+ All Categories
Home > Documents > Final Report Yr3

Final Report Yr3

Date post: 02-Jun-2018
Category:
Upload: quek-yuen-xian
View: 217 times
Download: 0 times
Share this document with a friend

of 58

Transcript
  • 8/10/2019 Final Report Yr3

    1/58

    Department of Mechanical Engineering

    In collaboration with

    Department of Mechanical and Materials Engineering

    The University of Western Ontario

  • 8/10/2019 Final Report Yr3

    2/58

    ACKNOWLEDGEMENTS

    This project is a collaboration between The University of Western Ontario,

    Department of Mechanical and Materials Engineering and The National University of

    Singapore, Department of Mechanical Engineering.

    We would like to express our sincere gratitude to Prof. S. H. Winoto for

    providing guidance, supervision, consultations and support for this project.

    We would also like to appreciate Prof. Chew C. M. for his time and effort in

    answering our queries.

    We would like to thank Chris, Daniel and Malini from The University of

    Western Ontario for the patience in communicating and assistance in researching.

    Finally, the idea generation and the assembly of the various parts into a hydro

    system was a crucial aspect of this project and we would like to thank everyone who

    we had interacted with at UWO and NUS for contributing in a way or another.

  • 8/10/2019 Final Report Yr3

    3/58

    TABLE OF CONTENTS

    1.0 INTRODUCTION 1

    1.1 BACKGROUND 3

    1.2 OBJECTIVE AND SCOPE 5

    2.0 PROJECT DETAILS 7

    2.1 LITERATURE REVIEW 7

    2.1.1 OVERVIEW OF CURRENT ELECTRICITY MARKETS IN

    INDIA

    7

    2.1.2 RURAL ELECTRIFICATION IN INDIA 8

    2.1.3 A CASE STUDY OF MICRO-HYDROPOWER SYSTEM

    WHICH HAS BEEN IMPLEMENTED

    8

    2.2 POSSIBLE SITE 9

    2.3 PENSTOCK 11

    2.3.1 MINIMUM DIAMETER OF PENSTOCK 11

    2 3 2 CHOICE OF PENSTOCK 12

  • 8/10/2019 Final Report Yr3

    4/58

    3.0 PROJECT PLANNING AND MANAGEMENT 36

    3.1 NUS TEAM 363.2 UWO TEAM 37

    4.0 DISCUSSION 38

    4.1 CONVENTIONAL METHODS OF GENERATING ELECTRICITY 38

    4.2 ALTERNATIVE SOURCES OF ELECTRICITY 39

    4.3 COST OF IMPLEMENTATION 40

    5.0 CONCLUSION AND RECOMMENDATION 42

    5.1 CONCLUSION 42

    5.2 RECOMMENDATION 42

    REFERENCES 44

  • 8/10/2019 Final Report Yr3

    5/58

    LIST OF FIGURES

    Fig 1.1 Fossil Fuel Prices between 2000-2009

    Fig 2.1 Map of district of Kinnaur

    Fig 2.2 Cost ratio of different materials

    Fig 2.3 Pressure distribution in penstock

    Fig 2.4 Schematic of a Pelton turbine

    Fig 2.5 Reaction turbine

    Fig 2.6 Water jet impinging on the rotor of a Turgo turbine

    Fig 2.7 Schematic of Turgo runner blades and water jet

    Fig 2.8 Stator and rotor of a generator

    Fig 2.9 Synchronous generator

    Fig 2.10 MAGNAPLUS SERIES of synchronous AC generator

    Fig 2.11 A battery based system

    Fig 2.12 A AC-based system

    Fig 2.13 Schematic drawing of system with blown up of intake, penstock and

  • 8/10/2019 Final Report Yr3

    6/58

    LIST OF TABLES

    Table 1.1 Comparison of expenditure of resources used between year 2006 and

    2030 in United States

    Table 1.2 China renewable energy deployment targets

    Table 1.3 Comparison of carious energy sources

    Table 1.4 Load analysis

    Table 2.1 Installed electricity generation capacity between 1996-2001

    (Thousands OF MW)

    Table 2.2 Summary tables of micro-hydropower project in Long Lawen

    Table 2.3 Characteristics of mild steel, HDPE and uPVC pipes

    Table 2.4 Turbine classifications and their optimal operating requirements

    Table 2.5 Micro-hydro system recommendations

    Table 2.6 Differences between different drive systems

    Table 2.7 Advantages and disadvantages of synchronous generator with coiled

    field

  • 8/10/2019 Final Report Yr3

    7/58

    APPENDICES

    A Detailed drawings of disk of the proposed Turgo turbine

    B Detailed drawings of a spoon of the proposed Turgo turbine

    C Detailed drawings of MAGNAPLUS SERIES Model 281MCSL1502 AC

    generator

  • 8/10/2019 Final Report Yr3

    8/58

    CHAPTER 1: INTRODUCTION

    As the world shifts the emphasis from conventional energy sources to alternative

    renewable resources, there is a greater focus on the usability of renewable energy

    sources [1]. The energy acquired from renewable resources lightens the tension on

    the limited supply of fossil fuels (conventional energy sources). Due to the scarcity

    of fossil fuels, prices of such raw materials have been raising through the years as

    shown in the F ig 1 1 below [2].

