Page 1 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Financial analysis of the sufficiency of Brattle’s
estimated ATWACC to support investment in a new
merchant peaker in Alberta
prepared by London Economics International LLC
July 6, 2018
Alberta is currently in the process of moving from an energy-only market design to an energy &
capacity market design. London Economics International LLC (“LEI”) was retained by
TransAlta Corporation (“TransAlta”) to review the methodologies proposed by the Brattle
Group (“Brattle”), AESO’s consultant, to estimate the After-tax Weighted Average Cost of
Capital (“ATWACC”) underpinning its Gross Cost of New Entry (“Gross CONE”) calculation.
In this memo, LEI presents quantitative evidence demonstrating that using Brattle’s ATWACC,
the resulting Gross CONE, and other assumptions from AESO, coupled with a more realistic
consideration of the debt structure (as would be required by any financial institution lending to
such a merchant generation project) leads to a lower return on equity for investors than the
expected returns Brattle identified in its justification for the cost of equity. This financial
analysis suggests that the ATWACC estimated by Brattle is too low, and therefore a capacity
price based on this ATWACC and associated Gross CONE would lead to an outcome where
investing in a merchant peaker in Alberta would not be an attractive economic investment.
Table of contents 1 WHY IS PROPER ESTIMATION OF THE CONE VALUE IMPORTANT TO THE CAPACITY MARKET DESIGN? ..... 2
2 OVERVIEW OF BRATTLE’S ATWACC ............................................................................................................... 2
3 FINANCING ASSUMPTIONS IMPLIED IN BRATTLE’S ATWACC CALCULATIONS ARE NOT REALISTIC ......... 3
3.1 THE SIZE OF DEBT SHOULD BE DERIVED USING A TARGET DEBT-SERVICE COVERAGE RATIO FOR THE PROJECT
BASED ON A RANGE OF EXPECTED CASHFLOWS ....................................................................................................... 4 3.2 DEBT HAS TO BE PAID DOWN WITHIN THE LIFETIME OF THE PROJECT ........................................................... 6 3.3 LEI’S PRO FORMA MODEL DEMONSTRATES BRATTLE’S ATWACC IS UNREALISTIC ..................................... 7
3.3.1 Assumptions .......................................................................................................................................... 8 3.3.2 Adding in cash sweep provisions ......................................................................................................... 11 3.3.3 Less ideal market conditions scenario .................................................................................................. 13
4 APPENDIX ........................................................................................................................................................... 15
Page 2 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
1 Why is proper estimation of the CONE value important to the
capacity market design?
The Cost of New Entry (“CONE”) is a key component in capacity market design. The Brattle
Group (“Brattle”) stated that CONE is one of the estimates needed to “anchor” the proposed
capacity market’s sloped demand curve. During the capacity market demand curve design, a
Gross CONE, which aims to reflect the annualized carrying cost of a new generator based on a
reference technology appropriate for Alberta’s market, is first estimated. Then, an Energy and
Ancillary Services (“E&AS”) offset, is subtracted from the Gross CONE to arrive at a Net CONE.
However, Brattle stated that “the Net CONE will not determine the market clearing price of
capacity” (emphasis by Brattle), and “rather the market clearing price will depend on the offers
that suppliers make into the capacity market auction.”1
While Net CONE is not the only determining factor of the capacity market clearing price, it does
have an important impact on the capacity market clearing price. For example:
▪ holding other factors constant (demand forecast, reliability requirement, and supply), changes in Net CONE shift the capacity demand curve and change the point of intersection between the cumulative supply of capacity offers and the demand curve, therefore influencing the capacity clearing price; and,
▪ if the Net CONE is materially lower than the actual cost of a new efficient generator, in the long run the market may not be able to procure the resources it needs to achieve its reliability target, as the capacity clearing price may not be attractive enough for investors to build new generating units.
As such, ATWACC is critical to ensuring that a key desired end-state of AESO’s capacity market
design – new investment by the private sector – is achieved.
2 Overview of Brattle’s ATWACC
The key components of ATWACC relate to the cost of equity, the cost of debt, and the capital
structure or leverage, as illustrated in the formula below:
ATWACC = cost of equity x (1-debt/capital) + (1-tax rate) x cost of debt x (debt/capital)
In the June 14th 2018 Working Group materials, Brattle recommended an ATWACC of 8.0%, for
new generation investment in Alberta, based on the assumptions shown in the table below.
1 AESO. “Cost of New Entry – Preliminary Estimates Selection Criteria, Energy and Ancillary Services Offset DCWG
#4”. June 14, 2018. Slide 7.
Page 3 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Figure 1. Brattle’s recommendation for Merchant Generation Cost of Capital
Source: AESO. “Cost of new Entry – Preliminary Estimates Selection Criteria. Energy and Ancillary Services Offset.
DCWG #4.” June 14, 2018. Slide 19.
According to Brattle and its presentation in the April and June Working Groups, its approach in
estimating ATWACC is based on the following steps:2
▪ estimate the cost of equity using publicly available data of US and Canadian companies considered comparable with methods such as the Capital Asset Pricing Model (“CAPM”) and Discounted Cash Flow (“DCF”);
▪ use data on cost of debt and debt-to-equity ratio from the same group of comparable companies; and, finally
▪ adjust the ATWACC for: (1) consensus forecast of 2021 Canadian market conditions; (2) yields of 20-year Canadian bonds.
Brattle also referenced discount rates used in fairness opinions in IPP transactions and used these
discount rates as an additional benchmark for their recommended ATWACC.
