ASSET MANAGEMENT PLAN PUBLIC WORKS
\
5/30/2014 ST. CLAIR TOWNSHIP –Public Works AMP
PW AMP Execu%ve Summary
ES Page 1
ASSET MANAGEMENT PLAN S T. C L A I R T OWN S H I P – P U B L I C WO R K S A M P
EXECUTIVESUMMARY
The Governments of Ontario and Canada require Municipali%es seeking capital funding to u%lize an Asset
Management Plan (AMP) to iden%fy and priori%ze long term needs of their infrastructure. In 2012, the
Province ini%ated the Municipal Infrastructure Investment Ini%a%ve (MIII) program to assist Municipali%es
in reaching their best prac%ce goals. The Township of St. Clair received funding towards the development of
a comprehensive Asset Management Plan to meet this requirement. Adop%on of this AMP as a whole for
implementa%on and con%nuous improvement, thereby meets the new requirement for applying for capital
funding, by demonstra%ng project priori%za%on on a standardized and consistent level.
In 2007, ini%al asset data collec%on and inventory for Road,
Sewer and Watermain networks were stored in the Cartegraph
work management database and integrated with ESRI GIS
mapping. Con%nuous data cleaning is ongoing. Bridge
repor%ng is currently maintained in an Access database stored
on the Township’s network server. Prepara%on has begun on
bridge and streetlight inventories for migra%on into
CarteGraph with GIS integra%on. CarteGraph is the source for
the majority of inventory repor%ng.
Es%mated condi%on assump%ons were completed based upon
known or es%mated install dates during ini%al inventory import. Ongoing condi%on informa%on is collected
on assets during rou%ne inspec%on and maintenance ac%vi%es. Paved Road segment condi%on assessment
is carried out using a computerized SCT Simple Segment Inspec%on system based on the Ministry of
Transporta%on of Ontario methodology. Newly assumed assets are ini%ally given an assumed perfect
condi%on ra%ng.
67%
20%
13%
Bridge Network
Condition
Good Fair Poor
Network Inventory
Network Type Inventory
Roads (Paved) 229 km
Roads (Gravel) 329 km Bridges/Culverts 92 Sidewalk/Trails 37km
Streetlights/Traffic 1325 Water 465 km
Sewers 232 km
1% 12%
31%56%
Paved Road Network
Condition
Very Poor
Poor
Acceptable
Good
PW AMP Execu%ve Summary
ES Page 2
* Typically, gravel roads are maintained rather than rehabilitated, therefore they were not included in the development of the capital
improvement plan but they still have a replacement cost of over $24M.
^ Not included in financial analysis using the Harfan application.
For the Township, the distribu%on of asset value by class based upon replacement cost es%ma%on is shown
above. With a Total Network Replacement Value of $447,816,731, the Township should theore%cally
allocate over $13M per year to ensure future sustainability of its assets. This represents the industry
recommenda%on of 2% -4% yearly investments in renewal ac%vi%es.
To make the most cost-effec%ve decisions with regard to rehabilita%on of infrastructure assets, an
integrated approach is required to acknowledge the close proximity and high level of interac%on between
the infrastructure networks. In simple terms, it is essen%al to look at the condi%on of all components of
infrastructure within a road segment before selec%ng a repair strategy.
The advanced use of the “Windows of Opportunity” concept can be used to coordinate the %ming for repair
with other components of infrastructure reducing the total cost of repairing the assets. The following figure
illustrates the concept of “Windows of Opportunity”.
Windows of Opportunity
23%
6%
12%
32%
9%
9%
1%6%
1% 1%
Asset ValueRoads (Paved HCB &
LCB)*Roads (Gravel)
Bridges/Culverts
Water
Sanitary Sewer
Storm Sewer
Water Tower &
EquipmentWWTP, Lagoons,& PS’s^
Streetlights
PW AMP Execu%ve Summary
ES Page 3
When the level of needs on the underground assets is minimal, as is the case in the Township, a manual
approach using GIS tools to coordinate the repairs is usually as effec%ve.