  • 8/10/2019 Final Report Yr3

    9/58

    contributor to global warming. This is not just an environmental and human

    catastrophe, but could inflict massive economic damage as well. The globalproduction of three of the six largest global crops is found to be experiencing

    significant losses due to global warming between 1981 and 2002 in a study and the

    study concluded that global wheat growers lost $2.6 billion and global corn growers

    lost $1.2 billion in 2002 [4]. Fossil power will become much more expensive if risks

    related to its use are included [5].

    As a result of the raising cost, as shown in the Tab l e 1 1 above, and the

    environmental catastrophe, most countries are beginning to look for other cheaper

    and greener alternatives, especially possible sources of renewable energy within

    their countries.

    Renewable energy sources include sunlight, wind, rain, tides and geothermal. These

    renewable sources have been widely used in several countries to replace the

    conventional sources. For example, in the United States of America, hydroelectricity

  • 8/10/2019 Final Report Yr3

    10/58

    One of the most consistent and available source of energy to harness is hydroelectric

    power. It does not depend on the time of the day and is one of the most predictablesources of renewable energy. It is also one of the cheapest methods of generating

    electrical power as shown in the Tab l e 1 3 below.

    Table 1.3 Comparison of various energy sources [9]

  • 8/10/2019 Final Report Yr3

    11/58

    Bengal the first Hydro Electric Power Station was installed. It was able to generate

    power up to a capacity of 130 kiloWatt. By 17th April, 1899, thermal power was alsoutilized to generate power.

    After Indias independence in 1947, there were plans to electrify the whole of India,

    including the rural area. Legislative Acts, such as The Indian Electric Supply Act in

    1948 were put in place to provide guidelines to provide electricity to the whole of

    India [12]. Despite the extensive array of sources, others such as air electricity, solar

    electricity and cow-dung gas electricity were explored to further provide sufficient

    electricity for the nation.

    However, even after more than 60 years of independence, up to 90 percent of all

    the villages in India are still not on the grid to receive electricity. Only 25 percent of

    the houses in the whole of India have been provided with a consistent flow of

    electricity [13].

  • 8/10/2019 Final Report Yr3

    12/58

    1.2 Objectives and Scope

    The objective of the project is to design an efficient micro-hydropower system that

    can meet the power and energy requirements 20 household living in the rural area.

    Since this micro-hydro system is providing electricity for off-grid households in rural

    areas, it is assumed that each household only has basic electric appliances. Tab le

    1 4 below shows the load analyses we will use for calculating the monthly energy

    consumption of one rural household.

    Table 1.4 Load Analysis [15]

    Appliance Power

    Rating

    (Watts)

    Hours

    per Day

    Hours per

    Month

    Monthly

    (kWh)

    Four fluorescent lamps 200 8 240 48

    Colour television 100 4 120 12

    Refrigeration 300 10 300 90

  • 8/10/2019 Final Report Yr3

    13/58

    It is not practical to come up with a minimum power requirement that can power all

    the appliances in table 1.4 at the same time for use by 20 households, as this willrequire a huge system that generate excessive amount of energy. Hence a minimum

    power requirement needed to support only key appliances for use by all the 20

    household at the same time is set: lamps

    = 20020 = 4

    The designed micro-system is set to provide power above the minimum requirement

    to support more appliances to be used at the same time while taking into

    consideration not to over-exceed the energy requirement. Taking the above factors

    into consideration, a micro-hydro system that can generate power at the range of 8-

    10KW is most suitable for the design.

  • 8/10/2019 Final Report Yr3

    14/58

    CHAPTER 2: PROJECT DETAILS

    2.1 Literature Review

    2.1.1 Overview of current electricity market in India

    India is the sixth largest consumer of electricity in the world, relying on coal as the

    primary source. Having the advantage of being the third largest coal producer in the

    world, India relies heavily on thermal power plants to produce more than three

    quarters of its electricity as shown in Tab l e 2 1 .

    Table 2.1 Installed electricity generation capacity, 1996-2001 (thousands of MW) [16]

    1996 1997 1998 1999 2000 2001

    Hydroelectric 20.99 21.10 21.89 22.44 24.50 25.14

    Nuclear 2.23 2.23 2.23 2.23 2.23 2.86

    G h l/S l 0 55 0 82 0 93 1 02 1 08 1 27

  • 8/10/2019 Final Report Yr3

    15/58

    subsidy given to the agriculture sectors and the electricity supplied to irrigation is not

    metered leading to wastage and theft.Therefore, India, like many developing countries, cannot afford to construct new

    plants to increase the electricity capacity to meet the growing demand.