Brattle stated that it did not consider the details of the actual financing arrangements in
developing its ATWACC. However, the details of the financing are critical to ensuring that the
ATWACC results in a Gross CONE and Net CONE that support investment in Alberta.
3 Financing assumptions implied in Brattle’s ATWACC calculations
are not realistic
LEI undertook a financial analysis that tests whether Brattle’s ATWACC and resulting Gross
CONE – when coupled with realistic financing requirements – can support investors in
generation in Alberta.
Capital structure is implicit in Brattle’s recommendation of an 8.0% fixed ATWACC over the life
of the reference generating unit. However, Brattle’s analysis only goes so far as to assume a
2 AESO. “Cost of new Entry – Preliminary Estimates Selection Criteria. Energy and Ancillary Services Offset. DCWG
#4.” June 14, 2018. Slide 19.
Page 4 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
leverage in the calculations of the ATWACC. To test the sufficiency of Brattle’s ATWACC, LEI
began by creating a pro forma financial model – similar to financial models that lenders would
create and test when considering lending to a project. The financial model starts with Brattle’s
ATWACC assumption and resulting Gross CONE and builds up to an income statement - with
revenues and costs - to estimate the cashflow generated by the project. LEI then added realistic
debt repayment terms.
3.1 The size of debt should be derived using a target debt-service coverage ratio for the
project based on a range of expected cashflows
Brattle developed the level of leverage of the reference technology based on the list of public
sample companies it used to estimate ATWACC. In this list of companies, there are moderately
leveraged Canadian generators and highly leveraged US generators. Using these sample
companies, Brattle assumed the level of debt-to-capital ratio of an Alberta merchant generation
cost of capital to be 50% to 65%. Brattle’s method in estimating ATWACC takes no consideration
of how debt financing would impact the project. In practice, the amount of debt a project can
borrow from banks is not derived from “peer reviews.” Rather, the level, pricing, and other terms
of the debt are typically a function of the earnings potential and revenue stability of the project.
LEI anticipates that the level of debt for peaker in Alberta would be significantly less than what
Brattle forecast if more realistic financing assumptions were incorporated.
Based on LEI’s experience in advising generation investors, as well as more common knowledge
about how merchant (unregulated) generation projects are financed, the key determining factor
for sizing the debt principal is the project’s expected debt service coverage ratio (“DSCR”),
defined as the ratio between the net operating income and debt payments (interest + principal
repayment). The available cash flow from operations is typically not certain and, to limit default
risk, lenders would want to ensure the borrower has enough cashflow cushion to pay its debt
obligations. The maximum size of the debt is therefore based on the level of debt and interest
payments, plus a cushion, that could be supported by such projected cashflows. This approach,
sometimes called “debt sculpting”, ensures that the project can expect to repay its principal and
interest in a timely manner.
Based on LEI’s experience with active lenders in the merchant generation space in North America,
bankers would typically require a DSCR of 2.0x to 3.0x for a merchant generating project.3
Although term loans from banks do not necessary require credit evaluation from credit agencies,
evaluation criteria from credit agencies serve as useful references. For example, Fitch Ratings has
3 Standard debt covenants may require specific levels of DSCR on a monthly, quarterly and/or annual basis. For the
purposes of this illustration, LEI conducted its analysis on an annual basis.
Page 5 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
stated that a full merchant exposure thermal power project with fully amortizing debt would
require an indicative DSCR of 1.8x in order obtain an investment grade BBB rating.4
Standard & Poor’s Project Finance Rating Criteria Reference Guide listed the DSCR as the key
metric in its project finance ratings framework, as presented in the green box in the Figure 2.5
Note that the DSCR is the only metric explicitly shown in the framework.
Figure 2. Standard and Poor’s Project Finance Ratings Framework
Source: Standard & Poor’s. “Standard & Poor’s Project Finance Ratings Criteria – Reference Guide”. September 16,
2014. Page 3.
In addition to DSCR, Standard & Poor’s uses a combination of market risk and operational risk
analysis to determine the credit rating of a project finance loan. For Standard and Poor’s,
merchant power plants are deemed to have moderate operational risk and moderate to high
market exposure. This combination of market and operation risk result in a high operational
4 Fitch Ratings. “Thermal Power Project Rating Criteria – Effective June 8, 2017 – June 1, 2018”. June 8, 2017
5 Standard & Poor’s. Accessible at:
https://www.spratings.com/documents/20184/86990/SPRS_Project%2BFinance%2BRatings%2BCriteria%2B
Reference%2BGuide_FINAL/cdfde690-57d1-4ff4-a87f-986527603c22
Page 6 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
phase business risk,6 leading to a DSCR requirement 2.5x to 5.0x for in order to obtain an
investment grade BBB rating.
In addition, lenders will routinely consider “low revenue” cases or “debt cases” for projected
cashflows in order to understand how the DSCR may vary with uncertain and volatile market
conditions. Although beyond the scope of LEI’s current quantitative exercise, LEI would suggest
that AESO similarly conduct a thorough sensitivity analysis on future potential energy and
capacity revenues for a merchant peaker as part of its rationalization of Brattle’s ATWACC.
3.2 Debt has to be paid down within the lifetime of the project
It is important to remember that the estimation of Gross CONE includes the return on and return
of capital over a specified timeframe. As a physical asset, the reference unit has various
timeframes – there is the “tax” life for purposes of calculating depreciation; there is the financing
term (and associated amortization requirements of the debt principal); there is the engineering
life (timeframe over which the equipment is expected to function without significant
deterioration); and finally there is the economic life (timeframe where the asset has an economic
useful life).
