Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
28
FORM-1A
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
29
FORM-I A
FORM-1 A (only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach explanatory
notes with the Form and submit along with proposed environmental management plan & monitoring
programme)
LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)- Enclosed as – IV (c)
1.1 Will the existing land use get
significantly altered from the project
that is not in consistent with the
surroundings? (Proposed land use
must conform to the approved Master
Plan / Development Plan of the area.
Change of land use if any and the
statutory approval from the competent
authority are submitted). Attach Maps
of (i) site location, (ii) surrounding
features of the proposed site (within
500 meters) and (iii) the site
(indicating levels & contours) to
appropriate scales. If not available
attach only conceptual plans.
: The project is situated on a designated residential
land. Copy of Lease Deed is enclosed as Annexure
I.
The following are hereby enclosed:
1. Surrounding features of the site (within 500
meters) : Annexure – VI
2. Conceptual Plan : Annexure – IV
1.2 List out all the major project
requirements in terms of the land area,
built up area, water consumption,
power requirement, connectivity,
community facilities, parking needs
etc.
: The major requirements of the project are
summarized as under:
1. Total plot area 4,670 sq.m.
2. Gross Built up
area
32,000.49 Sq.m.
3. Water
consumption
Daily water demand: 126 KLD
(80 KLD fresh + 46 KLD treated
waste water)
4. Power
requirement
Connected load 2041.63 KW
Demand load 1054.38 KW
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
30
5. Connectivity
facilities
• Alwar RS: 2.26 km NE*
• Jaipur International Airport:
112.41 km SW*
6. Parking needs Total ECU required : 256
Total ECU provided : 256
*Distances as measured from Google Earth
The details of the connectivity and community
facilities are given in Form 1 under point
Environmental sensitivity.
1.3 What are the likely impacts of the
proposed activity on the existing
facilities adjacent to the proposed site?
(Such as open spaces, community
facilities, details of the existing land
use, disturbance to the local ecology).
: Existing Facilities:
Direction Facilities
East Road 100” wide
Existing Road North
West Road 60” wide
South Road 80” wide
The impact due to the project may be increase in the
traffic loads and emissions. Due care will be taken
during operational phase to minimize the impact on
surroundings.
Disturbance to the local ecology:
Adjacent habitats indicate that the project site
would have supported only some common floral-
faunal species which uses wide variety of habitats
of the urban ecosystem. So, present project will not
have any adverse impact on the ecological
conditions.
About 595.39 (12.75%) area will be under
landscape/ green belt, Measures will be adopted to
recreate landform capable of maintain ecological
conditions and capacity to support the similar
habitats and species.
1.4 Will there be any significant land
disturbance resulting in erosion,
: Soil:
• Colour: Light Brown
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
31
subsidence & instability? (Details of
soil type, slope analysis, vulnerability
to subsidence, seismicity, etc may be
given).
• Soil stratum: Sandy Clay.
Soil analysis report enclosed as Annexure - V.
Slope Analysis:
The topography of the site is gentle with mild slope
tending towards NW from SE. The highest elevation
is 100.14 mRL, while the lowest elevation is 99.59
mRL. In post construction phase, the overall
direction of the natural gradient will be retained to
the extent possible. Contour plan enclosed as
Annexure III.
Vulnerability to Subsidence:
There is no subsidence reported in the area
Seismicity :
The area is classified as Zone IV (High Damage
Risk Zone) as per the BIS classification. The
building design is made with earthquake resistant
design structure. Structure with ductile detailing is
considered as per IS: 13920-1993.
1.5 Will the proposal involve alteration of
natural drainage systems? (Give
details on a contour map showing the
natural drainage near the proposed
project site)
: The slope of the site is gentle. The overall direction
of the natural gradient is retained to the extent
possible. The surface run-off will increase due to
increase in paved areas. The same will be
channelized to well connected storm water drains.
1.6 What are the quantities of earthwork
involved in the construction activity-
cutting, filling, reclamation etc. (Give
details of the quantities of earthwork
involved, transport of fill materials
from outside the site etc?)
