of 52
7/29/2019 final_Kim
1/52
1. Existing processes and business environment
Business environment U.S census on the Construction Industry
Contract type.
Existing processes Existing process
Current Used Technologies
Process mode
7/29/2019 final_Kim
2/52
Business Environment
1997 Economic Census (US census Bureau)
IndustryTotal number of
employees
Value of constructionwork
(US $1,000)
Value added
(US $1,000)
Construction 5,664,853 845,543,552 383,845,728
Building,developing, &
general contracting1,342,953 381,641,600 120,322,720
Heavy construction 880,400 127,841,600 68,775,976
Special tradecontractors
3,441,500 336,060,352 194,747,056
7/29/2019 final_Kim
3/52
Business Environment
The construction industry is very unique because1. It has many characteristics common to both
manufacturing and service industries.
2. It is fragmented and sometimes divisive.
3. It is very custom-oriented.4. It is incentive-oriented.
As a result
The construction industry highly depends onpersonnel rather than technologies.
Technologies play the role to support makingdecisions during industrys whole phases.
7/29/2019 final_Kim
4/52
Business Environment
Construction Management has emerged as a strongalternative to traditional construction contractingprocedures.
Construction manager represent owners profits in
the current construction industry that is getting morecomplicated and specialized.
Construction management treats the project planning,design, and construction phases as integrated tasks.
So, construction managers great role is tounderstand each specialized areas and to makediverse information into optimized information whilereducing resources and making more benefits.
7/29/2019 final_Kim
5/52
Business Environment
CM Agent
1%
CM at risk
30%
Design-build4%
Competitive
sealed
proposals
46%
Design-bid-build
19%
Example : Market share of CM type contracts.
Texas K-12 and public higher education projects
(source: Effects of State Legislation on Contracting Methods of PublicSchools and Universities)
Directly orindirectly,
constructionmanagementplays a big rolein 81% ofprojects.
7/29/2019 final_Kim
6/52
Business Environment
Relationships of project teams at CM at Risk
Owner
Designer
ConstructionManager
Owner
Designer
Contractual: Functional:
(Source:
IndependentContractors
ConstructionManager
IndependentContractors
7/29/2019 final_Kim
7/52
Existing Processes
Existing Working Processes
Planning Process
Constructability,
Procurability, Commissioning,
Operability, Maintainability,
Health, Sustainability
Analyses during Planning and
Design
Design ProcessPreliminary Studies Plans and Specifications
Construction Process
Evaluation of ProjectConstruction Performance
Plans and Specifications
Operations & Maintenance Process
Evaluation of Facility OperationPerformance
7/29/2019 final_Kim
8/52
Existing Processes
Current Used Technologies
Planning PhaseOwner Team
1. Assessment &
Objectives Setting2. Preliminary, planning &
Funding
3. Project DefinitionPackage
Design PhaseDesign Team
(Engineers/Architects)
1. Conceptual /
Schematic Design2. Design Development
3. Contract Documents
Construction PhaseConstruction Team(Construction Managers /General
Contractors/Subcontractors)
1. Bid or Negotiate, &
Award2. Construction Planning
3. Execution
4. Start-up
Operation PhaseOperations Team
(Users/Operators)
1. Operation/Manageme
nt / Maintenance2. End of Service Life
Decision
For Drafting & Rendering
AutoCAD, ArchiCAD
3D-Studio, FormZ
For Planning
Primavera Project Planning,MS Project
For Estimating
Dodge, MS Excel
For ContractingPrimavera Expedition
Technologies
7/29/2019 final_Kim
9/52
Existing Processes
Project Documentation Problems
(Source: CIFE Summer Program)
7/29/2019 final_Kim
10/52
Existing Processes
(Source: CIFE Summer Program)
Current Process-Issues / Problems
7/29/2019 final_Kim
11/52
Existing Processes
Current Technologies and Processes Problems
Lack of understanding
Danger not to reflect owners intend.
Inefficient work due to misunderstanding aboutprojects.
Not integrated data between each applications
Rework to interpret.