The 20-year assumption commonly used in the US for considering generation assets’ ATWACC
is neither the engineering life or the economic life of the asset, but rather its “tax” life. As is
common in the US, Brattle assumed that the economic life of a merchant generation unit in
Alberta is 20 years.7 Brattle did not tailor this assumption to Alberta’s market or to the different
generation technologies considered.
Brattle also assumed that the capital structure would remain constant throughout this economic
lifetime (as it uses the same ATWACC to discount the CONE over 20 years). This is an unrealistic
assumption, as the debt principal has to be paid down over time. Even though the project could
possibly obtain refinancing over its lifetime, the previous debt would still have to be repaid and
cash has to be set aside for principal repayment reserves. To achieve this pay down of principal,
project finance loans would typically include a cash sweep (or cash flow sweep) provision, under
which excess cash flows must be used to pay down debt. According to S&P, “these sweep
mechanisms can vary materially, both in terms of the percentage of excess cash flow that must be
6 Standard & Poor’s. “Standard & Poor’s Project Finance Ratings Criteria Reference Guide.” Page 145 Table 2 shows
that natural gas fired power stations as operating stability assessment rating of 5 to 6 out of a scale of 10 (lower
benign more stable). Page 157 Table 12 shows that merchant power plants have moderate to high market
exposure depending on level of contract. This combination results in a preliminary Operations Phase Business
Assessment score of 10 to 11, according to Table 1 in page 141.
7 AESO. “Cost of New Entry – Preliminary Estimates Selection Criteria. Energy and Ancillary Services Offset. DCWG
#4”. June 14, 2018. Slide 11.
Page 7 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
used to pay down debt (such as 100% or 50%), and the target level of debt paydown (i.e., the cash
flow sweep is no longer effective once a certain amount of debt has been paid down).”8
A constant capital structure over time would not be a realistic assumption for a physical asset
with a limited economic life. To test these assumptions, LEI’s pro forma financial model also
considers cash sweeps.
3.3 LEI’s pro forma model demonstrates Brattle’s ATWACC is unrealistic
LEI’s pro forma financial model relies on Brattle’s capital and debt costs assumptions, associated
Gross CONE and Net CONE values (based on AESO’s energy revenue assumptions). In addition,
LEI’s financial model reflects realistic debt provisions such as an appropriate DSCR and cash
sweep when determining the debt size and modeling the project’s cash flow.
The finance textbook “Corporate and Project Finance Modeling” describes four different methods
for sculpting debt: 9
1. using a solver tool to find both the repayments and the debt size by matching the target DSCR wit the modeled DSCR and setting the closing debt balance to zero;
2. using the definition of DSCR to determine the repayment and then sets the ending debt balance to zero by changing the debt size using the Goal Seek tool;
3. uses the fact that net present value of debt service is equal to the remaining debt balance to establish the size of the debt; and ,
4. backward induction approach that begins with a zero balance at the end of the debt term, and work backwards to establish the amount of the debt at commercial operation.
The method LEI uses in the pro forma model is the third method. The logic of LEI’s pro forma
model is presented in Figure 3.
8 Standard & Poor’s. “Standard & Poor’s Project Finance Ratings Criteria – Reference Guide”. September 16, 2014.
Page 85.
9 Edward Bodme. “Corporate and Project Finance Modeling.” October 2014. Chapter 41.
Page 8 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Figure 3. Illustration of merchant peaker pro forma model logic
It should be noted that the purpose of the model is not to suggest the correct assumed leverage
or specific DSCR or cash sweep values for a merchant peaking plant in Alberta. Instead, the pro
forma model is intended to numerically illustrate the internal inconsistency between Brattle’s
ATWACC and realistic financing requirements that would affect returns for investors. The
financial modeling analysis show that once certain reasonable debt structure requirements are
added to the financial analysis, the expected return to equity would be unattractively low for
investors. LEI recommends that AESO request that Brattle consider such real-world financing
considerations in its final Gross CONE calculations.
3.3.1 Assumptions
Using Gross CONE assumptions developed by Brattle and AESO’s energy & AS offset value to
yield a preliminary Net CONE, LEI created a 20-year pro forma financial. The key assumptions10
include:
▪ the reference technology is an Aero-Type combustion Turbine with capital costs at Cdn. $1,533/kW, consistent with Brattle’s presentation on June 14, 2018
10 The capital cost, ATWACC, resulting Gross CONE, and fixed O&M expenses, are all based on Brattle’s
assumptions presented to AESO’s Technical Working Group Session #4 on June 14, 2018, while the energy
profits are based on AESO’s presentation for Technical Working Group Meeting #3 on May 4, 2018. (Note, the
energy profits are an implied value, based on a Gross CONE of Cdn. $224.9/kW-year and the Net CONE in
2021 of Cdn. $45.19/kW-year presented by AESO using preliminary estimates off of forward prices).
AESO’s upfront capital cost
Brattle’s ATWACC
Gross CONEAnnual capacity + energy profit
AESO’s fixed O&M costs
EBITDADSCR
requirement
Maximum serviceable loan
Brattle’s cost of debt
Loan tenure
Annual interest payment
Annual principal
repaymentAnnual
Depreciation
EBIT Tax rateCash flow to equity holder
Realized ROE
Minimum upfront equity
Cash sweep percentage
AESO/Brattle assumption
LEI assumption based on common debt terms
Implied/calculated number
Color code
Page 9 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
▪ the cost of debt is assumed to be 6%, based on Brattle’s low-end estimate consistent with Brattle’s presentation on June 14, 2018;
▪ debt term of 20 years based on Brattle assumption in presentation on June 14, 2018; ▪ tax rate of 27%, same as Brattle’s assumption from presentation on June 14, 2018; ▪ the generator would be able to earn exactly the forecasted energy profits in the energy
market every year that correspond to AESO’s estimate of E&AS, which are captured in a Net CONE;
▪ the generator would be able to earn a capacity price exactly equal to this same Net CONE in the capacity market every year; and
▪ the generator would incur exactly the same amount of expected fixed O&M costs over its lifetime as was estimated in the Gross CONE.
