The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
i
FINAL REPORT
RESETTLEMENT ACTION PLAN (RAP) FOR AGASSA EROSION SITE,
OKENE LOCAL GOVERNMENT AREA
SUBMITTED TO
KOGI STATE NIGERIA EROSION AND WATERSHED MANAGEMENT PROJECT
(KGS-NEWMAP)
PLOT 247, TUNDE OGBEHA STREET, GRA, LOKOJA.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
i
RAP Basic Data/Information
S/N Subject Data
1 Intervention Site Agassa Gully Erosion sub-project, Okene LGA, Kogi State
2 Need for RAP Resettlement of People Displaced by the Project/Work
3 Nature of Civil Works Stabilization or rehabilitation in and around Erosion Gully site - stone
revetment to reclaim and protect road way and reinforcement of
exposed soil surface to stop scouring action of flow velocity, extension
of culvert structure from the Agassa Road into the gully, chute channel,
stilling basin, apron and installation of rip-rap and gabions mattress at
some areas.
Zone of Impact 5m offset from the gully edge.
4 Benefit(s) of the Intervention Improved erosion management and gully rehabilitation with reduced
loss of infrastructure including roads, houses, agricultural land and
productivity, reduced siltation in rivers leading to less flooding, and the
preservation of the water systems for improved access to domestic
water supply.
5 Negative Impact and No. of PAPs A census to identify those that could be potentially affected and eligible
for assistance has been carried out. However, Based on inventory, a
total of 241 PAPs have been identified.
6 Type of Losses Structures (buildings) and agricultural resources
7 Impact Mitigation Prudent approach to stabilisation efforts will reduce level of impact on
identified structures; damaged assets to be compensated at
replacement value
8 Census Cut-Off Date December 10, 2017
9 RAP Implementation Cost? SPMU implements with support from Federal Ministry of
Environment and other relevant Federal and State MDAs and World
Bank. RAP implementation committee shall include representatives of
the local government, local communities and PAPs, Site Committee,
NGO/CBOs, Ministry of Lands and Survey with support from the
Social Livelihoods Officer (Social Safeguard Specialist) of SPMU
10 Grievance Procedures A Community Leader as Chairman of the Committee, Site Committee
member, PAPs Representative, local government, elected
representative of the community at the LG, Affected local government
Land officer and SPMU as members, shall be formed to hear
complaints and facilitate solutions, so as to promote dispute settlement
through mediation to reduce litigation.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
ii
TABLE OF CONTENTS
Content Page
RAP Basic Data/Information i
Table of Content ii
List of Tables v
List of Figures vi
List of Maps vii
List of Appendices viii
Definitions of key Terms ix
List of Acronyms xii
Executive Summary xiii
Chapter One: Introduction
1.1 Background 1
1.2 The Need for a Resettlement Action Plan for the Proposed Project 1
1.3 The RAP and other Safeguard Instruments Triggered by the Project 2
1.4 Aim and Objectives of the RAP 2
1.5 Scope of Services and task of the RAP 2
1.6 Guiding Principles for the RAP 3
1.7 Approach/Methodology of RAP Preparation 3
1.8 Structure of the RAP Report 4
Chapter Two: Description of the Proposed Project and Socio-economic Baseline of the Project
2.0 Introduction 5
2.1 Description of Main NEWMAP Components 5
2.2 Kogi State and Description of Proposed Intervention Sites 6
2.3 Site Description 9
2.4 Geology, Relief & Drainage of Targeted Site 10
Chapter Three: Census and Socio-Economic Survey
3.1 Introduction 11
3.2 Census Cut-Off Date 11
3.3 Data Analyses and Interpretation 11
3.3.1 Analysis of Persons (Respondents) Interviewed 11
3.4 Socio Economic Date Results and Discussion 12
3.4.1 Agassa Household Demographics 12
3.4.2 Gender Distribution and Marital Status 12
3.4.3 Family Size and Average Age of Household Members 13
3.4.4 Educational level & Literacy Status 14
3.5 Agassa Socio-Economic Characteristics 14
3.5.1 Major Occupation of Household Heads 15
3.5.2 Household Income & Expenditure 15
3.5.3 Land and Other Resources: Ownership and Use 15
3.5.4 Household Residency & Housing Quality 15
3.5.5 Awareness of Proposed Project 16
3.5.6 Response on Desirability of Proposed Project 17
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
iii
Chapter Four: Impact of the Project
4.1 Introduction 18
4.2 Positive Impacts of the Project 18
4.3 Negative Impacts of the Project 18
4.4 Analysis of the Inventory of Affected Assets 18
4.5 Avoidance/Minimization of Resettlement 19
4.6 Mitigation Measures 19
4.7 Number and Types of Affected Persons 20
4.8 Inventory of Impacted Assets 20
4.8.1 Impact on Land and Structures 20
4.8.2 Impact on Agricultural Resources (Crops) 20
4.8.3 Impact on Utilities 20
4.8.4 Impact on Social Networks 20
4.8.5 Impact on Vulnerable Group 20
4.8.6 Potential Relocation Areas 21
Chapter Five: Chapter Five Relevant Local and Federal Policy, Legal & Regularity Framework
5.0 Introduction 22
5.1 The Resettlement Policy Framework (RPF) of The NEWMAP 22
5.2 Interim Guidelines for Addressing Legacy issues in World Bank Project 22
5.3 Policy on Disclosure and Access to information 23
5.4 Nigeria Regularity Framework 23
5.4.1 The Federal Ministry of Environment 23
5.4.2 Nigerian Law/Land use Act of 1978 & Resettlement Procedures 23
5.4.3 Requirements of the Land Use Act 24
5.5 International Guidelines 25
5.5.1 The World Bank Policy on Involuntary Resettlement WB OP 4.12 26
5.5.2 Conclusion Drawn from the Review of World Bank Policy on Involuntary
Resettlement 26
5.6 Comparison between Nigerian Land Use Act (1978) and World Bank operational
Policy (WB OP. 4.12) 26
5.7 Eligibility Criteria 30
Chapter Six: Valuation & Compensation of Affected Structures and Properties
6.0 Introduction 32
6.1 Valuation Methodology 32
6.1.1 Replacement Cost Method 32
6.1.2 Land Resettlement 32
6.1.3 Disturbance and other Incidental Contingencies 32
6.2 Affected Structures 32
6.2.1 Immovable Structures/Property 32
6.2.2 Moveable Structures/Property 32
6.2.3 Permanent Structures/Asset 33
6.2.4 Compensation and Other Resettlement Assistance 33
6.3 Modes of Restitution 33
6.4 Compensation Payment and Procedures for Delivery of Compensation 33
6.5 General Principle to be Adopted for Compensation 33
6.5.1 Procedure for Delivery of Compensation 33
6.6 Assistance to Vulnerable Groups 34
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
iv
6.7 Livelihood Restoration 34
6.7.1 Restoration Strategies 34
6.8 Provision of Amenities for the Communities 35
6.9 Environmental Protection and Management 35
Chapter Seven: Public Participation and Consultations
7.1 Introduction 36
7.2 Objective of the Consultation 36
7.3 The Stakeholders 36
7.3.1 Consultation Strategies 36
7.4 Discussion with Stakeholders and Summary of Outcome Conclusion 37
7.5 RAP Public Disclosure 38
Chapter Eight: RAP Implementation and Institutional Arrangement and Capacity Building
8.0 Introduction 42
8.1 Organisational Arrangement 42
8.2 Institutional Capacity Building Requirements and Costs 45
8.3 RAP Implementation Schedule 46
8.3.1 Resettlement Activities and Responsibilities 46
8.3.2 Estimated Cost of the RAP Implementation and Funding 48
8.3.3 Sources of Fund 48
8.3.4 Implementation Timetable 48
8.4 Coordination with Civil Works 49
Chapter Nine: Grievance Redress Mechanism
9.0 Introduction 51
9.1 Grievance Redress Process 51
9.2 Stages in grievance Redress process 51
9.3 Procedure for Registering a complaint 52
9.4 Grievance Log and Response Time 53
9.5 Monitoring Complaints 53
Chapter Ten: Monitoring and Evaluation
10.1 Introduction 54
10.2 Purpose of Monitoring 54
10.3 Components and Elements of the Monitoring Plan 54
10.4 Monitoring Framework (Internal and External) 55
10.4.1 Internal Monitoring 55
10.4.2 External Monitoring/Evaluation 55
10.5 Monitoring Parameters / Indicators 56
10.6 Reporting 56
10.7 Completion Audit 56
Bibliography 57
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
v
List of Tables
Table Page
2.1: Main NEWMAP elements and outcomes 5
2.2: The population of Kogi State by Local Government Area 10
5.1: Comparison between Nigerian Land Use Act and World Bank Operational Policy (0P4.12) 26
5.2: The Entitlement Matrix for Various Categories of PAPs 29
5.3: Eligibility Criteria for Compensation 31
7.1: Queries/Observations and Responses given to the Stakeholders 37
8.1: Roles and Responsibilities for Implementation of the RAP 42
8.2: Awareness and Capacity Building Needs of Relevant Stakeholders 45
8.3: Summary of Resettlement Activities and Responsibility for implementation of the RAP 46
8.4: Budget Estimate for the RAP Implementation 48
8.5: Major Component Tasks and Schedule for the RAP Implementation 49
9.1: A Typical Reporting Format for Grievance Redress 53
10.1: Monitoring Indicators 56
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
vi
List of Figures
Figure Page
3.1: Gender Distribution of Household Heads in Agassa 13
3.2: Marital Status of Household Heads in Agassa 13
3.3: Average Age of Household Heads in Agassa 13
3.4: Average Age of Dependent Household Members 13
3.5: Percentage Distribution of Family Size 14
3.6: Highest Educational Level of Household members in Agassa 14
3.7: Highest Educational Level of Household Heads in Agassa 14
3.8: Distribution of Household Heads by Occupation Type in Agassa 15
3.9: Households’ Reasons for Residing in Agassa Catchment 16
3.10: Types of Houses occupied by Households in Agassa 16
3.11: Awareness of Proposed Project 16
3.12: Desirability of Proposed Project 17
7.1: Consultation with Men/Elders Focal group (Friday, 26/01/2018) 39
7.2: Consultation with the Onoba of Agassa (Friday, 24/11/2017) 39
7.3: Consultation with Women Focal Group (Friday, 26/01/2018 39
7.4: Consultation with Youth Focal group at Agassa (Friday, 26/01/2018) 39
7.5: Cross Section of Stakeholders Meeting at Agassa (Friday, 26/01/2018) 39
7.6: Consultant and Stakeholders Forum (Friday, 26/01/2018) 40
7.7: Consultant and Stakeholders Forum (Friday, 26/01/2018) 40
7.8: Consultant and Stakeholders Forum (Friday, 26/01/2018) 40
7.9: A Cross Section of Participants during Consultation Meetings 40
7.10: Meeting of Consultant, NEWMAP Representatives and Agassa Community
Erosion Association 41
7.11: Site Inspection with the Engineering Crew of the NEWMAP 41
7.12: Site Inspection with the Engineering Crew 41
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
vii
List of Maps
Maps Page
2.1 Map of the World 7
2.2 Map of Africa 7
2.3 Map of Nigeria Showing Kogi State 7
2.4 Map of Okene Local Government Area 7
2.5 Map of Kogi State showing Okene Local Government Area 7
2.6 Current NEWMAP States 8
2.7 Corridor Mapping of Agassa Gully Erosion Site 8
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
viii
List of Appendices
Appendix Page
1: Minutes of Public Consultations 58
2: Focal Group Discussion (FGD) 60
2a: Attendance List: Community Consultation 63
2b: Socio-Economic Survey Questionnaire 68
2c: Cut-off Date Letter to Stakeholders 68
3: Safeguard Instruments Prepared for the Proposed Works 69
4: Approach/Methodology of RAP preparation 70
4.1: Analysis of Socio-Economic Background of PAPs 73
5: Summary of Valuation for Resettlement Action Plan for Agassa Community 75
6: Entitlement Summary for Owners of Structures and Economic Trees 80
6a: Agassa Tenants for Financial Assistance 83
7: Corridor Mapping of Agassa Gully Erosion Site at Okene, Kogi State 86
8: List of Experts who carried out the Survey 87
9: Photo gallery of Agassa PAP 88
10: Engineering Design of Agassa Gully Erosion 90
11: Standard Rate for Economic Trees and Cash Crops in Nigeria. 90
12: Cultivated Crops 92
13: Letter of appeal by Mall. Yahaya Suleiman (KGNM/AGASSA/17/004) 94
14: Stages in the Grievance Redress Process for the RAP 95
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
ix
DEFINITION OF TERMS
Word I Term Definition
Asset Inventory A complete count and description of all properties that will be acquired.
Bank World Bank
Census Official enumeration and collection of demographic information of people and
individuals in the sub-project locations of the Project.
Children All persons under the age of 18 years according to International Regulatory
Standard (Convention on the Rights of Child 2002).
Community A group of individuals broader than households, who identify themselves as a
common unit due to recognized social, religious, economic and traditional
government ties or shared locality
Compensation Payment in cash or in kind for an asset or resource acquired or affected by the
project.
Cut–off-Date A day on and beyond which any person who occupies land or assets, or
constructs assets on land, required for project use, will not be eligible for
compensation. The date is often the day the assessment of persons and their
property in the project area commences
Displacement Removal of people from their land, homes, farms, etc. as a result of a project’s
activities. Displacement occurs during the involuntary taking of lands and from
involuntary restriction or access to legally designated parks and protected areas
resulting in adverse impacts on the livelihoods of PAPs.
Entitlements Compensation and other forms of assistance provided to displaced persons in
the respective eligibility category.
Environmental
and Social
Management
Framework
(ESMF)
An environmental assessment instrument (document) which establishes a
mechanism to determine and assess future potential environmental and social
impacts of productive investments under the proposed NEWMAP project, and
then to set out mitigation, monitoring and institutional measures
to be taken during design, implementation and operation of the project activities
to eliminate adverse environmental and social impacts, offset them, or reduce
them to acceptable levels. This instrument has been prepared as a separate and
stand-alone document to be used in conjunction with the RPF.
Grievance
Procedures
The processes established (a) under law, local regulations, or administrative
decision to enable property owners and other displaced persons to redress issues
related to acquisition, compensation, or other aspects of resettlement, as well as
(b) specific grievance processes put in place as part of the design of a project.
Host Communities Communities receiving resettled people as a result of involuntary. resettlement
activities
Land Acquisition The process whereby a person is compelled by a public agency to alienate all or
part of the land he/she owns or possesses, to the ownership and possession of
that agency, for public purpose in return for a consideration.
Lost Income
Opportunities
Lost income opportunities refer to compensation to project affected persons
for loss of business income, business hours/time due to project
Market Rate Highest rate over the last five years based on commercial terms.
Market Value The most probable selling price or the value most often sought by buyers and
sellers. It assumes buyers and sellers have reasonable knowledge, act
competitively and rationally are motivated by self-interest to maximize
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
x
satisfaction and both act independently and without collusion, fraud or
misrepresentation
Physical
Displacement
Loss of residential structures and related non-residential structures and physical
assets because such structures / assets are located in the project area.
Private property
owners
Persons who have legal title to structures, land or other assets and are accordingly
entitled to compensation under the Land Act.
Project Affected
Person(s)
A person that loses assets and/or usage rights and/or income generation
capacities (e.g., land, structure, crops, businesses) because these
assets/rights/capacities are located in land to be acquired or used, for needs of
the project. Not all PAPs are displaced due to the Project, but all are potentially
affected in the maintenance of their livelihood.
Project-Affected
Community
A community that is adversely affected by the project.
Rehabilitation
Assistance
The provision of development assistance in addition to compensation such as
land preparation, credit facilities, training, or job opportunities, needed to enable
Project Affected Persons and Displaced Persons to improve their living
standards, income earning capacity and production levels; or at least maintain
them at pre-Project levels
Replacement Cost The amount of compensation that would have to be paid to replace an asset
including all cost associated with replacement of asset displaced by the
NEWMAP project at the present time, according to its current worth.
Resettlement Policy
Framework (RPF)
The present document, which is the overall Policy Framework for
Compensation, Resettlement and Rehabilitation of Project Affected Persons for
the PPP. The Policy Framework describes the process and methods for carrying
out resettlement under the Project, including compensation, relocation and
rehabilitation of project affected persons.
Resettlement
Action Plan (RAP)
The resettlement action plans prepared for specific micro-projects. It is a
resettlement instrument to be prepared when project activities are identified, that
require land acquisition that leads to physical displacement of persons, and/or
loss of shelter, and /or loss of livelihoods and/or loss, denial or restriction of
access to economic resources. The RAP is prepared by the party impacting
people and livelihoods in this manner and contains specific and legal binding
requirements to be taken by that party to resettle and compensate the affected
party before project activities causing this adverse impact are implemented.
Resettlement The measures taken to mitigate any and all adverse impacts of the project on
PAP’s property and/or livelihoods, including compensation, relocation (where
relevant), and rehabilitation
Resettlement
Assistance
Support provided to people who are physically displaced by a project. This may
include transportation, food, shelter, and social services that are provided to
affected people during their resettlement. Assistance may also include cash
allowances that compensate affected people for the inconvenience associated
with resettlement and defray the expenses of a transition to a new locale, such as
moving expenses and lost work days.
Right of Way Right to make a way over a piece of land, usually to and from another piece of
land.
Squatters Squatters are landless households squatting within the public / private land for
residential and business purposes.
“special assistance” This refers to special efforts provided to the vulnerable physically challenged
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xi
to vulnerable
people
persons such as those with blindness, paralysis, difficulties with locomotion,
incapacity to work, etc., who are displaced by the project. The “special
assistance” must be given by qualified persons/relatives/agencies, capable of
helping invalids by providing transitional support (e.g. moving expenses,
temporary food supply, etc.)
Vulnerable
Groups:
People who may by virtue of gender, ethnicity, age, physical or mental disability,
economic disadvantage or social status are more adversely affected by
resettlement than others; and who may have limited ability to claim or take
advantage of resettlement assistance and related development benefits.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xii
ABBREVIATIONS AND ACRONYMS
ARAP - Abbreviated Resettlement Action Plan
BIR - Boards of Internal Revenue
BPE - Bureau of Public Procurement
DAI - Disclosure and Access to information
DP - Displaced Persons
EA - Environmental Assessment
ESIA - Environmental and Social Impact Assessment
ESMF - Environmental and Social Management Framework
ESMP - Environmental and Social Management Plan
FGN - Federal Government of Nigeria
FGD - Focus Group Discussion
FMWR - Federal Ministry of Water Resources
GRC - Grievance Redress Committee
IDA - International Development Association
ICP - Investment Climate Program
CT - Information and Communication Technology
PR - Intellectual Property Rights
ITES - Information Technology Enabled Services
LGA - Local Government Authority
MDA - Ministry Departments and Agencies
NGQ - Non-Governmental Organization
PAD - Project Appraisal Document
PAP - Project Affected Person
PDO - Project Development Objective
PIM - Project Implementation Manual
PIU - Project implementation Unit
RAP - Resettlement Action Plan
ROW - Right of Way
RPF - Resettlement Policy Framework
SSI - Semi Structured interview
WB - World Bank
SPMU - State Project Management Unit
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xiii
EXECUTIVE SUMMARY
Introduction
Nigeria faces severe problem of soil erosion and flooding, due to both human and natural causes. Over
6000km2 of land are affected by erosion and 3400km2 are highly exposed. Erosion has devastating effect
on many people’s lives and destroys essential infrastructure for economic development and poverty
alleviation. Gully erosion contributes to environmental problems and damage large percentage of private
and public infrastructure all over the country. This undermines economic growth and is a threat to the
federal government of “vision 202020”
Recent assessment confirms that the scale of the problems transcends what communities, local
governments, states and federal government can address without help from development partners.
Consequently, the federal government (FGN) initiated the Nigeria Erosion and Watershed Management
Project (NEWMAP) to provide an institutional platform for the management of gully erosion and
flooding. The project is supported by financing from the World Bank, Global Environmental Facility and
Special Climate Change Fund, and the Government of Nigeria. NEWMAP finances activities
implemented by States and activities implemented by the Federal Government of Nigeria (FGN). The
project currently includes nineteen (19) States namely Anambra, Abia, Cross River, Edo, Enugu, Ebonyi,
Imo, Kogi, Delta, Oyo, Kano, Plateau, Gombe, Sokoto, Nasarawa, Niger, Borno, Katsina and Akwa-
Ibom.
Kogi State belongs to the second generation of participating states under the Kogi State NIGERIA
EROSION AND WATERSHED MANAGEMENT PROJECT (KOGI NEWMAP). One of the
intervention sites is the Agassa Erosion Gully in Okene L.G.A. To address the social and environmental
safeguard concerns, at the national level, two instruments were prepared, namely: an Environmental and
Social Management Policy (ESMP) and Resettlement Policy Framework (RPF) which complement each
other. The RPF addresses potential adverse social impacts that might arise from resettlement of people
affected by the project, while the ESMP addresses other possible harmful Social and Environmental
effects of the project. This RAP and associate ESMP derives the RPF and ESMF into specific cost,
measurable and monitor able action for the Agassa Gully intervention site.
Justification for RAP
The RAP identified potential Project Affected Persons (PAPs) and engaged them in participatory
discussions regarding the plan in order to adequately compensate them for their losses. Early
reconnaissance/Scoping of the intervention site revealed that inhabitants shall be displaced. In compliance
with the World Bank Operational Policy, OP 4.12, this RAP was prepared for managing the potential
impact on displaced persons.
Aim of RAP
The aim of the RAP is to identify and assess the human impact of the proposed works at the gully erosion
site in Agassa and prepare an action plan to be implemented in coordination with the civil works in line
with World Bank Policy and Nigeria Policies and Laws.
