+ All Categories
Home > Documents > Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML...

Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML...

Date post: 03-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
38
Bringing engineering to life Flood purge and SWH at Lincoln Squares Project Development of purging protocols October 2018
Transcript
Page 1: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Bringing engineering to life

Flood purge and SWH at Lincoln Squares Project

Development of purging protocols

October 2018

Page 2: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Presentation Outline

1. Introduction

2. Project objectives

3. Upstream catchment

4. System configuration

5. Performance results from previous studies

6. Development of purging protocols

Page 3: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%
Page 4: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Project Objectives

• Flood Mitigation

• Peak flow reduction for frequent events

• Determine impact on flooding contributing to

Elizabeth St for the 20 Year ARI event

• Stormwater Harvesting

• Irrigation of Lincoln, Argyle and University Squares

• Water balance optimisation to size storages and

pumps to maintain reliability of irrigation supply

Page 5: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Upstream Catchment

• Area to the north

~37ha

• Includes portion of the

University of

Melbourne and the

tram line on Swanston

St

• Meets at the 750mm

pipe adjacent Lincoln

Square (to the west)

Lincoln Square

University Square

Argyle Square

University of Melbourne

Page 6: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Lincoln Square Header Tank

University Sq Header Tank

Argyle Sq Header Tank

Transfer Lines

Project Layout

Lincoln Square Deep Sump-To access the SW pipe to the west- pumps up to the irrigation tanks

Plant RoomTreatment of water prior to delivering to header tanks

Page 7: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

System Configuration Overview

Need some “smarts” to

improve flood mitigation

performance

Overflows continue to

stormwater drain

Main

Tank

Lincoln

Square

Tank

P

P

Northern Catchment

Flows

Argyle Square

Tank

University

Square TankP

P

P

P

Proposed Pump

Proposed

Irrigation Pump

GPT

Filtration

UV

Page 8: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Main Tank

Applying the smarts

P

P

A

Proposed Pump

Actuator

Ex 750 ø

Main TankGPT

New JP 1,200 ø 1,200 ø GPT

Pre-emptive outlet

Ex 750 ø

Main Tank

A

Actuated Valve

To header

tanks for

irrigation

Irrigation systems

Or

Drainage system

Page 9: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Period Irrigation Area (m2)

Irrigation Demand

(Midway Efficient Use –

ML pa)

Expanded Lincoln Square 12,897 6.97

Expanded University Square 13,500 7.25

Expanded Argyle Square 9,790 5.17

Pelham and Bouverie Street Trees 2,304 1.20

Total 38,491 20.6

Council’s irrigation demands

The irrigation calibration produced a demand of 20.6 ML

for a mean year, showing consistency with the data

provided by Council.

Page 10: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Rainfall vs Yield

10

12

14

16

18

20

22

24

350 400 450 500 550 600 650 700

Sto

rmw

ate

r H

arv

est

ed

(M

L)

Annual Rainfall (mm)

Low rainfall, high harvest (Year 5)

Average rainfall, low harvest (Year 6)

Page 11: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Main Tank Size Comparison – Optimal Operation

Dry Mean

1 ML 54% 75%

2 ML 60% 80%

3 ML 61% 85%

13.1 ML

15.5 ML

14.6 ML

16.6 ML

14.7 ML

17.6 ML

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

Reli

ab

ilit

y (

%)

Page 12: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Main Tank Size Comparison – Sub Optimal Operation

Dry Mean

1 ML 40% 60%

2 ML 40% 64%

3 ML 40% 68%

9.7 ML

12.5 ML

9.7 ML

13.2 ML

9.7 ML

14.0 ML

0%

10%

20%

30%

40%

50%

60%

70%

80%

Reli

ab

ilit

y (

%)

Page 13: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Peak Flow Analysis

Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction

5 Year,

20Min

Pipe 1.55 1.51 2.6% 1.48 4.5%

Overland 1.83 0.362 80.2% 0.359 80.4%

TOTAL 3.38 1.872 44.6% 1.839 45.6%

20 Year,

20Min

Pipe 1.76 1.66 5.7% 1.63 7.4%

Overland 3.51 1.88 46.4% 1.87 46.7%

TOTAL 5.27 3.54 32.8% 3.5 33.6%

50 Year,

20Min

Pipe 1.77 1.75 1.1% 1.72 2.8%

Overland 4.88 3.31 32.2% 3.3 32.4%

TOTAL 6.65 5.06 23.9% 5.02 24.5%

• Marginal (to no) benefit to increasing the tank size to

3ML

Page 14: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Purging Analysis

Page 15: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Purging Assessment Outline