    2.1.2 Rural electrification in India

    Rural electricity supply in India has been lagging in terms of hours of supply. Only

    31% of the rural households have access to electricity and they face the same

    problems as industries which are mentioned earlier like frequent blackouts and high

    fluctuation of voltage and frequency.

    There are several reasons why less than 50% of the rural households are supplied

    with electricity. Firstly, some of the rural households are located at very isolated

    areas where transmission and distribution to these households are not economical.

    Furthermore, the tariffs for households and agriculture are generally well below

    actual supply costs about 26% [18]. Assuming that these rural households are

  • 8/10/2019 Final Report Yr3

    16/58

    which the team set at the start of the project. A summary table, Tab l e 2 2 is done

    and it serves as a reference for our team when designing the system.

    Table 2.2 Summary table of micro-hydropower project in Long Lawen village

    Parameters Description

    Implementation cost of Project $53,428.00

    Households to be served 40 in 1999 (planning stage)70 in 2002 (commissioning of

    project)

    Head 32m

    Flow rate 70liters/s to 500 liters/s

    Turbine used Crossflow impulse turbine

    Generator Synchronous installed in a

    single phase arrangement

    Output Power 8.2kW

  • 8/10/2019 Final Report Yr3

    17/58

  • 8/10/2019 Final Report Yr3

    18/58

    nce the minimum potential power is much higher than the required power, this siteis viable for the construction of a micro-hydro system.

    2.3 Penstock

    2.3.1 Minimum Diameter of Penstock

    In this section of the report, the minimum diameter of the penstock which is

    constructed by pipes will be determined. The calculations of the diameter will be

    based on the requirements of the turbine used.

    According to Fox, McDonald and Pritchard [22],

    (DjD

    )4 = D2fL

    ,

    h D di f j D Di f k

  • 8/10/2019 Final Report Yr3

    19/58

    To operate the turbine selected efficiently, a net head of 32m is required. Gross

    head required will therefore be 38m as the frictional loss by the penstock shouldonly be 10-15% of the gross head.

    With dimensions above, the minimum diameter of the penstock is 66.6mm. As such,

    a 100mm penstock will be used.

    2.3.2 Choice of penstock

    Tab l e 2 3 below shows the comparison between three of the most common

    materials used in penstock piping.

    Table 2.3 Characteristics of Mild Steel, HDPE and uPVC pipes [23]

    Material Friction Weight Corrosion Jointing Pressure

    Mild steel

  • 8/10/2019 Final Report Yr3

    20/58

    mild steel will be more expensive as weight is a major determinant in the

    transportation cost. Being heavier implies that more trips will have to be made totransport the same length of pipes required, thus higher cost.

  • 8/10/2019 Final Report Yr3

    21/58

    Pressure

    This pressure is dependent on the net head of the penstock. As shown in the F ig

    2 3 below, the maximum pressure will occur at the nozzle. For most penstock pipes,

    there is a build in safety factor of 1.5 - 2.5 [26]. Hence, for most of the materials, it

    is safe to assume that they will have the ability to withstand the pressure so long as

    they meet the system head requirement.

  • 8/10/2019 Final Report Yr3

    22/58

    2.4 Turbines

    Turbines can be broadly classified into two types, denoted as impulse and reaction

    shown in Tab l e 2 4 .

    Table 2.4 Turbine Classification and their optimal operating requirements [27]

    Turbinerunner

    High Head

    (>1000m)

    Medium head

    (20 to 100m)

    Low Head

    (5 to 20m)

    Ultra- lowHead

    (

  • 8/10/2019 Final Report Yr3

    23/58

    For reaction turbine, it consists of fixed guide vanes called stay vanes, adjustableguide vanes called wicket gates and rotating blades called runner blades as shown in

    F ig 2 5 . Water of high pressure will follow the spiral casing (volute) and flow

    towards the runner by the stay vanes and passes through the wicket gates at high

    tangential velocity. This briefly explains how the energy of the water is transferred

    to the shaft.

  • 8/10/2019 Final Report Yr3

    24/58

    to the turbine to produce power during seasons of low flow rate to ensure steady

    generation of energy throughout the year.For impulse turbine, adjustments to variations in stream flow can be done easily by

    changing the nozzle sizes or by using adjustable nozzles. It is much more difficult to

    make adjustments to variable water flow for small reaction turbines due to the high

    cost of variable guide vanes and blades.

