+ All Categories
Home > Documents > Forest Surveying

Forest Surveying

Date post: 14-Apr-2018
Category:
Upload: harishkumarravichandran
View: 233 times
Download: 1 times
Share this document with a friend

of 31

Transcript
  • 7/30/2019 Forest Surveying

    1/31

    1

    I. Scales

    General

    The distances measured on ground are plotted on paper in such a way that a fixed ratio is

    maintained between the distance on ground to the corresponding distance on paper. This ratio is

    known as scale and the process of plotting with scale is known as drawing to scale. Thus, the scale

    is defined as the ratio of ground distance to the plotted distance on plan, i.e.,

    Scale = Ground distance Plan

    distance

    For instance, if the scale is 1 cm = 5 cm, it means that one cm on paper indicates five meters on

    ground.

    Scales can be expressed in the following three ways:

    (1)Engineer's scale: In this case, the relation between the distance on plan and the distance onground is mentioned numerically in the style as 1 cm = 5 m, etc. such an expression grants

    convenience in reading and plotting.

    (2) Graphical scale: The scale is drawn on plant itself. Hence, a graphical scale represents a line,which is subdivided into plan distance to the corresponding convenient units of length on the

    ground. As the plan or map becomes old, the engineer's scale may shrink and may not give

    accurate results. However, such is not the case with graphical scale because if the plan or map

    shrinks, the scale will also shrink. Hence, graphical scale is drawn on survey maps.

    (3)Representative fraction: In this case, the ratio is worked out in such a way that numerator isunity and denominator is a fraction in the same unit of measurement as

    the numerator. This fraction is known as representative fraction and it is briefly written as R.F.

    it is desirable to write the scale in R.F. also. For instance, R.F. of a scale 1 cm = 5 m can be

    worked out as follows:

    Classification of scales:

    Scales are classified in the following fourcategories:

    I. Plain scaleII. Diagonal scaleIII. Vernier scaleI. Plain scale :

    From this type of scale, it is possible to read only in two dimensions on paper such as

    metres and decameters, hundreds and tenths, units and tenths, etc. Solution

    The procedure for construction of this scale will be as follows:

    (1) Select suitable number of metres divisible by 10 and work out the length ofscale

  • 7/30/2019 Forest Surveying

    2/31

    2

    (2) Draw a line 8 cm long the divide it into 4 equal parts. Each part thenrepresents 109 m.

    (3) Divide the first compartment into 10 equal parts, each part representing 1 m.(4) Finish up the scale, and mark on it 37 m as required.

    II.Diagonal scale:From this type of scale, it is possible to read in three dimensions on paper such as metres,

    decameters and centimeters; units, tenths and hundredths; etc. Solution:

    The procedure for construction of this scale will be as follows:

    (1)Construct the plain scale as before.(2)Make the construction on subdivision portion. Finish upon the scale and mark

    on it 26.6 m and 30.3m.

    III.Vernier scale:To read the fractional part of the smallest division of the main or primary scale, a device

    was found out by A.N. Vernier in 1631 and after his name, the device has come to be known as

    vernier scale.

    The difference between the smallest division on the main scale and that on the vernier

    scale indicates the fineness of vernier reading and it is known as the least count of the vernier.

    Vernier scale are of the following five types:

    (1) Direct vernier(2) Retrograde vernier(3) Extended vernier(4) Double vernier(5) Double-folded vernier (1) Direct vernier:

    In case of direct vernier, both the scales, namely, vernier and main move in the same

    direction and they are graduated in the same direction. As shown in fig. (n-1) parts of the main

    scale are taken and they are divided into n equal parts on the vernier scale.

    n

    Let d = value of the smallest division on main scale U =

    value of the smallest division on vernier scale.

    \ 1 2 3 4 5 6 7 8 9 10

    1 2 3 4 5 6 7 8 9

    Main Scale Vernier Scale

    (n-1

  • 7/30/2019 Forest Surveying

    3/31

    3

    Then, or

    (n - 1)d = nu

    n -1 ,u = ----- d

    n

  • 7/30/2019 Forest Surveying

    4/31

    4

    n

    fnn +1

    n

    dn

    thus, the ratio of the value of the smallest division on main scale to the total number of

    divisions on vernier scale indicates the least count of the vernier scale. (2) Retrograde vernier:

    In case of retrograde vernier, main scale and vernier scale move in opposite directions and

    graduations are also marked in opposite directions. (n+1) parts of the main scale are taken and

    they are divided I to n equal parts on the vernier scale. Thus, in case of retrograde vernier, the

    divisions of vernier scale will be larger than those of main scale and it will facilitate in easy

    reading. However, direct vernier is commonly used as it is simple is operation.

    Let d = value of the smallest division on main scale u =

    value of the smallest division on vernier scale

    Then,

    (n + 1)d = nu

    or

    n +1 ,u = ------ d

    n

    Least count of vernier = u -d = (n + 1)dd

    d

    Least count of vernier = d -u

    n 1 = d-------------d

    n

  • 7/30/2019 Forest Surveying

    5/31

    5

    d_

    n

    Thus least counts of direct and retrograde verniers are the same.