1. Scope

2. Philosophy and Approach

3. Method

4. Protocol Development

5. Graphical Outputs

6. Key Storms

7. Sensitivity Analysis

8. Summary

Page 16: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

1. Scope

Objective is to maximise Flood Mitigation without

significantly compromising Stormwater Harvesting

yield

✓ Flood Mitigation

• Reduction of Overland Flow (to Elizabeth St)

• Reduction of bypass discharge

✓ Stormwater Harvesting

• Irrigation of Lincoln, Argyle and University Squares

• Water balance optimisation to maximize Tank

Water Level after each storm

Page 17: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

2. Philosophy and Approach

Develop Purge protocols to address:

• Before Storm

✓ Purge Water to make Required Pre-Rain Air Space using

Predicted Rainfall

• During Storm

✓ To maintain detention

✓ To ensure tank is close to full post rain event

Page 18: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Key Variables:

• Before Storm

✓ Pre-Rains Air space: based on Predicted rainfall

✓ BOM 3-hour Rainfall Predictions

• During Storm

✓ Pre-peak Air Space

✓ Post-Peak Air Space

✓ Rainfall threshold for valve close

Page 19: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Key Performance Indicators:

• Flood Mitigation Objective

✓ Overland Flow Reduction

✓ Percentage reduction in downstream overland flow

• Stormwater Harvesting Objective

✓ After Rain Tank Water Level

✓ Tank percentage full at the end of the storm

Page 20: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Pre-Rain Flowchart

Predicted

Rainfall

Calculate Pre-

Rain Air Space

Pre-Rain

Coefficient

Purge Water to

reach Pre-rain

Air Space

Page 21: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Pre-Peak Flowchart

6 min Rainfall-

Onsite

Pluviograph

Calculate Rolling

30-min Runoff

and Rainfall

Does the

tank have

enough Air

Space?

Estimate Pre-

Peak Air Space

Pre-Peak

Coefficient

Close the Valve

Is it after

peak of the

rainfall?

Is 30-min

rolling Rainfall

more than the

threshold?

Rainfall

threshold for

valve close

Open the

Valve

Next 6 min

Tank Water

Level

NO

YES

NO

YES

NO

Page 22: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Post-Peak Flowchart

6 min Rainfall-

Onsite

Pluviograph

Calculate Rolling

30-min Runoff

and Rainfall

Does the

tank have

enough Air

Space?

Estimate Post-

Peak Air Space

Post-Peak

Coefficient

Close the Valve

Is it after

peak of the

rainfall?

Is 30-min

rolling Rainfall

more than the

threshold?

Rainfall

threshold for

valve close

Open the

Valve

Next 6 min

Tank Water

Level

YES

YES

NO

YES

NO

Page 23: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Selection of 50 storms

• Melbourne Regional Office Station # 086071

1. 6-min Rainfall data between 1873-2010

2. Maximum Daily Rainfall; 16 Storms

3. Maximum Hourly Rainfall; 10 Storms

4. Maximum 6-min Rainfall; 18 Storms

5. Design Storms; 6 Storms

1in 20 years: 30 min, 60 min and 90 min

1 in 50 Years, 30 min, 60 min, 90 min

Page 24: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

• Method

Selection of 50 storms

1in 20 Years, 30 min: 26.32 mm

1in 20 Years, 60 min: 34.42 mm

1in 20 Years, 90 min: 39.51 mm

1in 50 Years, 30 min: 32.57 mm

1in 50 Years, 60 min: 42.33 mm

1in 50 Years, 90 min: 48.47 mm

0

20

40

60

80

100

120

140

160

0 5 10 15 20 25 30 35 40 45 50

To

tal R

ain

fall (

mm

)

Series #

Page 25: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Water Quantity Model:

• DRAINS

✓ ILSAX hydrologic model

Page 26: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Water Balance Model

• Excel Spreadsheet based calculations

• Calculation time steps:

5 min for Design Storms and 6 min for the others

➢ 𝑷𝒓𝒆 𝑹𝒂𝒊𝒏 𝐴𝑖𝑟 𝑆𝑝𝑎𝑐𝑒 = 𝑃𝑟𝑒 − 𝑅𝑎𝑖𝑛 𝐶𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 ×𝑅𝑢𝑛𝑜𝑓𝑓 𝐶𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒𝑑 𝑏𝑎𝑠𝑒𝑑 𝑜𝑛 𝑃𝑟𝑒𝑑𝑖𝑐𝑡𝑒𝑑 𝑅𝑎𝑖𝑛𝑓𝑎𝑙𝑙 𝐷𝑒𝑝𝑡ℎ

