Date post: | 11-Nov-2014 |
Category: |
Technology |
Upload: | rijuldhruv |
View: | 1,863 times |
Download: | 1 times |
MSE 617 Seminar in Quality Assurance & Management
Team F includes:
Dhruv, Rijul
Habibi, Shayaan
Kalantari, Mahram
Ravinder Singh
Al-Doukhi, Murtadha
Professor:
LUIS ECHEVERRIA
California State University - Northridge
*The Manufacturing unit consists of four teams A, B, C and F
*Our main concentration is to detect a defect trend from our
data related to workstation F
*Our manufacturing flow consists of:
Machine Shop (Internal Supplier)
Plant out of State (Internal Supplier)
Paint Shop (Internal Supplier)
External Suppliers
F4 F3 F2 F1 A1
C6 C5
TEAM F
Machine
Shop (MS)
Plant out of
shape (OR)
Paint shop
(PS)
External
Suppliers (V)
Data Selection
Data sorting
Analysis based on Pareto charts
Corrective action plan
Assumptions:
1. The data under consideration is not subject to change.
2. The cost of execution corrective action plan doesn’t influence our
conclusion.
3. Type N/A in the charge back column pertains to the defects in the same
workstation.
Breakdown of data into four major workstations F1, F2, F3, F4
Total Number of Defects in Team F Workstation (internal)
Workstati
on
Total
defects
% %
cumulative
F1 1078 71% 71%
F2 416 27% 98%
F3 10 1% 99%
F4 21 1% 100%
Total 1525 100%
1078
416
10 21
0%
20%
40%
60%
80%
100%
120%
0
200
400
600
800
1000
1200
F1 F2 F3 F4
TOTAL DEFECTS
% CUMULATIVE
Total number of defects in F due to external charge backs
Workstation Defects Charged
back
(external)
Total
F1 1078 1 1079
F2 416 12 428
F3 10 7 17
F4 21 0 21
Total 1525 20 1545
The total numbers of defects due to external charge backs are
negligible
Maximum defects were found at the workstation F1 with charge
back N/A (internal defects)
Hence, our entire concentration would be to work on
workstation F1 and plan corrective action to reduce the defects.
Months
Work Station
F1
Workstation
F2
Workstation
F3
Workstation
F4 Total F
JAN 314 212 4 4 534
FEB 370 122 3 4 499
MARCH 394 82 3 13 492
TOTAL 1078 416 10 21 1525
314
370 394
212
122
82
4 3 3 4 4 13
0
50
100
150
200
250
300
350
400
450
JAN FEB MARCH
Work Station F1
Workstation F2
Workstation F3
Workstation F4
Workstation F1 is
a major
contributor of
defects in March
2003.
Our further
analysis will
include the
breakdown of data
to reduce
maximum defects
in March 2003.
CHARGE
BACK
JAN FEB MARCH Total %
cumulat
ive
F1(N/A) 69 54 106 229 21.24
F2 35 75 86 196 39.42
PS 29 97 28 154 53.71
V 66 8 63 137 66.42
A1 37 24 12 73 73.19
C1 7 36 10 53 78.11
B1 18 16 15 49 82.65
C6 9 9 24 42 86.55
A2 20 2 13 35 89.80
DS 0 11 15 26 92.21
MS 3 20 2 25 94.53
C2 14 3 3 20 96.38
T 1 7 1 9 97.22
F3 0 1 6 7 97.87
B2 1 0 5 6 98.42
C3 2 3 1 6 98.98
A3 2 2 1 5 99.44
B3 1 1 1 3 99.72
C4 0 0 1 1 99.81
PD 0 0 1 1 99.91
F4 0 1 0 1 100.00
TOTAL 314 370 394 1078
0
20
40
60
80
100
120
F1(…
F2
PS V
A1
C1
B1
C6
A2
DS
MS
C2 T F3
B2
C3
A3
B3
C4
PD F4
JAN
FEB
MARCH
Monthly charge back analysis by F
0.00
20.00
40.00
60.00
80.00
100.00
120.00
0
50
100
150
200
250
Total
% cumulative
Overall charge back – F1
Workstation F1 has the maximum of internal defects N/A that were identified within the team.
