Financial Impact to Flood Control Projects using 1-D and 2-D Modelling Methods in South San Francisco Bay
Flood Plain Management Association
September 6, 2018
Presented by:
Matt Powers, PE – GEI Consultants
Rohin Saleh, PE - Alameda County Flood Control District
Alameda County Flood Control and Water Conservation District
Mission: Support public safety, health, and welfare of residents and businesses in Alameda County
Flood Control District established in 1949
10 zones based loosely on watersheds
Western Alameda County: EB Hills to Bay
Project Purpose
• Evaluate ability to maintain flood protection for the 1% Annual Exceedance Probability (1% AEP) coastal event– Impact of 1D and 2D approaches– What is cost of system improvements?
Study Overview• Evaluate coastal flooding scenarios and extents (1‐D and 2‐D)
• Identify existing flood protection alignments in study area
• Assess the current conditions and suitability for flood protection
• Develop planning level design and construction cost estimates– Protection for 1% AEP coastal event
• Results inform comprehensive flood protection strategy– Consider planned SBSPRP restoration
Eden Landing Site
Alameda Creek FCC
Old Alameda Creek
Eden Landing North
Eden Landing South
Site History• Pre‐European ‐ extensive tidal marsh
• 1850’s on: solar salt works
• Early 2000’s: Acquired for wetlands restoration
Eden Landing RestorationEden Landing North
Eden Landing Ecological Reserve (~2008)• North Creek and Mt. Eden Creek
breaches• Tidal and muted tidal connection
SBSPRP Phase 1 Improvements (2013)• Numerous breaches, levee construction• Tidal and managed ponds
Eden Landing South
Following Acquisition (2000’s)• Improvements to water control
structures
SBSPRP Phase 2 Improvements• Restoration planning and permitting
in progress
Updated Topographic Model• Composite DEM for Eden Landing from best available sources
– SFEI LIDAR, 2004– Sanborn LIDAR, 2006– USGS LIDAR, 2010– USACE LIDAR, 2012– DHI Composite DEM, 2016– QSI LIDAR and bathymetric transects, 2016– Wood Rodgers, Inc. field transects, 2016
Hydraulic Evaluations• Evaluate coastal flood impacts from 1% EAP tidal event
– Maximum tide: El. 10.5’ NAVD88
• Compare inundation extents using 1‐D and 2‐D methodologies– Current site conditions
• EL North: includes completed restoration• EL South: no significant restoration
– 1‐D analysis: proposed FEMA FIRM mapping– 2‐D analysis: completed during this study
Existing Flood Control Features• Existing condition assessment
– Site reconnaissance and mapping– Evaluation of as‐built records
• Identify Potential Flood Protection Levee Alignments– Consider completed and planned restoration– North complex – one identified alignment– South Complex – three identified alignments
Existing Flood Control Features
• Identified Flood Protection Levee Alignments– North complex alignment (1)
Existing Flood Control Features
• Identified Flood Protection Levee Alignments– South complex alignments (3)
Project Determination• Comparison of flood levels to existing flood protection features
– 1‐D and 2‐D flood extents
Project Determination• Comparison of flood levels to existing flood protection features
– Determine need for system improvements
Project Determination• Comparison of flood levels to existing flood protection features
– Determine need for system improvements
Project Determination• Comparison of flood levels to existing flood protection features
– Determine need for system improvements
High Ground
High Ground
Project Determination• Comparison of flood levels to existing flood protection features
– Determine need for system improvements
Project Determination• Comparison of flood levels to existing flood protection features
– Determine need for system improvements– Significant improvements? (Project / No Project)
Project Determination Criteria Project / No Project
Levee Contains Flood and Meets Required Freeboard (Coastal levees - 2 feet) No Project
Landside Ground Surface Elevation Greater Than Flood Elevation No Project
Existing Levee Not Certifiable Project
Levee Contains Flood but Does Not Meet Required Freeboard Project
