FORM I
FORM - I (I) Basic Information
S. No Item Details
1 Name of the project/s Proposed throughput increase in LPG production
2 S.No. in the schedule 6(b) – Isolated storage & handling of hazardous chemicals
3 Proposed capacity / area / length / tonnage to be handled / command area / lease area / number of wells to be drilled
Expansion to 23,04,000 MTPA LPG throughput by 1. Increasing the number of operating shifts
from one to three2. Addition of 4 Tanker Lorry Filling Shed
(TLD)4 New/Expansion/Modernization Expansion of LPG throughput capacity.
For existing activity, the unit has Consent orders from Tamil Nadu Pollution Control board (TNPCB) under the Water (Prevention & Control of Pollution) Act, 1974 amended in 1988 and the Air (Prevention & Control of Pollution) Act, 1981 amended in 1987.
5 Existing Capacity/ Area etc. The existing LPG throughput of the Terminal is 5,76,000TPA on a single shift of operation. Number of storage units & TLD bays are given below, Description (existing Quantity 1. Storage Capacity(A) Refrigerated storage 1. SR – 01 for LPG(Propane)
15000 MT
2. SR – 02 for LPG (Butane) 15000 MT3. SR – 03 for LPG(Propane)
7500 MT
4. SR – 04 for LPG (Butane) 7500 MT(B) Mounded storage 1. LPG – 3 Nos. 300 MT each
6 Category of Project i.e. ‘A’ or ‘B’ Category ‘A’
7 Does it attract the general condition? If yes, please specify.
No.
8 Does it attract the specific condition? If yes, please specify.
No.
Page 1
FORM I
9 Location Survey No. 94 pt, 95 pt, 109, 110, 202 pt, 204, 207-216, 219-225. Athipattu Village Ponneri Taluk Thiruvallur District Tamil Nadu – 600 120
Plot / Survey / Khasra No. Village Tehsil District State
10 Nearest railway station/airport along with distance in Km.
Athipattu Pudhunagar Railway Station – 0.5 km Chennai International Airport – 42 km
11 Nearest town, city, district headquarters along with distance in Km.
Thiruvallur town (Dist. HQ) – 43 km (SW) Chennai City – 23km (S)
12 Village panchayats, Zilla parished, municipal corporation, local body (complete postal address with telephone nos. to be given)
The Commissioner, Minjur Panchayat Union, Thiruvallur District – 601 203
13 Name of the applicant M/s. IndianOil Petronas Pvt. Ltd. 14 Registered address Office:
12th Floor, Mohandev Building 13, Tolstoy Marg, New Delhi PIN Code - 110001 Factory: LPG Import/Export Terminal 143, Athipattu Village, NCTPS Main Road, Chennai - 600 120
15 Address for correspondence Name Mr. S. Sekar Designation (Owner/Partner/CEO) DGM (Plant) Address M/s. IndianOil Petronas Pvt. Ltd.
143, Athipatu Village, NCTPS Main Road, Chennai -
Pin Code 600 120 E-Mail [email protected] Telephone No 044-64553340; 91-9444441296 Fax No --
16 Details of Alternative Sites Examined, if any, location of these sites should be shown on a topo sheet.
No alternative sites are examined as the increase in LPG throughput will be achieved in the existing unit.
17 Interlinked Projects No 18 Whether separate application of interlinked
project has been submitted? Not Applicable
19 If yes, date of submission Not Applicable
Page 2
FORM I
20 If no, reason Not Applicable
21 Whether the proposal involves
approval/Clearance under the following acts: if yes, details of the same and their status to be given. (a)The Forest (Conservation) Act, 1980? (b)The Wildlife (Protection) Act, 1972? (c)The C.R.Z Notification, 1991?
No
22 Whether there is any government order/ Police relevant/ relating to the site?
Nil
23 Forest land involved (hectares) Nil 24 Whether there is any litigation pending
against the project and / or land in which the project is proposed to be set up? (a) Name of the Court (b) Case No. (c) Order/ directions of the Court, if any And its relevance with the proposed project
Nil
(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which
will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S. No. Information/Checklist confirmation Yes /
No
Details thereof with approximate quantities / rates, wherever possible) with source of
information data 1.1 Permanent or temporary change in
land use, land cover or topography including increase intensity of land use (with respect to local land use plan)
Yes The increase in LPG throughput will be achieved by, 1. Increasing the number of shifts of operation
from one to three and, 2. Installing 4 additional TLD bays Hence there will be minor change in the land use breakup of the project site. However, the proposed expansion will take place within the LPG Import/Export Terminal.
1.2 Clearance of existing land, vegetation and Buildings?
Yes Vacant land within the Terminal will be utilized for installing the additional TLD bay (4 nos.).
1.3 Creation of new land uses? No There will not be any creation of new land use as the proposed TLD bays will be installed within the Terminal.
Page 3
FORM I
1.4 Pre-construction investigations e.g.
Bore Houses, Soil testing? Yes Pre-construction investigation will be carried
out. 1.5 Construction works?
Yes Four additional TLD bays will be installed
within the Terminal. 1.6 Demolition works? No No demolition works will be involved. 1.7 Temporary sites used for construction
works or housing of construction workers?
No Construction workers will be hired locally.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations.
Yes Four additional TLD bays will be installed within the Terminal.
1.9 Underground works mining or tunneling?
No No underground works will be required.
1.10 Reclamation works? No No reclamation works required. 1.11 Dredging? No No need for dredging. 1.12 Off shore structures? No Not required 1.13 Production and manufacturing
processes? Yes Throughput capacity of LPG will be increased
by increasing the number of shifts of operation from one to three and addition of 4 TLD bays. However there will be no change in the storage and blending process that are in place at present.
1.14 Facilities for storage of goods or materials?
Yes Existing storage facilities for raw materials i.e. propane, butane & finished product i.e. LPG will be sufficient.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents?
Yes Existing sewage treatment plant is adequate to treat the sewage generated within the Terminal.
1.16 Facilities for long term housing of operational workers?
No Not required.
1.17 New road, rail or sea traffic during Construction or operation?
No Existing facilities are sufficient.
1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?
No Existing facilities are sufficient.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in Traffic movements?
No There is no need for closure or diversion of existing transport routes.
1.20 New or diverted transmission lines or pipelines?
No Not Applicable
Page 4
FORM I
1.21 Impoundment, damming, culverting,
realignment or other changes to the hydrology of watercourses or aquifers?
No No such issue is involved.
1.22 Stream crossings? No Not applicable. 1.23 Abstraction or transfers of water form
ground or surface waters? No There will be no withdrawal of ground water.
The existing water supply from Kattupalli Desalination Plant via CMWSSB shall be adequate.
1.24 Changes in water bodies or land surface affecting drainage or runoff?
No Not applicable.
1.25 Transport of personnel or materials for construction, operation or decommissioning?
Yes Movement of LPG Bullet Trucks will increase.
1.26 Long term dismantling or decommissioning or restoration works?
No No long term works involved in the proposed activity.
1.27 Ongoing activity during decommissioning which could have an impact on the environment?
No There will be no decommissioning works.
1.28 Influx of people to an area either temporarily or permanently?
No There will be no additional manpower required for the proposed expansion. There will only be an increase in the number of drivers entering/exiting the Terminal.
1.29 Introduction of alien species? No No such issue will be involved. 1.30 Loss of native species or genetic
diversity? No No such issue will be involved.
1.31 Any other actions? No Not envisaged.
Page 5
FORM I
2. Use of Natural resources for construction or operation of the Project (such as land,
water, materials or energy, especially any resources which are non-renewable or in short supply)
S. No. Information / checklist confirmation
Yes / No
Details there of (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha)
No Land required for installing the 4 TLD bays is available within the Terminal i.e. vacant land.
2.2 Water (expected source & competing users) Unit: KLD
Yes Water requirement is expected to increase by 37 KLD. The source water is from the Government Desalination Plant at Kattupalli via CMWSSB.
2.3 Minerals (MT) No Not Applicable. 2.4 Construction material - stone,
aggregates, and / soil (expected source - MT)
Yes Four additional TLD bays will be installed within the Terminal.
2.5 Forests and timber (Source - MT) No Nil
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), Energy (MW)
No Electricity : 3593 KVA (Existing) Source: Tamil Nadu Generation and
Distribution Corporation Limited (TANGEDCO)
Backup power supply 3×2000 KVA and 2×1010 KVA of DG sets are already available as backup power supply. No additional DG set is required for proposed expansion of the LPG blending plant.
2.7 Any other natural resources (use appropriate standard units)
No Not required.
3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S. No. Information/Checklist confirmation Yes / No
Details there of (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)
Yes Propane and Butane are received from Ennore Port and stored at Terminal. Description (existing Quantity
1. Storage Capacity (A) Refrigerated storage 1. SR – 01 for LPG (Propane)
15000 MT
Page 6
FORM I
2. SR – 02 for LPG (Butane) 15000 MT 3. SR – 03 for LPG (Propane)
7500 MT
4. SR – 04 for LPG (Butane) 7500 MT (B) Mounded storage 1. LPG – 3 Nos. 300 MT each The LPG throughput will increase by increasing the number of shifts of operation from one to three and by installing additional 4 nos. of TLD bays.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)
No No such issue will arise
3.3 Affect the welfare of people e.g. by changing living conditions?
Yes Positive impact is anticipated as availability of LPG as fuel for people will help in improving living conditions.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.
