Fletcher Park Renovations

1

Existing Conditions

Existing Conditions

Focus Group Comments

Design Objectives.

1) Create a unified park space2) Increase playground size3) Replace play equipment4) Refurbish sitting and supervision

area5) Construction of new basketball

court6) Remove bocce court

Objectives :

Design Objectives

7) Build a mini soccer field on natural turf (also as open play area)

8) Renovate gazebo9) Add a skatespot10) Add green screen between

railway and park11) Increase park security (better

lighting, eliminate hiding areas)

Design Proposal

Playground ModulesSkate Spot Modules

8

Questions and Answers