    Mechanical factors

    Maintenance of micro-hydropower systems is necessary throughout its life-cycle. It is

    important to have a system that has low maintenance cost for the users in the rural

    area. Although excessive slit or sand in the water may cause excessively wear and

    tear on the runner of most reaction turbines, the maintenance cost of an impulse

    turbine is less than that for a reaction turbine as they are free of cavitations

    problems [29]. Impulse turbine like Turgo turbine also facilitates easy inspection and

    repairs as only the top half of the Turbine needs to be removed. Such processes are

  • 8/10/2019 Final Report Yr3

    25/58

    However as micro-hydro system design aims to be implemented in different rural

    areas of developing countries in Asia, there is a need to specify a range of head andflow rate that most terrain and rivers can satisfy to ensure this design can be

    implemented in other areas other than the site mentioned in Section 2.2. If the

    design targets turbines that can operate efficiently at low head, a large flow rate

    would be needed to generate the power we need which may not be feasible for

    many rivers. A high head of above 100m is also not easily available in most terrains.Taking the above factors into consideration, turbines that can operate at an optimal

    efficiency at a mid-range head of between 20-100m are preferred. These

    considerations help narrow down on the choice of turbines based on Tab l e 2 4

    2.4.2 Choice of turbine

    From the list of impulse turbines in Tab l e 2 4 , Pelton and Turgo turbines are most

    commonly used in micro-hydropower system. After a comparison between the two

    types of turbines, Turgo turbine is chosen as the most suitable turbine for the micro-

  • 8/10/2019 Final Report Yr3

    26/58

    Table 2.5 Micro-hydro system recommendations

    Turgo runner is effectively a Pelton runner split down the middle. Hence, it can

  • 8/10/2019 Final Report Yr3

    27/58

    Operation of Turgo Turbine

    Fig 2.6 Water jet impinging on the rotor of a Turgo turbine [32].

  • 8/10/2019 Final Report Yr3

    28/58

    The Turgo runner is a cast wheel whose profile resembles a fan blade that is closed

    on the outer edges. The water jet is directed on one side, slides across the bladesand exits on the other side. Hence, the exiting water jet leaving the blades does not

    interfere with other blades and thus gives it the ability to handle a greater water

    flow.

    Specification of Turgo Turbine

    For this design, we are using a Turgo turbine working at 32m head 8kW with 24

    plastic spoons. This turbine is offered in the market at an affordable price of US$240

    and meets the power requirement of the project. It has a stainless hub and 33%

    glass fiber reinforced nylon spoons. [34] It has a relatively small dimension that can

    easily fit into our system. Detailed drawings of the turbine are shown in Append i x

    A and Append i x B .

  • 8/10/2019 Final Report Yr3

    29/58

    The shaft of the generator can be driven by different systems, which is the linkagebetween the turbine and the generator shaft. The differences are illustrated in

    Tab l e 2 6 below.

    Table 2.6 Differences between drive systems.

    Drive system Pros ConsDirect Drive Low maintenance, high

    efficiency, low cost.

    Speed of generator shaft

    must be compatible to

    turbine speed

    Wedge Belts Shafts need not be axially

    aligned, long service life.

    Will slip and creep.

    Should not be used with

    synchronous speed.

    Timing Belts Clean-running and high

    efficiency of up to 98%

    Costly and require high

    accurate alignment of the

    pulley [35].

    Gearbox Suitable for larger High maintenance cost.

  • 8/10/2019 Final Report Yr3

    30/58

    Fig 2.9 Synchronous generator

    Synchronous generator can be further classified into two different types, namely the

    permanent magnet synchronous and synchronous with coiled field. Both these

    system types have their advantages and disadvantages. Tab l e 2 7 and Tab l e 2 8

    below will indicate their respective strengths and weaknesses; this will aid the users

  • 8/10/2019 Final Report Yr3

    31/58

    Table 2.8 Advantages and disadvantages of synchronous generator with permanent magnet

    Synchronous with permanent magnet

    Advantages Disadvantages

    Simple and robust

    Reliable

    No slipping rings

    Low cost and maintenance

    Small and lightweight

    High power coefficient

    Narrow speed range

    Replacing large magnets are

    costly

    Low cost and frequency of maintenance are the primary concerns in deciding the

    choice of the generator type. Synchronous generator, as shown above in the table,

    has low cost and free from maintenance because it avoided the use of slip rings.

    In terms of design, the permanent magnetic generator is lighter in weight and

    smaller in size in relative to its coiled counterpart. This will allow users to install and

    transport our hydro system easily in rural India, which could present accessibility

  • 8/10/2019 Final Report Yr3

    32/58

    Table 2.9 Advantages and disadvantages of a squirrel caged induction generator

    Squirrel caged induction generator

    Advantages Disadvantages

    Simple in design and reliable

    No slip rings and brushes

    Low cost and maintenance

    Flat torque

    rugged

    Low efficiency

    Low power coefficient

    Narrow speed range

    Table 2.10 Advantages and disadvantages of an induction generator with coiled rotor [37]

    Induction generator with coiled rotor

    Advantages Disadvantages

    Wide range of speed

    No slipping rings and brushes

    Rugged

    complex structure

    low power coefficient

    unstable torque generator, also

    known as wavy torque

    high cost

  • 8/10/2019 Final Report Yr3

    33/58

    for smaller capacities. Our system will be required to generate 140KWH of

    electricity per day for a total of 20 households, thus it can no longer be

    considered a small capacity. A synchronous generator is more suitable in this

    case.