Site Description
Agassa is situated on Latitude 07o
32’33” and Longitude 06o
13’25” (UTMWGS84) 193514.920ME &
834753.666MN. Agassa gully erosion site is a set of gullies located in about four (4) gully fingers around
Agassa community in Okene LGA of Kogi State stretching from the Ahache area and extending to the
central burial ground area and beyond. The area is typically sandwiched between hills with steep slopes.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xiv
The gullies put together are about 3.5km with width varying from 2m to 5m and depth of 1m to 6m. The
gullies have existed in the community for about 20years, and it is caused by uncontrolled development,
unchecked water falls from the surrounding hills resulting in flooding and erosion. The erosion is
therefore as a result of Human and Natural causes, namely: unplanned settlement, nature of soil, slope
and lack of institutional intervention. Many residential buildings are likely to be destroyed and many are
under serious threat of collapse. The access roads in the community are exposed to destruction and the
gully has developed fingers. Urgent action is required at the site to salvage the environment, protect and
preserve lives and properties.
The affected site enjoys ample rainfall. The annual rainfall ranges from 1000mm to 1300mm per annum.
The vegetation is mostly Guinea Savannah. The geology of the area is basement complex comprising of
granite, gneiss and biotite. Most of the inhabitants of the area are generally Ebiras with few populations of
non-indigenes. Majority of the people are farmers, weavers and traders, the crop grown are mainly yam,
cassava, maize and beniseed.
The community is headed by a traditional ruler with the title of Onoba of Agassa with a strong attachment
to His subjects and well loved by his people. There exists a popular masquerade festival called
EKUECHI which is well celebrated around November of every year and Eche – Ane (festival of female)
and EcheAhana (day singing festival) and Okehi festival.
Legal Framework for land Acquisition
The legal framework for land acquisition in Nigeria is the Land Use Act of 1978 reviewed under CAP
202, 1990. The relevant World Bank operational policy (OP 4:12) which addresses land acquisition and
involuntary resettlement was reviewed. The area of variations between the Land Use Act of 1978 and the
World Bank’s OP 4.12 are mostly on rehabilitation measures, which are neither proscribed nor
mandated in the Act. Thus, it is noted in this RAP that in the course of project implementation, any
divergence between the Laws in Nigeria and that of the World Bank’s OP 4.12, the more beneficial to
the project affected persons shall take precedence in the implementation of this RAP.
Census Cut-Off Date
The established cut-off date to record the RAPs along the Agassa Gully Erosion corridor of work was
10th December, 2017, which was communicated to the PAPs and communities during the general
stakeholders meeting. A letter of notice was distributed to all stakeholders through the Community
Association Chairman to traditional rulers, Churches and Mosques. In the event of project delay for
more than two years, there will be need to update the socio-economic survey carried out for this RAP.
Impacts of Proposed Work
The major benefits of the project will occur in the form of improved erosion management and gully
rehabilitation which will lead to:
▪ Reduced loss of infrastructure including roads, houses etc.
▪ Reduced siltation in rivers leading to less flooding and the preservation of the water systems for
improved access to domestic water supply.
▪ Reduced risks of flood
▪ Restored vegetative cover, improved environmental conditions and more humid local microclimates,
leading to improved habitat for wildlife and carbondioxide exchange
▪ Environmental improvements due to land stabilization measures which preserve the landscape and
biodiversity.
Conversely, the implementation of the intervention measures would induce some negative impacts on the
people and their assets with regards to displacement. Based on the inventory carried out, a total of 241
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xv
persons have been identified as Project Affected Persons (PAPs) made up of different categories of
people whose structures and agricultural products shall be affected. Out of the total number of PAPs
inventorised, forty 40 were identified as tenants.
Mitigation Measures
The main objective of the RAP is to develop programmes that can improve the livelihoods of PAP’s or
restore them to the pre-displacement levels. To provide a safety net for all the PAPs and improve their
livelihood until they become self-sufficient and resilient to economic stresses as they were before the
project came or even better, appropriate mitigation measures and preparations of the entire resettlement
process have been developed and shall be ensured. Specifically, the following mitigation measures shall
be implemented:
- PAPs shall be consulted before and during the implementation of this RAP to ensure their full
participation in the RAP process.
- PAPs shall be compensated in line with this RAP before actual project implementation. This
implies that construction activities (displacement and demolition) will not take place until PAPs
have been full compensated.
- Assistance to PAPs / vulnerable persons shall be adhered to in line with the recommendations in
this RAP.
- RAP implementation including livelihood restoration measures shall be monitored by the SPMU
to ensure that PAPs and the vulnerables are restored to the pre-project social conditions.
- Grievance redress shall be given high priority in this project. For the vulnerable, priority shall be
given in all mitigation measures relating to them. Stress to this group shall be avoided. Where
mitigation measures include physical preparation of site as appropriate assistance support and
protection shall be provided to help them overcome difficulties in the process.
In order to adequately mitigate the negative impacts on the PAPs, the cost of the possible damage to
assets have been calculated by generating current market values and estimates for how much it would cost
to replace or repair affected assets including transaction costs where applicable. Unit costs were primarily
calculated using information from the local market. A register has been prepared for the PAPs with
regard to their losses and compensation.
Public Participation
Public participation in the RAP included consultations and communication. Consultation include a two-
way process in which ideas about the project and concerns of stakeholders and the project designers were
shared and considered mutually by affected populations and other stakeholders. Communication
included the dissemination of information of NEWMAP activities to the concerned public, the project
affected persons and other relevant issues.
Resettlement of PAPs and Livelihood Restoration
The PAPs were informed of the range of different mitigation measures/compensation package,
resettlement assistance, and livelihood improvement options available to them and were given the
opportunity to express their preferences. This option-based resettlement planning is part of a
development approach that aims to ensure that the PAPs are able to reconstruct their production
foundations and become self-sustaining, at least to pre-intervention work level. The PAPs have agreed to
move out of the setbacks of the gully corridor for the work and also to the various resettlement benefits
which are to be provided to improve their means of livelihood or restore to it to pre-impact status.
RAP Coordination and Implementation
The implementation of the RAPs shall require close collaboration among all the stakeholders with a
mutual understanding struck at the beginning. The institutional arrangement has been pragmatically
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xvi
designed to involve relevant Stakeholders with the SPMU as the project implementer. Federal Ministry of
Environment as well as other relevant Federal and state MDAs and World Bank concerned with erosion
and watershed management shall be involved as designed in the arrangement for implementation. Also,
the RAP implementation committee made up of representatives of the local government, local
communities and PAPs, Site committees, trade Union/NGO, lands and survey with support from the
social Safeguard Specialist of the SPMU shall ensure adequate handling of the resettlement issues.
No civil works contracts for the proposed rehabilitation work shall be initiated unless land is free of any
encumbrance. The major component tasks and schedule for the RAP implementation have been
developed in the RAP.
Major Component Tasks and Schedule for the RAP Implementation
ACTIVITIES 2017 2018 2019 REMARKS
NO
V
DE
C
JAN
FE
B
MA
R
AP
R
MA
Y
JUN
E
JUL
Y
AU
G
SE
P
OC
T
NO
V
DE
C
JAN
FE
B
MA
RC
H
AP
RIL
MA
Y
JUN
E
Consultation
/community
participation and
information to people
affected cut-off date
announcement census
and survey analysis
date and verification of
impacts
Nov2017-
March 2018
RAP Approval
April - August
2018
Disclosure of RAP
Sept. – Oct.
2018
RAP implementation
including payment of
compensation and or
supplementary
assistance
Nov. 2018
Implementation/ civil
work, commencement
of project
Nov. - Feb
2019
Mark-up visit by
stakeholder/SPMU
March 2019
Economic Restoration
Assessment
April - June
2019
Strengthening Organizational Capability
Based on the interaction with the relevant stakeholders, assessment and determination of the
characteristics of all project affected persons (PAPs), valuation of assets to be compensated a well as the
assessment of the institutional capacities of the different parties involved in the RAP implementation,
areas of awareness creation and training/capacity building have been identified. It is the responsibility of
the Social Safeguard Officer to ensure that all identified stakeholders are trained accordingly.
Budget Estimate
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xvii
The total cost implication for the implementation of the RAP is Forty Million, One Hundred and Thirty-
Nine Thousand, Four Hundred and Ninety Naira (N40,139,490.00) only. In the table below, this sum is
expected to cover compensation of assets affected and additional mitigations for livelihood restoration
measures coordination of additional mitigation, grievance management and compensation commission.
In addition, a provision of 10% contingences was added to amount to the overall cost such as inflation
that shall be allowed and added to the current budget.
SPMU is the source of this fund for the payment of the necessary compensation and mitigation measures
while, overall financial cost for compensation shall be made by issuing cheque which can only be cashed
after no dispute arises on the ownership and any other claim.
Budget Estimate for the RAP Implementation
S/No. Item Cost (N) Total (N)
A1 Compensation:
370,000.00
28,170,900.00
28,540,900.00
Agricultural Crops
Structures
Sub-total
B Additional Mitigation
624,000.00
100,000.00
724,000.00
Livelihood measures/assistance for
vulnerable group
Grievance Redress Management
Sub-total
C Implementation
Compensation commission: cost of
transportation, accommodation and
feeding
320,000.00
Capacity building/Institutional
strengthening
6,240,000.00
Disclosure 500,000.00
Management 200,000.00
Sub-total 7,260,000.00
E Add Contingencies (10%) 3,615,490.00
Grand Total 40,139,490.00
Grievance Redress Mechanism
The likelihood of dispute is much reduced because the PAPs and other relevant stakeholders have been
consulted and were part of the entire process of identifying PAPs and generating the market values for the
various assets. Nevertheless, in the event of any dispute, a conflict resolution mechanism has been
designed for the RAP implementation. This mechanism makes the judicial system the least desirable and
last resort to redress the issues if informal conciliation does not resolve the matter.
During training and Sensitization of PAPs to be carried out by the SPMU before compensation and
implementation, PAPs will be informed that their rights to expression of grievances should be exercised
on or before fifteen (15) days of the date of compensation payment. After this date, no other grievance
case(s) shall be admitted. Conversely, cheques issued to PAPs will not be valued until the end of 15 days
from date of receipt of cheque.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
xviii
After due interaction with the PAPs and relevant stakeholders, the following persons were recommended
to constitute the GRC: Community Head (Traditional Ruler) —as Chairman of the Committee, Site
Committee member, PAPs Representative, local government desk officer, local government land officer
and SPMU as members shall be formed to hear complaints and facilitate solutions so as to promote
dispute settlement through mediation to reduce litigation.
Monitoring and Evaluation
In order to successfully complete the resettlement management as per the implementation schedule and
compliance with the policy and entitlement framework, there would be need for monitoring and
evaluation of the RAP implementation. Monitoring and evaluation will be a continuous process and will
include internal and external monitoring. SPMU shall play a key role in reporting the progress of
implementation as well as compliance to the World Bank.
Disclosure
The RAP shall be disclosed in-country to the general public for review and comment before it is
approved by the Bank at designated locations and in World Bank communication info shop.
Conclusion
The proposed project, upon completion, will benefit the community. The potential impacts are limited
and will make the PAPs better than the pre-project stage. Grievances will be minimized, and provision
made to address any in the course of implementing this RAP.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
1
CHAPTER ONE
INTRODUCTION
1.1 Background
Soil Erosion in Nigeria has been a major environmental problem resulting in extensive impacts including
loss of human life and assets (e.g., roads, drainage, housing, farmlands, community assets, silted
waterways, and port). In fact, there is an estimated yield reduction of about 30 to 90 percent and almost
5% loss in GDP. These gullies, along with other forms of land degradation such as sheet erosion, can
undermine the progress made on economic growth and poverty alleviation in the country.
To solve the erosion problem, the Federal Government of Nigeria initiated the Nigeria Erosion and
Watershed Management Project (NEWMAP). The project is supported with financing from the World
Bank, Global Environment Facility, and the Special Climate Change Fund, and the Government of
Nigeria. NEWMAP finances activities implemented by states and the Federal government. The project
currently includes nineteen (19) States namely Anambra, Abia, Cross River, Edo, Enugu, Ebonyi, Imo,
Kogi, Delta, Oyo, Kano, Plateau, Gombe, Sokoto, Nasarawa, Niger, Borno, Katsina and Akwa-Ibom.
The lead agency is the Department of Erosion Control, Flood and Coastal Zone Management of the
Federal Ministry of Environment (FME), State and local governments, multi-sector operation involving
MDAs concerned with water resources management, public works, agriculture, regional and town
planning, earth and natural resources information, and disaster risk management. NEWMAP has four
key components, namely - Erosion and Watershed Management Investments, Erosion and Watershed
Institutions and Information Services, Climate Change Agenda Support and Project Management.
Generally, the project employs a sustainable and holistic approach of combining Engineering Watershed
Management and livelihood support solutions in tackling Erosion issues.
The Project Development Objective (PDO) of NEWMAP is: to rehabilitate degraded lands and reduce
longer-term erosion vulnerability in targeted areas. At State level, NEWMAP activities involve medium-
sized civil works, such as construction of infrastructure and/or stabilization or rehabilitation in and around
the gullies themselves, as well as small works in the small watershed where gullies form and expand.
These works trigger the World Bank’s Safeguard Policies including Environmental Assessment OP 401;
Natural Habitats OP 4.04; Cultural Property Op 11.03; Involuntary Resettlement OP 4.12 Safety of
Dams OP 4.37; Pest Management Safeguard Policy Op 4.09; and Projects on International Waterways
OP 7.50.
1.2 The Need for the Resettlement Action Plan for the Proposed Project
The proposed project triggers World Bank (WB)’s Operation Policy, OP 4.12 on Involuntary
Resettlement in that it requires acquisition of land as well as restrictions of access in areas bordering the
gully edges.
For WB supported projects, any project that causes displacement of any sort must be subjected to the
requirements of its Operational Policy, OP 4.12, on Involuntary Resettlement. It is in pursuant to this that
this RAP was prepared as part of the World Bank’s Environmental and Social Safeguard Policies.
The RAP identified the potential Projects Affected Persons (PAPs), affected / loss assets and engaged
them in participatory discussion regarding the plan in order to adequately compensate them for their
losses
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
2
1.3 The RAP and other Safeguard Instruments
NEWMAP investments include a strategic combination of civil engineering, vegetative land management
and other catchments projection measures, and community-led adaptive livelihood initiatives. The
sustainability of these investments will be reinforced by strengthening institutions and information services
across sectors and states, including support to improve governance, regulatory compliance, environmental
monitoring, impact evaluation, catchments and land use planning, and to strengthen Nigeria’s capacity to
promote and implement climate-resilient, low-carbon development.
The environmental and social safeguards concerns are being addressed through two national instruments
already prepared under the project: An Environmental and Social Management Framework (ESMF) and
a Resettlement Policy Framework (RPF). These framework instruments need to be translated into specific
cost, measurable, and monitor able actions for specific intervention sites through the preparation of site-
specific management and action plans.
ESMF — In general, the ESMF specifies the procedures to be used for preparing, approving and
implementing (a) Environmental and Social Assessments ESAs (b) Environmental and Social
Management Plans (ESMPs. ESMPs are essential elements for Category B projects.
RPF - The RPF applies when land acquisition leads to the temporary or permanent physical displacement
of persons, and/or loss of shelter, and /or loss of livelihoods and/or loss, denial or restriction of access to
economic resources due to project activities. It sets out the resettlement and compensation principles,
organizational arrangements and design, criteria to be applied to meet the needs of project-affected
people (PAP), and specifies the contents of a Resettlement Action Plan (RAP) for each package of
investments. A Resettlement Policy Framework (RPF), which serves as a practical tool during the
programme formulation, design, implementation and monitoring, was prepared for NEWMAP which
serves as a guide for the present terms of reference (See Appendix 3).
The activities of Component 1 will involve civil works in specific intervention sites — that is; construction
of drainage works and/or rehabilitation of gullies. This could result in the acquisition of land or
displacement of families, business or public infrastructure, thus triggering the World Bank OP 4.12 -
Involuntary Resettlement.
Against this background, Kogi State, under the Nigeria Erosion and Watershed Management Project
(KSG-NEWMAP), represented by the State Project Management Unit (SPMU) is preparing a
Resettlement Action Plan (RAP) for the project.
1.4 Aim and Objectives of the RAP
The aim of the RAP is to identify and assess the human impact of the proposed works at the Gully
erosion sites in Agassa community, and to prepare an Action Plan to be implemented in coordination
with the civil works in Line with World Bank safeguards Policy and Nigeria policies and laws. The
specific objectives of the RAP are to:
a. Conduct a census survey of impacted persons and valuation of assets affected;
b. Consult with the affected community and agencies;
c. Ascertain the number of vulnerable persons among PAPs and design livelihood restoration
measures suitable to addressing their economic sustenance; and
d. Describe compensation and other resettlement assistance to be provided to restore livelihood to
pre-displacement level.
1.5 Scope of Services and Task of the RAP
The tasks performed during this RAP preparation include the following:
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
3
1. Describe the project and components for which land acquisition and resettlement are required,
and an explanation of why a Resettlement Plan is required.
2. Legal analysis and framework, reviewing the Nigerian Laws and regulations and the World Bank
Policy requirements and measures proposed to bridge any gaps between them.
3. Conduct a census and declaring a cut-off date.
4. Estimate population displacement and categories of displaced persons to the extent feasible.
5. Determine eligibility criteria and entitlement matrix for defining various categories of displaced
persons and entitlement.
6. Undertake valuation of affected assets, both natural and built assets.
7. Compensate and assist persons based on the overall principle that affected people shall not suffer
net losses as a result of the project.
8. Describe possible mechanisms for transitional costs (such as moving expenses) and for restoring
livelihoods where they are adversely affected.
9. Organize procedures for delivery of entitlements, a description of the implementation process,
linking resettlement planning and implementation to both civil works and livelihood strategies.
10. Describe grievances and redress mechanisms that take into account the need for (a) registration
of grievances; (b) prompt and transparent action on grievances; (c) due process; (d) opportunity
for appeal; and (e) avoidance of legal proceedings to the extent possible.
11. Describe arrangements for funding resettlement activities including the preparation and review of
cost estimates, the flow of funds and the contingency arrangements.
12. Develop an institutional matrix that clearly identifies all the agencies, public or private, that will be
involved in the resettlement project, their respective roles, the budget allocated to each and the
legal arrangements to be made.
13. Describe mechanisms for consultations with, and participation of displaced persons in planning,
implementation and monitoring.
14. Describe the processes of monitoring, verification and evaluation required for effective
implementation of the resettlement process.
1.6 Guiding Principles.
The following principles have guided the resettlement planning process for Agassa gully erosion
site:
a. World Bank Safeguards Policy
b. Nigerian law and international best practices guide.
c. Implement a world-class resettlement process.
d. Process was driven by consultation and participatory planning
e. Compensation with replacement value and restore livelihoods at a minimum
f. Design compensation framework, replacement assets and livelihood restoration to ensure
sustainable benefit
g. Provide modern replacement assets and enable community continuity
1.7 The Methodology of RAP Preparation
The approach adopted for the RAP design was in accordance with the applicable World Bank safeguard
policies, Nigerian guidelines/laws and Terms of Reference (TOR). The methodology essentially entails
literature review including the review of the RPF, ESMF prepared for the NEWMAP. Other steps taken
by the Consultant in the preparation of the RAP are: baseline studies, public consultations, mapping of
the location of the affected assets using the real time differential GPS, census of PAPs, valuation of
affected assets and determination of the entitlement and eligibility matrixes. Detailed explanation of the
methodology employed in this RAP is provided in appendix 4.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
4
1.8 Structure of the RAP Report
The RAP is presented in ten chapters as indicated below:
Chapter One: General Background
Chapter Two: NEWMAP Project Components and Description of
Intervention Site
Chapter Three: Census and Socio-Economic Survey
Chapter Four: Impact of the Project
Chapter Five: Existing Legal Framework
Chapter Six: Valuation and Compensation and other Resettlement
Assistance
Chapter Seven: Public Participation and Consultations
Chapter Eight: RAP Implementation and Consultations
Chapter Nine: Grievance Redress Mechanism
Chapter Ten Monitoring and Evaluation
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
5
CHAPTER TWO
DESCRIPTION OF THE PROPOSED PROJECT AND SOCIO-
ECONOMIC BASELINE CONDITIONS
2.0 Introduction
This chapter contains the overall components of NEWMAP and a brief description of the proposed
intervention site. The Corridor Map of the Site (Map 2.7) and other related maps were also presented.
2.1 Description of NEWMAP Components
NEWMAP has four components as outlined in Table 2.1 and described below.
Table 2.1: Main NEWMAP elements, activities and outcomes
Component I Component 2 Component 3 Component 4
Title Watershed and
Catchment
Management
Investments
Watershed and
Catchment
Management
Institutions and
Information
Services
Climate Change
Agenda Support
Project
Management.
Sub- components 1A Flood Water
Containment
and Sub-
Watershed
Rehabilitation.
1B Integrated
Catchment
Management
1C Adaptive
Livelihoods
2A Federal
MDA
Effectiveness
and Services.
2B State MDA
Effectiveness and
Services.
2C Local
Government
Capacity.
2D Private Sector
Capacity.
3A Policy and
Institutional
Framework.
3B Low Carbon
Development.
Main activities Control Agassa
gully erosion sites
and conduct
Community-
based
catchment
interventions,
Strengthen the
Enabling
environment for
effective erosion
and catchment
management.
Strengthen
government
capacity to
promote low
carbon, climate
resilient
development.
Procure goods
and specialist
services to support
project
management,
safeguards,
M&E and
oversight.
Main outcome Erosion
controlled through
Engineering works
and priority sub-
watershed
rehabilitation and
more secure
livelihoods and
catchment
services
established.
More capable,
modernized and
coordinated
Federal, State and
Local institutions.
Government to
be better
equipped to
respond to climate
change,
and low-carbon
development
options
demonstrated.
Establish
systems for project
management,
M&E and best
practices for
future replication.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
6
2.2 Kogi State and Description of Proposed Intervention Site
The state was created on 27th
August 1991, with its administrative headquarters in Lokoja. It is structured
into 21 LGAs. The main indigenous ethnic groups that make up the state include, Igala, Ebira, Okun,
BassaKomo, BassaNge, Kakanda, Kupa, Ogori, Nupe, Oworo etc., while other groups from other parts
of Nigeria such as the Igbo, Hausa, Edo etc, are also domiciled in the state. The four major languages
spoken as first language in Kogi State include lgala, Ebira, Yoruba and Nupe. The official language among
the many ethnic groups remains English.