Problems caused by misunderstanding differentareas works.
7/29/2019 final_Kim
12/52
Conditions of new information technologies
Available and suitable technologies
Process model
Advantages
Assessment of the technologies
Benefit
Obstacle
2. Available and suitable information technologies
7/29/2019 final_Kim
13/52
Conditions of new alternative technologies
1. They can be easily understood without specialtraining.
Owner needs to know whats going on.
2. They are also easily understood by computer. The information has to be understood by both people
and computer.
3. They must integrate each areas tasks.We need the tool that can reduce meaningless works
like counting numbers or copying data.
7/29/2019 final_Kim
14/52
Available and suitable information technologies
1. 4D CAD System 4D CAD system is for integrating the information
within the design and construction phases.
4D CAD is now been developing to1. manage and minimize risk throughout all
stages of a construction project
2. effectively communicate the design, schedule,
and other project data3. rapidly explore design and construction
alternatives(By Martin Fischer, Kathleen McKinney Liston)
7/29/2019 final_Kim
15/52
Available and suitable information technologies
Applications based on 4D CAD The prototype of 4D CAD developed by 4D CAD
research team of Stanford University.
ProVis developed by VIRCON
Revit developed by AutoDesk
2. Information networking - VERA
7/29/2019 final_Kim
16/52
Available and suitable information technologies
Process Model of 4D-CAD Models
AutoCAD
dwg files
.P3
file
Start with
Primavera
AutoCAD
dxf
.pm
Multigen
Alias
Wavefront
.EGG
Egg-
VRML
translator
.wrl
file
VRML 4D
-Appli.
.VFD
Cave
VRML 4D
-Applet
Ended with:
Prototype developed to importVRML files and schedulecontent and provide basic 4Dfunctionality in an on-lineenvironment
Internal translatorwas updated forinput into Java/4Dapplication
Application waswritten to importVFD format intoCAVE to generaterelationshipsbetween 3Dcomponents andactivities
Hierarchical 3D file format
Commercial tool
Prototype 4D tools
(Source: CIFE Summer Program)
7/29/2019 final_Kim
17/52
Available and suitable information technologies
System Architecture of 4D-CAD (Pro Vis)
RDBMS(SQL)
Information Structure(Uniclass)
MS Project
ODBC
User Interface
VBA
SpreadsheetsCosting Models
Virtual Reality
AutoCAD
VBA
4D Simulator(ProVis)
VBA
VBA: Visual Basic for Applications
ODBC: Open Database Connectivity
RDBMS: Relational DatabaseManagement System
VBA: Visual Basic for Applications
VBA: Visual Basic for Applications(Source: VIRCON)
7/29/2019 final_Kim
18/52
Available and suitable information technologies
Advantages of 4D-CAD1. To reduce time and cost from design to
construction phases.
2. To help communications and understanding
between each teams.3. To improve the productivities and to reduce
meaningless works.
As a result Owners can expect to save the cost and to get
higher value.
Each teams can expect to earn more money by
improving their productivities.
