomy. However, for a grid-tie installation, it should be rated at 48 V, 74.576 𝑘𝐴ℎ for 4

hours of autonomy.

Page 37: Final Project Report - Hybrid Alternative Energy Solutions

27

5. Solar Charger (Charge Controller) Sizing:

- Finding the maximum Voc per module at the lowest recorded temperature in Georgetown

Voc per module (STC @25oC) = 60.55 𝑉

Temperature difference between STC and lowest recorded temp13

:

25 − 16.6 = 8.4 ℃

Voc increase at low temperature: 8.4 × 0.194 = 1.6296

Total Voc at recorded low temperature = 60.55 + 1.6296 = 62.1796 V

- Determining the maximum number of PV modules which can be connected in series:

The number of series connected PV modules shall not exceed the rated maximum Voc of the

charge controller (600 VDC).

2 series connected modules = 62.1796 × 2 = 124.3592 𝑉

3 series connected modules = 62.1796 × 3 = 186.5388 𝑉

9 series connected modules = 62.1796 × 9 = 559.616 𝑉

10 series connected modules = 62.1796 × 10 = 621.796 𝑉

- Finding the number of controllers and modules series strings per controller:

Maximum output current required from charge controllers =

((420 × 3386) (22))⁄ = 64,641.818

Where the minimum assumed battery voltage is 22 VDC

Number of controllers = (64,641.81880⁄ ) = 808

Number of strings = (33869⁄ ) = 376

Number of strings per controller = (808376⁄ ) = 2

Hence on each of the 808, 80A charge controllers 2 strings can be placed. Therefore, each charge

controller will be wired to 18 PV modules.

13 Lowest temperature recorded in Georgetown (16.6 ˚C): http://en.wikipedia.org/wiki/Geography_of_Guyana

Page 38: Final Project Report - Hybrid Alternative Energy Solutions

28

4.2.3.1.1.3 Designed Campus PV System Specifications

Item Rating Quantity

PV Module

420W Heliene 96M420

Monocrystalline Solar

Panel

STC DC watt Max Power (Pmax) 420 W

3386

Max Power Voltage (Vpp) 49.53V

Max Power Current (Ipp) 8.48 A

Open Circuit Voltage (Voc) 60.55 V

Short Circuit Current (Isc) 9.0 A

Temp Coefficient 0.194 V/˚C

PV Array

420W Heliene 96M420

Monocrystalline Solar

Panel

Peak Size = 3386 × 420 = 1,422,120 𝑊

MPPT Charge Controller

Schneider Electric

Xantrex MPPT 80-600

Max PV Voc 600 Vdc 808

Rated Output Current 80 A

Inverter Module

General Electric

700kW Brilliance Solar

Grid-Tie Inverter

Input Voltage Max 600 Vdc

1

MPPT Voltage Range 300-600 Vdc

MPP Dc Current 2400 Adc

Max Isc 3600 Adc

Nominal Ac Power 700kWAc

Nominal Ac Voltage 480 Vac

Battery Bank

428Ah S550 Rolls

Battery Bank

Off Grid 1398.315 kAh Required 3267

Grid-Tie 74.576 kAh Required 175

Page 39: Final Project Report - Hybrid Alternative Energy Solutions

29

4.2.3.1.1.4 Designed Campus PV System Land Requirements:

It is estimated that 10,000 sq ft of rooftop or ground area can generate 100kW [22]. As such, for

the designed 1.422MW Campus PV system, approximately 150,000 sq ft is required, equivalent

to 3.44 acres. With the addition of 0.5 acres for onsite facilities, such as housing the Balance-of-

System components, the total site is approximately 4 acres. It is worth mentioning that this figure

is a combination of both direct and indirect land utilization.

Figure 5: University of Guyana Aerial View

Source: https://www.google.com/maps

Utilizing Google Map imagery, an aerial survey of the campus was done to scout a suitable site

to “sit” the designed PV system. Some of the criteria used to select the site were:

- Lack of obstructions or obstacles which can cast a shadow or shade the arrays

- Usability of suitably sized land

- Location and security of site equipment

- Consideration for the type of mounting

- Consideration for fire

- Impact on the environment and surrounding eco-system

- The PV system will interface with the existing electrical network

Page 40: Final Project Report - Hybrid Alternative Energy Solutions

30

After examining the above mentioned criteria and potential sites around campus, the researcher

selected a 4 acre plot at the back of the campus between the “walk-way” and the recently

constructed National Forensic Laboratory.

N.B. The National Forensic Laboratory isn’t shown in the photo owing to the fact that new

imagery data for Guyana hasn’t been uploaded to Google Maps.

Figure 6: Proposed Site for the Designed Campus PV System

Source: http://www.daftlogic.com/projects-google-maps-area-calculator-tool.htm

Owing to the nature of the selected plot, some amount of site preparation is required prior to the

installation of any equipment. Some of these works include.

- Provision of site access for transportation vehicles, equipment and maintenance:

The proposed site is accessible to personnel and light vehicles for the purpose of surveying and

land demarcation; however a reinforced bridge will have to be constructed to allow heavy

machinery to access to selected site. Two proposed locations are highlighted in the above photo.

- Clearing of vegetation and Grading using earth moving equipment:

Where available the University can utilize its own equipment to minimize equipment rental costs

from a private contractor. However, to mitigate this, the University’s corporate partners or even

the Government (Ministry of Public Works) can be engaged to assist with such undertakings.

Page 41: Final Project Report - Hybrid Alternative Energy Solutions

31

4.2.3.1.1.5 Designed Campus PV System Mounting Requirements:

For large systems of this nature, it is typical for the ground mounting method to be utilized for

array positioning. This type of mounting is utilized when roof mounting is impractical or not

possible. Mounting is achieved utilizing racks, poles and other foundation elements to support

and secure the arrays [23]. It should be noted that this type of mounting isn’t constrained by

orientation and location issues.