Flood Elevation Greater Than Crest and Landside Elevation (Levee Overtopped) Project
Project Determination• Comparison of flood levels to existing flood protection features
– North Complex Alignment 1 (4.4 miles)
Project Determination Criteria
North Complex Alignment 1
2-D Analysis 1% AEP Coastal Flood Level
1-D Analysis 1% AEP Coastal Flood Level
Levee Meets Required Freeboard 4.4 mi(Entire Alignment)
0.5 mi
Landside Elevation Greater Than Flood Elevation None 0.2 mi
Existing Levee Not Certifiable None None
Levee Does Not Meet Required Freeboard None None
Flood Elevation Greater Than Crest and Landside Elevation None 3.7 mi
Project Determination• Comparison of flood levels to existing flood protection features
– South Complex Alignment 1 (3.3 miles)
Project Determination Criteria
South Complex Alignment 1
2-D Analysis 1% AEP Coastal Flood Level
1-D Analysis 1% AEP Coastal Flood Level
Levee Meets Required Freeboard None None
Landside Elevation Greater Than Flood Elevation None None
Existing Levee Not Certifiable 1.6 mi 0.1 mi
Levee Does Not Meet Required Freeboard 0.7 mi 0.2 mi
Flood Elevation Greater Than Crest and Landside Elevation 1.0 mi 3.0 mi
Project Determination• Comparison of flood levels to existing flood protection features
– South Complex Alignment 2 (1.2 miles)
Project Determination Criteria
South Complex Alignment 2
2-D Analysis 1% AEP Coastal Flood Level
1-D Analysis 1% AEP Coastal Flood Level
Levee Meets Required Freeboard None None
Landside Elevation Greater Than Flood Elevation None None
Existing Levee Not Certifiable 0.5 mi None
Levee Does Not Meet Required Freeboard 0.4 mi None
Flood Elevation Greater Than Crest and Landside Elevation 0.3 mi 1.2 mi(Entire Alignment)
Project Determination• Comparison of flood levels to existing flood protection features
– South Complex Alignment 3 (3.6 miles)
Project Determination Criteria
South Complex Alignment 3
2-D Analysis 1% AEP Coastal Flood Level
1-D Analysis 1% AEP Coastal Flood Level
Levee Meets Required Freeboard None None
Landside Elevation Greater Than Flood Elevation None None
Existing Levee Not Certifiable 0.8 mi None
Levee Does Not Meet Required Freeboard 2.8 mi None
Flood Elevation Greater Than Crest and Landside Elevation None 3.6 mi(Entire Alignment)
Conceptual Levee Improvements
• Levee Design Criteria– Freeboard: 2 feet for coastal levee– Cross Section:
• WS slope 5 to 1• LS slope 3 to 1• Crest width 18’ (allow future raise)
– Erosion Protection – vegetated slopes– Stability and under seepage
• USACE levee stability FS criteria
– Settlement: Bay Mud foundation– Consider suitable fill material and
construction approach
Construction Approach
Strip and excavate existing levee(north alignment ‐ partial degrade only)
Place geogrid and construct equipment corridor
Build levee embankment
Cost of Improvements• Conceptual cost estimates for construction
– 2017 cost basis– Base construction, non‐construction project costs
Non‐Construction Costs• Design engineering• CM and engineering during
construction• Environmental compliance /
permitting• Environmental mitigation• Legal / owner administration• Project contingency
Base Construction Costs• Mobilization / demobilization• Levee degrade• New Levee fill• Geotextile / geofabric• Foundation treatment• Hydroseeding• Misc. unlisted items
Estimated Project CostsEden Landing North (Phase 1)
1D Approach 2‐D Approach
Base Construction Costs $13.8MNo Significant
Improvements RequiredNon‐Construction Costs $7.2M
Total Estimated Cost $21M
Estimated Project CostsEden Landing South (Phase 2)
1D Approach 2‐D Approach
Align 1 Align 2 Align 3 Align 1 Align 2 Align 3Base Construction Costs $22.7M $15.4M $20.8M $13.0M $8.4M $9.6MNon‐Construction Costs $12.5M $8.5M $10.6M $7.2M $4.6M $5.3MTotal Estimated Cost $35.2M $23.9M $31.4M $20.2M $13.0M $14.9M(% Increase) 74% 84% 101% ‐‐‐ ‐‐‐ ‐‐‐
Conclusions• Modelling methodology has significant impact to flood control project costs– 1‐D analysis approach results in higher coastal flood levels within the Eden Landing site.
– Higher level of protection required• Significant improvements needed
– Higher project costs ‐ Real tax payer costs
Questions?