No Not applicable
3.5 Any other causes No Not applicable
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
S. No. Information / Checklist confirmation
Yes / No
Details there of (with approximate quantities/rates, wherever possible) with
source of information data 4.1 Spoil, overburden or mine wastes No Will not be generated.
4.2 Municipal waste (domestic and or commercial wastes)
No There will be no significant increase in municipal waste generation. Existing municipal waste management practices will be followed for additional quantity.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules)
Yes No increase in the hazardous waste generation is anticipated.
4.4 Other industrial process wastes No There will be no increase in the industrial waste generation.
4.5 Surplus product No There will be no generation of surplus products. 4.6 Sewage sludge or other sludge from
effluent treatment Yes Sludge from STP is used as manure on-site.
The same practice will continue for the expansion activity.
4.7 Construction or demolition wastes Yes Minor quantity of construction wastes will be generated that will be disposed off properly.
Page 7
FORM I
4.8 Redundant machinery or equipment No There will not be any redundant machinery or
equipment from the plant. 4.9 Contaminated soils or other materials No Not applicable. 4.10 Agricultural wastes No Not applicable. 4.11 Other solid wastes No No other solid wastes
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S. No.
Information / Checklist confirmation
Yes/ No
Details there of (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources
Yes Emissions from Diesel Generator set (5 nos.) can be expected during power failure. The emissions from mobile sources (bullet trucks) will increase due to the increase in throughput.
5.2 Emissions from production processes No The receipt, storage, blending & loading operation is carried out through pipelines and controlled by SCADA system. There are no emissions generated from production processes.
5.3 Emissions from materials handling storage or transport
Yes There will be no emissions from the production processes. However fugitive emissions from material i.e. LPG transport through bullet trucks will increase.
5.4 Emissions from construction activities including plant and equipment
Yes PM emissions from construction activities i.e. installation of 4 TLD bays will arise.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste.
No Safe disposal practices will ensure that no odours arise from handling of materials including construction materials, sewage and waste.
5.6 Emissions from incineration of waste No There will be no incineration of wastes at the plant.
5.7 Emissions from burning of waste in open air e.g. slash materials, construction debris.
No No such activities will be permitted.
5.8 Emissions from any other sources No Emissions from other sources are not expected to occur.
6. Generation of Noise and Vibration, and Emissions of Light and Heat
Page 8
FORM I
S. No. Information/Checklist confirmation Yes/ No
Details there of (with approximate quantities/rates, wherever possible) with source of information data with source of information data
6.1 From operation of equipment e.g., engines, ventilation plant, crushers
Yes Point source of noise generation will be DG set for which acoustic enclosures have been provided.
6.2 From industrial or similar processes No No major noise generating equipments are required in the operation of the Terminal.
6.3 From construction or demolition Yes Noise generated during construction activity will be restricted to the Terminal premises.
6.4 From blasting or piling No Not applicable.
6.5 From construction or operational traffic
Yes Due to increase in LPG throughput, there will be increase in the number of bullet trucks entering & exiting the Terminal. This source of noise is fugitive and is being controlled by existing avenue plantation & greenbelt around the Terminal. 6.6 From lighting or cooling systems No Noise generated from existing plant is well within limits prescribed by CPCB.
6.7 From any other sources No Nil
7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea
S. No. Information/Checklist confirmation
Yes / No
Details there of (with approximate quantities / rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials
Yes The safety features such as low-pressure alarm switch, gas detectors, Programmable Logic Control Unit (PLC) and suitable PPEs such as PVC suits, fire fighting facilities are being used to avoid hazardous events causing damage.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)
No Presently, the treated sewage is used for greenbelt development and same will be continued after expansion.
7.3 By deposition of pollutants emitted to air into the land and into water
No Gaseous pollutants from the DG sets are discharged through the stack of sufficient height (30m) as per CPCB guidelines.
7.4 From any other sources No No other polluting sources exist.
Page 9
FORM I
7.5 Is there a risk of long term build up
of pollutants in the environment from these sources?
No Adequate safety measures are already in place to prevent any loss / leak of raw materials & product.
8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No. Information/Checklist confirmation
Yes / No
Details there of (with approximate quantities/rates, wherever possible) with
source of information data 8.1 From explosions, spillages, fires
etc from storage, handling, use or production of hazardous substances
Yes Adequate safety features such as Gas Detectors, Flame Detectors, Heat Detectors, Smoke Detectors & Field Manual Call Points and suitable PPEs such as Fire Proximity suit, low temperature suit, PVC suits, gloves etc. are being used to enhance safety.
8.2 From any other causes No Nil
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloud burst etc)?
No The study area falls in Zone III according to the Indian Standard Seismic Zoning Map which is Moderately Stable zone. The Terminal has actively implemented Disaster Management Plan & Emergency Response Plan to deal with any natural disaster.
Page 10
FORM I
9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
(III) Environmental Sensitivity
S. No. Areas Name/ Identity
Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value.
None --
S. No.
Information/Checklist confirmation
Yes / No
Details there of (with approximate quantities/rates, wherever possible) with source of information data
9.1
Lead to development of supporting. Utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g. Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.)
Housing development
Extractive industry
Supply industry
Other
No
No
No
No
No
-
-
-
-
-
9.2 Lead to after-use of the site, which could have an impact on the environment.
No No major impacts are envisaged
9.3 Set a precedent for later developments
No Not envisaged
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects
No Not envisaged
Page 11
FORM I
2 Areas which are important or sensitive
for Ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests.
Ennore Mangrove Vegetation
Ennore Creek
4.4 km 3.5 km
3 Area used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration
None --
4 Inland, coastal, marine or underground waters
Buckingham Canal
8.7 km
5 State, National boundaries None Nil 6 Routes or facilities used by the public
for access to recreation or other tourist, pilgrim areas
None Nil
7 Defense installations None Nil 8 Densely populated or built-up area Athipattu
Pudunagar village
150m (S)
9 Area occupied by sensitive man-made land uses (Hospitals, schools, places of worship, community facilities)
Yes
10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism,
i l )
None None
11 Areas already subjected to pollution environmental damage. (those where existing legal environmental standards are exceeded)
None None
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, flooding, erosion, or extreme or adverse climatic conditions)
No The area under study falls in Zone III, according to the Indian Standard Seismic Zoning Map as of January 2012.
Page 12
FORM I
(IV) Proposed Terms of reference for EIA studies Terms of Reference (ToR) for Environmental Impact Assessment (EIA) studies in respect of isolated storage may include,
I. Executive summary of the project – prima facie idea of the objectives of the proposal, use of resources, justification, with compilation of EIA report, including EMP and the post-project monitoring plan in brief.
II. Project description 1. Justification for selecting the proposed expansion. 2. Details of proposed layout clearly demarcating various units within the plant. 3. Complete process flow diagram describing each of the unit processes and operations,
along with material and energy inputs & outputs. 4. Details on requirement of raw materials, its source and storage at the plant. 5. Details of inventory of hazardous materials stored at the plant. 6. Quantity of fuel required its source and transportation, a confirmed fuel linkage/ copy
of the MoU. 7. Source of water and its availability. Proof regarding availability of requisite quantity of
water from the competent authority. 8. Details on water balance including quantity of effluent generated, recycled & reused. 9. Details of effluent treatment plant, inlet and treated water quality with specific
efficiency of each treatment unit in reduction in respect of all concerned/regulated environmental parameters.
10. Explore the possibility of cooling towers installation. Details regarding the same. 11. Details of proposed source-specific pollution control schemes and equipments to meet
the national standards. 12. Details of the proposed methods of water conservation and recharging. 13. Management plan for solid/hazardous waste generation, storage, utilization and
disposal. 14. Details regarding infrastructure facilities such as sanitation, fuel storage, restroom, etc.
to the workers during construction and operation phase. 15. Details of safety measures taken at the plant to minimize risk at the plant. 16. Details of Firefighting Facilities available at the plant. 17. Any litigation pending against the project and /or any direction /order passed by any
Court of Law related to the environmental pollution and impacts in the last two years, if so, details thereof.
III. Description of the Environment 18. The study area shall be up to a distance of 10 km from the boundary of project area to
study physical, biological and socioeconomic environment, The study area may be up to a distance of 5 km for sampling and analysis of ambient air, water, soil and noise and ecological studies.
19. Location of the project site and nearest habitats with distances from the project site to be demarcated on a map (1: 50000 scale).
20. Land Use based on satellite imagery including location specific sensitivities such as national parks / wildlife sanctuary, villages, industries, etc. for the study area.
21. Demography details of all the villages falling within the study area. 22. Topography details of the project area.
Page 13
FORM I
23. The baseline data to be collected from the study area w.r.t. different components of
environment viz. air, noise, water, land, and biology and socio-economic. 24. Geological features and geo-hydrological status of the study area. 25. Surface water quality of nearby water sources and other surface drains. 26. Details on ground water quality as per IS : 10500 : 2012 for reverent parameters. 27. Details on ambient air quality as per National Ambient Air Quality Standards. 28. Stack and fugitive emissions for SMP, PM10, PM2.5, SO2, NOx, HC, VOCs, etc. 29. The air quality contours may be plotted on a location map showing the location of
project site, habitation nearby, sensitive receptors, if any and wind roses. 30. Details on noise levels at sensitive/commercial receptors. 31. Site-specific micro-meteorological data including mixing height. The wind roses will
also be shown on the map. 32. One season site-specific data excluding monsoon season. 33. Ecological status (terrestrial and aquatic) of the study area such as habitat type and
quality, species, diversity, rarity, fragmentation, ecological linkage, age, abundance, etc.