Based on the results of the condi%on assessment it was possible to iden%fy the immediate needs for Paved
Road and Bridge Networks requiring aJen%on. The following Table summarizes the results.
Network Needs IMMEDIATE Year 1
Network Type % in Needs Cost
Roads (Paved) 15% $26,970,865
Bridge Structures 1% $750,000
It is understood that an “Unlimited Budget” scenario is not a realis%c op%on; however, it is oMen analyzed
to determine the current and short term level of needs and corresponding costs to address these needs.
The following Table summarizes the total es%mated cost of repairs that have been iden%fied in the next 5
and 10 years.
Repair Costs for Next 5 -10Years
Network Type Estimated Cost of Repair
Next 5 Years
Estimated Cost of Repair
Next 10 Years
Paved Roads $36,271,230 $49,079,850
Bridge Structures $3,264,600 $6,061,350
* Repair Costs for other assets have not been identified.
Actual Funding by Network
Network Type Funding Allocations
Paved Roads $1,380,000^
Bridge Structures $156,000
* Funding Allocations for other assets have not been provided.
^ Includes Third Party Funding (AMO Federal Gas Taxes)
Considering that the immediate Paved Road network needs have been es%mated at over $26M, the current
yearly funding will result in a dras%c deteriora%on of the road network over the next decade. It should be
understood that this condi%on will also result in significant increases in maintenance ac%vi%es which may
no longer be cost-effec%ve due to poor condi%on of the roadways. It is clear that the current level of
funding for the Paved Road network is not adequate to sustain the assets into the future.
Based on the 10 year needs for Bridge Structures, an annual expenditure of approximately $6M would be
required to address the iden%fied improvements within a 10 year %meframe.
PW AMP Execu%ve Summary
ES Page 4
PAVED ROAD NETWORK - BUDGET SCENARIOS
As part of this assignment, mul%ple budget scenarios were analyzed to assess different investment
strategies to determine the short and long term effects on the overall Paved Road network asset
performance.
Council has received and reviewed several Paved Road budget scenarios and will discuss further during the
2015 budge%ng process. For the past six years the Township has experienced significant financial
headwinds with the yearly reduc%on in Provincial opera%ng funds, loss in OPG Lambton Genera%ng Sta%on
property tax revenues, increases in OPP costs, etc.
Infrastructure asset management is the combina�on of management, financial, economic, engineering, and
other prac�ces applied to physical assets with the objec�ve of providing the required Level of Service in the
most cost-effec�ve manner. It includes the management of the whole life cycle (design, construc�on,
commissioning, opera�ng, maintaining, repairing, modifying, replacing and decommissioning/disposal) of
physical and infrastructure assets. Opera�ng and sustainment of assets in a constrained budget
environment require some sort of priori�za�on scheme.1
1 hJp://en.wikipedia.org/wiki/Asset_manager
Public Works Asset Management Plan
Glossary Page 1
GLOSSARY
AGL – Applied GeoLogics Inc. (CarteGraph Support Service Provider)
AMP – Asset Management Plan
Asset Managers – Municipal staff responsible for the decisions and outcomes from the AMP
BCI – Bridge Condi%on Index (Ontario Ministry of Transporta%on standardized bridge condi%on ra%ng)
Bridge (Structures) – shall infer Bridges and Culverts greater than 3m in Span (>3m)
Cartegraph/CMMS –SoMware for Computerized Maintenance Management System
CCTV – Closed-Circuit Television (used for sewer pipe inspec%on)
CIP - Capital Improvement Plan
ESRI/GIS – SoMware for Geographic Informa%on System
DWQMS – Drinking Water Quality Management System
HCB – High Class Bituminous (eg. Asphalt Paved Road)
KPI’s - Key Performance Indicators
LCB – Low Class Bituminous (eg. Surface Treatment Paved Road)
LOS – Level of Service
MMS – Minimum Maintenance Standard
Municipality – shall infer The Corpora%on of the Township of St. Clair
OCI – Overall Condi%on Index
PACP – Pipeline Assessment and Cer%fica%on Program (standardized defect coding)
SCT – St. Clair Township
Sewers – shall infer both Sanitary Sewers and Storm Sewers
TCA – Tangible Capital Assets
Township – shall infer The Corpora%on of the Township of St. Clair
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 1 of 12
PW AMP
Document is Uncontrolled when Printed
1 ASSETMANAGEMENTPLAN
1.1 INTRODUCTION
St. Clair Township is a lower %er municipality located in the County of Lambton in the Province of Ontario,
Canada. The Township is commiJed to providing efficient, effec%ve, and economical services to our
taxpayers. We are located immediately south of the City of Sarnia and just across the St. Clair River from
Eastern Michigan. A short drive to either the 24/7 Interna%onal Bridge crossing in Point Edward, ON or
Ferry Service within the Municipality to the United States of America. The current popula%on is
approximately 15,000 2people.
