+ All Categories
Home > Documents > final_Kim

final_Kim

Date post: 04-Apr-2018
Category:
Upload: jsaul
View: 213 times
Download: 0 times
Share this document with a friend

of 52

Transcript
  • 7/29/2019 final_Kim

    1/52

    1. Existing processes and business environment

    Business environment U.S census on the Construction Industry

    Contract type.

    Existing processes Existing process

    Current Used Technologies

    Process mode

  • 7/29/2019 final_Kim

    2/52

    Business Environment

    1997 Economic Census (US census Bureau)

    IndustryTotal number of

    employees

    Value of constructionwork

    (US $1,000)

    Value added

    (US $1,000)

    Construction 5,664,853 845,543,552 383,845,728

    Building,developing, &

    general contracting1,342,953 381,641,600 120,322,720

    Heavy construction 880,400 127,841,600 68,775,976

    Special tradecontractors

    3,441,500 336,060,352 194,747,056

  • 7/29/2019 final_Kim

    3/52

    Business Environment

    The construction industry is very unique because1. It has many characteristics common to both

    manufacturing and service industries.

    2. It is fragmented and sometimes divisive.

    3. It is very custom-oriented.4. It is incentive-oriented.

    As a result

    The construction industry highly depends onpersonnel rather than technologies.

    Technologies play the role to support makingdecisions during industrys whole phases.

  • 7/29/2019 final_Kim

    4/52

    Business Environment

    Construction Management has emerged as a strongalternative to traditional construction contractingprocedures.

    Construction manager represent owners profits in

    the current construction industry that is getting morecomplicated and specialized.

    Construction management treats the project planning,design, and construction phases as integrated tasks.

    So, construction managers great role is tounderstand each specialized areas and to makediverse information into optimized information whilereducing resources and making more benefits.

  • 7/29/2019 final_Kim

    5/52

    Business Environment

    CM Agent

    1%

    CM at risk

    30%

    Design-build4%

    Competitive

    sealed

    proposals

    46%

    Design-bid-build

    19%

    Example : Market share of CM type contracts.

    Texas K-12 and public higher education projects

    (source: Effects of State Legislation on Contracting Methods of PublicSchools and Universities)

    Directly orindirectly,

    constructionmanagementplays a big rolein 81% ofprojects.

  • 7/29/2019 final_Kim

    6/52

    Business Environment

    Relationships of project teams at CM at Risk

    Owner

    Designer

    ConstructionManager

    Owner

    Designer

    Contractual: Functional:

    (Source:

    IndependentContractors

    ConstructionManager

    IndependentContractors

  • 7/29/2019 final_Kim

    7/52

    Existing Processes

    Existing Working Processes

    Planning Process

    Constructability,

    Procurability, Commissioning,

    Operability, Maintainability,

    Health, Sustainability

    Analyses during Planning and

    Design

    Design ProcessPreliminary Studies Plans and Specifications

    Construction Process

    Evaluation of ProjectConstruction Performance

    Plans and Specifications

    Operations & Maintenance Process

    Evaluation of Facility OperationPerformance

  • 7/29/2019 final_Kim

    8/52

    Existing Processes

    Current Used Technologies

    Planning PhaseOwner Team

    1. Assessment &

    Objectives Setting2. Preliminary, planning &

    Funding

    3. Project DefinitionPackage

    Design PhaseDesign Team

    (Engineers/Architects)

    1. Conceptual /

    Schematic Design2. Design Development

    3. Contract Documents

    Construction PhaseConstruction Team(Construction Managers /General

    Contractors/Subcontractors)

    1. Bid or Negotiate, &

    Award2. Construction Planning

    3. Execution

    4. Start-up

    Operation PhaseOperations Team

    (Users/Operators)

    1. Operation/Manageme

    nt / Maintenance2. End of Service Life

    Decision

    For Drafting & Rendering

    AutoCAD, ArchiCAD

    3D-Studio, FormZ

    For Planning

    Primavera Project Planning,MS Project

    For Estimating

    Dodge, MS Excel

    For ContractingPrimavera Expedition

    Technologies

  • 7/29/2019 final_Kim

    9/52

    Existing Processes

    Project Documentation Problems

    (Source: CIFE Summer Program)

  • 7/29/2019 final_Kim

    10/52

    Existing Processes

    (Source: CIFE Summer Program)

    Current Process-Issues / Problems

  • 7/29/2019 final_Kim

    11/52

    Existing Processes

    Current Technologies and Processes Problems

    Lack of understanding

    Danger not to reflect owners intend.

