Date post: | 12-Jan-2017 |
Category: |
Education |
Upload: | osp-international-llc |
View: | 155 times |
Download: | 0 times |
Free PMP® Exam
Sample Question
pm-exam-simulator.com
PMP® Exam Sample Question
Presented by Cornelius Fichtner, PMP
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
Provided by
www.pm-exam-simulator.com
This presentation showcases free sample questions to help you study for the PMP exam
Cost of Quality refers to the total cost of all
efforts related to quality throughout the
Product Life Cycle. Organizations should
invest in product quality improvement to
reduce which of the following?
If organizations don't invest in product quality improvements, the cost of product returns, warranty
claims, and recall campaigns increases.
Organizations should invest in
reducing the External Cost of Quality by improving product quality.
This will result in reduced product
returns and warranty claims.
Program Evaluation and Review Technique
depends on which of the following statistical
distributions?
A. Binomial Distribution B. Log-Normal Distribution C. Uniform Distribution D. Triangular Distribution
The PERT technique is based on the assumption that the underlying
data can be represented by a triangular distribution. This is another
way of saying that PERT is using a three-point (triangular)
estimation. Note: This question is intentionally a bit obscure.
However, it is a valid question because you must expect to find
"obscure" questions that are taken from sources other than the
PMBOK Guide on the real PMP Exam. If you come across a question
on the exam where you ask yourself "How on earth could anyone
know this?" then you need to make a selection and move on.
Joe is working as a project manager
on a highway construction project. He
wants to use a fixed price contract
instead of cost-plus contract. The risk
response strategy he is using in this
case is an example of?
The project manager in this example is currently performing
the Conduct Procurements process but the answer is in the Plan Risk
Responses process.
Risk Transference requires shifting some or all
of the negative impact of a threat, along with the
ownership of the response. A fixed price
contract may transfer risk to the seller, whereas
a cost-plus contract may transfer cost risk to the
buyer.
Get more free sample questions from
free.pm-exam-simulator.com