2 Statistics Canada In 2011, St. Clair (Township) had a population of 14,515.
Figure 1 - Loca%on St. Clair Township
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 2 of 12
PW AMP
Document is Uncontrolled when Printed
1.1.1 Background
This is the first Asset Management Plan (AMP) to be implemented in the Township of St. Clair. Dillon
Consul%ng Limited in associa%on with Monteith & Sutherland Limited, ASI Technologies Inc. and Harfan
Technologies Inc. was retained by the Township of St. Clair in August 2005 to undertake the
implementa%on of an Asset Management System (AMS) to assist the Township in managing municipal
infrastructure. Final reports from the Dillon 2007 plan were never adopted or implemented, but are the
basis for this AMP.
In October 2012, the Municipality applied for and obtained funding under the Ontario Municipal
Infrastructure Investment Ini%a%ve (MIII) to improve asset management planning following the Ontario’s
Ministry of Infrastructure guide Building Together: Guide for Municipal Asset Management Plans.
September 2013, Council supported the recommenda%on from the finance commiJee, that Council adopt
the AMP as an input into the budget process for decision making and the asset management strategies be
updated from %me to %me in accordance with best prac%ces, technology changes, financial constraints and
condi%on assessment outcomes.
Adop%on of this AMP as a whole for implementa%on and con%nuous improvement, thereby meets the new
requirement for applying for any provincial capital funding by demonstra%ng project priori%za%on on a
standardized and consistent level.
1.1.2 Goals and Objectives of the AMP
The 2013 objec%ve was to concentrate on geWng the Paved Road network and Bridge Structures
implemented to meet the new industry standard and review the remaining assets over the next 3 years.
This would address the immediate needs within the %me constraints, as soMware versioning issues are a
road block to our ability to fully incorporate other Public Works assets into an updated comprehensive
capital planning module at this %me.
Buildings and Fleet are managed outside of this plan. Their AMP has been received by Council.
The AMP shall include the short term Implementa%on plans and long term Life Cycle plans for Public Works
assets.
There is a need to obtain a framework, providing clear direc%on and consistency to those engaged in the
process of Asset Management. To manage in an informed and transparent decision making process to
deliver op%mized services at reduced cost and risk.
One of the goals of this plan is to improve the prac%ces currently followed by decision makers at the
Township to manage the infrastructure assets and make decisions on improvement plans in a %mely and
cost-effec%ve manner.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 3 of 12
PW AMP
Document is Uncontrolled when Printed
Maintain
inventory of
assets
Undertake
condition
assessments
Lead capital
planning
Project Long-
term funding
requirements
Collaborate
with
Operations to
formalized
record
keeping and
transition to a
more pro-
active
maintenance
and
inspection
focus
Foster
collaboration
between
Engineering,
Operations,
Planning,
and Finance
Implement
technology as a
key enabler of
more effective
and efficient
means of
conducting
business that
supports
business
decisions.
To properly accomplish this goal, it is essen%al to have an accurate knowledge and understanding of the
physical and opera%onal characteris%cs of the Township’s infrastructure networks and be able to iden%fy
and provide recommenda%ons to address deficiencies in the system to ensure an acceptable Level of
Service to the residents.