: The topsoil generated from the site preparation
activities was utilized at site itself for horticulture
purposes.
1.7 Give details regarding water supply,
waste handling etc during the
construction period.
Water supply:
The peak domestic water demand during
construction phase will be about 9 KLD (@45 lpcd/
person – 200 No.) which will be met from tanker
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
32
supply.
Waste handling:
Around 5 KLD effluent will be generated which will
be treated in septic tank followed by soak-pit.
Solid waste:
20 kg/day solid-waste (peak) will be generated
during construction phase and will be sent to
disposal site.
1.8 Will the low lying areas & wetlands
get altered? (Provide details of how
low lying and wetlands are getting
modified from the proposed activity)
: There are no wetlands and low lying areas around
the site.
1.9 Whether construction debris & waste
during construction cause health
hazard? (Give quantities of various
types of wastes generated during
construction including the
construction labour and the means of
disposal)
: Construction debris & waste comprise of various
domestic hazardous waste like paints, electrical
fittings, plastics, varnishes, empty containers,
adhesives, etc. The same was handled carefully.
Detailed quantification & management of the same
are given Form 1 under point 1.15.
2. WATER ENVIRONMENT
2.1 Give the total quantity of water
requirement for the proposed project
with the breakup of requirements for
various uses. How will the water
requirement met? State the sources &
quantities and furnish a water balance
statement.
The daily water requirement for the proposed
project will be 126 KLD (fresh water demand: 80
KLD and the recycled water demand 46 KLD). The
daily fresh water demand will be met from the
PHED water supply & Existing Borewell (1no).
Copy of NOC obtained from district collector and
application submitted to PHED is enclosed as
Annexure X.
The water balance flowchart showing break up of
requirements for various uses is given as under
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
33
Fresh water
80 KLD
Recycle/
Reuse
treated
wastewater
46 KLD
Group Housing :76 KLD
Flushing : 26 KLD
102 KLD
Waste water
S
T
P
Capacity
130 KLD
61 KLD
3 KLD
Sludge &
Evaporation
losses
7 KLD
STP treated wastewater
WATER BALANCE (Total)
Daily Water Demand = 80 + 46 = 126 KLD
Staff , Commercial & Visitor :
4 KLD
25 KLD
Excessive
treated
wastewater
49 KLD
Filter back wash @ 40 cu.m.
/ hr. for 15 min.: 7.5 KLD
6 KLD
Landscaping : 4.5 KLD
General washing : 8 KLD7 KLD
2.2 What is the capacity (dependable
flow or yield) of the proposed source
of water?
: The daily fresh water requirement will be
approximately 80 KLD, which will be met from
PHED water supply & Existing Borewell (1no).
2.3 What is the quality of water required,
in case, the supply is not from a
municipal source? (Provide physical,
chemical, biological characteristics
with class of water quality)
: The source of water supply will be PHED Supply &
existing bore well. The ground water quality was
analyzed by Vison Labs as per the IS 10500
standards. Monitoring reports are enclosed
Annexure V.
2.4 How much of the water requirement
can be met from the recycling of
treated wastewater? (Give the details
of quantities, sources and usage)
: The details are given as under:
S.
No. Particular
Quantity
(KLD)
1. Total wastewater generation from
domestic activities
102
2. STP Treated wastewater utilization
i Flushing 26
ii General washing 8
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
34
iii Landscaping 4.5
iv STP Filter back wash 7.5
2.5 Will there be diversion of water from
other users? (Please assess the
impacts of the project on other
existing uses and quantities of
consumption)
: No, There will be no diversion of water from the
other users as the daily fresh water demand to the
tune of 80 KLD will be met PHED water supply &
Existing Borewell (1no). (Copy of NOC obtained
from district collector and application submitted to
PHED is enclosed as Annexure X.)
2.6 What is the incremental pollution
load from wastewater generated from
the proposed activity? (Give details
of the quantities and composition of
wastewater generated from the
proposed activity.