7/29/2019 final_Kim
19/52
Assessment of the Technologies
Benefits for owners To save the cost and time
Better quality of a final product
Better understanding about the project
Benefits for design teams
To reduce planning time and cost
To communicate with each teams easily
To prevent errors and mistakes
To reduce rework
7/29/2019 final_Kim
20/52
Assessment of the Technologies
Benefits for construction manager teams To reduce the time and cost
To build database easily
To increase productivity
To reduce wasted materials To expect constructability
7/29/2019 final_Kim
21/52
Screenshot of InVIznOne
4D model of The Helsinki University of Technology
7/29/2019 final_Kim
22/52
Screenshots of ProVis (1)
7/29/2019 final_Kim
23/52
Screenshots of ProVis (2)
7/29/2019 final_Kim
24/52
3. A framework target plan
The characters of the cases which adopted 4D-CAD
The cases implemented by 4D-CAD
A long term IT adoption goals
7/29/2019 final_Kim
25/52
The characters of the cases which adopted 4D-CAD
4D-CAD Cases (1)Project Facility type Phase Contract Value
Disneys California
Adventure-Paradise PierAmusement Facility Project planning, Bid -
Paradise Pier-Seafood
Restaurant
Restaurant Construction
Administration
-
Paradise Pier HotelFaade Renovation
Hotel Renovation Planning, Construction -
Disney Concert Hall Concert Hall Construction $200 Million
Hospital Hospital Construction $400 Million
Lab/Office Facility Lab/Office Pre-Construction $100 Million
Office Complex Complex Bid $259 Million
Bay Street Project Theatre Planning, Construction -
7/29/2019 final_Kim
26/52
The characters of the cases which adopted 4D-CAD
4D-CAD Cases (2)Project Facility type Phase Contract Value
Sequus PharmaceuticalsPilot Plant
Multi-Purpose Planning, Construction -
School of Health,
University of Teeside
Educational
Institute University
Planning, Construction -
Westmorland PrimarySchool, Stockport
Educational Institute-High School
Planning, Construction -
7/29/2019 final_Kim
27/52
The characters of the cases which adopted 4D-CAD
Post-Construction AnalysisRountree Plumbing Paragon Mechanical Rosendin ElectricProcess Piping/HVAC Wet HVAC Dry Electrical
Contract Value $2,018,937 $1,071,237 $488,414
Increased DesignCosts
30% 20-30% 20-30%
Number of ChangeOrders 6 1 3
Reason for ChangeOrders
4-Owner Requested
1-Value Engineering
1-Unforeseen Condition
1-Owner Requested 3-Owner Requested
Percentage of TotalCost
-1.0028% 0.9958% 0.9746%
Productivity Significantly increased Much more Productive No DifferenceRework Dramatically reduced Minimal No Difference
Profitability Same Same Less
Expects greater return withincreased use
Expects greater returnwith increased use
Increased design timewith less benefit fromcoordination
(Source: Martin Fischer, CIFE)
7/29/2019 final_Kim
28/52
The characters of the cases which adopted 4D-CAD
Based on the cases, 4D-CAD makes more valuesfrom the projects on following conditions.
The projects have
Many stakeholders and players. Complicate functions.
Large scales.
and
Need much more information.
Adopt new technologies.
7/29/2019 final_Kim
29/52
The cases implemented by 4D-CAD
The project of the mine facilities in Chile (1) Case study description
A huge new copper concentrator facility to bebuilt some 10 kilometers from the existing
facilities It required
A 9.6 kilometer overland conveyor
An 164-kilometer pipeline to carry copper
concentrate Living and recreation facilities for the
approximately 7,500 workers on site
The covered building to hold some 400,000
metric tons of ore
7/29/2019 final_Kim
30/52
The cases implemented by 4D-CAD
The project of the mine facilities in Chile (2) Case Description (2)
It also required
A system of conveyor belt hoppers and
chutes the rock and deliver it to an 11.6-meter-in-diameter, 26,000-HP semi-autogenous grinding mill, three 18,000-HPball mills, and a set of 110 flotation cells.
7/29/2019 final_Kim
31/52
The cases implemented by 4D-CAD
The project of the mine facilities in Chile (3)
The Model of the Case Study Project
Th i l d b 4D CAD
7/29/2019 final_Kim
32/52
The cases implemented by 4D-CAD
The project of the mine facilities in Chile (4) Benefits
Reduction of 10% in cost
Reduction in schedule, from 18 to 16 months
Improved design reflected in a reduction inerrors during construction
Reductions in uncertainty and risk reflected in90% of fulfillment of the construction schedule
(Source: 4D-PS: Putting IT new work process into effect)
Th i l t d b 4D CAD
7/29/2019 final_Kim
33/52
The cases implemented by 4D-CAD
The Bay Street Project Case, Emeryville, CA (1) Activities
Start was 2D data and schedule with more than200 activities for a office complex more than
1,000,000 SF. 252 hours of InVizOne 3D modeling services.
200 hours of InVizOne 4D modeling services.