1.1.3 Development of the AMP
The AMP Steering CommiJee determined our Asset Management Plan (AMP) would be completed in-
house.
Without the existence of a current Official Plan (2000) or Strategic Plan (1995), development of this AMP
lacked clear direc%ves and goals. Both Plans are prior to amalgama%on of the former Township of Moore
and the former Township of Sombra that formed The Township of St. Clair in 2001.
CarteGraph is our work management system and is the source for most Infrastructure repor%ng.
Finance provides actual and es%mated budge%ng and valua%on data through the Tangible Capital Asset
Accoun%ng processes using PSAB 3150 Guidelines in 2009.
1.1.4 Benefits of Implementing an Asset Management Plan
An effec%ve Asset Management Plan based on an integrated approach will ensure the ongoing integrity and
sustainability of the infrastructure assets. Many benefits can be achieved from a full implementa%on.
Informed and %mely decisions will help municipali%es op%mize investments, save money in the long run,
and beJer manage risks. Improved municipal asset management will ensure financial sustainability and
direct limited provincial resources to the most cri%cal needs.
The AMP will assist the decision makers in the prepara%on of short term Capital Improvement Plans (CIP)
and predic%on of long term Life Cycle Plans. It will also contribute to improved day to day opera%ons
through efficiencies.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 4 of 12
PW AMP
Document is Uncontrolled when Printed
It should be understood, however, that an AMP is only a network tool to assist in the prepara%on of a
Capital Improvement Plan (CIP). It should be used by decision makers in reaching educated decisions,
supported by reliable and objec%ve technical data, for the infrastructure to be repaired. An AMP will help
the user in comparing asset condi%on throughout the network on the same basis. It will provide a
consistent approach in comparing the performance of each element of the infrastructure networks and
iden%fy components of the networks in need of rehabilita%on. An AMP is a powerful tool to assist decision
makers in iden%fying where they should concentrate their efforts and money. It is a network-level
instrument which, when u%lizing an integrated approach, will determine and priori%ze where renewal
ac%vi%es should be carried out at the network level. However, input will s%ll be required by the decision-
makers to finalize the CIP.
The final decision on capital improvement work is, in most cases, based on factors that are difficult to
incorporate into an AM model. (“Poli%cal” issues or socio-economic considera%ons from public
stakeholders are examples of such factors.) As is always the case, prac%cal engineering exper%se is essen%al
in the decision-making process. Typically, before the final decision is made, more detailed inves%ga%ve
work will be required to confirm the results.
Implementa%on will ensure the Township can meet new demands in a fiscally responsible and
environmentally sustainable framework while preserving the Townships’ quality of life.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 5 of 12
PW AMP
Document is Uncontrolled when Printed
1.2 STATE OF INFRASTRUCTURE
1.2.1 Asset Inventory
Asset data collec%on for Roads, Sewers and Watermains were
ini%ally inventoried in 2007. Inventory for these assets are
stored in the CarteGraph work management database and
integrated with ESRI GIS mapping. Bridge Structure repor%ng
is currently maintained in an Access database stored on the
Township network server. Prepara%on has begun on Bridge
and Street Light inventories, currently maintained in
spreadsheets, for importa%on into CarteGraph with GIS
Integra%on. Con%nuous data cleaning is ongoing. CarteGraph
is the source for most inventory repor%ng.
1.2.2 Asset Value
The Township asset values are based on the replacement cost es%ma%on detailed in APPENDIX A.1 - Asset
Values, which shows the distribu%on of these values. Based on the results and the recommended 2% to 4%
yearly investments in maintenance, the Township should theore%cally allocate over $13 M per year to
ensure future sustainability of its assets.