IV. Anticipated Environmental Impacts and Mitigation Measures 34. Impact on drainage of the area and the surroundings. 35. Impact of the project on the AAQ of the area. Details of the model used and the input
data used for modeling. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any.
36. Details of rainwater harvesting and its proposed usage in the plant. 37. Details regarding infrastructure facilities such as sanitation, fuel, restroom, etc., to be
provided to the workers during construction as well as to the casual workers including truck drivers during the operational phase.
38. Details of flora and fauna. Conservation plan in case of any scheduled fauna. 39. Proposed measures for occupational safety and health of the workers. 40. Proposed odour control measures. 41. Action plan for the greenbelt development – species, width of plantations, planning
schedule etc. in accordance to CPCB published guidelines. 42. In case of likely impact from the proposed project on the surrounding reserve forests,
Plan for the conservation of wild fauna in consultation with the State Forest Department.
V. Analysis of alternative resources and technologies 43. Details of alternative sources of energy such as photovoltaic cells use in the plant for
various applications. 44. Details on improved technologies.
VI. Environmental Monitoring Program
45. Monitoring programme for pollution control at source. 46. Monitoring pollutants at receiving environment for the appropriate notified parameters
– air quality, groundwater, surface water, etc. during operational phase of the project. 47. Specific programme to monitor safety and health protection of workers. 48. Appropriate monitoring network has to be designed and proposed, to assess the possible
residual impacts on various environmental parameters. 49. Details of in-house monitoring capabilities and the recognized agencies if proposed for
conducting monitoring.
Page 14
FORM I
52. Points identified in the public hearing and commitment of the project proponent to the same. Detailed action plan addressing the issues raised, and the details of necessary allocation of funds.
VIII. Environmental Management Plan 53. Administrative and technical organizational structure to ensure proposed post-project
monitoring programme for approved mitigation measures. 54. EMP devised to mitigate the adverse impacts of the project will be provided along with
item-wise cost of its implementation (capital and recurring costs). 55. Allocation of resources and responsibilities for plan implementation. 56. Details of the emergency preparedness plan and on-site and off-site disaster
management plan.
"I hereby given undertaking that data and information given in the application and enclosures are true to the best of the knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost".
Date : 15.10.2015
Place : Chennai
ABC Tcchno L abs
Signature of the applicant
With Name and Full Address
(Project Proponent I Authorized Signatory)
S.SEKAR DGM (Plant)
INDIANOIL PETRONAS PVT. LTD. 143, Athipa!tu Village, NCTPS Main Road,
Chennai - 600 120.
Page 16
PRE-FEASIBILITY REPORT
TABLE OF CONTENTS
1 INTRODUCTION ................................................................................................................. 1
1.1 NEED FOR THE PROJECT................................................................................................ 1
1.2 BACKGROUND OF THE PROJECT ................................................................................... 1
2 DESCRIPTION OF PROJECT SITE ................................................................................ 3
2.1 LOCATION OF THE PROJECT ......................................................................................... 3
2.2 CONNECTIVITY .............................................................................................................. 5
2.3 SITE ANALYSIS .............................................................................................................. 6
2.4 SITE SUITABILITY/ALTERNATE SITES .......................................................................... 9
2.5 CLIMATE ...................................................................................................................... 10
2.6 TEMPERATURE ............................................................................................................ 10
2.7 RAINFALL .................................................................................................................... 10
2.8 RELATIVE HUMIDITY .................................................................................................. 10
2.9 GEOLOGY .................................................................................................................... 10
2.10 SOIL ............................................................................................................................. 10
2.11 INFRASTRUCTURE ........................................................................................................ 10
2.11.1 TRANSPORT ................................................................................................................. 10
2.11.2 INDUSTRIES .................................................................................................................. 10
3 PROJECT DESCRIPTION ............................................................................................... 12
3.1 OPERATING PROCEDURE ............................................................................................ 12
3.1.1 OCEAN TANKER UNLOADING ..................................................................................... 12
3.1.2 STORAGE OF PRODUCT IN REFRIGERATED STATE .................................................... 14
3.1.3 TERMINAL OPERATION INCLUDING LOADING ........................................................... 14
3.2 MAGNITUDE OF OPERATION ....................................................................................... 14
3.3 RAW MATERIALS REQUIREMENT ............................................................................... 15
PRE-FEASIBILITY REPORT
3.4 MANUFACTURING PROCESS ........................................................................................ 16
3.4.1 PROPANE/BUTANE PUMPING ...................................................................................... 16
3.4.2 PROPANE/BUTANE HEATING TRAIN ........................................................................... 16
3.4.3 STATIC BLENDER & BLENDING CONTROL ................................................................. 17
3.4.4 PRODUCT TRANSFER TO LOADING GANTRY FOR LOADING ON ROAD TANKER ....... 17
3.4.5 PRODUCT TRANSFER TO INDANE BOTTLING PLANT .................................................. 18
4 EXISTING INFRASTRUCTURE AVAILABLE AT THE PLANT ............................. 19
4.1 DG SETS ....................................................................................................................... 21
4.2 BOILER ......................................................................................................................... 21
4.3 COOLING TOWER ......................................................................................................... 22
4.4 POLLUTION PREVENTION MEASURES ......................................................................... 24
4.4.1 AIR POLLUTION CONTROL MEASURES ....................................................................... 24
4.4.2 WATER POLLUTION CONTROL MEASURES ................................................................. 25
4.4.2.1 DOMESTIC SEWAGE ..................................................................................................... 25
4.4.2.2 EFFLUENT GENERATION, TREATMENT & DISPOSAL ................................................. 28
4.4.3 SOLID & INDUSTRIAL WASTE POLLUTION CONTROL MEASURES ............................. 28
4.4.3.1 SOLID WASTE .............................................................................................................. 28
4.4.3.2 INDUSTRIAL WASTE .................................................................................................... 29
4.5 FIRE FIGHTING SYSTEM ................................................................................................. 27
4.5.1 FIRE HYDRANT SYSTEM .............................................................................................. 27
4.5.2 FIRE EXTINGUISHERS .................................................................................................. 27
4.5.3 FIRE ALARM SYSTEM .................................................................................................. 30
4.6 RAINWATER DRAINAGE SYSTEM................................................................................. 28
4.6.1 RAINWATER HARVESTING SYSTEM ............................................................................. 28
4.6.2 STORM WATER MANAGEMENT SYSTEM ....................................................................... 30
4.7 PERSONAL PROTECTIVE EQUIPMENTS ....................................................................... 32
PRE-FEASIBILITY REPORT
4.8 GREEN BELT ................................................................................................................ 32
5 INFRASTRUCTURE FOR THE PROPOSED PROJECT ............................................ 32
5.1 INDUSTRIAL/PROCESSING AREA .................................................................................. 33
5.2 POWER REQUIREMENT ................................................................................................. 37
5.3 MAN POWER REQUIREMENT ........................................................................................ 37
5.4 WATER REQUIREMENT ................................................................................................ 37
6 PROJECT SCHEDULE & COST ESTIMATES ............................................................ 38
6.1 TIME SCHEDULE FOR THE PROJECT IMPLEMENTATION ............................................... 38
6.2 ESTIMATED PROJECT COST .......................................................................................... 38
PRE-FEASIBILITY REPORT
LIST OF TABLES
TABLE 2.1 ENVIRONMENTAL SETTINGS OF THE PROJECT SITE ..................................................... 10
TABLE 2.2 LIST OF INDUSTRIES IN THIRUVALLUR DISTRICT ......................................................... 12
TABLE 2.3 LIST OF INDUSTRIES IN VICINITY OF IPPL ................................................................... 13
TABLE 3.1 PRODUCTION CAPACITY (BEFORE AND AFTER EXPANSION) ......................................... 16
TABLE 3.2 RAW MATERIAL REQUIREMENT ..................................................................................... 17
TABLE 3.3 LIST OF HAZARDOUS MATERIALS USED IN THE FACTORY PREMISES ............................ 17
TABLE 3.4 MASS BALANCE ............................................................................................................... 20
TABLE 4.1 DETAILS ON D.G SET...................................................................................................... 21
TABLE 4.2 TECHNICAL DETAILS OF BOILER ................................................................................... 21
TABLE 4.3 COOLING TOWER SPECIFICATIONS .............................................................................. 23
TABLE 4.4 DETAILS ON APC MEASURES ........................................................................................ 24
TABLE 4.5 DETAILS ON EXISTING SEWAGE TREATMENT UNITS & CAPACITY ............................. 27
TABLE 4.6 SOLID WASTE GENERATION & DISPOSAL METHODS ................................................... 28
TABLE 4.7 INDUSTRIAL WASTE GENERATION & DISPOSAL METHODS ......................................... 29
TABLE 4.8 LIST OF TREE SAPLINGS ................................................................................................. 34
TABLE 5.1 LAND-USE BREAK UP ..................................................................................................... 24
PRE-FEASIBILITY REPORT
TABLE OF FIGURES
FIGURE 2.1 GOOGLE IMAGE SHOWING THE PROJECT SITE ............................................................... 3
FIGURE 2.2 LOCATION MAP OF THE PROJECT SITE ........................................................................... 4
FIGURE 2.3 ROAD NETWORK MAP AROUND PROJECT SITE ............................................................... 6
FIGURE 2.4 TOPO MAP SHOWING THE SURROUNDING FEATURES OF THE PROJECT SITE COVERING
10 KM RADIUS ............................................................................................................................ 8
FIGURE 2.5 LAND USE MAP OF THE PROJECT SITE COVERING 10 KM RADIUS ................................ 9
FIGURE 3.1 PROCESS FLOW DIAGRAM ............................................................................................ 20
FIGURE 4.1 SCHEMATIC DIAGRAM OF SEWAGE TREATMENT PLANT ............................................ 26
FIGURE 4.2 SCHEME OF RAINWATER HARVESTING POND .............................................................. 31
FIGURE 4.3 DRAINAGE LAYOUT SCHEME ........................................................................................ 33
FIGURE 5.1 SITE LAYOUT SHOWING PLANT AND UTILITIES ........................................................... 36
FIGURE 5.2 WATER BALANCE DIAGRAM FOR EXISTING PROCESS ................................................. 38
FIGURE 5.3 WATER BALANCE DIAGRAM FOR PROPOSED PROCESS ............................................... 39
PRE-FEASIBILITY REPORT
1
PRE-FEASIBILITY REPORT
1 INTRODUCTION
M/s Indian Oil Petronas Private Limited (IPPL) is a joint venture company, promoted by two
FORTUNE Global 500 oil majors, one of them being Indian Oil Corporation Limited (IOCL)
and the other being Petroliam Nasional Berhad (PETRONAS), Malaysia, the national oil
company of Malaysia. On 2nd August, 2012 a LPG Import/Export Terminal was
commissioned at Ennore near Chennai to cater to the Southern part of India.