Benefits Discovered opportunity to save $3 million in
reduced cost for unexcavated courtyards
Discovered opportunities to save $5 million in
reduced cost overall
Th i l t d b 4D CAD
7/29/2019 final_Kim
34/52
The cases implemented by 4D-CAD
The Bay Street Project Case, Emeryville, CA (2)
The Models of the Case Study Project
Th i l t d b 4D CAD
7/29/2019 final_Kim
35/52
The cases implemented by 4D-CAD
As a result of the smooth communication and clearunderstanding between each player
$2,000,000
$1,800,000
$1,600,000
$1,400,000
$1,200,000
$1,000,000
$800,000
$600,000
$400,000
$200,000
$0
$0 $500 $1,000 $1,500 $2,000 $2,500 $3,000 $3,500 $4,000 $4,500 $5,000
Total Unplanned Change by Individual Facilities ($000)
ValueofAvoidableChange
(Source: Building Better by Building Virtually First)
A l t IT d ti l
7/29/2019 final_Kim
36/52
A long term IT adoption goal
The impacts of 4D-CAD (1)
Schematic
DesignProgrammingDesign Develop/
Construction Document
Construction Ope
ration
The Sequent Phases of the Project
A l t IT d ti l
7/29/2019 final_Kim
37/52
A long term IT adoption goal
The impacts of 4D-CAD (2)
Owner
Designer4D-CAD Model
&
Libraries
ConstructionManager
Subcontractor
Subcontractor
Subcontractor
Subcontractor
Contracting
Flow of Information
4 A th t d t f hi i th l
7/29/2019 final_Kim
38/52
4. Assess the expected costs of achieving the plan
The major expected costs at the industry aspect
Collaboration between the players in the industry
Data exchange
The minor expected costs at the firm aspect The investment on equipments
The internal investment on the infrastructure
Potential risks
The implementation of adopting a new technology
Th j t d t t th i d t t
7/29/2019 final_Kim
39/52
The major expected costs at the industry aspect
Collaboration between each firms
The hesitance to open own information
E.g. drawings of a new high-tech elevator
The avoidance the rework due to feedback E.g. reworks to change finished plans due to
the problems of other teams
The responsibility problems E.g. whose responsibility about the costs due to
the changing plans
The major e pected costs at the ind str aspect
7/29/2019 final_Kim
40/52
The major expected costs at the industry aspect
The necessity to adjust the existing contractconditions
As the concept of the construction is changing,the contract conditions have to be modified.
The major expected costs at the industry aspect
7/29/2019 final_Kim
41/52
The major expected costs at the industry aspect
Data exchange
The standardization problem
Data supporting system
Internal supporting system e.g. AutoCADs libraries, Adobe
Photoshops plug-in applications concept
External supporting system
Web HubASP solutions
The minor expected costs at the firm aspect
7/29/2019 final_Kim
42/52
The minor expected costs at the firm aspect
The investment on equipments
New hardware and software
Employees training
The internal investment on the infrastructure Organizational restructure
Supporting system for new solutions
The enough infrastructure to maximize the
benefits of 4D-CAD
Potential risks
7/29/2019 final_Kim
43/52
Potential risks
The whole implementation of 4D-CAD
The lag time problem
The resistance of peoples to the new technology
The hidden costs
5 Analysis of the readiness of the CPM sector
7/29/2019 final_Kim
44/52
5. Analysis of the readiness of the CPM sector
The currently readiness of the implementation
The current commercial applications
The current rate of the automation
The impacts of the 4D-CAD The impacts in a short term
The impacts in a long term
The currently readiness of the implementation
7/29/2019 final_Kim
45/52
The currently readiness of the implementation
The current commercial applications
Each sub-sectors have own applications
The familiarness to the computer based works
The fast rate of networking development
The lack of linkage between each sub-setors
The current rate of the automation
The most segments are already automated or
being automated. The lack of linkage between planning and