    Inefficient work due to misunderstanding aboutprojects.

    Not integrated data between each applications

    Rework to interpret.

    Problems caused by misunderstanding differentareas works.

  • 7/29/2019 final_Kim

    12/52

    Conditions of new information technologies

    Available and suitable technologies

    Process model

    Advantages

    Assessment of the technologies

    Benefit

    Obstacle

    2. Available and suitable information technologies

  • 7/29/2019 final_Kim

    13/52

    Conditions of new alternative technologies

    1. They can be easily understood without specialtraining.

    Owner needs to know whats going on.

    2. They are also easily understood by computer. The information has to be understood by both people

    and computer.

    3. They must integrate each areas tasks.We need the tool that can reduce meaningless works

    like counting numbers or copying data.

  • 7/29/2019 final_Kim

    14/52

    Available and suitable information technologies

    1. 4D CAD System 4D CAD system is for integrating the information

    within the design and construction phases.

    4D CAD is now been developing to1. manage and minimize risk throughout all

    stages of a construction project

    2. effectively communicate the design, schedule,

    and other project data3. rapidly explore design and construction

    alternatives(By Martin Fischer, Kathleen McKinney Liston)

  • 7/29/2019 final_Kim

    15/52

    Available and suitable information technologies

    Applications based on 4D CAD The prototype of 4D CAD developed by 4D CAD

    research team of Stanford University.

    ProVis developed by VIRCON

    Revit developed by AutoDesk

    2. Information networking - VERA

  • 7/29/2019 final_Kim

    16/52

    Available and suitable information technologies

    Process Model of 4D-CAD Models

    AutoCAD

    dwg files

    .P3

    file

    Start with

    Primavera

    AutoCAD

    dxf

    .pm

    Multigen

    Alias

    Wavefront

    .EGG

    Egg-

    VRML

    translator

    .wrl

    file

    VRML 4D

    -Appli.

    .VFD

    Cave

    VRML 4D

    -Applet

    Ended with:

    Prototype developed to importVRML files and schedulecontent and provide basic 4Dfunctionality in an on-lineenvironment

    Internal translatorwas updated forinput into Java/4Dapplication

    Application waswritten to importVFD format intoCAVE to generaterelationshipsbetween 3Dcomponents andactivities

    Hierarchical 3D file format

    Commercial tool

    Prototype 4D tools

    (Source: CIFE Summer Program)

  • 7/29/2019 final_Kim

    17/52

    Available and suitable information technologies

    System Architecture of 4D-CAD (Pro Vis)

    RDBMS(SQL)

    Information Structure(Uniclass)

    MS Project

    ODBC

    User Interface

    VBA

    SpreadsheetsCosting Models

    Virtual Reality

    AutoCAD

    VBA

    4D Simulator(ProVis)

    VBA

    VBA: Visual Basic for Applications

    ODBC: Open Database Connectivity

    RDBMS: Relational DatabaseManagement System

    VBA: Visual Basic for Applications

    VBA: Visual Basic for Applications(Source: VIRCON)

  • 7/29/2019 final_Kim

    18/52

    Available and suitable information technologies

    Advantages of 4D-CAD1. To reduce time and cost from design to

    construction phases.

    2. To help communications and understanding

    between each teams.3. To improve the productivities and to reduce

    meaningless works.

    As a result Owners can expect to save the cost and to get

    higher value.

    Each teams can expect to earn more money by

    improving their productivities.

  • 7/29/2019 final_Kim

    19/52

    Assessment of the Technologies

    Benefits for owners To save the cost and time

    Better quality of a final product

    Better understanding about the project

    Benefits for design teams

    To reduce planning time and cost

    To communicate with each teams easily

    To prevent errors and mistakes

    To reduce rework

  • 7/29/2019 final_Kim

    20/52

    Assessment of the Technologies

    Benefits for construction manager teams To reduce the time and cost

    To build database easily

    To increase productivity

    To reduce wasted materials To expect constructability

  • 7/29/2019 final_Kim

    21/52

    Screenshot of InVIznOne

    4D model of The Helsinki University of Technology

  • 7/29/2019 final_Kim

    22/52

    Screenshots of ProVis (1)

  • 7/29/2019 final_Kim

    23/52

    Screenshots of ProVis (2)