➢ 𝑷𝒓𝒆 𝑷𝒆𝒂𝒌 𝐴𝑖𝑟 𝑆𝑝𝑎𝑐𝑒 = 𝑃𝑟𝑒 − 𝑃𝑒𝑎𝑘 𝐶𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 ×𝑅𝑜𝑙𝑙𝑖𝑛𝑔 30min𝑅𝑢𝑛𝑜𝑓𝑓

➢ 𝑷𝒐𝒔𝒕 𝑷𝒆𝒂𝒌 𝐴𝑖𝑟 𝑆𝑝𝑎𝑐𝑒 = 𝑃𝑜𝑠𝑡 − 𝑃𝑒𝑎𝑘 𝐶𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 ×𝑅𝑜𝑙𝑙𝑖𝑛𝑔 30min𝑅𝑢𝑛𝑜𝑓𝑓

➢ 𝑆𝑡𝑜𝑟𝑎𝑔𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 = 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝑆𝑡𝑜𝑟𝑎𝑔𝑒 + 𝑂𝑓𝑓𝑡𝑎𝑘𝑒 − 𝑇𝑎𝑛𝑘 𝑂𝑢𝑡𝑓𝑙𝑜𝑤

➢ 𝐷𝑆 𝑂𝑣𝑒𝑟𝑙𝑎𝑛𝑑 𝐹𝑙𝑜𝑤 = 𝑈𝑆 𝐹𝑙𝑜𝑤 − 𝑂𝑓𝑓𝑡𝑎𝑘𝑒 − 𝐵𝑦𝑝𝑎𝑠𝑠

Page 27: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

3. Method

Water Balance Model

• Rolling 30min Runoff calculation

y = 119.61x + 1350

R² = 0.8199

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

0 10 20 30 40 50 60

To

tal R

un

off

(K

L)

Rainfall depth (mm)

Page 28: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

4. Protocol Development

Phase 1:

Pre-Rain Coefficient: 10%,20%,…,100%

Pre-Peak Coefficient: 25%,50%,…,100%

Post- Peak Coefficient: 25%,50%,…,100%

No Rainfall Threshold for Valve Close

Page 29: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

4. Protocol Development

Phase 2:

Pre-Rain Coefficient: 30%,40%,50%

Pre-Peak Coefficient: 25%,50%,75%

Post- Peak Coefficient: 25%,50%,75%

No Rainfall Threshold for Valve Close

Page 30: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

4. Protocol Development

Storm #49

Rainfall SummaryTotal rainfall (mm) 24.44Duration (min) 180

Maximum Intensity (mm/hr) 84.9

Maximum Intensity (mm/6 min) 8.49

Estimated recurrance interval (1 in yr) 65

ProtocolsPre- Rain Coefficient 50%

Pre-peak Coefficient 75%

Post-peak coefficient 25%

Rainfall threshold for valve close (mm/ 30 min) 10

After adding Rainfall Threshold for Valve

Close (10 mm)

Page 31: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

4. Protocol Development

Phase 3:

Pre-Rain Coefficient: 50%

Pre-Peak Coefficient: 75%

Post- Peak Coefficient: 25%

Rainfall Threshold for Valve Close:

10 (mm/30min)

Page 32: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

5. Graphical Outputs

✓ Demonstration “Presentation Sheet”

Page 33: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

6. Key Storms

✓ Demonstration

Page 34: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

7. Sensitivity Analysis

Predicted rainfall is 50% less than the

Actual one. (-50% Error)

Not Sensitive

Page 35: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

7. Sensitivity Analysis

Predicted rainfall is 50% more than the

Actual one. (+50% Error)

Not sensitive

Page 36: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Summary

✓ Protocols are developed for dual function of

flood mitigation and stormwater harvesting.

✓ Pre-rain Air space is introduced based on the

predicted rainfall – threshold is approximately

15mm with optimally 50% airspace coefficient.

✓ Pre peak airspace coefficient is optimally 75%

✓ Post peak airspace coefficient is optimally 25%

✓ Rainfall depth threshold for valve close in 30 min

rolling period is 10mm.

Page 37: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Summary

✓ The performance (final tank volume and

reduction in overland flow) is more effective in

storms with less than 50mm rainfall.

✓ Performance is not sensitive to up 50% error in

rainfall prediction.

✓Overland flow upstream generally occurs in

events with intensity higher than 8 mm/6min (80

mm/hr).

✓Cannot rely solely on design storms for

complex analsyis

Page 38: Flood purge and SWH at Lincoln Squares Project · Peak Flow Analysis Storm / flow type Existing 2ML Tank % Reduction 3ML Tank % Reduction 5 Year, 20Min Pipe 1.55 1.51 2.6% 1.48 4.5%

Recommended