    2. Excitation: Electrical excitation of synchronous generators requires coils for

    exciting field while asynchronous generators do not need any coils forexcitation. This is because the necessary power for excitation of the armature

    coils is drawn from the power network or capacitor bank. The synchronous

    generators with permanent magnet are also free from exciting coils, which

    clearly is a huge advantage.

    3. Independent Operation: Synchronous generators can be utilized

    independently while the operations of asynchronous ones need to be fed with

    an exciting current from the power network or a capacitor bank.

  • 8/10/2019 Final Report Yr3

    34/58

    voltage before connection to the network and this necessitates consideration

    of any drop in the network.

    7. Power Coefficient: The power coefficient of a synchronous generator

    is higher compared to an asynchronous generator. The standard power factor

    of the synchronous generator is 90% of the front phase, and for

    asynchronous generator, the power factor is determined within 5% to 90% of

    the rear phase [39].

    8. Cost: Synchronous generators with permanent magnets are cheaper than an

    asynchronous generator if the power generated is expected to be less than750 KW. The price of a 600 KW induction generator is USD$ 263,000

    compared to USD$ 223,000 for a permanent magnet synchronous generator

    with similar power rating.

  • 8/10/2019 Final Report Yr3

    35/58

    Fig 2.10 MAGNAPLUS series of synchronous AC generator

    Table 2.11 Specifications of Model 281MCSL1502

    Voltage 240V

    Phase 3

  • 8/10/2019 Final Report Yr3

    36/58

    no energy loss through turbine

    Assumptions

    no energy loss through generator

    assume constant river flow for the system to operate 24 hours

    = 7 20 = 140 24 = 3360 ,

    = 8 360024 = 691200 ,

  • 8/10/2019 Final Report Yr3

    37/58

    2.6 DISTRIBUTION AND TRANSMISSION OF ELECTRICITY TO VILLAGE

    The considerations that we had in the type of micro-hydropower system we chose

    depended on the capacity, the anticipated power demand and the profile of your site.

    Another deciding factor is that our generator is an off grid, remote stand-alone

    system.

    The reason why we chose off-grid system instead of on-grid system is because we

    want our hydro generator to be able to be implemented in any areas with

    rivers/streams of constant water flow throughout the year. Also, most of the rural

    remote areas in India are not supplied by grid electricity.

    There are two types of off-grid micro-hydropower systems, namely battery-based

    and AC-direct.

    2.6.1 Battery-based

  • 8/10/2019 Final Report Yr3

    38/58

    combined with other energy sources, such as wind generators and solar-electric

    arrays, if the stream is seasonal. Also, a battery bank provides a way to store

    surplus energy when more is being produced than consumed [40].

    Disadvantages

    The modeling of battery is a complex task as its parameters varies with the mode ofoperation (charging and discharging mode). The control system is also complex and

    requires deep electrical engineering knowledge. There is also a need for more

    maintenance on the battery component, such as replacing the batteries after

    prolonged charging and discharging.

  • 8/10/2019 Final Report Yr3

    39/58

    generator that produces AC output at 120 or 240 volts, which can be sent directly to

    standard household loads. The system is controlled by diverting energy in excess of

    load requirements to dump loads, such as water- or air-heating elements. This

    technique keeps the total load on the generator constant. AC-direct system can be

    illustrated in F ig 2 12 below.

  • 8/10/2019 Final Report Yr3

    40/58

    2.6.3 Choice of micro-hydropower system

    Our choice of system will be AC-direct. Our stream is of enough potential and not

    seasonal in nature, hence we do not need to worry about non-consistent power

    supply and storing the additional power for future use. Therefore, we do not need to

    waste extra funding and time to design a battery-based system, when AC-direct is

    more than suitable. Lastly, ac-direct system requires much less maintenancecompared to battery based system, where the batteries need to be replaced after

    prolonged charging and discharging.

  • 8/10/2019 Final Report Yr3

    41/58

    34

    2.7 OVERALL SYSTEM

    F ig 2 13 shows how the system will look like after construction. The different components of the system will be explained in

    Tab le 2 12 .

    Fig 2.13 Schematic drawing of system with blown up of the intake, penstock and powerhouse

    Blown up of intake

    Blown up ofpenstock

    Blown up of powerhouse which

    housed the turbineand generator

    1

    2 &3

    4

  • 8/10/2019 Final Report Yr3

    42/58

    35

    Table 2.12 Description of Components

    s/n Component Description

    1 Intake Metal sheets will be used to guide water into the intake. To prevent debris and sediments to

    enter the penstock, a wire mesh and a filter will be used. Wire mesh will be placed at the outer

    layer of the intake to trap debris and the filter will be placed before the penstock entrance to

    trap fine sediment.

