+ All Categories
Home > Documents > FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment...

FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment...

Date post: 09-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
111
F4E (09) -GB I2 - 12 Fina l 27/1 1/2009 FUSION FOR ENERGY The European J oint Undertaking for ITER and the Development of Fusion Energy THE GOVERNING BOARD DECISION OF THE GOVERNING BOARD ADOPTING THE 2010 WORK PROGRAMME OF THE EUROPEAN JOINT UNDERTAKING FOR ITER AND THE DEVELOPMENT OF FUSION ENERGY THE GOVERNING BOARD OF FUSION FOR ENERGY HAVING REGARD to the Statutes annexed to the Council Decision (Euratom) No 198/2007 of 27 th March 2007 establishing the European Joint Undertaking for IT ER and the Development of Fusion Energy (hereinafter "Fusion for Energy") and conferring advantages upon it and in particular Articles 6(3)(d) and II thereof; HAVING REGARD to the Financial Regulation of Fusion for Energy" adopted by the Governing Board on 22 nd October 2007, last amended on 18 th December 2007 3 (hereinafter "the Financial Regulation"), and in particular Article 64 thereof ; HAVING REGARD to the Implementing Rules of the Financial Regulation" adopted by the Governing Board on 22 nd October 2007 last amended on the 8 th July 2008 5 (hereinafter "the Implementing Rules") and in particular Article 53 thereof; HAVING REGARD to the Fusion for Energy Project Plan and Resource Estimates Plan adopted by the Governing Board on 26 th November 2009; HAVING REGARD to the comments and recommendation of the Executive Committee on the proposal for the 2010 Work Programme adopted at its meeting of 4 _5 th November 2009' ; HAVING REGARD to the comments and recommendations of the Technical Advisory Panel adopted at its meeting on 4 th November 2009, WHEREAS: (I ) The Director should, in accordance with Article 8(4)(c), draw up an annual work programme; (2) The Governing Board should adopt the work programme. HAS ADOPTED THIS DECISION: Article 1 The 20 I0 Work Programme of Fusion for Energy annexed to this Decision is hereby adopted. 2 6 OJ. L 90, 30.03.2007, p. 58. F4E(07)-GB03-l l Adopted 22/1 0/2007 F4E(07)-GB04-06 Adopted 18/12/2007 F4E(07)-GB03-12 Adopted 22/1 0/2007 F4E(08)-GB06-06aAdopted 08/07/2008 F4E(09)-ECI7-Summary Adopted 05/11/2009 Page 1 of 53
Transcript
Page 1: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E (09)-GB I2 -12Fina l 27/1 1/2009

FUSION FOR ENERGYThe European Joint Undertaking for ITER andtheDevelopment of Fusion Energy

THE GOVERNINGBOARD

DECISION OF THE GOVERNING BOARD ADOPTING THE 2010 WORKPROGRAMME OF THE EUROPEAN JOINT UNDERTAKING FOR ITER AND

THE DEVELOPMENT OF FUSION ENERGY

THE GOVERNING BOARD OF FUS ION FO R ENE RGY

HAVING REGARD to the Statutes annexed to the Council Decision (Euratom) No 198/2007of 27th March 2007 establishing the European Joint Undertaking for ITER and theDevelopment of Fusion Energy (hereinafter "Fusion for Energy") and confer ring advantagesupon it and in particul ar Articles 6(3)(d) and II thereof;

HAVING REGARD to the Financia l Regulation of Fusion for Energy" adopted by theGo vern ing Board on 22nd October 2007, last amended on 18th Dece mber 2007 3 (hereinafter"the Financial Regulation"), and in particular Article 64 thereof;

HAVING REGARD to the Implementing Rules of the Financial Regulation" adopted by theGoverning Board on 22 nd October 2007 last amended on the 8th July 2008 5 (hereinafter "theImplementing Rules") and in part icular Arti cle 53 thereof;

HAVING REGARD to the Fusio n for Energy Project Plan and Resource Est imates Planadopted by the Gove rning Board on 26th November 2009;

HAVING REGARD to the comments and recomm endation of the Executive Committee onthe proposal for the 2010 Work Programme adopted at its meeting of 4_5 th No vember 2009' ;

HAVI NG REGARD to the comments and recomm endat ions of the Techni cal Advisory Paneladopted at its meeting on 4th November 2009,

WH EREAS:

(I ) The Director should, in accordance with Art icle 8(4) (c), draw up an annual workprogramme;

(2) The Governing Boa rd should adopt the work programme.

HAS ADO PTED THI S DECISION:

Article 1

The 20 I0 Work Programm e of Fus ion for Energy annexed to this Decision is hereby adopted.

2

6

OJ. L 90, 30.03.2007, p. 58.F4E(07)-GB03- l l Adopted 22/1 0/2007F4E(07)-GB04-06 Adopted 18/12/2007F4E(07)-GB03-12 Adopted 22/1 0/2007F4E(08)-GB06-06aAdopted 08/07/2008F4E(09)-ECI7-Summary Adopted 05/11/2009

Page 1 of 53

Page 2: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-] 2Final 27/1 ]/2009

Article 2

This Decision shall have immediate effect.

Done at Barcelona, 27th November 2009

For the Governing Board

Carlos Varandas

Chair of the Governing Board

Page 2 of 53

Page 3: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 2711112009

ANNEX I

FUSION FOR ENERGY WORK PROGRAMME 2010 (WP2010)

TABLE OF CONTENTS

PART I - INTRODUCTION, ASSUMPTIONS AND OVERALL OBJECTIVES 5

1.1. INTRODUCTION 51.2. ASSUMPTIONS 51.3. ITER CREDITS FOR PREPARATORY ACTIVITIES 61.4. MAIN OBJECTIVES 6

1.4.1. nIiK 61.4.2. BroaderApproach . 7143 DEMU.. . 7

PART II-ITER 8

2.1. WBS I.I-MAGNETS 92.1.1. Summary « 92.1.2. Procurement Arrangements.: .. 92.1.3. Main Procurements 92.1.4. List ofActivities 10

2.2. WBS 1.5 - VACUUM VESSEL 112.2.1. Summary II2.2.2. Procurement Arrangements.. .. 112.2.3. Main Procurements II2.2.4. List ofActivities II

2.3. WBS 1.6 - BLANKET 132.3.1. Summary 132.3.2. Procurement Arrangements 132.3.3. List ofActivities 13

2.4. WBS 1.7 - DIVERTOR 152.4.1. Summory: . 152.4.2. Procurement Arrangements.. . 152.4.3. Alain Procurements 152.4.4. List ofActivities 15

2.5. WBS 2.3 - REMOTE HANDLING (RH) 162.5.1. Summary.. . 16) .i" ) Procurement Arr(mg(~I11(~nts 162.5.3. List ofActivities 16

2.6. WBS 3.1 - VACUUM PUMPING AND FUELLING 182.6.1. Summary 182.6.2. Procurement Arrangements.. . 182.6.3. List ofActivities 18

2.7. WBS 3.2- TRITIUM PLANT 192.7.1. Summary : . 192.7.2. Procurement Arrangements.. . 192.7.3. List ofActivities.. .19

2.8. WBS 3.4 - CRYOPLANT 202.8.1. Summary. . 202.8.2. Procurement Arrangements.. . 202.8.3. List ofActivities 20

2.9. WBS4.1 AND4.3-POWERSUPPLIES 212.9.1. Summary 212.9.2. Procurement Arrangements 212.9.3. List ofActivities.. . 21

2.10. WBS4.5-CODAC 222.10.1. Summary, . 22

Page 3 of 53

Page 4: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 2711112009

2.10.2. Procurement Arrangements ", 222./ O. 3. List ofActivities 22

2.11. WBS 5.1.1-ION CYCLOTRON H&CD ANTENNA 232.//./. Summary 232.11.2. Procurement Arrangements.. . 232./1.3. List ofActivities 23

2.12. WBS 5.2 - ELECTRON CYCLOTRON 24W13S 5.2./13 ELECnWN CYCL071WN UPPER LAUNCHER. .. 24

2./2.1. Summary : .. 242.12.2. Procurement Arrangements: . 242./2.3. List ofActivities.. .... 24

W13S 52.3 ELECnWN CYCL071WN POWER SOURC~;;ANDW13S 5.2.4 EC POWER SUPPLl~;; 242./2.4. Summary : .. 242. J2.5. Procurement Arrangements.. . 242./2.6. List ofActivities 25

2.13. WBS 5.3-NEUTRALBEAM SySTEM 262./3./. Summary . 262.13. 2. Procurement Arrangements " 262./3.3. List ofActivities 26

2.14. WBS5.5 -DIAGNOSTICS 282./4.1. Summary.. .. 282.14.2. Procurement Arrangements.. . 282./4.3. List ofActivities... . 28

2.15. WBS 6.1 - SITE AND WBS 6.2· BUILDINGS 302./5./. Summary 302.15.2. Procurement Arrangements 302./5.3. List ofActivities... . 30

2.16. MATERIALS DEVELOPMENT 312.17. TEST BLANKET MODULES 332.18. PLASMA ENGINEERING 342.19. SAFETy 362.20. ENGINEERING SUPPORT 382.21. NUCLEAR DATA 392.22. ACTIVITIES OF QUALITY ASSURANCE (QA) AND PROJECT MANAGEMENT 402.23. CONTRIBUTIONS IN CASH .41

2.23./. Contribution to CEA[or 17UI Site Support 4/2.23.2. Contribution to the 171iR Organization.. .. 4/2.23.3. Contribution to Japan.. .. 4/

2.24. EXPERTS FOR TECHNICAL ASSISTANCE TO F4E........................................... .. .412.25. URGENT ACTIVITIES IN SUPPORT OF COST AND RISK ASSESSMENT 41

PART III· BROADER AI'PROACII 42

3.1. INTRODUCTION 423.2. JT60SA 42

3.2.1. F4E Funded Activities: .. 423.2.2. Procurement Arrangements 43

3.3. IFMlF 433.3.1. F4E Funded Activities : .. 433.3.2. Procurement arrangements 43

3.4. IFERC 443.4./. F4E Funded Activities 443.4.2. Procurement Arrangements 44

APPENDIX I - TABLE OF ACRONYMS AND ABBREVIATIONS 45

APPENDIX II - SUMMARY OF THE WP20IO BlJDGET.. 48

APPENDIX III - SlJMMARY OF THE AVAILABLE BUDGETS FOR GRANTS .49

APPENDIX IV - ESSENTIAL SELECTION AND AWARD CRITERIA FOR GRANTS 50

APPENDIX V - MAXIMlJM REIMBlJRSEMENT RATES FOR GRANTS 51

Page 4 of 53

Page 5: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/11/2009

PART I - INTRODUCTION, ASSUMPTIONS AND OVERALL OBJECTIVES

1.1. INTRODUCTION

The European Joint Undertaking for ITER and the Development of Fusion Energy ('Fusionfor Energy' or F4E) is a Joint Undertaking created under the Euratom Treaty by a decision ofthe Council of the European Union.

Fusion for Energy was established for a period of 35 years from 19'h April 2007 and islocated in Barcelona, Spain. The objectives of 'Fusion for Energy' are threefold:

• Providing Europe's contribution to the ITER International Fusion Energy Project asthe designated Domestic Agency for Euratom;

• Implement the Broader Approach agreement between Euratom and Japan as thedesignated Implementing Agency for Euratom;

• Prepare in the longer term for the construction of demonstration fusion reactors(DEMO).

In accordance with the Financial Regulation, this Work Programme lays down the activitiesof F4E that are to be implemented and financed through the 20 I0 budget.

1.2. ASSUMPTIONS

The 2010 F4E Work Programme (WP2010) for ITER is based on the following assumptions:

• The European schedule is based on the "modified" Scenario I. This scenario was usedas basis for this document;

• F4E will receive on time from 10 the necessary inputs foreseen in the ITER QualityManagement process deposited with the Nuclear Safety Authorities and in accordancewith Build-to-Print, Detailed Design and Functional Specification status agreed in2001 ;

• The necessary inputs from 10 will be provided in time to allow the associated PAs tobe signed according to the foreseen schedule;

• WP20 lOis in line with the Additional Direct Investments and the revised sharingagreed with 10 and other Domestic Agencies. The specific activities related to themodified baseline in the Blanket and Neutral Beam areas will be initiated after theITER Council approval;

• The planning of the activities and the corresponding delivery of components by theother ITER Domestic Agencies will be respected;

• A current understanding of the ITER Design and that some modifications might berequired in 2010 to adjust it to the possible ITER developments;

• F4E will continue active management of and involvement in the ongoing tasks signedunder EFDA, results of which are required to initiate certain F4E activities;

• Technically and commercially complex procurements will be implemented wheneverappropriate through the Competitive Dialogue procedure or through the negotiatedprocedure, in order to improve the alignment of supply chain response to F4E needs

Page 5 of 53

Page 6: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

and to proactively adopt cost containment measures. This will be done in compliancewith our Implementing rules;

• Grants related to recurring and sequential R&D activities, with a well defineddevelopment path eventually leading to a EU procurement package, will beimplemented whenever appropriate through the Framework Partnership Agreement(FPA) procedure, in order to streamline and channel R&D funding, improve itseffectiveness and reduce administrative burden to beneficiaries and F4E alike. Inconsideration of the transitional period for starting implementation of FPA,modifications may occur in the foreseen scheduling of grant activities included inWP2010;

• Procurements which encompass scope within the domain of both F4E and contractingauthorities, or for which a very close coordination between F4E and other entities isneeded, will be implemented whenever appropriate through the Joint Procurementprocedure.

Regarding WP2010 for Broader Approach, the main assumptions are:

• The project plans presented in this document are those approved by the BroaderApproach Steering Committee;

• The Work Programmes for the projects IFMIF/EVEDA, IFERC and the SatelliteTokamak Programme will be approved by the Broader Approach Steering Committee.

1.3. ITER CREDITS FOR PREPARATORY ACTIVITIES

This WP20 I0 includes an extensive programme of R&D and preparatory activities that haveto be carried out prior to signing the Procurement Arrangement for the Procurement Packagesagreed to be at Build-to-Print level. Recognising that F4E is carrying out work that shouldhave been completed by the 10, additional credit from the 10 is being requested by F4Ethrough ITER Task Agreements (ITAs). The activities indicated in this WP2010 as receivingadditional (ITA) credits may be cancelled in the event that the 10 would not make therequested credits available.

1.4. MAIN OBJECTIVES

1.4.1. ITER

With respect to activities related to ITER, the main objectives are:

• The negotiation and signature of the ITER Procurement Arrangements, proposed bythe ITER Organisation (10), according to the present schedule;

• The signature of procurement contracts for those components on the critical path (inparticular buildings, magnets and vacuum vessel);

• The continuation of design and R&D activities in areas including Remote Handling,Heating and Current Drive, Vacuum System, Tritium System, Diagnostics and TestBlanket Modules;

• The continuation of the preparation of safety and licensing documentation for ITER inCadarache and related safety studies;

• The investigation of manufacturing methods and non-destructive tests of criticalcomponents from the technical point of view with the objective of minimising the cost

Page 6 of 53

Page 7: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 2711112009

and risk of not meeting the technical requirements (radial plates, TF double pancake,divertor, vacuum vessel, blanket and first wall);

• The preparation of new facilities to test prototypes and components during thequalification process and construction respectively;

• The continuation of the activities for the preparation of the ITER site.

The most significant procurements to be initiated within WP2010 are related to:

• Magnets, for which procurement contracts for both TF coils (initially limited totooling and prototyping) and PF coils (initially limited to tooling) will be signed;

• Vacuum vessel, for which the main vessel procurement contract will be signed(initially limited to non recurring activities and to sector No 5);

• Buildings, for which the main excavation and tokamak complex foundation contractwill be signed (completing the activities initiated within WP2009).

Further to provide management and follow-up of contracts signed in direct support of theITER project, F4E continues to be responsible for the technical follow-up of a number oftechnology contracts previously managed by EFDA. The outcome of these contracts is animportant input for many of the activities that will be initiated by F4E.

1.4.2. Broader Approach

With respect to activities related to the Broader Approach (BA), the main objectives are:

• Regarding JT60SA, important TF coil procurement contracts were initiated withinWP2009 and are to be signed in 2010. Activities foreseen in WP2010 are mostly insupport of these ongoing procurements;

• Regarding IFMIF-EVEDA, Procurement Arrangements with the VoluntaryContributors will be completed by early 2010;

• Regarding IFERC, the Procurement Arrangement for the supply and maintenance ofthe CSC supercomputer will be completed during 20 IO.

1.4.3. DEMO

With respect to activities related to DEMO, in addition those undertaken under the BAIFERC project, no specific activities are foreseen to be implemented during 2010.

Page 7 of 53

Page 8: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/1 112009

PART II - ITER

In the following the activities of Fusion for Energy related to ITER are described accordingto the agreed Work Breakdown Structure. The tables provided in the text use the followingabbreviations:

AL I . -

WP ref. Work programme reference, univocally identifyingWP items.WPxx/yylzz, where xx arc the last two digits ortile year in which WP/budgctthe activitywas first financed, yy is a code identifying the ITERwas element(if available) or the F4E service in charge, zz is a sequential number for theyear.

G Grant

P Procurement (service, supply or works)

Y Credited by ITER 10 through PA

Y(ITA) Credited by ITER 10 through ITA

N Non credited

All activities indicated within WP20 I0 are planned to be committed under the 20 I0 budget.

During the implementation of the work programme activities, F4E may group more activitiesin a single call, or split one activity in more calls. This will in any case be performedpreserving the scope and objective presented in WP20 IO.

The foreseen time of publication of calls and invitations is indicative only, and based on thepresent understanding of the project development.

Page 8 of 53

Page 9: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

2.1. WBS 1.1 - MAGNETS

2.1.1. Summary

Activities will focus on the signature of further contracts for the procurement of the ITERmagnet components, some minor design/R&D activities and support contracts for qualitycontrol and testing.

2.1.2. Procurement Arrangements

EUll I, I.P6A.EU.0 I - Toroidal Field Coils Conductors 43.39 Dec 2007

EUII 1.1,P IA.EU.OI - Toroidal Field Coils 89.74* Jun 2008

EUII 1.1,P6C.EU ,0 I - Poloidal Field Magnet Conductors 11.23** May 2009

EUII I.I.P3A-B,EU.0 I - Polo idaI Field Coils PF2 to PF6 41.40** Jun 2009

EUII Magnet Structures: Pre-compression Rings 0.60*** Jan 2010

* Sum of TF Windings package credit from WBS I.1.1A plus insertion in the case from MagnetStructures WBS I, I ,2A,

** Updated credit values awarded through PCR-I64 for two double pancakes added to PF2 and PF6coils and bilateral agreement with RF-DA (to be approved by next ITER Council).

*** Does not include DCR w48 changes (increase from 4 to 9 rings), prototype ring and testing, as wellas 3 spare rings.

2.1.3. Main Procurements

WBS 1,I,IA - Toroidal Field Magnet Windings

Following the signature of the contracts for two prototypes of the radial plates and theforeseen signature of the TF winding pack supply contract in early 2010, the main work willfocus on the start up of the manufacturing activities at the companies for the production of thefirst mock-ups and prototypes. For the case insertion a small R&D task will be used to assessthe welding methods for the case closure and related non-destructive testing. Other tasks willregard characterization of resin or structural materials for the coils. A preliminary study ofthe cold test facility required for the TF windings at the supplier's premises will also becarried out.

WBS I.I.2A - Toroidal Field Magnet Structure

It is foreseen to issues the call for tender and sign the contract for the manufacture of the pre­compression rings.

WBS I,I,3A + I.I.3B - Poloidal Field Magnets (PF2 to PF6)

The first stage of the large manufacturing contract for the production of the PF coils at theCadarache site will be signed and will concentrate on the engineering activities for toolingand qualification processes. A preliminary study of the cold test facility required for the PFcoils on-site will also be carried out.

Page 9 of 53

Page 10: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27111/2009

WES 1.1.6A + 1.1.6C - Toroidal and Poloidal Field Magnet Conductors

In early 2010 the major contract for the manufacture of the conductors for the TF and PFcoils will be signed (included in WP2009). SUPPOlt contracts to perform the characterizationof the strand (both standard and extended) and the jacket structural materials during thewhole production will be initiated and signed. A new contract with the Sultan facility willalso be signed in order to test few conductor samples, as during 20 10 the conductormanufacturing will still be at the early stages.

2.1.4. List ofActivities

I mn __ , I ITI R Activity I -"L ' U ,OJ Credit I T~~e: nr m I TYpe I . Activ .uo I ~v.... :.: s~

WP09/11/03 1.1.1+1.1.3 P service Cold Test Facility Preparation II Y(lTA) 2009for TF & PF Coils

Procurement of magnetWP I0111/09 1.1.2 P supply structures: pre-compression 58 Y IOQI

rings

WPI0l11110 1.1.3

WPIO/II/II l.l.l

P supply

P supply

Procurement of Poloidal Fieldcoils PF2 to PF6 (Phase I)

Procurement of Toroidal Fieldcoils (Phase I)

25 Y

34 Y

2009

2009

WPI0l11112 1.1.6

WPI0l11101 1.1.6

WPI0l11/02 1.1.l+1.1.3

WPI0l11/04 l.l.l

WP I0111/05 1.1.1

WPIO/Il/06 1.1.6

WPI0l11/08 1.1.6

P service

P service

P service

P service

P service

P service

P service

Testing ofTF Nb3Sn Strands

Testing and Characterisationof PF strands

Analysis tasks in support ofmagnet activities

Testing ofTF StructuralMaterialsProcurement for Qualificationof Coil Insertion and CaseWelding and Definition offacilitiesSULTAN SampleManufacture & Tests

Jacket Material Qualification& Testing for TF and PF Coils

Page 10 of 53

32 Y 2009

36 Y 10QI

12 Y 10QI

43 Y 10QI

12 Y 10QI

18 Y 2009

49 Y 10QI

Page 11: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)·OB 12·12Final 27/11/2009

2.2. WBS 1.5 . VACUUM VESSEL

2.2.1. Summary

Following the outcome of the Design Review of the "Alternative VV and Blanket design", 10has taken the decision to modify the baseline design which demonstrated not fulfilling all therequirements of the project, especially in terms of integration of components. The new designis called MDR·A (Modified Reference Design A).