Conceptual Construction Cost Estimate
DescriptionNorth Flood Protection Alignment Alternative 1
South Flood Protection Alignment
Alternative 1
South Flood Protection Alignment
Alternative 2
South Flood Protection Alignment
Alternative 3
Construction Item
Mob/Demob $834,000 $1,404,000 $953,000 $1,253,000
Existing Levee Degrade
46,000 CY (see note 1)
146,000 CY 68,000 CY 121,000 CY
$506,000 $1,606,000 $748,000 $1,331,000
New Levee Fill238,000 CY 419,000 CY 298,000 CY 361,000 CY
$5,474,000 $9,637,000 $6,854,000 $8,303,000
Geotextile/Geofabric
159,000 SY 303,000 SY 204,000 SY 300,000 SY
$636,000 $1,212,000 $816,000 $1,200,000
Foundation Treatment19,300 LF 17,600 LF 12,400 LF 19,000 LF
$1,602,000 $1,461,000 $1,029,000 $1,577,000
Hydroseeding38 Acres 36 Acres 25 Acres 36 Acres
$125,000 $119,000 $83,000 $119,000
Unlisted Items $2,517,000 $4,254,000 $2,879,000 $3,795,000
Base Construction Subtotal
$11,694,000 $19,693,000 $13,362,000 $17,578,000
Non‐Construction Items
Engineering for Detailed Design
$1,169,000 $1,969,000 $1,336,000 $1,758,000
CM & Engineering Services
$1,754,000 $2,954,000 $2,004,000 $2,637,000
Environmental Compliance/Permitting
$585,000 $985,000 $668,000 $879,000
Environmental Mitigation
$1,754,000 $2,954,000 $2,004,000 $2,637,000
Right‐of‐Way Acquisition Not Applicable
Legal/Owner Administration
$468,000 $788,000 $534,000 $703,000
Financing Not Included
Escalation Not Included
Order‐of‐Magnitude Subtotal
Subtotal $17,424,000 $29,343,000 $19,908,000 $26,192,00
Program Order‐of‐Magnitude Total
Contingency $3,485,000 $5,869,000 $3,982,000 $5,238,000
Total Estimated Cost $20,909,000 $35,212,000 $23,890,000 $31,430,000
1-D Hydraulic Analysis, 1% AEP Event
Conceptual Construction Cost Estimate
Description
North Flood Protection Alignment
Alternative 1
South Flood Protection Alignment
Alternative 1
South Flood Protection Alignment
Alternative 2
South Flood Protection Alignment
Alternative 3
Construction Item
Mob/Demob
Not Applicable – No Significant
Improvements Required
$809,000 $520,000 $595,000
Existing Levee Degrade
146,000 CY 68,000 CY 121,000 CY
$1,606,000 $748,000 $1,331,000
New Levee Fill185,000 CY 127,000 CY 108,000 CY
$4,255,000 $2,921,000 $2,484,000
Geotextile/Geofabric
170,000 SY 111,000 SY 122,000 SY
$680,000 $444,000 $366,000
Foundation Treatment
17,600 LF 12,400 LF 19,000 LF
$1,461,000 $1,029,000 $1,557,000
Hydroseeding25 Acres 16 Acres 20 Acres
$83,000 $53,000 $66,000
Unlisted Items $2,426,000 $1,559,000 $1,784,000
Base Construction Subtotal $11,320,000 $7,274,000 $8,325,000
Non‐Construction Items
Engineering for Detailed Design
Not Applicable – No Significant
Improvements Required
$1,132,000 $727,000 $833,000
CM & Engineering Services
$1,698,000 $1,091,000 $1,249,000
Environmental Compliance/Permitting
$566,000 $364,000 $416,000
Environmental Mitigation
$1,698,000 $1,091,000 $1,249,000
Right‐of‐Way Acquisition
Not Applicable
Legal/Owner Administration
$453,000 $291,000 $333,000
Financing Not Included
Escalation Not Included
Order‐of‐Magnitude Subtotal
Subtotal Not Applicable $16,867,000 $10,838,000 $12,405,000
Program Order‐of‐Magnitude Total
ContingencyNot Applicable – No
Significant Improvements
Required
$3,373,000 $2,168,000 $2,481,000
Total Estimated Cost $20,240,000 $13,006,000 $14,886,000
2-D Hydraulic Analysis, 1% AEP Event