manufacturing
The impacts of the 4D CAD
7/29/2019 final_Kim
46/52
The impacts of the 4D-CAD
The impacts in a short term
The limited implementation due to not fullyintegrated data
A lot of modification manually due to lack ofaccurate logic to replace decision makings
The impacts in a long term
The fully integration through planners,
constructers and manufacturers To provide better quality controls
To maximize the value of projects
6 A detailed plan for the next incremental step
7/29/2019 final_Kim
47/52
6. A detailed plan for the next incremental step
The further IT adoptions goals of 4D-CAD
Plan
Design
Procurement
Finance Construction
The further IT adoptions goals of 4D CAD
7/29/2019 final_Kim
48/52
The further IT adoption s goals of 4D-CAD
Plan
The value analysis of the project
The examination of the project executions
Design To provide whole information include product
codes, specifications and etc
Procurement To integrate local dealers who provide
construction materials
To order materials as the needs of the
construction lead time
The further IT adoptions goals of 4D CAD
7/29/2019 final_Kim
49/52
The further IT adoption s goals of 4D-CAD
Finance
To reflect constructors finance status include loan
cost, procurement cost and etc
Construction To improve quality controls
To enhance construction productivity
E.g. Mobile computing on construction site,
quality control by image processing
References
7/29/2019 final_Kim
50/52
References
1. US census Bureau
(http://www.census.gov/epcd/www/97EC23.HTM)2. Donald S. Barrie and Boyd C. Paulson, Professional
Construction Management - 3rd Edition, McGraw Hill, 1992
3. K. Everette Sylvester, Effects of State Legislation onContracting Methods of Public Schools and Universities,
Forum on Construction Project Delivery for Texas Public Work,January 31, 2001
4. Construction Management Associations of America(http://www.cmaanet.org )
5. 4D CAD Research(http://www.stanford.edu/group/4D/index.shtml)
6. CIFE Summer Program (http://www.stanford.edu/group/CIFE )
7. 3D/4D Workshops (http://www.stanford.edu/group/4D/4d-workshop-main.htm )
8. Construction Research Agenda Workshop( http://www/ce/berkeley.edy/~tommelein/CEMworkshop.htm )
References
http://www.census.gov/epcd/www/97EC23.HTMhttp://www.cmaanet.org/http://www.stanford.edu/group/4D/index.shtmlhttp://www.stanford.edu/group/CIFEhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www/ce/berkeley.edy/~tommelein/CEMworkshop.htmhttp://www/ce/berkeley.edy/~tommelein/CEMworkshop.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/CIFEhttp://www.stanford.edu/group/4D/index.shtmlhttp://www.cmaanet.org/http://www.census.gov/epcd/www/97EC23.HTM7/29/2019 final_Kim
51/52
References
9. VIRCON ( http://www.bartlett.ucl.ac.uk/vircon/ )
10. K. Everette Sylvester, Effects of State Legislation onContracting Methods of Public Schools and Universities,Forum on Construction Project Delivery for Texas Public Work,January 31, 2001
11. Robert A. Rodgers, A 4D-CAD implementation UtilizingJSPACE Schedule Simulator, Virginia Tech
12. Martin Fischer, 4D CAD: Learning from your virtualmistakes, Stanford University
13. Mark J. Clayton, Paul Teicholz, Martin Fischer, & John Kunz,Virtual components consisting of form, function andbehavior, Automation in Construction 8, 1999, pp. 351-367.
14. Gijsbertus T. Luiten, Frits P. Tolman and Martin A. Fischer,Project-modeling in AEC to integrate design andconstruction, Computers in Industry 35, 1998, pp. 13-29.
References
http://www.bartlett.ucl.ac.uk/vircon/http://www.bartlett.ucl.ac.uk/vircon/7/29/2019 final_Kim
52/52
References
14. Paul Teicholz, Vision of Future Practice, White paper on AEC
Practice and Research Issues for the Future.
15. Peter Barrett, Construction management pull for 4D CAD,University of Salford.
16. Leonardo Rischmoller, 4D-PS: Putting an IT new workprocess into effect, Bechtel Group, Inc., June 12, 2002
17. Martin Fischer, Building better by building virtually first,Stanford University