: At present there is no major source of water pollution
at the site. Characteristic of influent & effluent along
with estimated pollution load is given as:
Total wastewater generation 102 KLD
Composition of wastewater & treated water
Parameters Influent (mg/l) Effluent (mg/l)
pH 7.5 - 8.5 7 - 8
Suspended solids 275 - 325 <10 mg/l
BOD 250 - 300 <10 mg/l
COD 375 - 500 <50 mg/l
Oil & Grease 35-50 <5 mg/l
Coliforms (MPN
/ 100 ml)
105 - 107 50 - 500 / less
2.7 Give details of the water
requirements met from water
harvesting? Furnish details of the
facilities created.
: Rain run-off from the terraces and landscaped/open
areas will be channelized to well design storm water
network followed by ground water recharge.
The details are tabulated as under:
Details of structures
Number of recharge pits 2
Volume of recharge pit 27 cu. m.
Location recharge pits Given in mosaic plan
enclosed as Annexure VII
Annual recharge (approx) 2,725 cu. m.
*Source: Indian Meteorological Department
Details of the same given in CP & EMP.
2.8 What would be the impact of the land : The runoff characteristic for more than 80% area has
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
35
use changes occurring due to the
proposed project on the runoff
characteristics (quantitative as well as
qualitative) of the area in the post
construction phase on a long term
basis? Would it aggravate the
problems of flooding or water
logging in any way?
been altered permanently due to change in land use
pattern by the project and leads to increase in
quantity of runoff due to reduced infiltration.
However, to avoid water logging / flooding problems
2 structure of 27 cu.m. capacity has been provided
along with storm water drain for better infiltration of
rain water. In addition to that excess rain water
collection sump (01 nos.) of 30 cu.m. capacity is also
recommended. By this way water flooding / logging
condition chances will be minimum at the site.
2.9 What are the impacts of the proposal
on the ground water? (Will there be
tapping of ground water; give the
details of ground water table,
recharging capacity, and approvals
obtained from competent authority, if
any)
: The source of water supply will be existing bore
well. The area falls under the Umrain Block, which is
Over exploited block as per CGWA classification.
S. No. Particulars Description
1 Recharging
capacity
Recharging capacity approx.
2,725 cu.m. / annum, while
the direct abstraction is Nil.
2 Approval from
competent
authority
Application for Fresh water
supply has been applied to
PHED. Ground water will be
accepted only after taking
necessary approval form
competent authority.
2.10 What precautions/measures are taken
to prevent the run-off from
construction activities polluting land
& aquifers? (Give details of
quantities and the measures taken to
avoid the adverse impacts)
: Construction period is ongoing. Effective measures
will be adopted during construction phase to reduce
the storm water run-off from the construction site-
• Construction material is being stored at the
earmarked places and covered with a temporary
shed.
2.11 How is the storm water from within
the site managed? (State the
provisions made to avoid flooding of
the area, details of the drainage
: Following measures will be adopted to manage the
storm water and avoid flooding of the area:
• Narrow flow through planter well-integrated into
its perimeter landscaping.
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
36
facilities provided along with a site
layout indication contour levels)
• Silt fencing will be installed at selected locations
across the site.
• To avoid water logging / flooding problems 2 rain
water harvesting structure are provided.
2.12 Will the deployment of construction
laborers particularly in the peak
period lead to unsanitary conditions
around the project site (Justify with
proper explanation)
: Provisions are made to provide appropriate
facilities, as described below, will help to prevent
unsanitary conditions in and around the project
area.
• The civil contractor is held responsible for site
sanitation and will be bound by the management
to adhere to healthy level of sanitation.
• For sewage wastewater temporary septic-tank
followed by soak-pit will be provided at the site.