Kogi state lies within latitude 7.49°N and longitude 6.45°E and is one of the states in the middle belt
identified geopolitically as the north central zone. It has a total land area of 28,313.53 square kilometres.
It shares common boundaries with ten (10) states and the Federal Capital Territory (FCT). To the North,
it shares boundaries with Niger, FCT, and Nassarawa; to the West, by Kwara, Ekiti, Ondo, Edo, and
Delta; while to the East, by Benue, Anambra and Enugu.
Kogi State has a geological feature depicting young sedimentary rocks and alluvium along river beds,
which promotes agricultural activities. The state features ferrasols soil type and famous hills like Ososo
hills, which spread from Edo State to the western part of Kogi State, and Aporo hill on the eastern part.
Another famous hill is Mount Patti, which lies in Lokoja and stands at about 750 metres above sea level.
Kogi state has an average maximum temperature of 260
C and an average minimum [temperature of 22OC,
while the annual rainfall ranges from 1016 mm to 1524 mm. The State has two distinct weather, the dry
season which last from November to February, and rainy season, which last from March to October. The
vegetation of the state consists of mixed leguminous (guinea) woodland to forest savannah, and has a wide
expanse of Fadama in the river basin and long stretches of tropical forest in the western and southern belt
of the state.
2.3 Site Description
Agassa is situated within Latitude 07o
32’33”and Longitude 06o
13’25” UTM (WGS84) 193514.920ME &
834753.666MN. Agassa gully erosion site is a set of gullies located in about four (4) gully fingers around
Agassa community in Okene LGA of Kogi State, stretching from the Ahache area and extending to the
central burial ground area and beyond. The area is typically sandwiched between hills with steep slope.
The gullies put together are about 3.5km with width varying from 2m to 5m and depth of 1m to 6m. The
gullies have existed in the community for about 20years and it is caused by uncontrolled development,
unchecked water falls from the surrounding hills resulting to poor drainage control. The erosion is
therefore a result of human and natural causes namely unplanned settlement, nature of soil, slope and
lack of institutional intervention. Many residential buildings are likely to be destroyed and many are under
serious threat of collapse. The access roads in the community are exposed to destruction and the gully
has developed fingers. Urgent action is required at the site to salvage the environment, protect and
preserve lives and properties.
The affected site enjoys ample annual rainfall, which ranges from 1000mm to 1300mm per annum. The
vegetation is mostly Guinea Savannah. The geology of the area is basement complex comprising of
granite, gneiss and biotite. Most of the inhabitants of the area are generally Ebiras with few populations of
non-indigenes. Majority of the people are farmers, weavers and traders, and the crops grown are mainly
yam, cassava, maize and beniseed.
The community is headed by a traditional ruler with the title of Onoba of Agassa with a strong attachment
to his subjects and well loved by his people. There exists a popular masquerade festival called
EKUECHI, which is well celebrated around November of every year. There are also Eche–Ane (festival
of female), EcheAhana (day singing festival) and Okehi festival.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
7
Map 2.1: Map of the World Map 2.2: Map of Africa
Map 2.3: Map of Nigeria Showing Kogi State Map 2.4: Map of Okene Local Government
Map 2.5: Map of Kogi State Showing Okene Local Government Area
st Kogi State
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
8
Map 2.6: Current NEWMAP States
Map 2.7: Corridor Mapping of Agassa Gully Erosion Site at Okene, Kogi State (See Full Size in
Appendix 7)
AB
IA
EDO ENUGU
OYO
KOGI
SOKOTO
KANO
PLATEAU
GOMBE
DELTA
AN
AM
BR
A
EBO
NY
I
IMO
CR
OSS
RIV
ER
CURRENT NEWMAP STATES ABIA
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
9
2.4 Geology, Relief and Drainage of Targeted Site
Geology: Kogi State has two main rock types, namely, basement complex rocks of the Precambrian age in
the western half of the state and extending slightly eastwards beyond lower Niger valley and the older
sedimentary rocks in the eastern half. The geology of the area is mostly sedimentary terrain comprising of
clay, fine grains and sand stones. The various sedimentary rock groups extend along the banks of Rivers
Niger and Benue and south-eastwards through Enugu and Anambra States to join the Udi Plateau.
Relief and Drainage: The land rises from about 300 meters along the Niger Benue confluence, to the
heights of between 300 and 600 meters above sea level in the uplands Agbaja Plateau, which ranges from -
335 to 366 meters above sea level, and the much higher Okoro-Agbo hills at Ogidi in ljumu LGA are
some of the predominant landforms of the State. The State is drained by the Niger and Benue Rivers and
their tributaries.
The confluence of the Niger and Benue Rivers which could be viewed from the top of Mount Patti is
located within the State. The Benue River is navigable as far as Garua in the rainy season floods, but up to
Makurdi in Benue State in the dry season (Iloeje, 1979).
The Maboro (Anambra) is the biggest River in Igala land. Maboro, Okura, Ubele and Ofu Rivers run off
the Dekina, Ankpa, Otukpo watershed. Osomera falls at Kilometre 4 on Okene - Ajaokuta Road, Ofejiji
falls in Okura-Olafia and Egeneja warm spring in Bassa Local Government Area are other drainage
features (Benue State, 1985).
The bigger rivers have wide flood plains such as the portion of the lower Niger in Kogi State, which is
more than 1,600 meters wide at Lokoja, while the small streams have narrow valleys. The general rain is
undulating and characterized by high hills, Jos plateau and numerous inselbergs and elongated ridges.
Climate: The State has an annual rainfall of between 1,100mm and 1,300mm. The rainy season lasts
from April to October, and the dry season which lasts from November to March is very dusty and cold as
a result of the north-easterly winds, which heralds the harmattan.
Soils: The flood plains of the Niger and Benue River valleys in Kogi State have the hydromorphic soils
which contain a mixture of coarse alluvial and colluvial deposits (Areola, 1985). The alluvial soils along
the valleys of the rivers are sandy, while the adjoining laterite soil is deeply weathered and grey or reddish
in colour, sticky and permeable.
Vegetation: The vegetation is mostly of Guinea Savannah. The rain forest belt (selva type) covers Dekina,
Ofu, Ankpa, Olamaboro, ldah and Bassa Local Government Areas with rich deciduous and occasional
stunted trees including palms, iroko, mahogany, akee apple and other towering trees. Other LGAs are in
the guinea savannah or parkland savannah belt with tall grasses and some trees.
These are green in the rainy season with fresh leaves and tall grasses, but the land is open during the dry
season, showing charred trees and the remains of burnt grasses. The trees which are in clusters are up to
six meters tall, interspersed with grasses which grow up to about three meters.
These trees include locust bean, Shea butter, oil bean and the isoberlinia. The different types of
vegetations are, however, not in their natural luxuriant state owing to the careless human use of the forest
and the resultant derived deciduous and savannah vegetation.
Ecological Problems: The ecological problems in the state are not necessarily peculiar to it. Some of these
include leaching, erosion and general impoverishment of the soil. These problems are compounded by
the annual bush burning of the savannah that further exposes the top soil to more erosion. Floods pose a
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
10
problem on the flood plains during the rainy season, while aridity is a problem to several areas at short
distances from the rivers during the dry season. Much damage is done to land and property as a result of
these phenomena
Education: Kogi State is home to the Federal University Lokoja, Kogi State University, Anyigba, Federal
Polytechnic, ldah, Kogi State Polytechnic, Lokoja, Federal College of Education, Okene, College of
Education, Ankpa, College of Agriculture, Kabba, Kogi State College of Education, Technical (Kabba),
and Salem University. Others are college of Nursing and Midwifery in Obangede, School of Health
Technology in ldah and ECWA School of Nursing in Egbe.
Demographics: The result of the 2006 Census shows that there are a total of 3,314,043 persons in Kogi
State among whom 1,672,903 are males while 1641,140 are females. Annual population growth rate in
Kogi State is 3.2% (NPC, 2007).
Table 2.2: The population of Kogi State by Local Government Areas
Name Status Population
Census
1991-11-26
Population
Census
2006-03-21
Population
Projection
2016-03-21
Kogi State 2,147,756 3,314,043 4,473,500
Adavi Local Government Area 157,092 217,219 293,200
Ajaokuta Local Government Area 97,904 122,432 165,300
Ankpa Local Government Area - 266,176 359,300
Bassa Local Government Area 88,496 139,687 188,600
Dekina Local Government Area 177,513 260,968 352,300
Ibaji Local Government Area - 127,572 172,200
Idah Local Government Area - 79,755 107,700
Igalamela-Odolu Local Government Area - 147,048 198,500
Ijumu Local Government Area 66,603 118,593 160,l00
Kabba/Bunu Local Government Area - 144,579 195,200
Kogi Local Government Area 82,483 115,100 155,400
Lokoja Local Government Area - 196,643 265,400
Mopa-Muro Local Government Area - 43,760 59,100
Ofu Local Government Area 108,095 191 ,480 258,500
Ogori/Magongo Local Government Area - 39,807 53,700
Okehi* Local Government Area 146,264 223,574 301,800
Okene Local Government Area - 325,623 439,500
Olamaboro Local Government Area 104,705 158,490 213,900
Omala Local Government Area - 107,968 145,700
Yagba East Local Government Area 88,780 147,641 199,300
Yagba West Local Government Area 76,936 139,928 188,900
Nigeria Federal Republic 88,992,220 140,43179011 193,392,500
Source: National Population Commission of Nigeria (web), National Bureau of Statistics (web).
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
11
CHAPTER THREE
CENSUS AND SOCIO-ECONOMIC SURVEY
3.1 Introduction
The socio-economic conditions of the PAPs in Agassa gully project activities are summarized in this
Chapter. Socio-economic survey was premised on the PAPs along the corridor of the Agassa gully erosion
site with a view to determining their socio-economic conditions, and how the project stands to impact
them.
The survey, had several primary objectives which include:
• To inform the affected population about the proposed intervention work;
• To announce the kick-off and cut off-date for capturing those affected by the proposed project who
are along the zone of impact;
• To obtain feedback from the affected population about the intervention work;
• To establish the social profile of the affected population along the corridor;
• To record/update the base line situation of all affected people;
• To identify the affected households, individuals and assets;
• To identify vulnerable individuals or groups;
• To record all assets and impacts within the ROW (setback from edge of gully).
3.2 Census Cut-Off Date
The Census Cut-Off Date refers to the date after which PAPs will NOT be considered eligible for
compensation, i.e. they are not included in the list of PAPs as defined before the end of socio-economic
survey of the PAPs.
The census commenced with the announcement of the kick-off date on November 27, 2017. Following
the conclusion of the census on December 10th
, 2017, the cut-off date was declared to be December 10,
2017, after which no newly arrived persons or families will be eligible for resettlement benefits. In
addition, improvements to housing etc. made after the date will not be eligible for compensation (repairs,
such as fixing a leaky roof, are permissible). The cut-off date was announced and made known through
appropriate traditional means of reaching-out during the community awareness campaigns at site level and
through the local government.
The cut-off date was intended to prevent speculation and rent-seeking in order to become eligible for
additional resettlement benefits. This is bearing in mind the period between the cut-off date and the time
actual productive investments would start, and that only after PAPs have been compensated according to
the requirements of this RAP. Nevertheless, if works are not initiated two years or more elapsed after
declaration of a cut-off date, an updated census and evaluation of properties/assets must be carried out.
3.3 Data Analyses and Interpretation
Specifically, the following thematic socio-economic indicators were included in the survey: gender, age
distribution; marital status; nature of trade/occupation of vendor/PAPS; income category, etc. The data
analyses and interpretation focus on the socio-demographic background information of respondents,
identified Project Affected Persons (PAPs) and affected assets.
3.3.1 Analyses of Persons (Respondents) Interviewed
A total of 200 questionnaires were administered to community members including identified Project
Affected Persons across the length of the gully corridor. The respondents refer to any person considered
to live or do businesses in the communities in the gully site areas who may not necessary be affected.
Project affected persons are those actually affected by the project. It is important to note that the impact
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
12
of project activities on the sources of livelihood of PAPs along the gully corridor vary among them. While
some are directly affected (those within 5m from the edge of the gully), others are not, (such as those
within general watershed area).
The response of those met or to whom questionnaires were administered provided an average idea of the
prevailing situation in the proposed project area. Therefore, it is believed that the information provided
by these categories of people are accurate about the businesses they represent/operate or property/asset
they own or represent.
3.4 Socio-Economic Data Results and Discussions
A number of field studies were carried out to gather additional information on the baseline social
conditions that may potentially be affected during project implementation and operation. This involves
inventory of project affected persons, especially the individuals/communities/vulnerable groups, physical
based assets, including administration of questionnaire and oral interviews to gather other relevant social
data.
A social/economic survey was carried out to obtain relevant baseline social and economic data to
complement information earlier obtained from consultations. This essentially involved structured
public/community consultations (Nos. 5) and focal group discussions (FGDs) to reveal other underlying
social issues that may affect and or assist in the implementation.
Some of the topics included are:
a. Demographic structure of the community;
b. Leadership patterns and political process;
c. Family structure;
d. Services available in or near the community: schools, health facilities, credit facilities, religious
organizations, government agencies;
e. Debit/credit relationships;
f. Existing organizations (e.g. age grades, religious groups) and capacity for community actions;
g. Conflicts and divisions (ethnic, religious. etc.) within the community or between communities;
h. Important local customs and festivals;
i. Educational levels;
j. Permanence of the community;
k. Primary forms of livelihood;
l. Community attitudes towards erosion and drainage;
m. Relevant aspects of gender relations; women’s vs. men’s roles.
3.4.1 Agassa Household Demographics
The demographics of the households living in Agassa include the gender distribution of the households,
their marital status, and level of education attained, literacy status, household size, and gender distribution
of household members. The results obtained are presented in relevant charts and tables below (Please see
Appendix 4.1).
3.4.2 Gender Distribution and Marital Status
The gender distribution of the household heads in Agassa watershed showed that 69 percent were males
and 31 percent were females. The analysis of the marital status of the household heads showed that 94.9
percent were married, while 0.5 percent were singles. Also, 1 percent is divorced, while 3 percent are
separated. Others (no response) are 0.6 percent. See Figures 3.1 and 3.2 respectively for more details.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
13
Figure 3.1: Gender distribution of household heads in Agassa Figure 3.2: Marital Distribution of Household heads in
Agassa
3.4.3 Family Size and Average Age of Household Members
The average age of household heads in Agassa was about 54 years (Figure 3.3). The minimum was 22
years, while the maximum was 100 years. The implication of the above are in two folds: (1) there is no
child headed household heads in the community, (2) elderly persons (above 65 years old) represent about
70 percent of the household heads in the community. This age grade constitutes the vulnerable group
which Kogi NEWMAP may need to pay more attention to (where need be) during the implementation of
RAP. Furthermore, the age of dependants in households is captured in Figure 3.4 below.
Figure 3.3: Average Age of Household Heads in Agassa Figure3.4: Average Age of Dependent Household Members
in Agassa
69%
31%
GENDER
MALE FEMALE
0
5
10
15
20
25
30
35
40
20 -35
36 -50
51 -65
66 -80
81 -95
96 -110
AGE OF HOUSEHOLD HEADS
0.5
94.9
1 3 0.60
20
40
60
80
100
MARITAL STATUS
MARITALSTATUS
0
5
10
15
20
25
30
35
40
45
0 - 9 10 - 19 20 - 29 30 - 39
Pe
rce
nta
ge A
ge
AGE OF DEPENDENT HOUSEHOLD MEMBERS
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
14
Figure 3.5: Percentage Distribution of Family Size
3.4.4 Educational Level and Literacy Status
The analysis of the educational level of the household heads and their literacy status is presented in Table
4.6 and Figure 4.1 respectively. The result obtained showed that only about 33 percent of the household
heads in the project area had completed secondary school education, and about 17 percent completed
primary education. There were also about 20 percent who had completed tertiary education, while about
26 percent had no formal education. Less than 5 percent of the household heads in the area on the
average or about 21 percent in Agassa had undergone vocational training. The literacy status of the family
heads on the other hand showed that about 87 percent are literate, while only about 13 percent or
approximately 1 in 10 are illiterates or cannot read nor write.
Figure 3.6: Highest Educational Level of Figure 3.7: Highest Educational Level of
Household Members in Agassa Household Heads in Agassa
3.5 Agassa Socio-economic Characteristics
The socio-economic characteristics of the households in Agassa analysed in this section include the major
occupation of the household heads, family income from both the heads and contribution from other
family members including transfer payments from relations, and average household expenditures on
major items on per capita basis.
20%
50%
25%
5%
FAMILY SIZE
0 - 4 5 - 9 10 - 14 15 & Above
0
20
40
Educational Level
EducationalLevel
Literacy Status
Literate
Illiterate
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
15
3.5.1 Major Occupation of Household Heads
The analysis of the distribution of household heads by occupations types in Agassa area showed that
about 36 percent are engaged in trading or business, 25 percent are civil servants, about 16 percent are
farmers, while about 14 percent are artisans. See Table 4.7 for more details on the occupation types in
the catchment area.
Figure 3.8: Distribution of household heads by Occupation Type in Agassa
3.5.2 Household Income and Expenditure
The unadjusted average per capita monthly income of households in Agassa is about N8,925, while the
range is about N94,231, which is indicative of a high disparity in income levels among households living
in the catchment area. Furthermore, the median per capita income in the area is about N7,075, which
implies that about 50 percent of the households earn this amount or below, while another 50 percent earn
incomes above this level monthly per head (see Table 3.8).
The household income and expenditure summaries in Table 4.9 below shows that the monthly per capita
total expenditure in Agassa is about N6,444, while the median expenditure for the households within the
catchment is about N6000. In the same vein, the monthly per capita food expenditure in the area is
N2,693, while the median is N2000 monthly per head. See Table 3.9 below for more details on the
monthly income and expenditure of households in Agassa catchments area.
3.5.3 Land and Other Resources: Ownership and Use
The land and other resources ownership and uses cover the following analysis: the reasons why
households chose to live in the catchment, the housing types and materials used in housing construction
as a measure of the quality of housing, methods of farmland acquisition, types of crops grown, problems
faced and land use intensity measured by the frequency of land use and visits. Other analyses include
household farming experience, major uses of non-agricultural land, major water sources, rain harvesting
method adopted by households that depend on this source and their satisfaction with water obtained from
their main sources. The detailed analysis is presented in relevant tables and subsections below.
3.5.4 Household Residency and Housing Quality
The analysis of the reasons for households residency in Agassa showed that about 90 percent of the
households chose to live in that catchment because it is their ancestral home. Less than 10 percent are in
the watershed for business reasons, while about 2 percent hold some form of employment in the
catchment. See Figure 3.10 below for more details.
020406080
100
Distribution by Occupation Type in Agassa
Distribution by Occupation Typein Agassa
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
16
Figure 3.9: Households’ reasons for residing in Agassa catchments
HOUSING: Majority of the houses in the community are bungalows - predominantly old structures - with
little or no modern facilities. Some of the buildings in the area are made up of mud and corrugated
roofing sheets. The buildings are of single room type as shown in table 3.10 below.
Figure 3.10: Types of Houses Occupied by Households in Agassa
3.5.5 Awareness of Proposed Project
Many (87.5%) of the respondents are aware that work is about to start on the gully corridor and see it as a
welcome development while 5% are not aware and 7.5% are not sure.
Figure3.11: Awareness of Proposed Project
0
50
100
AncestraHome
BusinessLocation Place of
EmploymentOthers
Total
0
50
100
YesNo
Not Sure
.
020406080
100
Types of Houses Occupied
Types of Houses Occupied
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
17
3.5.6 Response on Desirability of Proposed Project
Majority (90%) desire the proposed project. Ten percent (10%) of them are not sure whether they desire
the proposed project. No respondent answered emphatically ‘no’.
Figure 3.12: Desirability of Proposed Project
0
20
40
60
80
100
Yes No Not Sure
-
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
18
CHAPTER FOUR
IMPACT OF THE PROJECT
4.1 Introduction
The inventory of assets and analysis carried out in the course of preparing this RAP identified project
impacts hereby classified into positive and negative impacts..
4.2 Positive Impacts of the Project
The major benefits will occur in the form of improved erosion management and gully rehabilitation
which will provide for:
• Reduced loss of infrastructure including roads, houses, etc.
• Reduced loss of agricultural land and productivity from soil loss caused by surface erosion.
• Reduced siltation in rivers leading to less flooding and the preservation of the water systems for
improved access to domestic water supply.
• Reduced risks of floods (due to reduced siltation)
• Progressively restored vegetative cover, improved environmental conditions and more humid
local microclimates. This results in increased vegetation cover for wildlife and carbon
sequestration.
• Environmental improvements due to land stabilization measures which preserve the landscape
and biodiversity.
4.3 Negative Impacts of the Project
Although the Project is expected to have a lot of positive impacts as presented above in section 4.4, it is
however not without some attendant negative impacts. Based on the inventory carried out, land
acquisition, will be very minimal and shall be restricted to the 5m setback along the gully corridor.
Notwithstanding, the intervention will lead to the following adverse impacts:
- Loss of economic trees and agricultural crops;
- Loss of structures;
- Loss of public utilities;
- Loss of businesses and,
- Loss of accommodation.
The account of the quantity and specification of the affected items is presented in the section under
analysis of inventory of affected assets.
4.4 Analysis of the Inventory of Affected Assets
An inventory of Assets to be displaced along the gully corridor is categorized into economic trees, affected
businesses, structures, residential accommodation and utilities as shown below.