Type Description Typical Grid

Connection

Rack

Typically used for large utility scale projects.

In most instances, rack mounting is used in

non-tracking applications.

Grid-Tie

Ballasted

This type of mounting is utilized in large scale

commercial flat roof and reclaimed landfill

projects, as well as those where pile driving

isn’t possible due to soil composition.

Tracking

As the name suggests, such systems follow the

sun’s position utilizing various control

mechanisms. This form of ground mounting

has superior efficiency when compared with

the other types. A two axes or single axis

approach is usually employed to achieve

tracking.

Pole

This type of mounting utilizes a steel pole,

affixed to a special cross member or rack arm

which allows arrays to be mounted onto its top

or side. The arrays weight allows it to be

balanced, thereby enabling seasonal tilting.

Off Grid

The designed system is non-tracking and grid connected; therefore either the Rack or Ballasted

mounting can be employed to support the arrays. It is worth mentioning that regardless of the

type of mounting implemented, consideration must be given for flooding14

and wind loading.

Unlike solar panels, mounting elements aren’t sold by third party resellers, instead direct contact

must be made with such manufacturers. This is done since these manufacturers offer added

services to their customers such as site surveys and custom designs, among others. This also

allows the manufacturer to guarantee their products warranty for the stipulated duration. As a

consequence the researcher is unable to state the specific number of mounting elements required

to support the designed system or its corresponding estimated cost.

14 The year 2005 in Review, See: http://www.guyana.org/special/year2005.html

Page 42: Final Project Report - Hybrid Alternative Energy Solutions

32

N.B. It must be said that, utilizing a distributed roof mounting approach for the designed

system is seen as being unfavorable owing to a number of reasons, chief of which is the fact that

a structural and loading analysis must be done for each individual roof structure. The researcher

therefore thought it best to only examine ground mounting.

4.2.3.1.1.6 Designed Campus PV System Angle of Tilt

Arguably one of the most important aspects of the PV system, the angle of tilt dictates how

sunlight will strike the array, allowing the best output to be achieved from the panels. Since the

sun’s position is continually changing, the angle of tilt can be best described as being either fixed

or adjustable [24].

Figure 7: Sun Position and Direction

based on Hemispheric Location

Source: http://www.westechsolar.com/Solar_Information/Collector_Install

ation_Guide.html

The figure illustrates how

consideration for the angle of tilt

changes throughout the year due to

seasonal changes and hemispheric

location.

Based on the University’s

hemispheric location, the designed

system should be oriented due south.

It cannot be overstated, but a tracking system which follows the sun’s ever changing position

would yield the best output. Unfortunately, in some instances the savings garnered from tracking

systems are expensed to maintain the system and ensuring its functionalityvi. Similarly the power

the solar tracker utilizes negates some of its benefits. That said, to compensate, non-tracking

systems usually employ one of two options:

- Addition of more panels with a fixed tilt.

- Utilizing mounting elements that allow for seasonal adjustment.

Page 43: Final Project Report - Hybrid Alternative Energy Solutions

33

Fixed Tilt Angle:

Figure 8: Site Coordinates

Source: http://itouchmap.com/latlong.html

Using the site latitude and formula “If your latitude is below 25°, use the latitude times 0.87”

𝐹𝑖𝑥𝑒𝑑 𝑇𝑖𝑙𝑡 𝐴𝑛𝑔𝑙𝑒 = 6 × 0.87 = 5.22°

This angle of tilt is from the horizontal. It is said by some, that for fixed tilt PV installations, the

angle of tilt should be as should as close as possible if not equal to the site latitude.

Adjustable Tilt Angle:

Figure 9: Adjustable Angle Calculation

Source: http://solarelectricityhandbook.com/solar-angle-calculator.html

Page 44: Final Project Report - Hybrid Alternative Energy Solutions

34

An online tool was utilized to perform the above calculations, based on the site location and data.

Mounting elements can be designed to allow for adjustment at the specified angles; however this

will require direct contact with manufacturers.

4.2.3.1.1.7 Designed Campus PV Balance-Of-System Components:

This refers to the mechanical and/or electrical equipment or hardware utilized to assemble and

integrate the PV system to the existing electrical network. The figure below, illustrates a PV

system with the BoS components in the shaded region. Typically, the balance-of-system consists

of wiring, circuit breakers and disconnect/isolation switches, batteries, inverter(s), frames and

supports, surge protectors, lightning arrestors [25], among others. It is through the BoS that the

following can be achieved:

Cost Control Improved Efficiency

Figure 10: PV System with Balance-of-System Components Shaded

Source: A. Malla and A. Niraula: Importance of balance of system in solar PV application

Balance-of-System can be divided into the following broad categories:

Mounting Structure/Elements Cables & Protection Devices

Power Conditioning Units Storage

Page 45: Final Project Report - Hybrid Alternative Energy Solutions

35

Although some aspects of BoS have been discussed previously, specific considerations for each

category will be outlined below:

Mounting Structure/Elements:

Design

Tilt angle

Orientation

PV array shading

Cables & Protection Devices Proper cable sizing

Efficient wiring methods

Proper Equipment grounding

Wiring protection from Over-current

and Under-current

Storage:

Proper battery sizing

Protecting batteries from overcharging

Minimizing the occurrences of exposed

battery terminals and slack contacts

Power Conditioning Units:

Proper equipment sizing to cater to

specified load(s), power factor and

surge.