    (3) Extended vernier:

    This type of vernier is just similar to the direct vernier scale except that every second

    division is omitted. It, the therefore, follows that in case of extended vernier scale, (2n-1)

    divisions of the main scale are taken and they are divided into n equal parts. Let d = value of

    the smallest division on main scale

    u = value of the smallest division on vernier scale Then

    (2n - 1)d = nv

    or

    (2n - 1)dv = -

    n

    Least count of vernier = 2d -u

    = 2d -(2n - 1)d

    n

    d ^ 2n - 2n +1

    d

    n

    (4) Double vernier:

    When the main scale is running in both the directions with common zero, it becomes

    easier to employ a single vernier scale with common zero, as shown in fig. 2-1. Such cases usually

    occur when vertical angels are to be measured with a common horizontal plane. Extreme care

    should be exercised to properly read the vernier scale, i.e., the directions of reading of main and

    vernier scales should be the same. Exercise I

    1. Draw a plain scale 1cm = 5m and show on it 48m.2. Draw a diagonal scale 1cm = 4m to show m and dm. Show on the scale 23.2m and 37.4m.3. Construct a vernier scale with least count as 1/100. The smallest division on the main scale is

    0.10m. Show a reading of 3.46m.

  • 7/30/2019 Forest Surveying

    6/31

    6

    II. Chain Surveying

    Principle of chain survey

    The main principle of chain survey is to prepare a framework or network of triangles

    because a triangle is a figure, which can be plotted on paper by measuring its sides only. Great

    care has to be exercised in the formation of well-proportioned or well- conditioned triangles so

    that the process of chain surveying becomes smooth. A well - proportioned or well-shaped triangle

    has no angle greater than 1200 or smaller than 300. As far as possible, the triangles formed should

    resemble to the shape of an equilateral triangle. If, however, the conditions are not favorable for

    forming well-proportioned triangles, extreme care should be taken in chaining and plotting of the

    unavoidable ill- proportioned or ill-conditioned triangles. Instruments required in chain survey:

    Following instruments are required for carrying out a chain surveying:

    (1) Chain and 10 arrows(2) Tape of 10 m or 20 m length(3) Ranging rods about 10 to 15 in number(4) Offset rod(5) Cross-staff or optical square to set right angles(6) Plumb bob(7) Field book with pencils, rubber, pen-knife, etc.(8) Box sextant, if any angle other than 900 is to be set up or measured.(9) Miscellaneous items such as hammer, axe, nails pegs, bundle of string, chalk, etc.

    Procedure for carrying out chain survey:

    Following are the four distinct steps involved in carrying out the chain survey of any plot of land:

    (1) Reconnaissance survey(2) Marking of stations(3) Preparation of reference sketches(4) Running of survey lines

    (1) Reconnaissance survey;A reconnaissance survey indicates the preliminary inspection of the site of work and hence,

    first of all, the survey our visits the area to be surveyed. The salient features of the site are studied

    with reference to the following aspects:

  • 7/30/2019 Forest Surveying

    7/31

    7

    (i) Index plan: The survey our prepares an index plan or sketch in the field book showingroughly the area to e surveyed and important objects such as buildings, roads,

    streams, etc. are included in this index plan. It also contains the sequence in which the

    survey lines are to be measured. The stations are indicated by number or letter and the

    direction in which the work is to proceed is shown by arrows.

    (ii) Main station: Suitable positions of main stations are decided by the surveyor. Theimportant fact to be kept in mind is the intervisibility of main stations. The lengths of

    main survey lines are measured roughly by pacing or some such approximate method

    of measurement.

    (iii) Study of area: During reconnaissance survey, the surveyor has to carry out intensivestudy of the site so that he can get a clear picture of the area to be surveyed, probable

    difficulties to be encountered during the work, time required to finish up the job, etc.

    (2) Marking of stations:The stations selected during reconnaissance survey should be properly marked on ground by

    using suitable equipment so that they can be readily and easily identified. Depending upon the

    nature of ground and importance of stations, the marking of stations is done with ranging rods,

    wooden pegs, nails, stones, etc.

    (3) Preparation of reference sketches:After marking of stations, the location or reference sketches of these stations should be neatly

    drawn in the field book. The reference sketch of a station helps in locating the station at a

    future date or in cases where its position is not traceable ad it is to be fixed again. Two

    measurements from permanent structures will be sufficient. But usually three measurements

    are taken to ensure the check on exact location of the stations. The measurements are taken

    with reference to the permanent objects that may be in the form of corner of a building,

    electric or telegraph post, compound wall or gate, trees, etc. The measurements are taken to

    the nearest 5-mm. North line should invariable be drawn on the reference sketch. Thus, the

    position of a station is resorted with the help of its reference sketch by swinging arcs from the

    respective permanent structures. (4) Running of survey line:

    The work of chaining is then started. Base line is first to be measured. The work is carried out

    as follows:

    (i) Chain is laid down on the ground after proper ranging.

  • 7/30/2019 Forest Surveying

    8/31

    8

    (ii) Offsets of nearby details are taken and recorded in the field book in the usual manner.(iii) Chain is then stretched or taken forward and the process is repeated till the end of line

    is reached.

    (iv) Other lines of the framework are then gradually taken and measured.Plotting work

    The details entered in the field book are ten plotted on paper in the drawing office. The

    drawing materials required for plotting work include brushes, colours, ink, pencils, pins, rubber,

    saucers, weights, etc. following are the drawing instruments required for plotting work.