1. Economic Trees affected in Agassa
Economic Trees Number
Banana/Plantain 11
Coconut 07
Orange 03
Pawpaw 03
Umbrella fruits 01
Bamboo 03
Palm tree 50
Guava 01
MoringaOlifera 04
Pineapple 01
Castor 01
Garden Egg 01
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
19
2. Affected Businesses
Business Number
Poultry 01
Shop/kiosk 02
3. Structures affected in Agassa
Structure Number
Well 03
Fence 12
Buildings 20
Uncompleted buildings 02
Bathrooms/Toilets 04
Pavements 02
4. Affected residential accommodations =31
5. Electric poles to be relocated = 2
4.5 Avoidance/Minimization of Resettlement
To avoid negative impacts, or minimize as much as possible, the following measures were taken:
• A full opportunity for involvement of all stakeholders, especially the direct stakeholders (project
affected persons) provided through public participation and engagement of the stakeholder
communities. This afforded the concerned stakeholders the opportunity to contribute to both the
design and implementation of the project activities thereby reducing the likelihood of occurrence
of some of the impacts.
• Kogi State NEWMAP/Contractor will adhere to the 5 meter setback required for construction as
stipulated in the Engineering Design.
• The setback on the corridor was made known to the stakeholders (5m) and that in the event of
work in such locations all affected properties are to be removed by their owners to give the
required right of way for the work.
4.6 Mitigation Measures
The main objective of the RAP is to develop programmes that can improve the livelihoods of PAP’s or
restore them to the pre-displacement levels. To provide a safety net for all the PAPs and improve their
livelihood until they become self-sufficient and resilient to economic stresses as they were before the
project came or even better, appropriate mitigation measures and preparations of the entire resettlement
process have been developed and shall be ensured. Specifically, the following mitigation measures shall
be implemented:
- PAPs shall be consulted before and during the implementation of this RAP to ensure their full
participation in the RAP process.
- PAPs shall be compensated in line with this RAP before actual project implementation. This
implies that construction activities (displacement and demolition) will not take place until PAPs
have been full compensated.
- Assistance to PAPs / vulnerable persons shall be adhered to in line with the recommendations in
this RAP.
- RAP implementation including livelihood restoration measures shall be monitored by the SPMU
to ensure that PAPs and the vulnerable are restored to the pre-project social conditions.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
20
- Grievance redress shall be given high priority in this project. For the vulnerable, priority shall be
given in all mitigation measures relating to them. Stress to this group shall be avoided. Where
mitigation measures include physical preparation of site as appropriate assistance support and
protection shall be provided to help them overcome difficulties in the process.
4.7 Number and Types of Affected Persons
A total of 76 PAPs will be affected by the project. This includes 40 asset owners and 36 tenants. Similarly,
the PAPs are made up of 51 males and 25 females. In terms of number of family members of PAPs, the
project recorded a total number of 241 persons from the 76 PAPs.
The list of Affected Persons and compensation entitlements is shown in Appendix 5. Assets types is
provided in
Appendix 4.1
4.8 Inventory of Impacted Assets
The affected assets include structures and farmlands essentially. These have been identified and are as
shown in this subsection.
4.8.1 Impact on Land and Structures
The structures that could be affected in the course of work or that could constitute hindrance to work
have been identified as depicted in Map 2.5. In Appendix the PAPs who own these structures are
identified in relation to the numbered structures.
4.8.2 Impact on Agricultural Resources (Crops)
Impacted agricultural resources include Mango trees, Coconut trees, Plantain trees, Castor stems,
Plantain, Banana trees, Bamboo, Orange trees, Pawpaw, Guava and Cashew
trees as outlined in Table 4.1.
4.8.3 Impact on Utilities
Two electric wooden poles were identified which shall cause hindrance in the course of work.
4.8.4 Impact on Social Networks
The physical displacement of PAPs will result in the disruption of some social networks, in terms of
nearness to each other. However, the nature of the mitigation/compensation shall largely ensure that
those affected will still be in close contact with each other, for sustainable use of the affected area and in
line with the principles of the NEWMAP. Consultations and interactions initiated during the preparation
of this RAP shall be sustained on the need to give way for the reclamation of the devastated areas once
compensated.
4.8.5 Impact on Vulnerable Group
Thirty six (36) vulnerable PAPs were identified as tenants in the affected properties. By this position, they
would be homeless when the buildings are eventually brought down for civil work in the course of the
intervention work. Thus, they will need assistance to help them overcome difficulties in the process. They
cannot successfully relocate without adequate support and assistance.
In addition to other mitigation measures, a relocation assistance of twelve thousand (N12, 000.00) Naira
only has been computed for each tenant as an appendage to the owners of the properties in appendix 6B.
The assistance sum was arrived at following consultation with the affected tenants. It was informed that
the tenants are on monthly rent of one thousand naira (N1,000) only. To assist them from the shock of
the project, it was agreed that Kogi State NEWMAP will pay for three (3) months’ rent for each of them.
Furthermore, the sum of nine thousand naira (N9,000) only is to take care of haulage (transport).
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
21
To provide a safety net until they become self-sufficient and resilient to economic stress as they were pre-
project or even better, appropriate preparedness of the entire resettlement process has been ensured.
Also, priority shall be given to this group in all mitigation measures related to them. Furthermore, stress
to this group shall be avoided where mitigation measures include physical preparation of sites (Kindly see
subsection 5.3 for mitigation measures).
4.8.6 Potential Relocation Areas
Generally, relocation within the vicinity of the PAPs’ current residences is feasible. Such relocation sites
shall be worked out between the community leaders i.e., ward head and landlords, and to be supervised
by the Chairman, Agassa Community Association, as well as the livelihood unit of the SPMU.
Notably to mention in this RAP is that there is no permanent displacement.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
22
CHAPTER FIVE
RELEVANT LOCAL AND FEDERAL POLICY,
LEGAL AND REGULATORY FRAMEWORKS
5.0 Introduction
The comprehensive review of the following policy and regulatory frameworks guided the preparation of
this RAP.
5.1 The Resettlement Policy Framework (RPF) of the NEWMAP
The Resettlement Policy Framework (RPF) was prepared as a guide to set out the general terms under
which land acquisition/encroachment, and/or any form of involuntary displacement of persons from the
land or right of way of the project can take place, to comply with the World Bank Operational Policy (OP
4.12 - Involuntary Resettlement).
The Resettlement Policy Framework (RPF) specified that during implementation stage and following the
identification of sub-projects and sites for the developments, individual resettlement action plans should
be prepared that must be consistent with the provisions of the RPF. It also provided a generic process for
the preparation of resettlement plan.
The RPF specified that in addressing impacts, resettlement plan must include measures to ensure that the
displaced persons are:
a. Informed about their options and rights pertaining to resettlement;
b. Consulted on, offered choices among, and provided with technically and economically feasible
resettlement alternatives;
c. Provide prompt and effective compensation at full replacement cost for losses of assets
attributable to the project; and
d. Enabled to restore and preferably improve their living standards compared to the pre-project
condition
Overall, the objective of the RPF is to ensure that PAPs are meaningfully consulted, are involved in the
planning process, and are adequately compensated to the extent that at least their pre-displacement
incomes have been restored and in a fair and transparent process.
The RPF specifies that occupants who must be displaced will be relocated at a minimum cost and to a
nearby location. It also states that occupants who must be relocated will be assisted physically by inclusion
of preparatory site work in the works programme of the contractor and/or by payments to relocate shops
and items of livelihoods to alternative locations. It also recommends the setting up of a dispute resolution
mechanism that will address complaints and grievances that may emanate from the resettlement or
compensation process.
The preparation of this RAP is consistent with the guidelines and recommendations of the RPF of
NEWMAP which is also found to be in agreement with the guidelines of the World Bank Involuntary
Resettlement 0P4.12 and Cultural Property OP 11.03.
5.2 Interim Guidelines for Addressing Legacy Issues in World Bank Projects
The interim guideline aims to provide Bank project teams and Management with guidance on how to
address legacy issues related to Safeguards documents when:
a) The Bank restarts engagement in a project after a significant passage of time, or
b) The Bank becomes engaged significantly late in a project or in a component of a project that is
already well underway.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
23
Legacy issues in the context of social impacts are also commonly understood as impacts that remain after
a development project, factory, business, similar project enterprise, or mine has ceased operations.
The ESMF specifies that the interim guidance note of the World Bank may not sufficiently cover such
legacy issues because those types of legacy issues may require situation-specific approaches or other
approaches not well addressed through the use of the Bank’s Safeguards work. In order words, there is
need to complement the interim guideline with local legacy procedures.
5.3 Policy on Disclosure and Access to Information (DAI)
The objective of the Policy on Disclosure and Access to Information (DAI) is to provide a clear
framework for ensuring greater awareness and understanding of the Bank’s development function and
mission through public outreach, and providing better access to information, particularly on the Bank’s
operations.
5.4 Nigeria Regulatory Framework
With regards to management of the bio-physical environment throughout Nigeria, the overall
responsibility was held by the now defunct Federal Environmental Protection Agency (FEPA), which was
absorbed into the Federal Ministry of Environment (FME) in 1999. The State Environmental Protection
Agencies or, as the case maybe, State Ministries of Environment performs this function at state and local
levels.
5.4.1 The Federal Ministry of Environment (FME)
The Federal Ministry of Environment’s mandate includes the establishment of federal water quality
standards and effluent limitations, protection of air and atmospheric quality; protection of the ozone layer;
control the discharge of hazardous substances; inter alia, and ensures that all major development projects
in Nigeria are subject to mandatory Environmental Impact Assessment (EIA) pursuant to EIA Act. No.
86 (Decree No. 86) of 1992
As contained in FEPA Acts 58 of 1988 and 59 of 1992, all lands in Nigeria belong to the Federal
Government and are entrusted to the State Governors of the respective states to hold in trust for the
public and for public interest. In the event of use of land for public interest, the Act specifies as follows:
a. That the government should resettle and/or compensate occupants of land with Certificate of
Occupancy (C of O); or
b. Issue notice to occupiers of land prior to displacement of land for public project.
In practice, governments do not compensate known rightful owners of land/asset when the affected
land/assets are located within the right of way of utilities. Rather, the government enforces involuntary
displacement by demolition the structures and assets that are located within the land mapped for project.
5.4.2 Nigeria Law/Land Use Act of 1978 and Resettlement Procedures
The Land Use Act, Cap 202, 1990 Laws of the Federation of Nigeria is the applicable law regarding
ownership, transfer, acquisition and all such dealings on Land. The provisions of the Act vest every Parcel
of Land in every State of the Federation in the Executive Governor of the State. The Governor holds
such parcel of land in trust for the people and government of the State. The Act categorized the land in a
state to urban and non-urban or local areas. The administration of the urban land is vested in the
Governor, while the latter is vested in the Local Government Councils. At any rate, all lands irrespective
of the category belong to the State while individuals only enjoy a right of occupancy as contained in the
certificate of occupancy, or where the grants are deemed.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
24
Thus, the Land Use Act is the key legislation that has direct relevance to resettlement and compensation
in Nigeria. Relevant Sections of these laws with respect to land ownership and property rights,
resettlement and compensation are summarized in this section.
The concept of ownership of land as known in the western context is varied by the Act. The Governor
administers the land for the overriding common good and benefits of the citizens of the State. The law
makes it lawful for the Governor to grant statutory right of occupancy for all purposes; the agricultural
(including grazing and ancillary activities), residential and other purposes, grant easements appurtenant to
statutory rights of occupancy and to demand rent. But the limit of such grant is 500 hectares for
agricultural purpose and 5,000 for grazing except with the consent of the Governor.
The statutory Rights of Occupancy are for a definite time (the limit is 99 years) and may be granted
subject to the terms of any contract made between the state governor and the holder.
The Local Government Authority, under the Act, is allowed to enter, use and occupy for public purpose
any land within its jurisdiction that does not fall within an area compulsorily acquired by the Government
of the Federation or of relevant State; or subject to any laws relating to minerals or mineral oils.
5.4.3 Requirements of the Land Use Act
The state is required to establish an administrative system for the revocation of the rights of occupancy,
and payment of compensation for the affected parties. So, the Land Use Act provides for the
establishment of a Land Use and Allocation Committee in each State that determines disputes as to
compensation payable for improvements on the land. (Section 2 (2) (c).
In addition, each State is required to set up a Land Allocation Advisory Committee, to advise the Local
Government on matters related to the management of land. The holder of occupancy of such revoked
land is to be entitled to the value of the unexhausted development as at the date of revocation (Section
6)(5). Where land subject to customary right of Occupancy and used for agricultural purposes is revoked
under the land Use Act, the local government can allocate alternative land for the same purpose (Section
6(6).
In the event that the Local Government refuses or neglects to pay compensation to a holder occupier,
within a reasonable time, the Governor may proceed to effect assessment under section 29 and direct the
Local Government to pay the amount of such compensation to the holder or occupier. Section 6) (7).
Where a right of occupancy is revoked on the ground either that the land is required by the Local, State
or Federal Government for public purpose or for the extraction of building materials, the holder and the
occupier shall be entitled to compensation for the value at the date of revocation of their unexhausted
improvements. Unexhausted improvement has been defined by the Act as:
anything of any quality permanently attached to the land directly resulting from the expenditure
of capital or labour by any occupier or any person acting on his behalf; and increasing the
productive capacity the utility or the amenity thereof and includes buildings, plantations of long-
lived crops or trees, fencing walls, roads and irrigation or reclamation works, but does not include
the result of ordinary cultivation other than growing produce.
Developed Land is also defined in the generous manner under Section 50(1) a follows: land where there
exists any physical improvement in the nature of road development services, water, electricity, drainage,
building, structure or such improvements that may enhance the value of the land for industrial,
agricultural or residential purposes.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
25
It follows from the foregoing that, compensation is not payable on vacant land on which there exist no
physical improvements resulting from the expenditure of capital or labour.
The compensation payable is the estimated value of the unexhausted improvements at the rate of
revocation. Payment of such compensation to the holder and the occupier as suggested by the Act is
confusing. Does it refer to holder in physical occupation of the land or two different persons entitled to
compensation perhaps in equal shares? The correct view appears to allow from the general tenor of the
Act. First, the presumption is more likely to be the owner of such unexhausted improvements. Secondly,
the provision of section 6(5) of the Act, which makes compensation payable to the holder and the
occupier according to their respective interests, gives a pre-emptory directive as to who shall be entitled to
what.
Again, the Act provides in section 30 that where there arises any dispute as to the amount of
compensation calculated in accordance with the provisions of section 29, such dispute shall be referred to
the appropriate Land Use and Allocation Committee. It is clear from section 47 (2) of the Act that no
further appeal will lie from the decision of such a committee. If this is so, then the provision is not only
retrospective but also conflicts with the fundamental principle of natural justice, which requires that a
person shall not be a judge in his own case. The Act must, in making this provision, have proceeded on
the basis that the committee is a distinct body quite different from the Governor or the Local
Government. It is submitted, however, that it will be difficult to persuade the public that this is so since
the members of the committee are all appointees of the Governor.
Where a right of occupancy is revoked for public purposes within the state of the Federation; or on the
ground of requirement of the land for the extraction of building materials, the quantum of compensation
shall be as follows:
a) In respect of the land, an amount equal to the rent, if any, paid by the occupier during the year in
which the right of occupancy was revoked.
b) In respect of the building, installation or improvements therein, for the amount of the
replacement cost of the building, installation or improvements to be assessed on the basis of
prescribed method of assessment as determined by the appropriate officer less any depreciation,
together with interest at the bank for delayed payment of compensation.
c) With regards to reclamation works, the quantum of compensation is such cost as may be
substantiated by documentary evidence and proof to the satisfaction of the appropriate officer.
d) In respect of crops on land, the quantum of compensation is an amount equal to the values
prescribed and determined by the appropriate officer.
Where the right of occupancy revoked is in respect of a part of a larger portion of land, compensation
shall be computed in respect of the whole land for an amount equal in rent, if any, paid by the occupier
during the year in which the right of occupancy was revoked less a proportionate amount calculated in
relation to the area not affected by the revocation; and any interest payable shall be assessed and
computed in the like manner. Where there is any building installation or improvement or crops on the
portion revoked, the quantum of compensation shall follow as outlined above and any interest payable
shall be computed in like manner.
5.5 International Guidelines
International Development Partners/Agencies such as World Bank and other financial organizations
interested in development projects recognize this highly especially in development that result in
involuntary resettlement. It is against this background that policies and guidelines have been set for
managing such issues. The World Bank’s policy on involuntary resettlement will be applied in any sub-
project of the NEWMAP that displaces people from land or productive resources due to land take.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
26
Where there is conflict between national legislation and World Bank Operational Policies, the latter
policies shall prevail.
5.5.1 The World Bank Policy on Involuntary Resettlement (WB OP. 4.12)
The Bank’s policy on Involuntary Resettlement advocates that where feasible, involuntary resettlement
should be avoided or minimized. Resettlement shall be conceived and executed as a sustainable
development program, where it is inevitable, providing sufficient investment resources to enable persons
displaced by the project share in project benefit.
Persons displaced shall be:
i. Duly consulted and should have opportunity to participate in the planning and execution of the
resettlement;
ii. Compensated for their losses at full replacement cost prior to civil works;
iii. Assisted with the move and supported during the transitional period in the resettlement site;
iv. Assisted in their effort to improve their former living standards, income earning capacity and
production levels or at least to restore them.
For the nature of the Flood and Erosion Site in Agassa, which will also involve some civil works
constructions, the World Bank required the preparation of a Resettlement Action Plan to be used to
guide the execution of a sustainable resettlement or compensation process for all the PAPs.
5.5.2 Conclusion Drawn from the Review of World Bank Policies on Involuntary Resettlement
Review of the different policy guidelines of the World Bank (OP/BP 4.12) shows that primarily, the
World Bank agrees that PAPs be compensated or assisted irrespective of legal status of PAPs to the
land/or place they occupy. The key concern articulated in this policy is to ensure that PAPs are
compensated or assisted including income restoration measures to ensure that they are not economically
worse off relative to pre-project period.
5.6 Comparison between Nigerian Land Use Act and the World Bank Operational Policy (0P4.12)
In this section a comparison is made between the Nigerian Land Use Act and the World Bank’s
operational policy on involuntary resettlement.
Table 5.1: Comparison of Nigerian Land Use Act (1978) and World Bank Operational Policy (OP 4.12)
CATEGORY NIGERIAN LAW OP 4.12 Of WORLD BANK MEASURES
Land Owners:
Statutory Rights
Cash
compensation
based upon
market value
Recommends land-for-land
compensation, or cash
compensation at replacement
cost.
Cash compensation at
replacement cost.
Land Owners:
customary
Rights
Cash
compensation for
land
improvements;
compensation
in kind with other
village/ district land
Equivalent value. If not, cash
at full replacement value,
including transfer costs.
Cash at full replacement
value, including transfer
costs.
Land Tenants Entitled to
compensation
based on the
amount of rights
they hold upon
Entitled to some form of
compensation subject to the
legal recognition of their
occupancy.
Compensation subject to
the legal recognition of
their occupancy.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
27
land.
Land Users Land users without
title rights be it
customary, C of O
or R of O are not
entitled to any
form of
compensation.
Entitled for compensation for
crops and entitled for land
replacement and income loss
compensation for minimal of
pre-project level.
Compensation for crops
and entitled for land
replacement and income
loss compensation for
minimal of pre-project
level.
Owners of Non-
permanent
Buildings
Cash
compensation
based on
prevailing market
value
Entitled to in-kind
compensation or cash
Compensation at full
replacement cost including
labour and relocation
expenses, prior to
displacement.
Compensation at full
replacement cost
Owners of
permanent
Buildings
Cash
compensation
based on
prevailing market
value
Entitled to in-kind
compensation or cash
compensation at full
replacement cost including
labour and relocation
expenses, Prior to
displacement.
Compensation or cash
compensation at full
replacement cost
including labour
Losers of
livelihoods,
farmers, business
people,
employees etc.
No consideration
other than cash
values for assets as
described above by
asset category
Key objective is restoration of
capacity to generate incomes at
least at levels prior to losses.
Programs of assistance to
achieve this objective-
Compensation for periods of
lost income.
Restoration of capacity to
generate incomes at least
at levels prior to losses.
Programs of assistance to
achieve this objective-
Compensation for
periods of lost income.
Grievance
procedure
No specification
requirement for
establishing an
independent
grievance
mechanism
The Grievance Mechanism
Will Be Set Up as Early as
Possible in The Process, To
Receive and Address in A
Timely Fashion Specific
Concerns About
Compensation and Relocation
That Are Raised by Displaced
Persons And/or Members Of
Host Communities. Including
A Recourse mechanism
designed to resolve disputes in
an impartial manner. The
grievance mechanism, process,
or procedure should address
concerns promptly and
effectively, using an
understandable and
transparent process that is
culturally appropriate and
Procedures to follow
grievance redress
mechanism established.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
28
readily accessible to all
segments of the affected
communities, at no cost and
without retribution.
Rejection of
Compensation
No categorical
Statement
Where compensation to an
affected person in accordance
with an approved resettlement
plan has been offered, but the
offer has been rejected, the
taking of land and related
assets may only proceed if the
project owner has deposited
funds equal to the amount
offered as compensation plus
10 percent in a secure form of
escrow or other interest-
bearing deposit satisfying the
Bank’s fiduciary requirements.
The project owner must also
provide a means satisfactory to
the Bank for resolving the
dispute concerning the offer of
compensation in a timely and
equitable manner
The World Bank
recommendation is to be
implemented.
Adapted from the Resettlement Policy Framework for the project, April 2006 Revised 2013.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
29
Table 5.2: The Entitlement Matrix for Various Categories of PAPs
Type of Loss Entitled Person Description of Entitlement
1.Permanent loss of land
1.1Cultivable/residential/c
ommercial land
1.1 (a)Legal owners of land
(b) Occupancy/Hereditary
Tenant
1.1 (a) Land for land compensation is preferred
priority, or Cash compensation at replacement
value based on market rate plus 10% compulsory
acquisition surcharge as second option
(b) & (c) Compensation will be paid as plus a
one- time lump sum grant for restoration of
livelihood and assistance for relocation.
2. Damage to land (such
as abutting sub-project
site)
2.1. By excavation etc.
from burrows for earth for
construction.