Currently, IPPL has proposed to increase its LPG throughput capacity by increasing the
number of shifts from one to three and by installing four additional truck loading decanting
(TLD) bays. The proposed expansion will take place at their Terminal located at Athipattu
Village, Ponneri Taluk, Thiruvallur District. The LPG throughput will increase from 5,76,000
TPA to 23,04,000 TPA.
The expansion requires Environmental Clearance from Ministry of Environment, Forests &
Climate Change under Category ‘A’ in the Schedule 6 (b) “Isolated storage & handling of
hazardous chemicals” of EIA Notification 2006 to commence the production. Letter issued by
SEIAA is enclosed as Annexure for reference. 1.1 NEED FOR THE PROJECT
India is the fourth largest consumer of LPG (15 million tonnes per year) in the world
following USA, China and Japan. With home deliveries of 3 million LP Gas cylinders per
day (900 Million/year), India is also the third largest domestic consumer of LPG. Since a gap
exists between demands and supply via indigenous production, nearly 22% of the LPG
demand in India is satisfied through import.
With a combined bottling capacity of 0.4 million TPA, Tamil Nadu was facing a LPG deficit
of 0.8 million TPA and this shortfall was met by transporting LPG from Mangalore by road.
IPPL has recently commenced operations at Ennore to meet the LPG requirements of Tamil
Nadu, Karnataka and Andhra Pradesh. The IPPL facility at Ennore was set up with the aim of
increasing LPG availability and eliminating transportation costs by bullet trucks.
1.2 BACKGROUND OF THE PROJECT
M/s Indian Oil Petronas Pvt. Ltd. (IPPL) has set up the Import/Export terminal at Ennore for
undertaking the following activities:
PRE-FEASIBILITY REPORT
2
Import of Propane/Butane in refrigerated state in jetty through ship tankers and unloading
the same at the jetty.
Transfer of product through cross country pipeline and storing in dedicated refrigerated
tanks.
Transfer of product from tanks through pumps to heating train and then to online blending
system for production of Domestic LPG and Auto LPG.
Mercaptan dosing of the LPG and transfer to loading gantry for loading onto road tankers
for dispatch to destination.
IPPL have obtained Environmental Clearance from MoEFCC for the existing LPG
throughput capacity of 6,00,000 MTPA vide F.No. 11-76/2011-IA.III enclosed as Annexure
I. The Compliance Certificate for the existing EC condition from MoEFCC is enclosed as
Annexure II.
For existing activity, the unit has obtained Consent Orders from Tamil Nadu Pollution
Control board (TNPCB) under the Water (Prevention & Control of Pollution) Act, 1974
amended in 1988 and the Air (Prevention & Control of Pollution) Act, 1981 amended in
1987. The Consent to Establish has been enclosed as Annexure III and the Consent to
Operate has been enclosed as Annexure IV.
IPPL have obtained CRZ clearance for cross country pipeline from Ennore to the project site
vide F.No. 11-76/2011-IA.III enclosed as Annexure V.
PRE-FEASIBILITY REPORT
3
2 DESCRIPTION OF PROJECT SITE
2.1 LOCATION OF THE PROJECT
The proposed expansion will be carried out within the existing factory premises of M/s.
IndianOil Petronas Pvt. Ltd. located at Survey No. 94pt, 95pt, 109, 110, 202pt, 204, 207 to
216, 219-225, Athipattu Village, Ponneri Taluk, Thiruvallur District – 600 120. The Google
map showing the project site is given in Figure 2.1. The general location of the project area
is represented in Figure 2.2.
FIGURE 2.1 – GOOGLE IMAGE SHOWING THE PROJECT SITE
PRE-FEASIBILITY REPORT
4
FIGURE 2.2- LOCATION MAP OF THE PROJECT SITE
PRE-FEASIBILITY REPORT
5
2.2 CONNECTIVITY
The project site is well connected by road and rail network. The project site is located
adjacent to NCTPS road which connects to SH 56 (Thiruvotiyur-Ponneri-Panchetty road).
Athipattu Railway Station is located at the distance of about 340m on southwestern direction.
This railway station connects with important cities of Tamil Nadu like Chennai, Trichy, etc
through southern railway broad gauge lines. The Chennai International Airport is located at
the distance of about 30 km on Northwestern direction. Map showing the road network
around the proposed project site covering 10 km radius is given in Figure 2.3.
FIGURE 2.3 ROAD NETWORK MAP AROUND PROJECT SITE
Location of Project Site
PRE-FEASIBILITY REPORT
6
2.3 SITE ANALYSIS
The total plot area of the Terminal is around 110 acres. This area is adequate for the proposed
throughput increase. A copy of the land ownership document of M/s. IndianOil Petronas
Private Limited is enclosed in Annexure VI and the land use map of Athipattu Village is
shown in Annexure VI A.
Topographically, the area is of plain terrain. Maps showing the topographical features around
the proposed project site covering 10 km radius are given in Figure 2.4. The land use
classification of the project site is Industrial and the project site (10 km radius) is surrounded
by un-irrigated land followed by irrigated land, area not available for cultivation and
settlements. The Land Use map of the project site covering 10 km radius is given in Figure
2.5.
PRE-FEASIBILITY REPORT
7
FIGURE 2.4 – TOPO MAP SHOWING THE SURROUNDING FEATURES OF THE PROJECT SITE COVERING 10 KM RADIUS
PRE-FEASIBILITY REPORT
8
FIGURE 2.5 – LANDUSE MAP SHOWING THE SURROUNDING FEATURES OF THE PROJECT SITE COVERING 10 KM RADIUS
PRE-FEASIBILITY REPORT
9
2.4 SITE SUITABILITY/ALTERNATE SITES
IPPL has proposed to increase its LPG production capacity without changing any of the
existing operating settings. Hence no alternative sites are considered. The site has the
following additional advantages:
The necessary infrastructure in terms of land, water and personnel is readily available
No addition of any storage, equipment and machineries.
There will be no significant adverse impact on the environment due to the project; rather
many beneficial impacts are estimated.
There is no adverse sitting factor such as reclassification of land use and pattern,
displacement etc.
Details of environmental settings of the project site is also given in the Table 2.1.
Table 2.1 - Environmental Settings of the Project Site
S. No. Particulars Details
1 Latitude 13°15'18"N
2 Longitude 80°18'8"E
3 Site Elevation above MSL 3 m
4 Topography Plain
5 Present land use at the site Special & Hazardous Industrial Area
6 Nearest highway National Highway 5 – 14.0 km (W)
7 Nearest railway station Athipattu Railway Station – 0.5 km (SW)
8 Nearest airport Chennai International Airport– 42 km (SW)
9 Nearest town / city Athipattu Pudunagar – 150m (S)
10 Water body Ennore Creek - 3.5 km (SE)
Buckingham Canal – 8.7 km (S)
Bay of Bengal – 4.2 km (E)
Karanodai river – 13 km (W)
11 Nearest Port Ennore - 3 km (NE)
Chennai – 16.4 (S)
12 Hills / valleys Nil in 10 Km radius
13 Archaeologically important places Chennai Fort – 20 km (S)
14 National parks / Wildlife
Sanctuaries/Eco sensitive zones as
per Wild Life Protection Act, 1972
Nil in 15 Km radius
15 Reserved / Protected Forests Nil in 10 Km radius
16 Seismicity Zone III, according to the Indian Standard
Seismic Zoning Map as of January 2012.