  • 7/29/2019 final_Kim

    24/52

    3. A framework target plan

    The characters of the cases which adopted 4D-CAD

    The cases implemented by 4D-CAD

    A long term IT adoption goals

  • 7/29/2019 final_Kim

    25/52

    The characters of the cases which adopted 4D-CAD

    4D-CAD Cases (1)Project Facility type Phase Contract Value

    Disneys California

    Adventure-Paradise PierAmusement Facility Project planning, Bid -

    Paradise Pier-Seafood

    Restaurant

    Restaurant Construction

    Administration

    -

    Paradise Pier HotelFaade Renovation

    Hotel Renovation Planning, Construction -

    Disney Concert Hall Concert Hall Construction $200 Million

    Hospital Hospital Construction $400 Million

    Lab/Office Facility Lab/Office Pre-Construction $100 Million

    Office Complex Complex Bid $259 Million

    Bay Street Project Theatre Planning, Construction -

  • 7/29/2019 final_Kim

    26/52

    The characters of the cases which adopted 4D-CAD

    4D-CAD Cases (2)Project Facility type Phase Contract Value

    Sequus PharmaceuticalsPilot Plant

    Multi-Purpose Planning, Construction -

    School of Health,

    University of Teeside

    Educational

    Institute University

    Planning, Construction -

    Westmorland PrimarySchool, Stockport

    Educational Institute-High School

    Planning, Construction -

  • 7/29/2019 final_Kim

    27/52

    The characters of the cases which adopted 4D-CAD

    Post-Construction AnalysisRountree Plumbing Paragon Mechanical Rosendin ElectricProcess Piping/HVAC Wet HVAC Dry Electrical

    Contract Value $2,018,937 $1,071,237 $488,414

    Increased DesignCosts

    30% 20-30% 20-30%

    Number of ChangeOrders 6 1 3

    Reason for ChangeOrders

    4-Owner Requested

    1-Value Engineering

    1-Unforeseen Condition

    1-Owner Requested 3-Owner Requested

    Percentage of TotalCost

    -1.0028% 0.9958% 0.9746%

    Productivity Significantly increased Much more Productive No DifferenceRework Dramatically reduced Minimal No Difference

    Profitability Same Same Less

    Expects greater return withincreased use

    Expects greater returnwith increased use

    Increased design timewith less benefit fromcoordination

    (Source: Martin Fischer, CIFE)

  • 7/29/2019 final_Kim

    28/52

    The characters of the cases which adopted 4D-CAD

    Based on the cases, 4D-CAD makes more valuesfrom the projects on following conditions.

    The projects have

    Many stakeholders and players. Complicate functions.

    Large scales.

    and

    Need much more information.

    Adopt new technologies.

  • 7/29/2019 final_Kim

    29/52

    The cases implemented by 4D-CAD

    The project of the mine facilities in Chile (1) Case study description

    A huge new copper concentrator facility to bebuilt some 10 kilometers from the existing

    facilities It required

    A 9.6 kilometer overland conveyor

    An 164-kilometer pipeline to carry copper

    concentrate Living and recreation facilities for the

    approximately 7,500 workers on site

    The covered building to hold some 400,000

    metric tons of ore

  • 7/29/2019 final_Kim

    30/52

    The cases implemented by 4D-CAD

    The project of the mine facilities in Chile (2) Case Description (2)

    It also required

    A system of conveyor belt hoppers and

    chutes the rock and deliver it to an 11.6-meter-in-diameter, 26,000-HP semi-autogenous grinding mill, three 18,000-HPball mills, and a set of 110 flotation cells.

  • 7/29/2019 final_Kim

    31/52

    The cases implemented by 4D-CAD

    The project of the mine facilities in Chile (3)

    The Model of the Case Study Project

    Th i l d b 4D CAD

  • 7/29/2019 final_Kim

    32/52

    The cases implemented by 4D-CAD

    The project of the mine facilities in Chile (4) Benefits

    Reduction of 10% in cost

    Reduction in schedule, from 18 to 16 months

    Improved design reflected in a reduction inerrors during construction

    Reductions in uncertainty and risk reflected in90% of fulfillment of the construction schedule

    (Source: 4D-PS: Putting IT new work process into effect)

    Th i l t d b 4D CAD

  • 7/29/2019 final_Kim

    33/52

    The cases implemented by 4D-CAD

    The Bay Street Project Case, Emeryville, CA (1) Activities

    Start was 2D data and schedule with more than200 activities for a office complex more than

    1,000,000 SF. 252 hours of InVizOne 3D modeling services.