Asset Values
Infrastructure Network Length (km) / Count
Estimated Replacement Cost 2013
Estimated Replacement Cost 2007
% of Total Assets
Roads (Paved HCB & LCB) 229km $103,098,918 $80,772,000 23%
Roads (Gravel) 329km $24,682,477 $21,087,400 6%
Bridge Structures 92 $54,358,000 $33,513,000 12%
Sidewalk/Trails 37km $6,071,000 $6,009,957 1%
Street Lights/Traffic Signals 1325 $1,650,750 $1,471,000 1%
Water 465km $142,847,977 $141,530,000 32%
Sanitary Sewer 118km $42,427,492 $30,873,000 9%
Storm Sewer 114km $39,954,851 $33,358,000 9%
Water Tower & Equipment $4,307,460 $19,000,000
1%
WWTP, Lagoons,& PS’s $28,417,806 6%
Total Asset Value $447,816,731 $367,614,357 100%
Table 2 – Asset Values
Before managing an asset, it is important to know the value of the asset to determine if the improvement
dollars spent are jus%fied to protect it. Based upon replacement unit prices, approxima%ons of the total
value of the assets were calculated. All assets have a limited life expectancy. Replacement costs and
lifecycle management is outlined in APPENDIX A.2 - TCA Procedures & AssumpCons.
Network Inventory
Network Type Inventory
Roads (Paved) 229 km
Roads (Gravel) 329 km
Bridges/Culverts 92
Sidewalk/Trails 37km
Streetlights/Traffic 1325
Water 465 km
Sewers 232 km
Table 1 – Network Inventory
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 6 of 12
PW AMP
Document is Uncontrolled when Printed
Project Priority Indicate High/Medium/Low
Health or Safety Issues
Cost Saving/Paybacks
Asset Maintenance/Replacement
Growth Related Needs
Service Enhancement
Other
Table 3 - Project Priority Risks
1.2.3 Asset Condition
Es%mated condi%on assump%ons were developed based on known or es%mated install dates upon ini%al
inventory import. Ongoing condi%on informa%on is collected on assets during rou%ne inspec%on and
maintenance ac%vi%es, or during contracted inspec%on services. Paved Road segment condi%on
assessment is carried out using a computerized SCT Simple Segment Inspec%on system based on the
Ministry of Transporta%on of Ontario methodology. Newly constructed assets are ini%ally given an
assumed perfect condi%on ra%ng.
Appropriate condi%on monitoring reduces the likelihood of cri%cal asset failure.
1.2.4 Asset Risk
Most issues are addressed as per MMS. The Water network has its own risk analysis within the
Municipali%es DWQMS.
Budget considera%ons include project
priori%es, as well as other priori%es in
rela%on to need or environment.
Assets should be managed in a proac%ve
manner with considera%on to the
probability of failure and the consequence
of failure.
1.3 LEVELS OF SERVICE (LOS)
Current Service Levels are considered acceptable and are based on historical infrastructure management
prac%ces. Asset Managers at the Township recognize that to con%nue to provide an adequate Level of
Service to their ratepayers, it is essen%al to first develop a strategy that would ensure the sustainability of
those assets. Levels of Service are currently undocumented. The approach to address this is to develop in-
house KPI’s (key performance indicators).
Our asset performance is compared against other municipali%es as part of the annual Municipal
Performance Measurement Program Repor%ng. This report can be found on the Municipality’s’ website
www.twp.stclair.on.ca.
Service is oMen directly related to finances, regula%ons, and Council direc%on term by term.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 7 of 12
PW AMP
Document is Uncontrolled when Printed
1.4 ASSET MANAGEMENT STRATEGY
Decisions are presently made on the renewal of assets to replace, rehabilitate or con%nue with current
maintenance ac%vi%es based on Council/Poli%cal direc%ons within short electoral terms, instead of over
long term life-cycle management of the asset.
Our goal is to move Roads, Water, Sewer analysis to an Op%mized Life/Minimal Cost method. This method
u%lizes a calcula%on to allocate funding to the assets which will see the greatest increase in life, for the
minimal amount of funds. This favors performing treatments on assets at op%mized life cycle points. This
means that some assets which are in poor condi%on may be allowed to deteriorate further un%l the benefit
of replacement is sufficient to divert funds from preserva%on and rehabilita%on ac%vi%es.
The implementa%on of an AMP is to ensure adequate financial reserves are set aside for the preserva%on,
rehabilita%on and replacement of aging and expanding infrastructure assets, including features and
facili%es, for Paved Roads, Bridges, Water and Sewers.