The amount of debt is based on the DSCR threshold of 2.5x instead of an assumed level of
leverage. In addition, LEI considered the requirement for cash sweeps. The model’s primary
output is a calculated return on equity, which is then compared to the returns that Brattle
identified in its ATWACC analysis.
A truncated snapshot of the financial pro forma showing the results for 2021-2026 is presented in
Figure 4 below. The full 20-year (2021-2040) model is available in the appendix. With a DSCR
requirement of 2.5x, the project would be able to obtain an initial 50% debt-to-capital ratio.
However, the realized return on equity (shown as internal rate of return (“IRR”) value), is only
9.23%, which is lower than the cost of equity range of 11.6% to 13.4% assumed by Brattle in its
ATWACC calculation.
Page 10 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Figure 4. Project proforma with debt sized using 2.5x DSCR (2021-2026) (Cdn.$)
Source: LEI analysis
Note that in the model, the DSCR is fixed over the modeling period because the net operating
income does not change. Therefore, the DSCR’s limiting constraint on debt size is fixed, and
refinancing is not a realistic option to the project unless a new financier is willing to take on a
higher level of risk than the original lender, or the expected revenue of the project increases. As
debt principal is being paid down over time, the return on equity realized by the project would
Peaker 2021 2022 2023 2024 2025 2026
Financing
Upfront Capital cost ($/kW) 1,533.00$
Debt ($/kW) 50% $767.57
Equity ($/kW) 50% $765.43
Cost of debt (%) 6.00%
IRR on equity (%) 9.23%
Tax rate 27%
Assumed ATWACC 8.00%
Assumed debt term 20
Cash sweep 0%
Target DSCR 2.5
Interest expense ($/kW) $46.05 $44.80 $43.47 $42.07 $40.58 $39.00
Base principal repayment ($/kW) $20.87 $22.12 $23.45 $24.85 $26.34 $27.92
Cash Sweep Principal payment ($/kW) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Remaining principal ($/kW) $767.57 $746.70 $724.58 $701.14 $676.29 $649.94 $622.02
Implied debt term 20.00
Debt service amount $66.92 $66.92 $66.92 $66.92 $66.92 $66.92
Average life-time leverage 28.5%
Cash flow
Capacity market revenue ($/kW) 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$
Energy market profit ($/kW) 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$
Fixed O&M 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$
EBITDA ($/kW) 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$
DSCR 2.50 2.50 2.50 2.50 2.50 2.50
Maximum annual debt service amount ($/kW) 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$
Interest payment ($/kW) 46.05$ 44.80$ 43.47$ 42.07$ 40.58$ 39.00$
Depreciation ($/kW) 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$
EBIT ($/kW) 44.60$ 45.85$ 47.18$ 48.58$ 50.07$ 51.65$
Tax 12.04$ 12.38$ 12.74$ 13.12$ 13.52$ 13.95$
FCFE (765.43)$ 88.34$ 88.00$ 87.64$ 87.26$ 86.86$ 86.43$
GROSS CONE implied from Assumed ATWACC 224.9 224.9 224.9 224.9 224.9 224.9
Assumed eneryg profits 179.7 179.7 179.7 179.7 179.7 179.7
Net CONE 45.2 45.2 45.2 45.2 45.2 45.2
Clearing price (multiple of Net CONE) 1 45.2 45.2 45.2 45.2 45.2 45.2
Legend
Brattle's Assumption
LEI Assumption
Key model Outputs
Page 11 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
be lower than the assumed cost of equity in Brattle’s ATWACC, as not all available cash is payable
to the equity owner.
This means that Brattle’s ATWACC and Gross CONE methodology is internally inconsistent. By
taking into account a realistic and fundamental aspect of the financing - the DSCR - the capital
structure will result in a situation where an equity investor will not be able to achieve the return
on equity assumed within the ATWACC that Brattle developed to get to the Gross CONE value.
In other words, a capacity demand curve derived from the ATWACC proposed by Brattle will
not result in an attractive return to investors – the realized return to equity for investors would
actually be lower than the risk-adjusted return that Brattle uses to estimate its ATWACC.
3.3.2 Adding in cash sweep provisions
In addition, it is possible that the financing institution would want to add a cash sweep provision
in the debt structure for a new generation project. Such provisions have become common in a
merchant power environment, in order to protect lenders against volatile and sometimes
prolonger uneconomic market conditions. Lenders use cash sweeps to guard against a risk that
the asset may be functionally obsolete before all the debt is paid down (or refinanced). As such,
cash sweeps are a way for lenders to mandate loan repayment over a shorter timeframe than the
nominal term of the load. For example, if the financing institution expects the total bankable life
of the merchant peaker to be 15 years11 - with the initial loan term being 10 years and a re-
financing contemplated for an additional five years, then it is possible that the bank would ask
for a cash sweep would be 70% - such that the initial loan is expected to be fully repaid around
year 10.