    (1) compass box(2) drawing board of suitable dimensions;(3) drawing table;(4)paper;(5)protractor;(6) rolling parallel ruler(7) set of French curves(8) set of scales;(9) set squares;(10) straight edge of steel(11) tee - square etc.The plotting work should be carried out carefully so that a decent well-looking drawing

    emerges after the work is completed. The items such as lettering, inking, colouring, etc. should be

    done in an artistic way. The map must contain the scale with which it is drawn and the north line

    should be exhibited at suitable spot on the map. The conventional signs which are commonly used

    must be used. Exercise II

    1. Calculate the distance of the road around the buildings of the campus by chain surveying2. Find the area of the field by cross staff survey

    II. Compass survey

    The process of triangulation is not possible when the area is to be surveyed is large with

    irregular boundaries and many obstacles. In such cases, traversing is adopted. In the process of

    traversing, the direction of the survey line is fixed by taking the angular measurements with

  • 7/30/2019 Forest Surveying

    9/31

    9

    suitable instruments. Thus, a traverse consists of a series of connected lines whose lengths and

    direction are known. Compass:

    The instruments which is used for finding out the magnetic bearings or simply bearings of

    a line is known s a compass and any compass essentially consists of the following three parts:

    (1) Circle - with graduations;(2) Line of sight; and(3) Magnetic needle supported loosely.

    Following are the main five types of compasses:

    (1) Prismatic compass(2) Surveyor's compass(3) Compass over a level(4) Trough compass(5) Tubular compass.

    Each type of the above compass will be now briefly described.

    Prismatic compass:

    The prismatic compass is the most convenient, handy and portable instrument. It is

    circular is shape and its diameter varies from 85 mm to 110 mm. it is made up of a non-magnetic

    metal. It essentially consists of the following parts;

    A magnetic needle of broad type supported over a centrally situated pivot made of

    hard steel is provided.

    A graduated aluminum ring is attached with the needle and it is divided into

    degrees and half degrees. The graduations start from zero marked at south end of

    the needle and they run clockwise so that 900, 1800 and 2700

    are marked respectively at west, north and east. The figures are written inverted.

    Eye vane and object vane are fixed diametrically opposite to each other. The

    reflecting prism is provided near eye vane. The line joining eye vane and object

    vane passes through the centre of compass.

    Focussing stud is provided to adjust the eyesight's of the different persons.

    A break pin is provided to stop the oscillations of the ring.

  • 7/30/2019 Forest Surveying

    10/31

    10

    A glass cover is provided at the top so that dust particles cannot enter the compass

    box.

    Sunglasses are provided to facilitate the sighting of objects in sunlight.

    A hinged mirror with sighting or object vane is provided. The mirror can be

    inclined at any angle so that it becomes possible to sight the objects which are too

    low or too high.

    Method of using the prismatic compass:

    Suppose it is required to observe the bearing of line AB. The procedure will be as follows.

    (i) The temporary adjustments of the compass are carried out. it involves twooperation, namely, centering and leveling. The process of obtaining centre of

    compass over the centre of the peg is known as centering. The can be done either

    by a plumb bob or by allowing a small pebble to fall from the centre of the

    compass and hit the peg. The compass can be held in hand, but it is generally

    mounted on a light tripod. The process of making the needle horizontal is known

    as leveling and it is achieved h means of a ball and socket joint. When the

    compass is leveled, the need swings freely. It should be clamped, when perfectly

    leveled.

    (ii) After centering and leveling of the compass is done over the station A, the sightingvane and prism of the compass are raised. The prism is adjusted so that readings

    can be clearly seen.

    (iii) The compass box is rotated until the ranging rod at station B, hair of object vaneand slit of eye vane are in the same line.

    (iv) The needle is brought to rest by pressing the knob, if necessary and then, thereading is taken. The readings are usually taken upto an accuracy of 15 minutes.

    The reading will indicate the angle, which the line AB makes with the north line.

    Exercise III a1. Estimate the area of the field by compass survey by radiation and traversing.2. Find the included angles of the marked points in the field.

  • 7/30/2019 Forest Surveying

    11/31

    11

    Measurements of angles and bearings

    Definitions: Bearings:

    A bearing of a line is defined as the angle made by the line with some reference direction

    or meridian. Meridians:

    Following are the three meridians that are commonly used in survey work:

    (1) Arbitrary meridian(2) Magnetic meridian(3) True meridian.

    Methods of designation:

    Following are the two systems of designation of bearings;

    (1) Quadrantal bearing system(2) Whole circle bearing system

    (1) Quadrantal bearing system:In this system, the angle is measured from north or south to east or west. Thus, there are four

    quadrants, namely, NE, SE, SW and NW, as shown in fig. 7-10. Thus, 9in this system, the

    numerical value of the angle does not exceed 90

    0

    and it also helps in trigonometricalcalculations. The quadrantal bearings are also referred to as reduced bearings or R.B

    (2) Whole circle bearing system:In this system, the angle is measured from the magnetic north in clockwise direction and its value

    will therefore vary from 00 to 3600. The bearing is known as whole circle bearing or W.C.B. Every

    line has two bearings, namely, fore bearing (F.B) and back bearing (B.B.). The reading of line AB

    taken from point a is the F.B. of line AB and the reading of line AB taken from point B is its B.B.