It is important to note that, BoS locations should include provisions which allow for the

following:

- Accessibility for maintenance

- Installation of new equipment

- Suitable clearance and workspace

- Ventilation and cooling

- Protection from insects and rodents

Page 46: Final Project Report - Hybrid Alternative Energy Solutions

36

4.2.3.1.1.8 Designed Campus PV System Material Costing

Item Price

Source Unit Total

420W Heliene

96M420

Monocrystallin

e Solar Panel

$420 $1,422,120 Free Clean Solar

http://www.freecleansolar.com/ShoppingCart.asp

Comment:

Owing to the quantity, the above source does not ship directly to Guyana, hence a US based

freight company will have to be sourced to carry out this process.

Schneider

Electric

Xantrex MPPT

80-600

$1,115 $900,920 Wholesale Solar

http://www.wholesalesolar.com/products.folder/contro

ller-folder/Xantrex-MPPT-80-600.html

General

Electric 700kW

Brilliance

Solar Grid-Tie

Inverter

$700,000*

General Electric

Ground

Mounting $400,000*

S550 428Ah

Rolls Battery

Bank

$1,523 $266,525

https://www.wholesalesolar.com/cart/ $4,975,641

Cabling and

Breakers $150,000*

Miscellaneous 10% Overall Cost

Total Grid-Tie Costing $4,223,521.5 Total Off-Grid Costing $9,403,549.1

Remarks:

- All prices displayed are in USD

- Estimated prices are indicated by a *

Page 47: Final Project Report - Hybrid Alternative Energy Solutions

37

4.2.3.1.2 Wind Energy:

4.2.3.1.2.1 Wind Data:

With the assistance of rigging personnel, an anemometer was installed atop the 42 metre E-

Governance tower, located on campus. From this sensor a hard-line was used to communicate

with two data loggers mounted at ground level. The data loggers, namely the Logic Energy

Windtracker and Hobo Micro Station, became operational on February 14th

and May 12th

respectively, with the assistance of engineers from the Guyana Energy Agency (GEA). The

researcher made periodic checks to readout data, as well as to ensure the data loggers were

operational and in good working order. Owing to a technical mishap the Hobo Micro Station lost

data recorded prior to May 12th.

4.2.3.1.2.1.1 Logic Energy Windtracker:

This is a cumulative data logger, once initialized it records data on an hourly basis. When data is

“readout” via the memory card slot and subsequently uploaded to http://report.windtrackers.com

all data recorded is illustrated in the appropriate form. A breakdown of the number of hours and

corresponding wind speed is shown, as well as the average wind speed recorded thus far. This

module also shows the direction of wind acting on the wind vane of the sensor.

4.2.3.1.2.1.2 Interpreting the Logic Energy data:

The data in this section was recorded on July 22nd

, 2014 and the images below were sourced

from http://shop.logicenergy.com/pages/windtracker.

Figure 11: Logic Energy Windtracker illustration of Campus Wind Data using a Histogram

Page 48: Final Project Report - Hybrid Alternative Energy Solutions

38

The figure above illustrates all the wind data recorded at the last readout. As can be seen the

most observed wind speed is 5m/s with at a total of 1186.3 hrs of observation, followed by 4m/s

at 928.2 hrs and lastly 6 m/s at 725.3 hrs. The occurrence of 2-3m/s wind speed can be

considered to be calm periods, while the occurrences of 7-10 m/s wind speed can be considered

to be periods of gust. It can therefore be said that, the campus receives an average wind speed

between the range of 4-6 m/s.

Figure 12: Logic Energy Windtracker illustration of Campus Wind Data using Wind Rose Intensity

The Wind Rose Intensity diagram above, illustrates the direction in which wind is strongest and

frequently occurring. This information is important since it allows a determination of the best

location to sit wind turbines.

Examining the image, it can be observed that the 4-6 m/s wind speed range has a total frequency

of 76.42% with a direction of 22.5˚. It can be said that any wind turbine situated on campus

should be oriented within North to North East direction.

It was however, highlighted by one of the engineers for GEA that the vane on the anemometer

was not positioned in the true North direction, but rather Northeasterly. As such the wind rose

data is skewed by a few degrees. After consultation it was indicated that the wind rose data,

although skewed, can be corrected by simply taking the offset angle into account.

The researcher is unable to make this correction but the statement regarding the turbine

orientation still holds true, based on pertinent data.

Page 49: Final Project Report - Hybrid Alternative Energy Solutions

39

4.2.3.1.2.1.3 The Hobo Micro Station:

This is a four sensor data logger, optimized to allow monitoring of one or more locations15

. This module differs from the Logic Energy

module in the sense that, its sampling or logging interval can be adjusted. When initialized, the logging interval was set to 1 hour. The

wind speed is determined by, counting the number of revolutions made on the anemometer and dividing this figure by the sampling

interval expressed in seconds. It is important to note that this module allows for more informed conclusions to be drawn when

examining its data.

4.2.3.1.2.1.4 Interpreting the Hobo Micro Station data:

15 See Hobo Micro Station 7645-L Manual

Page 50: Final Project Report - Hybrid Alternative Energy Solutions

40

The data in this section was recorded on July 22nd

, 2014 and the image above was sourced from

the HOBOware Pro software.

A close examination of the HOBOware plot reveals very important information related to the

wind speed experienced on campus. It can be seen that during the course of the day the campus

experiences wind speeds in various clusters. These clusters can be grouped as follows, 0-3 m/s,

4-6 m/s and 7-9 m/s. The latter cluster occurs less frequent, and can be said to be a random

occurrence at best. Similar to the Logic Energy Windtracker data, the 4-6 m/s cluster seems to be

the most predominant. One intriguing observation, when examining the HOBOware plot, is that

the wind speeds occur at varying portions of the day. For instance, the 4-6 m/s cluster can occur

around noon on one day, and occur during the later afternoon or evening on another. That said,

one cannot definitively say which period of the day is best for producing wind energy.