    2 Turbine Turbine is used to convert mechanical energy of water to electrical energy which will be

    distributed to the village. Water from the penstock will flow through a nozzle and hit the spoons

    of the Turgo turbine causing the disk to rotate activating the generator.

    3 Generator The mechanical energy harnessed from the turbine system will drive the generator shaft, which

    causes the rotor of the generator to cut through the varying magnetic field line created by the

    permanent magnet. This change in the magnetic field will induce a current, which is an ACcurrent in our system.

    4 Off-Grid AC-Direct system A micro-hydropower off-grid AC-direct system does not have battery storage, so the system is

    designed to supply the load directly. This consists of a turbine generator that produces AC

    output at 120 60Hz, which can be sent directly to standard household loads.

  • 8/10/2019 Final Report Yr3

    43/58

    36

    CHAPTER 3: PROJECT PLANNING AND MANAGEMENT

    Progress of our project and UWOs proposal are noted down in Gantt charts shown in Tab le 3 1 and Tab le 3 2 respectively.

    3.1 NUS TEAM

    NUS/UWO Capstone Proposed Project Schedule

    NUS REPORT TARGETS Proposed by the UWO team 10/03/2011

    Table 3.1 Gantt chart of NUS Team

    List of Activties Planned Actual % Status

    Start Dur Start Dur Done 1 2 3 4 5 6 7 8

    NUS Report Due 1 7 1 7 100% Research on location 1 1 1 2 100% Research on Turbine 1 1 2 3 100% Research on Generator 1 3 2 4 100% Costing Issue 3 1 3 4 100% Parameter Calculation of turbine 3 2 3 4 100%

    Research on financial feasibilty 3 1 3 4 100%

    Week 1 was the week of Monday, September 19th, 2011

  • 8/10/2019 Final Report Yr3

    44/58

    37

    3.2 UWO TEAM

    NUS/UWO Capstone Proposed Project Schedule

    UWO PROPOSAL TARGETS Proposed by the UWO team 10/03/2011

    Table 3.2 Gantt chart of UWO Team

    List of ActivtiesPlanned Actual % Status

    Start Dur Start Dur Done 1 2 3 4 5 6 7 8

    UWO Proposal Due 1 3 1 3 100%

    Problem Definition 1 3 1 2 100%

    Background and Research 1 3 1 3 100%

    Milestone Identification 2 2 2 2 100%

    Assign Group Roles 1 1 1 1 100%

    Define Resources and Budget 1 3 1 3 100%

    Week 1 was the week of Monday, September 19th, 2011

  • 8/10/2019 Final Report Yr3

    45/58

    CHAPTER 4: DISCUSSION

    4.1 Conventional methods of generating electricity

    Table 4.1 Capital Costs per MW of Power Plants in India [41]

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    roxCapitalCostsperMW

    inMillionUSD

    Capital Costs per MW of Power Plants in India

    (Million USD)

  • 8/10/2019 Final Report Yr3

    46/58

    methods of acquiring electricity by using coal. It is not environmentally friendly as

    the process of burning coal and fuel produces a lot of carbon dioxide and other

    harmful gases that are attributing to the current climate change.

    As such, providing electricity through conventional methods is not considered in this

    proposed project.

    4.2 Alternative sources of energy

    From Tab l e 4 1 , it is clearly seen that the capital cost of producing electricity by

    water through dam-based hydro plants and small hydro plants making use of rivers

    is lower than that of nuclear, solar and wind powered plants.

    Next, the variability of constructing a dam-based hydro plant and a micro-hydro

    plant in a rural area of India with 20 households is examined.

    Firstly, the size of the hydro system is a major factor in determining the cost per unit

    of the electricity produced. In most mega-hydro systems, the infrastructure of the

  • 8/10/2019 Final Report Yr3

    47/58

    near the dams. They will need to find other lands to farm when their farmland are

    eroded and their diets might also changed due to the reduction in the fishes in their

    area.

    4.3 Cost of implementation

    Table 4.2 Cost of equipment in proposed system

    Components Cost

    Penstock $1500

    Turbine plus coupling shaft $540

    Generator $3100

    Controller* $400

    Transmission line* $500

    Powerhouse* $200

    Miscellaneous* $1200

    Installation* $2000

    Total cost $9440

  • 8/10/2019 Final Report Yr3

    48/58

    as commercial users. As such, in actual fact, the cost of electricity generated will

    exceed the initial cost even more, thus showing the efficiency of our system.

  • 8/10/2019 Final Report Yr3

    49/58

    CHAPTER 5: CONCLUSION AND RECOMMENDATIONS

    5.1 Conclusion

    After an intensive literature research, a simple micro-hydro power system has been

    proposed to be implemented in the rural areas of different countries around the

    world. Although the planning was only done on a location in Khad which is in theDistrict of Kinnaur, we are confident that such a system can be implemented in other

    rural areas of similar terrain, head and flow rate of the river.