17 Defense Installations Nil in 10 Km radius
PRE-FEASIBILITY REPORT
10
2.5 CLIMATE
The district enjoys a tropical climate. The period from April to June is generally hot and dry.
The weather is pleasant during the period from November to January.
2.6 TEMPERATURE
The maximum temperature of the district is 37.9°C and the minimum temperature is 18.5°C.
Like other parts of Tamil Nadu, hot climate prevails during the month of April - May and
humid climate during the rest of the year except December - February when it is slightly cold.
2.7 RAINFALL
The district receives rain under the influence of both southwest and northeast monsoons.
Most of the precipitation occurs in the form of cyclonic storms caused due to the depressions
in Bay of Bengal chiefly during Northeast monsoon period. The southwest monsoon rainfall
is highly erratic and summer rains are negligible. The average rainfall of the district is 1104.4
mm, of which the Northeast monsoon contributes to the tune of 690 mm.
2.8 RELATIVE HUMIDITY
The relative humidity varies between 65 and 85% in the mornings while in the afternoon it
varies between 40 and 70%. Usually mornings are more humid than afternoons.
2.9 GEOLOGY
Geologically, the district is underlain by formations ranging in age from Archaean to Recent.
Crystalline rocks comprising Charnockites, gneisses and associated rocks are restricted to the
western part of the district. The central and eastern parts are underlain by a thick pile of
Gondwana shales, clays and sandstones below the recent alluvial deposits. Geophysical
investigations in the district have established the presence of multi-layered substratum,
indicating fracture zones in the crystalline formations and multiple granular zones in porous
formations.
2.10 SOIL
Soils in the district have been classified into i) Red soil ii) Black soil iii) Alluvial soil and iv)
Colluvial soil. Red soil of red sandy/clay loam type and Ferruginous red soils are also seen at
places. Black soils are deep to very deep and generally occur in the depressions. Alluvial
PRE-FEASIBILITY REPORT
11
soils occur along the river courses and eastern part of the coastal areas. Sandy coastal
alluvium (arenaceous soil) are seen all along the sea coast as a narrow belt. Black soil is the
predominant soil found in Thiruvallur and the nearby areas.
2.11 INFRASTRUCTURE
2.11.1 TRANSPORT
The project site is located adjacent to NCTPS road which is connecting the National Highway
5 (Chennai to Kolkata) at 14 km distance. Athipattu Railway Station is located at the distance
of about 1.2 km on Northwestern direction. This railway station connects with important
cities of Tamil Nadu like Chennai, Trichy, etc through southern railway broad gauge lines.
2.11.2 INDUSTRIES
The site is located near Ennore Port surrounded by Ambattur Industrial Estate and
Sriperumbudur Industrial Estate. Some of the major industries located in the Thiruvallur
District are listed below.
Table 2.2 – List of industries in Thiruvallur District
INDUSTRIAL ESTATES TYPE OF INDUSTRIES
GOVERNMENT OWNED
Ambattur Industrial Estate, Ambattur Manufacturing engineering and
machining components and other
products
Electrical Industrial Estate, Kakalur Manufacturing lamps, motors, PCBs,
connector and other products
SIDCO Industrial Estate, Chennai Manufacturing rubber products, metal
sheets, and other products
Industrial Estate, Madhavaram
SIDCO Industrial Estate, Kakalur Manufacturing and Forging industries
Petrochemical Industrial Estate, Vichoor Petroleum based products
SIDCO Industrial Estate, R.K. Pet Textile products
SIDCO Industrial Estate, Gummidipoondi Manufacturing automobile components
Industrial Estate, Mugappair Manufacturing electrical equipments
PRIVATELY OWNED
G.K. Industrial Estate, Porur Forging and casting industries
M.M.Industrial Estate, Alapakkam
Moccaram Industries, Velappan Chavadi
Nagappa Industrial Estate, Puzhal Wood industries
Ekambara Naicker Industrial Estate,
Alapakkam
Manufacturing rubber products
Some industries located in the vicinity of IPPL are shown in the following table,
PRE-FEASIBILITY REPORT
12
Table 2.3 - List of industries in vicinity of IPPL
Indian Organic Chemicals Ltd
Sri Ram Fibers Ltd
Madras Fertilizers Ltd.
Kothari Chemicals Ltd.
Tamil Nadu Petroporducts Ltd.
Ennore Thermal Power Station Power Generation
Ashok Leyland Ltd
Ennore Foundries Ltd
EID Parry (I) Ltd
Manali Petrochemicals
TPL Petro Chemicals
Jagadambal Carbonic Ltd.
South India Carbonic Ltd.
Madras Rubber Factory
Chennai Petroleum Corporation
Balmer Lawrie
IOCL Bottling Plant LPG Bottling
IOTL Bulk Terminal LPG Storage
3 PROJECT DESCRIPTION
3.1 OPERATING PROCEDURE
The operation of the terminal is as follows,
Ocean tanker unloading
Storage of product in refrigerated state
Terminal operation including loading
3.1.1 OCEAN TANKER UNLOADING
Propane/Butane will be received in parcels of 13500 MT to 26000 MT at the Jetty of Ennore
Port and will be pumped by ship tanker’s pumps @ 1000MT/hr through 2 nos. marine
unloading arms and will be transferred through 2 nos. cross country pipelines each having
total length of approx. 12.5 KM.
Propane/Butane will be stored in the refrigerated storage tanks which will have a net filling
capacity of 15000 MT of Butane and 15000 MT Propane.
The tanks operating pressures will be slightly above atmospheric pressure (1500 mm WCg).
Temperatures of (-)5oC and (-43)oC will be maintained in tanks for Butane and Propane
respectively. During unloading operation of the ship into the storage tanks, the flash vapour
displaced from storage tanks, from the heat coming from unloading pipes (both during pre-
cooling and ship unloading operation) enters into a re-liquefaction unit comprising of the
PRE-FEASIBILITY REPORT
13
Flash Gas Compressors, Condenser, Receiver and mounded bullets etc. Re-liquefied
Propane/Butane is stored in the mounded bullets.
Both the unloading lines run parallel throughout the entire length from jetty to storage
terminal.
The critical parameters involved in operation of this terminal needs to be studied in details
considering the following:
Product is received in refrigerated state.
Cross country pipeline meant for product transfer from jetty to terminal is close to ambient
temperature.
Product shall be stored in refrigerated state.
Product shall be heated to 15oC prior to blending, mercaptan dosing and transfer to loading
stations.
The metal temperature inside the Propane/Butane feed-line increases proportional to the time
available between two ship unloading operations, due to heat ingress from the environment.
Heat ingress depends on the ambient temperature and the thermal conductivity of the
insulation. Pre-cooling of the two cross-country lines carrying Propane/Butane (also called
Propane/Butane feed-lines) is primarily necessary to prevent metal stress due to contact of
cold Propane/Butane delivered by the ship on the warm Propane/Butane feed lines.
The time required for pre-cooling is a function of the initial temperature inside the
Propane/Butane feed-lines and the ambient temperature. The state of the Propane/Butane in
this line depends on the degree of heat exchanged in the pre-cooling operation.
The pre-cooling operation is one of the requirements prior to the ship unloading operation.
The start of the ship unloading operation is ensured by the necessary checkpoints at the
source and the destination of the Propane/Butane feed-line. In this case, the source is the jetty
and the destination is the Propane/Butane storage tanks.
Cold Propane/Butane delivered by the ship is pumped by the ship’s pump from the jetty to
the Propane/Butane storage tank. The vapour generated, principally due to this unloading
operation, is drawn into the flash compressors located inside the battery limit wherein it is
compressed, liquefied and stored in Propane/Butane Receiver and then pumped to mounded
bullets as well as to refrigerated tanks in case of emergency resulting out of non-evacuation
from mounded bullets.
PRE-FEASIBILITY REPORT
14
3.1.2 STORAGE OF PRODUCT IN REFRIGERATED STATE
The function of these tanks is to store butane or propane. Both these tanks are identical in all
respect and Propane/Butane can be stored in any of these tanks. But normally SR-01-01 will
be used for Butane and Butane rich mixture storage and SR-01-02 will be used for Propane
and Propane rich mixture storage. The capacity of each tank is 15000 MT. These tanks will
receive propane or butane from jetty. It is pumped by ship’s pump at a rate of 1000 T/hr,
through two nos. of marine unloading arm and transferred to storage tanks via 2 nos. of 18”
pipelines each having total length of approx. 12.5 km.
These tanks are vertical flat bottom, double wall, double integrity refrigerated tanks. The
tanks are normally operated at 500-1000 mmwc. Both the tanks are designed for propane
storage case, which is more stringent.
The Propane/Butane storage tanks (SR-01-1/SR-01-02) is operated at about 500-1000 mmwc
or just above atmospheric pressure. The tank is a double integrity cup-in tank construction
with a domed roof for the outer tank. Each tank shall have effective storage capacity of 15000
MT excluding dead level and vapours space. Since, both the inner and outer tanks are
designed for the same conditions, in case of failure of the inner tank, the outer tank acts as a
perfect secondary containment chamber, confining the inner tank contents in the outer tank.