The 20 I0 activities will be focused on the first phase of the procurement for the main vacuumvessel "first of a kind" sector (number 5) and will concentrate mainly on the engineeringactivities for design, validation mock-ups, tooling and materials.

2.2.2. Procurement Arrangements

2.2.3. Main Procurements

At beginning of2010 10 will provide F4E with drawings suitable to issue the call for tenderfor the EU sectors.

Important F4E commitments in 2010 include sector engineering activities and the material forthe first sector manufacturing. Several smaller activities will be signed to support thepreparation of technical and contractual documentation for manufacturing studies and mock­ups to speed up the finalization of the main contract for sector 5.

2.2.4. List ofActivities

WP101lS/09 1.5.1 G I I N 10QI

Consultancy with ANB aboutWP10llSII0 I.S. I P service expeditingand inspection 6 N IOQ2

olic

WPIOIIS/OI 1.5. I P supplyProcurement of Main Vessel

S4 y 10Q3(phase I)

WPIOIIS/02 1.5.1 P serviceStudy for Mock-up Definition

4 y IOQ2for Sectors

WP101lS/03 1.5.1 P service Analysis of Welding Distortion3 y IOQ2

for Sectors

Support in preparation of finalWPIOIIS/04 I.S. I P service technical documentation for VV 6 y 10QI

contract

WPIOIIS/OS 1.5. I P serviceAnalysis of VV Loads &

8 y 10QIStresses

Page 11 of 53

Page 12: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

WPIOIlS/07 1.5.1

WPlOll5/08 1.5.1

P service

P service

Study for Concept Manufacturefor SectorsEngineering Support for VV

Page 12 of 53

F4E(09)-GB 12-12Final 27111/2009

4 Y 10Ql

6 Y,Y(lTA) 2009

Page 13: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/Il/2009

2.3. WBS 1.6 - BLANKET

2.3.1. Summary

During 20 I0, the activities in the blanket area will essentially focus on the FW component.They will consist of the continuation of the key tasks initiated in order to adequately prepareF4E to implement the Procurement Arrangement for the supply of 50% of the FW, plannedfor 2012.

2.3.2. Procurement Arrangements

None in 2010.

2.3.3. List ofActivities

These activities cover 3 main areas as follows:

• Qualification activities, aiming at demonstrating the adequate mastery of the neededtechnologies for FW fabrication, applied to fully representative geometries; High heatflux testing of semi-prototypes will be a key part of the programme, to formallycomplete phase 2 of the ITER qualification programme; contracts for the manufactureof full-scale prototypes shall then be signed with Industry which will also includedevelopment of repair techniques for series production.

• Supporting R&D tasks, aiming at completing the mechanical characterization of thejoint between structural SS and the heat sink copper alloy.

• Engineering design, covering conceptual and detailed design and analyses of the FWpanels to support ITER 10 in the overall design effort and subsequent preparation ofthe PA specifications.

WP I0116/08 1.6.1 P service Completion of Be/CuCrZrjoint16 Y 10Q3

repair technique

WP091l6/02 1.6.1 GContinuation of BeiCuCrZr HIP

18 Y,Y(ITA) 2009joining development

WP091l6/04 1.6.1 P service Engineering Support to Blanket 12 N 10QI

High heat flux testing of FW

WP09/16/05 1.6.1 G mock-ups before and after23 Y(ITA) 2009irradiation, including

trans ortation

Continuation of technologyWPIOll6/03 1.6.1 G development for enhanced first 12 Y,Y(ITA) IOQ3

wall design (5MW1m2)

Engineering Support fortheWPI01l6/04 1.6.1 P service detailed Design ofITER blanket 12 Y,Y(ITA) 10QI

shield and FW anels

WPI 011 6/05 1.6.1 P supplyManufacture of a ITER higher HF

18 Y IOQ3full prototype

Page 13 of 53

Page 14: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/11/2009

WP I0116107 1.6.1 P supplyManufacture of a ITER standardHF full prototype

Page 14 of 53

18 Y IOQ3

Page 15: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

2.4. WBS 1.7 - DlVERTOR

2.4.1. Summary

During 2010, the activities in the divertor area will essentially focus on the Inner VerticalTarget (IVT).

2.4.2. Procurement Arrangements

EUl7 1.7.P2B.EU.OI - Divertor Inner Vertical Target 20.20 Jan.2010

2.4.3. Main Procurements

Two main Calls for Tender will be issued: one for the procurement of the IVT full sizeprototype and one for the procurement of its Carbon Fibre Composite material:

2.4.4. List ofActivities

Complementary activities aiming at increasing competition and decreasing fabrication costs,will include: testing of full Tungsten mock-ups and prototypes, as well as mock-ups madefrom alternative CFC materials and validation of repair techniques on full-scale vertical targetpoloidal units before start of the series production.

WPIOl17102 1.7.2 P supplyManufacturing of Inner Vertical

27 y 1OQ2Target Full Size Prototypes

WPIOl17/01 1.7.1 P supplyManufacture of Carbon Fibre

10 y 10QIComposite prototypical batch

WP09l17/05 1.7.2 P supplyManufacturing of mock ups and

18 y 2009prototypes for the full W divertor

Qualification of repairWPIOl17/03 1.7.2 P service technologies on full size PFC 7 Y IOQ2

com onents

Page 15 of 53

Page 16: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-l2Final 27/1 l/2009

2.5. WBS 2.3 - REMOTE HANDLING (RH)

2.5.1. Summary

In 2010 the various design and R&D activities in the RH field will continue in order toprogress with the conceptual design, the preparation of the functional specifications andinterface requirements, the finalization of the scope of the supply, and the related R&Dactivities; all this in view of the preparation of the still-to-come Procurement Arrangementsfor the four different in-kind RH procurement packages under EU responsibility.

2.5.2. Procurement Arrangements

None in 2010.

2.5.3. List ofActivities

Complementary activities will include system studies and the technological surveys oncomponents (motors, sensors etc.) that are compatible with the ITER environmentalconstraints, in particular gamma radiation and, in case of the in-vessel viewing system, withvacuum, high temperature baking (-240 C) and, if required, high magnetic field (-8T).

• Divertor RH: The activities in 2010 will go on with the completion of what is coveredby the present Grant with TEKES. After this, a new grant will be initiated with stillwith TEKES related to the completion of the conceptual design of the DIV RHdevices and tools, completion of conceptual design for the DTP2 Extension andUpgrade in view of a prototyping and testing phase and continuation of the testcampaigns with the existing DTP2 hardware.

• Transfer Cask System (TCS): Design activities, by signing task orders in the frame ofthe existing engineering support contracts, of a generic cask-pallet system to beintegrated later on with the Air Transfer System layout. A Grant is also planned to besigned in 2010 which beneficiary should play the role of design integrator in supportofF4E, in view of subsequent PA and industrial procurement preparation.

• In Vessel Viewing System (lVVS): Activities related to the execution of further R&Dactivities (further lab tests aiming at increases of the performances of the presentproof-of-principle mock-up) and, design integration activities on the whole IVVS areplanned.

• Neutral Beam RH: A Grant to review, extend and complete the present NB RHconceptual design is planned. Synergies should be established with the NBTF designactivities.

• Radiation Tolerance Programme: The objective is to complete irradiation tests and todefine a common strategy with other F4E groups (e.g. Diagnostics) and ITER on thissubject.

Page 16 of 53

Page 17: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 27/1 112009

WP I0/23/04 2.3.2 GDTP2 E&U Follow-upand DTP2 Operation

28 Y(ITA) TEKES (FI)* 2009

WP09/23/04 2.3.5

WPI0/23/05 2.3

G

G

Gathering ofrequirements for NBIRH, and feedbackto/from NBIdesign.Start ofengineering design ofNBI RHIrradiation ofRHcomponents (motors,sensorsetc.)

25 Y(ITA)

8 Y(ITA)

2009

10QI

WPI0/23/01 2.3.4 G

IVVS DesignFinalisation IncludingSupplementary LabTests

29 Y(ITA) IOQ2

WPI0/23/02 2.3.7 GATS DesignCompletion &TCSInte ration

6 Y(ITA) 10QI

WP I0/23/03 2.3 P service Engineering Support forRH

22 Y(ITA) 10Q3

* Unique experimental facility (according to art.l58.b ofF4E Implementing Rules)

Page 17 of 53

Page 18: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

2.6. WBS 3.1 - VACUUM PUMPING AND FUELLING

2.6.1. Summary

The close and effective collaboration with the 10 in the definition and substantial progress ofall pre-procurement activities in the area of vacuum pumping will continue in 20 I0, withseveral important procurements and grants being signed.

2.6.2. Procurement Arrangements

None in 2010.

2.6.3. List ofActivities

It is intended to sign a new Grant on the finalization of the detailed design of the Cold ValveBoxes (CVB) and Cryojumpers, as well as to initiate a procurement contract on theManufacture of Pre-Production Cryopump (PPC), its test vessel and related activities. Finally,it is also expected to finalize the design of the Heating Neutral Beam (HNB) Cryopumps andits interfaces to the cryopump in the MITICA facility.

With respect to the very important issue of Leak Detection and Localization (LD&L) in theITER machine, grants will be signed to support R&D work that ITER 10 is recommending inorder to define the conceptual design of this system. Different methods will beassessed/tested in order to localize water and/or helium leaks inside the vacuum vessel orcryostat.

WP09/31/01 3.1.1 P serviceDetailed design and specification for

17 Y(ITA) 2009the CYBs and cryojumpers

WPI0/31103 3.1.1 P supply Procurement of Pl'C and test vessel 20 Y(ITA) 10Ql

Optimisation and performance studiesfor leak detection system including

WP09/31104 3.1.3 G proof-of-principle tests.Review of 37 Y(lTA) 2009leak localization concepts and theirpossible realization

WPI0/31101 3.1.1 P serviceFollow up of procurement ofPPC and

20 Y(ITA) 10QItest vessel

R&D in support of Conceptual designWPI0/31/02 3.1.3 G of leak detection system and Leak 29 Y(lTA) 10Ql

Localisation systems

Page 18 of 53

Page 19: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

2.7. WBS 3.2 - TRITIUM PLANT

2.7.1. Summary

Activities to support ITER 10 in the preparation of the Procurement Agreements (PAs) forIsotope Separation System (ISS) and Water Detritiation System (WDS), the two EU in-kindcontributions to the ITER Tritium Plant, will continue.

2.7.2. Procurement Arrangements

EU32 WDS part I - Tritiated water holding tanks (storage 4.78and emergency)

1un2010

2.7.3. List ofActivities

R&D work for specific issues (development of large size and tntium compatibleelectrolysers, their demonstration, etc.) as well as detailed designs will be carried out.

In particular, the contract for the detailed design for the tritiated water holding tanks of theWDS (2 large emergency tanks - 300 m3 - and other smaller holding tanks - <20 m3) will besigned.

R&D in support of conceptualWP09132/01 3.2 G design for WDS and detail design 26 Y(lTA) 2009

of the tanks

Preparation oftender specs for

WP09132/04 3.2 GWDS Tanks and follow up of

4 Y(ITA) 2009production of drawings formanufacturin

WP10/32/04 3.2 P service Conceptual and detailed design of6 Y,Y(ITA) 2009WDS

WPIO/32/06 3.2 P service Conceptual and Detailed design of22 Y(lTA) IOQ1

ISS

Page 19 of 53

Page 20: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/l 1/2009

2.8. WBS 3.4 - CRYOPLANT

2.8.1. Summary

The activities to be signed for the cryoplant in 2010 will focus on finalising the engineeringdesign requirements (engineering support contracts), reviewing functional specifications andmitigating the main technical risks in the procurement (R&D on compressor technology).

2.8.2. Procurement Arrangements

EU34 LN2, 80 K Loop and Ancillary Equipment 30.12 Dec 2010

2.8.3. List ofActivities

WPIO/34/02 3.4 GCryoplant Procurement 5 y 10Q2Pre aration

WP09134/02 3.4 P service Engineering Support to10 y IOQ1

ct' 0 lant

WP09/34/03 3.4 P service Optimization of16 y 10Q4

Cr 0 Iant Desi n

WPI 0/34/0 I 3.4 P service R&D on compressor8 y 10Q1

technology

Page 20 of 53

Page 21: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-l2Final 27/11/2009

2.9. WBS 4.1 and 4.3 - POWER SUPPLIES

2.9.1. Summary

Activities will be focusing on the preparation for the procurement of the Pulsed Powerelectrical network and the Steady State electrical network including: detailed design of ITERelectrical distribution system, and qualification of components with respect of operationunder magnetic field.

2.9.2. Procurement Arrangements

EU41, EU43 4.I.PIA-P8B.EU.OI - Detailed design of the SSEN 7.00and PPEN

Oct 2009

EU41, EU43 Assembly of the SSEN and PPEN, and SSEN cables 13.30 Apr 2010

2.9.3. List ofActivities

WPlO/43/01 4.3

WPIO/43/02 4.3

P service

G

Engineering support toower su lies

Technical specs of thequalification contract

Page 21 of 53

12 Y

5 Y(lTA)

IOQ2

IOQ2

Page 22: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27111/2009

2.10. WBS 4.5 - CODAC

2.10.1. Summary

The CODAC system, up to the local controllers, will be developed by ITER using Fund, withthe help of the Domestic Agencies and with direct help from industry. Fusion for Energy rolewill be to manage the instrumentation and control functions contained in the procurementarrangements.

2.10.2. Procurement Arrangements

Not applicable.

2.10.3. List ofActivities

A service contract related to Instrumentation and Control (I&C) for systems procured by F4Ewill be signed in 2010. This service contract will produce the design of I&C systemsaccording to 10 CODAC standards and support F4E suppliers in the procurement of I&Chardware. A smaller contract will be signed in order to prepare a resource loaded schedule forI&C and to support F4E with the technical specification of the service contract.

WPIO/45104 4.5 P serviceReview oflTER I&C

3 N 2009s ecifications

Support on I&C design andWPIO/45103 4.5 P service implementation in the frame of 12 Y lOQ2

EUPAs

Page 22 of 53

Page 23: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/1 1/2009

2.11. WBS 5.1.1 - ION CYCLOTRON H&CD ANTENNA

2.11.1. Summary

The IC Antenna procurement type is Build-to-Print, with 100% EU sharing. Criticalprocurement contracts will be signed in 2010, specifically for the RF vacuum windows andFaraday screens bars.

2.11.2. Procurement Arrangements

None in 2010.

2.11.3. List ofActivities

WPIO/51101 5.1

WP09/51103 5.1

P supply

P supply

Faraday Screen R&D

RF VacuumWindowsR&F

Page 23 of 53

20 Y(ITA)

27 Y(lTA)

IOQ2

2009

Page 24: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final27I11/2009

2.12. WBS 5.2 - ELECTRON CYCLOTRON

WBS 5.2.1B -ELECTRON CYCLOTRON UPPER LAUNCHER

2.12.1. Summary

In 2010 all the major prototype contracts will be signed, in support of the design and forcompletion before the PAs for the system are signed. The design work will be orientedtowards the production of a final detailed design. In addition, support will be provided to the[0 on some critical issues on the area of ECH, such as performance analysis update, commoncomponent strategy (with JADA), and general integration of the Electron Cyclotron H&CDin the ITER system.

2.12.2. Procurement Arrangements

None in 20 10.

2.12.3. List ofActivities

WP09l52/07 5.2.1 GDetailed design, analysis,

18 Y(lTA) 2009testing and documentation

WP09/52/08 5.2.1 P service Engineering activities in22 Y(lTA) 10QI

support of EC Upper Launcher

WP09/52/09 5.2.1 P supply EC UL prototypes 40 Y(lTA) 2009

WBS 5.2.3 ELECTRON CYCLOTRON POWER SOURCES AND WBS 5.2.4 EC POWERSUPPLIES

2.12.4. Summary

The development of the European gyrotron for ITER will continue signing the grant for thetest of the first gyrotron prototype which refurbishment, performed on the basis of the resultsof the first test campaign, will be completed by industry in summer 20 IO. The tests on therefurbished 2 MW gyrotron prototype will yield essential experimental results for thedecision on the future European development programme in this area. In addition, supportwill be provided to 10 on some critical issues on the area of ECH, e.g. space allocation in theRF building, preparation of specification for the PA for the gyrotrons and the EC PowerSupplies.

2.12.5. Procurement Arrangements

None in 2010.

Page 24 of 53

Page 25: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

2.12.6. List ofActivities

F4E(09)-GB12-12Final 27/11/2009

WP09/52/02 5.2.4 P serviceEngineering SUPPOlt

12 Y IOQ3to EC PS

WP09/52/03 5.2.4 GSupport to ITER

16 Y(ITA) 2009Or anizationTests with the

WP09/52/05 5.2.3 Grefurbished 2MW

4 Y CRPP (CH)* 20091st prototype

rotron

WP 10/52/03 5.2.3 P supply Mirrors for RFCU 5 Y 2009

* Unique experimental facility (according to art.158.b ofF4E Implementing Rules)

Page 25 of 53

Page 26: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27111/2009

2.13. WBS 5.3 - NEUTRAL BEAM SYSTEM

2.13.1. Summary

The substantial support provided by Europe to 10 for the development of the NB system willcontinue in 2010. Several procurement contracts related to the Test Facility will be initiatedand signed (cooling and cryo-systems, beam source etc.). The implementation of the PA onthe NB Power Supply, signed in 2009, will enter in its most active phase with the signature ofthe first procurement contracts.

2.13.2. Procurement Arrangements

The second PA in the table below is not included in the PAs already foreseen in the agreedsharing among ITER Parties. The signature of this PA is therefore conditional on the positivedecision of the ITER Council to include the NBTF into the ITER baseline and on thesubsequent agreement by the EU that this facility will be subject of an in-kind procurement ofthe EU.

EU53

EU53

5.3.P6.EU.OI - Procurement of NB power supplies 19.52and related systems

The full size ITER injector Ion Source Test Facility TBD**and MV Test Facility (SPlDER/PRIMAIMITICA)*

lui 2009

lun 2010

* Depending upon NBTF approval process.

** The credit allocated for the NB test Facility is 60 kIUA. Additionally 8.8 klUA from the 10 R&DFund have already been agreed by the IC. The sharing amongst DAs is not yet defined.

2.13.3. List ofActivities

:. ., '

1 ", -'tie \"1 - ,

n~~~~IType" -';::..-- ':- , .. .

Infrastructures of theWPIO/53/09 5.3 P supply neutral beam test 49 Y 10QI

facility -Cooling system

WPIO/531l0 5.3 P supplyIon Source Test Facility

21 Y 10QI- Ion Source

WPIO/531l1 5.3 P supplyIon Source Test Facility

16 Y IOQI- Vessel

Ion source test facility

WP09/53/06 5.3 P supply(power supplies - HVD

24 Y 2009and TX Line)

WPIO/531l2 5.3 GR&D on very high

24 Y(ITA) CEA (FR)*voltage insulation IOQ2

Page 26 of 53

Page 27: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB J2-12Final 27/1112009

Infrastructures of the

WPIO/53/02 5.3 P supplyneutral beam test

9 Y lOQIfacility -High VoltageDeck and Bushing

Protoypes for the

WPlO/53/04 5.3 P supplyfinalisation of the Bvto-

8 Y(lTA) IOQIP specifications inNBarea

WPIO/53/05 5.3 P service Engineering support in15 Y IOQlthe NB area

Vacuum and GasWPIO/53/07 5.3 P supply Injection Plants for 52 Y IOQI

PRIMA

WPlO/53/08 5.3 P supplySPIDER Control &

25 Y IOQ2DAQ

* Unique technical competence (according to Oit.158.c of F4E Implementing Rules)

Page 27 of 53

Page 28: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

2.14. WBSS.S - DIAGNOSTICS

2.14.1. Summary

Contracts to be signed within this work programme will focus on developing system-leveldesigns for the main diagnostics; completing R&D on the critical path for each system; andadvancing designs of principal sub-assemblies.

2.14.2. Procurement Arrangements

2.14.3. List ofActivities

Systems required for ITER first plasma will see the design of key components progressedbeyond Preliminary Design Review level. To facilitate the R&D activities, frameworks willbe established for the conduct of necessary irradiation testing and for the procurement ofsupplies and analytical support, including fabrication of prototypes and provision of testequipment. An independent activity will be initiated to undertake the design integration ofdiagnostic systems in ports under EU responsibility, including port plug design and/orcustomisation and integration in the ports of systems to be provided by other DomesticAgencies.

Concerns over the lifetime of optical assemblies close to the plasma, which is an issuecommon to several diagnostics, will be addressed through specific R&D aimed at identifyingdesign opportunities and providing generic design guidelines. Finally, an activity will beinitiated to provide diagnostic-specific technical support for F4E in its negotiations withITER 10 of the Diagnostic Procurement Arrangements, which are due to be signed in 2010and 2011.

Activities will focus on completion of the designs for the diagnostics and associated portplugs in the nine diagnostic procurement packages for which the EU is responsible, to thelevel appropriate for a conceptual design review. In a few cases the design may be advancedto a more detailed level. The activities will include design and engineering studies; system­level optimisation to meet measurement requirements to be agreed with ITER 10; prototypingand testing of relevant components; and assessment of the Procurement Arrangementtechnical specifications.