    However, due to existing restrictions, we are not able to conduct on site testing to

    determine the actual flow rate and more accurate electricity consumption of the

    village. If given the opportunities and time, a more accurate and comprehensive

    study of the location and system can be done. These details will be further

    elaborated in the next section.

  • 8/10/2019 Final Report Yr3

    50/58

    2. Motor to be used as a generator: The possibility of using motor to

    generate electricity is not nil as motor and generator work based on the same

    theory of Faradays Laws. This can be done if the connections required are

    done correctly. However, given the mechanical background of the team, this

    task of designing a circuit board which allows motor to act as a generator can

    only be done with consultation with an experienced electrical engineer. As

    such, if given time, such method can be explored first before a decision onthe type of generator used is made.

  • 8/10/2019 Final Report Yr3

    51/58

    REFERENCES

    1. http://www.investopedia.com/terms/r/renewable_resource.asp#axzz1cZ7Fo8

    xC

    2. http://energy.gov/science-innovation/energy-sources/fossil

    3. http://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-

    High-Cost-of-Fossil-Fuels.pdf

    4. http://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-

    High-Cost-of-Fossil-Fuels.pdf

    5. http://www.awerbuch.com/shimonpages/shimondocs/VGlobal_0305.pdf

    6. http://www.umich.edu/~envst320/fossil.html

    http://www.investopedia.com/terms/r/renewable_resource.asp#axzz1cZ7Fo8xChttp://www.investopedia.com/terms/r/renewable_resource.asp#axzz1cZ7Fo8xChttp://www.investopedia.com/terms/r/renewable_resource.asp#axzz1cZ7Fo8xChttp://energy.gov/science-innovation/energy-sources/fossilhttp://energy.gov/science-innovation/energy-sources/fossilhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://www.awerbuch.com/shimonpages/shimondocs/VGlobal_0305.pdfhttp://www.awerbuch.com/shimonpages/shimondocs/VGlobal_0305.pdfhttp://www.umich.edu/~envst320/fossil.htmlhttp://www.umich.edu/~envst320/fossil.htmlhttp://www.umich.edu/~envst320/fossil.htmlhttp://www.awerbuch.com/shimonpages/shimondocs/VGlobal_0305.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://cdn.publicinterestnetwork.org/assets/5AEyj6aT4Fssg0TwPGnr4w/The-High-Cost-of-Fossil-Fuels.pdfhttp://energy.gov/science-innovation/energy-sources/fossilhttp://www.investopedia.com/terms/r/renewable_resource.asp#axzz1cZ7Fo8xChttp://www.investopedia.com/terms/r/renewable_resource.asp#axzz1cZ7Fo8xC
  • 8/10/2019 Final Report Yr3

    52/58

    13. http://www.electmen.org/elc_hisind.htm

    14. http://www.cercind.gov.in/08022007/Act-with-amendment.pdf

    15. CANMET Energy Technology Centre. (2004). Micro hydro systems : buyers

    guide. Retrieved from http://canmetenergy-canmetenergie.nrcan-

    rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdf

    16. Lamb, P.M. (2006). The India electricity market: country study and

    investment context. Retrieved from http://iis-

    db.stanford.edu/pubs/20975/India_Country_Study__UPDATE.pdf.

    17. Bharadwaj, A & Tongi, R. (n.d). Distributed power generation: rural India -

    case study. Retrieved

    fromhttp://ahec.org.in/wfw/pdf/rural_india_power_generation_case_study.pd

    f.

    http://www.electmen.org/elc_hisind.htmhttp://www.electmen.org/elc_hisind.htmhttp://www.cercind.gov.in/08022007/Act-with-amendment.pdfhttp://www.cercind.gov.in/08022007/Act-with-amendment.pdfhttp://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdfhttp://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdfhttp://iis-db.stanford.edu/pubs/20975/India_Country_Study__UPDATE.pdfhttp://iis-db.stanford.edu/pubs/20975/India_Country_Study__UPDATE.pdfhttp://ahec.org.in/wfw/pdf/rural_india_power_generation_case_study.pdfhttp://ahec.org.in/wfw/pdf/rural_india_power_generation_case_study.pdfhttp://ahec.org.in/wfw/pdf/rural_india_power_generation_case_study.pdfhttp://ahec.org.in/wfw/pdf/rural_india_power_generation_case_study.pdfhttp://iis-db.stanford.edu/pubs/20975/India_Country_Study__UPDATE.pdfhttp://iis-db.stanford.edu/pubs/20975/India_Country_Study__UPDATE.pdfhttp://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdfhttp://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdfhttp://www.cercind.gov.in/08022007/Act-with-amendment.pdfhttp://www.electmen.org/elc_hisind.htm
  • 8/10/2019 Final Report Yr3