Based on the result, we breakdown the charge backs for the month of March.
106
86
28
63
12 10
15
24
13 15
2 3 1 6 5
1 1 1 1 1 0 0
20
40
60
80
100
120
Charge back - March
MARCH
The internal defects are
again higher for the month
of March.
Therefore, we concentrate
extensively on defects
found in F1 which further
strengthens our decision
towards accurate corrective
action plan.
DEFECT CODE JAN FEB MARCH DEFECTS %
cumulative
B 98 86 116 300 27.80
E 66 87 61 214 47.64
H 19 30 64 113 58.11
K 10 47 56 113 68.58
C 11 65 22 98 77.66
D 21 23 29 73 84.43
R 60 0 0 60 89.99
X 6 1 23 30 92.77
J 8 5 11 24 95.00
F 2 19 2 23 97.13
M 8 7 5 20 98.98
A 5 0 6 11 100.00
TOTAL 314 370 395 1079
300
214
113 113 98
73 60
29 24 23 20 11
0.00
20.00
40.00
60.00
80.00
100.00
120.00
0
50
100
150
200
250
300
350
B E H K C D R X J F M A
DEFECTS
Overall family of defects – F1
The family of defect B is causing the maximum number of defects viz. 300 in
workstation F1.
We further breakdown the family of defect code B to find out which family
code is a major contributor overall as well as in the month of March.
Defect Code Jan Feb March Total %
Cumulative
B05 22 18 65 105 35%
B02 17 30 27 74 60%
B01 23 0 14 37 72%
B08 2 23 1 26 81%
B10 9 8 4 21 88%
B04 12 0 0 12 92%
B06 3 5 1 9 95%
B07 5 2 2 9 98%
B03 5 0 2 7 100%
Total 98 86 116 300
65
0
10
20
30
40
50
60
70
B05 B02 B01 B08 B10 B04 B06 B07 B03
March
Jan
Feb
105
74
37
26 21
12 9 9 7
0%
20%
40%
60%
80%
100%
120%
0
20
40
60
80
100
120
B05 B02 B01 B08 B10 B04 B06 B07 B03
Total
% Cumulative
B05 family defect code is
responsible to cause the
maximum defects overall.
It is also the highest in the
month of March.
UNIT
S/N
JAN FEB MARCH TOTAL
DEFECT
S
%
Cumulativ
e
165 0 42 133 175 16.23
277 0 56 103 159 30.98
272 65 49 0 114 41.56
275 27 60 27 114 52.13
166 0 22 88 110 62.34
274 15 80 0 95 71.15
164 28 61 0 89 79.41
162 83 0 0 83 87.11
163 55 0 0 55 92.21
276 41 0 0 41 96.01
167 0 0 22 22 98.05
278 0 0 13 13 99.26
168 0 0 7 7 99.91
279 0 0 1 1 100.00
TOTAL 314 370 394 1078
133
103
0
27
88
0 0 0 0 0
22
13 7
1
42
56 49
60
22
80
61
0 0 0 0 0 0 0 0 0
65
27
0
15
28
83
55
41
0 0 0 0 0
20
40
60
80
100
120
140
165 277 272 275 166 274 164 162 163 276 167 278 168 279
MARCH
FEB
JAN
175 159
114 114 110 95 89 83
55 41
22 13 7 1
0.00
20.00
40.00
60.00
80.00
100.00
120.00
0
20
40
60
80
100
120
140
160
180
200
165 277 272 275 166 274 164 162 163 276 167 278 168 279
TOTAL DEFECTS
% Cumulative
Unit number 165 not only has
maximum number of defects
overall but also during the 3
month period (Jan 2003-March
2003) with the highest in March
2003.
