iHeat Design Review for the City of Kendrick Thursday, July 30 th , 2009 1
Transcript
Page 1: For the City of Kendrick Thursday, July 30 th, 2009 1.

1

iHeat Design Reviewfor the City of Kendrick

Thursday, July 30th, 2009

Page 2: For the City of Kendrick Thursday, July 30 th, 2009 1.

2

Overview• Problem Statement• Primary Client Needs• Current System & Recommendations• Thermal Model• Non Traditional Solutions• Off the Shelf Solutions• Custom Built Solutions• Questions

Page 3: For the City of Kendrick Thursday, July 30 th, 2009 1.

3

Problem StatementDevise a cost effective heating method to allow pool usage

as early as Memorial Day weekend.

Page 4: For the City of Kendrick Thursday, July 30 th, 2009 1.

4

Primary Client Needs• Safety• Time of Year• Energy Conservation• Temperature• Longevity• Budget• Simplicity• Aesthetics

Page 5: For the City of Kendrick Thursday, July 30 th, 2009 1.

5

Current System & Recommendations

• Leak

• Cover Usage

• Surge Tanks

• Flow Meter

• Shading

Page 6: For the City of Kendrick Thursday, July 30 th, 2009 1.

6

Thermal ModelInitial Heat Up

Source Temperature Rise

Surface Area BTU/hr

iHeat 25oF 3,480sqft 1,203,241

www.poolinfo.com 25oF 3,480sqft 915,240

www.solardirect.com 25oF 3,480sqft 1,392,000

www.poolproducts.com 25oF 3,480sqft 1,096,200

Increasing the temperature of 5,000 gallons of water 25oF in 24 hours requires an addition of 44,000BTU/hr

Page 7: For the City of Kendrick Thursday, July 30 th, 2009 1.

7

Nontraditional Solutions

• Directly capturing the sun’s heat by painting the pool walls with thermo-sensitive paint or using an advanced thermal cover system.

Page 8: For the City of Kendrick Thursday, July 30 th, 2009 1.

8

• Heater powered by alternative energy source, such as wind, hydroelectrics, or methane gas from compost or manure.

Nontraditional Solutions

Page 9: For the City of Kendrick Thursday, July 30 th, 2009 1.

9

Off-the-Shelf Solutions• Propane Heater

• Electric Heat Pumps

• Direct Solar Panels

• Hybrid System

Page 10: For the City of Kendrick Thursday, July 30 th, 2009 1.

10

Off-the-Shelf SolutionsPropane Heater

• Initial Cost: $3500 - 7,500 • Unit Purchase Price, Installation, Propane Tank, Lines

• Seasonal Operating Expense: $4000-5000• Longevity: ~7 yrs • Time to heat: 3-4 days

Page 11: For the City of Kendrick Thursday, July 30 th, 2009 1.

11

• Initial Cost: $13,000-20,000• Unit Purchase Price, Installation, Lines

• Seasonal Operating Expense: $600-1000• Longevity: 10-15 yrs• Time to heat: 3-4 days

Off-the-Shelf SolutionsElectric Heat Pumps

Page 12: For the City of Kendrick Thursday, July 30 th, 2009 1.

12

• Initial Cost: $12,000-30,000 + installation• Seasonal Operating Expense: $200-400• Longevity: 10-15 yrs• Time to heat: 2-3 weeks

Off-the-Shelf SolutionsDirect Solar Panels

Page 13: For the City of Kendrick Thursday, July 30 th, 2009 1.

13

Combines solar panels with a heater in the same system.

Accommodates insufficient sunlight.

Minimizes size of heater and size of solar array.

Off-the-Shelf SolutionsHybrid System

Page 14: For the City of Kendrick Thursday, July 30 th, 2009 1.

14

Off-the-Shelf SolutionsSummary

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21$0

$20,000

$40,000

$60,000

$80,000

$100,000

$120,000

Off-the-Shelf Long Term Cost Comparison

Heat Pumps LowHeat Pumps HighPropane Heater LowPropane Heater HighSolar Panels LowSolar Panels High

Year

Cum

malt

ive C

ost

Page 15: For the City of Kendrick Thursday, July 30 th, 2009 1.

15

Custom Built Solutions• Solar Array - Spiral • Solar Array - Manifolds & Sheets

Page 16: For the City of Kendrick Thursday, July 30 th, 2009 1.

16

Custom Built SolutionsSolar Array - Spiral• Initial Cost: $5,000-6,000 • Seasonal Operating Expense: $200-400• Longevity: 10+ yrs • Drip hose, PVC fittings, framing

Page 17: For the City of Kendrick Thursday, July 30 th, 2009 1.

17

• Initial Cost: $6,000-7,000• Seasonal Operating Expense: $200-400• Longevity: 10+ yrs• Lexan sheets, PVC manifolds

Custom Built SolutionsSolar Array - Manifolds & Sheets

Page 18: For the City of Kendrick Thursday, July 30 th, 2009 1.

18

System Cost per ft2 ft2 Total

Off-the-Shelf Solar

$ 7.00 2400 $12,000-30,000

Spiral $ 3.00* ? ?

Manifolds & Sheets

$ 3.50* ? ?

Custom Built SolutionsComparison to Off-the-Shelf

Page 19: For the City of Kendrick Thursday, July 30 th, 2009 1.

19

Questions