2.13 What on-site facilities are provided
for the collection, treatment & safe
disposal of sewage? (Give details of
the quantities of wastewater
generation, treatment capacities with
technology & facilities for recycling
and disposal)
: Details of onsite facilities provided for collection,
treatment & safe disposal of sewage:
Post Construct Wastewater Quantity: 102 KLD
Collection Closed pipe line system connected to
collection tank of STP
Facility for
Recycling /
Reuse
Following facility for recycling is
proposed:
Dual Plumbing will have separate:
1. Pipe line for domestic wastewater drain
2. Pipeline for treated wastewater supply.
Usage Dual plumbing for recycling / reuse of
treated wastewater:
• Flushing : 26 KLD
• Landscaping : 4.5 KLD
• General washing : 8 KLD
• Filter Backwash: 7.5 KLD
2.14 Give details of dual plumbing system
if treated waste is used for flushing of
toilets or any other use.
: Dual plumbing system details are given in the mosaic
plan enclosed as Annexure VII. There will be
separate pipelines for the supply of the fresh-water
and treated-water from STP. Treated-water will be
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
37
used for the flushing purposes, landscaping and
general washing purposes, while the fresh water will
be used for domestic consumption.
3. VEGETATION
3.1 Is there any threat of the project to
the biodiversity? (Give a description
of the local ecosystem with it’s
unique features, if any)
: Since the site is already situated admist of the urban
ecosystem which comprises common floral and
faunal species which generally found in the same
ecosystem, so there will be no impact on the existing
biodiversity and surrounding urban ecosystem.
3.2 Will the construction involve
extensive clearing or modification of
vegetation? (Provide a detailed
account of the trees & vegetation
affected by the project)
Construction phase is ongoing and vegetation
clearance are completed at the site.
3.3 What are the measures proposed to
be taken to minimize the likely
impacts on important site features
(Give details of proposal for tree
plantation, landscaping, creation of
water bodies etc along with a layout
plan to an appropriate scale)
: Due care will be taken to protect the important site
features:
• A total of 595.39 (12.75%) area is designated
under landscaping/greenbelt will help in
minimizing the impacts.
4. FAUNA
4.1 Is there likely to be any displacement
of fauna- both terrestrial and aquatic
or creation of barriers for their
movement? Provide the details.
: No, None
4.2 Any direct or indirect impacts on the
avifauna of the area? Provide details.
: None
4.3 Prescribe measures such as corridors,
fish ladders, etc to mitigate adverse
impacts on fauna
: No
5 AIR ENVIRONMENT
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
38
5.1 Will the project increase atmospheric
concentration of gases & result in
heat islands? (Give details of
background air quality levels with
predicted values based on dispersion
models taking into account the
increased traffic generation as a
result of the proposed constructions)
: Impact on Air Quality
The impact on air quality is assessed based on
emissions of the proposed DG set and vehicular
emissions. SO2, NOx and CO will be the important
pollutants emitting from these sources.
Mitigation measures:
• Carpooling will be encouraged.
• Provisions of separate entry/ exit to the project.
About 12.75% area will be under landscape which
will help to contain the emissions within the
permissible norms.
FIG.1 : Isopleths Showing Maximum Incremental Ground Level Concentrations of SO2
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
39
FIG.2 : Isopleths Showing Maximum Incremental Ground Level Concentrations of NOx
FIG.3: Isopleths Showing Maximum Incremental Ground Level Concentrations of CO
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
40
5.2 What are the impacts on
generation of dust, smoke,
odorous fumes or other hazardous
gases? Give details in relation to
all the meteorological parameters.
: No smoke, odorous fumes or other hazardous gases will
be generated. The impacts of dust and gaseous
pollutants due to different activities will be localized
and will not affect the surrounding environment. The
same will be mitigated by effective EMP.
5.3 Will the proposal create shortage
of parking space for vehicles?
Furnish details of the present level
of transport infrastructure and
measures proposed for
improvement including the traffic
management at the entry & exit to
the project site.
: There will be no shortage of parking space.
Total ECU required : 256 ECU
Total ECU provided : 256 ECU
The peak intensity of traffic is given in the traffic
monitoring report (enclosed as Annexure- V). The
project will contribute 256 ECU additional load of the
same.