    200 hours of InVizOne 4D modeling services.

    Benefits Discovered opportunity to save $3 million in

    reduced cost for unexcavated courtyards

    Discovered opportunities to save $5 million in

    reduced cost overall

    Th i l t d b 4D CAD

  • 7/29/2019 final_Kim

    34/52

    The cases implemented by 4D-CAD

    The Bay Street Project Case, Emeryville, CA (2)

    The Models of the Case Study Project

    Th i l t d b 4D CAD

  • 7/29/2019 final_Kim

    35/52

    The cases implemented by 4D-CAD

    As a result of the smooth communication and clearunderstanding between each player

    $2,000,000

    $1,800,000

    $1,600,000

    $1,400,000

    $1,200,000

    $1,000,000

    $800,000

    $600,000

    $400,000

    $200,000

    $0

    $0 $500 $1,000 $1,500 $2,000 $2,500 $3,000 $3,500 $4,000 $4,500 $5,000

    Total Unplanned Change by Individual Facilities ($000)

    ValueofAvoidableChange

    (Source: Building Better by Building Virtually First)

    A l t IT d ti l

  • 7/29/2019 final_Kim

    36/52

    A long term IT adoption goal

    The impacts of 4D-CAD (1)

    Schematic

    DesignProgrammingDesign Develop/

    Construction Document

    Construction Ope

    ration

    The Sequent Phases of the Project

    A l t IT d ti l

  • 7/29/2019 final_Kim

    37/52

    A long term IT adoption goal

    The impacts of 4D-CAD (2)

    Owner

    Designer4D-CAD Model

    &

    Libraries

    ConstructionManager

    Subcontractor

    Subcontractor

    Subcontractor

    Subcontractor

    Contracting

    Flow of Information

    4 A th t d t f hi i th l

  • 7/29/2019 final_Kim

    38/52

    4. Assess the expected costs of achieving the plan

    The major expected costs at the industry aspect

    Collaboration between the players in the industry

    Data exchange

    The minor expected costs at the firm aspect The investment on equipments

    The internal investment on the infrastructure

    Potential risks

    The implementation of adopting a new technology

    Th j t d t t th i d t t

  • 7/29/2019 final_Kim

    39/52

    The major expected costs at the industry aspect

    Collaboration between each firms

    The hesitance to open own information

    E.g. drawings of a new high-tech elevator

    The avoidance the rework due to feedback E.g. reworks to change finished plans due to

    the problems of other teams

    The responsibility problems E.g. whose responsibility about the costs due to

    the changing plans

    The major e pected costs at the ind str aspect

  • 7/29/2019 final_Kim

    40/52

    The major expected costs at the industry aspect

    The necessity to adjust the existing contractconditions

    As the concept of the construction is changing,the contract conditions have to be modified.

    The major expected costs at the industry aspect

  • 7/29/2019 final_Kim

    41/52

    The major expected costs at the industry aspect

    Data exchange

    The standardization problem

    Data supporting system

    Internal supporting system e.g. AutoCADs libraries, Adobe

    Photoshops plug-in applications concept

    External supporting system

    Web HubASP solutions

    The minor expected costs at the firm aspect

  • 7/29/2019 final_Kim

    42/52

    The minor expected costs at the firm aspect

    The investment on equipments

    New hardware and software

    Employees training

    The internal investment on the infrastructure Organizational restructure

    Supporting system for new solutions

    The enough infrastructure to maximize the

    benefits of 4D-CAD

    Potential risks

  • 7/29/2019 final_Kim

    43/52

    Potential risks

    The whole implementation of 4D-CAD

    The lag time problem

    The resistance of peoples to the new technology

    The hidden costs

    5 Analysis of the readiness of the CPM sector

  • 7/29/2019 final_Kim

    44/52

    5. Analysis of the readiness of the CPM sector

    The currently readiness of the implementation

    The current commercial applications

    The current rate of the automation

    The impacts of the 4D-CAD The impacts in a short term

    The impacts in a long term

    The currently readiness of the implementation

  • 7/29/2019 final_Kim

    45/52

    The currently readiness of the implementation

    The current commercial applications

    Each sub-sectors have own applications

    The familiarness to the computer based works

    The fast rate of networking development

    The lack of linkage between each sub-setors

    The current rate of the automation

    The most segments are already automated or

    being automated. The lack of linkage between planning and

    manufacturing

    The impacts of the 4D CAD

  • 7/29/2019 final_Kim

    46/52

    The impacts of the 4D-CAD

    The impacts in a short term

    The limited implementation due to not fullyintegrated data

    A lot of modification manually due to lack ofaccurate logic to replace decision makings