WP09/55/02 5.5

WPI 0/55/10 5.5

G

G

Complete Design of in-vesselDiagnostics to ConceptualDesign Review level

Complete Design of port plug­based Diagnostics to ConceptualDesign Review level

Page 28 of 53

24 Y,Y(ITA) 2009

24 Y(ITA) 10QI

Page 29: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/11/2009

WPIO/55/11 5.5 P service Engineering SUPPOlt for18 Y 10QIdiagnostic integration

Irradiation and post-irradiationWPIO/55112 5.5 G testingof diagnostic components 24 Y 10QI

and assemblies

WPI 0/55113 5.5 GPort plug design, testing and

24 Y 10QIdiagnostic integration

WPIO/551l4 5.5 P supplySupplies and Support for Design

61 Y,Y(lTA) 10QIof Diagnostics andPort Plugs

Support for Finalization ofWP09/55123 5.5 G Technical Specificationsfor 24 Y 2009

Port-based Diagnostics

WPIO/55/09 5.5 GR&D/Design of IVS Joints,

34 Y 10QIFeedthroughs and Connectors

Page 29 of 53

Page 30: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 27/11/2009

2.15. WBS 6.1 - SITE and WBS 6.2 - BUILDINGS

2.15.1. Summary

During 2010 the Architect Engineer will develop the design of the buildings from theconceptual design to a design stage detailed enough to allow the issueing of the call for tenderfor the construction of the civil engineering of the Tokamak complex.

Work programme 2010 activities will prepare the site and the Tokamak pit to allow thebeginning of the Tokamak complex civil engineering construction in 20 II.

2.15.2. Procurement Arrangements

EU62 6.2.P2.EU.OI - PF Coil Fabrication Building (B55) 12.80 Nov 2008

EU62 6.2.P2.EU.04 - Tokamak Complex Anti-Seismic 6.20 May 2009Bearings Supply

EU62 6.2.P2.EU.03 - Tokamak Excavation & Support 31.00 May 2009Structure

EU62 6.2.P2.EU.02 - Architectural and Engineering 54.70 May 2009Services

EU62 Construction of all buildings 273.20 Jan 2010

2.15.3. List ofActivities

WP09/62/03 6.2 GSUPPOIt Study for Accidental

12 N 10QIScenarios

WP I0/62/03 6.2 P supplyAnti-Seismic Bearings

25 Y 2009Fabrication

WP09/62/07 6.2 P worksTokamak Complex Foundations

12 Y IOQI(phase 2)

WP09/62/11 6.2 P service Global construction insurance 12 Y 2009

Analysis, design optimization andWPIO/62/01 6.1&6.2 P service cost reduction strategies for the 12 Y,Y(lTA) 10QI

ITER building structures

WP I0/62/02 6.2 P service Mandatory and complementary73 Y 2009building insurance

Page 30 of 53

Page 31: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/1112009

2.16. MATERIALS DEVELOPMENT

Material development focuses on the further optimization and validation of materialsforeseen for ITER TBM modules, in particular on EUROFER, the structural material for theEU reference concepts, and on EUROFER ODS as well as SiC/SiC composites for thermaland electrical insulation (SiC-Dual), both, for dual coolant options that could be tested at alater stage or in collaboration with partners.

Activities foreseen in 2010 are in particular on characterization of EUROFER base material(new heat EUROFER-97/3 fabricated in 2009) and various joints needed in the TBM project(different weld processes, diffusion bonding, solid HIP & different weld-geometries). Theactivities are complemented by further development on missing design rules including areview by industry, maintenance of the data base and R&D on improvement of the materials.

The SiC-Dual material fabricated by industry shall be characterized and screened by a lowdose irradiation campaign.

Furthermore, F4E will continue to develop EUROFER-ODS material. The next steps includefurther optimization of properties, in particular of the fabrication process, preparation forfabrication at industrial level and multi-ion-beam irradiation.

WPIO/MD/OI GCharacterization and validation of EUROFER and

24 N 2009EUROFER welds for TBM use.

WP09/MD/02 G Design rules for EUROFER (Creep-fatigue) 18 N 2009

WPIO/MD/03 GDevelopment of SiC-SiC composites (hasic

36 N lOQIcharacterisation and irradiation campaigns)

WPIO/MD/02 GDevelopment of SiC-SiC composites

12 N IOQ1(characterisation of physical properties)

Development: EUROFER and EUROFER ODS

WPIO/MD/04 G[Optimisation of properties and processes]

24 N 10Q1EUROFER ODS [Ion Beam and n-Irradiationcampaigns]

WP10/MD/05 GDevelopment: EUROFER ODS [Optimisation of

18 N 10Q1properties and processes]

WPI0/MD/08 GEUROFER hase materials&wclding for TBM use:Irradiation campaigns. Characterisation andvalidation

Page 31 of 53

39 N 2009

Page 32: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 27111/2009

EUROFER Qualification of welds for TBM(second batch of material produced with mock-up

WP09/MD/08 G fabrication). Irradiation campaigns forqualification 36 N 10QIof welds for TBM (second batch of materialproduced with mock-up fabrication)

WPIO/MD/06 G EUROFER Data base and design rules 30 N 10QI

WP09/MDII0 P serviceEUROFER TBM design rules: for EUROFER

18 N 2009welds. Rules for welds

WPIO/MD/07 P serviceEUROFER TBM design rules: High Temperature

18 N 2009rules

WP09/MDI12 GQualification of EUROFER for TBM

12 N 2008(Maintenance of data base)

Page 32 of 53

Page 33: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/1112009

2.17. TEST BLANKET MODULES

The Test Blanket Modules (TBM) will be unique components in ITER as they use the ITERmachine as a test facility and are the only components to be installed in ITER which are notpart of the EU in-kind commitment.

The activities on the TBMs to be signed in 20 I0 include the following:

• Continuation of the conceptual design (e.g. TBM re-design in case of limitation on the

amount of ferromagnetic materials in ITER, further validation / optimization of He

flow in manifolds at the back of the TBMs, etc.)

• Definition of fabrication procedures on the basis of nuclear standards, the fabrication

of subcomponents test mock-ups and the transfer to Industry have been initiated in the

work program 2009 and will continue in 2010 in the field of assembly of

subcomponents by welding to form the TBM box structure

• Integration of TBM Systems into the ITER machine

• Development of materials database and computer codes for TBM safety analyses

Development andsupply of qualified

WP09/56/02 5.6 P service TBM box fabrication 22 N 2009proceduress ecifications

WP09/56/03 5.6 P serviceEngineering Support for

10 N 2009PrSRofTBM

WPIO/56/06 5.6 P serviceEngineeringSupport to

20 N 2009TBM

HCLL/HCPB TBMsWP09/56/06 5.6 G Preliminary Safety 10 N 2009

Re ort PrSRCompletion of DB and

WPIO/56/07 5.6 G definition of EN 18 N IOQ2com uted code for TBMTritium Extraction

WP09/56/11 5.6 GSystem (TES) for

12 N ENEA (IT)* 10QIHCLL- TBM: Testcam ai n in TRIEX

WPIO/56/01 5.6 GTBM systems

12 N IOQ2conceptual designWP I0/56/02 5.6 G TBM conceptual design 12 N IOQI

WP I0/56/05 5.6 P service TBM fabrication12 N IOQI

ualification

* Unique experimental facility (according to art.l Sx.b ofF4E Implementing Rules)

Page 33 of 53

Page 34: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

2.18. PLASMA ENGINEERING

Plasma engineering will continue providing support to ITER-I0 for the design andpreparation for operation of the ITER machine. The 20 I0 activities range from optimizationof plasma scenarios and systems to the evaluation of the impact of design changes on themachine performance and operation.

These activities are in large part, funded by means of competed ITAs which are published byITER-I0 as open calls to all the DAs and assigned on the basis of the DAs replies.

In 2010, ITAs on the following general areas are expected:

• Plasma Operation & Control;

• Plasma wall interaction and runaway modelling;

• Development of analysis tools.

_(f;!i'F33!!§;(fi3;il.t.'llt//X"Y;if~i~{!lltt.'t"( r;)/..;?/0»"'0,.,n ,: V';(:';ill+;H3)!!,,; iJW$~;/>;:x,. 'S'/ff;;!/!;;? »? ?ii+i iJ/JJ/S~MJJ;i

WP I0/PE123 G Run-away electrons characterization 12 Y(ITA) IOQ2and control

WPI0/PE/01 GEdge modelling coordination and

12 Y(lTA) IOQ2simulations (incl dust)

WPI0/PE/02 P service SOLPS code development 12 Y(lTA) 10QI

WPIO/PE/03 GEvaluation of 3D magnetic field in

24 Y(ITA) IOQ2ITER

Plasma control (incl extended RT),WPIO/PE/04 G control systemdesign, simulation 18 Y(lTA) IOQ3

and VDE analysis

Development of run-away (RE)WPIO/PE/05 G code for ITER and simulation of RE 12 Y(lTA) IOQ2

(damage) in ITER

WPIO/PE/06 GMHD stability and pedestal -

18 Y(lTA) IOQ3including controlled ELM regimes

WPI0/PE/07 GEngineering models for plasma

12 Y(lTA) IOQ2feedback control.

WPI0/PE/08 GConceptual design of plasma

12 Y(lTA) IOQ2control and protection system

WPIO/PE/09 GStudy of a pulse sequenee simulator

12 Y(lTA) IOQ3for tokamak.

WP10/PEIl0 P serviceEngineering support and analysis

18 Y,Y(lTA) IOQ2for PE

WPIO/PEIlI GITER scenario and plasma

12 Y(ITA) IOQ3perfomance analysis

WPI0/PEIl2 GPlasma control developement &

12 Y(ITA) IOQ3integration

WPIO/PEIl3 P service Eng Support and analysis 18 Y(ITA) IOQ3TF and TBM ripple analysis for

WPI0/PEIl4 G ITER 24 N 10QI

Page 34 of 53

Page 35: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 27/11/2009

WP10/PEI15 G Study of plasma start up 12 Y(ITA) 2009

WP10/PEI16 GThe study of control of plasma

12 Y(ITA) 2009current, position and shape

WPI0/PEI17 GSelf-consistentsimulations of

12 Y(lTA) 2009plasma scenarios

WP10/PEI18 GMagnetic reconstruction of the

12 Y(lTA) 10Q1plasma boundary

WP10/PEI19 GAnalysis of Resistive Wall Mode

12 Y(lTA) 10Q1control by in-vessel (RMP) coils

Self-consistent TransportWPIO/PE/20 G Simulations of Plasma Scenarios 12 Y(ITA) 10Q1

with Fixed-Boundary Equilibria

Edge magnetic field structure for

WP10/PE/21 GELM control in ITER and

12 Y(lTA) 2009associated power/particle fluxes toplasma-facing components

WP10/PE/22 GRippleanalysis andcharacterization

24 Y,Y(lTA) 2009of effects in ITER

* Unique technical competence (according to ar1.158.c ofF4E Implementing Rules)

Page 35 of 53

Page 36: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/11/2009

2.19. SAFETY

Activities will focus on the support of the ITER licensing process, by performing relatedsafety studies and R&D, and to support EU-PA activities by giving on request safety relatedadvice.

To control the dust and tritium inventories inside the vacuum vessel, techniques for theirquantification, monitoring and removal are investigated. Supporting safety analyses willinclude calculations for accident sequences and application of ALARA to occupationalradiation exposure for inspection, maintenance and repair activities inside the cryostat and forcoil and power supply distribution systems.

Radiological and Environmental Monitoring System

A first activity in this area aims at the development of specific monitoring devices for redzones highly tritiated and irradiated and containing activated Beryllium dust.

Radwaste Treatment and Storage

Concerning storage and disposal of radioactive and tritiated wastes, R&D activities areplanned to limit and/or control the tritium out-gassing from the waste packages, to measuretheir tritium content and to decontaminate tools from the hot cell facility.

11I1!~I!i'li;;;

YAP 111111IJJIII~I;;ff'/iidGjj0;\JIJillllli 11- Y'KKcc; iNY ,;§;;'t~·W;fj;Ugg~5i UJJ,c'iC'/;;;iV'i;iiJ) iVY

WPIO/SF/05 GBusbar arcmodel validation and supporting

18 Y(lTA) 10QIexperiments

WPIO/SF/06 GCombined H2/Dustexplosion computer

45 Y(ITA) 2009code development

Invessel dustmeasurement and removalWP09/SF/04 G techniques assessment andvalidation R 18 Y(lTA) 2009

diagnostics

WPIO/SFI07 GMetal Waste Detritiation, T outgassingand

42 Y(lTA) IOQ2measurement, and Be Waste Management

Supporting safety analysis to follow upWP09/SF/06 G ITER design evaluation and licensing 24 Y(ITA) 10Q2

process

WP09/SF/07 P serviceSupport to ORE and Safety analysis in

12 Y(ITA) 10Q2support of ITER licensing

Supporting safety analyses to follow upWPIO/SF/08 P service ITERdesign evolutionand licensing 12 Y(ITA) 10QI

process

The ALARA application to OccupationalWP09/SFIlI G Radiation Exposure based on ITER design 12 Y(ITA) IOQ2

evolution

The ALARA application to OccupationalWPIO/SF/09 P service Radiation Exposure based on ITER design 12 Y(lTA) IOQ3

evolution

Page 36 of 53

Page 37: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

P serviceP service

WPIO/SF/04 G

Waste Management SupportMonitoring Devices forRedZonesIn vessel tritium inventory control by laserspectroscopy

Page 37 of 53

24

F4E(09)-GB12-12Final 2711112009

IOQ2

Page 38: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-01312-12Final 27111/2009

2.20. ENGINEERING SUPPORT

Activities listed here are in addition to the ones indicated in each of the previous areas andfocus upon Engineering Analyses, Code and Standards and foresees new step of contracts insupport of the design of components and systems and their cost optimization. The Codes andStandards activity in 20 lOis devoted to the tracking of international codes for analyses anddesign of mechanical and electrical systems, assess and follow up of notified body, inspectionentities, etc.

Most of the engineering support activities will be implemented through specific contracts tobe signed within existing Framework Contracts.

,.C. ~I A.<tivityTitievC ~::,~;

-

rame I"."" r.1I

WP09/ES/02 G Electromagnetic analyses 12 Y,Y(ITA) 2009WP09lES/04 G Mechanical analyses 12 Y,Y(ITA) 2009WP09/ES/07 P service Thermo-hydraulic analyses 12 Y,Y(1TA) ]OQ2WP09/ES/08 G Thermo-hydraulic modeling 12 Y,Y(ITA) 10QIWP]O/ES/OI P service Electromagnetic analyses 12 Y,Y(1TA) 10QIWPIO/ES/02 P service Neutronic analyses 12 Y,Y(ITA) ]OQIWPIO/ES/03 P service Mechanical analyses ]2 Y,Y(ITA) 10QI

WPIO/MFI02 P serviceMaterial characterization at

12 Y,Y(1TA) ]OQ2room/elevated temperatures

WPIO/MF/03 P serviceMaterial characterization at cryogenic

12 Y,Y(ITA) IOQ2temperatures

WP]0/MF/04 P service Support for the quality control of12 Y,Y(1TA) IOQ2

components

WP]0/MF/05 P service Joining technologies and qualification 12 Y,Y(ITA) IOQ2

WPIO/ES/08 P serviceSupport on Codes & Standards and

12 N IOQ2reviewof Structural Design Criteria

WPI O/MF/O1 GCorrosion Assessment for water cooled

12 Y(1TA) IOQ2components

Page 38 of 53

Page 39: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27III 12009

2.21. NUCLEAR DATA

This mid term activity for 20 I0 focuses on the development of tools, improvements andupdate of Nuclear Data files mainly in support of TBM and Broader Approach (lFMIF)activities. In addition nuclear data experiments for validation have to be pursued andmeasurement techniques still developed.

WP09IND/OI GDevelopment of tools, improvements of data 24 N lOQIandvalidation in support ofTBM activities

WPIOIND/OI GNuclearData improvements and 24 N IOQIdevelopment of tools

Page 39 of 53

Page 40: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/11/2009

2.22. ACTIVITIES OF QUALITY ASSURANCE (QA) AND PROJECTMANAGEMENT

A follow-up of activities at the supplier's premises is necessary to assure the correctexecution of the contracts in compliance with the technical and management specificationsand the contractual Quality Plans. Assistance to F4E is also requested to prepare suchactivities, including assessment and risk management for the procurements and advise in thedefinition of the inspection procedures.This follow-up is achieved by sending qualified Inspectors from verifying bodies to thesuppliers' premises (and their subcontractors) to follow and verify the progress of work onF4E's behalf. The inspectors shall be the witnesses of F4E for the correct execution of themanufacturing sequences, manufacturing procedures, test methods, test performance and testreports during the production of the services and components. They shall report on Quality,Production and Schedule to the F4E Technical Responsible Officer defined in the relevantcontract.For a proper preparation of the inspection procedures to be included into the manufacturingcontracts and in order to be ready for the time when manufacture will start, a frameworkcontract is planned to be signed in 2010.

Contracts supporting F4E on project management matters are also planned to be signed in2010. Professional support (1-2 ppy) on this topic from an engineering company is requiredfor specific tasks such as consultancy for the preparation of technical/managementspecifications and cost/risk estimates, in the definition of internal processes and in themanagement of the documentation.

WPIO/POI08 P service

WP09/POIO 1 P service

SUPPOIt of Project Management

Service of inspectors for ITER projectcontracts follow-up

Page 40 of 53

5 N

12 Y

10Ql

2009

Page 41: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-l2Final 27/l 1/2009

2.23. CONTRIBUTIONS IN CASH

2.23.1. Contribution to CEAfor ITER Site Support

F4E shall contribute through CEA/AIF to certain ITER expenditures, in some cases byreimbursing CEAIAIF of costs incurred to provide site support to the ITER Organization, inaccordance with the Annex on Site Support attached to the ITER Agreement. The site supportactivities to be financed by F4E in 2010 shall include fees to be paid to CEA for the use ofsome of the existing temporary buildings by the ITER Organization in accordance with thearrangement signed between CEA, the Commission and Fusion for Energy in 2009.

2.23.2. Contribution to the ITER Organization

This corresponds to the annual EU share of the 20 II contributions in cash to the ITEROrganisation for its management, to be adopted during the next ITER Council.

2.23.3. Contribution to Japan

This cash contribution to Japan corresponds to the transfer of procurement responsibilityfrom EURATOM to Japan under the supervision of the ITER Organisation.

2.24. EXPERTS FOR TECHNICAL ASSISTANCE TO F4E

F4E has issued a call for expressions of interest for individual experts to provide technicalassistance in a number of specific areas related to ITER and the Broader Approach. Provisionis included here for a total number of approximately 2800 days for experts in 2010.

2.25. URGENT ACTIVITIES IN SUPPORT OF COST AND RISK ASSESSMENT

Some activities (corresponding to a total of about 5 man-years) may be necessary to becarried out in the estimation of costs and in the assessment of risk during the course of theyear. Such activities could be both grants and procurements under the 3.1 or 3.2 budget line.

WPI O/PO/OI P serviceUrgent Activities in support of cost

5 Y,Y(ITA) IOQIand risk assessment

WPlO/PO/03 P serviceUrgent Activities in support of cost

5 N IOQIand risk assessment

WPIO/PO/04 GUrgent Activities in support of cost

5 Y,Y(ITA) IOQIand risk assessment

WPIO/PO/06 GUrgent Activities in support of cost

5 N lOQIand risk assessment

Page 41 of 53

Page 42: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 2711112009

PART III - BROADER ApPROACH

3.1. INTRODUCTION

The European contributions to the Broader Approach Activities are financed to a large extentby contributions in kind from the following Members of F4E: France, Germany, Italy, Spain,Switzerland and Belgium. Only in limited number of cases, where no contribution by theseMembers is foreseen, the contribution will have to be financed by the F4E budget.

For the contributions to be provided by Members of F4E, Procurement Arrangements will beconcluded in late 2009 and 2010 between F4E and the Japanese Implementing Agency,subject to the conclusion of corresponding Agreements of Collaboration between F4E and theMembers concerned. The list of procurement arrangements planned and the status ofimplementation is reported below and in the Project Plan.

In the following the activities of Fusion for Energy related to BA are described. The tablesprovided in the text use the following abbreviations:

I . IWI' ref. Work programme reference, univocally identifying

WI' items.WPxx/yy/zz, where xx arc the last two digits of the year in which WP/budgctthe activity was first financed, yy is a code identifying the ITER WBS clement(if available) or the F4E service in charge, zz is a sequential number for theyear.

G Grant

I' Procurement

All activities indicated within WP20 I 0 are planned to be committed under the 2010 budget.

During the implementation of the work programme activities, F4E may group more activitiesin a single call, or split one activity in more calls. This will in any case be performedpreserving the scope and objective presented in WP201O.

The foreseen time of publication of calls and invitations is indicative only, and based on thepresent understanding of the project development.

3.2. JT60SA

3.2.1. F4E Funded Activities

For JT60SA, direct procurement activities in 2010 will be limited to support the TFConductor procurement under the responsibility of F4E which was issued in 2009, and arclisted in the table below.

In addition F4E will conclude Procurement Arrangements with JAEA, backed bycorresponding Agreements of Collaboration.

Page 42 of 53

Page 43: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/1 112009

I wrref.'e"vi.." 'of. I I Call •Type'

WPIO/BA/02 P SULTAN production sample manufactureIOQ3

and tests

WPIO/BAl03 P Strand qualification phase tests 2009

WPIO/BAl04 P Strand production control tests 2009

WPIO/BA/05 P SC dummy conductor manufacturing 10QI

3.2.2. Procurement Arrangements

In accordance with the EU Project Execution Plan for the JT-60SA project, the followingProcurement Arrangements are expected to be signed between F4E and JAEA forcomponents under the responsibility of the EU.

• Cryostat Body (2010 Q2). This will cover the supply of the cylindrical part of thecryostat. This supply will be covered by an AoC with CIEMAT (Spain).

• Power Supplies (2010 Q2). This PA will cover the supply of the power supplies for allsuperconducting magnets as well as for the in-vessel coils. This supply will becovered by AoCs with ENEA (Italy) and CEA (France).