4.2.3.1.2.2 Estimated Output Utilizing Wind Data:

Figure 13: Typical Wind Turbine Power Curve

Source: http://shop.logicenergy.com/pages/windtracker-info

In order to determine the power which can be generated by a wind turbine, its power curve is

utilized. Merging the Logic Energy Windtracker data with this typical power curve, a picture

begins to immerge as to how much energy can be generated.

Page 51: Final Project Report - Hybrid Alternative Energy Solutions

41

Wind Speed [m/s]

Hrs Power Curve

[kW] Energy Generated

[kWh]

2 265.3 0 0

3 415.5 0 0

4 928.2 2 1856.4

5 1186.3 4 4745.2

6 725.3 7 5077.1

7 174 10 1740

8 18.8 14 263.2

9 2.8 17 47.6

10 0.3 19 5.7

Total 3716.5 13735.2 kWh

Table 12: Energy Potential

As of July 22nd

2014, the Logic Energy module has been in operation for 3716.5 hrs or 154 days.

The energy potential table illustrates how much energy would have been produced during that

time period. Based on the energy potential findings it becomes apparent that a low speed turbine

is better suited for campus use. This is reiterated when observing that the “cut-in” and “start-

up” speed for most turbines are typically 3.5 m/s and 6m/s respectively. It is of importance to

note that because the 4-6 m/s cluster holds favorable potential, turbine choice should make full

use of this cluster’s potential.

4.2.3.1.2.3 Feasibility of Utilizing Wind Energy for Campus Power

Based on the previous sections, the question of feasibility begs to be asked. With that said, the

researcher will discuss common benchmarks16

used to address the feasibility of utilizing wind

energy for campus power.

- Noise Impact:

Because a wind turbine consists of rotating parts, noise is an innate aspect of electricity

production. It is said that manufactures are currently utilizing various techniques to reduce the

amount of noise produced by turbines, however it is a factor of some concern. In most instances

noise limits the installed capacity of wind farms, especially when considering proximity to

residential areas, and in this case classrooms and students. It can therefore be said, that owing to

the wind speeds which propagate the campus, the installed capacity will be considerable, and

consequently noise production/pollution to the surroundings will be significant.

16 See http://www.renewableenergyworld.com/rea/news/article/2009/04/wind-farm-design-planning-research-and-

commissioning

Page 52: Final Project Report - Hybrid Alternative Energy Solutions

42

- Visual Impact and Flicker:

As mentioned in previous section, the installed capacity of a wind farm on campus would be

considerable. Be that as it may, the resulting visual impact will be staggering. Imagine a once

clear field or open plot of land, filled with the slow rotating blades of wind turbines, this won’t

be aesthetically pleasing to everyone.

As part of the visual impact consideration, flicker becomes a concern. Flicker is the shadow

caused by the rotating blades of a wind turbine. Essentially more turbines equate to a greater

amount of flicker to be considered. If oriented and placed correctly flicker shouldn’t be a major

issue unless the shadow cast affects students on campus.

- Gird (Campus) Stability/Connection:

The 4-6 m/s cluster doesn’t occur during a fixed portion of the day. With that in mind, recall the

University’s peak demand occurs during the course of the day and not in the evening. It becomes

apparent that wind conditions needed to drive the turbines to product the necessary electricity to

meet the campus’s electricity demand might not always exist during the day. A connection of

this nature can be described as intermittent17

at best, meaning that at instances when wind speed

isn’t sufficient to drive the turbines to produce their rated output, the campus will need to source

power from the GPL supply.

Concluding Remarks:

As previously mentioned, the wind data was recorded at a height of 42 metres. One could

therefore propose the utilization of higher hubs in order to tap into stronger wind currents,

however intermittence, foundation and other factors will need to be addressed. However, based

on the data presented and all factors considered, it can be said that wind power would not be

capable of supplying power to the University’s campus as a single source. It must be combined

with another more reliable source, but its intermittence must be catered to ensure supply stability.

17 See

http://www.umass.edu/windenergy/publications/published/communityWindFactSheets/RERL_Fact_Sheet_2a_Capa

city_Factor.pdf

Page 53: Final Project Report - Hybrid Alternative Energy Solutions

43

4.2.3.1.3 Bio-Energy:

As described in the literature review, bio-energy, is said to be energy produced from either plant

or animal based organic matter. With this definition in mind, the researcher thought it best to

outline possible bio-energy avenues the University can undertaken.

4.2.3.1.3.1 Potential Bio-Energy Avenues:

4.2.3.1.3.1.1 Rice Husk:

This is the exterior protective encasing of a rice grain. It’s larger than the rice grain, convex in

shape and is yellowish in color. In Guyana rice husk is usually discarded, left in open fields to

the elements or burnt by millers at the end of rice production processvii

. With an abundance of

rice husk locally, the University can seek to invest in a rice husk power plant, commonly termed

rice husk gasifier. This plant utilizes the gasification process, which consists of a set of chemical

reactions that use a small amount of oxygen to convert the rice husk into syngas, which is used to

produce electricity.

It is estimated that the production of 1kW of power requires 1.30~1.85 kg of rice husk. Hence to

supply 700kW to the campus approximately 910~1295 kg of rice husk is required. Owing to

advances in technology water supplied to the plant is recycled to prevent harm to the

environment.

Should the University, go the route of acquiring a plant of this nature, the following should be

taken into account:

- Transportation: Rice husk is not native to the campus and therefore it will have to be

transported to an onsite facility from a rice mill. Enclosed vehicles should be utilized to

prevent dust content within the husk from posing a hazard to motorists, pedestrians and the

environment. This will also ensure the preservation of the moisture content within the husk.