    The impacts in a long term

    The fully integration through planners,

    constructers and manufacturers To provide better quality controls

    To maximize the value of projects

    6 A detailed plan for the next incremental step

  • 7/29/2019 final_Kim

    47/52

    6. A detailed plan for the next incremental step

    The further IT adoptions goals of 4D-CAD

    Plan

    Design

    Procurement

    Finance Construction

    The further IT adoptions goals of 4D CAD

  • 7/29/2019 final_Kim

    48/52

    The further IT adoption s goals of 4D-CAD

    Plan

    The value analysis of the project

    The examination of the project executions

    Design To provide whole information include product

    codes, specifications and etc

    Procurement To integrate local dealers who provide

    construction materials

    To order materials as the needs of the

    construction lead time

    The further IT adoptions goals of 4D CAD

  • 7/29/2019 final_Kim

    49/52

    The further IT adoption s goals of 4D-CAD

    Finance

    To reflect constructors finance status include loan

    cost, procurement cost and etc

    Construction To improve quality controls

    To enhance construction productivity

    E.g. Mobile computing on construction site,

    quality control by image processing

    References

  • 7/29/2019 final_Kim

    50/52

    References

    1. US census Bureau

    (http://www.census.gov/epcd/www/97EC23.HTM)2. Donald S. Barrie and Boyd C. Paulson, Professional

    Construction Management - 3rd Edition, McGraw Hill, 1992

    3. K. Everette Sylvester, Effects of State Legislation onContracting Methods of Public Schools and Universities,

    Forum on Construction Project Delivery for Texas Public Work,January 31, 2001

    4. Construction Management Associations of America(http://www.cmaanet.org )

    5. 4D CAD Research(http://www.stanford.edu/group/4D/index.shtml)

    6. CIFE Summer Program (http://www.stanford.edu/group/CIFE )

    7. 3D/4D Workshops (http://www.stanford.edu/group/4D/4d-workshop-main.htm )

    8. Construction Research Agenda Workshop( http://www/ce/berkeley.edy/~tommelein/CEMworkshop.htm )

    References

    http://www.census.gov/epcd/www/97EC23.HTMhttp://www.cmaanet.org/http://www.stanford.edu/group/4D/index.shtmlhttp://www.stanford.edu/group/CIFEhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www/ce/berkeley.edy/~tommelein/CEMworkshop.htmhttp://www/ce/berkeley.edy/~tommelein/CEMworkshop.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/4D/4d-workshop-main.htmhttp://www.stanford.edu/group/CIFEhttp://www.stanford.edu/group/4D/index.shtmlhttp://www.cmaanet.org/http://www.census.gov/epcd/www/97EC23.HTM
  • 7/29/2019 final_Kim

    51/52

    References

    9. VIRCON ( http://www.bartlett.ucl.ac.uk/vircon/ )

    10. K. Everette Sylvester, Effects of State Legislation onContracting Methods of Public Schools and Universities,Forum on Construction Project Delivery for Texas Public Work,January 31, 2001

    11. Robert A. Rodgers, A 4D-CAD implementation UtilizingJSPACE Schedule Simulator, Virginia Tech

    12. Martin Fischer, 4D CAD: Learning from your virtualmistakes, Stanford University

    13. Mark J. Clayton, Paul Teicholz, Martin Fischer, & John Kunz,Virtual components consisting of form, function andbehavior, Automation in Construction 8, 1999, pp. 351-367.

    14. Gijsbertus T. Luiten, Frits P. Tolman and Martin A. Fischer,Project-modeling in AEC to integrate design andconstruction, Computers in Industry 35, 1998, pp. 13-29.

    References

    http://www.bartlett.ucl.ac.uk/vircon/http://www.bartlett.ucl.ac.uk/vircon/
  • 7/29/2019 final_Kim

    52/52

    References

    14. Paul Teicholz, Vision of Future Practice, White paper on AEC

    Practice and Research Issues for the Future.

    15. Peter Barrett, Construction management pull for 4D CAD,University of Salford.

    16. Leonardo Rischmoller, 4D-PS: Putting an IT new workprocess into effect, Bechtel Group, Inc., June 12, 2002

    17. Martin Fischer, Building better by building virtually first,Stanford University