• ECH Power Supplies (20 I0 Q2). This PA will cover the supply of 2 EC Gyrotronspower supplies. This supply will be covered by an AoCs with CRPP (Switzerland).

• Cryogenic System (20 I0 Q2). This PA will be for the supply of the entire cryogenicsystem for the magnet. This supply will be covered by an AoCs with CEA (France).

• Sector Coils power supplies (2010 Q2). This PA will cover the supply of the powersupplies for the sector coils. This supply will be covered by an AoCs with CNR-RFX(Italy).

3.3. IFMIF

3.3.1. F4E Funded Activities

In terms of direct contributions from F4E, as part of F4E contributions to the IFMIF/EVEDABA Project, "cash contributions to the common expenses of the Project Team" are to beforeseen in the 20 I0 budget for an expected total of 260 k€, this budget will cover themissions outside Japan of the EU members of the Project Team.

In addition F4E will conclude a Procurement Arrangements with JAEA, backed bycorresponding Agreements of Collaboration.

3.3.2. Procurement arrangements

Most procurement arrangements for IFMIF/EVEDA are planned to be signed in late 2009.Only a remaining PA for diagnostics is expected for 20 I0 (Q3) to be backed by anAgreement of Collaboration with CEA (France).

Page 43 of 53

Page 44: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27111/2009

3.4. IFERC

3.4.1. F4E Funded Activities

No activities for the IFERC projects are foreseen to be directly funded by F4E in 2010.

3.4.2. Procurement Arrangements

The main procurement arrangement for the IFERC project, for the supply and maintenance ofthe Supercomputer for the CSC Subproject, is planned to be signed in the second quarter of2010. This PA will be backed by a corresponding Agreement of Collaboration with CEA(France).

Page 44 of 53

Page 45: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

ApPENDIX I -

TABLE OF ACRONYMS AND ABBREVIAnONS

F4E(09)-GBI2-12Final 27/11/2009

AlE Architect Engineer

AGPS Accelerator Power Supplies

ALARA As Low As Reasonably Achievable

ANB Authorized Notification Body

ANS Analytical System

AVDEs Asymmetric Vertical Displacement Event

ATS Air Transfer System

BSM Blanket Shield Module

BTP Build-to-Print

C&I Control and instrumentation

CFC Carbon Fibre Composites

CMM Cassette Multifunctional Mover

CVB Cold Valve Boxes

CVD Chemical Vapour Deposition

CXRS CorePlasma Charge-Exchange Recombination Spectroscopy System

DA Domestic Agency

DACS Data Acquisition and Control System

DCLL Dual Coolant Lithium Lead

DCR Design Change Request

DEMO Demonstration Fusion Reactors

DGEBF Di-Glycidyl Ether ofBisphenol F (impregnation resin)

DlV Divertor

DNB Diagnostic neutral beam

DTP Divertor Test Platform

EAF European Activation File

EB Electron Beam

EBBTF European Breeding Blanket Test Facilities

EC Electron Cyclotron

ECUL Electron Cyclotron Upper Launchers

ECH Electron Cyclotron Heating

EFDA European Fusion Development Agreement

EFF European Fusion File

ELM Edge Localized Mode

EPC Engineering Procurement Contract

F4E Fusion for Energy

FS Functional Specification

FW First Wall

FWP First Wall Panel

HAZOP Hazard Operability studies

HCLL Helium-Cooled Lithium-Lead

Page 45 of 53

Page 46: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 27/1 1/2009

HCPB Helium Cooled Pebble Bed

H&CD Heating & Current Drive

HIP Hot Iso-staticPressing

HNB Heating Neutral Beam

HV High Voltage

HVAC Heating Ventilation &Air Conditioning

HVD High Voltage Deck

HW Hardware

IC Ion Cyclotron

I&C Instrumentation and Control

ICH Ion Cyclotron Heating

IFMIF International Fusion Materials Irradiation Facility

INB Installation Nucleaire de Base

10 ITER Organization

IR Infra Red

ISEPS Ion Sourceand Extraction PowerSupplies

ISS Isotope separation system

ITA ITER Task Agreement

IVT Inner Vertical Target

IVVS In-Vessel Viewing System

LD&L Leak Detectionand Localization

LFS-CTS Low Field Side - Collective Thomson Scattering

MAR Materials Assessment Report

MDR Modified Design Reference

MHB Material Handbook

MHD Magneto-Hydro-Dynamic

MIG Metal Inert Gas

MV Medium Voltage

NB Neutral Beam

NBI Neutral Beam Injector

NBPS Neutral Beam Power System

NBTF Neutral Beam Test Facility

ODS Oxide Dispersion Strengthened

ORE Occupational Radiation Exposure

P&ID Process and Instrumentation Diagram

PA Procurement Arrangement

PF Poloidal Field

PFC PlasmaFacing Components

PFD Process Flow Diagram

PIE Post Irradiation Examination

PMU Prototypical Mock-Up

PP Procurement Package

PPC Pre-Production Cryopump

Page 46 of 53

Page 47: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 271lJ/2009

PrSR Preliminary Safety Report

PTC Prototype Torus cryopump

IOQ(I,2,3,4) Quarter 1,2,3,42010

QA Quality Assurance

R&D Reasearch & Development

RAFM Reduced Activation Ferritic Martensitic

RF Radio Frequency

RFCU Radio Frequency Control Unit

RH Remote Handling

RMP Resonant Magnetic Perturbation

RNC Radial Neutron Camera

RWM Resistive Wall Mode Control

SDC ITER SDC (Structural Design Criteria/Code)

SHPC Safety and Health Protection Coordination

SiC-Dual SiC/SiC compositematerial forelectrical andthermal Insulation

SS Steady State

SW Software

TBM Test Blanket Module

TCS Transfer cask System

TES Test Extraction System

TF Toroidal Field

TH Thermal Hydraulical

UT Ultrasonic

VS Vertical Stability

VV Vacuum Vessel

WAVS Wide Angle Viewing System

WBS Work Breakdown Structure

WDS Water Detritiation System

WP Work programme

Page 47 of 53

Page 48: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 27/11/2009

ApPENDIX II -SUMMARY OF THE WP2010 BUDGET

3.1+3.5

3.1

3.1+3.5

3.1+3.5

3.1+3.5

3.6

Expenditure in support of ITER, credited byITER 10 through PA

Expenditure in support of ITER through hostorganizationContribution in cash in support of ITER

Contribution in cash for transfer of procurementsto Japan

Design and R&D in support of ITER, credited byITER 10 through ITA

Expenditure budgeted againstotherrevenueSubtotals

11.06

17.88

28.94

7.43

276.18

0.5

60.00

17.70

14.07

290.75 77.70

6.46

Notes

A table showing the indicative budget for grants to be awarded in this Work Programme,both credited and non-credited by ITER, is provided in Appendix III.

Figures corresponding to items to be credited by 10 through ITA are provisional, and arebased on the present understanding of the share of work to be assigned to F4E by 10

Page 48 of 53

Page 49: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB12-12Final 27111/2009

ApPENDIX III -SUMMARY OF THE AVAILABLE BUDGETS FOR GRANTS

1.1 Ma nets1.5 Vacuum Vessel 0.051.6 Blanket 2.101.7 Divertor2.3 Remote Handlin 2.843.1 Vacuum Pum in & Fuellin 1.013.2 Tritium Plant 0.433.4 Cr 0 lant 0.12

4.1/4.3 Power Su lies 0.064.5 CODAC

5.1 Ion C clotron

5.2 Electron C clotron 1.775.3 Neutral Beam S stem 0.505.5 Dia nostics II.316.2 Buildin s 0.15

Material Develo ment 4.51Test Blanket Module 1.51Plasma En ineerin 5.1I 0.36

Safet 2.63En ineerin Su art 0.56

Nuclear Data 0.60Urgent activities in support of

cost and riskassessment 0.50Broader A roach

NB: Figures shown in this table are the currently estimated values. Modifications may occurwithin the budget limits.

Page 49 of 53

Page 50: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GBI2-12Final 27/11/2009

ApPENDIX IV -ESSENTIAL SELECTION AND AWARD CRITERIA FOR GRANTS

As regards grant actions referred to in this work programme, the essential selection andaward criteria, in accordance with Articles 165 and 166 of the Implementing Rules of theFinancial Regulation, are:

Essential Selection Criteria

The applicants' technical and operational capacity:

professional, i.e. scientific and/or technological competencies, qualifications andrelevant experience required to complete the action.

The applicants' financial capacity:

stable and sufficient sources of funding in order to maintain the activitythroughout the action.

Essential Award Criteria

Relevance and quality of the proposal with regard to the objectives and prioritiesset out in this work programme and in the relevant call for proposals.

Efficiency of the implementation as well as of the management structure andprocedures in relation to the proposed action.

Budget and cost-effectiveness in particular with regard to the objectives and therespected results.

With regard to the specific action, more details will be provided in the call for proposals.Evaluation thresholds and weighting will also be given in the call for proposals.

A proposal which does not fulfil the conditions set out in the work programme or in the callfor proposals shall not be selected. Such a proposal may be excluded from the evaluationprocedure at any time.

The timetable and indicative amounts for the actions are defined in this Work Programme.

Page 50 of 53

Page 51: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(09)-GB 12-12Final 27/11/2009

ApPENDIX V -MAXIMUM REIMBURSEMENT RATES FOR GRANTS

The upper limits for the reimbursement of eligible costs [or grants are laid down in Article153 of the Implementing Rules of the Financial Regulation of the Joint Undertaking and aresummarised in the following table.

Research, technological 40%development anddemonstration activities

Coordination and support 100%actions

Management, audit certificates 100%and other specific aetivities

Page 51 of 53

Page 52: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related
Page 53: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(IO)-GBI5-09bFinal 31103/20 I0

FUSION FOR ENERGYThe European Joint Undertaking for ITER and the Development of Fusion Energy

THE GOVERNING BOARD

DECISION OF THE GOVERNING BOARD ADOPTING THE FIRST AMENDMENTTO THE 2010 WORK PROGRAMME OF THE EUROPEAN JOINT

UNDERTAKING FOR ITER AND THE DEVELOPMENT OF FUSION ENERGY

THE GOVERNING BOARD OF FUSION FOR ENERGY

HAVING REGARD to the Statutes annexed to the Council Decision (Euratom) No 198/2007of 27'h March 2007 establishing the European Joint Undertaking for ITER and theDevelopment of Fusion Energy (hereinafter "Fusion for Energy") and conferring advantagesupon it l and in particular Articles 6(3)(d) and II thereof;

HAVING REGARD to the Financial Regulation of Fusion for Energl adopted by theGoverning Board on 221\d October 2007, last amended on 18th December 200i (hereinafter"the Financial Regulation"), and in particular Article 64 thereof;

HAVING REGARD to the Implementing Rules of the Financial Regulation4 adopted by theGoverning Board on 221\d October 2007 last amended on the 8th July 20085 (hereinafter "theImplementing Rules") and in particular Article 53 thereof;

HAVING REGARD to the Fusion for Energy Project Plan6, Resource Estimates Plan7

, 2010Work ProgrammeS, 2010 Budgct9 adopted by the Governing Board on 27th November 2009;

WHEREAS the Director should, in accordance with Article 8(4)(c) of the Statutes, draw upan annual work programme for adoption by the Governing Board on the basis of commentsand recommendations from the Executive Committee and Technical Advisory Panel,

HAS ADOPTED THIS DECISION:

Article 1

Under WBS 5.2.3 "Electron cyclotron power sources and WBS 5.2.4 EC power supplies" anadditional row is added to the table in section 2.12.6 "List of Activities" as follows:

ITER ActivityDuration

Credit Unique Time ofWI> ref. Activity Title of contractWBS/PBS Type (months) Status beneficiary Coli

WPlO/52 5.2.3 P supplySupply of extra consumabJes 10 y 2009104 for gvrotron testing

4

5

6

8

9

OJ, L 90, 30,03.2007, p, 58,F4E(07)-GB03-11 Adopted 22/1 0/2007F4E(07)-GB04-06 Adopted 18/12/2007F4E(07)-GB03-12 Adopted 22/1 0/2007F4E(08)-GB06-060 Adopted 08/07/2008F4E(09)-GB 12-08 Adopted 27111/2009F4E(09)-GB 12-09 Adopted 27/l 1/2009F4E(09)-GB 12 -12 Adopted 27/11/2009F4E(09)-GB 12-15 Adopted 27/11/2009

Page 1 of 2

Page 54: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(l0)-GBI5-09bFinal 31103/2010

------------------------cA·,.tiele-2!--------------------

This Decision shall have immediate effect.

Done at Barcelona, 30-31 st March 2010

For the Governing Board

Carlos Varandas

--Ghair-of the Governing~Board

Page 2 of 2

----------+

Page 55: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

................ . ..'.. ;' ....•'': .'I..'.'."...

F4E(l0)-GBI6-14Final 10/0612010

FUSION FOR ENERGYThe European Joint Undertaking for ITER and the Development of Fusion Energy

THE GOVERNING BOARD

DECISION OF THE GOVERNING BOARD ADOPTING THE SECOND AMENDED2010 WORK PROGRAMME OF THE EUROPEAN JOINT UNDERTAKING FOR

ITER AND THE DEVELOPMENT OF FUSION ENERGY

THE GOVERNING BOARD OF FUSION FOR ENERGY

HAVING REGARD to the Statutes annexed to the Council Decision (Euratom) No 198/2007of 27th March 2007 establishing the European Joint Undertaking for ITER and theDevelopment of Fusion Energy (hereinafter "Fusion for Energy") and confen'ing advantagesupon it and in particular Articles 6(3)(d) and II thereof;

HAVING REGARD to the Financial Regulation of Fusion for Energl adopted by theGoverning Board on 22"d October 2007, last amended on 18th December 20073 (hereinafter"the Financial Regulation"), and in particular Article 64 thereof;

HAVING REGARD to the Implementing Rules of the Financial Regulation4 adopted by theGoverning Board on 22"d October 2007 last amended on the 8th July 20085 (hereinafter "theImplementing Rules") and in particular Article 53 thereof;

HAVING REGARD to the Fusion for Energy Project Plan and Resource Estimates Planadopted by the Governing Board on 26th November 2009;

HAVING REGARD to the comments of the Executive Committee on the proposal for theAmended 2010 Work Programme adopted at its meeting of 19-20'h May 20106

;

HAVING REGARD to the comments and recommendation of the Technical Advisory Paneladopted at its meeting on 26th May 20 I0,

WHEREAS:

(I) The Director should, in accordance with Article 8(4)(c), draw up an annual workprogramme;

-----'(2)--Tlre-Governing-B<Yard sh-ould adopt-tlre-work-programme.

HAS ADOPTED THIS DECISION:

Article 1

The Amended 2010 Work Programme of Fusion for Energy annexed to this Decision ishereby adopted.

2

4

6

OJ. L 90,30.03.2007, p. 58.F4E(07)-GB03-11 Adopted 2211 012007F4E(07)-GB04-06 Adopted 1811212007F4E(07)-GB03-12 Adopted 2211 0/2007F4E(08)-GB06-06a Adopted 08/07/2008F4E(l 0)-Ee21-Summary Adopted 20/5120 I0

Page 1 of 48

Page 56: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10106/2010

Article 2

This Decision shall have immediate effect.

Done at Barcelona, lO'h June 2010

For the Governing Board

Carlos Varandas

Chair of the Governing Board

Page 2 of 48

Page 57: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GB16-14Final 10/06/2010

ANNEX 1

FUSION FOR ENERGY WORK PROGRAMME 2010 (WP2010)

..TABLE.OFCONIENTS

PART I - INTRODUCTION, ASSUMPTIONS AND OVERALL OBJECTIVES 5

1.1. INTRODUCTION 51.2. ASSUMPTIONS 51.3. ITER CREDITS FOR PREPARATORY ACTIVITIES 6lA. MAIN OBJECTIVES 6

1.4.1. ITER........... .. . 61.4.2. Broader Approach...... .. 71.4.3. DEMO .. 7

PART II - ITER 8

2.1. WBSI.I-MAGNETS 92.1.1. SUmlllary............................ .. .....................................9

2.1.2. Procurernent Arrangernents.. . 92.1.3. Main Procurements.......... . ,. 92.1.4. List ofActivities .. . .. 10

2.2. WBS 1.5 - VACUUM VESSEL 1I2.2.l. Sammmy........................... .. 112.2.2. Procurement Arrangements............................. . 112.2.3. Main Procurernents . 112.2.4. List ofActivities .. 11

2.3. WBS 1.6-BLANKET 132.3.1. Summary.. .......................132.3.2. Procurement Arrangements........ . "".. . " 132.3.3. List ofActivities............................. . .. .. 13

2A. WBS 1.7-DIVERTOR 152.4.l. Summill}' .. 152.4.2. Procurernent Arrangements . 152.4.3. Main Procurements.. 152.4.4. List qfActivities.. .. 15

2.5. WBS 2.3 - REMOTE HANDLING (RH) 162.5.l. Summill}'...... . .. 162.5.2. Procurement 162.5.3. List .. .

2.6. WBS 3.1 - VACUUM PUMPING AND FUELLING 182.6.1. Summill)'.......... .. 182.6.2. Procurelnent Arrangel1lents 182.6.3. List ofActivities .. 18

2.7. WBS3.2-TRITIUMPLANL 192.7.1. SummillY... .. 192.7.2. Procurement Arrangements "................. . " 192.7.3. List ofActivities.. .. 19

2.8. WBS 3.4 - CRYOPLANL 202.8.1. SU11Unal)I " ""... . 202.8.2. Procurelnent Arrangernents """... . , 20

2.9. WBS4.1 AND4.3-POWERSUPPLIES 212.9.1. Sul1lrncu:y............. . ""... .. .. "" .. " 212.9.2. Procurement Arrangements . " " " 212.9.3. List ofActivities... .. 21

2.10. WBS 4.5 - CODAc................................................. . 222.10.1. Summm:y........... .. 22

Page 3 of 48

Page 58: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GB16-14Final 10106/2010

2.10.2. Procurement Arrangements 222.10.3. List ofActivities . 22

2.11. WBS 5.1.1-IONCYCLOTRON H&CDANTENNA 232.11.1. Summmy. . 232.11.2. Procurement Arrangements.... ..,. 232.11.3. List ofActivities. . 23

2.12. ·WBS5:2'ELECTRONCYCLOTRON:.. :..:::.::: ::.:.: :: :.. :::.:..::.: : 23WBS 5.2. IB -ELECTRON CYCLOTRON UPPER LAUNCHER 23

2. 12. I. Summmy .. . 232.12.2. Procurement Arrangements . 232. 12.3. List q[Activities . 23

WBS 5.2.3 ELECTRON CYCLOTRONPOWER SOURCES AND WBS 5.2.4 EC POWER SUPPLIES 242.12.4. Summarv.............. ..242.12.5. Procurenlent Arrangernents.... . 242. 12.6. List ofActivitie.\ .. . 24

2.13. WBS 5.3 .. NEUTRAL BEAM SySTEM........................................ . 252.13.1. Summmy . 252.13.2. Procurement Arrangements ., 252. 13.3. List ofAc/ivities . 25

2.14. WBS5.5 - DIAGNOSTICS 272.14.1. SummGly.... . 272.14.2. Procurement Arrangements... . 272.14.3. List ofActivities . 27

2.15. WBS 6.1 - SITE AND WBS 6.2 - BUILDINGS 292.15. I. SummGlY . 292. 15.2. Procurement Arrangements. . 292. 15.3. List q[Activities 29

2.16. MATERIALS DEVELOPMENT 312.17. TEST BLANKET MODULES 332.18. PLASMA ENGINEERING 342.19. SAFETy 362.20. ENGINEERING SUPPORT 372.21. NUCLEAR DATA 382.22. ACTIVITIES OF QUALITY ASSURANCE CQA) AND PROJECT MANAGEMENT 392.23. CONTRIBUTIONS IN CASH 40

2.23. I. Contribution to CEAjiJr ITER Site Support . 402.23.2. Contribution to the ITER Organization ., 402.23.3. Contribution to Japan. . 40

2.24. EXPERTS FOR TECHNICAL ASSISTANCE TO F4E 402.25. URGENT ACTIVITIES IN SUPPORT OF COST AND RISK ASSESSMENT 40

PART III: BROADER APPROACH ; ;;.;..:..:.:;;: :: : :.:..;;;:;;;;;..;;;; ;..:;;:; ::: :: ; 41

3.1. INTRODUCTION 413.2. JT60SA 41

3.2.1. F4E Funded Activities . 413.2.2. Procurenlent Arrangefnents.......... . 42

3.3. IFMIF . 423.3. I. F4E Funded Activities 423.3.2. Procurement arrangements.. . . 43

3.4. IFERC . 433.4. I. F4E Funded Activities 433.4.2. Procurement Arrangements . 43

API'ENDIXI.•.TABLE··OFACRON¥MS·AND-ABBREVIATIONS· .44····-

APPENDIX II - SUMMARY OF THE WP2010 BUDGET 47

APPENDIX III - SUMMARY OF THE AVAILABLE BUDGETS FOR GRANTS 48

APPENDIX IV - ESSENTIAL SELECTION AND AWARD CRITERIA FOR GRANTS 49

APPENDIX V - MAXIMUM REIMBURSEMENT RATES FOR GRANTS 50

Page 4 of 48

Page 59: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10/06/20 I0 i!:O

PART I - INTRODUCTION, ASSUMPTIONS AND OVERALL OBJECTIVES

1.1. INTRODUCTION

The European Joint Undertaking··for ITER and the Development ofFusion Energy ('Fusion·for Energy' or F4E) is a Joint Undertaking created under the Euratom Treaty by a decision ofthe Council of the European Union.

Fusion for Energy was established for a period of 35 years fi'om 19th April 2007 and islocated in Barcelona, Spain. The objectives of 'Fusion for Energy' are threefold:

• Providing Europe's contribution to the ITER International Fusion Energy Project asthe designated Domestic Agency for Euratom;

• Implement the Broader Approach agreement between Euratom and Japan as thedesignated Implementing Agency for Euratom;

• Prepare in the longer term for the construction of demonstration fusion reactors(DEMO).