    Let us consider the W.C.B. system for finding out the relation between F.B. and B.B. of a

    given line AB. In case I,

    B.B. = F.B. + 1800

    In case II ,

    B.B. = F.B. - 180'

  • 7/30/2019 Forest Surveying

    12/31

    12

    Thus, a general expression can be framed as follows:

    B.B. = F.B. 180a Use +

    sign if F.B. is less than 1800 and Use - sign

    if F.B. is greater than 180a

    In the quadrantal system, there will not be any changes in the value of F.B. and B.B.

    except that their respective quadrants will be interchanged. Thus if F.B. is in NE quadrant, B.B.

    will be in SW quadrant. Thus N is to be substituted for S and E is to be substituted for W and so

    on. Exercise III b

    1. Convert the Q.B. to W.C.B.a. N120 280 E. b. N 680 270 W c. S 430 380 E d. S 370 520 W

    2. Convert W.C.B. to Q.B.a. 3050 170' b. 650 40' c. 1710 37' d. 2080 19'

    IV Plane Table Survey

    General

    In case of plane table survey, the measurements of survey lines of the traverse and their

    plotting to a suitable scale are done simultaneously on the field. Following are the cases in which

    the plane table survey is found to be useful.

    (1) Compass survey cannot be carried out with success in industrial areas of the town.Plane table survey will be the best alternative in such cases.

    (2) For preparing plans on a small scale, plane table survey proves to be speedy, easy andaccurate.

    (3) The city or town has expanded within two or three decades and it is required to plotthe developed area on the previously plotted plan of the existing area.

    Instruments required for plane table survey:(1)Alidade

  • 7/30/2019 Forest Surveying

    13/31

    13

    (2)Drawing board. Accessories requiredfor plane table survey:

    (1) Plumbing fork(2) Spirit level(3) Trough compass(4) Miscellaneous.

    Miscellaneous:

    In addition to the above-mentioned accessories, the miscellaneous items required will be

    the drawing paper of the best quality, pencil , rubber, scale, pins, water-proof cover to protect the

    board, etc.

    Temporary adjustments of plane table:

    Following three distinct operations at each survey station are carried out for the temporary

    adjustments of a plane table;

    Centering

    Levelling

    Orientation.

    Methods of plane table survey

    Following re the four methods by which an object might be located on paper by plane

    table:

    (1) Radiation(2) Intersection(3) Traversing(4) Resection.

  • 7/30/2019 Forest Surveying

    14/31

    14

    (1) Radiation:

    This is the simplest method and it is useful only when the whole traverse can be commanded

    from a single station. The procedure is as follows:

    (2) Intersection:

    This method is useful where it is not possible to measure the distances on ground as in case of

    a mountainous country. Hence, this method is employed for locating inaccessible points, the

    broken boundaries, rivers, fixing survey stations, etc.

    (3) Traversing:This method resembles the work of a compass survey and it is useful for the survey work of

    roads, rivers, etc. the traverse is run as usual and the details on the line are taken by radiation

    or offsets.

    (4) Resection:

    The process of resection is used for establishing the instrument stations only and it thus helps

    in ascertaining the fact that the point plotted on plan is the station occupied by the plane table.

    Exercise IV

    1. By plane table survey using radiation method and intersection method plot the fieldboundaries.

    2. Find the area of the field by triangulation.V Levelling

    General

    Levelling is defined as a method of determining the relative elevations of points on the

    surface of earth or an operation for finding out the difference in heights. Thus, the data obtained

    from the process of Levelling will be useful in the following two respects;

  • 7/30/2019 Forest Surveying

    15/31

    15

    (1) To establish points for various engineering purposes at desired elevations withrespect to a given datum.

    (2) To work out the elevations of given points relative to each other or with respect to agiven datum.

    Definitions of some common terms in levellings:

    (1) Backsight and foresight and intermediate sight: Backsight or B.S. is the first readingfrom any set up of the instrument and foresight or F.S. is the last reading taken before

    disturbing the instrument from its set up. All sights taken between B.S. and F.S. are

    known as intermediate sights or I.S.

    (2) Bench mark: A fixed point of known elevation is called the bench mark or B.M.(3) Change point or turning point: The point indicating the shifting of level is known as a

    change point (C.P.) or a turning point (T.P.)

    (4) Datum: A datum surface or line is any arbitrarily assumed level surface or line fromwhich the vertical distance are measured.

    (5) Elevation: The vertical distance of a point with respect to a given datum, eitherpositive or negative, is known as the elevation of that point.

    (6) Height of instrument: The elevation or R.L. of the line of collimation, when theinstrument is correctly levelled, is known as the height of instrument.

    (7) Horizontal line: The line in a horizontal plane is known as a horizontal line. A horizontalplane at any point is a plane tangential to the level surface at that point

    (8) Level line: The line drawn on a level surface is known as a level line.(9) Level surface: This is a surface on which all the points are equidistant from the centre of earth.

    As earth is sphere, a level surface will be a curved surface. Examples of a level surface are

    liquid surface or a sea water, liquid surface of lake, etc.