The majority of the gravel road network is considered to be in very good condi%on. Maintenance
improvements are carried out on the en%re Gravel Road Network over 2 years. Therefore, there is no
medium to long term capital plans in the network. These improvements are usually funded through the
opera%ng budget.
To es%mate an infrastructure's remaining service life, it is essen%al to know its actual state and the
projected service life of its family type. The remaining service life es%mates will assist staff in the
determina%on of “when” and “how much” to invest in immediate and long term scenarios, to counter the
effects of deteriora%on and to ensure the %mely renewal of infrastructure. These assump%ons are
documented in APPENDIX A.2 - Tangible Capital Asset Procedures & AssumpCons.
There is an extensive list of planned and unplanned maintenance and repair ac%vi%es incorporated into
CarteGraph and associated to assets through the Work Order system. Some of these ac%vi%es are being
associated to the individual asset history for further evalua%on of asset condi%on and behaviors to assist in
iden%fying and priori%zing improvement needs. This is best done on assets associated to Work Orders
through planned maintenance. We are striving to be more effec%ve in this area as the organiza%on is s%ll
growing at different levels of u%lizing the CarteGraph Work Order management system.
Considera%on of alterna%ve procurement methods and new technologies should be given to reduce costs
of addressing infrastructure needs. The current Municipality’s procurement policy is provided in APPENDIX
A.3 - Procurement Policy.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 8 of 12
PW AMP
Document is Uncontrolled when Printed
Figure 2 - Sample of CarteGraph Work Order Ac%vi%es
1.4.1 Integrated Approach
To make the most cost-effec%ve decisions with regard to renewal of infrastructure assets, an integrated
approach to acknowledge the close proximity and high level of interac%on between the infrastructure
networks. In simple terms, it is essen%al to look at the condi%on of all components of infrastructure within
a road segment before selec%ng an improvement strategy.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 9 of 12
PW AMP
Document is Uncontrolled when Printed
The advanced use of the “Windows of Opportunity” concept can be used to coordinate the %ming for repair
with other components of infrastructure reducing the total cost of repairing the assets. The following figure
illustrates the concept of “Windows of Opportunity”.
Figure 3 – “Windows of Opportunity” Concept
When the level of needs on the underground assets is minimal, as it is the case in the Township, a manual
approach using GIS tools to coordinate the repairs is usually as effec%ve.
The next step is to priori%ze the improvements, determine when they should take place, establish what
kind of improvement should be applied and determine how much it would cost.
1.4.2 Capital Improvement Plan (CIP)
In 2007, a 50 year CIP for all assets based mostly on the condi%on of the assets, was provided. For
budge%ng purposes, a 5 Year Capital Program for all assets was developed but never adopted.
Renewal forecasts are developed based on expected remaining life of assets using a number of composite
factors. The remaining life of an asset may be based on some or all of the following drivers:
• CondiCon
• Capacity
• Risk
• Maintenance & Repair
• Conformance to Standards
• Design Life
A proposed 10 year Capital Improvement Plan, based on the Actual Budget Scenario is included in
APPENDIX B.3 - CIP Paved Roads.
Burgess Engineering Inc. developed the OSIM Biennial Inspection Report that provides a 10 year Capital
Improvement Plan. The 2013 Report is summarized in APPENDIX C.1 - Bridge Report Summary.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 10 of 12
PW AMP
Document is Uncontrolled when Printed
1.5 FINANCING STRATEGY
1.5.1 Sources of Funding
Funding comes from a variety of sources including property taxes, user fees, debt issuance, 3rd party
contribu%ons and drawing on reserves.
• Tax levy
• User Fees
• Debt Financing
• 3rd Party Contribu%ons
• Reserves
1.5.2 Funding Strategy
Typically, Unlimited and Actual budget scenarios are analyzed along with mul%ple “What if” Scenarios for
comparison.