This cost should be factored into the overall feasibility assessment for the establishment of

such a plant on campus.

- Moisture Content: Every rice husk plant is designed to operate within a moisture

content18

tolerance, usually stipulated by the manufacturer. This tolerance is of importance

since it becomes difficult for the plant to operate effectively outside the specified range;

usually igniting the husk is problematic. To ensure safe operation, the moisture content

should be checked prior to removal from the mill and before it is added to the plant.

18 See http://cturare.tripod.com/fue.htm

Page 54: Final Project Report - Hybrid Alternative Energy Solutions

44

- Storage: This serves as a quality control and protective measure, ensuring the

moisture content is kept at an acceptable level. This will also eliminate environmental

concerns about air pollution. The storage area19

will allow for testing and monitoring of the

husk. It is envisioned that some form of husk storage (e.g. a shed) will be established at the

mill to serve as a loading centre as well as to aid in preserving the favorable properties of the

rice husk.

Apart from the above mentioned considerations, the value added nature of rice husk should be

taken into account. At the end of the process, the ash produced can be utilized in a variety of

applications, such as in fertilizers and in production of high strength concrete.

Typical Rice Husk Power Plant Specifications:

The information below summarizes specifications for a 700 kW Rice Husk Power Plant,

manufactured by Shangqiu Haiqi Machinery Equipment co. ltd. Wooden containers are used to

ship the assembly to the customer and engineers are sent to assist with the assembly and training

of personnel.

Cost $10,00 – 100,00 USD

Warranty 1 year

Moisture Content 15-20%

Power Consumed 5-15 kW

Fuel Consumption 500-1000 kg

Output Voltage 220 V, 380 V, 400 V, 600 V

Weight 10-40 t

Raw Material Rice husk, wood pellets, saw

dust, bagasse, etc

Cooling Method Water Cooling

Maintenance & Servicing Engineers available as needed

Supplier: http://haiqimachine.en.alibaba.com/product/1468126695-

212084418/Haiqi_brand_700kw_biomass_gasifier_generation_power_plant_for_industry.html

19 See

http://www.bilaspuruniversity.ac.in/PDF/CollegeCorner/Collaborative%20Study%20ICBL%20and%20Bilaspur%20

Vishwavidyalaya%20%281%29.pdf

Page 55: Final Project Report - Hybrid Alternative Energy Solutions

45

4.2.3.1.3.1.2 Bio-energy:

As of late bio-energy has been gaining attention locally, in the form of biodiesel. Biodiesel

power plants as the name suggests use biodiesel as opposed to diesel to produce electricity.

Biodiesel is produced from the chemical reactions between natural oils and alcohol. It can be

made from vegetable oil or fat.

In order to undertake a biodiesel imitative it is advised that the University partner with the

Guyana Sugar Corporation (Guysuco) and the Institute of Applied Science and Technology

(I.A.S.T) in order to examine possible biodiesel avenues. This partnership will allow the

University to garner the requisite knowledge as it relates to the establishment of a biodiesel

production plant and other areas of biodiesel agreement.

4.3 Objective Two

4.3.1 Current Campus Consumption:

As indicated in the “Determination of Campus Consumption & Demand” section, the

University’s estimated monthly electricity consumption is estimated at 117905.97 kWh. This

value is an illustration of the loads connected to the campus’s electricity network. These loads

include lighting fixtures, air-conditioning units, fans, laptops, printers and other office

equipment, among others.

Examining a Report [26], Energy Audit of Technology Building, complied by a former student, a

holistic view of the University’s consumption can be painted. Extrapolating key points from the

analysis done on the “Technology Buildings” it can be conceived that most of the University’s

consumption can be attributed to lighting. That said, any energy measure which seeks to reduce

consumption, must do so with a view of encompassing all connected loads.

4.3.2 Suggested Consumption Reduction Measures:

Below are a few measures which can be undertaken to reduce campus consumption:

- Use of LED Lamps: LED (Light Emitting Diodes) technology has become popular in

recent years owing to a number of factors20

, some of which are longer lasting, more efficient,

durable and cost-effective. The only deterrent to the implementation of LED lamps is the

20 See http://eartheasy.com/live_energyeff_lighting.htm#led

Page 56: Final Project Report - Hybrid Alternative Energy Solutions

46

initial cost; this can be likened to the implementation energy saving bulbs a few years ago, at

the time it was said that the high cost outweighed the benefits.

A T8 LED tube costs approximately $10-20USD, this cost varies based on quantity.

- Comprehensive Examination & Upgrade of Existing Electrical Network: From an

observers perspective, one can notice defective security lamps that are “on” during the day

and “off” at night, an antiquated wiring system, which can be seen as an electrical hazard

only awaiting the right mix of factors to malfunction. It can therefore be envisioned that

some aspect of the University’s consumption can be attributed to “slack connections” and the

old wiring which make up the electrical network.

A complete top-to-bottom examination of the electrical network is needed, and if necessary

an immediate overhaul should be undertaken.

Page 57: Final Project Report - Hybrid Alternative Energy Solutions

47

4.4 Objective Three

4.4.1 Solar Power Implementing Guide

The manual below was modified from a generic template to suit country specific factors, non-

applicable aspects were omitted.

Source: http://www.leonics.com/support/article2_12j/articles2_12j_en.php

1. Determine power consumption demands The first step in designing a solar PV system is to determine the total power and energy

consumption of all loads that need to be supplied by the solar PV system.

1.1 Calculate total Watt-hours per day for each appliance used:

Add the Watt-hours needed for all appliances together to get the total Watt-hours per day which

must be delivered to the appliances.

