Fisk Corporate Headquarters Houston, Texas. Penn State AE Senior Capstone Project Stephen Blanchard – Construction Management Option Advisor: Dr. John Messner. Fisk Corporate Headquarters Houston, Texas. Stephen Blanchard Construction Management. Project Summary. Project Summary - PowerPoint PPT Presentation
Popular Tags:
37
Fisk Corporate Headquarters Houston, Texas Penn State AE Senior Capstone Project Stephen Blanchard – Construction Management Option
Transcript
Page 1: Fisk Corporate Headquarters Houston, Texas

Fisk Corporate HeadquartersHouston, Texas

Penn State AE Senior Capstone ProjectStephen Blanchard – Construction Management Option

Advisor: Dr. John Messner

Page 2: Fisk Corporate Headquarters Houston, Texas

Project Summary Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Project LocationHouston, Texas

Building InformationOffice Size: 37,780 Sq. FeetPre-Fab Size: 16,380 Sq. Feet2 Stories Above GradeStructural Steel

Construction LogisticsCost: $7,957,144Duration: 11/21/11 – 10/5/12Delivery: Design-Bid-BuildContract Type: Lump Sum

Ownership Team InformationFisk Electric Corp.Tutor Perini Corp.

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 3: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Problem Identification47 Week Construction DurationScheduling GapsLimited Activity Overlap (Finish to Start)

BackgroundExtensive General Conditions ImplicationsFisk Electric Carried General Conditions

Includes Tutor Perini Staffing and Fees

General Conditions OverviewTotal Cost: $1,122,90614% of Construction Costs

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 4: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Original Structure Erection ScheduleDuration: 90 DaysAll Activities on Critical PathRelationships: Finish to Start (All Activities)Separated Pours

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 5: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Re-Sequencing Process1. Remove All Schedule Gaps2. Re-Sequence Activities3. Identify Potential Overlap

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 6: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Re-Sequencing Process1. Remove All Schedule Gaps2. Re-Sequence Activities3. Identify Potential Overlap

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

OneMonth

Page 7: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Re-Sequencing Process1. Remove All Schedule Gaps2. Re-Sequence Activities3. Identify Potential Overlap

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 8: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Re-Sequencing Process1. Remove All Schedule Gaps2. Re-Sequence Activities3. Identify Potential Overlap

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 9: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Duration ResultsOverall Schedule Reduced by 4 WeeksNo Activity Durations Were Altered

Phase ReductionsOffice Sitework: 1 WeekOffice Structure: 2 WeeksOffice Interiors: 1 Week

Non-Critical Path Phase ReductionsFab-Shop Enclosure: 7 WeeksFab-Shop Interior: 2 WeeksLandscape/Hardscape: 2 Weeks

Phase Duration ComparisonProject Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 10: Fisk Corporate Headquarters Houston, Texas

Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

General Conditions Savings Breakdown General Conditions 5% Savings Cost Implications$50,698 Total GC Savings

Savings Type$45,780 in Weekly Savings$4,917 in Monthly Savings

Non-QuantifiableActivity Duration ReductionsCrew MobilizationsCrew Consistency

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 11: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Problem Identification$1,223,400 Electrical CostCostly Distribution SystemRedundant Components

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 12: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Problem Identification$1,223,400 Electrical CostCostly Distribution SystemRedundant Components

Original One-LineDiagram

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 13: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Redesign Process

1. Eliminate Distribution Panel Redundancy

2. Streamline Step-Down Voltage System

3. Back-Feed Data Center Distribution System

Eliminate Distribution Panel RedundancyProject Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 14: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Redesign Process

1. Eliminate Distribution Panel Redundancy

2. Streamline Step-Down Voltage System

3. Back-Feed Data Center Distribution System

Streamline Step-Down Voltage SystemProject Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 15: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Redesign Process

1. Eliminate Distribution Panel Redundancy

2. Streamline Step-Down Voltage System

3. Back-Feed Data Center Distribution System

Back-Feed Data Center Distribution SystemProject Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 16: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 17: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Combined Distribution PanelRedesign Results

1. Combined Distribution Panel

2. Single Step-Down Voltage Distribution System

3. Changes in Feeder Sizing and Distances

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 18: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Single Step-Down Voltage Distribution SystemRedesign Results

1. Combined Distribution Panel

2. Single Step-Down Voltage Distribution System

3. Changes in Feeder Sizing and Distances

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 19: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Changes in Feeder Sizing and DistancesRedesign Results

1. Combined Distribution Panel

2. Single Step-Down Voltage Distribution System

3. Changes in Feeder Sizing and Distances

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 20: Fisk Corporate Headquarters Houston, Texas

Electrical System Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Cost Impacts Schedule ImpactsConstructability ConcernsDavid RinehartTed Robertson

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 21: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Project LEED FactsA/E Instructed to Design LEED Facility

35% Additional Area – 60% of Electric Bill

48 Points Available w/ No Design Changes

Did Not Apply for LEED Building Certification

No Construction LEED Practices Implemented

Business CaseTax Incentives

1% Certified2.5% Silver

Contractor Reputation

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 22: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Construction LEED Implementation Cost SummaryGBCI FeesProject Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 23: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Problem Identification