• Provisions of fully internalized parking including
the parking facilities for the visitors.
• Guided traffic ways within the project site.
• Speed humps will be installed for speed restrictions
inside the project area.
5.4 Provide details of the movement
patterns with internal roads,
bicycle tracks, pedestrian
pathways, footpaths etc., with
areas under each category.
: The movement pattern inside the project area will be
guided by traffic-ways. There will not be any separate
bicycle-tracks or pedestrian-pathways on the periphery
(driveway). Mosaic plan is enclosed as Annexure VII.
5.5 Will there be significant increase
in traffic noise & vibrations? Give
details of the sources and the
measures proposed for mitigation
of the above.
There is no significant increase in noise and vibration.
The noise and vibration levels will be well within the
norms.
The following measures will be adopted to reduce the
noise:
1. Trees with heavy foliage will be planted at the
periphery so as to restrict the noise levels within the
permissible norms.
2. Both entry and exit will be manned with trained and
efficient security.
3. Road markings, Stop lines, parking lanes will be
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
41
painted to guide the internal road user.
5.6 What will be the impact of DG
sets & other equipment on noise
levels & vibration in & ambient
air quality around the project site?
Provide details.
: Post Construction phase:
The important source of pollution during post
construction phase will be emissions from 1 D.G. set of
capacity 125 kVA, used in case of power cuts or failure
(for common area power back up).
The details of the DG set, fuel consumption and stack
height, is given as under:
Capacity Fuel Fuel
consumption
Stack
height
125 kVA: 1 no HSD 20.8 l/hr 49 m
The DG sets will be housed in an inbuilt acoustic
enclosure for maximum noise attenuation.
The DG sets deployed will be EPA/ CPCB certified for
the permissible standards of noise & vibrations.
6. AESTHETICS
6.1 Will the proposed constructions in
any way result in the obstruction
of a view, scenic amenity or
landscapes? Are these
considerations taken into account
by the proponents?
: There will be a visual impact on the surroundings. This
will add to the change in the localized physical impact.
6.2 Will there be any adverse impacts
from new constructions on the
existing structures? What are the
considerations taken into account?
: Due care is being taken in construction phase and
adverse impacts during post construction phase will
also be mitigated by effective EMP.
6.3 Whether there are any local
considerations of urban form &
urban design influencing the
design criteria? They may be
explicitly spelt out.
: The building is designed on the urban architectural
form basis.
6.4 Are there any anthropological or
archaeological sites or artifacts
: No, there is no anthropological or archaeological site in
the close vicinity as per the data available from
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
42
nearby? State if any other
significant features in the vicinity
of the proposed site have been
considered.
secondary sources.
7. SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any
changes to the demographic structure
of local population? Provide details.
: The project will provide housing facilities to approx.
1162 residents.
7.2 Give details of the existing social
infrastructure around the proposed
project.
: Within 1.0 km area habitation is towards west,
Sonawa Mohalla (West). The Indira Gandhi Stadium
towards N and market place is in 100 meters around
the bus stand Shanti Kunj Bus Stop 280 m SE.
Transportation Bus Govt. Roadways / Private -
Tractors, Scooters, Motor Cycles,
(Public transport available).
Shanti Kunj Bus Stop 280 m SE
Public
Infrastructures:
Aravali Vihar Police Station 149 m S
Fire Station 177 m SE
Saras Dairy Alwar Plant 641 m South
Districts Sports officer 190 m N
Schools and
Institutes :
Kendra Vidhyalya No.1(Moti Dungri)
Alwar 556 m North; Bal Bharti Sr.