2.2 By severance of
agricultural holding
2.1. (a)Legal owner/s
(b) Village/s or clan/s with
customary ownership
2.2. (a)Legal owner/s
(b) Village/s or clan/s with
customary ownership
2. 1 (a) & (b) Restoration of land to pre-
construction condition or cash
compensation at prevailing rates for necessary
bulldozer/ tractor hours
to restoring level and/or truckloads of earth for
fill
2.2 Provision of water course to connect severed
segment with source
of water
3. Loss of income and
livelihood
3.1. Temporary loss of
access to land for
cultivation
3.1 Cultivator occupying land 3.1. Estimated net income for each lost cropping
season, based on land record averages of crops
and area planted in the previous four years
3.2. Loss of agricultural
crops, and fruit and wood
trees.
3.3 Loss of income by
agricultural tenants
because of loss of land
they were cultivating
3.2. (a) Owner/s of crops or
trees. Includes crops trees
owned by
encroachers/squatters
(b) /tenant
3.3 Persons working on the
affected lands
3.2. (a) Cash compensation for loss of agricultural
crops at current market value of mature crops,
based on average production.
Compensation for loss of fruit trees for average
fruit production years to be computed at current
market value.
Compensation for loss of wood-trees at current
market value of wood (timber or firewood, as the
case may be).
3.2. (b) Partial compensation to tenants for loss of
their crops/trees as per due share or agreement
(verbal or written)
3.3 One-time lump sum grant to agricultural
tenants (permanent, short- term or long-term
agricultural labour (this will be in addition to their
shares in crop/tree compensation)
a) Tree/perennial crops: Harvesting of the crops
will be given a first priority but where harvesting is
not possible, counting of the affected crops will
be done in the presence of the owner.
Computation of the costs will be done according
to market rates and will include cost of regrowing
perennial trees to maturity where applicable.
b) Annual crops: Crops will be harvested by the
owner and therefore no compensation will be
paid for crops. Where crops cannot be harvested,
compensation at the market rate will be paid
4. Permanent loss of
Structures
4.1 Residential and
commercial
Structures
4.1. (a)Owners of the
structures whether or not the
land on which the structure
stands is legally occupied
(b) Renters
4.1. (a) Cash compensation for loss of built-up
structures at full replacement costs
Owners of affected structures will be allowed to
take/reuse their salvageable materials for
rebuilding/rehabilitation of structure.
In case of relocation, transfer allowance to cover
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
30
cost of Shifting (transport plus loading/unloading)
the effects and materials will be paid on actual
cost basis or on current market rates.
(b) One-time cash assistance equivalent to 4
months rent moving to alternate premise.
Transfer allowance to cover cost of shifting
(transport plus loading/unloading) personal
effects paid on actual cost basis or on current
market rates.
4.2. Cultural, Religious,
and community structures
/facilities School, church,
water channels, pathways,
and other community
structures/installations
4.2.Community 4.2. Complete rehabilitation/restoration by the
Project: or, Cash compensation for restoring
affected cultural/community structures and
installations, to the recognized patron/custodian.
5. Special provision for
vulnerable APs
5.1 Re-establishing and/or
enhancing livelihood
5.1 Women headed
households, disabled or
elderly persons and the
landless
5.2 Change in Livelihood
for women and other
vulnerable AP5 that need
to substitute their income
because of adverse impact
5.2. (a) Vulnerable APs,
particularly Women enrolled
in a vocational training facility
5.2. (b) owner/s whose
landholding has been
reduced to less than 5 acres
Unanticipated adverse
impact due to project
intervention or associated
activity
The Project team will deal with any unanticipated consequences of the Project
during and after project implementation in the light and spirit of the principle of
the entitlement matrix.
5.7 Eligibility Criteria
There are three basic categories of eligibility for resettlement benefits:
i. Persons holding legal title (or the equivalent in customary-law) to the land they occupy or use to
derive their livelihood. This shall be entitled to receive compensation for their assets at
replacement value.
ii. Persons lacking title but with legal rights that can ratified by recognized legal process, e.g. heirs to
an estate.
iii. Persons with no legal or legitimate claim to the land they occupy or use.
Those having legitimate rights shall receive assistance to regularize their status and shall be treated just as
those having legal rights. Persons having no legal rights to land under law may not be compensated for the
land they occupy but they are entitled to compensation for other assets / improvement on the land (e.g.
housing) and to receive assistance. In practice, this may mean that squatters and other non-legal occupants
receive the same entitlement as those having legal rights. Where cash compensation is used for very poor
people, it is strongly recommended that supervision be provided so that such compensation is not used
for consumption or other unsustainable expenditures. The census carried out has enabled the
identification of those affected and eligible for assistance and the nature of assistance.
The entitlements, as the case may be, consist of replacement housing, building lots, or cash
compensation. Under Bank Policy, cash compensation is only appropriate when there is an active market
in land or housing and where such assets are actually available for purchase. Communal rights to land and
other assets are recognized. Clans, lineages and other community property have been subjected to the
same procedures as for privately held land. In such cases, traditional law may be taken into account.
Tenants will be granted resettlement entitlements along with owners or they may be given a subsidy to
find a new rental property. Entitlements shall include transitional support such as moving expenses,
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
31
assistance with food and childcare during a move and other needed support. All PAPs irrespective of
their status, whether they have formal titles, legal rights or not, squatters or otherwise encroaching illegally
on land, are eligible for some kind of assistance if they occupied the project area before the cut-off date.
All persons residing, conducting activities or earning income within the project affected areas at the cut-
off-date, which is the last day of inventory of loss will be entitled to compensation and resettlement
assistance. To determine their eligibility, PAPs are classified as follows:
➢ Persons who have formal right to land (including customary and traditional rights recognized under
➢ Nigerian law);
➢ Persons with temporary or leased rights to use land; and
➢ Persons who do not have formal legal right to lands or other assets at the time of the census, but who
have claim to such legal rights by virtue of occupation or use of those assets.
➢ Businesses within the community
Those who do not have the legal title to land but reside in the affected area before the cut-off-date will be
compensated for properties such as houses and other investment on the land, but will not be
compensated for the land. The eligibility criteria for compensation are outlined n Table 5.3.
Table 5.3: Eligibility Criteria for Compensation
PAP Classification Eligible for Compensation No Compensation Assistance
Those with legal right to
land
Land or asset at replacement
cost, taking into account
market values for land
For land, assets, and
structure on the land
after the cut-off- date
Assistance
as needed
Those with temporary or
leased rights to land at cut-
off date
Land and assets at
replacement cost, taking into
account market values for
structures and materials
For land, assets, and
structure on the land
after the cut-off- date
Assistance
as needed
Those with no legally
recognised right to land
but arrived before cut-off
date.
Assets at replacement cost
except that compensation
may be “topped off” to allow
the PAP to acquire a new
residence in a place where
he/she can legally reside.
For land Assistance
as needed
Those who arrived after
Cut-off-date
None None None
Those with business
located within the
Community
Assets and lost income as a
result of lost business during
project duration
For business located in
community after the
cut-off - date and
outside the affected
area.
Assistance
as needed
This RAP will be aligned with the World Bank Operational Policy, which indicates best practices for
rehabilitation of livelihoods of people affected by the implementation of the project. The Bank’s policy
will be applicable because they are involved in the funding of the project and also because its policy must
fulfil the pro-poor objectives of the project, ensuring that the conditions of PAPs are preferably improved
and at least restored to pre-displacement levels as well as offers special considerations for vulnerable and
landless PAPs.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
32
CHAPTER SIX
VALUATION AND COMPENSATION OF AFFECTED STRUCTURES AND PROPERTIES
6.0 Introduction
Issues of valuation of assets to be affected by the implementation of proposed project intervention works
are discussed in chapter six. The general principles adopted in the formulation of the compensation
valuation, the World Bank’s safeguard policies on entitlement, the entitlement matrix, and proof of
eligibility as well as valuation methodology are also examined in this chapter.
6.1 Valuation Methodology
Valuation of assets to be affected by the implementation of the project was conducted in conformity with
the general principles contained in the World Bank Safeguards Policy that lost income and properties will
be valued at their full replacement cost such that the PAPs should experience no loss. The asset valuation
was conducted based on the current market prices in the Agassa and Nigeria standard. The following
methods and principles guided the valuation of assets.
6.1.1 Replacement Cost Method
World Bank OP4.12 requires that current market value of asset within the project area be used to
determine the compensation rate for land, building and other assets. This entails carrying out market
survey of land per square meter and the market prices of the affected assets.
DaLA method was used to determine compensation for economic trees because of it robustness and
advantage over the traditional method of assessing the cost of an economic tree. DaLA method states that
market value of yield per tree for the current season (agricultural season) and cost of re-planting and
nursery should be used to determine the compensation rate for the economic tree while the Traditional
Method equates the capital of the existing structure/ tree to the cost of reinstating the structure/ tree on
the same type of plot at the current labour, material and other incident costs.
6.1.2 Land Resettlement
The World Bank OP 4.12 requires that displaced owners of land be provided with an area of land
equivalent to their displaced land. It states that land restoration should be in a location that has similar
value as the one displaced by the project. However, the owners of the lands who are indigenes of the area
willing to give out their portions of land which will be required by the project activities will be
compensated by monetary value based on the findings of the needs assessment.
6.1.3 Disturbance and Other Incidental Contingencies
Affected business premises, which will have to close shop or be relocated, will be given compensation for
loss of business time or assistance for transportation.
6.2 Affected Structures:
6.2.1 Immovable Structures/Property:
This consists of all structures/property that are not moveable (Immovable) such as Fence, Mud and Block
Building, Economic Trees and Flowers, etc. All assets valued for compensation within this project fall
under the category of immoveable assets.
6.2.2 Moveable Structures/Property:
This includes Kiosks, Metal and Wooden containers and Water Tanks. There was no property/structure
classified under moveable; this is as a result of the rural nature of the project area.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
33
6.2.3 Permanent Structures/Asset
This consists of structures that will be displaced or removed permanently due to the project. Such assets
exist in these locations as some part of the area is densely populated.
The SPMU will arrange and make payment of estimated values to the beneficiaries according to the
provision of this RAP. This is to enable the PAPs to start arranging for alternative resettlement elsewhere.
6.2.4 Compensation and Other Resettlement Assistance
The description of the packages of compensation and other resettlement measures to assist this category
of eligible displaced persons to achieve the objectives of the plan have been evaluated and presented as
captured. All PAPs due for compensation have been duly identified.
6.3 Modes of Restitution
All project affected persons (PAP) have been carefully documented with their phone numbers. All the
PAPs can be reached by the Village/District Heads as the streets/houses are not in existence. The
notification for payment will include how payments will be made and the set date. The peculiar local
security situations will be taken into consideration by the SPMU in reaching out to the PAPs for
payments.
6.4 Compensation Payment and Procedures for Delivery of Compensation
The main objective of the RAP is to develop programmes that aim to improve the livelihoods of PAPs or
restore them to the pre-displacement levels. Where impact on land is intense such that sustainability of
livelihoods may be affected, preference will be given to land compensation rather than cash pay-outs. This
applies to the PAPs who are not physically displaced but who are affected by a land loss that affects their
properties.
6.5 General Principles to be adopted for Compensation
The general principles which should be followed for the payment of compensation for lost assets shall be:
a) Paid prior to acquisition or displacement;
b) At replacement cost;
c) The full cost of materials, and labour required for reconstructing a building of similar surface and
standing;
d) Compensate all the PAPs adequately for properties and income lost;
e) Check and ensure that resettlement was built in as an upfront project cost to avoid inadequate
compensation. That is to say, the affected person must be able to have their farming activities
restored in a different location using the compensation paid;
f) To include cost of moving, such as transport costs as well as any associated land titling or transfer
fees;
g) To make all payments in monetary forms as agreed with the PAPs;
h) To make payments by the Resettlement and Compensation Committee. This committee will
include members of the SPMU and selected community leaders from the affected location.
6.5.1 Procedure for Delivery of Compensation
The procedure for delivery of compensation to PAPs shall include but not limited to the following:
a) Full payment of compensation carried out before possession of acquired sites.
b) Implementation committee communicates the amount to be paid to the PAPs
c) Transfer to individual accounts is the preferred first mode of payment. SPMU shall make
arrangements with the nearest bank to effect payments without any challenge to the PAPs. The
accounts shall be domiciled in the bank, and a cheque issued to an individual PAP, to be cashed
after fifteen days if no dispute arises.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
34
d) Necessary document of payments to the affected persons should be presented to local land/asset
valuation committee from the Local Government and/or other independent witnesses of the
affected person and leaders of the communities.
e) Proper receipts should be issued and copies given to the affected persons including the Finance
Department of SPMU
f) Comprehensive reports on payment made are submitted for review by SPMU Management.
6.6 Assistance to Vulnerable Groups
For the purposes of this RAP, vulnerable persons are defined as those who by virtue of gender, ethnicity,
age, physical or mental disability, economic disadvantage, or social status, may be more adversely affected
by resettlement than others, and who may be limited in their ability to claim or take advantage of
resettlement assistance and related project development benefits.
PAPS who are not Head of household and are susceptible to loss of shelter shall be assisted with cash
equivalent to three month rent to save them from homelessness.
A total of 36 persons were identified as vulnerable persons in this project.
6.7 Livelihood Restoration
Whether implemented by Community Associations, the NGO or a firm, all livelihoods activities
supported will be selected by communities themselves, guided by a list of potential activities, with
sensitization carried out and informed by exposure visits to other project sites.
The community liaison and support professional will provide technical services to the Community
Association and facilitate the overall process, backstopped by the NEWMAP Technical Officer. As
activities are selected, and groups and/or individuals develop appropriate plans, trainers with expertise in
specific livelihood activities will be retained for short periods to provide hands-on instruction for
participants.
Emphasis must be direct on people most in need of livelihood support of livelihood support, for example
those most affected by erosion and intervention works (the poor, landless, disabled, women and female-
headed households).
6.7.1 Restoration Strategies
1. Livelihood Identification and Preparation Support
The community liaison and support professional will work closely with the Community Associations
(CAs) that may wish to develop group activities. Community Associations will receive training - according
to identified needs — in small business development and developing a business plan, basic bookkeeping,
banking, accessing commercial finance, marketing, customer relations, leadership and team building,
customer relations, leadership and team building.
2. Livelihood Sub-grants for Income, Skills and Employment Opportunities
The SPMU will provide grants to Community Associations to implement community sub-projects
selected by the Community Associations and/or individuals. The community sub-projects will include:
(i) those which generate income, and/or
(ii) those which provide technical skills that could lead to employment opportunities or new start-ups.
Eligible activities may include:
• Geo-textile manufacture from coconut-palm leaves and husks, other crop residues and other
materials.
• Gabion box manufacture.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
35
• Construction skill training on gabion box installation/erection and other masonry/concrete works
for the affected communities to work on the project.
• Horticulture on reclaimed lands.
• Seedling nurseries for fruit trees and other species, operated by women.
• Planting/protection of moringa (moringaolifera) or other locally appropriate trees for soil
stabilization, food products and other economic and environmental benefits.
• Vetiver grass nurseries for use in gully stabilization.
• Grass-cutter and other small livestock, mushroom, and snail production.
• Beekeeping and honey production.
• Establishing small retail-shops.
• Skill training in the service sector, such as auto and small machine mechanics, bicycle repair,
welding, tool sharpening, food production, solar and satellite installation and sale.
• Specialized marketing facilities such as private warehouses and transport equipment.
• Skills for employment in local industries could also be taught such as environmentally friendly
rock quarrying, or sawmill operation, security-related activities depending on needs in local
labour markets.
Technical support will be provided by the community liaison and support professionals, Community
Associations and individuals to identify and develop suitable, market driven livelihood options. Selection
criteria will favour those people most affected by gully erosion/intervention works, the poorest in the
community, and women.
6.8 Provision of Amenities for the Community
In support of the communities and as part of the social responsibility of SPMU, assistance could be given
to the poor communities as may be requested by the PAPs to make their relocation tolerable.
6.9 Environmental Protection and Management
Alongside this RAP, an Environmental and Social Management Plan (ESMP) has been prepared to
address adverse impacts during the work. Thus, this section of the RAP should be read and understood
as well as applied in light of the ESMP.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
36
CHAPTER SEVEN
PUBLIC PARTICIPATION AND CONSULTATIONS
7.1 Introduction
The Public Consultation process for the project began during the early stage of reconnaissance level-
survey. This has further been enriched through interactions and consultation with the relevant
stakeholders in the course of the preparation of this RAP. Public consultation and participations are
essential because they afford PAPs and the general public the opportunity to contribute to both the design
and implementation of the project activities and reduce the likelihood for conflicts. The more direct
involvement of the local level people in the planning and management processes, the greater the
likelihood that resource use and protection problems will be solved, the likelihood of development
opportunities occurring in a balanced way and to the broad benefit of all communities in the project.
7.2 Objective of the Consultation
Providing adequate information to affected communities and stakeholders reduces the potential for
conflicts, minimizes the risk of project on communities and enables resettlement and compensation in a
comprehensive development programme.
In Specific terms, the sensitization campaign and public consultation sought to achieve the following:
• Inform stakeholders of the project activities and provide adequate information on the project, its
components and its activities with affected communities.
• Establish grievance and effective complaints mechanism on the project.
• Obtain vital information about the needs and priorities of affected settlements.
• Inform the PAPs and the communities about various options of resettlement and compensation.
• Obtain cooperation and support of the project affected persons
• Ensure accurate and transparent resettlement and rehabilitation process for Project affected Persons.
7.3 The Stakeholders
Stakeholders for the purpose of this project are defined as all those people and institutions that have an
interest in the successful planning and execution of the project. This includes those positively and
negatively affected by the project. The key stakeholders identified and consulted included the political
leaders in the relevant local government areas, community heads, other opinion leaders in the
communities, individuals affected by the project activities / those who own properties that are directly or
indirectly affected, special interest groups such as CBOs, etc.
7.3.1 Consultation Strategies
The process of resettlement and public participation includes both information exchange (dissemination
and consultation), and collaborative forms of decision making. Information dissemination and
consultation with stakeholders, especially the Project Affected Persons (PAPs) means transfer of
information from Project proponents to the affected population. It provides an opportunity for all the
communities in the areas to raise issues and concerns pertaining to the project, and allow the
identification of alternatives and recommendations.
Specific objectives of the public information campaign and public consultation include: fully shared
information about the on-going project, its components and its activities, with affected people, obtain
information about the needs of the affected people, and their reactions towards proposed activities,
ensure transparency in all activities related to land acquisition and compensation payments and ask local
residents especially the interested and Affected Parties about the problems anticipated with the project,
and how these can be overcome.
The consultation process ensured that all those identified as stakeholders were consulted. Two Focal
Group Discussions/meetings were held with the relevant MDAs in Okene LGA, Onoba of Agassa and
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
37
other concerned community members at an enlarged level on the 26th February, 2017, also at different
times and smaller units.
Furthermore, especially with the PAPs, one-to-one meeting was used during the household census survey
carried out in the Project area.
7.4 Discussion with Stakeholders and Summary of Outcome Conclusion
During the stakeholders meeting, the Consultant updated the community with the focus and objectives of
the Project and the role the RAP implementation will play along with other related information. Other
burning matters discussed were the issues/grievances that will result during the implementation of the
project and the support needed from all stakeholders to ensure effective project work and successful
implementation.
The meeting also gave the opportunity to update the persons that would be displaced resettlement
options that would be available to them. The process of the grievance redress mechanism was also
presented to them as a way out of any grievances that might emanate during the project.
The community residents understand that the intending Project Affected Persons (PAPs) have the rights
to be heard and their concerns captured in the project implementation. Subsequently, the meeting gave
the residents the opportunity to be aware of the compensation for properties that would fall within 5m of
the gully corridor.
All the residents that attended the meeting were happy with the news of the project work and declared
their interest and support for the NEWMAP Project. In concluding, the residents were commended for
their attendance and commitment to the overall objectives of the project.
Table 7.1: Queries/Observations and the responses given to the stakeholders.
S/No ISSUES RESPONSES
1 Resident Stakeholders welcomed the proposed project and were
very much delighted and hopeful with regards to the approach
undertaken by the KOGI-NEWMAP and World Bank to
address the current problems of watershed and erosion, which
are currently affecting their lives negatively.
The consultant acknowledged the
residents widespread support for the
proposed project and encouraged them
to sustain it throughout the project cycle
2 Members of the community had before now carried out some
palliative measures (use of concrete structures, sand bags and
drainages) to mitigate the impact of the gullies at different
sections though these additions have been totally eroded by
exacerbated impact of the gully. Are there plans in place to
enable the communities sustain the project area and beyond
completion of works?
One of the NEWMAP components is to
help communities build capacity to check
erosion and effectively manage their
watersheds on a sustainable basis
3 The present watershed and gully erosion are serious problems
spanning from Ahache through Inakakanna to AgassaUvette
area of the community. Road construction should be
incorporated if not captured.
Based on the engineering report
received, some selected roads will be
rehabilitated
4 The majority of stakeholders commented that awareness
creation was essential for the long- term success of the erosion
and watershed management program; and that manpower
The consultant noted the views and as a
result serious awareness campaign carried
out in Agassa by the Consultant and KG-
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
38
development should be Included in the program. SPMU.
5 The construction activities may result in loss of properties, lands
or damage to their economic trees and crops. In such cases, will
there be compensations for such damages?
Yes, there will be compensations for
property damages or loss of assets as a
result of project implementation. The
purpose of the RAP is to methodically
identify such properties and assets that
may be impacted and establish level of
compensations that may be made.
6 Community safety concerns regarding the next cycle of rainy
season were keenly expressed. The community is very
apprehensive of the advancement of the gully when the rains
come pounding.
The concerns were noted. It is important
that the community provide the necessary
support to help speed up conclusion of
all due diligent aspects of the project. It is
hoped that the project will proceed
expeditiously enough as to not cause
further damages to the community; this
could only be done when ESMP and
RAP reports are concluded.