    (10) Line of collimation: The line joining the intersection of cross-hairs and optical centre ofthe object glass and its continuation is known as line of collimation.

    (11) Mean sea level: The average height of the sea for all states of the tides is known as meansea level or M.S.L.

  • 7/30/2019 Forest Surveying

    16/31

    16

    (12) Reduced level: The elevation of a point or its vertical distance above or below the datum isknown as its reduced level or R.L.

    (13) Station: The point which is to be set up at a given elevation or whose elevation is to befound out is known as the station and it thus indicates the point at which the staff is held and

    not the point at which the level is set up.

    (14) Vertical angle: The angle formed by the intersection of two lines in a vertical plane isknown as the vertical angle.

    (15) Vertical line or plumb line: The line normal to a level surface is known as a vertical line ora plumb line and the plane which contains a vertical line is called a vertical plane.

    Principles of levelling

    Some of the important principles that are to be observed in simple direct levelling are as

    follows.

    (1) Change point: The intermediate staff should be carefully selected and it should be inthe form of firm point which can be easily located. The elevation of change point

    should be carefully determined as a slight error in it will be reflected in the

    subsequent readings. If convenient, a bench mark can be used as a change point.

    (2) Lengths of B.S. and F.S.: For accurate work, the lengths of B.S. and F.S. should bemaintained nearly equal. If this condition is satisfied, the error due to non-parallelism

    of the line of collimation and the bubble line will be reduced to a great extent. This

    fact can be proved by considering the line of collimation downwards and upwards.

    Entering the staff readings:

    The staff readings are to be noted immediately after they are observed. For this purpose, a

    level book with specially ruled out columns is used. Following points should be observed at the

    time of entering staff readings in a field book:

    (1)The staff readings should be entered in proper columns and in order of theirobservations.

  • 7/30/2019 Forest Surveying

    17/31

    17

    (2)The first entry and the last entry on any page are respectively B.S. and F.S. Hence, ifI.S. is to be carried over to the next page, it is to be entered as I.S. and F.S. on the

    carried forward page and B.S. and I.S. on the brought forward page.

    (3)For each staff reading, a horizontal row is reserved except for staff reading of a C.P. Incase of staff reading for a C.P., F.S. of C.P. are written in the same

    horizontal line with the note of C.P. in the remarks column in the same horizontal line.

    (4)The R.L. of plane of collimation should be written in line with B.S.(5)The description of B.M. should be briefly and accurately written in the remarks

    column. If required, the description of other important, features and change points

    may be entered in the remarks column and the sketches may be drawn on the left hand

    side of the page.

    Reduction of levels:

    Following are the two methods of working out the reduced levels of points from the

    observed staff readings:

    (1) Collimation system(2) Rise and fall system

    (1) Collimation system;

    In this system, the level of line of collimation is found out by adding the B.S. taken on B.M. of

    known R.L. the readings of various other points, when subtracted from this level, will give the

    R.L. of the respective points. At every point, a new level of line of collimation is obtained and the

    process is repeated till the last point is reached.

    The arithmetical check of this system is carried out by applying the following rule:

    I F.S. - I B.S. = First R.L. - Last R.L.

  • 7/30/2019 Forest Surveying

    18/31

    18

    It should, however, be noted that the above rule does not provide the check on the reduced

    levels of the intermediate points. However, this system proves to be easy, simple and rapid.

    (2) Rise and fall system:

    This system consists of finding out the difference in levels between two consecutive points by

    comparing each point with the preceding point. Rise is indicated, if the staff reading is smaller and

    fall is indicated, if the staff reading is greater. By adding rise or subtracting the fall, R.L. of each

    point can be obtained

    This system provides arithmetical checks in three ways as follows: I F.S.- I B.S. = L Falls - I Rises = First R.L. - Last R.L.

    It is thus seen that this system provides a complete check on intermediate calculations also.

    Hence, this system, though laborious and tedious, is adopted for accurate work.

    Exercise V

    1. Find the reduced levels of the points of the given points by height of collimation method and

    rise and fall method and check arithmetically

    VI Contouring

    General:

    A contour is an imaginary line, which joins the points of equal elevation on the ground.

    Thus, it represents a line in which the surface of the ground is intersected by a level surface. The

    plan showing the elevations and depressions of the surface of the ground is known as the contour

    plan or contour map.

    Contour interval:

    The vertical distance between any two consecutive contours in known as contour interval

    and it is kept constant for a contour plane, once it is adopted. The horizontal distance between two

    points on two consecutive contours is known as the horizontal equivalent and it will naturally

    depend on the steepness of the ground

    Interpolation of contours:

  • 7/30/2019 Forest Surveying

    19/31

    19

    The process of placing or spacing the contour lines proportionally between the plotted

    ground points is known as the interpolation of contours and it is based on the assumption that the

    slope of ground between the two point is uniforms. Following are the three methods of

    interpolation of contours:

    (1) Estimation(2) Arithmetical calculations(3) Graphical.

    (1) Estimation;

    In this method, the position of contour point is judged by estimation only. The method is

    rapid. But as it give approximate results, it is useful for small scale maps only.

  • 7/30/2019 Forest Surveying

    20/31

    20

    In this method, the position of contour point is worked out by exact mathematical calculation.