Sec. School 214 m NNW ; Dungri
Public School 600 m North; Royal
Academy Alwar 310 m NE; Central
Academy 273 m SW ; Iron Institute
750 m North ; APS School 5 km,
Arya Kanya Vidhyalaya 2 km;
Recreation and
Amusements :
Phool Bagh Palace 258 m NE; Moti
Doongri Children Park 556 m North;
Rajiv Gandhi Smriti Udyan 500 m
North; Pratap Auditorium 140 m NE;
Football ground 286 m NE; Ashok
Leyland Guest House towards 150 m
E ; Hotel Mayur 72 m SE
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
43
Hospital Mathura Devi Memorial Hospital 625
m North; Veterinary hospital 351 m
SW;
7.3 Will the project cause adverse effects
on local communities, disturbance to
sacred sites or other cultural values?
What are the safeguards proposed?
: No
8. BUILDING MATERIALS
8.1 May involve the use of building
materials with high-embodied
energy. Are the construction
materials produced with energy
efficient processes? (Give details of
energy conservation measures in the
selection of building materials and
their energy efficiency)
: The basic materials used were PPC cement, steel,
ready-mix concrete, sand, hard-wood, glass, etc.
• Ready-Mix concrete was be used.
• Energy savings by the use of low embodied
energy materials over conventional material is
given as:
Material % Energy Saving Achieved
PPC 46.87
Steel 40
8.2 Transport and handling of materials
during construction may result in
pollution, noise & public nuisance.
What measures are taken to
minimize the impacts?
: During the construction phase, the following
measures will be taken to prevent pollution.
• Covering loads to limit materials or litter blowing
off and reducing smells.
• Ready-mix concrete will be used for concreting.
• Water spraying to prevent dust pollution from
different sources of construction.
• Speed restriction of all the vehicles approaching
the site and within the site.
• All transportation vehicles will be suitably covered
with tarpaulin & overloading of the vehicles will
be avoided and pollution checked vehicle will be
must.
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
44
8.3 Are recycled materials used in roads
and structures? State the extent of
savings achieved?
: Yes, the waste generated as PPC cement, reinforced
steel, ceramic tiles were used as a construction
material.
Fly ash was used as building material (Copy of bills
is enclosed as Annexure XIX)
8.4 Give details of the methods of
collection, segregation & disposal of
the garbage generated during the
operation phases of the project.
: All the wastes from different sections will be
collected and treated as per the Municipal Handling
rules.
Collection:
A system of segregation at source will be
implemented. Colour-coding bins will be provided
for different types of wastes.
The details of the various activities generating solid
waste, classification, collection facilities, treatment
and disposal is given as mentioned at point No.1.15
(Form 1).
9. ENERGY CONSERVATION
9.1 Give details of the power
requirements, source of supply,
backup source etc. What is the
energy consumption assumed per
square foot of built-up area? How
have you tried to minimize energy
consumption?
: Energy:
S. N Description
1. Source of
supply
Will be met through Alwar Vidyut
Vitran Nigam Limited
2. Electrical
Load
Connected load 2041.63 KW
Max Demand 1054.38 KW
4. DG Sets No. of DG sets 1
DG Capacity 125 kVA
Energy conservation techniques:
• Taking advantage of day lighting wherever
possible to reduce the need for electric lights.
• Total light load will be reduced by 25% by the use
of energy efficient CFL Lamps.
• Total landscape light load can be reduced by 20%
by the use of solar powered fixtures.
• Common area light load can be reduced by 20% by
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
45
the use of CFL lights.
• Total power load can be reduced by 10% by the use
of solar hot water generator.
• Power factor will be maintained around unity. All
capacitors will be provided with Harmonic Filters to
avoid distortion in Voltage.
• Details of total energy savings is tabulated as under:
S. No. Particulars Actual Load
(KW)
Load saving
(KW)
Energy Saving
(KWh)
1 Lighting load – Flats 535 107 1070
2 Total Power load 1351 135.1 1351.237
3 Landscape & External Light Load 10 3 24
4 Common area Light load 26 5.1 61.611
TOTAL
2506.848
(22.6% reduction)
9.2 What type of, and capacity of,
power back-up to you plan to
provide?
: There will be power back up for common areas as well
as essential services through 1 DG set of capacity of
125 kVA.