7 Will there be employment or incentives for the youth? This issue shall be recommended in the
report. The contractor’s attention shall be
drawn to work with the youths to
encourage employment and
empowerment for the youths.
8 The Onoba of Agassa and Community Representative, Mallam
Saeed Idris took time to plead with the residents to exercise
patience and work continuously with the consultants as World
Bank projects involve stages and process implementation
The Consultant endorsed this view. A lot
of cooperation of the community was
enjoyed in the course the project.
7.5 RAP Public Disclosure
SPMU will in conjunction with Federal Ministry of Environment publish this RAP report in 2 national
newspapers in line with the regulatory requirements of Nigeria, and then at designated centres accessible
to stakeholders, following which it will show evidence of country disclosure to World Bank external sites.
Subsequently, the Executive Summary of the RAP report will be translated to local languages and copies
made available and distributed with a letter accompanied to local government authorities concerned. This
could be done by a) publishing it on SPMU’s website; b) depositing/posting it in a range of publicly
accessible places such as, Traditional Heads’ palaces and community squares where they could be
protected and not abused. In addition, SPMU will ensure that the affected public is adequately sensitized
through public meetings, notices, and handbills/information booklets.
Once this RAP is disclosed, the public has to be notified both through administrative structures and
informal structures about the availability of the RAP documents and also be requested to make their
suggestions and comments. The complete approved RAP report will be made available in easily
accessible locations in or near the affected areas.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
39
Figure 7.1: Consultation with Men/Elders Focal group (Friday 26/01/2018)
Figure 7.3: Consultation with Women Focal Group Friday 26/01/2018
Figure 7.2: Consultation with the Onoba of Agassa on Friday 24/11/2017
Figure 7.4: Consultation with Youth Focal group at Agassa on Friday 26/01/2018
Figure 7.5: Cross Section of Stakeholders Meeting at Agassa on Friday 26/01/2018
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
40
Figure 7.6: Consultant and Stakeholders Figure 7.7: Consultant and Stakeholders
Forum Friday 26/01/2018 Forum Friday 26/01/2018
Figure 7.8: Consultant and Stakeholders Forum Friday 26/01/2018
Figure 7.9: A Cross Section of Participants during Consultation Meetings
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
41
Figure 7.10: Meeting of Consultant, NEWMAP Representatives and Agassa Community Erosion
Association
Figure 7.12: Site Inspection with the Engineering
Crew
of the NewMap
Figure 7.11: Site Inspection with the Engineering
Crew of the NEWMAP
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
42
CHAPTER EIGHT
RAP IMPLEMENTATION AND INSTITUTIONAL ARRANGEMENT
AND CAPACITY BUILDING
8.0 Introduction
This section explains the various roles and responsibilities of the various institutions involved in the
implementation of the RAP. The proposal for capacity building of stakeholders are presented and
elaborated.
8.1 Organizational Arrangement
The implementation of the RAP shall require close collaboration among all the project stakeholders. A
properly constituted structure for the project implementation is imperative and agreement must be
reached from the outset with the relevant parties. The roles and responsibilities of all the various relevant
stakeholders in the implementation and administration of the RAP are presented in Table 8.1.
Table 8.1: Roles and Responsibilities for Implementation of the RAP
S/No. Category Roles and Responsibilities
1 Kogi State -
NEWMAP SPMU
• Develop and implement RAP and other safeguard instrument;
• Drives activities of procurement, capacity building, service-
provider mobilization, and monitoring;
• Coordinates the many participating MDAs at State and Local
Government levels;
• Prepare a detailed action plan and time table for the day to day
RAP implementation;
• Organize the necessary training and capacity building measures
for the unit itself and for other partner organizations and
committees;
• Establish all local level institutions and committees which will
participate in the implementation of the RAP and provide them
with the necessary training and capacity building measures;
• Ensure the systematic monitoring, review and evaluation of the
RAP in accordance with the framework and guidelines provided
in the RAP;
• Monitor and take corrective actions and submit reports to the
relevant higher bodies for timely action;
• Implement the RAP including their involvement to redress
complaints and internal monitoring;
• Organize the necessary orientation and training for SPMU
officials in consultation with communities;
• Implement payment of compensation and other measures
(relocation and rehabilitation entitlement) to PAPs in a timely
manner
• Ensure that progress reports are submitted to the World Bank
regularly through the KSG - NEWMAP SPMU
2 KSG-NEWMAP
SPC
Coordinates and undertake compensation activities in accordance with
the principles and procedures specified in the RAP;
The SPC approves the fund for compensation;
3 PROJECT
ACCOUNTANT
The project Accountant will be responsible for the actual transfer of
payments.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
43
4 KSG-NEWMAP
SPMU SLO (Social
Livelihood Officer)
• Initiates the implementation of the RAP
• Reviews and approve contractors’ implementation plan for the
social and livelihoods impacts mitigation measures (or
mitigation and enhancement measures);
• Liaises with the Contractors and KSG -NEWMAP SPMU on
implementation of the RAP
• Coordinates on behalf of SPMU day to day activities with the
relevant line departments and oversee the implementation of
RAP instrument, prepare compliance reports with statutory
requirements, etc.,
• Monitors and supervise regularly the implementation of RAP;
• Observe payment of compensation to PAPs;
• Identifies and liaises with all relevant stakeholders for the RAP
implementation
• Responsible for the enforcement of all safeguard requirements
and ensuring the sustainability of all RAP provisions
• Implement the income restoration in accordance with the
principles and procedures specified in the RAP;
5 KSG-NEWMAP
M&E (Monitoring
and Evaluation
Officer)
• Develops the monitoring and evaluation protocol;
• Monitors target achievements;
• Identifies non-performance and take corrective actions;
• Oversees the overall monitoring of the project;
• Derives data from the SLO in addition to oversight checks.
• Include RAP implementation in the overall project M&E
6 KSG-NEWMAP
SMPU Technical
Committee Officers
• Review, update and approve work program and activities for the
implementation of the RAP;
• Review, update and approve operational guidelines of
contractors’ work plans for and other agencies for
implementation of the RAP;
• Develop and supervise inter-agency/organization collaborations
for the smooth implementation of the RAP;
• Provide technical support to all stakeholders necessary for
smooth implementation of the RAP
7 Kogi State MDAs • Supervise and enforce full payment of compensation benefits to
PAPs;
• Make appropriate recommendations or input into the
compensation payment process to ensure smooth
implementation
8 Local Government
Technical Committee
/Officer
• Coordinates activities at the local level for implementation of
the RAP;
• Ensures appraisal of properties affected by the project and for
which compensation is to be paid;
• Coordinates sensitization and awareness campaigns at the local
and community levels on the project and RAP;
• Appoints a suitable Desk Officer for RAP information
management
• Participates in grievance redress;
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
44
• Monitors implementation of the RAP at the local and
community levels;
• acts as liaison to KSG-NEWMAP SPMU, SMDAs and other
organizations and groups working towards implementation of
the Project and RAP;
• Provides technical support to all stakeholders for the
implementation of project and RAP;
• Facilitates interaction and cooperation between all stakeholders
to ensure smooth implementation of the project and RAP.
9 KSG-NEWMAP
Resettlement and
Compensation
Implementation
Committee (RIC)
• Responsible for supervision of compensation activities;
• Carry out meetings regularly with all PAPs;
• Provide all necessary information to PAPs regarding guidance
value and basis for calculations to be used for compensation
payments;
• Carry out appraisal of PAPs and PAAs and finalize entitlements
for each PAP;
• Prepare detailed implementation plan (quarterly) and pay
entitlements to PAPs;
• Ensure efficient implementation of the RAP;
• Ensure that all grievances related to the payments of
compensation to PAPs and other stakeholders are promptly
addressed in consultation with KSG-NEWMAP SPMU.
10 Community
Committees/
Interest Groups/
Traditional
Authorities
(NGOs/CBOs/
CSOs)
• Perform external monitoring functions to ensure compliance
with RAP provisions/ requirements;
• Support and assist in the mobilization of various relevant grass
root interest groups and stakeholders;
• Serve and support in the identification of genuine PAPs for
compensation payments;
• Assist in resolving grievance of PAPs;
• Provide support to PAPs during pre and post compensation
payments;
• Select livelihood opportunities to all PAPs and community
interest groups;
• Participate in the development approval and implementation of
livelihood restoration activities and programs;
• Mobilize and support all vulnerable groups particularly the aged
widows, orphans and the disabled to get their compensation
entitlements and livelihood support assistance:
8.2 Institutional Capacity Building Requirements and Costs
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
45
The result from various consultation meetings with stakeholders suggests that awareness creation and
capacity building should be provided through training and education programs. The cost estimates and
duration for the training program are outlined in table 8.2. Considering the respectively high level of
literacy, public awareness and education amongst the citizenry in the area, a simple training program is
suggested for the successful implementation of the RAP.
Table 8.2: Awareness and Capacity Building needs for relevant Stakeholders
S/N Duration Subject Target
Audience
Resources Budget
1 3 days Involuntary Resettlement
and Relevant Safeguard
Instruments/Covenants
World Bank OP 4.12
Involuntary Resettlement
Gaps between OP 4.12 &
Nigerian Land Use Act
and how to bridge them
Principles of RPF and
RAP
• Planning
requirements
• Implementation
requirements
• Grievance and
Conflict Management
and Resolution
• Documentation and
disclosure
requirements
• Eligibility and
entitlements matrix
Monitoring and
evaluation of RAP
activities and
operations.
SPMU Staff a. Full text of OP
4.12 for each
participant
b. PowerPoint
presentation
1,300,000.00
2 3 days Resettlement Action Plan
Implementation
Background
Resettlement packages
Consultations and
negotiations with project
affected persons (PAPs)
Grievance redress
mechanism
SPMU,
members of
Resettlement
and Grievance
Redress
Committee
a. PowerPoint
presentation
b. Associated
Hand-outs
1,300,000.00
3 1 day Social and Resettlement Contractors, b. PowerPoint 900,000.00
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
46
Considerations in Rural
Development project/
Project start up
Social and Resettlement
aspects arising during
construction and
operation stages
Social and Resettlement
Good Practices in public
works
Community relations in
urban project
management
SPMU, LG,
CBOs/CSOs
presentation
c. Associated
Hand-outs
4 3 days Public involvement and
Consultation in RAP
RAP Overview
RAP Implementation and
the public
Community participation
and consultation
Monitoring and
evaluation.
SPMU, LG,
Contractors, and
relevant
MDAs,
Community
Leaders/CBOs/
NGOs/PAP s
Hand-outs/Fliers 2,740,000
TOTAL N6,240,000.00
The estimated cost for capacity building for the various agencies and groups to be involved in the
implementation of the RAP is Six Million, Two hundred and Forty Thousand Naira (N6, 240,000.00)
only.
8.3 RAP Implementation Schedule
8.3.1 Resettlement Activities and Responsibilities
The range of activities and management tasks/responsibilities designed to effectively implement the RAP
are outlined in Table 8.3. The activities contained in the RAP have to be integrated into various phases of
the project construction. The key elements of the implementation schedule are contained in Table 8.3.
Construction activities will need to be planned, designed, executed (actual construction works) before
commissioning and decommissioning.
Table 8.3: Summary of Resettlement Activities and Responsibility for implementation of the RAP
S/N Project Cycle Phase Activity Responsibilities
1 Planning Scoping and
screening
Clearance and final disclosure
of the RAP
Review and approval of RAP
and implementation guidelines
Development and preparation
of livelihood support
assistance to PAPs and
vulnerable groups and other
Consultant supervision
by KSG –NEWMAP
SPMU,
CBOs/NGOs/SMDAs
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
47
social issues mitigation
WB No-Objection
2 Design Preparation of
RAP and
Consultations
Consultations and preparation
of the RAP
Communication and
awareness on notifications of
values, making of offers,
payment of compensation
modalities, meetings with
PAPs on eligibility criteria for
payment of compensation.
KSG-NEWMAP
SPMU, SMDAs,
CBOs/NGOs, LG
Committee
Completion and
Integration
Training and capacity building
Final version of the RAP
Inclusion of the RAP in
contract documents
Capacity building Training
WB No-Objection
Vetting of request for
compulsory land acquisition
and issuance of land titles to
resettled PAPs
Establishment of Resettlement
and Compensation
Committee, grievance and
dispute resolution Committee
Procedures for actual dispute
resolutions
3
Construction Implementation
and Monitoring
Taking possession of site
Coordination of RAP and
social and livelihood activities
Internal and external
monitoring of mitigation
measures for social and
livelihood impacts for the
communities, PAPs and
vulnerable groups
Preparation and approval of
monitoring and evaluation
reports
Non-conformance and
corrective actions
Adherence to contractual
clauses and obligations
regarding this RAP
implementation by
contractor(s).
KSG-NEWMAP
SPMU, SMDAs, LG
Committees,
CBOs/NGOs,
Contractors
4 Operation (Post
implementation)
Operations and
Maintenance
Monitoring, evaluation and
reporting on social and
KSG -NEWMAP
SPMU, SMDAs, LG
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
48
livelihood sustainability issues
Post impact auditing
Committee /Staff
CBOs/NGOs,
Contractor(s)
8.3.2 Estimated Cost of the RAP Implementation and Funding
The total cost implication for the implementation of the RAP is Forty Million, One Hundred and Thirty-
Nine Thousand, Four Hundred and Ninety Naira (N40,139,490.00:00) Only (Table 8.4). This sum is
expected to cover compensation for assets affected and additional mitigations for livelihood restoration
measures including the coordination of additional mitigation activities, grievance management as well as
compensation commissions.
Table 8.4: Budget Estimate for the RAP Implementation
S/No. Item Cost(N) Total
A1 Compensation:
370,000.00
28,170,900.00
28,540,900.00
Agricultural Crops
Land/Structures
Sub-total
B Additional Mitigation
624,000.00
100,000.00
724,000.00
Livelihood measures/assistance for
vulnerable group
Grievance Redress Management
Sub-total
C Implementation
Compensation commission 320,000.00
Capacity building/Institutional
strengthening
6,240,000.00
Disclosure 500,000.00
Management 200,000.00
Sub-total N7,260,000.00
E Add Contingencies (10%) N 3,615,490.00
Grand Total N40,139,490.00
Allow time for annual/seasonal crop owners to harvest their crops. Careful management of the site based
on 5m setback will reduce compensation amount.
The total cost of RAP is Forty Million, One Hundred and Thirty-Nine Thousand, Four Hundred and
Ninety Naira (N40, 139,490.00) only.
8.3.3 Sources of Fund
The source of fund for the compensation and mitigation measures including the overall implementation
of this RAP is Kogi State Project Management Unit (KG-SPMU) of NEWMAP.
8.3.4 Implementation Timetable
Before any project activity is implemented, PAPs will need to be compensated in accordance with this
RAP and the resettlement policy framework.
The schedule for the implementation of activities must be agreed to between the Resettlement
Committee and the PAPs and Social Livelihood Officers. These include the target dates for start and
completion of all compensation payment before commencement of construction work. The major
component tasks for the RAP are outlined in Table 8.5
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
49
Table 8.5: Major Component Tasks and Schedule for the RAP Implementation
ACTIVITIES 2017 2018 2019 REMARKS
NO
V
DE
C
JAN
FE
B
MA
R
AP
R
MA
Y
JUN
E
JUL
Y
AU
G
SE
P
OC
T
NO
V
DE
C
JAN
FE
B
MA
RC
H
AP
RIL
MA
Y
JUN
E
Consultation
/community
participation and
information to people
affected cut-off date
announcement census
and survey analysis
date and verification of
impacts
Nov 2017-
March 2018
RAP Approval
April - August
2018
Disclosure of RAP
Sept. – Oct.
2018
RAP implementation
including payment of
compensation and or
supplementary
assistance
Nov. 2018
Implementation/ civil
work, commencement
of project
Nov. - Feb 2019
Mark-up visit by
stakeholder/SPMU
March 2019
Economic Restoration
Assessment
April - June
2019
8.4. Coordination with Civil Works
The resettlement program will be co-coordinated with the timing of civil works. The required
coordination has contractual implications, and will be considered in procurement and bidding schedules,
award of contracts, and release of cleared RoW sections to project contractors. The timing mechanism of
this RAP ensures that no PAP is displaced (economically or physically) due to civil works activity before
compensation is paid and resettlement sites with adequate facilities are prepared and provided for the
PAPs.
The project will adhere to the following important principles in its implementation:
• No construction should be undertaken unless PAPs have received their resettlement entitlements
in accordance with this RAP.
• Information sharing and consultations with PAPs will continue throughout the planning and
implementation phase of the project, including the relocation and the restoration of livelihoods.
• A completion survey of the delivery of compensation and resettlement entitlements will be
undertaken as per this RAP and other relevant instrument prepared for the project.
• The schedule for the implementation of activities must be agreed to between the Resettlement
Committee and the PAPs such as;
- target dates for start and completion of civil works, and
- dates of possession of land that PAPs are using.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
50
CHAPTER NINE
GRIEVIANCE REDRESS MECHANISM
9.0 Introduction
Grievance is a common phenomenon in involuntary resettlement, which if not amicable and timely
resolved, invariably gives rise to local resistance, political tension and unnecessary delays in executing
developmental projects. A grievance redress mechanism for the Project is aimed at addressing any
legitimate concern of PAPs who consider themselves deprived of appropriate treatment under the
project. The mechanism includes:
i. A recording and reporting system including grievances filled both verbally and in writing.
ii. Staff with responsibility at various level of government and
iii. A time frame to address the filled grievance
9.1 Grievance Redress Process
There is no one-size-fits-all procedure for grievance resolution; the best solutions to conflicts are generally
achieved through localized mechanisms that take account of the specific issues, cultural contexts, local
customs and project conditions and scale. The procedure to be adopted for grievance resolution for this
RAP is as spelt out in the grievance log (Appendix 13), which indicates as follows:
a. Receive and register a complaint.
b. Screen and assess the complaint.
c. Attempt alternative responses.
d. Decide on the best approach or response based on agreed criteria
e. Implement the approach
f. Announce the result
g. Track and evaluate the results
h. Learn from the experience and communicate back to all parties involved.
i. Prepare a timely report to Management on the nature and resolution of grievances.
9.2 Stages in the Grievance Redress Process
Stage 1: Community Grievance Committee;
This will be coordinated by a representative of the Focal NGO, other members will be drawn as follows:
- Two (2) representatives from Community Association,
- A representative from the Onoba (Ward Head),
- A representative from the LGA,
- A representative from the Department of Lands and Survey in the Local Government and
- The Social and Livelihood Officer of the SPMU as the Secretary
This is the first stage of grievance uptake. Aggrieved persons should lodge their complaints in the
Grievance Complain Box that will be situated at the residence of the Ward Head from where the Focal
NGO can access the complaints. This Committee is expected to contact the aggrieved person and resolve
the issues within two (2) weeks of receiving the complaint. The decision reached should be
communicated to the aggrieved person and the SPMU in writing within the stipulated time. In the event
that the aggrieved person is dissatisfied with the decision reached by this Committee, he/she should
proceed to the second grievance redress committee.
Stage 2: The Project Management Unit GRS
This Committee will be coordinated by the Project Coordinator, Kogi State SPMU, and members of the
Committee shall include:
- One representative from the department of flood and erosion control in the Ministry of
Environment and Natural Resources.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
51
- One representative from the Ministry of Lands and Survey
- A representative from the Focal NGO
- The Project Accountant
- The Project Environmental Officer,
- The Project Operations Officer and,
- The SLO as the Secretary.
This Committee is expected to verify the complaint made by the PAP in consultation with the aggrieved
person. Solutions to the issues should be resolved within two (2) weeks of receiving the complaint. PAPs
are provided with Kogi State NEWMAP official line for enquiries and registering of complaints in
addition to documented complaint (+234 810 946 7464). Where the aggrieved person is dissatisfied with
the decision of this Committee, he/she should proceed to the third higher level Committee.
Stage 3: NEWMAP Steering and Technical Committee
This Committee will be coordinated by the Hon. Commissioner or the Permanent Secretary in the
Ministry of Environment and Natural Resources. Other members will be:
- Two (2) representatives of PAPs
- A representative of the Focal NGO
- The Social and Livelihood Specialist from the FPMU
- A representative of the Umbrella NGO or Ombudsman
- Social and Livelihood Officers from 2 neighbouring NEWMAP states and,
- The Project Coordinator of the SPMU as the Secretary
Complaints received by this Committee should be resolved within one (1) month of receiving the
complaint. Decisions reached at this stage are expected to put an end to the matter under contention.
However, if the aggrieved person is still dissatisfied, he/she should be referred to the judicial courts for
further redress.
9.3 Procedure for Registering a Complaint
The procedure for reporting grievances is specified below:
a) The affected person files his/her grievance, relating to any issue associated with the resettlement
process or compensation, in writing or phone to the project Resettlement Committee (Phone
numbers will be provided by the SPMU). Where it is written, the grievance note should be signed
and dated by the aggrieved person. And where it is phone, the receiver should document every
detail.
b) A selected member of the Site Committee will act as the Project Liaison Officer who will be the
direct liaison with PAPs in collaboration with an independent agency/NGO person in order to
ensure objectivity in the grievance process.
c) Where the affected person is unable to write, the local Project Liaison Officer will write the note
on behalf of the aggrieved person.
d) Any informal grievances will also be documented.
Due registration of a complaint or grievance by the grievance redress officer is good for reference
purposes and for making progress updates. Consequently, a registration format should capture the
complainant personal data, date the complainant is reported, date the grievance log was uploaded onto
the project database, date information on proposed correct action is sent to the complainant and the date
the case or complaint is closed out.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
52
9.4 Grievance Log and Response Time
The process of grievance redress will start with registration of the grievances to be addressed, for
reference purposes and to enable progress updates of the cases. Thus, a Grievance Form will be filed with
the Grievance Redress Committee by the person affected by the project. The Form/Log (Table 9.1)
should contain a record of the person responsible for an individual complaint, and records dates for the
date the complaint was reported; date the Grievance Log was uploaded onto the project database; date
information on proposed corrective action sent to complainant (if appropriate), the date the complaint
was closed out and the date response was sent to complainant.