    Let us take a simple case to illustrate this method. IF two-ground points P and Q are situated at

    a distance of 25 m with respective elevations as 80.50 m and 70.50 m. Assuming, the contour

    intervals as 2 m, the contour points for 72 m, 74 m, 76 m, 78 m and 80 m will have to be

    established on line PQ by applying the rule of three.

    Now, difference in levels between P and Q = 80.50-70.50

    = 10 m.

    Distance between P and Q = 25 m.

    ^rr)=1.25m

    Similarly, distance of 78 m contour point from P f

    25x2.5"6.25m

    10

    distance of 76 m contour point from P f

    25x4.5"

    11.25m10

    Exercise VI

    1. Find the reduced levels of the points in the field for a given grid interval and plot the contour

    map of the area.

    (2) arithmetical calculations;

  • 7/30/2019 Forest Surveying

    21/31

    21

    VII. Computation of Areas

    Methods for computation of areas

    Following are three methods adopted for the purpose of computing the areas:

    Geometrical figures

    Ordinates

    Planimeter

    II. Ordinates

    The above method becomes tedious especially when the plot is in the form of a long

    narrow strip and hence, in such cases, the area of the plot is computed by drawing a base line and

    ordinates are put up along this base line at regular intervals. The height of each ordinate is

    measured. By knowing the length of constant interval between the ordinates and height of each

    ordinate, the area of the plot can be computed by adopting any one of the following rules:

    1. Mid-ordinate rule2.

    Average ordinate rule

    3. Trapezoidal or average end area rule4. Simpson or parabolic rule

    (1) Mid -ordinate rule

    Let n = Number of equal parts

    d= Length of each equal part L= Length of

    base line = nd or d= L/n

  • 7/30/2019 Forest Surveying

    22/31

    22

    Then,

    Area = dh1+dh2+dh3+ . . .. dhn

    = d(hx+h2+h3+-------- hn )

    = L/n (h1+h2+h3+ . . .. hn)

    (2) Average ordinate rule

    In this case, the length of average ordinate is obtained by dividing the sum of all

    ordinates with the total number of ordinates measured.

    Let O1, O2, etc. = Ordinates at each of the points of division n,d and L as

    above. Then

    Number of ordinates = n+1

    O0 + O1 + O2.... + On n +1

    (3) Trapezoidal or average end area rule:

    In this case, the area of each trapezium formed between successive divisions is

    calculated independently and then added together to obtain the total area of the plot. This

    method of more accurate than the previous two methods.

    = { OIOl d + O L+O l d + ........... 0_, +On d 1I 2 2 2 I

    Area

    h1, h2 etc = Ordinates at mid-points of each division.

  • 7/30/2019 Forest Surveying

    23/31

    23

    = d/ 2[O0 + 2O1 + 2O2 + 2O3 + ........ + On ]

    + O1+O2+ O +................ + On-1

    (4) Simpson or parabolic rule

    In this case, the boundary of the plot is not assumed straight. But it is considered as a

    curve in the form of a parabola.

    Area of figure ABGDE = area of trapezium ABGE + area under curve EDG ( O + On'0

    ' x2d I + 2/ x Area of parallelogram CFGE2 J /3

    Oo + O x2d] + % x 2d x DH{ 2 J /3

    ^ Oo + O2Now DH = O10 2

    2

    (O 0 + O 2 _ ^ 2 / , , Oo + O2-----1 x2dI + % x 2d x O1 -

    0------ -

    2 J /3 1 2

    = d/3 [3Oo+3O2+4Ox - 2Oo - 2O2] = d/3 [ Oo+4Ox+Oi] Similarly, area between ordinates

    O2 and O4 will be given by the equation.

    d

  • 7/30/2019 Forest Surveying

    24/31

    24

    = d/3 [ O2+4O3+O4] and so on.

    Hence, total area between ordinates Oo and O4=

    The above rule can be summarized as follows:

    d/3 [ Oo+4O1+2O2 + 4O3 + O4]

    d/3 [ Oo+4O1+2O2 + 4O3 +. .

    2On-2+4On-1 + On]

    It is thus seen that there should be even number of divisions of the area or in other words, the

    total number of ordinates must be odd. If this is not the case, the area of the last division is

    worked out separately and then, added together to obtain the final area. The area of plot, if

    worked out by this rule, gives better results as compared o above mentioned all the rules.

    Exercise VII

    1.Following perpendicular offsets were taken from a chain line to a curved boundary line atintervals of 10m:

    0,7.38, 5.26, 6.45, 7.33, 7.87, 8.23, 0.

    Compute the area between the chain line, the curved boundary line and the end

    offsets by applying (1) average ordinate rule, (2) trapezoidal rule, and (3) simpson rule.

    2.Following table gives the perpendicular offsets taken from the center-line of road to ahedge:

    Compute he area between the center-line of road and hedge by applying (1) trapezoidal rule

    and (2) Simpson rule.

    Offset no. Oo O1 O2 O3 O4 O5 O6 O7 O8

    Offset in m 4 6 5 7 5 4 3 4 6

    Distance in m 0 15 30 45 60 80 100 110 120

  • 7/30/2019 Forest Surveying

    25/31

    25

    VIII. Theodolite Surveying

    General

    The Theodolite is an extraordinary accurate instrument used in surveying for measuring

    horizontal and vertical angles. It has also very wide applications in various surveying operations such as

    establishing grades, setting out curves, extending survey lines, etc. Thus, a Theodolite is an instrument

    for angular measurements and it given angles of required precision.