A truncated model showing the proforma with a 70% cash sweep, but at a lower DSCR of 1.8x
requirement (to offset the cash sweep provision, which lowers the riskiness of the loan, and also
reflecting the low end of DSCR requirement for investment grade bond based on Fitch Ratings’
guidance presented earlier in the paper), for 2021-2026 is presented in the figure below. The full
20-year (2021-2040) model is available in the appendix. In this scenario, due to the lower DSCR,
the project would be able to increase its leverage to 70%. However, without refinancing after the
first loan is paid down, the return on equity is only 8.86%, which again shows that a merchant
peaker in Alberta would be an unattractive investment as compared to the 11.6% to 13.4% return
on equity required by investors in Brattle’s ATWACC.
11 For reference in the US, the modified accelerated cost recovery system (“MACRS”) schedule of a combustion
turbine is 15 years
Page 12 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Figure 5. Pro forma model with 70% cash sweep and 1.8x DSCR (2021-2026) (Cdn.$)
Source: LEI analysis
As an additional verification of the conclusions, LEI also tested what would happen if the project
were to obtain refinancing in year 11 with a 5-year loan, and the size of the loan were based on a
1.8x DSCR for the subsequent five years. This scenario resulted in a return on equity of 9.12%,
which is an improvement over no-refinancing, but still lower than Brattle’s assumed return on
Peaker 2021 2022 2023 2024 2025 2026
Financing
Upfront Capital cost ($/kW) 1,533.00$
Debt ($/kW) 70% $1,066.07
Equity ($/kW) 30% $466.93
Cost of debt (%) 6.00%
IRR on equity (%) 8.86%
Tax rate 27%
Assumed ATWACC 8.00%
Assumed debt term 20
Cash sweep 70%
Target DSCR 1.8
Interest expense ($/kW) $63.96 $59.40 $54.62 $49.61 $44.35 $38.84
Base principal repayment ($/kW) $28.98 $33.54 $38.32 $43.33 $48.59 $54.11
Cash Sweep Principal payment ($/kW) $47.01 $46.14 $45.24 $44.29 $43.30 $42.26
Remaining principal ($/kW) $1,066.07 $990.08 $910.40 $826.84 $739.21 $647.32 $550.96
Implied debt term 11.00
Debt service amount $92.94 $92.94 $92.94 $92.94 $92.94 $92.94
Average life-time leverage 18.9%
Cash flow
Capacity market revenue ($/kW) 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$
Energy market profit ($/kW) 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$
Fixed O&M 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$
EBITDA ($/kW) 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$
DSCR 1.80 1.80 1.80 1.80 1.80 1.80
Maximum annual debt service amount ($/kW) 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$
Interest payment ($/kW) 63.96$ 59.40$ 54.62$ 49.61$ 44.35$ 38.84$
Depreciation ($/kW) 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$
EBIT ($/kW) 26.69$ 31.25$ 36.03$ 41.04$ 46.30$ 51.81$
Tax 7.21$ 8.44$ 9.73$ 11.08$ 12.50$ 13.99$
FCFE (466.93)$ 20.15$ 19.78$ 19.39$ 18.98$ 18.56$ 18.11$
GROSS CONE implied from Assumed ATWACC 224.9 224.9 224.9 224.9 224.9 224.9
Assumed eneryg profits 179.7 179.7 179.7 179.7 179.7 179.7
Net CONE 45.2 45.2 45.2 45.2 45.2 45.2
Clearing price (multiple of Net CONE) 1 45.2 45.2 45.2 45.2 45.2 45.2
Legend
Brattle's Assumption
LEI Assumption
Key model Outputs
Page 13 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
equity in its recommended ATWACC. The detailed model for this additional verification scenario
is available in the appendix.
key finding from the pro forma modeling exercise is that the return on equity realized by a
merchant peaking plant would be less than the assumed cost of equity in Brattle’s ATWACC, and
the reason for this is because Brattle has not considered the realistic debt requirements that will
drive the financing of such merchant generation projects. Therefore, Brattle’s estimated
ATWACC of 8% is too low. As a consequence, the resulting Net CONE will not attract private
investment. This conclusion is not conditioned on the specific DSCR multiple and cash sweep
percentage. Indeed, as shown in Figure 6, the realized return on equity will be below the assumed
cost of equity in Brattle’s ATWACC under a variety of SCR and cash sweep considerations.
Figure 6. Sensitivity analysis on return on equity under different debt terms (DSCR and cash sweep)
3.3.3 Less ideal market conditions scenario
The results of the financial model presented in Figure 4 and Figure 5 reflect ideal market outcomes
– the reference peaker would not readily expect to always earn capacity revenues at its Net CONE
and energy revenues consistent with that the Net CONE projection. There are many risks to
future energy and capacity markets. Therefore, the analyses and conclusions presented above are
likely an overly optimistic reflection of potential market outcomes. In order for the capacity
market to clear at Net CONE every year, it would require new generators to clear the capacity
market every year. If this is not the case, the capacity market would likely clear below Net CONE
as “new” resources that cleared in previous years would become “existing” resources and would
bid their avoidable costs, which would be well below the Net CONE.
Furthermore, in the pro forma model presented in Figure 5, at a 6% cost of debt, the level of
leverage is 70%. But according to Brattle’s analysis, at a 65% leverage, it would expect the cost of
debt to be 100 basis points higher, at 7%. This would increase the interest payments each year,
which in turn would lower the amount of debt the project could carry due to limitations from the
DSCR.
To illustrate a less idealized market revenue outlook, we created another scenario for the
proforma model. While keeping the 70% cash sweep and 1.8x DSCR, we further assumed that
after the first year, the capacity market would clear at 0.9x Net CONE instead of 1.0x Net CONE
to reflect the likelihood that new assets would not clear the capacity market every year.