2 Points from LEED Silver

7/19 Optimize Energy Performance Credits

2% Energy Efficiency Increase = 1 LEED Credit

Goal – Improve Energy Efficiency by 4%

Currently No Window Shading System

Western/Eastern FacadeProject Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 24: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Southeastern Corner Façade Rendering Southwestern Corner Façade RenderingArchitectural Shade #1

6’ Overhang

Above Second Story Grazing

E, S, & W Facades

Material: Solid Black Aluminum Paneling

Supports: Steel Columns Buried in Ground

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 25: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Southwestern Corner Façade Rendering Southeastern Corner Façade RenderingArchitectural Shade #2

6’ Overhang

Above Second Story Grazing

E, S, & W Facades

Material: White, Acrylic Translucent Glazing

Supports: Steel Columns Buried in Ground

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 26: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Southern Façade Rendering Louver DetailArchitectural Shade #3

6’ Overhang

Above Second Story Grazing

E, S, & W Facades

Material: Louvered MetallicPanes

Supports: Steel Columns Buried in Ground

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 27: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Total Annual Energy

Left = Before Shading; Right = After Shading

CO2 Emissions

Peak Energy Demand

Eastern Façade Energy Summary

Total Annual Energy Savings11.9 (kBtu/ft^2)

Peak Electric Demand Savings1.6 (W/ft^2)

CO2 Emissions Reduction5.5 (lbs/ft^2)

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 28: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Energy Summary

Average Energy Reduction12%

Affected to Unaffected Ratio1:2

12% * 1/3 = 4%

*Loading Higher in Solar Areas vs. Non-Solar

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 29: Fisk Corporate Headquarters Houston, Texas

LEED Implementation Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

“Two Dimensions” BIM to Implement Architectural Overhangs

Overhangs Designed in Revit

Easy to Communicate Technical Overhang Information to Team

Quicker Transition Between the Designs

4D Installation Sequence

Problem Background

Unusual Façade Installation

$20,000 in Back Chargers

Façade Already Modeled by Architect & Structural

$5,280 to Implement BIM Façade Detailing

Worker Tolerance Error

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 30: Fisk Corporate Headquarters Houston, Texas

Final Recommendations Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Analysis #1: Project SequencingCost Savings: $50,698Schedule Savings: 4 Weeks5% Reduction in Owner Carried General Conditions

Analysis #2: Electrical System RedesignCost Savings: $11,669Schedule Savings: 4.5 DaysFewer Components to Maintain & ServiceNo Additional Constructability Concerns

Analysis #3Cost Incurred: $28,266Gained LEED Building Certification1% Reduction in State Property TaxImproved Specialty Contractor Image

Architectural Overhangs AdoptedGained LEED Silver4% Minimum Improvement in Energy EfficiencyBIM Implementation to Ease Design Change

Savings Summary

Analysis #1$50,698

Analysis #2$11,669

Analysis #3($28,266)

Total Savings$34,101

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 31: Fisk Corporate Headquarters Houston, Texas

Acknowledgements Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Industry Special Thanks

Wayne McDonald

David Rinehart

Ted Robertson

Fisk Corporate Headquarters Project Team

PACE Industry Members

My Family and Friends

Academic

Dr. John Messner

Dr. Robert Leicht

Dr. Richard Mistrick

Professor Dodson

Professor Holland

Penn State AE Faculty

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 32: Fisk Corporate Headquarters Houston, Texas

Questions? Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Analysis #1: Project SequencingCost Savings: $50,698Schedule Savings: 4 Weeks5% Reduction in Owner Carried General Conditions

Analysis #2: Electrical System RedesignCost Savings: $11,669Schedule Savings: 4.5 DaysFewer Components to Maintain & ServiceNo Additional Constructability Concerns

Analysis #3Cost Incurred: $28,266Gained LEED Building Certification1% Reduction in State Property TaxImproved Specialty Contractor Image

Architectural Overhangs AdoptedGained LEED Silver4% Minimum Improvement in Energy EfficiencyBIM Implementation to Ease Design Change

Savings Summary

Analysis #1$50,698

Analysis #2$11,669

Analysis #3($28,266)

Total Savings$34,101

Project Summary

Analysis #1: Project Sequencing Sequencing Process Schedule Results Cost Implications

Analysis #2: Electrical System Redesign Electrical Redesign Redesign Impacts

Analysis #3: Implementation of LEED LEED Cost Analysis Architectural Breadth Energy Impacts BIM Research

Final RecommendationsAcknowledgments

Page 33: Fisk Corporate Headquarters Houston, Texas

Appendices – Project Sequencing Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Revised General Conditions EstimateOriginal General Conditions Estimate

Page 34: Fisk Corporate Headquarters Houston, Texas

Appendices – Electrical Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Panelboard DP Panelboard H-1 Panelboard H-2

Page 35: Fisk Corporate Headquarters Houston, Texas

Appendices – Electrical Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Panelboard L-1 Panelboard L-1B Original Bill of Material

Page 36: Fisk Corporate Headquarters Houston, Texas

Appendices – Electrical Redesign Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Original Bill of Material Redesigned Bill of Material Redesigned Bill of Material

Page 37: Fisk Corporate Headquarters Houston, Texas

Appendices – LEED Fisk Corporate HeadquartersHouston, Texas

Stephen BlanchardConstruction Management

Eastern Façade Energy Charts Southern Façade Energy Charts Western Façade Energy Charts