    Definitions and terms used for Theodolite work

    It is necessary to clearly understand the meanings of the following terms that are used during the

    manipulation process of a Theodolite:

    (1) Axis of level tube: It is a straight line tangential to the longitudinal curve of the level tube at itscenter. It is also known as the bubble line and it is horizontal, when the bubble is central.

    (2) Axis of telescope: It is the line joining the optical center of the object glass to the center of theeyepiece.

    (3) Centering: It is the operation carried out to ascertain the fact that the vertical axis of theinstrument passes through the center of the peg fixed at the required station point. It is carried out

    by suspending a plumb bob from the underside of the instrument.

    (4) Changing face: The operation of changing the position of vertical circle either from left to rightor from right to left of the observer is known as changing face. For a transit Theodolite, it is done

    by revolving the telescope through 180o in the vertical plane and through 180o in a horizontal

    plane. For a non-transit Theodolite, releasing and then do it, reversing the telescope for end to

    end.

    (5) Face left: When the vertical circle of the instrument is on the left of the observer taking reading,the position is known as face left position and in such position,

    the telescope is said to be in normal or direct or in bubble up position. The observation of an angle

    (horizontal or vertical) made with face left position is known as face left (F.L) observation.

  • 7/30/2019 Forest Surveying

    26/31

    26

    (6) Face right: When the vertical circle of the instrument is on the right of the observer taking reading,the position is known as face right position and in such position, the telescope is said to be in inverted

    or reversed or in bubble down position. The observation of an angle (horizontal or vertical) made

    with face right position is known as face right (F.R) observation.

    (7) Horizontal axis: It is the axis about which the telescope and the vertical circle rotate in a verticalplane. It is also known as trunnion axis or transverse axis.

    (8) Line of sight: The term line of sight or line of collimation is used to indicate an imaginary line joiningthe optical center of the object glass and intersection of the crosshairs of the diaphragm and its

    continuation.

    (9) Swinging the telescope: It is the operation of turning the instrument in a horizontal plane about itsvertical axis. Swinging is said to be right swing if the instrument is moved in clockwise direction and

    it is said to be left swing, if the instrument is moved in anti-clockwise direction.

    (10)Transitting: It is the operation of revolving the telescope in a vertical plane by 180 o about thehorizontal or trunnion axis. It is also referred to as plunging or reversing.

    (11) Vertical axis: It is the axis about which the telescope can be rotated in a horizontal plane.The lower and upper plates of the instrument rotate about this axis.

    Temporary adjustments of Theodolite

    At every set up of the instrument, certain temporary operations are carried out

    before the observations are made. These operations are known as temporary

    adjustments or station adjustments and they are made to achieve the following two

    conditions.

    1. The plane of collimation is horizontal2. The vertical axis passes through the center of the peg.

    Following are the three temporary adjustments of a Theodolite:

    1. Levelling up

  • 7/30/2019 Forest Surveying

    27/31

    27

    2. Elimination of parallax.

    Measurement of horizontal angles

    The general procedure for measuring horizontal angle by theodolite will be as

    follows.

    (1) The instrument is set up at station O and the temporary adjustments are performed to levelit accurately.

    (2) Let the verniers on upper plate be named as A and B. Adjust the vernier A to the zero(usually marked 360o) of the horizontal circle. If there is no instrumental error, the reading

    on vernier B will be 180o. Also see that the vertical circle is to the left. Now both plates are

    clamped and thus the instrument will revolve about its outer axis.

    (3) The lower clamp is loosened and it is pointed towards the left hand side object P. The lowerclamp is tightened and the object is bisected accurately by using the lower tangent screw.

    The readings of verniers A and B should be checked and as such, there should be not

    change in the previous readings. It may also be noted that the left hand side object is

    bisected first because of the fact that the graduations on the scale plate run in clockwise

    direction.

    (4) The upper clamp is loosened and the instrument is rotated clockwise about the inneraxis to bisect the object Q. The upper clamp is then clamped and the object Q is

    bisected accurately by using upper tangent screw.

    (5) The readings of both the verniers are taken. The reading of vernier A gives directly theangle POQ while the value of angle POQ on vernier B can be obtained by deducting

    180o from the reading.

    (6) The man value of two readings gives the angle POQ with one face.(7) The face is changed by transiting the telescope and the whole process is repeated. Thus,

    mean value of angle POQ is obtained with other face.

    (8) The average horizontal angle is thus obtained by taking the mean of the two valuesobtained with two faces.

  • 7/30/2019 Forest Surveying

    28/31

    28

    During the above process, care should be taken to manipulate the proper clamps and to record the

    readings properly. It is also not necessary to set vernier A to zero initially. It may be set at any desired

    reading. But in that case, the difference between the initial and final readings on vernier A should be

    worked out to get the angle POQ.

