19
TOPIC- Formwork for Bridge and Centering Of Arch NAME ENROLL NO. PATEL NIRMAL 131100106036 PATEL PRIYANKA 131100106037 PATEL Shivani 131100106039 PATEL VIRAJ 131100106040 PATEL YASH 131100106042 GUIDED BY: Prof. PINANK R. PATEL Prof. MIHIR B. NAIK
Transcript
Page 1: Formwork for Bridge and Centering Of Arch

TOPIC- Formwork for Bridge and Centering Of Arch

NAME ENROLL NO.PATEL NIRMAL 131100106036PATEL PRIYANKA 131100106037PATEL Shivani 131100106039PATEL VIRAJ 131100106040PATEL YASH 131100106042

GUIDED BY: Prof. PINANK R. PATEL Prof. MIHIR B. NAIK

Page 2: Formwork for Bridge and Centering Of Arch

CONTENTSCENTERING OF ARCHCENTERING OF BIG ARCHESFALSE WORK FOR BRIDGESSLIP FORMWORK

Page 3: Formwork for Bridge and Centering Of Arch

Centering of an ArchCentering is the temporary structure

required to support brick, stone or concrete work of arch, Dome etc. during its construction .

The centering choice depends upon several factors like ; Shape of ArchSpan of OpeningThickness of SoffitMaterial used in arch construction …etc

Page 4: Formwork for Bridge and Centering Of Arch

Width of the thinner soffit is 10 cm . If the width of the soffit is wider than 10 cm. ,

two ribs suitably spaced & shaped at the Top may be used.

Page 5: Formwork for Bridge and Centering Of Arch

Centering for a wide soffit and bigger span

Page 6: Formwork for Bridge and Centering Of Arch

Centering for big Arches of bridgesFor the construction of big arches, the

centering will be invariably required.factors:-

Nature & type of arch (i.e. span, rise etc…)Foundation conditionsDepth of water , liability to flood, etc…Distance required between support of

centering for the passage of traffic.Size & lengths of timber availableAvailability of labour.

Page 7: Formwork for Bridge and Centering Of Arch

It has Three type,1. Timber truss centering2. Trestle centering3. Steel truss centering

Page 8: Formwork for Bridge and Centering Of Arch

1. Timber truss centering

It is very useful when,The arch provided in deep valleyThe support for centering are to rest in deep

water.The passage of traffic is required.

Page 9: Formwork for Bridge and Centering Of Arch

2. Trestle centering

Page 10: Formwork for Bridge and Centering Of Arch
Page 11: Formwork for Bridge and Centering Of Arch

3. Steel truss centering

It is very useful when,It is impossible to use trestle type centeringDepth of water is moreArches constructed for heavy flood.

Page 12: Formwork for Bridge and Centering Of Arch

False work for BridgesFalse work consists of temporary structure used in

construction to support spanning or arched structures in order to hold the component in place until its construction is sufficiently advanced to support itself.

The construction of falsework in bridges consists ofTimber or concrete foundation padsTimber corbelsSand jacks and wedgesSteel sill beamsTimber or round hollow steel postsSteel cap beamsTimber or steel stringer beams & timber joists.

Page 13: Formwork for Bridge and Centering Of Arch
Page 14: Formwork for Bridge and Centering Of Arch

Causes of failure of false workThe failure may occurs due to

The overloaded of the falseworkThe inadequate designThe lateral instability of a beam

In some cases, the localized flange bending may takes place at the interface between the cap and sill beams and posts.

Page 15: Formwork for Bridge and Centering Of Arch

Pile formwork• The slip formwork

proves to be economical for vertical structures, which are in the form of concrete shafts.

• They are widely used for piers, chimneys, towers, missile, launching bases, water reservoir, silos, revolving restaurants, etc.

Page 16: Formwork for Bridge and Centering Of Arch
Page 17: Formwork for Bridge and Centering Of Arch

The essential parts of slip forms are follow- sheathing- wales or ribs- yokes- working platform or deck- suspended scaffolding-lifting devices

Advantages The construction of joints is eliminated. The construction work can be carried out speedily. There is considerable saving in cost of forms as there is less

wastage of forms and they can be used several times.

Page 18: Formwork for Bridge and Centering Of Arch

ReferenceGoogle imageAdvanced construction Equipments by R.P.

RETHALIYAAdvanced construction Techniques by

Mahajan publication.

Page 19: Formwork for Bridge and Centering Of Arch

Thanks…