𝑇𝑜𝑡𝑎𝑙 𝑊𝑎𝑡𝑡 − ℎ𝑟𝑠 = ∑(𝐴𝑝𝑝𝑙𝑖𝑎𝑛𝑐𝑒 𝑊𝑎𝑡𝑡 𝑟𝑎𝑡𝑖𝑛𝑔 × 𝐻𝑟𝑠 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛)

1.2 Calculate total Watt-hours per day needed from the PV modules.

Multiply the total appliances Watt-hours per day times 1.3 (the energy lost in the system) to get

the total Watt-hours per day which must be provided by the panels.

2. Size the PV modules Different size of PV modules will produce different amount of power. To find out the sizing of

PV module, the total peak watt produced needs. The peak watt (Wp) produced depends on size

of the PV module and climate of site location. We have to consider “panel generation factor”

which is different in each site location. For Guyana, the panel generation factor is 3.47. To

determine the sizing of PV modules, calculate as follows:

2.1 Calculate the total Watt-peak rating needed for PV modules

Divide the total Watt-hours per day needed from the PV modules (from item 1.2) by 3.47 to get

the total Watt-peak rating needed for the PV panels needed to operate the appliances.

2.2 Calculate the number of PV panels for the system

Divide the answer obtained in 2.1 by the rated output Watt-peak of the PV modules available to

you. Increase any fractional part of result to the next highest full number and that will be the

number of PV modules required.

N.B. The Result of the calculation is the minimum number of PV panels. If more PV modules

are installed, the system will perform better and battery life will be improved. If fewer PV

Page 58: Final Project Report - Hybrid Alternative Energy Solutions

48

modules are used, the system may not work at all during cloudy periods and battery life will be

shortened.

3. Inverter sizing An inverter is used in the system where AC power output is needed. The input rating of the

inverter should never be lower than the total watt of appliances. The inverter must have the same

nominal voltage as your battery.

For stand-alone systems, the inverter must be large enough to handle the total amount of

Watts you will be using at one time. The inverter size should be 25-30% bigger than total

Watts of appliances. For instance, if the appliance type is a motor or compressor then inverter

size should be at a minimum 3 times the capacity of those appliances and must be added to

the inverter capacity to handle surge current during starting.

For grid tie systems or grid connected systems, the input rating of the inverter should be

same as PV array rating to allow for safe and efficient operation. However, it is

recommended that the inverter be sized larger than the system, to cater for load growth.

4. Battery sizing The battery type recommended for using in solar PV system is deep cycle battery. This type of

battery is specifically designed to be discharged at low energy level and rapid recharged or cycle

charged and discharged day after day for years. The battery should be large enough to store

sufficient energy to operate the appliances at night and cloudy days. To find out the size of

battery, calculate as follows:

4.1 Calculate total Watt-hours per day used by appliances.

4.2 Divide the total Watt-hours per day used by 0.85 for battery loss.

4.3 Divide the answer obtained in item 4.2 by a suitable depth of discharge.

4.4 Divide the answer obtained in item 4.3 by the nominal battery voltage.

4.5 Multiply the answer obtained in item 4.4 with days of autonomy (the number of days that

you need the system to operate when there is no power produced by PV panels) to get the

required Ampere-hour capacity of deep-cycle battery.

𝐵𝑎𝑡𝑡𝑒𝑟𝑦 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 (𝐴ℎ) = (𝑇𝑜𝑡𝑎𝑙 𝑊𝑎𝑡𝑡 𝐻𝑟𝑠 × 𝐷𝑎𝑦𝑠 𝑜𝑓 𝐴𝑢𝑡𝑜𝑛𝑜𝑚𝑦)

(0.85 × 𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝐷𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 × 𝑁𝑜𝑚. 𝐵𝑎𝑡𝑡𝑒𝑟𝑦 𝑉𝑜𝑙𝑡𝑎𝑔𝑒)

N.B. For grid-tie systems, the days of autonomy should be expressed in hours, typically 2-4 hrs

is used. This is due to the fact that, in the event of a blackout, a backup generator will take the

place of the grid, until power is restored by the utility. For high dependency systems like

hospitals, this figure should be higher to cater for catastrophic grid failure, e.g 1-2 days. On the

other hand, for standalone systems, the days of autonomy typically chosen is 7 days, and this is

dependent upon cloud over.

5. Solar charge controller sizing The solar charge controller is typically rated against Amperage and Voltage capacities. Select the

solar charge controller to match the voltage of PV array and batteries and then identify which

Page 59: Final Project Report - Hybrid Alternative Energy Solutions

49

type of solar charge controller is right for your application. Make sure that solar charge controller

has enough capacity to handle the current from PV array.

For the series charge controller type, the sizing of controller depends on the total PV input

current which is delivered to the controller and also depends on PV panel configuration

(series or parallel configuration).

For the MPPT type charge controller, the following should be done:

• Name-XXYY (XX is nominal battery voltage, YY is maximum charge current)

• Find out what is nominal battery voltage that charge controller will charge and select XX

• Find out what is Wp of PV module and

• Select the suitable charge current (CC) = (Wp) / XX

• Find out YY by multiplying CC and the safety factor (NEC requirement) = (CC) x 1.2

• Check that Vpm(system) is in range that Name-XXYY can handle (MPPT voltage range)

• If PV modules are in series, need to check that Vpm(system) = Vpm(module) x Module in

series

• If PV modules are in parallel, need to check that Vpm(system) = Vpm(module)

• Check that Voc(system) is not more than Name-XXYY range (Maximum open circuit voltage)

• If PV modules are in series, need to check that Voc(system) = Voc(module) x Module in series

• If PV modules are in parallel, need to check that Voc(system) = Voc(module)

According to standard practice, the sizing of solar charge controller is to take the short circuit

current (Isc) of the PV array, and multiply it by 1.3

𝑆𝑜𝑙𝑎𝑟 𝑐ℎ𝑎𝑟𝑔𝑒 𝑐𝑜𝑛𝑡𝑟𝑜𝑙𝑙𝑒𝑟 𝑟𝑎𝑡𝑖𝑛𝑔 = 𝑇𝑜𝑡𝑎𝑙 𝑠ℎ𝑜𝑟𝑡 𝑐𝑖𝑟𝑐𝑢𝑖𝑡 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑜𝑓 𝑃𝑉 𝑎𝑟𝑟𝑎𝑦 × 1.3

- Mounting requires consultation with PV installers to determine suitable supports based on the

intended application.