Furthermore, we increased the cost of debt from 6.0% to 6.5% to reflect a higher level of leverage.
10.27% 0% 25% 50% 75% 100%
1.8 12.2% 10.3% 9.3% 8.8% 8.4%
2.0 10.8% 9.3% 8.6% 8.2% 8.0%
2.5 9.2% 8.2% 7.8% 7.6% 7.5%
3.0 8.5% 7.8% 7.5% 7.3% 7.3%
3.5 8.2% 7.5% 7.3% 7.2% 7.1%
DS
CR
(x)
Cash sweep (%)
Page 14 of 18
London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Note that these are still very pragmatic assumptions for the Alberta capacity market, and would
not constitute a true “debt” or “low” case scenario that lenders would use to stress test the
financials and size the debt. Figure 7 presents the results of this adjusted (lower revenue and
higher debt cost) pro forma model over the 2021-2026 timeframe. The full 20-year version of this
proforma model is available in the appendix. As show below, the return on equity in this scenario
drops to 7.81%. A rational investor would not invest in a merchant peaking generator project for
this level of return on equity.
Figure 7. Pro forma model with lower capacity market revenue and higher debt cost (2021-2026) (Cdn.$)
Source: LEI analysis
Peaker 2021 2022 2023 2024 2025 2026
Financing
Upfront Capital cost ($/kW) 1,533.00$
Debt ($/kW) 65% $996.44
Equity ($/kW) 35% $536.56
Cost of debt (%) 6.50%
IRR on equity (%) 7.81%
Tax rate 27%
Assumed ATWACC 8.00%
Assumed debt term 20
Cash sweep 70%
Target DSCR 1.8
Interest expense ($/kW) $64.77 $59.92 $54.97 $49.75 $44.26 $38.49
Base principal repayment ($/kW) $25.66 $30.51 $35.47 $40.68 $46.17 $51.95
Cash Sweep Principal payment ($/kW) $48.92 $45.69 $44.75 $43.77 $42.73 $41.64
Remaining principal ($/kW) $996.44 $921.86 $845.66 $765.44 $680.99 $592.09 $498.51
Implied debt term 11.00
Debt service amount $90.43 $90.43 $90.43 $90.43 $90.43 $90.43
Average life-time leverage 17.2%
Cash flow
Capacity market revenue ($/kW) 45.20$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$
Energy market profit ($/kW) 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$
Fixed O&M 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$
EBITDA ($/kW) 167.30$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$
DSCR 1.80 1.80 1.80 1.80 1.80 1.80
Maximum annual debt service amount ($/kW) 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$
Interest payment ($/kW) 64.77$ 59.92$ 54.97$ 49.75$ 44.26$ 38.49$
Depreciation ($/kW) 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$
EBIT ($/kW) 25.88$ 26.21$ 31.16$ 36.38$ 41.87$ 47.64$
Tax 6.99$ 7.08$ 8.41$ 9.82$ 11.30$ 12.86$
FCFE (536.56)$ 20.96$ 19.58$ 19.18$ 18.76$ 18.31$ 17.84$
GROSS CONE implied from Assumed ATWACC 224.9 224.9 224.9 224.9 224.9 224.9
Assumed eneryg profits 179.7 179.7 179.7 179.7 179.7 179.7
Net CONE 45.2 45.2 45.2 45.2 45.2 45.2
Clearing price (multiple of Net CONE)0.9 45.2 40.7 40.7 40.7 40.7 40.7
Legend
Brattle's Assumption
LEI Assumption
Key model Outputs
Page 15 of 18 London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
4 Appendix
Figure 8. Project proforma using Brattle’s ATWACC and Gross CONE assumptions with debt sized using a 2.5x DSCR (Cdn.$)
Peaker 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Financing
Upfront Capital cost ($/kW) 1,533.00$
Debt ($/kW) 50% $767.57
Equity ($/kW) 50% $765.43
Cost of debt (%) 6.00%
IRR on equity (%) 9.23%
Tax rate 27%
Assumed ATWACC 8.00%
Assumed debt term 20
Cash sweep 0%
Target DSCR 2.5
Interest expense ($/kW) $46.05 $44.80 $43.47 $42.07 $40.58 $39.00 $37.32 $35.55 $33.66 $31.67 $29.55 $27.31 $24.93 $22.41 $19.74 $16.91 $13.91 $10.73 $7.36 $3.79
Base principal repayment ($/kW) $20.87 $22.12 $23.45 $24.85 $26.34 $27.92 $29.60 $31.37 $33.26 $35.25 $37.37 $39.61 $41.99 $44.51 $47.18 $50.01 $53.01 $56.19 $59.56 $63.13
Cash Sweep Principal payment ($/kW) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Remaining principal ($/kW) $767.57 $746.70 $724.58 $701.14 $676.29 $649.94 $622.02 $592.42 $561.05 $527.79 $492.54 $455.17 $415.56 $373.57 $329.07 $281.89 $231.88 $178.88 $122.69 $63.13 $0.00
Implied debt term 20.00
Debt service amount $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92 $66.92
Average life-time leverage 28.5%
Cash flow
Capacity market revenue ($/kW) 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$
Energy market profit ($/kW) 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$
Fixed O&M 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$
EBITDA ($/kW) 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$
DSCR 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50
Maximum annual debt service amount ($/kW) 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$ 66.92$
Interest payment ($/kW) 46.05$ 44.80$ 43.47$ 42.07$ 40.58$ 39.00$ 37.32$ 35.55$ 33.66$ 31.67$ 29.55$ 27.31$ 24.93$ 22.41$ 19.74$ 16.91$ 13.91$ 10.73$ 7.36$ 3.79$