The Project Liaison officer working with the local Government Desk Officer in recording all grievances
will ensure that each complaint has an individual reference number, and is appropriately tracked and
recorded actions are completed.
The response time will depend on the issue to be addressed but it should be addressed with efficiency
and will not last more than ten working days. The Grievance committee will act on it within 10 working
days of receipt of grievances. If no amicable solution is reached, or the affected person does not receive a
response within 15 working days, the affected person can appeal to a designated office in the SPMU,
which should act on the grievance within 15 working days of its filing.
Table 9.1: A Typical Reporting Format for Grievance Redress
Community
project &
Name of
Complainant
Type of Grievance Grievance Resolution
Aff
ect
ed
bu
t n
ot
info
rmed
ab
ou
t
Co
mp
en
sati
on
awar
ded
Co
mp
en
sati
on
no
t p
aid
befo
re
Rese
ttle
men
t
ben
efi
ts a
war
ded
are n
ot
pro
vid
ed
Oth
er
Dat
e o
f
Co
mp
lain
t
Dat
e r
ece
ived
Pen
din
g
Cas
e r
efe
rred
to
the c
ou
rt
Community Project 1
Complainant A
Complainant B
Complainant C
Community Project 2
Complainant D
Complainant E
TOTAL
9.5 Monitoring Complaints
The Project Liaison Officer will be responsible for:
• providing the grievance Committee with a weekly report detailing the number and status of
complaints
• any outstanding issues to be addressed
• monthly reports, including analysis of the type of complaints, levels of complaints, actions to reduce
complaints and initiator of such action.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
53
CHAPTER TEN
MONITORING AND EVALUATION
10.1 Introduction
To establish effectiveness of all the resettlement activities, this Monitoring and Evaluation (M&E)
procedure for the RAP has been designed. With this, it is possible to readily identify problems and
successes as early as possible.
Monitoring involves periodic checking to ascertain whether activities are going according to the plan. It
provides the feedback necessary for the project management to keep the programmes on schedule. By
contrast, evaluation is essentially a summing up, the end of the project assessment of whether those
activities actually achieved their intended aims.
10.2 Purpose of Monitoring
The purpose of monitoring is to provide project management, and directly affect persons with timely,
concise, indicative information on whether compensation, resettlement and other impact mitigation
measures are on track to achieve sustainable restoration and improvement in the welfare of the affected
people, or that adjustments are needed.
In short, monitoring answers the question: Are project compensation, resettlement and other impact
mitigation measures on time and having the intended effects?
Monitoring verifies that:
• Actions and commitments for compensation, resettlement, land access, and development in the
RAP are implemented fully and on time
• Eligible project affected people receive their full compensation on time, prior to the start of the
main project activities on the corridors;
• RAP actions and compensation measures have helped the people who sought cash compensation
in restoring their lost incomes and in sustaining/improving pre-project living standards;
• Compensation and livelihood investments are achieving sustainable restoration and improvement
in the welfare of Project-Affected persons and communities
• Complaints and grievances are follow up with appropriate corrective action and, where necessary,
appropriate corrective actions are taken; if necessary, change in RAP procedure are made to
improve delivery of entitlements to project affected people.
• Vulnerable persons are tracked and assisted as necessary
10.3 Components and Elements of the Monitoring Plan
In order to fully deliver on the commitments and objectives of this RAP, the following components and
elements of the RAP are to be effectively monitored.
a. Actions and commitments towards the payment of compensation
b. Measures to mitigate adverse social impacts
c. Livelihood support assistance to PAPs
d. Implementation or contractual responsibility to project-based community
e. Regular consultation and communication with PAPs.
f. Gender and vulnerable person’s livelihood restoration activities
g. Active participation of youths in construction work/activities
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
54
10.4 Monitoring Framework (Internal and External)
Monitoring will consist of:
a. Internal monitoring by the SPMU as an integral part of its management activities working with the
impacted communities; and
b. External monitoring by CBOs/NGOs/traditional authorities and other stakeholders, working with
the impacted communities.
10.4.1 Internal Monitoring
Internal monitoring activities must be carried out simultaneously with the implementation of the RAP.
This will assure mainstreaming of social and livelihood issues with construction activities.
The objectives of the internal monitoring are:
i. Daily operations planning;
ii. ii. Management and implementation and
iii. Operational trouble shooting and feedback.
The periodicity of internal monitoring will be daily or weekly depending on the issues and level of
impacts or changes going on or taking place. All aspects of internal M&E shall be supervised by the
SPMU Management Team and should provide high level evaluation of internal performance and impact
monitoring and other reports. The management team will be supplemented by staff with appropriate
skills to carry out:
a. RAP project resettlement requirements as defined by this RAP;
b. Gathering and presentation of additional monitoring indicators to be used;
c. Reporting requirements and formats for daily, weekly and monthly updates.
d. Appraisal of RAPs and full payment of compensation
e. Livelihood support assistance to PAPs
f. Progress updates on the implementation of women and vulnerable persons’ action plan
g. Implementation of contractual responsibility to project-based communities and PAPs
h. Social and livelihood sustainability issues
Regular progress reports shall be prepared and submitted to SPMU Management by the Social
Livelihood Officer (SLO). The internal monitoring will look at inputs, processes and outcomes of
compensation/resettlement/other impact mitigation measures.
Process and output monitoring functions will ensure that there is regular
a. Assessment of program implementation strategies and methodologies
b. Review of lessons learnt and best practices and provide recommendations to strengthen the
design and implementation of RAP
c. Communication with the affected communities
d. Agreement on resettlement and compensation policy, procedures, and rates
e. Performance of livelihood program delivery and uptake
f. Implementation of grievance resolution once conflicts arise
10.4.2 External Monitoring/Evaluation
External monitoring and or evaluation of PAP activities will deliver the objectives of compliance and
effect monitoring that is: -
a. Ensure that project implementation is in conformity with RAP objectives and procedures
b. Ensure that impact of project implementation on baseline poverty levels and other livelihood
issues are monitored
c. Assure that resettlement objectives are met
d. Compensation payments and benefits are paid promptly
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
55
e. Social and livelihood parameters are compared with baseline conditions and,
f. Guarantees effectiveness of existing community structures- CBOs/NGOs/various project
implementation committees.
10.5 Monitoring Parameters/Indicators
Indicator that will be monitored broadly centre around delivery of compensation, resolution of
grievances, land access, increase or decrease in PAPs assets, social stability, health, level of satisfaction and
number of project affected persons that benefit from the livelihood restoration programs. Specifically
some monitoring indicators for this RAP are outlined in Table 10.1.
Table 10.1: Monitoring Indicators/Parameters
Indicators Variables
Consultation
And Reach out
Number of people reached or accessing information, information
requests, and issues raised, etc. Number of local CBOs participating in the
project implementation.
Compensation and
establishment of
Interest Groups
Physical progress of compensation and assistance, number of PAPs affected
(land, trees, and crops), number of PAPs compensated by type of loss,
amount compensated by type and owner, number of replacement assets
recovered, and compensation disbursement to the correct parties.
Socio-economic
Changes
Level of income and standard of living of the PAPs. Number of income
restored, improved or declined from the pre-displacement levels.
Training Number of SPMU and RAP committee members trained
Grievance redress
mechanism
No. of cases referred to GRC
No. of cases settled by CRC
No. of cases pending with CRC
Average time taken for settlement of cases
No. of CRC meetings /No. of PAPs moved to the court
No. of pending cases with the court
No. of cases settled by the court
Overall
Management
Effectiveness of compensation delivery system
Timely disbursement of compensation;
Census and asset verification/quantification procedures in place; Co-
ordination between local community structures, PAPs and SPMU
10.6 Reporting
RAP monitoring reports will be prepared for the following tasks: Internal monitoring, External
monitoring, Completion audit & Compensation. SPMU will use a device such as a bar chart/Gantt chart
or MS Project table to assess and present information on progress of time bound actions.
Performance monitoring reports for the SPMU RAP management team will be prepared at regular
intervals (monthly), beginning with the commencement of any activities related to resettlement, including
income restoration. These reports will summarize information that is collected and compiled in the
quarterly narrative status and compensation disbursement reports and highlight key issues that have
arisen. As a result of the monitoring of inputs, processes, outputs and outcomes of RAP activities, project
management will be advised of necessary improvements in the implementation of the RAP.
10.7 Completion Audit
SPMU shall commission an external party to undertake an evaluation of RAPs physical input to ensure
and assess whether the outcome of RAP complies with the involuntary resettlement policy of the World
Bank. The completion audit should bring to closure SPMU’s liability for resettlement.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
56
BIBLIOGRAPHY
Abbreviated Resettlement Action Plan (ARAP) for the construction of Alternate Bridge at (Km
7 + 350) along Enugu Abakaliki Road, Emene Enugu State (2012)
Environmental and Social Management Plan (ESMP) for Asu-Umunaga Flood Site
(Manuscript) (2015)
Environmental and Social Management Framework for the Nigeria Erosion and Watershed
Management Project
International Finance Cooperation (IFC), Handbook for preparing a Resettlement Action Plan
Land Use Act (1978), Federal Republic of Nigeria.
Project Appraisal Document (2011) Growth and Employment in States Project.
Project Appraisal Document for Nigeria Erosion and Watershed Management Project
Project Implementation Manual for Nigeria Erosion and Watershed Management Project
Proposed Project Restructuring of Nigeria Growth and Employment in States Project (2013)
Resettlement Action Plan (RAP) for Ethiopia-Kenya Power Systems Interconnection Project
(KETRACO 2012)
Resettlement Action Plan (RAP) for Ganga River Front Development Project (BUIDCO). 2013
Resettlement Action Plan (RAP) for the Rehabilitation Amachalla Gully Erosion Site (2013).
Resettlement Action Plan (RAP) for the Asu-umunaga Flood Intervention Site (2015) (Draft).
Resettlement Policy Framework (2010), Growth and Employment for States Project
Resettlement Policy Framework for Nigeria Erosion and Watershed Management Project
World Bank (2000), Resettlement and Rehabilitation Guidebook, Washington DC
World Bank (2001), Operational Policies: Involuntary Resettlement OP.4.12 and Annex.
World Bank Environmental and Social Frame Work 2017, Washington DC
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
57
APPENDICES
Appendix 1: MINUTES OF PUBLIC CONSULTATION MEETING ORGANIZED BY RAP
CONSULTANT FOR KOGI STATE NIGERIA EROSION AND WATERSHED
MANAGEMENT PROJECT
S/NO. AGENDA DESCRIPTION
1 Community Agassa
2 Date 26/01/2018
3 Venue Agassa LGEA community School compound
4 Time 11:50am
5 Language of
Communication
English interpreted to Ebira by Mall. Idris Saheed
6 Attendance The attendance list is as attached
7 Participants RAP Consultant and his team
RAP Field Officers and Supervisors
The Estate Surveyor & Valuer
Agassa Community Association Leaders and Members
Agassa NEWMAP Site Committee Members
Agassa Chiefs and Elders
Agassa Village/Clan Heads and Representatives
Agassa Women Leaders and Representatives
Agassa Youth Leader and Representative
Vulnerable Group
Landlords, Land Owners and Tenants Living along the corridor
8 Opening Prayer On arrival of the Consultant and his team, the people of Agassa were already
seated. The opening prayer was said by Elder Salami Ariko and the meeting
started.
9 Opening
Remarks
The RAP consultant, Dr. Femi Olaitan greeted and welcomed the people. He
introduced himself and the consulting team to the people.
10 Consultant’s
Speech
The RAP consultant, Dr. Femi Olaitan started by introducing his team and
thanks the participants for their patience. He emphasized that NEWMAP
project is aimed at making the environment a better place for everybody
through control of erosion site in all the communities. He also said that his civil
works may affect shops, economic trees, buildings and properties along the
corridor of the Erosion Gully. He also stated that government will assist in
reconstructing any affected properties. Hence, the Resettlement Action Plan
(RAP) will beg for the cooperation of the people to make the work a success.
The consultant also informed them that any other improvement on the affected
properties after evaluation will not be considered for compensation.
11 Consultant’s
Questions and
Responses from
Community Members
The following basic questions were asked by the consultant
Question 1: Please can you give us a brief history of the erosion site including
its cause?
Response:
▪ Yakubu Bello said that when he was growing up, the erosion was still
small but now it has increased leading to loss of lives. He said the erosion
was as a result of flood from the hill side which flows down to the
community thereby causing havoc and continuously widening down to the
river.
▪ Yusuf Momoh said heavy flood flows down from the top part of the
community, widening the gully and increasing its menace. He was a victim
of this menace as he lost his house to flood even after spending a lot to
procure trips of stone to stop the menace and no one came to his rescue.
Question 2: Are you aware of the proposed NEWMAP intervention?
Response: The community said Yes
Question 3: Are the people of the community happy with the project?
Response: Yes
Question 4: Are you willing to support the project to its completion?
Response: They responded Yes
Question 5: Do you believe you are the ones to benefit from this project?
Response: They answered Yes
Question 6: What would the community do to person(s) that would want to
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
58
stop this project?
Responses:
▪ Mr. Sunday E. Sanni said they will banish him from town.
▪ Mr. Yusuf Momoh said they will report such person to the community
leaders who will rebuke the person.
▪ Salami Ismaila said they will set up a vigilante group that will protect the
worker/team.
▪ Mr. Enemo Ajayi said they will mobilize themselves in prayers and commit
such persons to God.
Question 7: What kind of challenges including resistance from local people do
you think NEWMAP including their consultants and contractors might face
during the project implementation (construction and operation)?
Response:
▪ Mr. Yusuf Oseni said one of the challenges that the contractors might face
is if the civil work starts without proper compensation/resettlement of
people whose assets might be destroyed as the project is being done.
Question 8: Is there any dispute in the community that may stall the project?
Responses: They replied No
Question 9: What are the existing dispute settlement instruments in the
community?
Responses: Mrs. Salihu Kadijat said they have traditional leaders and chiefs
who they report matters to and they resolve it amicably.
Question 10: Are you concerned that this project may not be completed?
Responses:
▪ Mrs. Oseni Fati said they are entertaining fear because when such projects
start they are not always completed, she cited some project like rural
electricity and borehole project in the community.
▪ Mr. Yusuf Oseni said he believes in the project
12 Comments,
Questions and
Answers
Question 1: Mr. David Aroke asked for clarification on how the capturing for
PAP (Project Affected Person) will be carried out?
Response:
The Consultant responded by saying that it is only those whose assets are along
the project corridor which might be affected are those qualified to be captured
with the asset they are claiming for compensation. He said adequate
information and sensitization will be made before the enumeration starts so
that the rightful owners of the assets will be aware of what is going on, as there
is no room for representation.
13 FGD There was an in-depth Focal Group Discussion concurrently for the
Elders/Men, women, and youth, in order to ascertain their own opinion,
concerns, support and interest on the intervention. There was group
photograph after the FGD.
14 Vote of
Thanks/Closing
Remark
Mr. Saeed Idris, the Community Association chairman thanked the
Consultant, his team members, KSG-NEWMAP, Federal Government of
Nigeria and World Bank for their intervention because flood has always been a
perennial problem and its effect has been devastating on the community he
stated. He promised that they will support the project. He prayed for God’s
blessings on all partners involved in NEWMAP work and wished the
consultant and his team journey mercies.
15 Closing Prayer Closing Prayer was said by Mallam Momoh Isa
16 Field Officers Mr. Muhammed Jamiu Muhammed
Mr. Abbas Suleiman
Omeiza Onivehu
Mr. Matthew Yakubu Onuvava
Mr. Obenege Suleiman
Dr. (Mrs) Ngozi Johnson
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
59
Appendix 2: FOCAL GROUP DISCUSSION (FGD)
An in-depth Focal Group Discussion (FGD) was held after the consultation with the elders, men, women
and youths of Agassa Community to ascertain the specific concerns about the intervention project.
The result of the FGD meeting is summarised below:
SUMMARY OF FOCAL GROUP DISCUSSION
Category of People Questions from Consultant and
His Team
Responses from the Community
Members.
Elders/Men of Agassa
Community
Do we have existing shrine that
this project is likely to affect
Elder Salami Airkochunu answered yes
and he called Ahachi - aba at AgassaUvete.
He said that relocation may not be
applicable as there is no physical object to
be relocated aside water body, but noted
that appeasement of the god may be
inevitable after due consultation with the
custodian.
Do Elders accept the project. Another elder, Ismaila Umar, responded
in affirmation after they all echoed yes.
The consultant expressed his joy saying
that with this responses men and
equipment on site will be saved.
Is there any graveyard within the
erosion corridor.
There was confusion after some silence as
regards if any, but eventually the Erosion
committee Chairman, Mallam Saeed Idris
confirmed one from the family of
Abdulazeez.
Do you have any concern as
regards how well you think the
project should be executed
Abdulkarim Ajayi expressed fears on
whether the people from the area will be
engaged. He advised that the contractor
should engage the people from the area
and ensure that qualitative work is done.
What particular role will men
played in the project
Hon. Abdulkarim Ajayi said that, the men
will be very much on ground to monitor
and help the contractor in any way
possible. He advice that due to the ability
of the erosion to separate families and
communities, bridges and walkways should
be constructed
What tradition or cultural
prohibitions do you want us to
know about.
Elder Salami Arikochunu, mention that
some of the community prohibitions
includes going near their wives and
daughters without their consent. Women
worker are not allow to witness all the right
masquerade festivals and men stranger
should avoid participation in the Echane
festival in order not to be beaten up.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
60
Who should be the recipient of
the claim in case of
compensations
Mallam Yakubu O. Zubair said that the
head of the house is entitled to the claim
on behalf of the household but in case of
death, his eldest child will be entitled to
the claim.
The consultant thanks the
elders for their patience and
understanding
Women of Agassa Are you aware that NEWMAP
intervention project is coming to
Agassa
They chorused Yes. Mama Awawu
Sumaila said they are patiently waiting
Do you all like the project Yakubu Bilikis said Yes
Do you think the project will
benefits you all
They all chorused Yes and Yakubu Bilikis
added that they are patiently waiting and
praying
What would be your
contributions
We are praying and prepared to support
the project in any possible way particularly
by cooking food for them to buy so as to
prevent them from going too far to get
food
Is there any dispute in the
community that is likely to
hinder the project execution
They all echoed no
Is the community willing to take
the ownership and ensure it
completion
They all said Yes
What will you recommend to
ensure smooth completion of
the project
Mama Awawu Sumaila said that they are
already working towards making the
project a successful one by stopping
people from dumping refuse on the
erosion site. She advised the contractor to
provide refuse dump site and incinerator
for proper refuse disposer.
The consultant, thank the
women for their understanding.
Youth of Agassa Are the youths aware of the
oncoming project in Agassa
They all said yes and Yakubu O. Zubair
said very well
Are you willing to support the
project.
Obaro Nasiru, said Yes
Are you ready to secure the
human and equipment
Muhammed Jamiu Muhammed said Yes
What particular role will the
youth played during the project
executive
We will make sure that the human and
equipment of the contractor are safe and
prepared to work with them, said Tijani
Abdulsalam
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
61
What in your own thinking can
cause trouble between you and
the contractor
Asuku Jamiu said, giving work that
members of the community can handle to
other people outside our community can
cause trouble. Another issue that can cause
problem is when the contractor refuses to
pay wages and salaries as and when due
There was observation from
Saka Itopa Dahiru, the site
committee Chairman observed
that, their youth should be
engaged in carrying out the
project.
The consultant Dr. Femi
Olaitan expresses his gratitude
to the entire community
members for their patience,
understanding and cooperation.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
66
Appendix 2a
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
67
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
68
APPENDIX 2c
APPENDIX 2B RESETTLEMENT ACTION PLAN (RAP) FOR AGASSA EROSION SITES
SOCIO-ECONOMIC SURVEY QUESTIONNAIRE
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
69
Appendix 3: Safeguard Instruments Prepared for the Proposed Works
S/No. Safeguard
Instrument
Focus Remarks
1.
Environmental
and Social
Management
Frameworks
(ESMF)
Used as a practical tool during program formulation, design,
implementation and monitoring.
Describes the steps involved in identifying and mitigating the
potential adverse environmental and social impacts of future
investment activities.
Provides guidance in cases where the screening results indicate
that a separate Environmental and Social Impact Assessment
(ESIA) or an Environmental Management Plan is required.
the ESMP
prepared with this
Triggered along
with RAP
2
Resettlement
Policy
Framework
(RPF)
Provides the direction to all actors involved in sub-projects
implementation, for the identification of resettlement implications
and measures to adopt to minimize or address resettlement issues
created by each sub-project.
Set out the policies, principles, institutional arrangements,
schedules and indicative budgets that will take care of any
anticipated resettlements. The arrangements ensure that there is a
systematic process (as against an hoc one) for the different stages
of the implementation of a framework that assures participation
of affected persons, involvement of relevant institutions and
stakeholders, adherence to both World Bank and Government
procedures and requirements, and outline compensation for
affected persons.
Provides the framework within which Resettlement Action Plans!
Resettlement Action Plans are developed when the project is
certain of the locations and specific impacts of the sub-projects.
Contains a screening /checklist for determining whether WB OP
4.12 is triggered or not it also provides procedures and guidelines
to be followed when the policy is triggered. That is. contains a
practical tool (e.g. screening checklist) to guide the preparation of
Resettlement Action Plans (RAP) for sub-projects during the
implementation of the comprehensive programme.
Triggered this
Standalone
Resettlement
Action
Plan in relation to
the proposed
works
3
Environmental
& Social
Screening &
Scoping
Screening—
• First step in the initial assessment of the possible
environmental impacts of the proposed project.
• The purpose of the environmental/social screening is to
identify if the road rehabilitation project requires an ESIA
through the elimination of irrelevant environmental issues
and focusing on potentially significant issues at the planning
and design stages.