3.1.3 TERMINAL OPERATION INCLUDING LOADING
The operation of terminal can be classified as follows:
Propane/Butane/LPG pumping
Propane/Butane/LPG heating
Static blender, blending control and mercaptan dosing
Product transfer to loading gantry for loading in road tanker
Sick tanker unloading
Product transfer to Indane bottling plant.
3.2 MAGNITUDE OF OPERATION
The proposed project is the increase in LPG production capacity within the existing facility
by tripling the number of shifts of operation and installing 4 additional TLD bays to achieve
the final LPG throughput of 23,04,000MTPA. The details of proposed and existing operation
are given in Table 3.1.
PRE-FEASIBILITY REPORT
15
Table 3.1– Production capacity (Before and After expansion)
S. No. Name of the products
Capacity of Operation (MTPA)
Existing Proposed
Additional After Expansion
1. LPG 5,76,000 17,28,000 23,04,000
* The existing capacity is taken from Consent Order.
3.3 RAW MATERIALS REQUIREMENT
The raw materials required for the proposed expansion is given in Table 3.2.
TABLE 3.2 - Raw Material Requirement
TABLE 3.3 – List of hazardous materials used in the factory premises
S. No Name of
the
material
Physical
state
Unit of storage &
Capacity
No. of
units
Total storage
capacity
(MT)
Material
storage area
1 Propane Liquid SR-01 1 15000 Refrigerated
Storage
2. Butane Liquid SR-02 1 15000 Refrigerated
Storage
3. Propane Liquid SR-03 1 7500 Refrigerated
Storage
4. Butane Liquid SR-04 1 7500 Refrigerated
Storage
5. LPG Liquid Mounded Storage
(300 MT)
3 900 Mounded
Storage
S. No. Name of the
raw material
Quantity (TPA)
Existing Proposed
Additional
After Expansion
1. Propane 2,88,000 8,64,000 11,52,000
2. Butane 2,88,000 8,64,000 11,52,000
Total 5,76,000 1,728,000 23,04,000
PRE-FEASIBILITY REPORT
16
3.4 MANUFACTURING PROCESS
LPG production at IPPL consists of the following stages,
The products (Butane & Propane) are received in refrigerated state.
Cross country pipeline meant for product transfer from jetty to terminal is close to
ambient temperature.
Product shall be stored in refrigerated state.
Product shall be heated to 15oC prior to blending, mercaptan dosing and transfer to
loading stations.
3.4.1 PROPANE/BUTANE PUMPING
Each tank is provided with three pumps of capacity 220 m3/hr each. These pumps are
submersible, retractable and centrifugal pumps.
The pumps are provided for following functions:
Transfer of Propane/Butane to equipment house for heating and then to blending plant for
production of LPG followed by mercaptan dosing.
Pre-cooling (primary) of the cross country pipelines from jetty to the storage tanks.
Each tank is provided with automatic flow control valve meant for minimum flow return
and designated flow return to facilitate production of LPG of different ratio of Propane &
Butane.
Each pump column is provided with a provision both at the bottom and top with isolation
valves at top portion. This is meant for startup nitrogen purge operation.
3.4.2 PROPANE/BUTANE HEATING TRAIN
Since propane and butane have different boiling points they are stored in dedicated tanks at
different temperatures. Propane and butane are heated in separate heating trains to 15oC in
two steps.
Pre-heating of refrigerated propane liquid and butane liquid is done by condensing hot
vapours at 37oC to avoid freezing problems when direct heating with steam.
The propane used for heating propane/butane is vaporized in a kettle type propane vaporizers
by condensing steam. The steam condensate is used to heat the propane and butane to 15oC in
the exchangers. The propane vaporizers heat the propane to 37oC by LP steam at 1.0 Kg/cm2.
PRE-FEASIBILITY REPORT
17
The condensate coming from the shell side of heat exchanger are collected in water
condensate receiver and transferred through pump to condensate polishing unit.
3.4.3 STATIC BLENDER & BLENDING CONTROL
After heating propane and butane to 15oC they are volumetrically mixed in static blenders at
a certain ratio (50% propane, 50% butane & 20 ppm Ethyl Mercaptan/Ton LPG) to produced
LPG. The ratio is determined by a processor and controlled by flow measurement in the
propane and butane discharge lines on downstream of the heating train. The presetting of the
flow rate is governed by the temperature in the tanks which are indications for the
composition. The vapour pressure of the mixture is supervised by continuous measurement
downstream the static mixture with the help of online vapour pressure analyzer.
If the vapour pressure of the mixture exceeds the desired one, the flow ratio of Propane &
Butane is corrected by blending control system and off specification product is returned back
to storage tanks.
The blended product is thereafter odorized by injecting Ethyl Mercaptan at a rate of 0.45 Kg
per 37.5 M3 of liquid LPG.
3.4.4 PRODUCT TRANSFER TO LOADING GANTRY FOR LOADING ON ROAD
TANKER
Pure propane, pure butane and blended LPG is filled into road tankers via loading arms.
There are two nos. filling gantries, total of 16 nos. (including 4 additional TLDs proposed)
loading points including Propane/Butane/Auto & Domestic LPG loading provision at
dedicated loading points. Sick tanker unloading facilities at one point in each gantry is also
provided.
Through integration with various sub-systems, which includes process, utility & safety, an
efficient automated control is achieved.
Normal loading sequence will be as follows:
First truck will enter the entry gate then it will be weighted and given receipt for the
related information. Afterwards the truck will enter bay area where it will fill the
specified weight of LPG as per loading rack computer. The filled truck will be sent to exit
gate where all commercial formalities will be carried out.
PRE-FEASIBILITY REPORT
18
After getting information from loading rack computer field operator can now drain the
remaining LPG from pipeline into the drain collecting lines. Truck liquid arm can now be
removed from the truck.
Flow metering system for LPG loading to road tanker consist of strainer, vapour
eliminator, mass flow meter, set/stop control valve, batch controller, excess flow check
valve, card reader and vehicle grounding.
3.4.5 PRODUCT TRANSFER TO INDANE BOTTLING PLANT
The blended LPG is also transferred to adjacent Indane bottling plant through pipeline.
Through integration with various sub-systems, which includes process, utility & safety, an
efficient automated control is achieved.
Flow metering system for LPG transfer to bottling plant consist of mass flow meter with
temperature and density correction, excess flow check valve and automatic shut down/remote
operated valve.
The process flow diagram is shown in Figure 3.1.
PRE-FEASIBILITY REPORT
19
FIGURE 3.1 – PROCESS FLOW DIAGRAM
TABLE 3.4 – Mass balance for complete loading / unloading operation
Number
of bays
(A)
Filling
capacity
(B)
Number of hours
of operation per
day (C)
Average production
per day
(D) = (A) x (B) x (C)
Number of
days working
per year (E)
Average
production /year
(F) = (D) x (E)
12
(existing)
20 T/hr 8 1920 TPD 300 5,76,000 MTPA
16 (final) 20 T/hr 24 7680 TPD 300 23,04,000 MTPA
4 EXISTING INFRASTRUCTURE AVAILABLE AT THE PLANT
4.1 DG SETS
As back-up power 5 Nos. of DG sets having capacity of 3×2000 KVA and 2×1010 KVA are
available in the existing plant. For the expansion activity, no additional DG set is proposed.
Specifications of the D.G Set used at IPPL is shown in Table 4.1 & 4.2.
TABLE 4.1 – Details on D.G Set
S. No. Tag No. Sl.No Capacity Fuel
Consumption/Hr
Stack
Height in m Stack
Dia in
mm Total
height
Up to
port
hole
1 DG-21-01-C 7RN02086 2000 Kva 400 Ltr
30 7.5 750
2 DG-21-01-B 7RN02081 2000 Kva 400 Ltr
3 DG-21-01-A 7RN02080 2000 Kva 400 Ltr
4 DG-21-02-B DPN00111 1010 Kva 200 Ltr
5 DG-21-02-A DPN00110 1010 Kva 200 Ltr
4.2 BOILER
Two boilers (one standby) having 12 TPH steam generation capacity has already been
installed at the premises. For the expansion no additional boilers have been proposed. Details
on the boiler used at IPPL have been shown in the following table.
PRE-FEASIBILITY REPORT
20
TABLE 4.2 – Technical details of Boiler
DESCRIPTION UNITS SM-120 DH/10.54 KG/CM2 (g)
Type Three Pass Wet back smoke tube boiler
Design Code IBR 1950
Steam Output F & A
1000C
kg/hr 12000
Design Pressure kg/cm2g 10.54
Safety valve set pressure kg/cm2g 10.54
Dryness fraction % 98
Thermal Efficiency on
NCV
% 89+/-2 on HSD & 94 +/- 2 on LPG Firing
with Economiser
Heat output 106 kcal/hr 6.48
Volumetric heat release
rate
106
kcal/hr.m3
0.74
Heating surface area M2 239
Steam space m3 4.92
Water holding capacity
upto
NWL
m3 19.12
FUEL
Type HSD
NCV kcal/kg 9500
Type LPG
NCV kcal/kg 10500
Burner Thermax Oertli
Type Pressure Jet
Light up Pilot Burner By High voltage spark
Fuel supply pressure kg/cm2g 25
Turn Down 1 : 4
Modulation Step less
4.3 COOLING TOWER
Cooling tower having 700 CMH water cooling capacity has already been installed at the
premises. For the expansion no additional boilers have been proposed. Technical
specifications of the cooling tower used at IPPL have been shown in the following table.