Depreciation ($/kW) 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$
EBIT ($/kW) 44.60$ 45.85$ 47.18$ 48.58$ 50.07$ 51.65$ 53.33$ 55.10$ 56.99$ 58.98$ 61.10$ 63.34$ 65.72$ 68.24$ 70.91$ 73.74$ 76.74$ 79.92$ 83.29$ 86.86$
Tax 12.04$ 12.38$ 12.74$ 13.12$ 13.52$ 13.95$ 14.40$ 14.88$ 15.39$ 15.93$ 16.50$ 17.10$ 17.74$ 18.42$ 19.14$ 19.91$ 20.72$ 21.58$ 22.49$ 23.45$
FCFE (765.43)$ 88.34$ 88.00$ 87.64$ 87.26$ 86.86$ 86.43$ 85.98$ 85.50$ 84.99$ 84.45$ 83.88$ 83.28$ 82.64$ 81.96$ 81.24$ 80.47$ 79.66$ 78.80$ 77.89$ 76.93$
GROSS CONE implied from Assumed ATWACC 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9
Assumed eneryg profits 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7
Net CONE 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2
Clearing price (multiple of Net CONE)1 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2
Page 16 of 18 London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Figure 9. Pro forma model with 70% cash sweep and debt sized using a 1.8x DSCR (Cdn.$)
Peaker 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Financing
Upfront Capital cost ($/kW) 1,533.00$
Debt ($/kW) 70% $1,066.07
Equity ($/kW) 30% $466.93
Cost of debt (%) 6.00%
IRR on equity (%) 8.86%
Tax rate 27%
Assumed ATWACC 8.00%
Assumed debt term 20
Cash sweep 70%
Target DSCR 1.8
Interest expense ($/kW) $63.96 $59.40 $54.62 $49.61 $44.35 $38.84 $33.06 $26.99 $20.64 $13.97 $6.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Base principal repayment ($/kW) $28.98 $33.54 $38.32 $43.33 $48.59 $54.11 $59.89 $65.95 $72.31 $78.98 $85.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cash Sweep Principal payment ($/kW) $47.01 $46.14 $45.24 $44.29 $43.30 $42.26 $41.16 $40.02 $38.82 $37.56 $30.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Remaining principal ($/kW) $1,066.07 $990.08 $910.40 $826.84 $739.21 $647.32 $550.96 $449.91 $343.94 $232.81 $116.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Implied debt term 11.00
Debt service amount $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Average life-time leverage 18.9%
Cash flow
Capacity market revenue ($/kW) 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$
Energy market profit ($/kW) 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$
Fixed O&M 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$
EBITDA ($/kW) 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$
DSCR 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80
Maximum annual debt service amount ($/kW) 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$
Interest payment ($/kW) 63.96$ 59.40$ 54.62$ 49.61$ 44.35$ 38.84$ 33.06$ 26.99$ 20.64$ 13.97$ 6.98$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Depreciation ($/kW) 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$
EBIT ($/kW) 26.69$ 31.25$ 36.03$ 41.04$ 46.30$ 51.81$ 57.59$ 63.66$ 70.01$ 76.68$ 83.67$ 90.65$ 90.65$ 90.65$ 90.65$ 90.65$ 90.65$ 90.65$ 90.65$ 90.65$
Tax 7.21$ 8.44$ 9.73$ 11.08$ 12.50$ 13.99$ 15.55$ 17.19$ 18.90$ 20.70$ 22.59$ 24.48$ 24.48$ 24.48$ 24.48$ 24.48$ 24.48$ 24.48$ 24.48$ 24.48$
FCFE (466.93)$ 20.15$ 19.78$ 19.39$ 18.98$ 18.56$ 18.11$ 17.64$ 17.15$ 16.64$ 16.10$ 21.45$ 142.82$ 142.82$ 142.82$ 142.82$ 142.82$ 142.82$ 142.82$ 142.82$ 142.82$
GROSS CONE implied from Assumed ATWACC 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9
Assumed eneryg profits 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7
Net CONE 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2
Clearing price (multiple of Net CONE)1 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2
Page 17 of 18 London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Figure 10. Pro forma model with 70% cash sweep and debt sized using a 1.8x DSCR and refinancing (Cdn.$)
Peaker 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Financing
Upfront Capital cost ($/kW) 1,533.00$
Debt ($/kW) 70% $1,066.07
Equity ($/kW) 30% $466.93
Cost of debt (%) 6.00%
IRR on equity (%) 9.12%
Tax rate 27%
Assumed ATWACC 8.00%
Assumed debt term 20
Cash sweep 70%
Target DSCR 1.8
Interest expense ($/kW) $63.96 $59.40 $54.62 $49.61 $44.35 $38.84 $33.06 $26.99 $20.64 $13.97 $6.98 $23.49 $16.96 $10.12 $2.94 $0.00 $0.00 $0.00 $0.00 $0.00
Base principal repayment ($/kW) $28.98 $33.54 $38.32 $43.33 $48.59 $54.11 $59.89 $65.95 $72.31 $78.98 $85.97 $69.45 $75.98 $82.83 $48.95 $0.00 $0.00 $0.00 $0.00 $0.00
Cash Sweep Principal payment ($/kW) $47.01 $46.14 $45.24 $44.29 $43.30 $42.26 $41.16 $40.02 $38.82 $37.56 $30.31 $39.36 $38.12 $36.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
New debt $391.52
Remaining principal ($/kW) $1,066.07 $990.08 $910.40 $826.84 $739.21 $647.32 $550.96 $449.91 $343.94 $232.81 $116.28 $391.52 $282.71 $168.60 $48.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Implied debt term 15.00