- Online Resources:

- http://www.solarelectricityhandbook.com/solar-calculator.html

- http://www.energymatters.com.au/climate-data/cable-sizing-calculator.php

4.4.2 Wind Energy Implementing Guide

1. Site Selection:

- To determine wind resource

- To identify any impediments that would prevent site development

- To select preliminary site boundary and identify legal requirements

- To develop preliminary site design

2. Assess Project Feasibility:

- To develop cost analysis

- To perform onsite wind monitoring

Page 60: Final Project Report - Hybrid Alternative Energy Solutions

50

3. Detailed Assessment:

- To undertake a detailed site specific investigation to enable an assessment of the project

and possible wind turbine layout

4. Planning and Environmental Approval:

- To prepare the documental necessary for regulatory and community or residential (if

necessary) assessment of the project

- To undertake any necessary environmental referrals and permit documentation

5. Construction:

- To finalize the overall project cost

- To finalize the design and produce construction drawings

- To prepare the required management plans in accordance with the conditions of approval

prior to construction

- To obtain all pre-construction approvals and permits

- To undertake construction of the project within predetermined guidelines and endorsed

management plans

- To monitor compliance with any relevant conditions of approval and management plans

during the construction phase

6. Operation:

- To undertake the operation of the wind farm in accordance with any operational

conditions and guidelines based on management plans, as well as ensuring compliance

7. Decommissioning:

- To identify whether the site can be redeveloped after decommissioning

- To ensure decommissioning occurs within acceptable standards

Page 61: Final Project Report - Hybrid Alternative Energy Solutions

51

Chapter Five: Recommendations & Conclusion

5.1 Chapter Introduction:

This chapter seeks to outline recommendations and develop conclusions based on the outcomes

of the Results and Analysis Chapter.

5.2 Objective One:

The researcher recommends the following, should the University consider implementing an

alternative energy project.

5.2.1 Solar Energy:

As can be seen some aspects of the design may appear vague, this is only due to the fact that the

researcher was unable to garner the requisite information and hands-on-knowledge needed to

pronounce on said aspects, as such estimations where used to supplement. With this report as a

base or reference, it is recommended that the University consult with a PV installer. The installer

will make modifications where necessary to improve the design.

5.2.2 Wind Energy:

With the data examined, although the 4-6 m/s cluster is favorable, it falls below the average wind

speed needed to generate rated power. That said, it is recommended that more data be gathered at

varying heights to make a conclusive decision, as to whether wind energy can be generated to

provide campus power.

5.2.3 Bio-energy:

At best, the bio-energy option would see the University partnering with corporate entities more

versed in the field. For instance, should the University acquire a biodiesel capable generator, a

fuel agreement could be arranged with IAST. On the other hand, UG can go the route of

acquiring its own biodiesel production equipment and generator, and can partner with said

entities for training and initial assistance with maintenance. Nonetheless, UG must partner to

become more informed about the technology.

5.2.4 Concluding Remarks:

Alternative energy is undoubtedly the future of electricity generation. Every year improvements

are made to the existing technologies, while research and development continues to birth new

technologies. In Guyana, alternative energy measures are being implemented at varying levels,

and in the near future widespread use is envisioned. As such the University should seek to

establish an Alternative Energy Research Lab. This facility will allow students to work on

alternative energy projects, conduct research and be able to gain hands on exposure. In order to

establish the facility the University should partner with other Institutions both local and foreign.

It is worth mentioning, of the three alternative energy sources examined, solar energy seems the

most favorable, and despite its cost the technology is tried-and-true.

Page 62: Final Project Report - Hybrid Alternative Energy Solutions

52

5.3 Objective Two:

The University needs a more proactive conservation campaign. Posting “Please turn off

lights when not in use” notices in classrooms is a good measure. However it is believed that

this measure falls short of its desired goals. The University’s conservation drive must be

taken to the students in a more direct manner, whether it is in the form of consultations or

discussions.

Implementing energy saving technologies as pilot projects. For instance, UG could utilize

LED security lamps in a section of the campus or T8 LED tubes in a few classrooms, to

examine their functionality. After monitoring, if their use has found favor, implementation

can be done on a larger scale.

Recommendations regarding the electrical network have already been mentioned; however

the researcher suggests immediate consultation with an electrical contractor. Their

recommendations should be taken under advisement and where necessary corrective

measures should be undertaken.

It would be remiss of the researcher not to mention work done by previous students regarding

energy conservation measures. As such it is recommended that conservation measured

outlined in the “Redesign and modeling of the UG’s Turkeyen Campus Electricity

Distribution System to cater for the World Bank Infrastructure Project” and “Energy Audit of

Technology Buildings” Reports by Saleem Abdool and Kevon Grimmond respectively, be

reexamined to determine their feasibility.

5.4 Objective Three:

It is recommended that supplementary resources be utilized in conjunction with the

manuals/guidelines prepared in section 4.4. This is due to the fact that they were prepared from

an introductory perspective and can be seen as basic at best.