PRE-FEASIBILITY REPORT
21
TABLE 4.3 – Cooling Tower Specifications
PRE-FEASIBILITY REPORT
22
4.4 POLLUTION PREVENTION MEASURES
4.4.1 AIR POLLUTION CONTROL MEASURES
The existing APC measures already in place at IPPL have been shown in the following table.
Since no additional equipments have been proposed for the expansion, there will be no
additions to the existing APC measures.
TABLE 4.4 – Details on APC measures
S. No. Equipment Capacity Number APC measure
Stack details
Height in m Stack
Dia in
mm Total
height
Up to
port
hole
1 Diesel
Generator 2000 Kva 3 Stack
30 7.5 750
2 Diesel
Generator 1010 Kva 2 Stack
3 Boiler 12 TPH 2 Stack 30 10.5 1000
PRE-FEASIBILITY REPORT
23
4.4.2 WATER POLLUTION CONTROL MEASURES
4.4.2.1 DOMESTIC SEWAGE
Adequate capacity of wastewater treatment system has been provided for treating domestic
wastewater. Since only the shifting population of workers is expected to increase, there will
be minimum increase in the quantity of domestic wastewater (sewage).
There will be an increase only in domestic wastewater generation due to an increase in the
number of drivers. The additional quantity of wastewater will also be treated in the existing
Sewage Treatment Plant (treatment capacity 80 KLD) which is adequate to handle the
additional quantity of effluent.
The layout of the Sewage Treatment Plant is given in Figure 4.1.
The Characteristics of the raw sewage at present is as below:
pH - 4.5 to 7
Suspended Solids - 600 to 700 mg/l
Oil & Grease - 2 to 5 mg/l
COD - 500 to 600 mg/l
BOD (3 Days at 27oC) - 400 to 600 mg/l
The Characteristics of the sullage at present is as below:
pH - 4.5 to 7
Suspended Solids - 200 to 400 mg/l
Oil & Grease - 10 to 20 mg/l
COD - 400 to 500 mg/l
BOD (3 Days at 27oC) - 100 to 150 mg/l
PRE-FEASIBILITY REPORT
24
THE SCHEME OF SEWAGE TREATMENT PLANT
Figure 4.1 shows a schematic representation of the existing treatment system. This plant will
be able to handle and treat the increased quantum of the wastewater and is detailed in Table
4.5.
Extract
Sludge Recirculation Excess sludge
Gardening
FIGURE 4.1 – SCHEMATIC DIAGRAM OF SEWAGE TREATMENT PLANT
Aeration tank
Settling tank
Pressure Sand Filter
Activated Carbon Filter
Partially treated collection tank
Treated sewage collection tank
Sludge drying beds
Raw sewage collection tank
PRE-FEASIBILITY REPORT
25
TABLE 4.5 - Details of the existing sewage treatment units and capacity
PROCESS DESIGN DETAILS
Screen Chamber
Normal flow designed 3.75 m3/hr
No. of Screen Chamber One
Angle of Inclination 45o
Width of the Opening 25 mm
Size of the screen chamber 0.5m x 0.5m x 1.0m T.D
Free Board 300 mm
Common Collection/Equalization Tank
Normal flow designed 3.75 m3/hr
No. of Tanks One
Volume of Tank 45 m3
Free Board Based on gravity inlet
Aeration Tank
Type Activated Sludge Treatment
Normal flow designed 3.75 m3/hr
No. of Tanks One
Volume of the tank 37.5 M3
Free board 300 mm
Inlet BOD to the Reactor 300 mg/L
BOD Loading 15 Kgs/Day
Clarifier
Normal Flow Designed 3.75 m3/hr
Supernatant Overflow 3.75 m3/hr
No. of Tanks One
Volume of the tank 15 m3
Free board 300 mm
Area of the Clarifier 3 m2
SWD 1.5m+0.25m
Clarified Water Tank
Normal Flow Designed 3.75 m3/hr
No. of Tanks One
Volume of the tank 15 m3
Free board 300 mm
Treated Water Storage Tank
Normal Flow Designed 3.75 m3/hr
No. of Tanks One
Volume of the tank 45 m3
Free board 300 mm
Treated Water Storage Tank
No. of Tanks Two
Size of the Tank 1.0m x 1.0m x 0.5m TD
Free board 300
PRE-FEASIBILITY REPORT
26
4.4.2.2 EFFLUENT GENERATION, TREATMENT & DISPOSAL
Currently IPPL utilizes raw water for two major industrial activities, (i) operating the DM
Plant and (ii) operating the Cooling Tower. The DM Plant provides feed water to the Boiler
which generates effluent in the form of blow-down water.
Blow-down water from boiler water is directly disposed to the solar evaporation pond. Blow-
down water from DM plant & Cooling Tower water is treated using RO plant which in turn
produces permeate and reject water. RO permeate is recycled to DM plant and the reject
water is diverted to solar evaporation ponds.
After the expansion, raw water will be used exclusively for operating the Cooling Tower.
Effluent will be generated from blowdown of the DM Plant and Cooling Tower. There will
be no change in the quantity of effluent generated and so the same disposal practices will be
followed.
4.4.3 SOLID & INDUSTRIAL WASTE POLLUTION CONTROL MEASURES
4.4.3.1 SOLID WASTE
The details of solid waste generated onsite are given in Table 4.4 along with quantity and
disposal methods. The generated solid waste is being disposed by existing authorized
practices as given in Table 4.6.
TABLE 4.6 – Solid Waste Generation & Disposal Methods
S.
No.
Type of
Waste Category
Quantity of generation
Disposal method Existing
After proposed
expansion
1 STP sludge Non-
hazardous
120kg/Month 315 kg/Month Used as manure for
green belt development
* There will be no significant change in the quantity of municipal solid waste generated on-
site.
4.4.3.2 INDUSTRIAL WASTE
The details of industrial waste generated before and after expansion of the plant are given in
Table 4.7 along with quantity and disposal methods.
PRE-FEASIBILITY REPORT
27
TABLE 4.7 – Industrial Waste Generation & Disposal Methods
S.
No.
Type of
Waste Category
Quantity of generation
Disposal method Existing
After proposed
expansion
1 Spent /
used oil Hazardous
(5.1)
0.92
KL/yr
For the expansion activity
no increase in the quantity
of hazardous waste beyond
0.92 KL/yr is envisaged.
Disposed to CPCB
authorized recyclers
*IPPL has obtained authorization for handling the current quantity of hazardous waste from
Tamil Nadu Pollution Control (TNPCB Authorization No. 4254 Proceedings No.: T5/E-
AMB0079/HWA/2012) which is enclosed in Annexure VII.
4.5 FIRE FIGHTING SYSTEM
4.5.1 FIRE HYDRANT SYSTEM
The Propane/Butane/LPG import facility of IPPL at Ennore has an extensive network of
pressurized fire hydrant system (8.8 kg/cm2G) having 48 double headed hydrants and 42 Nos
water monitors. This system enables to fight fire anywhere within Terminal and to cool
vessels and structures to ensure their safety during· an incident involving incidents of
dangerous heat flux from a burning fire.
Pressure maintaining electric jockey pumps have been installed to maintain the pressure in
the system. The minimum pressure at most remote hydrant with system fully loaded will not
be less than 7.8 kg/cm2 G. The hydrant system pressure is maintained by one 15m3/hr Jockey
Pump and a stand by Jockey Pump. The fire hydrants are spaced maximum 15 Meters apart
as per requirements of TAC.
A schematic layout of the Fire Hydrant system has been shown in Annexure VIII.
4.5.2 FIRE EXTINGUISHERS
The respective Fire Extinguishers are placed all around the buildings for immediate use.
4.5.3 FIRE ALARM SYSTEM
Fire Fighting Facility Alarms have been provided to display in Fire Pump House and Main
Control Room for operation of fire fighting pumps, deluge valves, MV sprayers, fire hydrants
PRE-FEASIBILITY REPORT
28
and monitors. MV water spray system have been provided to activate through operation of
heat actuated quartzoid bulbs fusing at 79oC and commence the first aid cooling of
equipment, vessels and structure. A dedicated Fire Alarm network with manual call point
type fire alarm in the hazardous as well as in non-hazardous area has been provided.
An audio visual main annunciation panel is provided at the Main Control room for hydrant
system, Deluge valve system and medium velocity water spray system. This panel provides
Centralized information about vessels or areas or structures which are affected by fire and fire
fighting systems in operation. Repeater fire alarm panel has been provided at fire water pump
house, S&D Building.
Combined actions of M.V spray systems, fire hydrants and monitors supported by number of
fire fighting pumps working in parallel and large water storage will ensure that conditions for
major accident hazards are never allowed to occur. Details on the Fire Protection System
layout, Gas & Flame detector layout and the Fire Organization Chart have been shown in
Annexure VIII, Annexure IX and Annexure X.