9.3 What are the characteristics of the
glass you plan to use? Provide
specifications of its characteristics
related to both short wave and
long wave radiation?
: Plain glass has been used for fenestration purposes
only. Characteristics are as under*:
Parameters 5 mm clear 8 mm clear
Light transmission 90% 88%
Light reflectance 8% 8%
Solar factor 85% 81%
Shading coefficient 0.97 0.94
Solar energy:
Transmission 82% 77%
Reflectance 8% 7%
Absorption 10% 16%
U –value 5.8 W/m2K 5.7 W/m
2K
Source: www.sunguardglass.com
9.4 What passive solar architectural
features are being used in the
building? Illustrate the
applications made in the proposed
: Building design and envelope have been optimized
through selection of appropriate wall and roof
construction and through adoption of solar passive
measures after studying the sun path analysis to provide
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
46
project. shading devices for windows and roof which would
reduce energy demand.
Components of the solar architectural features in the
proposed building:
• Adequate natural cross-ventilation.
• Sufficient day-lighting with direct heat gains
• Adequate shading devices
1. Natural cross ventilation: There will be adequate
openable windows and doors in the living spaces,
kitchens & bathrooms.
2. Shading: South facing glass can be a source of
overheating during summer months. The potential
for overheating will be controlled by roof over
carefully designed to shade the glass during the
summer (sun higher in the sky) but not block
sunlight during the winter (lower in the sky). The
towers are aligned in a way that acts as shading
devices.
9.5 Does the layout of streets &
buildings maximize the potential
for solar energy devices? Have
you considered the use of street
lighting, emergency lighting and
solar hot water systems for use in
the building complex?
Substantiate with details.
: Yes. Solar geysers will be used.
S.
No.
Equipment Location Number Capacity of each
equipment
Total capacity
1. Solar geysers Building terraces 15
250 L 3.75 KL
(approx)
2. Solar standalone
street lighting system
Street & landscape
area
36 nos.
(approx.)
90 W each 3.24 KW
9.6 Is shading effectively used to : Yes, use of shading has been plan effectively.
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
47
reduce cooling/heating loads?
What principles have been used to
maximize the shading of Walls on
the East and the West and the
Roof? How much energy saving
has been effected?
Modified SHGC (Solar Heat Gain coefficient)
including the effect of overhangs is calculated for
proposed design.
SHGC for proposed design SHGC limit as per
ECBC
0.16 0.25
Walls.
East and West Elevations.
Walls that face the east and west will be well insulated
as possible, to prevent summer heat gain.
Following additional measures are suggested to be
used for maximizing the shading of walls on the East
and the West:
• Shading by means of Verandah on East Facade.
• Very few Openings and high thermal mass to reject
and store the Solar heat on South facing Façade.
Roof:
Roofs will be covered with reflective china mosaic
tiles having lower U valves for lesser heat gains inside
the building.
9.7 Do the structures use energy-
efficient space conditioning,
lighting and mechanical systems?
Provide technical details. Provide
details of the transformers and
motor efficiencies, lighting
intensity and air-conditioning load
assumptions? Are you using CFC
and HCFC free chillers? Provide
specifications
Transformers:
• Automatic power factor compensating multiple
capacitor units will be provided for maintaining of
average power factor of 0.95 to have effective
savings in energy cost.
• All cables shall be derated to avoid heating during
use. This also indirectly reduces losses and
improves reliability.
• LV Power supply duly terminated at each floor
through XLPE cable with a suitable size MDB.
The project does not envisage central air conditioning
and use of chillers.
Lighting System:
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
48
Day light factor for towers is varying between 1.6% to
1.75 %.
Details of recommended Lux level is given as under:
S. No. Space Illumination Level (Lux)
i. Entrance 150-200-300
ii. Lifts 50-100-150
iii. Corridor, passageways, stairs 50-100-150
iv. Covered car par
• Floor
• Entrance and exits
5-20
50-100-150
v. Outdoor car park 5 – 20
9.8 What are the likely effects of
the building activity in altering
the micro-climates? Provide a
self-assessment on the likely
impacts of the proposed
construction on creation of heat
island & inversion effects?