    For measuring horizontal angles with high precision without increasing the size of the scale plate, the

    following two methods have been found out:

    (1) Repetition method(2) Reiteration method

    (1) Repetition method

    In this method, the same angle is repeatedly measured two times or more by allowing the vernier

    to remain clamped each time at the end of each measurement and thus, the angle is added several times

    mechanically. However, care should be taken to add 360o for every complete evolution to the final

    reading. The average horizontal angle is then obtained by dividing the final reading by the number of

    repetitions. The face is then changed and the whole process is repeated. Thus, the average horizontal

    angle is obtained by taking the mean of the two value obtained by taking the mean of the two values

    obtained with two faces.

    The procedure is the same as described above. But is is more exhaustive and laborious. However,

    there is no advantage by increasing the number of repetitions indefinitely. Usually the angle is

    accumulated three times with each face and it gives fairly accurate result.

    When this method is adopted, the following errors are eliminated:

    (1)Error due to eccentricity of verniers;(2)Error due to inaccurate bisection of the object;(3)Error due to inaccurate graduations and(4)Error due to line of collimation and trunnion axis not being perpendicular to each other.

  • 7/30/2019 Forest Surveying

    29/31

    29

    The repetition method of measuring horizontal angle does not eliminate errors due to slip, displacement

    of station signals, dislevelment of the bubble, etc. because these errors are cumulative in nature. (2)

    Reiteration method

    This method is also known as method of series or direction method. It is generally preferred when

    several angles are to be measured at a station. The procedure consists in measuring successively several

    angles in clockwise direction and finally the horizon is closed. The term closing the horizon is used to

    mean the process of measuring the angle between the last station and the initial station. Thus, it gives a

    check on the angle measured because of the fact that sum of angles around a point is 360 o. This method is

    less tedious than the repetition method and it gives equally precise observations in short time.

    Measurement of vertical angles:

    The angle made between the inclined line of sight and the horizontal line of collimation is known

    as the vertical angle. If the point is above the horizontal plane, it is called the angle of depression and is

    treated as negative. Following is the procedure for measuring vertical angle, as shown in

    (1) The instrument is set up at station O and it is leveled accurately with reference to the altitudebubble.

    (2) The zero of vertical vernier is exactly set to zero of the vertical circle with the help of the verticalcircle with the help of the vertical circle clamp and tangent screw.

    (3) The bubble of the altitude level is brought at the center by means of the clip screws. Thus, theline of collimation becomes horizontal with respect to the zero reading on the vernier.

    (4) The vertical circle clamp is loosened and the telescope is sighted in vertical plane to P. Theaccurate bisection is obtained with the help of vertical circle tangent screw.

    (5) The readings on both the verniers of vertical circle are taken, the mean of which gives therequired vertical angle.

    (6) The face is changed and another value of angle is obtained by repeating the process.(7) The average vertical angle is thus obtained by taking the mean of the two values obtained with

    two faces.

    It is easy to understand that the above procedure can also be adopted to measure the

    vertical angle between two points subtended at the instrument station. It will be equal

    to the sum or difference of the two readings depending on the relative positions of the

    points with reference to the horizontal line of collimation. Exercise

    VIII

  • 7/30/2019 Forest Surveying

    30/31

    30

    1.Determine the horizontal angles by theodolite survey2.Using the theodolite find the vertical angle and horizontal distances

    IX. Ghat tracer

    Ghat tracer is an useful instrument for finding gradients, setting out grade contours, preliminary survey

    of hill route for road alignment and also for contouring and leveling.

    Construction: It consists of a triangular frame with a hollow metal sighting tube fitted with an eyepiece at

    one end and with cross wires at the other. It is hung by a pivot at apex, on an upright staff, by means of a

    clamping pin and nut. About 2 to 3 cm below the sighting tube and parallel to it there is a racked

    horizontal bar, attached to the tube rigidly by 2 small vertical bars, one at other end. A weight suspended

    on the bar can be moved along the racked bar by means of a screw, fixed on the supporting bracket,

    operating the pinion on the rack. Upper part of the weight has a knife edge, which forms an index, by

    which readings can be taken on the scale of the gradients of 1 in 6 or 1 in 120. The line of sight is the line

    joining the centre of the eyehole and the intersection of cross wires. The tube and consequently the line

    of sight can be set to any desired gradient by moving the weight of the racked bar.

    Method of use:

    The T shaped sight vane or target, on which readings are taken, has its cross line at the same height as the

    height of the axis of the sighting tube. To find the gradient of slope an assistant is sent ahead with the

    sight vane and the weight is moved along the bar till the cross wires are aligned on the sight vane and the

    gradient read on the scale. When the sight is taken uphill weight is moved backward from zero mark and

    vice versa. If it is desired to layout on the ground an alignment at a fixed gradient the index is set to the

    required gradient and the weight screwed down. An assistant is sent with the sight vane, who moves up

    and down till he is on the required gradient. To establish a line of sight, set the index exactly in the centre

    of the sighting tube at zero gradients. Exercise IX

    1. Using the ghat tracer mark the contours of the alignment

  • 7/30/2019 Forest Surveying

    31/31

    31

    CONTENTS

    Ex. No. Title Page No.I. Scales 1

    II. Chain Surveying 7

    III. Compass Surveying 11

    IV. Plane Table surveying 16

    V. Levelling 19

    VI. Contouring 24

    VII. Computation of areas 26

    VIII. Theodolite surveying 30

    IX. Ghat tracer 36


Recommended