+ All Categories
Home > Education > Free PMP® Exam Sample Questions

Free PMP® Exam Sample Questions

Date post: 12-Jan-2017
Category:
Upload: osp-international-llc
View: 155 times
Download: 0 times
Share this document with a friend
19
Free PMP® Exam Sample Question pm-exam-simulator.com
Transcript

PMP® Exam Sample Question

Presented by Cornelius Fichtner, PMP

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Cost of Quality refers to the total cost of all

efforts related to quality throughout the

Product Life Cycle. Organizations should

invest in product quality improvement to

reduce which of the following?

A. Internal Cost of Quality B. Prevention Costs C. Appraisal Costs D. External Cost of Quality

If organizations don't invest in product quality improvements, the cost of product returns, warranty

claims, and recall campaigns increases.

D. External Cost of Quality

Organizations should invest in

reducing the External Cost of Quality by improving product quality.

This will result in reduced product

returns and warranty claims.

Program Evaluation and Review Technique

depends on which of the following statistical

distributions?

A. Binomial Distribution B. Log-Normal Distribution C. Uniform Distribution D. Triangular Distribution

Program Evaluation and Review Technique is the PERT technique

and relies on three-point estimating.

D. Triangular Distribution

The PERT technique is based on the assumption that the underlying

data can be represented by a triangular distribution. This is another

way of saying that PERT is using a three-point (triangular)

estimation. Note: This question is intentionally a bit obscure.

However, it is a valid question because you must expect to find

"obscure" questions that are taken from sources other than the

PMBOK Guide on the real PMP Exam. If you come across a question

on the exam where you ask yourself "How on earth could anyone

know this?" then you need to make a selection and move on.

Joe is working as a project manager

on a highway construction project. He

wants to use a fixed price contract

instead of cost-plus contract. The risk

response strategy he is using in this

case is an example of?

A. Risk Avoidance

B. Risk Transfer

C. Risk Mitigation

D. Risk Acceptance

The project manager in this example is currently performing

the Conduct Procurements process but the answer is in the Plan Risk

Responses process.

B. Risk Transfer

Risk Transference requires shifting some or all

of the negative impact of a threat, along with the

ownership of the response. A fixed price

contract may transfer risk to the seller, whereas

a cost-plus contract may transfer cost risk to the

buyer.


Recommended