Scoping
• Assist to identify the Issues that are likely of most importance
during the ESIA and eliminates those that are of little
concern;
• Appropriate time and space boundaries of the ESIA study;
• Information necessary for decision-making; and, Significant
effects and factors to be studied in detail
• Critical step in the preparation of an in determining the terms
of reference (TOR) of the ESIA/ESMP.
Defined the level
of impacts and
thus the
ESIA
4
Environmental
and Social
Impact
Assessment
(ESIA)/ESMP
Ensures sustainable development and/or to ensures compliance
with local, regional and international regulations relating to
environmental protection and conservation.
Provides framework for gathering and documenting information
and views on the environmental consequences of activities so
that the importance of the effects and the scope of enhancing,
modifying and mitigating them can be properly evaluated
ESMP is being
currently prepared
along with this
RAP
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
70
Appendix 4: Approach/Methodology of RAP Preparation
Approach/Methodology of RAP Preparation.
The strategy/methodology for the preparation of the RAP took into cognisance the Terms of Reference
and/Scope of Work defined in the Request for Proposals for this RAP. This RAP was prepared in
accordance with applicable World Bank safeguard policies and Nigerian Land Use Act.
The distinct phases for preparing the proposed RAP include: Literature review; Public Consultation, Data
Gathering, Inventory of affected assets, census of project affected persons, valuation of assets and
quantification of compensation. Also, the study assessed the capacity of SPMU and other implementing
institutions.
1. Literature Review
A review of the relevant literature was carried out with a view to gaining a further and deeper
understanding of the project and the social conditions that exist along the gully corridors and the
communities buffering the targeted area generally. This included reviewing the Project-specific.
Background documents such as:
• Environmental and Social Management Framework
• Resettlement Policy Framework
• NEWMAP Project Appraisal Document (PAD);
• NEWMAP Project Implementation Manual (PIM)
• World Bank safeguards policies
• Intervention design - Detailed engineering designs and high resolution digital imagery for the site,
complimented by the deployment of Differential Geographic Positioning System(GPS) on ground to
obtain spatial data. Other relevant documents were also reviewed such as recent World Bank projects in
and elsewhere (other countries) where there have been resettlements and affected populations as their
potentially is under the NEWMAP project, publications on land acquisition, compensation that bears
relevance to the RAP, United Nations (2006) Human Development Report, National Bureau of Statistics
(2009) Social Statistics in Nigeria, Nigeria Land use Act and other National laws, World Bank
Operational Policies, etc.
2. Stakeholders/Public Consultation
Stakeholders, for the purpose of this project, were defined as all those people and institutions that have
interests in the planning and execution of the project. This includes those positively and negatively
affected by the project.
The local community participated in the design of the subproject and the choices made along the way
through their assistance with the provision of historical background on the watershed, the gully erosion
formation, and storm water flow challenges as well as local efforts to manage the situations, etc.
Several discussions and meetings were held in the field and off the field with relevant stakeholders,
especially with project affected persons, individuals, community leaders, and the local government
officials to seek their opinion on the resettlement issues and the impact of the project. The essence was to
ensure a broad-based partnership for achieving harmonious working relationship for implementing and
monitoring the project with successful outcomes.
Different methods of communication to reach the stakeholders included face to face meeting, telephones
and e-mails in order to identify the left out PAPs, assess the situation and thus develop appropriate
compensation mechanism.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
71
3 Data Gathering (Field Work)
The data gathering involve visits to various government offices at federal and state levels, private libraries,
internet searches, etc. to obtain relevant information.
A spatial analysis of the features along the gully corridor was carried out with physical assessment and
measurement supported with the aid of Geographical Information System (GIS), complimented by the
deployment of Differential Geographic Positioning System(GPS) on ground to obtain spatial data. The
corridor was directly obtained on ground with the Differential GPS with the gully shoulders/offset from
the edges with a setback of 5meters. These were then plotted directly to obtain the Corridor Map of
Agassa as indicated for the affected assets. This enabled identification and physical count of the features
that falls within each buffer ring categories as shown.
As a point of emphasis, for the purpose of planning, a 5-meter setback of offset from the gully edge was
used for the alignment as the areas of impact as made known by the Engineering Specialist. During
project implementation and when the final design is ready, it is expected that the population should be
kept informed as plans evolved and, when the final design is ready. The affected area should be marked
off with pickets or flags before actually engineering work at the site.
The field work also included socio-economic survey, census of potential project affected persons, etc.
Based on the engineering design for the proposed action, a detailed household census and inventory of
fixed assets was carried out within the polygon affected by the proposed project works, with a survey of
each household, farm business affected by the project, including temporary structures such as kiosks or
squatters’ shacks.
Furthermore, detailed information on the families, kin groups, business employees and others who
occupy or use the land for their livelihood were collected including basic demographic data on age, sex,
occupation, livelihood, income, educational level, and preference for resettlement.
The inventory of assets included the size and construction of dwellings, other buildings, wells and other
infrastructure such as fencing, permanent crops such as fruit trees. Each structure was geo-referenced and
located on a map.
As much as possible, public infrastructure were recorded and mapped together with information on the
catchment areas of people who frequent these institutions.
In addition to the census and inventory of assets, the responsible team will carry out socioeconomic
assessment of the affected community or communities. Among the topics that should be investigated are
economic and ethnic differences within the community, the livelihoods of the affected people, the social
ties that bind the community together (such as kinship, friendship, ethnic ties, debt-credit relationships),
conflicts within the community and with other communities, and other pertinent social characteristics that
characterize the affected community.
The analysis should focus on how the sub-project will impact on the community and also how these
features of local society can be mobilized to implement the program in the best possible way. It was
considered necessary to identify vulnerable people who may need additional support such as widows,
orphans, female-headed households, the elderly, persons with disabilities, etc. Regardless of the form of
compensation adopted, special consideration needs to be given to vulnerable people who lack an
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
72
alternative means of social support. This requires the presence of social specialists on the scene, before,
during and after the actual move to ensure that some people are not driven back into poverty and misery.
Final Copy of Resettlement Action Plan for Agassa Gully Erosion Site
Plate 1: Some enumeration exercise with members of the Community 4 Cut-off Date
The Census cut-off date refers to the date after which PAPs will NOT be considered eligible for
compensation, i.e. they are not included in the list of PAPs as defined before the socio-economic survey
of the PAPs ended.
At the conclusion of the census, the cut-off date was declared on December 10, 2017, after which no
newly arrived persons or families will be eligible for resettlement benefits. In addition, improvements to
housing etc. made after the date will not be eligible for compensation (repairs, such as fixing a leaky roof,
are permissible). The cut-off date was announced and made known through appropriate traditional
means of reaching-out during the community awareness campaigns at site level and through the local
government.
The cut-off date was intended to prevent speculation and rent-seeking in order to become eligible for
additional resettlement benefits. This is especially more so bearing in mind the time period between the
cut-off date and the time actual productive investments would start, and that only after PAPs have been
compensated according to the requirements of this RAP. Nevertheless, if the project is not initiated
before two years elapsed after declaration of a cut-off date, an updated census and evaluation of
properties/assets must be carried out.
5 Eligibility Matrix Construction
Based on the data collected, an eligibility matrix that matches different categories of displaced people or
land losses with specific entitlements designed to compensate people for losses caused by project works
was constructed.
6 Damage and Loss Assessment (DaLA)
To assess damage and losses of economic assets identified, the Damage and Loss Assessment (DaLA)
Methodology was adopted. DaLA is a flexible, comprehensive damage and loss assessment
methodological tool presently used by the World Bank for the estimation of overall impacts such as that
caused by disaster. The tool which captures the closest approximation of damage and losses is in line with
World Bank Op 4.12 provisions on involuntary resettlement.
The DaLA Methodology bases its assessments on the overall economy of the affected area. It uses the
national/location accounts and statistics as baseline data to assess damage and loss. It also factors on the
impact of disasters on individual livelihoods and incomes to fully define the needs for recovery and
reconstruction.
The tool analyses three main aspects:
• Damage (direct impact) refers to the impact on assets, stock, and property, valued at agreed
replacement (not reconstruction) unit prices. The assessment should consider the level of damage
(whether an asset can be rehabilitated/repaired, or has been completely destroyed).
• Losses (indirect impact) refer to flows that will be affected, such as reduced incomes, increased
expenditures, etc. over the time period until the assets are recovered. These will be quantified at present
value. The definition of the time period is critical. If the recovery takes longer than expected, losses might
increase significantly.
• Economic effects (sometimes called secondary impacts) include fiscal impacts, implications for GDP
growth, etc. This analysis can also be applied at sub-national level.
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
73
Appendix 4.1:
Analysis of Socio-economic background of PAPs shows:
PAPs Education Attainment
The level of educational attainment of PAPs indicate that 48.2% do not have formal education while 17.1
are graduates.
Table Showing Level of Education
Qualification Frequency Percentage
B.Sc./HND 7 17.5
NCE 3 7.5
ND 0 0
SSCE 6 15
FSLC 5 12.5
No Formal 19 47.5
Total 40 100
Income
The monthly income of PAPs shows that 68% earn less than N19,000.00, an indication of the level of
poverty of the PAPs.
Income (N) Frequency Percentage
0 – 19,000 27 67.5
20,000 – 39,000 3 7.5
40,000 – 59,000 4 10
60,000 – 89,000 5 12.5
90,000 and above 1 2.5
Total 40 100
020406080
100120
Educational Level
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
74
Gender
In terms of gender distribution, 85% of the PAPs are males while 15% are females
GENDER FREQUENCY PERCENTAGE
Female 6 15
Male 34 85
Total 40 100
0 –19,000
20,000 –39,000
40,000 –59,000
60,000 –89,000
90,000and
above
Total
67.5
7.5 10 12.52.5
100
PERCENTAGE INCOME DISTRIBUTION
Gender
Female
Male
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
75
Occupation
PAPs are generally engaged in productive occupations and spread in diverse professions indicated below
Occupation Frequency Percentage
Trader 10 25
Retiree 4 10
Civil Servant 6 15
Schooling 2 5
Engineer 1 2.5
Farmer 14 35
Teacher 2 5
Tailoring 1 2.5
Total 40 100
0
20
40
60
80
100
OCCUPATIONAL DISTRIBUTION
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
86
APPENDIX 7
Corridor Mapping of Agassa Gully Erosion Site at Okene, Kogi State
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
87
Appendix 8: List of Experts who carried out the Survey
S/N Name Phone No. /Email Address Organizational Association Position
1. Malam Idris Saeed 08062636191 Agassa Agassa Erosion Committee Chairman
2. Mal. Mohammed Jamiu 08034332978 Agassa Agassa Erosion committee Secretary
3. Zainabu Isa Agassa Agassa Erosion Committee Member
4. JimohIsah 08033916325 Agassa Rep. Member
5. Mr Omeiza Onivehu 08036820436 Lokoja c/o RAP Consultant Estate
Surveyors
6. Okonkwo Vincent Amechi 08080986336 Lagos Rep. RAP Expert
7. Arc. Suleiman Obenege 09033762756 Lokoja Dept. Of Arch. Tech. Kogi State
Polytechnic, Lokoja
Safeguard
Expert
8. Dr. Johnson Ngozi Gloria 080361466608 Lokoja Dept of Surveying &
Geoinformatics. Kogi Poly.
Lokoja
GIS &
Mapping
Specialist
9. Dr. Femi Paul Olaitan 08036794316 Lokoja RAP consultant PAPs Data
Officer
10. Prof. H. I. Jimoh 0811443900 Lokoja Social Consultants Consultation
Expert
11. Abbas Suleiman 07030939226 Okene Research Assistant R/Assistant
12. Garbson Ola 08033323995 Lokoja Computer Analyst Computer
Expert
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
88
APPENDIX 10: Engineering Design of Gully Erosion Site
APPENDIX 11: Standard Rate for Economic Trees and Cash Crops in Nigeria.
(National Technical Development Forum (NTDF) on Land Administration Harmonized Rate for
Economic Trees and Cash Crops for Compensation assessment in the Six (6) Geo-political Zones and
the Federal Capital Territory of Nigeria)
SCHEDULE A: ECONOMIC TREES
S/NO. ECONOMIC TREES MATURED
N K
IMMATURED 60%
N K
SEEDLING 60%
N K
1 Afara (Hardwood) 5,000.00 30,000.00 1,500.00
2 African Capaiba/Chiha/Softwood 2,000.00 1,200.00 600.00
3 Akinde 1,000.00 600.00 300.00
4 Alara (Hardwood) 5,000.00 3,000.00 1,500.00
5 Apple 7,000.00 4,200.00 2,100.00
6 Arere Hardwood 5,000.00 3,000.00 1,500.00
7 Ashishan/Agereshi (Hardwood) 300.00 180.00 90.00
8 Bagarwa 2,000.00 1,200.00 600.00
9 Banana/Ayaba 1,000.00 600.00 300.00
10 Baobab/kuka/lgiOse 2,000.00 1,200.00 600.00
11 Breadfruit/Dinya 1,000.00 600.00 300.00
12 Bush Mango/Ogbonno/Igiapon/
Oro/Ive
3,000.00 1,800.00 900.00
13 Cactus 2,000.00 1,200.00 600.00
14 Cashew/Yazawa 2,000.00 1,200.00 600.00
15 Cassia 400.00 240.00 120.00
16 Castor Oil Tree 500.00 300.00 150.00
17 Citus/Lemo
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
89
18 Cocoa 3,000.00 1,800.00 900.00
19 Coconut/Kwakwa (cultivated) 4,000.00 2,400.00 1200.00
20 Coconut/Kwakwa (Wild) 2,000.00 1,200.00 600.00
21 Coffee 5,000.00 3,000.00 1,500.00
22 Date PaIm/Dabino/Iko 2,000.00 1,200.00 600.00
23 Euoalyptus/Rastata 2,500.00 1,500.00 750.00
24 Fig tree/Baure 2,000.00 1,200.00 600.00
25 Giginya 2,000.00 1,200.00 600.00
26 Gmelina 4,000.00 2,400.00 1,200.00
27 Goriba 2,000.00 1,200.00 600.00
28 Grape 8,000.00 4,800.00 2,400.00
29 Guava/(Plantation) 2,000.00 1,200.00 600.00
30 Guava (W lid) 1,500.00 900.00 45.00
31 Hardwood (Others) 5,000.00 3,000.00 1,500.00
32 Idi/Isi-Oda 150.00 90.00 45.00
33 Igi Abale (Hardwood) 5,000.00 3,000.00 1,500.00
34 Igi Abas (Hardwood) 5,000.00 3,000.00 1,500.00
35 Igi Abo 300.00 180.00 90.00
36 Igi Akuku 300.00 180.00 90.00
37 Igi Apaba/Ringworm 100.00 60.00 30.00
38 Igi Egbesi 300.00 180.00 90.00
39 Igi Gagamoyin 300.00 180.00 90.00
40 Igi Iyeye 600.00 360.00 180.00
41 Igi Lapalapa 150.00 90.00 15.00
42 Igi Ode (Hardwood) 5,000.00 3,000.00 1,500.00
43 Igi Ogbigbo 300.00 180.00 90.00
44 Indian Bambool/Oparun 200.00 120.00 60.00
45 Indigo Tree/EIu 1,000.00 600.00 300.00
46 Ira 350.00 210.00 105.00
47 Iroko/kadaura (Hardwood) 5,000.00 3,000.00 1,500.00
48 Iron Tree/Hihi/Gbabaiye 5,000.00 3,000.00 1,500.00
49 Isin 500.00 300.00 150.00
50 lya/Other Softwoods 2,000.00 1,200.00 600.00
51 Jogelle/Jegelegede 2,500.00 1,500.00 750.00
52 Kirya (Hardwood) 5,000.00 3,000.00 1,500.00
53 Kolanu/Obi/Gore 3,000.00 1,800.00 900.00
54 Konkwagh 2,000.00 1,200.00 600.00
55 Lalle/Henna 1,000.00 600.00 300.00
56 Locust Bean
Tree/Doruwa/IgiIru/Dawadawa
3,000.00 1,800.00 900.00
57 Mahogany/Madachi 8,000.00 4,800.00 2,400.00
58 Mango (Plantation) 4,000.00 2,400.00 1,200.00
59 Mango (Wild) 3,000.00 1,800.00 900.00
60 Neem/Dognayaro 1,000.00 600.00 300.00
61 Obeche (Hardwood) 5,000.00 3,000.00 1,500.00
62 Ogbonno/Oro 3,000.00 1,800.00 900.00
63 Oha 500.00 300.00 150.00
64 Okro Tender /Chimbing Okro
/Ager Okoho
500.00 300.00 150.00
65 Okuku 100.00 60.00 30.00
66 Opiye (similar to Locust Beans) 3,000.00 1,800.00 900.00
67 Orange (Plantation) 4,000.00 2,400.00 1,200.00
68 Orange (Wild) 3,000.00 1,800.00 900.00
69 Oriri 600.00 360.00 180.00
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
90
70 Palm Tree/Kwara (Plantation) 3,000.00 1,800.00 900.00
71 Palm Tree/Kwara (Wild) 2,000.00 1,200.00 600.00
72 Pawpaw/Gwanda (Agric) 2,000.00 1,200.00 600.00
73 Pawpaw (Loca) 1,500.00 900.00 450.00
74 Pear (Avocardo) 4,000.00 2,400.00 1,200.00
75 Pear (Local) 2,000.00 1,200.00 600.00
76 Plantain 1,500.00 900.00 450.00
77 Raffia Palm 1,000.00 600.00 300.00
78 Rubber 1,000.00 600.00 300.00
79 Shajini (Hardwood) 5,000.00 3,000.00 1,500.00
80 Shear Butter Tree 2,000.00 1,200.00 600.00
81 Shear Nut Tree/Kadanya
82 Shediya/Odan 200.00 120.00 60.00
83 Silk Cotton/Rimi (Soft wood) 2,000.00 1,200.00 600.00
84 Sisal 2,000.00 1,200.00 600.00
85 Star Apple/Ag balumo/Udara 1,500.00 900.00 450.00
86 Teak (Hardwood) 5,000.00 3,000.00 1,500.00
87 Tsamiya 2,000.60 1,200.00 600.00
88 Umbrella Treei Tamina Katapa 1,000.00 600.00 300.00
89 Yiase (Hardwood) 5,000.00 3,000.00 1,500.00
90 Zogalle 2.50000 1,500.00 750.00
Appendix 12: Cultivated Crops
1 Acha 170,000.00 102,000.00 51,000.00
2 Bambara Nuts /Beans 180,000.00 108,000.00 54,000.00
3 Beans 150,000.00 90,000.00 45,000.00
4 Beniseed 150,000.00 90,000.00 45,000.00
5 Bitter Leaf 200.00/stand 120.00/stand 60.00/stand
6 Carrot 50,000.00 30,000.00 15,000.00
7 Cassava 150,000.00 90,000.00 45,000.00
8 Cocoyam 100,000.00 60,000.00 30,000.00
9 Cotton/Owu 120,000.00 72,000.00 36,000.00
10 Cowpeas 150,000.00 90.000.00 45,000.00
11 Garden Egg/lkon/Yalo 30,000.00 18,000.00 9,000.00
12 Ginger 50,000.00 30,000.00 15,000.00
13 Groundnut/Epa. 50,000.00 30,000.00 15,000.00
14 Ground Pears
15 Guinea Corn/Oka Baba/Tamba 80,000 .00 45,000.00 24,000.00
16 Jute/Rama/Kenaf 32,000.00 19,200.00 9,600.00
17 Maize 100,000.00 60,000.00 30,000 .00
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
91
18 Melon 100,000.00 60,000.00 30,000.00
19 Millet/Jero 100,000.00 60,000.00 30,000.00
20 Okro/Ila 35,000.00 21,000.00 10,500.00
21 Onion 50,000.00 30,000.00 15,000.00
22 Pepper 120,000.00 72,000.00 36,000.00
23 Pineapple 80,000.00 48,000.00 24,000.00
24 Potato (Irish) 100,000.00 60,000.00 30,000.00
25 Potato (Sweet) 50,000.00 30,000.00 15,000.00
26 Pumpkin 20,000.00 12,000.00 6,000.00
27 Pumpkin Leaf/Ugu 50,000.00 30,000.00 15,000.00
28 Rice (Fadama, Upland) 150,000.00 90,000.00 45,000.00
29 Sorghum 80,000.00 48,000.00 24,000.00
30 Soya beans 200,000,00 120,000.00 60,000.00
31 Spinach/Alefo 25,000.00 15,000.00 7,500.00
32 Sugar Cane 240,000.00 144,000.00 72,000.00
33 Tiger Nut/Aaya 35,000.00 21,000.00 10,500.00
34 Tobacco 20,000.00 12,000.00 6,000.00
35 Tomato 70,000.00 42,000.00 21,000.00
36 Vegetables (Cabbage, Lettuce, etc.,) 25,000.00 15,000.00 7,500.00
37 Water Melon 50,000.00 30,000.00 15,000.00
38 Water Yam/Ewura 100,000.00 60,000.00 30,000.00
39 Wheat 250,000.00 150,000.00 75,000.00
40 Yam/Isu 350,000.00 210,000.00 105,000.00
41 Ziziga 50,000.00 30,000.00 15,000.00
42 Moringa Alicafera 1000.00 500.00 250.00
X
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
94
APPENDIX 13:
LETTER OF APPEAL BY MALL. YAHAYA SULEIMAN (K GNM/AGASSA/17/004)
The Final Draft RAP Report for Agassa Gully Erosion Sites for NEWMAP, Kogi State.
95
Appendix 14: Stages in the Grievance Redress Process for the RAP
Is complainant satisfied with committee
Closure of grievance by committee
Yes
Treatment of grievance
Closure of grievance by Committee
No
Autonomous traditional/local Authority
Traditional leaders (comprising leaders of the four units)
SPMU specialist and LG Desk Officer
The Local Government Grievance Redress Desk Officer
Okene Local Government Chairman
KSG-NEWMAP SPMU (Social Safeguards officer)
KSG-NEWMAP SPMU Project Coordinator
Kogi State Honourable Commissioner for Environment
The Courts (Judicial System)
Is complainant satisfied with
committee
Closure of grievance
Yes