4.6 RAINWATER DRAINAGE SYSTEM
4.6.1 RAINWATER HARVESTING SYSTEM
The facility at IPPL has adequate rain water harvesting and storm drainage system.
Catchment area has been designed to capture rainwater along the driveways namely, Paved
Roads, Truck Parking, Fire Water Reservoir and Elevated Water Tank. The total catchment
area along the driveways is 45,672 m2. Collected rainwater along with stormwater is diverted
to Rain Water Harvesting Pond. Major catchment sites along the built area include the D.G
room, Electrical Substation and Administrative Block. Along the built area rainwater
catchment is designed to have a capacity of 4636 m2. The total rainwater catchment area at
IPPL is approximately 50,309 m2. Details on the Rainwater Harvesting Pond currently in use
at IPPL are shown in Figure 4.2.
PRE-FEASIBILITY REPORT
29
FIGURE 4. 2 – SCHEME OF RAINWATER HARVESTING POND
PRE-FEASIBILITY REPORT
30
4.6.2 STORM WATER MANAGEMENT SYSTEM
Storm water run-off from roads/paved/landscaped areas is being directed to Rain Water
Harvesting Pond. The storm water management in this facility ensures that the project site
does not get flooded. This can be achieved by design, construction and maintenance of the
drain using best engineering practices. The storm run-off does not get contaminated. This is
realized by keeping the areas clean the drains periodically. Spillage of fuel/oil from storage
places will be properly managed. The layout shows the rainwater harvesting & storm water
management system is given in Figure 4.3
PRE-FEASIBILITY REPORT
31
FIGURE 4.3 – DRAINAGE LAYOUT SCHEME
PRE-FEASIBILITY REPORT
32
4.7 PERSONAL PROTECTIVE EQUIPMENTS
For meeting the toxic hazard emergency and for preventing accidents arising out of spillage
of various chemicals and operating personnel, personal protective equipments are provided
and the need based extra PPE will be assessed and provided to the respective location
personnel.
4.8 GREEN BELT
An area of about 22 acres of land is already developed with green belt. No additional green
belt area has been proposed. Trees have been planted along periphery of the terminal
compound wall. The existing variety & number of trees that have already been planted at the
premises have been shown in the following table.
TABLE 4.8 – List of tree saplings
S. No. List of tree saplings Nos.
1 Spathodia 250
2 Peltophorum 120
3 Bauhunia 150
4 Indian Cod Tree 175
5 Neem Tree 180
6 Poovarasu 150
7 Delonix Regia 225
8 Nagalingam 100
9 Arasu Tree 50
10 Manoranjitham 100
5 INFRASTRUCTURE FOR THE PROPOSED PROJECT
The proposed expansion will be carried out within the existing land that belongs to IndianOil
Petronas Private Limited. The land use classification of the site is industrial. The land use
break-up showing the existing and proposed activities is given in Table 5.1. All required
amenities and facilities are available in the existing plant itself. The site layout showing plant
and other amenities is given Figure 5.1.
PRE-FEASIBILITY REPORT
33
TABLE 5.1 - Land Use Break-Up
Sl.No Description
Breakup Area
(existing)
(sq.m)
Breakup Area
(change)
(sq.m)
Final Breakup
in %
1 Production Building 4287 4654.5 1.05
2 Area for Future Facilities 130000 129632.5 29.11
3
Ancillary / Supporting
Buildings 8158 No change 1.83
4 Storage Area 6212 No change 1.39
5 Road Area 37000 No change 8.31
6 Parking Area 61500 No change 13.81
7
Green Belt / Landscape
Area 174993 No change 39.29
8
Rain Water Harvesting
Pond Area 23200 No change 5.21
Total 445350 445350 100
5.1 INDUSTRIAL/PROCESSING AREA
The total land available under the ownership of the IPPL is 110 acres (445350 sq. m.). The
proposed establishment activities will be carried out within the above area itself which is
sufficient for the planned activities. There will be no addition of any storage, equipment and
machineries. The infrastructure layout for the proposed expansion is represented in the
Figure 5.1.
PRE-FEASIBILITY REPORT
34
FIGURE 5.1 – SITE LAYOUT SHOWING PLANT AND UTILITIES
PRE-FEASIBILITY REPORT
35
5.2 POWER REQUIREMENT
TANGEDCO has agreed to meet IPPL’s demand quota of 3593 KVA. During power
shutdown, DG sets will be operated to maintain continuous plant functioning.
5.3 MAN POWER REQUIREMENT
The total man power of the IPPL is about 110 nos. (inclusive of contract workers). The unit is
currently operated on a single shift basis which is planned to increase to three shifts. For the
new establishment, no additional manpower is required now as the required number of
workers were already recruited upon completion of training period. The shifting population
of workers (drivers) is expected to increase due to the increase in number of shifts.
5.4 WATER REQUIREMENT
The total water requirement of the existing plant is about 150 KLD and it will be increased to
187 KLD after the proposed expansion. The additional quantity of water will be utilized for
domestic purposes. The total water requirement of the plant will be sourced from Govt.
Desalination Plant at Kattupalli through CMWSSB. A copy of the agreement has been shown
in Annexure XI. The water balance diagram showing water requirement and waste water
generation & usage of treated water during existing and proposed process is shown in
Figures 5.2 & 5.3 respectively.
PRE-FEASIBILITY REPORT
36
FIGURE 5.2 - WATER BALANCE DIAGRAM FOR EXISTING PROCESS
PRE-FEASIBILITY REPORT
37
FIGURE 5.3 - WATER BALANCE DIAGRAM FOR PROPOSED PROCESS
PRE-FEASIBILITY REPORT
38
5.5 ENVIRONMENT MANAGEMENT PLAN (BUDGET)
S. No. Description (Cost in lakhs rupee)
Capital cost
Recurring cost per annum
1 Sewage treatment plant (O&M) 25 2
2 Environmental assessment & reporting
-- 0.9
3 Greenbelt development 7 5.28
4 Occupational health check-up -- 1
5 Occupational safety 21 4
Total 53 13.2
6 PROJECT SCHEDULE & COST ESTIMATES
6.1 TIME SCHEDULE FOR THE PROJECT IMPLEMENTATION
Upon issuance of Environmental Clearance M/s IPPL will obtain necessary consent
orders from TNPCB for commencing the installation of additional 4 TLD bays.
6.2 ESTIMATED PROJECT COST
The estimated cost for installing the additional TLD bays (4 nos.) Rs. 20 crores.
7 CORPORATE SOCIAL RESPONSIBILITY
M/s Indian Oil Petronas Pvt Ltd have submitted their proposal for carrying out the
following activities
S. No. Activity Expense
1 Constructing toilet facilities at Government
High School, Athipattu village
49.5 lakhs
2 Providing drinking water supply to
Athipattu village
74 lakhs
Total 123.5 lakhs
-
DR. H"MALLESHAPPA,I.tr"S.,MEMBER SECRETARY
STATE LEVEL ENVIRONMENTIMPACT ASSESSMENTAUTHORITY, TAMILNADU,3 rd Floor, PanagalMaaligai,No.1 Jeenis Road, Saidapet,Chennai-15.
ToThe Di
Letter No. SEIAA-TN/F -2453 l20l 4 Dt. 11.12.2014.
Mini of En\ironment & Forests (IA Division)
.O. Complex,Lodhi Road,ew Delhi - 110 003^
Sub: SEIAA -TN - Proposed expansion of Production capacity of LPG Import /Export Terminal at Athipattu village, Ponneri Taluk, Tiruvallur District, byM/s. Indian Oil Petronas Pvt Ltd. - Minutes - Reg.
Ref: 1. Application for EC dt.20.03.2014, from. M/s. IPPL"2. Minutes of 62't SEAC rneeting held on 19.IL20I4
Kind attention is invited to the subject and reference 1't cited, wherein application was
made for Environmental Clearance under EIA Notification, 2006 for the Proposed expansion
of Production capacity of I-PG hnport / Export Terminal, by M/s.Indian Oil Petronas Pvt
Ltd, under Category 6'B 1" and schedule S.No.6 (b) at Athipattu village, Ponneri Taluk,
Tiruvallur District.
From the copy of minutes received in this office of the Reconstituted EAC, MoEF,
GOI, (in its 24thmeeting, held on 29-30'h September 2014), for the Proposed LPG Pipeline
from Kochi Refinery in State of Kerala to Coimbatore District in State of Tamilnadu, it was
noted that - the LPG Storage facilities functioning as Receipt Terminal is to be treated as
an Integrated facility with the pipeline and project treated as Category oA'"
In similar lines, the pipeline and connected Storage / Blending unit are taken as
integrated facility, following which the subject was placed before the SEAC -TN in the
62nomeeting held on26.l\.2014. The Committee recommended and decided to forward the
file to MoEF, GOI for furlher processing.
Hence the file is hereby treated as "A" category and forwarded to MoEF, GOI, for
further processing as per the minutes cited.
{-{Sq dqe
Annexure 1
E,
t
ir'The receipt of this letter along with project proposals
acknowledsed.
Encl: File No- 2453 12014
+
" .l;
:'
r
SEIAA-TN
I43, Alhipattu village, NCTPS main road,Chennai - 600 120