    53/58

    23. CANMET Energy Technology Centre. (2004). Micro hydro systems : buyers

    guide. Retrieved from http://canmetenergy-canmetenergie.nrcan-

    rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdf

    24. http://www.engineeringtoolbox.com/piping-materials-cost-ratios-d_864.html

    25. http://www.ppfahome.org/pvc/faqpvc.html

    26. http://www.eee.nottingham.ac.uk/picohydro/docs/impman(ch11-12).pdf

    27. Hydropower Basics :

    Turbineshttp://www.microhydropower.net/basics/turbines.php#Turgo

    28. Cengel, Y. A. , & Cimbala, J. M. (2010) Fluid mechanics: Fundamentals and

    application. New York, NY: McGraw-Hill.

    http://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdfhttp://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdfhttp://www.engineeringtoolbox.com/piping-materials-cost-ratios-d_864.htmlhttp://www.engineeringtoolbox.com/piping-materials-cost-ratios-d_864.htmlhttp://www.ppfahome.org/pvc/faqpvc.htmlhttp://www.ppfahome.org/pvc/faqpvc.htmlhttp://www.microhydropower.net/basics/turbines.php#Turgohttp://www.microhydropower.net/basics/turbines.php#Turgohttp://www.microhydropower.net/basics/turbines.php#Turgohttp://www.microhydropower.net/basics/turbines.php#Turgohttp://www.ppfahome.org/pvc/faqpvc.htmlhttp://www.engineeringtoolbox.com/piping-materials-cost-ratios-d_864.htmlhttp://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdfhttp://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/fichier/79276/buyersguidehydroeng.pdf
  • 8/10/2019 Final Report Yr3

    54/58

    34. Suppliers contacted: Hartvigsen Hydro :Components for microhydro systems;

    RockyHydro; EcoInnovation Ltd

    35. Roy Beardman. (2010). Timing Belt. Retrieved October 28, 2011,

    fromhttp://www.roymech.co.uk/Useful_Tables/Drive/Timing_belts.html

    36. Danish Wind Industry Association. (2003). Asynchronous (induction)

    Generators. Retreived October 30, 2011,

    from http://www.motiva.fi/myllarin_tuulivoima/windpower%20web/en/tour/w

    trb/async.htm

    37. Ameli, M.T., Moslehpour, S., Mirzaie, A. (2008) Feasibility Study for Replacing

    Asynchronous Generators with Synchronous Generators in Wind Farm Power

    Stations. Retrieved November 1, 2011,

    fromhttp://www.ijme.us/cd_08/PDF/129-%20ENT%20204.pdf

    http://www.roymech.co.uk/Useful_Tables/Drive/Timing_belts.htmlhttp://www.roymech.co.uk/Useful_Tables/Drive/Timing_belts.htmlhttp://www.roymech.co.uk/Useful_Tables/Drive/Timing_belts.htmlhttp://www.motiva.fi/myllarin_tuulivoima/windpower%20web/en/tour/wtrb/async.htmhttp://www.motiva.fi/myllarin_tuulivoima/windpower%20web/en/tour/wtrb/async.htmhttp://www.motiva.fi/myllarin_tuulivoima/windpower%20web/en/tour/wtrb/async.htmhttp://www.ijme.us/cd_08/PDF/129-%20ENT%20204.pdfhttp://www.ijme.us/cd_08/PDF/129-%20ENT%20204.pdfhttp://www.ijme.us/cd_08/PDF/129-%20ENT%20204.pdfhttp://www.ijme.us/cd_08/PDF/129-%20ENT%20204.pdfhttp://www.motiva.fi/myllarin_tuulivoima/windpower%20web/en/tour/wtrb/async.htmhttp://www.motiva.fi/myllarin_tuulivoima/windpower%20web/en/tour/wtrb/async.htmhttp://www.roymech.co.uk/Useful_Tables/Drive/Timing_belts.html
  • 8/10/2019 Final Report Yr3

    55/58

    44. Thandaveswara, B.S. (n.d). Hydraulics. Retrieved

    from http://nptel.iitm.ac.in/courses/IIT-MADRAS/Hydraulics/pdfs/Unit4/4_1g.pdf

    http://nptel.iitm.ac.in/courses/IIT-MADRAS/Hydraulics/pdfs/Unit4/4_1g.pdfhttp://nptel.iitm.ac.in/courses/IIT-MADRAS/Hydraulics/pdfs/Unit4/4_1g.pdf
  • 8/10/2019 Final Report Yr3

    56/58

    1

    APPENDIX A

    Fig A.1 Detailed drawings of disk of the proposed Turgo turbine

  • 8/10/2019 Final Report Yr3

    57/58

    APPENDIX B

  • 8/10/2019 Final Report Yr3

    58/58

    3

    APPENDIX C

    Fig C.1 Detailed drawings of MAGNAPLUS SERIES Model 281MCSL1502 AC generator


Recommended