Debt service amount $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $92.94 $51.88 $0.00 $0.00 $0.00 $0.00 $0.00
Average life-time leverage 21.9%
Cash flow
Capacity market revenue ($/kW) 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$ 45.20$
Energy market profit ($/kW) 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$
Fixed O&M 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$
EBITDA ($/kW) 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$ 167.30$
DSCR 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80
Maximum annual debt service amount ($/kW) 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$
Interest payment ($/kW) 63.96$ 59.40$ 54.62$ 49.61$ 44.35$ 38.84$ 33.06$ 26.99$ 20.64$ 13.97$ 6.98$ 23.49$ 16.96$ 10.12$ 2.94$ -$ -$ -$ -$ -$
Depreciation ($/kW) 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$
EBIT ($/kW) 26.69$ 31.25$ 36.03$ 41.04$ 46.30$ 51.81$ 57.59$ 63.66$ 70.01$ 76.68$ 83.67$ 67.16$ 73.69$ 80.53$ 87.71$ 90.65$ 90.65$ 90.65$ 90.65$ 90.65$
Tax 7.21$ 8.44$ 9.73$ 11.08$ 12.50$ 13.99$ 15.55$ 17.19$ 18.90$ 20.70$ 22.59$ 18.13$ 19.90$ 21.74$ 23.68$ 24.48$ 24.48$ 24.48$ 24.48$ 24.48$
FCFE (466.93)$ 20.15$ 19.78$ 19.39$ 18.98$ 18.56$ 18.11$ 17.64$ 17.15$ 16.64$ 16.10$ 412.97$ 16.87$ 16.34$ 15.78$ 91.73$ 142.82$ 142.82$ 142.82$ 142.82$ 142.82$
Remaining borrowing power -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 41.06$ 92.94$ 92.94$ 92.94$ 92.94$ 92.94$
GROSS CONE implied from Assumed ATWACC 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9
Assumed eneryg profits 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7
Net CONE 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2
Clearing price (multiple of Net CONE)1 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2
Page 18 of 18 London Economics International LLC contact:
717 Atlantic Ave, Suite 1A Julia Frayer/ Victor Chung
Boston, MA 02111 Tel: (617) 933-7221
www.londoneconomics.com [email protected]
Figure 11. Pro forma model with lower capacity market revenue and higher cost of debt (Cdn.$)
Peaker 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Financing
Upfront Capital cost ($/kW) 1,533.00$
Debt ($/kW) 65% $996.44
Equity ($/kW) 35% $536.56
Cost of debt (%) 6.50%
IRR on equity (%) 7.81%
Tax rate 27%
Assumed ATWACC 8.00%
Assumed debt term 20
Cash sweep 70%
Target DSCR 1.8
Interest expense ($/kW) $64.77 $59.92 $54.97 $49.75 $44.26 $38.49 $32.40 $26.00 $19.26 $12.16 $4.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Base principal repayment ($/kW) $25.66 $30.51 $35.47 $40.68 $46.17 $51.95 $58.03 $64.43 $71.18 $78.27 $72.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cash Sweep Principal payment ($/kW) $48.92 $45.69 $44.75 $43.77 $42.73 $41.64 $40.49 $39.28 $38.00 $36.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Remaining principal ($/kW) $996.44 $921.86 $845.66 $765.44 $680.99 $592.09 $498.51 $399.99 $296.28 $187.10 $72.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Implied debt term 11.00
Debt service amount $90.43 $90.43 $90.43 $90.43 $90.43 $90.43 $90.43 $90.43 $90.43 $90.43 $76.86 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Average life-time leverage 17.2%
Cash flow
Capacity market revenue ($/kW) 45.20$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$ 40.68$
Energy market profit ($/kW) 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$ 179.70$
Fixed O&M 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$ 57.60$
EBITDA ($/kW) 167.30$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$ 162.78$
DSCR 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80
Maximum annual debt service amount ($/kW) 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$ 90.43$
Interest payment ($/kW) 64.77$ 59.92$ 54.97$ 49.75$ 44.26$ 38.49$ 32.40$ 26.00$ 19.26$ 12.16$ 4.69$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Depreciation ($/kW) 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$ 76.65$
EBIT ($/kW) 25.88$ 26.21$ 31.16$ 36.38$ 41.87$ 47.64$ 53.73$ 60.13$ 66.87$ 73.97$ 81.44$ 86.13$ 86.13$ 86.13$ 86.13$ 86.13$ 86.13$ 86.13$ 86.13$ 86.13$
Tax 6.99$ 7.08$ 8.41$ 9.82$ 11.30$ 12.86$ 14.51$ 16.24$ 18.06$ 19.97$ 21.99$ 23.26$ 23.26$ 23.26$ 23.26$ 23.26$ 23.26$ 23.26$ 23.26$ 23.26$
FCFE (536.56)$ 20.96$ 19.58$ 19.18$ 18.76$ 18.31$ 17.84$ 17.35$ 16.83$ 16.29$ 15.71$ 63.94$ 139.52$ 139.52$ 139.52$ 139.52$ 139.52$ 139.52$ 139.52$ 139.52$ 139.52$
GROSS CONE implied from Assumed ATWACC 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9 224.9
Assumed eneryg profits 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7 179.7
Net CONE 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2 45.2
Clearing price (multiple of Net CONE)0.9 45.2 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7 40.7