In accordance with the Financial Regulation, this Work Programme lays down the activitiesofF4E that are to be implemented and financed through the 2010 budget.

1.2. ASSUMPTIONS

The 2010 amended F4E Work Programme (WP2010) for ITER is based on the followingassumptions:

• The European schedule is based on the Scenario I Modified Accelerated. Thisscenario was used as basis for this document;

• F4E will receive on time from 10 the necessary inputs foreseen in the ITER QualityManagement process deposited with the Nuelear Safety Authorities and in accordancewith BUild-to-Print, Detailed Design and Functional Specification status agreed in2001;

• The necessary inputs fi'om 10 will be provided in time to allow the associated PAs tobe signed according to theforeseen schedule;

• WP2010 is in line with the Additional Direct Investments and the revised sharingagreed with 10 and other Domestic Agencies;

• The planning of the activities and the cOITesponding delivery of components by theother ITER Domestic Agencies will be respected;

• A current understanding of the ITER Design and that some modifications might berequired in 2010 to adjust it to the possible ITER developments;

• F4E will continue active management of and involvement in the ongoing tasks signedunder EFDA, results of which are to initiate certain F4E activities;

• Technically and commercially complex procurements will be implemented wheneverappropriate through the Competitive Dialogue procedure or through the negotiatedprocedure, in order to improve the alignment of supply chain response to F4E needsand to proactively adopt cost containment measures. This will be done in compliancewith our Implementing rules;

Page 5 of 48

Page 60: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10/06/20I0

Grants related to recurring and sequential R&D activities, with a well defineddevelopment path eventually leading to a EU procurement package, will beimplemented whenever appropriate through the Framework Partnership Agreement(FPA) procedure, in order to streamline and channel R&D funding, improve itseffectiveness and reduce administrative burden to beneficiaries and F4E alike. In

. cOl'isidcriilionor··lhc····lriinsitioniil····pci'iodfol'sliirting········implcmcntiilionofFPA, .... .modifications may occur in the foreseen scheduling of grant activities included inWP2010;

• Procurements which encompass scope within the domain of both F4E and contractingauthorities, or for which a very close coordination between F4E and other entities isneeded, will be implemented whenever appropriate through the Joint Procurementprocedure.

Regarding the amended WP201 0 for Broader Approach, the main assumptions are:

• The project plans presented in this document are those approved by the BroaderApproach Steering Committee;

• The Work Programmes for the projects IFMIF/EVEDA, IFERC and the SatelliteTokamak Programme will bc approved by the Broader Approach Steering Committee.

1.3. ITER CREDITS FOR PREPARATORY ACTIVITIES

This WP20 I0 includes an extensive programme of R&D and preparatory activities that haveto be carried out prior to signing the Procurement AITangement for the Procurement Packagesagreed to be at Build-to-Print level. Recognising that F4E is carrying out work that shouldhave been completed by the 10, additional credit from the 10 is being requested by F4Ethrough ITER Task Agreements (ITAs). The activities indicated in this WP2010 as receivingadditional (ITA) credits may be cancelled in the event that the 10 would not make therequested credits available.

1.4. MAIN OBJECTIVES

1.4.1. ITER

With respect to activities related to ITER, the main objectives are:

• The negotiation and signature of the lTER Procurement Arrangements, proposed bythe ITER Organisation (10), according to the present schedule;

• The signature of procurement contracts for those components on the critical path (inparticular buildings, magnets and vacuum vessel);

• The continuation of design and R&D activities in areas including Remote Handling,Heating and CUtTent Drive, Vacuum System, Tritium System, Diagnostics and TestBlanket Modules;

• The continuation of the preparation of safety and licensing documentation for ITER inCadal~acheand;~eIaiedsafeiysiua;es;

• The investigation of manufacturing methods and non-destructive tests of criticalcomponents from the technical point of view with the objective of minimising the costand risk of not meeting the technical requirements (radial plates, TF double pancake,divertor, vacuum vessel, blanket and first wall);

Page 6 of 48

Page 61: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14 (toFinal 10/06/20I0

• The preparation of new facilities to test prototypes and components during thequalification process and construction respectively;

• The continuation of the activities for the preparation of the ITER site.

The most significant procurements to be initiated within WP2010 are related to:

• Magnets,fClr whiCh procllrelnentcoI1ti·actst'orbothTF· coils (iniiially limited totooling and prototyping) and PF coils (initially limited to tooling) will be signed;

• Vacuum vessel, for which the main vessel procurement contract will be signed(initially limited to non recUlTing activities and to material for sector No 5);

• Buildings, for which the main excavation and tokamak complex foundation contractwill be signed (completing the activities initiated within WP2009).

FUlther to provide management and follow-up of contracts signed in direct support of theITER project, F4E continues to be responsible for the technical follow-up of a number oftechnology contracts previously managed by EFDA. The outcome of these contracts is animpOltant input for many of the activities that will be initiated by F4E.

1.4.2. Broader Approach

With respect to activities related to the Broader Approach (BA), the main objectives are:

• Regarding JT60SA, the procurement architecture for the TF coils ((initiated with theconductor procurement in WP2009) willbe completed by other important contracts inWP2010. Additional smaller activities foreseen in WP2010 are in support of theseongoing procurements;

• Regarding IFMIF-EVEDA, Procurement Arrangements with the VoluntaryContributors will be completed by early 2010;

• Regarding IFERC, the Procurement Arrangement for the supply and maintenance ofthe CSC supercomputer will be completed during 20 IO.

1.4.3. DEMO

With respect to actIvItIes related to DEMO, in addition those undertaken under the BAIFEReprojeet; nospeeifieaetivities are ·foreseen·to·be implemented· during 201O.

Page 7 of 48

Page 62: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final I0106/201 0

PART II - ITER

In the following the activities of Fusion for Energy related to ITER are described accordingto the agreed Work Breakdown Structure. The tables provided in the text use the followingabbreviations:

iiX \>i> »ii;;>i»;; iii:> .. ",: ·:.ii;··· :..:....,- ." \>

WP ref. Work programme reference, univocally identifyingWP items.WPxx/yy/zz, where xx <Irc the last two digits of the year in which WP/budgetthe activity was first financed, yy is a code identifying the iTER WBS clement(if available) or the F4E service in charge, zz is a scqucllliallltllllbcr for theyear.

G Grant

G(FPA) Grant implemented through a FrameworkPattnership Agreement

P Procurcment (service, supply or works)

Y Credited by ITER 10 through PA

Y(ITA) Credited by ITER 10 through ITA

N Non credited

All activities indicated within WP20 I0 are planned to be committed under the 20 I0 budget.

During the implementation of the work programme activities, F4E may group more activitiesin a single call, or split one activity in more calls. This will in any case be perfOlmedpreserving the scope and objective presented in WP2010.

The foreseen time of publication of calls and invitations is indicative only, and based on thepresent understanding of the project development.

The foreseen duration of activities is indicative only. Modifications of durations may reflect adifferent phasing of the activity with respect to the initial planning, in line with the financingdecision nature of the WP20 I0 and the change in the procurement strategy, including theadoption of instruments such as stages, options, lots.

S6ineaetivitieshaVebeenrefu6vedfr6fu·WP201Ofuainlybased6iithef6116wingieas6ns:

• Activities were moved to 2011 due to the change of reference scenario (the initialWP2010 had been defined based on the basis of Scenario I Modified) or to a differentallocation of priorities;

• Activity are not any more required by 10 (relevant to activities credited throughITAs);

• Changes in the procurement strategy were identified in order to simplify procurementprocedures or to better implement cost containment and risk reduction measures.

Page 8 of 48

Page 63: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 1010612010

2.1. WBS 1.1 - MAGNETS

2.1.1. Summary

.... .. :Adivitieswill···focusoiiihe·signiilureofTurfherconfriidsTorfheprocuremeiifoffhe·lTERmagnet componcnts, somc minor design/R&D activitics and support contracts for qualitycontrol and testing.

2.1.2. Procurement Arrangements

System ITER ,. it (kIVA) ~. ..

EUII I, 1.P6A.EU.Ol ~ Toroidal Field Coils Conductors 43.39 Dec 2007

EUII I.I.PI A.EU.Ol . Toroidal Field Coils 89.74* Jun 2008

EUll 1.1.P6C.EU.Ol - Poloidal Field Magnet Conductors 11.23** May 2009

EUll l.l.l'3A-B.EU.Ol - Poloidal Field Coils PF2 to PF6 41.40** Jun 2009

EUll Magnet Structures: Pre-compression Rings 0.60*** May2010

* Sum of TF Windings package credit from WBS 1.1.lA plus insertion in the case from MagnetStructures WBS 1.1.2A.

** Updated credit values awarded through peR-1M for two double pancakes added to PF2 and PF6coils and bilateral agreement with RF-DA.

*** Does not include DCRA8 changes (increase from 4 to 9 rings), prototype ring and testing, as wellas 3 spare rings.

2.1.3. Main Procurements

WBS 1.1.lA - Toroidal Field Magnet Windings

Following the signature of the contracts for two prototypes of the radial plates and theforeseen signature of the TF winding pack supply contract by mid-20 I0, the main work willfocus·onthestart up ofthe manufacturing activities at the companies for the production ofthefirst mock-ups and prototypes. For the case insertion a small R&D task will be used to assessthe weldillg methods for the case closure and I'elated noncdestructive testing. Othel' tasks willregard characterization of resin or structural materials for the coils. An engineeringstudy forthe insertion and cold testing of either the 10 EU TF coils or all the 19 TF coils in a commonfacility, in agreement with JADA,will also be launched.

WBS 1.1.2A·- Toroidal Field Magnet Structure

It is foreseen to issucs thc call for tender and sign thc contract for the manufacture of the pre­compreSSIOn nngs.

.. WBS1.1.3A..± LL3B=PoloidaLEieldMagnets (PE2to_PE6) .

The first stage of the large manufacturing contract for the production of the PF coils at theCadarache site will be signed and will concentrate on the engineering activities for toolingand qualification processes. A preliminary study of the cold test facility required for the PFcoils on-site will also be can'ied out.

Page 9 of 48

Page 64: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106/2010

WBS 1.1.6A + 1.1.6C - Toroidal and Poloidal Field Magnet Conductors

By mid-2010 the major contract for the manufacture of the conductors for the TF and PFcoils will bc signed (included in WP2009). Support contracts to perform the characterizationof the strand (both standard and extended) and the jacket structural materials during the

.whole production wilL be. initiated.. andsigned,..A .newcontract.with ..the..Sultan..facility.will.also be signed in order to test few conductor samples, as during 20 I0 the conductormanufacturing will still be at the early stages.

2.1.4. List ofActivities

<> <« j.tl~lli~> >; ..,c''',> I > >00.;.... i~",;> <";.",i <

>i>T~P¥[X' (>; >$;~i1ii »S¥\lA< ...•>«««) > ~",' '",>i I» »>'?"OO'l ,'.';;;»> lei\" <><

WP09111/03 1.1.1+1.1.3 P serviceCold Test Facility Preparation

II Y,Y(ITA) IOQ3for PF Coils

Procurement of magnetWPIOIII/09 1.1.2 P supply structures: pre-compression 58 Y IOQ3

rings

WPIOIIIIIO 1.1.3 P supplyProcurement of Poloidal Field

25 Y IOQ2coils PF2 to PF6 (Phase I)

WPIOII III I 1.1.1 P supplyProcurement ofToroida! Field

34 Y 2009coils (Phase I)

WPIO/ll1l2 1.1.6 P service Testing ofTF Nb3Sn Strands 32 Y IOQ3

WPIO/II/OI 1.1.6 P serviceTesting and Characterisation of

36 Y IOQ3PF strands

WPIO/II/02 1.1.1+1.1.3 P serviceAnalysis tasks in support of

12 Y IOQ3magnet activities

WPIO/II/04 1.1.1 P serviceTesting ofTF Structural

43 Y IOQ4MaterialsProcurement for Qualification

WPIOIII/05 1.1.1 P serviceof Coil Insertion and Case

12 Y IOQ2Welding and Definition ofFacilities

WPIO/II/06 1.1.6 P serviceSULTAN Sample

18 Y 2009& Tests

WPIOllI/08 1.1.6 P serviceJacket Material Qualification &

49 Y IOQ3Testing for TF and PF Coils

Additional tcsts and activitiesWPIOIlI/13 1.1.1 P service on magnet components 6 Y IOQ2

prototypes and mock-ups

Page 10 of 48

Page 65: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106/2010

2.2. WBS 1.5 - VACUUM VESSEL

2.2.1. Summary

Following the outcome of the Design Review of the "Alternative VV and Blanket design", 10has takenthe decision to modify the baseline"designwhichdemonstratednotfulfillingalltherequirements of the project, especially in terms of integration of components. The new designis called MDR-A (Modified Reference Design A).

The 2010 activities will be focused on the first phase of the procurement for the main vacuumvessel "first of a kind" sector (number 5) and will concentrate mainly on the engineeringactivities for design, validation mock-ups, tooling and materials.

2.2.2. Procurement Arrangements

2.2.3. Main Procurements

At beginning of 201010 will provide F4E with drawings suitable to issue the call for tenderfor the EU sectors.

ImpOliant F4E commitments in 2010 include sector engineering activities and the material forthe first sector manufacturing. A few smaller activities will be signed to support thepreparation of technical and contractual documentation for manufacturing studies and mock­ups to speed up the finalization of the main contract for sector 5.

2.2.4. List ofActivities

i. ;,,,,,., ••••• Duration of•••• l'YI'J' ,i,""

•• COlltraftStatus '<;al\.'J

< "~" ..u (mouths)

I···· .... ... 1

WPIOl15101 1.5.1 P supplyProcurement of Main Vesse!

54 Y 10QI(phase I)

Support in preparation of finalWPIOl15/04 1.5.1 P service technical documentation for VV (, Y, Y(ITA) IOQ2

--contract---

WP 10115105 1.5.1 P service Analysis of VV Loads & Stresses 8 Y, Y(lTA) IOQ2

Page 11 of 48

Page 66: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GB16-14Final 10/06/20 I0

WPIO/15/08 1.5.1 P service Engineering Support for VV

Page 12 of 48

6 Y,Y(lTA) 10Q110Q2

Page 67: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106/2010

2.3. WBS 1.6 - BLANKET

2.3.1. jl"lnn,ary

During 2010, the activities in the blanket area will essentially focus on the FW component.They will consistofthecontinuationofthekey·tasksinitiatedlnorde[to·adequately prepare ..F4E to implement the Procurement Arrangement for the supply of 50% of the FW, plannedfor 2012.

2.3.2. Procurement Arrangements

None in 20 IO.

2.3.3. List o.fActivities

These activities cover 3 main areas as follows:

• Qualification activities, aiming at demonstrating the adequate mastery of the neededtechnologies for FW fabrication, applied to fully representative geometries;manufacture and high heat flux testing of qualification semi-prototypes will be a keypart of the programme, to formally complete phase 2 of the ITER qualificationprogramme; contracts for the manufacture of full-scale prototypes shall then be signedwith Industry which will also include development of repair techniques for seriesproduction.

• Engineering design, covering conceptual and detailed design and analyses of the FWpanels to support ITER 10 in the overall design effort and subsequent preparation ofthe PA specifications.

.... ····\Jl'ERi/

sur~tion...

..... A.';yi!?' < of ......... "",,! ..D". ."'" contract... ...... .. .. (tll~llllls) ••

WPlOI16/08 1.6.1 P serviceCompletion of Bc/CuCrZr

16 Y IOQ3joint repair technique

WP09116/02 1.6.1 GContinuation of Bc/CuCrZr

18 Y,Y(lTA) IOQ3HIP joining development.. ... .... ....

Ell"giliccdilg"Sup"i)"oiff6 . ...... . ... ..........

WP09116/04 1.6.1 P serviceBlanket

12 N 10QI

High heat flux testing of FW

WP09l16/05 1.6.1 Gmock-ups before and after

23 Y,Y(ITA) IOQ2irradiation, and foracceptance tests

Continuation of technologyWI' I0116/03 1.6.1 G development for enhanced 12 Y IOQ3

first wall design (5MW/m2)

Engineering Support for the

WPlOI16/04 UJ.! P servicedetailed Design of ITER

12 Y,Y(ITA) IOQ2~::~~~:t shield and FW

,,-,,-,,-_...- -..--- -- ..- ..-

Page 13 of 48

Page 68: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GB16-14Final 10/06/2010

WP10/16/07 1.6.1Manunlcturc of a ITER

P supply...................... I ,_~.t~n4~.rQJjI..f~JJ.p:t.:Q.tg.typ_~_ -

Page 14 of 48

18 Y,Y(lTA) 10Q3

Page 69: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(1 O)-GB 16-14 ft/Final 10/06/2010

2.4. WBS 1.7 - DIVERTOR

2.4.1. Summary

During 20 I0, the activities in the divetior area will essentially focus on the Inner Vetiical

2.4.2. Procurement Arrangements

2.4.3. Main Procurements

Calls for Tender will be issued for the procurement of the IVT full size prototype and for theprocurement of its Carbon Fibre Composite material:

2.4.4. List ofActivities

Complementary activities aiming at increasing competition and decreasing fabrication costs,will include: testing of full Tungsten mock-ups and prototypes, as well as mock-ups madefi'om alternative CFC materials,and engineering design, covering conceptual and detaileddesign and analyses of the IVT.

•• lTER> I :;'c.,; y' »I> "A ;,;,;:", >i> 'ryp~' .•...... '"......

WP10117/02 1.7.2 P supplyManufacturing of Inner Vcltica!

27 y IOQ3Target Full Size Prototypes

WPIOI17/01 1.7.1 P supplyManufacture of CarbOll Fibre

10 y IOQ2Composite prototypical batch

WP091l7/05 1.7.2 P supplyManufacturing of mock ups and

18 N 2009prototypes for the full W divcrtor

Engineering Support forWP I0117/04 1.7.2 P service procurement of divcrtor 12 Y IOQ3

components

WP I0117/05 1.7.1 G Characterisation of ere material 6 y IOQ3

WP I0117/06 1.7.2 P supply Pre-production qualification 52 y IOQ3

Page 15 of 48

Page 70: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

~) F4E(lO)-GBI6-14Final 10106/2010

2.5. WBS 2.3 - REMOTE HANDLING (RH)

2.5.1. Summary

In 2010 the various design and R&D activities in the RH field will continue in order topr()gt:ess with tile c()ilceptuaf clesign, tl1epreparaii()11 .()[tl1e ·fllllcii()nalspecificati()llsanclinterface requirements, the finalization of the scope of the supply, and the related R&Dactivities; all this in view of the preparation of the still-to-come Procurement Arrangementsfor the four different in-kind RH procurement packages under EU responsibility.

2.5.2. Procurement Arrangements

None in 2010.

2.5.3. List ofActivities

Complementary activities will include system studies and the technological surveys oncomponents (motors, sensors etc.) that are compatible with the ITER environmentalconstraints, in patlicular gamma radiation and, in case of the in-vessel viewing system, withvacuum, high temperature baking (-240 C) and, if required, high magnetic field (-8T).

• Divertor RH: The activities in 2010 will go on with the completion of what is coveredby the present Grant with TEKES. After this, a new grant will be initiated with VTT(FI) and TUT (FI) (officially delegated by TEKES) related to the completion of theconceptual design of the DlV RH devices and tools, completion of conceptual designfor the DTP2 Extension and Upgrade in view of a prototyping and testing phase andcontinuation of the test campaigns with the existing DTP2 hardware.

• Transfer Cask System (TCS): Design activities, by signing task orders in the frame ofthe existing engineering suppOll contracts, of a generic cask-pallet system to beintegrated later on with the Air Transfer System layout. A Grant is also planned to besigned in 2010 which beneficiary should play the role of design integrator in supportofF4E, in view of subsequent PA and industrial procurement preparation.

• In-Vessel Viewing System (lVVS): Activities related to the execution offurther R&Dactivities (furthet'Jab Jests aiming at increases of the performances oLthe presentproof-of-principle mock-up) and, design integration activities on the whole IVVS areplanned.

• Neutral Beam RH: A Grant to review, extend and complete the present NB RHconceptual design is planned. Synergies should be established with the NBTF designactivities.

• Radiation Tolerance Programme: The objective is to complete irradiation tests and todefine a common strategy with other F4E groups (e.g. Diagnostics) and ITER on thissubject.

Page 16 of 48

Page 71: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14 6J)Final 10106/2010

* Umque expenmental faclhty (accordmg to ar1.158.b of F4E Implementmg Rules)

I iI" ··,"""/iiii iLx iYiYi'iiCy 11 ,yi .........1\!J'~,~u~/

iii>> II'rF*

*,}pe"iy\,(iL,,,,: of'Y Tim~ol/

',!",,~,!~ '~" "? ., '.i.','•...... "

.,·.. i·· \Yy

DTP2 E&U Follow-VTT(FI); .........

.1'11'10/23/04 2.3.2 G ul,and bTl''! 28 Y(lTAjTUT (FI)*

ldQ2Operation

Gathering ofrequirements for NBfRH, and feedback

WP09/23/04 2.3.5 G to/from NSf 25 Y(ITA) 2009design.Start ofengineering design ofNBl RHIrradiation of RH

WP I0123/05 2.3 G components (motors, 8 Y(lTA) IOQ4sensors etc.)IVVS Design

WPI0/23/01 2.3.4 GFinalisation Including

29 Y(ITA) IOQ3Supplementary LabTestsATS Design

WPIO/23/02 2.3.7 G Completion &TCS 6 Y(lTA) IOQ3Integration

WP 10/23/03 2.3P Engineering Support

22 Y(lTA) IOQ3service for RH

WP I0/23/06 2.3P R&D on IVVS

7 Y(ITA) IOQ4service piczoll1otors

..