Page 63: Final Project Report - Hybrid Alternative Energy Solutions

53

Bibliography

[1] U. o. C. Scientist, "Clean Energy," 4 August 2013. [Online]. Available:

http://www.ucsusa.org/clean_energy/our-energy-choices/renewable-energy/public-benefits-of-

renewable.html. [Accessed Decemeber 2013].

[2] H. Long, "Let's stop complaining about excessive student debt and do something about it,"

theguardian.com, 1 April 2013. [Online]. Available:

http://www.theguardian.com/commentisfree/2013/apr/01/time-to-do-something-about-student-

debt-crisis. [Accessed January 2014].

[3] A. F. Change, "CONTINUES TO UNDERFUND GOVERNMENT THE UNIVERSITY OF GUYANA," Alliance,

19 September 2013. [Online]. Available: http://afcguyana.com/afcnew/?p=4159. [Accessed

January 2014].

[4] S. Marshall, "UG accounts a mess!!," Guyana Times, 2013 September 2013. [Online]. Available:

http://www.guyanatimesgy.com/?p=30619. [Accessed january 2014].

[5] G. I. Agency, "Guyana taking serious steps to promote energy conservation," GINA, 16 November

2013. [Online]. Available: http://gina.gov.gy/wp/?p=16872. [Accessed January 2014].

[6] Unknown, "Guyana Economy," mangobay.com, [Online]. Available:

http://www.mongabay.com/reference/country_studies/guyana/ECONOMY.html. [Accessed

December 2013].

[7] Unknown, "Wartsila's excellent Operations & Maintenance services expanded and strengthen in

Guyan," Wartsila.com. [Online]. [Accessed Decemember 2013].

[8] G. P. &. L. inc, "Development and Expansion Programme 2013-2017," March 2013. [Online].

Available:

http://www.gplinc.net/sites/default/files/Uploaded%20Files/D&E%20Programme%202013%20-

%202017%20-%20F.pdf. [Accessed December 2013].

[9] G. P. &. L. inc, "GPL Annual Report 2011," Guyana Power & Light inc, Georgetown, 2012.

[10] Dictionary of Engineering, New York: McGraw Hill Companies inc, 2003.

[11] A. Shah, "Climate Change and Global Warming," November 2013. [Online]. Available:

http://www.globalissues.org/issue/178/climate-change-and-global-warming. [Accessed January

2014].

Page 64: Final Project Report - Hybrid Alternative Energy Solutions

54

[12] Unknown, "Alternative Energy," [Online]. Available: http://www.altenergy.org/. [Accessed January

2014].

[13] P. Institute, "Sources of Renewable Energy," [Online]. Available:

http://www.pembina.org/re/sources. [Accessed January 2014].

[14] R. F. a. E. Monoian, A Field Guide to Renewable Energy Technologies (1st Ed.), 2010.

[15] energybeta.com, The Renewable Energy Guide, 2010.

[16] N. M. Association, "Backgrounder on Clean Coal Technology," [Online]. Available:

www.nma.org/pdf/fact_sheets/cct.pdf . [Accessed January 2014].

[17] B.Viswanathan, An Introduction to Energy Sources, Chennai: National Centre For Catalysis

Research, Indian Institute of Technology, 2006.

[18] Angelika, "Off-Grid or Grid-Tied Solar – What’s the Difference?," howtousesolar.com, [Online].

Available: http://howtousesolar.com/off-grid-or-grid-tied-solar-whats-the-difference-2/. [Accessed

January 2014].

[19] D. A. Barber, "Tracking Cloud Cover Effects on Large-Scale PV Plants," EnergyTrend, 29 9 2011.

[Online]. Available: http://pv.energytrend.com/knowledge/Tracking_Cloud_20110929.html.

[Accessed 1 june 2014].

[20] European Comission, "Energy Research: The key advantages of Concentrated Solar Plants,"

[Online]. Available:

http://ec.europa.eu/research/energy/print.cfm?file=/comm/research/energy/nn/nn_rt/nn_rt_cs/

article_1115_en.htm. [Accessed 25 May 2014].

[21] Tetra Tech inc, "Potential Health and Environmental Impacts Associated with the Manufacture and

Use of Photovoltaic Cells," Electric Power Research Institue & California Energy Commission,

California, 2003.

[22] Seattle City Light, "Guide to Installing a solar Electric System," Seattle City Light, Seattle, 2013.

[23] P. a. J. D. P. William Brooks, "NABCEP Photovoltaic (PV) Installer Resource Guide," NABCEP Certified

PV Installer Study and Resource Guide, March 2012.

[24] M. Boxwell, Solar Electricity Handbook - 2014 Edition: A Simple Practical Guide to Solar Energy -

Designing and Installing Photovoltaic Solar Electric Systems, Greenstream Publishing, 2013.

[25] A. M. a. A. Niraula, "Importance of balance of system in solar PV application," Rentech Symposium

Compendium, Volume 2, pp. 65-69, December 2012.

Page 65: Final Project Report - Hybrid Alternative Energy Solutions

55

[26] K. Grimmond, "Energy Audit of Technology Buildings," Georgetown, 2011.

End Notes

i http://www.ucsusa.org/clean_energy/our-energy-choices/renewable-energy/how-geothermal-energy-works.html ii http://en.wikipedia.org/wiki/Coal iii http://eetd.lbl.gov/ee/ee-1.html iv http://longerhealthylife.net/Ecology.html v http://www.stabroeknews.com/2013/news/stories/11/04/airport-runway-extension-begun-cjiac/ vi http://solartradingpost.com/solar-angle-calculators.html vii http://www.kaieteurnewsonline.com/2012/01/04/special-ministerial-team-tackling-cane-grove-rice-dust-pollution/


Recommended