It is very important for a municipality to determine if the current level of funding is appropriate to con%nue
to provide an adequate Level of Service to its residents. It is also essen%al to allocate adequate funding to
ensure sustainability of the assets in the future. It is oMen suggested in literature that 2% to 4% of the value
of an asset should be spent yearly to ensure sustainability of the assets. Based on the asset replacement
cost es%ma%on of $447,816,731, the Township should theore%cally allocate over $13M per year to ensure
future sustainability
Funding remains the biggest challenge in reaching sustainability. Par%cularly with property tax funded core
services such as Roads and Bridges.
Taxa%on and user rates have historically fallen short of recognizing the true life-cycle cost of infrastructure
assets resul%ng in a growing list of deferred capital projects. Further shorYalls can be contributed to the
yearly reduc%ons in provincial funding, the loss of OPG property tax revenues, increases in policing and
other costs to maintain the same levels for other tax based services.
There has not been a formal commitment to address Long Term Capital Investment needs at this %me.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 11 of 12
PW AMP
Document is Uncontrolled when Printed
1.6 CONCLUSIONS & RECOMMENDATIONS
The Township of St. Clair has historically been in a reac%ve, worst-first environment. With the increase in
communica%on and understanding of our systems, our direc%on is moving towards a proac%ve, op%mized
life management of our assets. There is the need to look ahead long term with our financial strategies
instead of to the past.
Levels of Service and Key Performance Indicators need to be decided and documented to benchmark our
plan.
To con%nue good asset management, the Township should consider reviewing current prac%ces for
poten%al costs savings and op%mized asset improvement in our opera%onal methods
Further considera%ons should be given to mul%-year contracts and seeking partnerships with neighboring
municipali%es.
Recommenda%ons for funding include the u%liza%on of third party contribu%ons and the dedica%on of the
AMO Gas Tax to Paved Roads. It is further recommended to increase our tax levy to address the iden%fied
funding short fall.
Communica%on of our progress can be posted on our Municipal website ( www.twp.stclair.on.ca ) and in
our St. Clair Beacon household flyer.
As part of this assignment, mul%ple budget scenarios were analyzed to assess different improvement
strategies to determine the short and long term effects on the overall Paved Road network performance.
Recommenda%ons were presented to Council and included in APPENDIX A.5 - Conclusions and
RecommendaCons.
1.7 PLAN IMPROVEMENT AND MONITORING
The Township of St. Clair has taken worthy ini%a%ve with the introduc%on and integra%on of the
CarteGraph Asset Management System to manage our asset inventory and condi%ons. The Township has
considerable investment in this system and is dedicated to upda%ng, maintaining and progressing with the
u%liza%on of this resource for assessing and priori%zing asset needs and incorpora%ng Levels of Service and
risk tolerance. Con%nuous dedica%on and improvement is necessary for advancement.
PW Asset Management Plan Public Works Asset Management Plan
Issued 30-MAY-2014
Revision 000 30-MAY-2014
Page 12 of 12
PW AMP
Document is Uncontrolled when Printed
The Asset Management Plan is an integral living document. To ensure it remains useful and relevant, the
following reviews are to be performed.
Asset Management Plan
AMP WHOLE / EXECUTIVE SUMMARY Review Cycle 5 Years
INTRODUCTION Review Cycle 5 Years
ASSET MANAGEMENT PLAN OVERVIEW Review Cycle 3 Years
PAVED ROADS Review Cycle 3 Years
BRIDGE STRUCTURES Review Cycle 3 Years
SIDEWALK / TRAILS Review Cycle 3 Years
STREET LIGHTS / TRAFFIC SIGNALS Review Cycle 3 Years
WATER NETWORK Review Cycle 3 Years
SEWER NETWORK Review Cycle 3 Years
APPENDIX Review Cycle 5 Years
Table 4 - Document Review Cycle
The Asset Management Plan, as a whole, is expected to be updated and communicated to Council every
five years. The Execu%ve Summary will be rewriJen at the same %me. Individual sec%ons should be
updated as new rela%ve data and informa%on become available.
Future reviews should include a look at other suppor%ng plans and policies within the context of this AMP.