Page 17 of 48

Page 72: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(1 O)-GB16-14Final 10/06/2010

2.6. WBS 3.1 - VACUUM PUMPING AND FUELLING

2.6.1. Summary

The c10seandeffective collaboration withthe 10 in the definition and substantialprolSress of.all pre-procurement activities in the area of vacuum pumping will continue in 20 I0, withseveral important procurements and grants being signed.

2.6.2. Procurement Arrangements

None in 2010.

2.6.3. List o.fActivities

It is intended to sign a new Grant on the finalization of the detailed design of the Cold ValveBoxes (CVB) and Cryojumpers, as well as to initiate a procurement contract on theManufacture of Pre-Production Cryopump (PPC), its test vessel and related activities. Finally,it is also expected to finalize the design of the Heating Neutral Beam (HNB) Cryopumps andits interfaces to the cryopump in the M1T1CA facility.

With respect to the very impOltant issue of Leak Detection and Localization (LD&L) in theITER machine, grants will be signed to support R&D work that ITER 10 is recommending inorder to define the conceptual design of this system. Different methods will beassessed/tested in order to localize water and/or helium leaks inside the vacuum vessel orcryostat.

• Umque tools and facllttlCs (accordll1g to art.158.b of F4E Implementll1g Rules)

Un~que ~,- .<ITER . ...• ';r.., 1 nn~,Ul

UU"I "~~,, ~~ .,

Detailed design andWP09l3 1/01 3.1.1 P service specification for the 17 Y(ITA) IOQ2

CYBs and crvoiumocrs

WP 10/31/03 3.1.1 P supplyProcurement of pre

20 Y(ITA) IOQ3and test vesselOptimisation andperformance studies torleak detection system

I iilclUdihifpi'()iSt::of: I IWP09/31/o4 3.1.3 G

principle tests. Review37 Y(JTA) CEA (FR)* IOQ2

ofleak localizationconcepts and theirDossiblc realizationFollow up of

WPIO/31/01 3.1.1 P service procurement of ppe 20 Y(ITA) JOQ3and test vessel

R&D in support ofConceptual design of

WPIO/31/02 3.1.3 G leak detection system 29 Y(JTA) IOQ4and Leak Localisationsystems

...

Page 18 of 48

Page 73: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106/2010

2.7. WBS 3.2 - TRITIUM PLANT

2.7.1. SUlIlmary

Activities to support ITER 10 in the preparation of the Procurement Agreements (PAs) forIsotopeSeparation'System'(ISS)"'and"Water'Detritiation·System(WBS);···the··two·EUin·kindcontributions to the ITER Tritium Plant, will continue.

2.7.2. Procurement Arrangements

uP>IQi;;:?

EU32 WDS part 1 ""- Tritiated water holding tanks (storage and 4.78emergency)

Apr2011

2.7.3. List ofActivities

R&D work for specific issues (development of large size and tntlUm compatibleelectrolysers, their demonstration, etc.) as well as detailed designs will be canied out.

In particular, the contract for the detailed design for the tritiated water holding tanks of theWDS (2 large emergency tanks - 300 m3 - and other smaller holding tanks - <20 m3) will besigned.

ITER . D~r~t~?llof .

A.",,"Type' I m ..., contract rCan

(months)

R&D in SUppOlt of conceptual designWP09/32/01 3.2 G for WDS and detail design of the 26 YetTA) 2009

tanks

Preparation of tender specs for WDSWP09l32104 3.2 G Tanks and follow up of production of 4 Y 2009

drawings for manufacturing

WI' 10/32/04 3.2 P serviceConceptual and detailed design of

6 Y(lTA) IOQ3WDS

WI' 10/32/06 3.2 P serviceConceptual and Detailed design of

22 Y(lTA) IOQ4ISS

Page 19 of 48

Page 74: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

2.8.

2.8.1.

WBS 3.4 - CRYOPLANT

Summary

F4E(10)-GBI6-14Final 10/06/2010

The activities to be signed for the cryoplant in 2010 will focus on finalising the engineeringdesign requirements (engineering support contracts), reviewing functional specifications andmitigating the main technical risks in the procurement (R&D on compressor technology).

2.8.2. Procurement Arrangements

2.8.3. List ofActivities

I WP: ,"0. or . I Time orITER. I A, ~;:l~:Type"__, HUe

Call~...

WP09/34/02 3.4 P serviceEngineering Support to

10 y 10QIcryoplant

WP09/34103 3.4 P serviceOptimization of Cryoplant

16 y IOQ4Design

WPIO/34/01 3.4 P serviceR&D on compressor

8 y IOQ3technology

Page 20 of 48

Page 75: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106120 I0

2.9. WBS 4.1 and 4.3 - POWER SUPPLIES

2.9.1. Summary

Activities will be focusing on the preparation for the procurement of the Pulsed Powerelectrical network and thc Steady State electrical network induding: detailed design of ITEReleetrieal distribution system, and qualification of components with respect of operationunder magnetic field.

2.9.2. Procurement Arrangements

EU41, EU43

EU41, EU43

4.I.PIA-P8B.EU.OI - Detailed design nf the SSEN and 7.00PPEN

Assembly of the SSEN and PPEN, and SSEN cables 13.30

Oct 2009

Feb 2011

2.9.3. List ofActivities

Page 21 of 48

Page 76: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

2.10. WBS 4.5 - CODAC

F4E(lO)-GBI6-14Final 10/06/201 0

2.10.1. SummalY

The CODAC system, up to the local controllers, will be developed by ITER using Fund, withthe help of the Domestic Agencies and with direct help from industry. Fusion for Energy rolewill be to manage the instrumentation and control functions contained in the procurementarrangements.

2.10.2. Procurement Arrangements

Not applicable.

2.10.3. List ofActivities

A service contract related to Instrumentation and Control (I&C) for systems procured by F4Ewill be signed in 2010. This service contract will produce the design of I&C systemsaccording to 10 CODAC standards and support F4E suppliers in the procurement of I&Chardware. A smaller contract will be signed in order to prepare a resource loaded schedule forI&C and to support F4E with the technical specification of the service contract.

ITER ...... .. ~" I I)uro tioq of r."II•Type ,

I Sta-t~'; ·~~t...:" ~~

. uu<

WP I0/45104 4.5 P serviceReview of ITER I&C

3 N 2009snccifications

Support on I&C design andWP I0/45103 4.5 P service implementation in the frame of 12 Y IOQ3

EU PAs

Case study of the application ofWPI0/45105 4.5 P service the CODAC I&C standards to a 4 N IOQ3

existing fusion machine

Support on I&C design andWI' I0/45106 4.5 P service implementation in the fi'amc of 13 N IOQ4

EU PAs

Page 22 of 48

Page 77: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GB16-14 0'fJFinal 10/06120I0

2.11. WBS 5.1.1- ION CYCLOTRON H&CD ANTENNA

2.11.1. Summmy

The IC Antenna procurement type is Build-to-Print, with 100% ED sharing. Criticalprocurement contracts will be signed in 2010, specifically for the RF vacuum windows andFaraday screens bars.

2.11.2. Procurement Arrangements

None in 20 IO.

2.11.3. List ofActivities

ITERWP ref. WBS/PBS

..,Tvoe

J:)tl..;\ti~not'~ol1tract(montlIs)·

CreditShttus

WPIO/51/01 5.1

WP09/51/03 5.1

P supply

P supply

Faraday Screen R&D

RF Vacuum WindowsR&F

20 Y(ITA)

27 Y(ITA)

IOQ3

IOQ2

2.12. WBS 5.2 - ELECTRON CYCLOTRON

WBS 5.2.1B -ELECTRON CYCLOTRON UPPER LAUNCHER

2.12.1. Summary

In 2010 all the major prototype contracts will be signed, in support of the design and forcompletion before the PAs for the system are signed. The design work will be orientedtowards the production of a final detailed design. In addition, support will be provided to thc10 on some critical issues on the area of ECH, such as performance analysis update, commoncomponent strategy '(withJADA),and general integration of the ElectronCyclotronH&CDin the ITER system.

2.12.2. Procurement Arrangements

None in 2010.

2.12.3. List ofActivities

ITER .,.." Duration of

WBS/PBS Typo' (:oll:tract Status(months)

WP09/52/07 5.2.1 GDetailed design, analysis,

18 Y(ITA) IOQ3testing and documentation

WP09/52/08 5.2.1 P serviceEngineering activities in

22 Y(lTA) IOQ3support of EC Upper Launcher

WP09/52/09 5.2.1 P supply EC UL prototypes 40 Y(lTA) IOQ2

Page 23 of 48

Page 78: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(l0)-GBI6-14Final 10106/2010

WBS 5.2.3 ELECTRON CYCLOTRON POWER SOURCES AND WBS 5.2.4 EC POWERSUPPLIES

2.12.4. Summary

ThedevelopmentoftheEuropean--gyrotronfor-ITERwilleontinuesigningthe.6'fant-·forthe·test of the first gyrotron prototype which refurbishment, performed on the basis of the resultsof the first test campaign, will be completed by industry in summer 2010. The tests on therefurbished 2 MW gyrotron prototype will yield essential experimental results for thedecision on the future European development programme in this area. In addition, supportwill be provided to 10 on some critical issues on the area of ECH, e.g. space allocation in theRF building, preparation of specification for the PA for the gyrotrons and the EC PowerSupplies.

2.12.5. Procurement Arrangements

None in 2010.

2.12.6. List ofActivities-

J~ER I UU';;; 1. ..IIn'm.. -

I PBS1 I '" , '. I I orne or",. .,

WP09/52/02 5.2.4 P serviceEngineering Support

12 y IOQ4to EC PS

WP09/52/03 5.2.4 GSupport to ITER

16 Y(lTA) 2009Or~anization

Tests with theWP09/52/05 5.2.3 G refurbished 2MW 1st 4 Y CRPP (CH)* 10QI

nrototvnc Qvrotron

WPI0/52103 5.2.3 P supply Mirrors for RFCU 5 Y 10QI

Supply of extraWPI0/52/04 5.2.3 P supply consumablcs for 10 Y 2009

gyrotron testing

* Unique experimental facility (according to art.158.b ofF4E Implementing Rules)

Page 24 of 48

Page 79: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14 ~Final 10106/2010

2.13. WBS 5.3 - NEUTRAL BEAM SYSTEM

2.13.1. SU11lmmy

The substantial support provided by Europe to 10 for the development of the NB system willcontinue in 20 IO. Several procurement contracts related to the Test Facility will be initiatedand signed (cooling and cryo-systems, beam source etc.). The implementation of the PA onthe NB Power Supply, signed in 2009, will enter in its most active phase with the signature ofthe first procurement contracts.

2.13.2. Procurement Arrangements

The details about the second PA have now been added toafter the table below after thepositive decision of the ITER Council to include the NBTF into the ITER baseline and on thesubsequent agreement by the ED that this facility will be subject of an in-kind procurement ofthe ED.

EU53

EU53

5.3.P6.EU.OI - Procurement of NB power supplies and 19.52related systems

The full size ITER injector Ion Source Test Facility and MV 47.5*Test Facility (SPIDERIPRIMNMITICA)*

Jul2009

Jul2010

*The total credit allocated for the NBTF is 60 kIVA. Additional 8,8 kIVA from the 10 R&D fund have alreadybeen agreed by the ITER Council. The total considered here is therefore 68.8 kIVA. The actual sharing amongstDAs is now being finalized. Small changes may still apply.

2.13.3. List ofActivities

ITERWBS/PBS

Ar'tiyVpi;..tyoTime

Call

Infrastructures of the........ WP I0153109 5:3 P supply ncutral-hcalnlCst-facility--~ 49 Y

Cooling system

WP 10/53110 5.3 P supplyIon Source Test Facility-

21 yIon Source

WP 10/53111 5.3 P supply Ion Source Test Facility - 16 YVessel

Ion source test facility

WP09/53106 5.3 P supply(power supplies ~ HVD 24 Yand TX Line)

Page 25 of 48

IOQ3

10QI

10QI

10Q2

Page 80: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10/06/2010

ErJ<:~_\ ;" .. \\ it P~r#Ji~~ «i.>'yk~4?~< ;/~)rfWrl~f.X I~K~'

;,;?f.~9I1tr~~t

<< 'j X. > (month~} ···~·~·"·"'Vf.'/.

................ ..... liYfl'-tisl{[i"ct'(ij'c':f(jfthc ............... ..... ·······1

WP 10/53/02 5.3 P supplyneutral beam test facility-

9 y IOQ2High Voltage Deck andBushing

WPI0/53/05 5.3 P serviceEngineering support in the

15 y 10QINB area

WP I0153/08 5.3 P supply SPIDER Control & DAQ 25 Y IOQ3

Ion source test tllcilityWP I0/53115 53 P supply power supplies - optional 22 y 2009

sUDolicsInfrastructures of theNeutral Beam Test

WP10/53113 5.3 P supply Facility - Accelerator and 36 y IOQ3Ground Related PowerSuppliesDesign, development,support to the procurement

WPI0/53/14 5.3 G (fPA)up to acceptance, of the

48 y ConsorzioIOQ3

infl'astructurcs, sub- RfX (IT)*systems and componentsofthc NBTf

* Unique technical competence (according to art l58,c ofF4E Implementing Rules)

Page 26 of 48

Page 81: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14 ct2Final 10/06/2010

2.14. WBS5.5 - DIAGNOSTICS

2.14.1. Summary

Contracts to be signed within this work programme will focus on developing system-leveldesigns for the main diagnostics; completing R&D on the critical path for each system; andadvancing designs of principal sub-assemblies.

2.14.2. Procurement Arrangements

2.14.3. List ofActivities

Systems required for ITER first plasma will see the design of key components progressedbeyond Preliminary Design Review level. To facilitate the R&D activities, frameworks willbe established for the conduct of necessary irradiation tcsting and for the procurement ofsupplies and analytical SUppOlt, including fabrication of prototypes and provision of testequipment. An independent activity will be initiated to undertake the design integration ofdiagnostic systems in pOlts under EU responsibility, including port plug design and/orcustomisation and integration in the ports of systems to be provided by other DomesticAgencies.

Concerns over the lifetime of optical assemblies close to the plasma, which is an issuecommon to several diagnostics, will be addressed through specific R&D aimed at identifyingdesign opportunities and providing generic design guidelines. Finally, an activity will beinitiated to provide diagnostic-specific technical support for F4E in its negotiations withITER 10 of the Diagnostic Procurement Arrangements, which are due to be signed in 2010and 2011.

............ ,Acctivities will focus on of the for the and associatedplugs in the nine diagnostic procurement packages for which the EU is responsible, to thelevel appropriate for a conceptual design review. In a few cases the design may be advancedto a more detailed level. The activities will include design and engineering studies; system­level optimisation to meet measurement requirements to be agreed with ITER 10; prototypingand testing of relevant components; and assessment of the Procurement Arrangementtechnical specifications.

WP09/55/02 5.5

Complete Design of in~---- ------- ---YcsscrDhign'ost'ic-s'To·"·_·_­G

Conceptual DesignReview level

24 Y,Y(ITA) 2009

Page 27 of 48

Page 82: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106/2010

,> > 1\i~~~!<'''' :2,:,,£\ \\ \\ \ ?'\< Y\i\; ;>

y "A'.,,·w;},,'~y~f'

\ Y~L'l¥~! '~r....... ! 1\'

\ \e> > Y Y'>;y \ \"Y ;; y, <N\'\......... ! .......... ~2,I~p_I __~~~, __!?,~~}g!~,_g.r " ........... I .......

port plug-basedWP 10/55110 5.5 G Diagnostics to 24 Y(lTA) IOQ3

Conceptual DesignReview level

Engineering SupportWPI0/55111 5,5 P service for diagnostic 18 Y IOQ3

integrationIrradiation and post-irradiation testing of

WP I0/55112 5,5 P service diagnostic 24 Y IOQ3components andassembliesPort plug design,

WPI0/55113 5.5 P service testing and diagnostic 24 Y IOQ3intc!!ratioll

Supplies and Support

WPI0155114 5,5 P supplyfor Design of

61 Y,Y(ITA) IOQ3Diagnostics and PortPlugsSupport forFinalization of

WP09/55/23 5.5 GTechnical

24 Y IOQ3Specifications forPort~bascd

DiagnosticsR&DlDcsign of IVS

WPI0155109 5,5 G Joints, Fccdthroughs 34 Y IOQ3and Connectors

CEA (PR)*

Design of MagncticsCRPP(CH)*

WP I0/55115 5,5 GDiagnostics to

29 Y(ITA) ENEA (IT)* IOQ2Conceptual Design

SCK-CENReview level

(BE)*VTT (PI)*

* Unique technical competence (according to arUSS,c ofF4E Implementing Rules)

Page 28 of 48

Page 83: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

2.15. WBS 6.1 - SITE and WBS 6.2 - BUILDINGS

F4E(lO)-GBI6-14 ef2~Final 10106/2010

2.15.1. Summary

During 2010 the Architect Engincer will develop the design of the buildings from theconceptual design to a design stage detailcd cnough to allow the issueing of the call for tenderfor the consttUction of the civil engineering of the Tokamak complex.

Work programme 2010 activities will prepare the site and the Tokamak pit to allow thebeginning of the Tokamak complex civil engineering construction in 20 II.

2.15.2. Procurement Arrangements

, dueI (~Il;A;

EU62 6.2.P2.EU.OI - PF Coil Fabrication Building (B55) 12.80 Nov 2008

EU62 6.2.P2.EU.04 - Tokamak Complex Anti-Seismic Bearings 6.20 May 2009Supply

EU62 6.2.P2.EU.03 - Tokamak Excavation & Support Structure 31.00 May 2009

EU62 6.2.P2.EU.02 - Architectural and Engineering Services 54.70 May 2009

EU62 Construction of all buildings 349.47 May2010

2.15.3. List ofActivities

i1rER > Duration of

Tyr.;-' .•... V"C contract << I> fruo~ths\ ••••

WP09/6216.2 G

Support Study for12 N IOQ3

03 Accidental Scenarios

WPIO/621 Anti-Seismic Bcaring-s y "

036.2 P supply

Fabrication25 IOQ2

WP09l6216.2 P works

Tokamak Complex12 Y 2009

07 Foundations

WP09/6216.2 P service

Global construction12 Y 2009

II insurance

Analysis, design

WPIO/621optimization and cost

016.1&6.2 P service reduction strategies for 12 Y,Y(ITA) 10QI

the ITER buildingstructures

..-- -.----M~\n~Jafoly-'ritla'-"---

~.-..--

WPIO/62102

6.2 P service complementary building 73 Y IOQ3insurance

WP I0/6216.2 P works

Construction site update6 Y IOQ4

04 and adaptation

Page 29 of 48

Page 84: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106120 I0

WP 10/621 6.2 P service Site supp0l12010 12 Y 200906

··WPTO/6216.2 P service

'S'lIl'ip'6i't"f6i'-'cbhstfU'cl'i"61f"6 y IOQ2

07 contracts preparation

Page 30 of 48

Page 85: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14 \it9Final I0/06/20 I0

2.16. MATERIALS DEVELOPMENT

Material development focuses on the further optimization and validation of materialsforeseen··forITERTBMmodules;inparticularonEUROFER;·thesh'uctural materiaj···for theEU reference concepts, and on EUROFER ODS as well as SiC/SiC composites for thermaland electrical insulation (SiC-Dual), both, for dual coolant options that could be tested at alater stage or in collaboration with partners.

Activities foreseen in 20 I0 are in particular on characterization of EUROFER base material(new heat EUROFER-97/3 fabricated in 2009) and various joints needed in the TBM project(different weld processes, diffusion bonding, solid HIP & different weld-geometries). Theactivities are complemented by further development on missing design rules including areview by industry, maintenance of the data base and R&D on improvement of the materials.

The SiC-Dual material fabricated by industry shall be characterized and screened by a lowdose irradiation campaign.

Furthelmore, F4E will continue to develop EUROFER-ODS material. The next steps includefurther optimization of properties, in particular of the fabrication process, preparation forfabrication at industrial level and multi-ion-beam irradiation.

.." .. DurationCredit

Time... ,,;.,;. of··(:()JltnlC! of••. /Type ."

••••••• (months) Status Call

WPIO/MD/OI GCharacterization and validation of EUROFER and

24 N IOQ2EUROFER welds for TBM usc.

WP09lMD/02 G Design rules for EUROFER (Creep-fatigue) 18 N IOQ3

WPIO/MD!03 GDevelopment of SiC-SiC composites (basic

36 N IOQ3characterisation and irradiation campaigns)

WPIO/MD/02 GDevelopment of SiC-SiC composites (characterisation of

12 N IOQ3physicalpropcrtics)

Development: EUROFER and EUROFER ODSWPIO/MD/04 G [Optimisation of properties and processes] EUROPER 24 N IOQ4

ODS [Ion Beam and n-Irradiation campaigns]

WPIO/MD/05 GDevelopment: EUROFER ODS [Optimisation of

18 N IOQ4properties and processesJ

-".- ,,_n,_. ___•• _.,,~_. ..---_.-....-.--,.---- -·EUROFER--basc·lnatcl'i-als&wclding-t'orTBM'·usc:--.. ··-----WPIO/MD/08 G

Irradiation campaigns. Characterisation and validation39 N IOQ2

Page 31 of 48

Page 86: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10/06/20I0

: :i ;,;"Li .....,.'. :i .i :: V:~'" ·r: i~f:t~I' ')~~t'\

" ''I'l-(l.~, 'i : i : "+,,l~ ; IY'·· ;

............ ............... ......................