: Heat emission from the project can be from the following
sources:
• Heat absorbed and radiated from the paved and
concrete structures.
• Increased population for a particular stretch of land.
Heat Island Effect: Roof
• The roofs will be covered with solar panels which will
reduce the exposed roof area.
Heat Island Effect: Non-roof:
• Hard paving onsite has been reduced to the best
possible extent.
• About 12.54% of the area will be under landscape,
which will mitigate heat island effect.
9.9 What are the thermal
characteristics of the building
envelope? (a) Roof; (b)
external walls; and (c)
fenestration. Give details of the
material used and the U-values
or the R values of the
individual components.
The building materials were selected with characteristics
that limit heat ingress into the inside of the building will
be minimized.
Climate zone: Composite
Building type: 24 hrs used building
U value (W/m2-°C) R value (m
2°C/W)
Roof 0.261 3.5
Wall 0.440 2.1 Source:ECBC CODE 2007
Vertical Fenestration:
Vertical Fenestration
Maximum U- Maximum Maximum VLT
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
49
factor SHGC
3.30 W/m2-°C 0.25 0.27 Source:ECBC CODE 2007
9.10 What precautions & safety
measures are proposed against
fire hazards? Furnish details of
emergency plans.
Essential fire safety measures will be installed into the
building to ensure the safety of the occupants within the
building in the event of fire or other emergency.
The entire building will be designed as per NBC-2005 of
India pertaining to fire-hazards.
Hazard classification as per the NBC-2005, Part IV-Fire
& Life Safety:
� Group A, sub division A-4: Buildings above 45 m in
height but not exceeding 60 m.
Minimum fire fighting requirement (as per NBC 2005
Part IV Table 23) will be provided in the project. The
same is tabulated as under:
S.No. Item Group Housing
[ Height >45 m but <60 m]
1. Fire extinguisher Required
2. Hose reel Required
3. Dry riser Not Required
4. Wet riser Required
5. Down comer Not Required
6. Yard hydrant Required
7. Automatic sprinkler system Required
8. Manually operated fire alarm system Required
9. Automatic detection & alarm system Not Required
10. Underground water tank 75000 litres
11. Terrace water tank 10000 itres
12. Pump capacity for pump near underground static water storage
tank (Fire Pump) with minimum pressure of 3.5 kg/cm2 at terrace
level
One electric and one diesel
pump of capacity 2280 l/min
and one electrical pump with
capacity 180 l/min
13. At the terrace tank level with minimum pressure of 2.0 kg/cm2
Not Required
Safety measures:-
• Proper fire-exits and exit-signage will be provided.
• Fire-extinguishers of appropriate type will be placed on
Project : Panache Form- I A
Promoted by: Goldendunes Colonizers Pvt. Ltd.
50
a readily accessible place and will be maintained
accordingly.
9.11 If you are using glass as wall
material provides details and
specifications including
emissive and thermal
characteristics.
: Glass is not used as wall material except for the windows.
9.12 What is the rate of air
infiltration into the building?
Provide details of how you are
mitigating the effects of
infiltration.
: Building is designed with positive pressure.
9.13 To what extent the non-
conventional energy
technologies are utilized in the
overall energy consumption?
Provide details of the
renewable energy technologies
used.
: The solar energy will be utilized efficiently for-
• 10% energy demand will be reduced by preheating the
water by using Solar geysers.
10 ENVIRONMENT MANAGEMENT PLAN
The Environment Management Plan would consist of all mitigation measures for each item
wise activity to be undertaken during the construction, operation and the entire life cycle to
minimize adverse environmental impacts as a result of the activities of the project. It would
also delineate the environmental monitoring plan for compliance of various environmental
regulations. It will state the steps to be taken in case of emergency such as accidents at the site
including fire.
***********