Working towards Job number F1-07 will
help us reduce the maximum number of
defects
134
119
104
86 84 78
55
45 44 43 40 36
30 27 25 22 19 12 10 8 8 7 7 7 6 6 4 3 2 2 1 1
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
20
40
60
80
100
120
140
160F1-0
7
F1-1
0
F1-1
9
F1-1
3
F1-1
8
F1-1
4
F1-2
0
F1-1
2
F1-1
1
F1-0
1
F1-0
9
F1-0
8
F1-0
5
F2-0
2
F1-0
6
F2-0
1
F1-0
3
F1-1
7
F1-0
2
F2-1
3
F2-1
7
F1-0
4
F2-0
9
F2-1
6
F1-1
5
F1-1
6
F2-0
4
F2-0
7
F2-0
5
F2-1
0
F2-1
9
F4-0
2
TOTAL DEFECTS
% Cumulative
Overall analysis of Job number – F1
Group Jan Feb March Total defects %
cumulative
Operations 243 324 312 879 81.54
External supplier 66 8 63 137 94.25
Engineering 1 18 16 35 97.50
Internal supplier 4 20 3 27 100.00
Total 314 370 394 1078
Operations Group is the highest
potential root cause of total number
of defects in the workstation F1
during the period of Jan 2003 –
March 2003.
879
137
35 27
0.00
20.00
40.00
60.00
80.00
100.00
120.00
0
100
200
300
400
500
600
700
800
900
1000
OPERATIONS EXTERNALSUPPLIER
ENGINEERING INTERNALSUPPLIER
TOTALDEFECTS
%cumulative
243
66
1 4
324
8 18 20
312
63
16 3
0
50
100
150
200
250
300
350
OPERATIONS EXTERNALSUPPLIER
ENGINEERING INTERNALSUPPLIER
JAN
FEB
MARCH
Total Defects: Team F constitutes of 1525 defects out of which 1078 are contributed
by workstation F1.
Charge backs: Internal charge backs N/A maximum for workstation F1
Monthly Defects: Maximum numbers of defects caused in Jan 2003. However, F1
contributes 80% of defects (394/492) in March 2003 as compared to 59% of defects
(314/534) in Jan 2003. Therefore, team decided to concentrate on March 2003 data.
Family defect code: B was found to cause maximum number of overall defects.
Further breaking down the defect code B resulted in family defect code B05 to cause
the maximum number of defects overall as well as in March 2003.
Unit S/N: 165 accounted to maximum number of defects when the data was broken
down even more.
Job no.: F1-07 causing maximum defects.
Group: Operations group is the one that is causing the maximum defects. Hence
improvement is needed on that group.
Therefore, Focusing on workstation F1 especially for the month of March 2003 with
charge backs N/A (internal defects), family defect code B05, Unit S/N 165, Job No.
F1-07 and group of Operations, Team F would be able to reduce the maximum
number of defects.
The corrective action plan will be done using the
Plan-Do-Check-Act problem solving technique.
A thorough inspection team should be at place to
keep internal defects in F1 at the minimal.
It is very important for team F since it is the last
team in the manufacturing flow and the final output
of production maybe input to customers in the
form of finished goods.
Placing a very strong quality team (quality
engineers, inspectors, etc.) to strengthen the quality
process to achieve ‘zero defects’.
Pilot test the model to identify any technical issues
and make changes as necessary in order to reduce
defects generating from family code B05.
Hold brainstorming sessions and organize team
meetings with all the members that were responsible for
Job no. F1-07 as maximum defects had occurred while
performing the job.
Analyze and refine current tools and processes and
ensure that equipments are up to date with proper
calibration thereby reducing machine wear and
maintenance issues.
Employee training and seminars to be provided to
refresh quality control standards and deliver high quality
products.
An improved quality plan in place which includes any
process, procedure or system changes requirement and
any monitors or controls necessary to prevent
recurrence of the problem.
Once the above corrective actions are implemented to
improve the efficiency of team F, we would
continuously monitor the process to make sure there is
continuous improvement according to the PDCA cycle.
Continuous Improvement
Workstation F1 needs the most improvement due to high
number of defects.
The suggested corrective action plan will improve each area
assessed in workstation F1.
As per our recommendation, the next or alternate
corrective action would be to concentrate on maximum
defects occurring from other workstations too (especially
F2) to improve overall efficiency and quality performance
of team F.
With potential utilization of all the statistical tools and
problem solving techniques we believe that the ideal quality
aim of ‘zero defects’ can be achieved.