WPIO/MD/06 G EUROFER Data base and design rules 30 N IOQ4

WP09/MD/I0 P service EUROFER TBM design rules: for EUROFER welds, 18 N IOQ4Rules for welds

WPIO/MD/07 P service EUROFER T8M design rules: High Temperature rules 18 N IOQ3

Low dose irradiation and post~Irradiati()n examinationWPIO/MDIlI G(FPA) for ElJROFER base and weld materials for T8M 48 N IOQ3

application

Page 32 of 48

Page 87: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10106/20 I0

2.17. TEST BLANKET MODULES

The Test Blanket Modules (TBM) will be unique components in ITER as they use the ITER.. rnachin~as.aJ~stJac;ilityan(laI~th~Ql11Y9QmPQn~ntstQ .. Q~jl1Stall~c1 ...illJIER\Vhi(;h.ar~.. nQt

part of the EU in-kind commitment.

The activities on the TBMs to be signed in 2010 include the following:

• Continuation of the conceptual design (e.g. TBM re-design in case oflimitation on the

amount of ferromagnetic materials in ITER, further validation 1 optimization of He

flow in manifolds at the back of the TBMs, etc.)

• Definition of fabrication procedures on the basis of nuclear standards, the fabrication

of subcomponents test mock-ups and the transfer to Industry have been initiated in the

work program 2009 and will continue in 20 lOin the field of assembly of

subcomponents by welding to form the TBM box structure

• Integration ofTBM Systems into the ITER machine

• Development of materials database and computer codes for TBM safety analysesn .

lrElt .C .0(V" ••••." A, "!~'\(JU~.n.• \ '\ .,> ". ..... >

WP09/56/03 5.6 P serviceEngineering Support

10 N IOQ2for PrSR ofTBM

WPI0/56/06 5.6 P serviceEngineering Support 20 N IOQ2toTBM

HCLL/HCPBTBMsWP09/56/06 5.6 G Prcliminaly.Safcty 10 N. .. IOQ4

RCllort (PrSR)ComplctionofDB

WP I0/56/07 5.6 Gand definition of EN

18 N IOQ3computed codc forTBMTritium Extraction

WP09/56/11 5.6 GSystem (TES) for

12 N ENEA (1'1')* IOQ4HCLL-TBM: Testcampaign in TRIEX

WPIO/56/01 5.6 GTBM systems

12 N IOQ3conceptual design

WP I0/56/02 5.6 GTBM conceptual

12 N IOQ3... --..~ .".- ----,- ~... - -------- .--.- ,___design"."._ -- ._.-.. ----- ..." _.- .-, .-.-._~

WP I0/56/05 5.6 P serviceTBM fabrication

12 N IOQ3qualification

WPIO/PE/14 5.6 GTF and TBM ripple 24 N IOQ3analysis tor ITER

Page 33 of 48

Page 88: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10/06/20I0

Engineering supportWI' I011' Ell 3 5.6 P service and analysis for PE 12 N IOQ3

. (IBM)R&D in SUPPOit to

WI' 10156/08 5.6 G(FpA) the finalization of the24 N IOQ3/4

TBM Systemsconce tual dcsi '11

* Unique experimental facility (according to arUSS.1i ofF4E Implementing Rules)

2.18. PLASMA ENGINEERING

Plasma engineering will continue providing support to ITER-IO for the design andpreparation for operation of the ITER machine. The 20 I0 activities range from optimizationof plasma scenarios and systems to the evaluation of the impact of design changes on themachine performance and operation.

These activities are in large part, funded by means of competed ITAs which are published byITER-IO as open calls to all the DAs and assigned on the basis of the DAs replies.

In 2010, ITAs on the following general areas are expected:

• Plasma Operation & Control;

• Plasma wall interaction and runaway modelling;

• Development of analysis tools.

< i n';••""\of •••i" i;".;,i" , <

i i/ y'I'~p~i iii :< i •• iii iiSlalt's •••. "i

WpIO/pE/OI GEdge modelling coordination and

12 Y(ITA) IOQ4simulations (inc! dust)

WpIO/pE/02 P service SOLPS code development 12 Y(ITA) IOQ3

WpIO/pE/03 GEvaluation of 3D magnetic field in

24 Y(ITA) IOQ4ITER

Plasma control (inc! extended RT),WI' I0IPE/04 G control system design, simulation and 18 Y(ITA) IOQ3

VDE analysis

Development of run-away (RE) codeWI' I0/pE/05 G for ITER and simulation of RE 12 Y(lTA) IOQ3

(damage) in ITER

WpIO/pE/06 GMHO stability and pedestal - including

18 Y(lTA) IOQ3controlled ELM regimes

......WplO/PE/07 _..G Engineering models for plasma _12. Y(lTA).~ ...IOQ3...----- -'Tccab-iicK-co-ilfi'ol:'--- -- --- - ---------,-,-,_.--,,- -.---- -.-"

WpIO/pE/08 GConceptual design of plasma control

12 Y(lTA) IOQ3and protection system

WI' I011' E/09 GStudy of a pulse sequence simulator for

12 Y(ITA) IOQ4tokamak.

Page 34 of 48

Page 89: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(l0)-GBI6-14Final 10/06/2010

WPIO/PEIlO P serviceEngineering support and analysis for

18 Y,Y(ITA) IOQ2PE

WPIO/PEIlI GITER scenario and plasma pcrfomancc

12 Y(ITA) IOQ3analysis

WPIO/PE/12 GPlasma control dcvclopcll1cnt &

12 Y(ITA) IOQ4;n"""'''';M

< y •....... > i.> > .> '.,'(. '" ,,0',," iofi> .••••.• I§\~t,\~i

,of•• iii Tip~ ••• •• > >

WPIO/PE/15 G Study of plasma start up 12 Y(ITA) IOQ2

WPIO/PEIl6 GThe study of control of plasma current,

12 Y(ITA) IOQ3position and shape

WPIO/PE/17 GSelf-consistent simulations ofp!asma

12 Y(lTA) IOQ2scenarios

WPIO/PEIl8 GMagnetic reconstruction of the plasma

12 Y(ITA) IOQ3boundary

WPIO/PE/19 GAnalysis of Resistive Wall Mode

12 Y(ITA) IOQ3control by in-vessel (RMP) coils

Edge magnetic field structure for ELM

WPIO/PE/21 Gcontrol in ITER and associated

12 Y(ITA) 10QIpower/particle fluxes to plasma-hieingcomponents

Page 35 of 48

Page 90: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

2.19. SAFETY

F4E(10)-GBI6-14Final 10/06/20I0

Activities will focus on the support of the ITER licensing process, by performing relatedsafetystudies··andR&D;and···tosupportEU·PAactivities···by giving on request safetyrelatedadvice.

To control the dust and tritium inventories inside the vacuum vessel, techniques for theirquantification, monitoring and removal are investigated. Supporting safety analyses willinelude calculations for accident sequences and application of ALARA to occupationalradiation exposure for inspection, maintenance and repair activities inside the cryostat and forcoil and power supply distribution systems.

Radiological and Environmental Monitoring System

A first activity in this area aims at thc developmcnt of specific monitoring dcviccs for redzones highly tritiated and irradiated and containing activated Beryllium dust.

Radwaste Treatment and Storage

Concerning storage and disposal of radioactive and tritiated wastes, R&D activities areplanned to limit and/or control the tritium out-gassing from the waste packages, to measuretheir tritium content and to decontaminate tools from the hot cell facility.

i .......c' lof

i'I'l'#~'i/

ii i ....Cu'

\ i\ i'i / P\~i~$

WI' I0/SF/05 GBusbar arc model validation and supporting

18 Y(lTA) IOQ3experiments

WPIO/SF/06 GCombined H2/Dust explosion computer code

45 Y(ITA) IOQ4development

In vessel dust measurement and removalWP09/SF/04 G techniques assessment and validation - 18 Y(ITA) 2009

diagnostics

...... ... ....

WP09/SF/06 GSupporting safety analysis to follow up ITER

24 YetTA) IOQ3design evaluation and licensing process

WP09/SF/07 P serviceSupport to ORE and Safety analysis in support of

12 Y(lTA) IOQ2ITER licensing

WI' 10/SF/08 P serviceSupporting safety analyses to follow up ITER

12 Y(lTA) 10QIdesign evolution and licensing process

The ALARA application to Occupational·TT IV(lTAj. -WrOiJ/sFlfT G ----RaJfat'foIl"'Ex'posui:c"biiscITo'iiTfEfr-acsl"gn---- ··TO(j3

evolution

The ALARA application to OccupationalWPIO/SF/09 P service Radiation Exposure based on ITER design t2 Y(ITA) IOQ3

evolution

Page 36 of 48

Page 91: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GB16-l4Final 10106/2010

.- ' of

~;:t~,i: I T~:~lofI Typ~'A,""",,._,

I I

WPIO/SF/04 GIn vessel tritiulll inventory control by laser

24 Y(ITA) IOQ4spectroscopy

WPIO/SFIOI P serviceRadiological and Environmental Monitoring

12 Y(ITA) IOQ3System Support

WPIO/SF/IO P service Engineering studies for radwastc processes 12 Y(ITA) IOQ3

2.20. ENGINEERING SUPPORT

Activities listed here are in addition to the ones indicated in each of the previous areas andfocus upon Engineering Analyses, Code and Standards and foresees new step of contracts insupport of the design of components and systems and their cost optimization. The Codes andStandards activity in 20 lOis devoted to the tracking of international codes for analyses anddesign of mechanical and electrical systems, assess and follow up of notified body, inspectionentities, etc.

Most of the engineering support activities will be implemented through specific contracts tobe signed within existing Framework Contracts.

, .".0,.. / / Duratiollof :.Unique

TYP~'.,." contract

---

.,(nlollths) bencfi£iary

WP09lES/02 G Electromagnetic analyses 12 Y,Y(ITA) IOQ3

WP09/ES/07 P service ThcrmoMhydraulic analyses 12 Y,Y(ITA) IOQ2

WP09/ES/08 G Thermo-hydraulic modeling 12 Y,Y(lTA) IOQ3

WPIO/ES/OI P service Electromagnetic analyses 12 Y,Y(ITA) IOQI

WPIO/ESI02 P service Ncutrollic analyses 12 Y,Y(ITA) IOQI

WPIO/ES/03 P service Mechanical analyses 12 Y,Y(lTA) IOQI

WPIO/MF/02 P serviceMaterial characterization at

12 N IOQ2... ....... ... . .... . .. XQQlu!clcY1Jtcd__ tclupcraturcs . ... I ...... . . .

WPIO/MF/03 P serviceMaterial characterization at

12 N IOQ2cryogen ic· temperatures

WPIO/MF/04 P service Support for the quality12 N IOQ4

control of components

WPIO/MF/05 P service Joining technologies and12 N IOQ3

qualification

Support on Codes &WPIO/ES/08 P service Standards and review of 12 Y(ITA) IOQ3

Structural Design Criteria

WPIO/MFIOI GCorrosion Assessment f<)r

12 Y(lTA) IOQ3water cooled components

Assessment of the EU_... --

WPIO/MF/06 G materials database12 N IOQ4

WPIO/MF/07 P service Corrosion issucs 23 Y(lTA) IOQ4

WPIO/ES/09 P service Electrical Engineering 12 N IOQ3

Page 37 of 48

Page 92: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

WPIO/ES/IOAlternative code forI1cutronics calculations 12 Y,Y(lTA)

F4E(10)-GBI6-14Final 10/06/2010

CEA (FR)* IOQ4

* Unique technical competence (according to arUSS.c ofF4E Implementing Rules)

2.21. NUCLEAR DATA

This mid term activity for 2010 focuses on the development of tools, improvements andupdate of Nuclear Data tIles mainly in suppoli of TBM and Broader Approach (IFMIF)activities. In addition nuclear data experiments for validation have to be pursued andmeasurement techniques still developed.

WP09lND/OI GDevelopment of tools, improvements of data and

24 N IOQIvalidation in support ofTBM activities

WP IO/ND/O 1 GNuclear Data improvements and development of

24 N IOQItools

Page 38 of 48

Page 93: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(I O)-GB 16-14 e19Final 10/06/2010

2.22. ACTIVITIES OF QUALITY ASSURANCE (QA) AND PROJECTMANAGEMENT

A. fQJIQ.\Yc\)P .. QL;:19!iyi!i~$Jlt th~$\)ppli9r'$ pr~mi$9$ is 11~9~$$arYJQa$$Ilf~Jh~.cQrt:~ct ...execution of the contracts in compliance with the technical and management specificationsand the contractual Quality Plans. Assistance to F4E is also requested to prepare suchactivities, including assessment and risk management for the procurements and advise in thedefinition of the inspection procedures.This follow-up is achieved by sending qualified Inspectors from verifying bodies to thesuppliers' premises (and their subcontractors) to follow and verify the progress of work onF4E's behalf. The inspectors shall be the witnesses of F4E for the correct execution of themanufacturing sequences, manufacturing procedures, test methods, test perfOimancc and testreports during the production of the services and components. They shall report on Quality,Production and Schedule to the F4E Technical Responsible Officer defined in the relevantcontract.For a proper preparation of the inspection procedures to be included into the manufacturingcontracts and in order to be ready for the time when manufacture will start, a frameworkcontract is planned to be signed in 2010.

Contracts supporting F4E on project management matters are also planned to be signed in2010. Professional support (1-2 ppy) on this topic fi·om an engineering company is requiredfor specific tasks such as consultancy for the preparation of technical/managementspecifications and cost/risk estimates, in the definition of internal processes and in themanagement of the documentation.

WPIO/PO/08 P service Support of Project Management

WP09lPO/01 P serviceService of inspectors for ITER projectcontracts follow-up

Page 39 of 48

12 Y IOQ3

Page 94: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

2.23. CONTRIBUTIONS IN CASH

F4E(lO)-GBI6-14Final 10106/2010

2.23.1. Contribution to CEA ITER Site

F4E shall contribute through CEAIAIF to certain ITER expenditures, in some cases byreimbursing CEAIAIF of costs incurred to provide site support to the ITER Organization, inaccordance with the Annex on Site Support attached to the ITER Agreement. The site supportactivities to be financed by F4E in 2010 shall include fees to be paid to CEA for the use ofsome of the existing temporary buildings by the ITER Organization in accordance with thearrangement signed between CEA, the Commission and Fusion for Energy in 2009.

2.23.2. Contribution to the ITER Organization

This corresponds to the annual EU share of the 2011 contributions in cash to the ITEROrganisation for its management, to be adopted during the next ITER Council.

2.23.3. Contribution to Japan

This cash contribution to Japan corresponds to the transfer of procurement responsibilityfrom EURATOM to Japan under the supervision of the ITER Organisation.

2.24. EXPERTS FOR TECHNICAL ASSISTANCE TO F4E

F4E has issued a call for expressions of interest for individual experts to provide technicalassistance in a number of specific areas relatcd to ITER and the Broader Approach. Provisionis included here for a total number of approximately 2800 days for experts in 20 IO.

2.25. URGENT ACTIVITIES IN SUPPORT OF COST AND RISK ASSESSMENT

Some activities (corresponding to a total of about 5 man-years) may be necessary to becarried out in the estimation of costs and in the assessment of risk during the course of theyear. Such activities could be both grants and procurements under the 3.1 or 3.2 budget line.

WPref. "T;;~' Activity Title 'v, ~O<,..;·~;~t·

WP10/PO/Ol P serviceUrgent Activities in support of cost

5 Y,Y(lTA) 10Q2and risk assessment

WP10/PO/03 P serviceUrgent Activities in support of cost

5 N 10Q2and risk assessment

WP10/PO/04 GUrgent Activities in support of cost

5 Y,Y(lTA) 10Q2and risk assessment

WP10/PO/06 GUrgent Activities in support of cost

5 N 10Q2and risk assessment

Page 40 of 48

Page 95: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14 ,.,£:

Final 10106/2010 0<'

PART III - BROADER ApPROACH

3.1. INTRODUCTION

The European contributions to the Broader Approach Activities are financed to a large extentby contributions in kind fi'om the following Members of F4E: Francc, Germany, Italy, Spain,Switzerland and Belgium. Only in limited number of cases, where no contribution by theseMembers is foreseen, the contribution will have to be financed by the F4E budget.

For the contributions to be provided by Members of F4E, Procurement Arrangements will beconcluded in late 2009 and 2010 between F4E and the Japanese Implementing Agency,subject to the conclusion of corresponding Agreements of Collaboration between F4E and theMembers concerned. The list of procurement arrangements planned and the status ofimplementation is repOlted below and in the Project Plan.

In the following the activities of Fusion for Energy related to BA are described. The tablesprovided in the text use the following abbreviations:

Abbl" ....< r

Y<...... y.

WPref Work programme reference, univocally identifyingWP items.wPxx/yylzz, where xx arc the last two digits of the year in which WP/budgctthe activity was first financed, yy is a code identifying the lTER WBS clement(if available) or the F4E service in charge, zz is a sequential number for theyear.

G Grant

P Procurement

All activities indicated within WP2010 are planned to be committed under the 2010 budget.

During the implementation of the work programme activities, F4E may group more activitiesin a single call, or split one activity in more calls. This will in any case be performedpreserving the scope and objective presented in WP2010.

Thetoreseentillle of publication ofcallsandinvitationsisindicativcol11y,andbased on thepresent understanding of thc project development. . ..

3.2. JT60SA

3.2.1. F4E Funded Activities

For JT60SA, direct procuremcnt activities in 2010 will include the superconducting strandsfor the TF coils, which will conclude the first phase of the TF procurement strategy initiatedin WP2009. Activities Activities are listed in the table below.

In addition F4E will conclude Procurementcorresponding Agreements ofCollaboration:"

An'angements with JAEA, backed by

Page 41 of 48

Page 96: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10/06/2010

• ref. Arliv"vActivity 10'. Time'Typ~" .

I

WPIO/BNOI G Conductor insert manufacture and tests lOQ3

WPIO/BN02 P serviceSULTAN production sample manufacture

IOQ3and tests

WPIO/BN03 P service Strand qualification phase tests 18 IOQIWPIO/BN04 P service Strand production control tests 18 IOQlWPIO/BN05 P supply SC dummy conductor manufacturing IOQ3WP09/BNOI P supply TF Coils conductor SC and copper strands 2009WPIO/BN06 P supply Magnets preassembly tooling IOQ4

3.2.2. Procurement Arrangements

In accordance with the EU Project Execution Plan for the JT-60SA project, thc followingProcurement Arrangements are expected to be signed bctwcen F4E and JAEA forcomponents under the responsibility of the EU.

• Cryostat Body (2010 Q3). This will cover the supply of the cylindrical part of thecryostat. This supply will be covered by an AoC with ClEMAT (Spain).

• Power Supplies (2010 Q3). This PA will cover the supply of the power supplies for allsuperconducting magnets as well as for the in-vessel coils. This supply will bccovered by AoCs with ENEA (Italy) and CEA (France).

• ECH Power Supplies (2010 Q4). This PA will cover the supply of 2 EC Gyrotronspower supplies. Originally this supply was to be covered by an AoCs with CRPP(Switzerland) but recently the Swiss Government has indicated their will to withdraw£i'om this project and hence the matter is under discussion.

• Cryogenic System (2010 Q3). This PA will be for the supply of the entire cryogenicsystem for the magnet. This supply will be covered by an AoCs with CEA (France).

..• Sector Coils power supplies (2010 Q4).This·PA will cover the supply ofthe powersupplies for the sector coils. This supply will be covered by an AoCs with CNR-RFX(Italy).

3.3. IFMIF

3.3.1. F4E Funded Activities

In terms of direct contributions from F4E, as part of F4E contributions to the IFMIF/EVEDABA Project, "cash contributions to the common expenses of the Project Team" are to beforeseen in the 2010 budget for an expected total of 260 k€, this budget will cover the

. missions outsideJapan oftheEUmembers ofthe Project Team.' ... ----

In addition F4E will conclude a Procurement Arrangements with JAEA, backed bycorresponding Agreements of Collaboration.

Page 42 of 48

Page 97: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(lO)-GBI6-14Final 10106/2010

3.3.2. Procurement arrangements

Most procurement an·angements for IFMIF/EVEDA are planned to bc signed by July 2010.Only a remaining PA for diagnostics is expected for 2010 Q4 to be backed by an Agreementof Collaboration with CEA (France).

3.4. IFERC

3.4.1. F4E Funded Activities

No activities for the IFERC projects are foreseen to be directly funded by F4E in 2010.

3.4.2. Procurement Arrangements

The main procurement arrangement for the IFERC project, for the supply and maintenance ofthe Supercomputer for the CSC Subproject, is planned to be signed in the second quarter of2010. This PA will be backed by a corresponding Agreement of Collaboration with CEA(France).

Page 43 of 48

Page 98: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

ApPENDIXI-

TABLE OF ACRONYMS AND ABBREVIAnONS

F4E(10)-GB16-14Final 10106/2010

NE Architect Engineer

N:;PS A. . Power < .........................................................

ALARA As Low As Reasonably Achievable

ANB Authorized Notification Body

ANS Analytical System

AVDEs Asymmetric Vertical Displacement Event

ATS Air Transfer System

BSM Blanket Shield Module

BTP Build-to-Print

C&I Control and instrumentation

CFC Carbon Fibre Composites

CMM Cassette Multifunctional Mover

CVB Cold Valve Boxes

CVD Chemical Vapour Deposition

CXRS Core Plasma Charge-Exchange Recombination Spectroscopy System

DA Domestic Agency

DACS Data Acquisition and Control System

DCLL Dual Coolant Lithium Lead

DCR Design Change Request

DEMO Demonstration Fusion Reactors

DGEBF Di-Glycidyl Ether of Bisphenol F (impregnation resin)

DIV Divertor

DNB Diagnostic neutral beam

DTP Divertor Test Platfonn

EAF European Activation File

EB Electron Beam

.............. EBBTF European Breeding Blanket Test Facilities

EC Electron Cyclotron

ECUL Electron Cyclotron Upper L,aunchers

ECH Electron Cyclotron Heating

EFDA European Fusion Development Agreement

EFF European Fusion File

ELM Edge Localized Mode

EPC Engineering Procurement Contract

F4E Fusion for Energy

,,--,,--- ... . FS r. ,1<•

FW First Wall

FWP First Wall Panel

HAZOr j-Iazard Operability studies

HCLL Helium-Cooled Lithium-Lead

Page 44 of 48

Page 99: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(l0)-GB16-14 d'PFinal 1010612010

HCPB Helium Cooled Pebble Bed

H&CD Heating & CUlTent Drive

HIP Hot Iso-static Pressing

HNB Heating Neutral Beam

iTV Hi"h-...

HVAC Heating Ventilation &Air Conditioning

HVD High Voltage Deck._-HW Hardware

IC Ion Cyclotron

I&C Instrumentation and Control

ICH Ion Cyclotron Heating

IFMIF International Fusion Materials Inadiation Facility

INB Installation Nucleaire de Base

10 ITER Organization

IR Infra Red

ISEPS Ion Source and Extraction Power Supplies-

ISS Isotope separation system

ITA ITER Task Agreement

IVT Inner Vertical Target

IVVS In-Vessel Viewing System

LD&L Leak Detection and Localization

LFS-CTS Low Field Side .- Collective Thomson Scattering

MAR Materials Assessment Report

MDR Modified Design Reference

MHB Material Handbook

MI-ID Magneto-Hydro-Dynamic

MIG Metal Inert Gas

MV Medium Voltage

NB Neutral Beam

.......... NBI Neutral-Beam-lnjcctol:

NBPS Neutral Beam Power System

NBTF Neutral Beam Test Facility

ODS Oxide Dispersion Strengthened

ORE Occupational Radiation Exposure

P&ID Process and Instrumentation Diagram

PA Procurement AlTangement

PF PoloidaI Field

PFC Plasma Facing Components

PFD ---P-rocess··Flow.Diagram---

PIE Post In'adiation Examination•.-

PMU Prototypical Mock-Up

PP Procurement Package

PPC Pre-Production Cryopump-

Page 45 of 48

Page 100: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10/06/2010

PrSR Preliminary Safety Report

PTC Prototype Torus cryopump

IOQ(l ,2,3,4) Quarter 1,2,3,4 2010

QA Quality Assurance

........ R&D Reasearcll&Development I

RAFM Reduced Activation Ferritic Martensitic

RF Radio Frequency

RFCU Radio Frequency Control Unit

RH Remote Handling

RMP Resonant Magnetic Perturbation

RNC Radial Neutron Camera

RWM Resistive Wall Mode Control

SDC ITER SDC (Structural Design Criteria/Code)

SHPC Safety and Health Protection Coordination

SiC-Dual SiC/SiC composite material for electrical and thermal Insulation

SS Steady State

SW Software

TBM Test Blanket Module

TCS Transfer cask System

TES Test Extraction System

TF Toroidal Field

TH Thermal Hydraulical

UT Ultrasonic

VS Vertical Stability

VV Vacuum Vessel

WAYS Wide Angle Viewing System

WBS Work Breakdown Structure

WDS Water Detritiation System

WP Work programme...................................................................... ... ............................ .............. . ................................

Page 46 of 48

Page 101: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(1 O)-GB 16-14Final 10106/2010

ApPENDIX II -SUMMARY OF THE WP2010 BUDGET

2010 Budget (M€)

RefLine

3.1+3.5

3.1

3.1+3.5

3.1+3.5

3.1+3.5

3.6

3.1+3.5+3.6

3.2

3.2

3.3

ActiVIty It e

Expenditure in support of ITER,credited by ITER 10 through PA

Expenditure in support of ITERthrough host organization

Contribution in cash in support ofITER

Contribution in cash for transfer ofprocurements to Japan

Design and R&D in support of ITER,credited by ITER 10 through ITAExpenditure budgeted against otherrevenue

Subtotals

Total ITER construction

Design and R&D in support ofITER,not credited by ITER 10 (incl.materials, TBM, nuclear data)

Technology for ITER

Expenditure in support of BroaderA roach

19.565

30.527

7.300

0.060

0.500

18.027

285278

393.505

4.492

11.792

6.323

60.000

17.700

77.700

3.3

3.3

3.4

3.4

Contribution in cash in support ofIFMIF-EVEDA Project Team

Subtotals

Technology for Broader Approachand DEMO

Appointment of experts for Technicalassistance to F4E

Other expenditure

Total expenditure by type

0.260

0.060 6.3230.260

6.643

1.300

1.300I

Notes

A table showing the indicative budget for grants to be awarded in this Work Programme,both credited and non-credited by ITER, is provided in Appendix III.

Figures corresponding to items to be credited by 10 through ITA are provisional, and arebased on the present understanding of the share of work to be assigned to F4E by 10

Page 47 of 48

Page 102: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-l4Final 10/06/2010

ApPENDIX III -SUMMARY OF THE AVAILABLE BUDGETS FOR GRANTS

01.5 Vacuum Vessel

1.2001.6 Blanket

0.0801.7 Divertor

2.9312.3 Remote Handling

0.6603.1 Vacuum Pumping & Fuelling

0.4703.2 Tritium Plant

03.4 Cryoplant

04.114.3 Power Su lies

4.5 CODAC5.1 Ion Cyclotron

2.0495.2 Electron Cyclotron

6.5005.3 Neutral Beam System

9.1035.5 Diagnostics

6.2 Buildings 0.1504.410

Material Development1.460

Test Blanket Module4.145

Plasma Engineering 0.3602.330

0.050Engineering Support 0.560

0.620Nuclear Data

Urgent activities in support ofcost and risk assessment 0.500 0.250

Broader Approach 0.060

NB:FigUfessh6Whihthistable~iij'etheeUft'efitlyestimatedViiInes:ModificaflohsiniiyoccUf

within the budget limits.

Page 48 of 48

Page 103: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GBI6-14Final 10106/2010

ApPENDIX IV -ESSENTIAL SELECTION AND AWARD CRITERIA FOR GRANTS

As regards grant actions referred to in this work programme, the essential selection andaward criteria, in accordance with Articles 165 and 166 of the Implementing Rules of the

Essential Selection Criteria

The applicants' technical and operational capacity:

professional, i.e. scientific andlor technological competencies, qualifications andrelevant experience required to complete the action.

- The applicants' financial capacity:

stable and sufficient sources of funding 111 order to maintain the activitythroughout the action.

Essential Award Criteria

- Relevance and quality of the proposal with regard to the objectives and prioritiesset out in this work programme and in the relevant call for proposals.

- Efficiency of the implementation as well as of the management structure andprocedures in relation to the proposed action.

- Budget and cost-effectiveness in particular with regard to the objectives and therespected results.

With regard to the specific action, more details will be provided in the call for proposals.Evaluation thresholds and weighting will also be given in the call for proposals.

A proposal which does not fulfil the conditions set out in the work programme or in the callfor proposals shall not be selected. Such a proposal may be excluded from the evaluationprocedure at any time.

The timetable and indicative amounts are Programme.

Page 49 of 48

Page 104: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(IO)-GBI6-14Final 10106/20 I0

ApPENDIX V -MAXIMUM REIMBURSEMENT RATES FOR GRANTS

The upper limits for the reimbursement of eligible costs for grants are laid down in Article153 of the Implementing Rules of the Financial Regulation of the Joint Undertaking and are

. summarised.in.theJollow.ingJable....

Research, technological 40%development anddemonstration activities

Coordination and support 100%actions

Management, audit certificates 100%and other specific activities

Page 50 of 48

Page 105: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

••--,.;.­;... ...••• ••'.-. .. ., -••

F4E(10)-GB18-10Final 02/12/2010

FUSION FOR ENERGYThe European Joint Undertaking for ITER and the Development of Fusion Energy

THE GOVERNING BOARD

DECISION OF THE GOVERNING BOARD ADOPTING THE THIRD AMENDED 2010 WORK

PROGRAMME OF THE EUROPEAN JOINT UNDERTAKING FOR ITER AND THE DEVELOPMENT OF

FUSION ENERGY

THE GOVERNING BOARD OF FUSION FOR ENERGY

HAVING REGARD to the Statutes annexed to the Council Decision (Euratom) No 198/2007 of27th March 2007 establishing the European Joint Undertaking for ITER and the Development ofFusion Energy (hereinafter "Fusion for Energy") and conferring advantages upon it' and inparticular Articles 6(3)(d) and 11 thereof;

HAVING REGARD to the Financial Regulation of Fusion for Energl adopted by the GoverningBoard on 22nd October 2007, last amended on 18th December 20073 (hereinafter "the FinancialRegulation"), and in particular Article 64 thereof;

HAVING REGARD to the Implementing Rules of the Financial Regulation 4 adopted by theGoverning Board on nnd October 2007 last amended on the 8th July 20085 (hereinafter "theImplementing Rules") and in particular Article 53 thereof;

HAVING REGARD to the Fusion for Energy 2010 Work Programme adopted by the GoverningBoard on 27th November 2009 and amended on 31th March 2010 and 10th June 2010;

HAVING REGARD to the Fusion for Energy Project Plan and Resource Estimates Plan adopted bythe Governing Board on 26th November 2009;

HAVING REGARD to the comments and recommendations of the Executive Committee andTechnical Advisory Panel during their joint meeting on 11th November 2010;

WHEREAS the Director should, in accordance with Article 8(4)(c) of the Statutes, draw up anannual work programme for adoption by the Governing Board on the basis of comments andrecommendations from the Executive Committee and the Technical Advisory Panel;

2

3

4,

OJ. L 90, 30.03.2007, p. 5S.F4E(07)-GB03-11 Adopted 22/10/2007F4E(07)-GB04-06 Adopted IS/l2/2007F4E(07)-GB03-12 Adopted 22/1 0/2007F4E(OS)-GB06-06a Adopted OS/07/200S

Page 1 of 7

Page 106: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GB18-10Final 02/12/2010

HAS ADOPTED THIS DECISION:

Article 1

1.1. Under WBS 1.5" VACUUM VESSEL, second paragraph of Summary is replaced by:

"WP2010 activities are focused on engineering design, validation mock-ups, tooling andmaterials. In addition, the manufacturing of the "first-of-a-kind" sector (sector 5) will beinitiated.

The stainless steel material for sectors 5, 4 and 3 will be procured: the joint release of materialpurchase stages for multiple sectors will simplify the logistics of material procurement, reducethe risk of having dissimilar properties for the various material batches; furthermore thepurchase will reduce F4E's exposure to fluctuations in the stainless steel market.

Forming and cutting of plates and forgings of sector 5 will be started: it is foreseen that ANB willauthorise early in 2011 the fabrication of the sector, furthermore plate cutting can start evenbefore AN B authorisation; therefore, the release of these activities by F4E in 2010 willintroduce some schedule contingency."

1.2. Two additional rows are added to the table in section 2.2.4. - List of Activities as follows,the related budget adjustments are included in the Appendix II summary table:

WPlO/1S/09 1.5,1 P supplyProcurement of Main Vessel-

S4 y 10Q1Material Procurement for Sector 3

WP10/1S/10 1.5,1 P supplyProcurement of Main Vessel-

S4 y lOQ1Material Procurement for Sector 4

WP10/15/11 1.5.1 P supplyProcurement of Main Vessel-

54 y lOQ1Manufacturing of Sector 5

1.3. Under WBS 6.1- SITE and WBS 6.2 - BUILDINGS, Summary is replaced by:

"Within WP2010 activities the Architect Engineer will develop the design of the buildings fromthe conceptual design to a design stage detailed enough to allow issuing the call for tender forthe construction of the civil engineering part of the Tokamak Complex. Contractors will preparethe site and the Tokamak pit to allow for the beginning of the Tokamak Complex civilengineering construction.

Page 2 of 7

Page 107: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(10)-GB18-10Final 02/12/2010

In addition, the second phase of Architect Engineer activities will be initiated: this will allow foranticipation of certain works on site, and therefore for the increase of schedule contingency inthe project plan. Furthermore this will have the additional advantage of a more continuousinvolvement of the Architect Engineer site team, therefore slightly reducing the cost to F4E (nopartial de-mobilisation and remobilisation ofthe site team will be needed)."

1.4. One additional row is added to the table in section 2.15.3. - List of Activities as follows,the related budget adjustments are included in the Appendix II summary table:

WP10/62/0B 6.2 PserviceArchitect Engineer ~ Subsequentservices

Article 2

72 y 2009

The following activities are cancelled from the 2010 Work Programme, the related budgetadjustments are included in the Appendix II summary table:

F!8 y;yyyy; ;";"'i'i"!iLY'i'i,!·Z. 1·i".Xy;JiEiJifi «i ij:'!J'iiJSJPJiJiJifJi!2!i)WP09/16/02 Blanket Continuation of Be/CuCrZr HIP joining development

WP09/55/02 Diagnostics Complete Design of in-vessel Diagnostics to Conceptual Design Review level

WP09/55/23 Diagnostics Support for Finalisation of Technical Specifications for Port-based Diagnostics

WP09/S6/06 Test Blanket Modules HCLL/HCPB TSMs Preliminary Safety Report (PrSR)

WP09/62/03 Sites & Buildings Support Study for Accidental Scenarios

WP09/5F/06 Safety Supporting safety analysis to follow up ITER design evaluation and licensing process

WP09/5F/ll Safety The ALARA application to Occupational Radiation Exposure based on ITER design evolution

WPlD/16/03 Blanket Continuation of technology development for enhanced first wall design (SMW1m2)

WPlD/16/07 Blanket Manufacture of a ITER standard HF full prototype

WP1O/16/08 Blanket Completionot BelCu CrZr jointrepairtechnlque

WP1O/17/02 Divertor Manufacturing of Inner Vertical Target Full Size Prototypes

WP1O/45/03 CODAC Support on I&C design and implementation in the frame of EU PAs

WP1O/SS/09 Diagnostics R&D/Design of IVS Joints, Feedthroughs and Connectors

WPlD/55/l2 Diagnostics Irradiation and post-irradiation testing of diagnostic components and assemblies

WP1O/55/l4 Diagnostics Supplies and Support for Design of Diagnostics and Port Plugs

WPlD/ND/Ol Nuclear Data Nuclear Data improvements and development of tools

WPlD/PE/01 Plasma Engineering Edge modelling coordination and simulations (incl. dust)

WP1O/PE/05 Pia sma Engineering Development of run-away (RE) code for ITER and simulation of RE damage in ITER

WPlD/PE/07 Plasma Engineering Engineering models for plasma feedback control

WPlD/PE/08 Plasma Engineering Conceptual design of plasma control and protection system

WPlD/PE/09 Plasma Engineering Study of a pulse sequence simulator for tokamak

WP1O/PE/12 Plasma Engineering Plasma control development & integration

WP1O/SF/Ol Safety Radiological and Environmental Monitoring System Support

WPlD/5F/09 Safety The ALARA application to Occupational Radiation Exposure based on ITER design evolution

Page 3 of?

Page 108: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(1O)-GB18-1OFinal 02/12/2010

Article 3

The following activities are moved from Work Programme 2010 into Work Programme 2011,the related budget adjustments are included in the Appendix II summary table:

» »C> HH> >Ar~~»C >,YC> C»/,P»>,,/,»p>/;/y hTilJeY>;>ii'iiPP!VygYi/YYYYY!'Y;>Y/c0!Y>;S(",/S(i!WP09/11/03 Magnets Cold Test Facility preparation for PF Coils

WP09/5l/03 ICH Antenna RF Vacuum Windows R&D

WP09/56/11 Test Blanket Modules Tritium Extraction System (TES) for Hell-TBM: Test campaign in TRIEX

WP09/ES/02 Engineering Analyses Electromagnetic analyses

WP09/MO/02Materials

Design rules for EUROFER (Creep-fatigue)Development

WP09/MO/1OMaterials

EUROFER TBM design rules for EUROFER weldsDevelopment

WP09/PO/OlQA and Project

Service of inspectors for ITER project contracts follow-upmanagement

WP1O/ll/0l Magnets Testing and characterisat'lon of PF strands

WP1O/ll/02 Magnets Analysis tasks in support of Magnet activities

WPlO/ll/09 Magnets Procurement of Pre-compression Rings

WP1O/ll/l2 Magnets Testing of TF Nb3Sn Strands

WP1O/17/04 Divertor Engineering Support for procurement of Dlvertor components

WP10/17/06 Divertor Pre-production Qualification

WPlO/23/0l Remote Handling IVVS Design Finalisation Including Supplementary Lab Tests

WP1O/23/02 Remote Handling ATS Design Completion &TCS Integration

WPlO/23/05 Remote Handling Irradiation of RH components (motors, sensors etc.)

WPlO/3l/0lVacuum Pumping and

Follow-up of procurement of PPCFuelling

WP1O/3l/02Vacuum Pumping and

R&D in support of Conceptual design of leak detection system and Leak Localisation systemsFuelling

WP1O/3l/03Vacuum Pumping and

Procurement of PPCFuelling

WP1O/32/04 Tritium Plant Detailed design of WDS

WP1O/32/06 Tritium Plant Conceptual design of ISS

WPlO/34/0l Cryoplant R&D on compressor technology

WPlO/45/05 COOAC Case study 6ffhe applkailOn 6fthecOClA(I&C standards to an existing fusion plant system

WP1O/5l/0l ICH Antenna Faraday Screen R&D

WPlO/53/07 Neutral Beam System Infrastructures of the Neutral Beam Test Facility - Vacuum and Gas Injection Plants for PRIMA

WPlO/53/08 Neutral Beam System Infrastructures of the Neutral Beam Test Facility - Instrumentation & Control System

WPlO/53/09 Neutral Beam system Infrastructures of the Neutral Beam Test Faclfity - Cooling System

WP1O/53/13 Neutral Beam systemInfrastructures of the Neutral Beam Test Facility - Accelerator and Ground Related Power

Supplies

WPlO/53/l4 Neutral Beam SystemDesign, development, support to the procurement up to acceptance, of the infrastructures,

sub-systems and components at the NBTF

WPlO/56/05 Test Blanket Modules TBM fabrication qualification

WPlO/62/02 Buildings Mandatory and complementary bUilding insurance

WP1O/62/04 Buildings Construction site update and adaptation

WP1O/MO/OlMaterials

Characterisation and validation of EUROFER and EUROFER welds for TBM useDevelopment

WP1O/MO/02Materials

Development of SiC-SiC composites (characterisation of physical properties)Development

WP1O/MO/03Materials

Development of SiC-SiC composites (basic characterisation and irradiation campaigns)Development

Page 4 of 7

Page 109: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(1O)-GB18-1O

Final 02/12/2010

diC,P) PPPi',i);AreaC'H;p);W;' I'P;:;;iif;;XiYiii/:SiiidP;; PPd iYi; d<ii idiiii

WP1D/MO/D4Materials Development: EUROFER and EUROFER ODS [Optimisation of properties and processes]Development EUROFER ODS [Ion Beam and n-Irradiation campaigns]

WP1D/MO/D6Materials

EUROFER Data base and design rulesDevelopment

WPlD/MO/D7Materials

EURQFER TBM design rules - High Temperature rulesDevelopment

WPlD/MO/D8Materials EUROFER base materials & welding for TBM use - Irradiation campaigns - Characterisation andDevelopment validation

WPlD/MO/llMaterials Low dose irradiation and post-irradiation examination for EUROFER base and weld materials

Development for TBM application

WPlD/MF/D2 Materials Material characterisation at room/elevated temperatures

WPlD/MF/D4 Materials Support for the quality control of components

WPlD/PE/D3 Plasma Engineering Electromagnetic modeling (including 3D)

WPlD/PE/ll Plasma Engineering iTER scenario and plasma performance analysis

WPlD/PE/13 Test Blanket Modules Engineering support and analysis for PE (TBM)

WPlD/PE/14 Test Blanket Modules TF and TBM ripple analysis for ITER

WPlD/SF/D4 Safety In vessel tritium inventory control by laser spectroscopy

WPlD/SF/OS Safety Busbar Arc Model Validation and Supporting Experiments

WP1D/SF/06 Safety Combined H2/Dust explosion computer code development

WP1D/SF/1O Waste Treatment Engineering studies for radwaste processes - RWF

Page 5 of 7

Page 110: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

F4E(1O)-GB18-10Final 02/12/2010

Article 4

Appendix II - The table titled "Summary of the WP2010 budget" shall be amended as follows(note that the previous figures shown in strikeout text):

3.1+3.5 Design and R&D in support of lTER,credited by ITER 10 throughPA

3.1+3.5 Contribution in cash in support of ITER

3.1+3.5 Contribution in cash for transfer of procurement to Japan

3.1+3.5 Design and R&D in support of ITER, credited by ITER 10 through ITA

3,6 Expenditure budgeted against other revenue

Subtotals

3.1+3.5+3.6 TOTAL ITER CONSTRUCTION

3.2

3,2

Design and R&D in support of ITER, not credited by ITER 10 (incl.materials, TBM, nuclear data

Total Technology for ITER

0,850 300,9220,000

~ 2€i€i,§§11 Q,§QQ

0,000 0,00077,812W;OOG

0,000 0,0009,090

+1,;'00

8,370 4,2900,000

~ ~

0,000 0,000 0,000

9,220 305,212 86,902

~ ~ -401,334

~

1,330

I2,420 I 0,000

~ ~

3,750.....-

3.3 Expenditure in support of Broader Approach

3.3 Contribution in cash in support of IFMIF-EVEDA Project team

Subtotals

3.3 Total Technology for Broader Approach and DEMO

0,000 5,9100,000

G,GW ~

0,000 0,0000,256G,<W

0,000 5,910 0,256G,GW ~ G,<W

6,166¥46

3.4

3.4

Appointment of expert for technical assistance to F4E

Total Other expenditure

0,000 I 0,000

1,300

I 1,300

Page 6 of 7

Page 111: FUSION FOR ENERGY · F4E(09)-GBI2-12 Final 27/11/2009 and to proactively adopt cost containment measures. This will be done in compliance with our Implementing rules; • Grants related

This Decision shall have immediate effect.

Done at Barcelona, 2nd December 2010

Article 5

For the Governing Board

Carlos VarandasChair of the Governing Board

Page 7 of 7

F4E(10)-GB18-10Final 02/12/2010


Recommended